A method for manufacturing a steel plate cage based on a cast-in-place pile

By manufacturing steel plate cages through a fully automated production line, the problems of low processing efficiency and deformation of existing pile foundation steel cages have been solved, achieving efficient production and reducing the need for testing.

CN118650386BActive Publication Date: 2026-11-10GUANGDONG ZHONGQIANG CONSTR ENG
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202410814938.0
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-06-24
Publication Date
2026-11-10
Estimated Expiration
2044-06-24

AI Technical Summary

Technical Problem

The existing pile foundation steel reinforcement cages have low processing efficiency, require a large amount of manual labor, are prone to deformation during lowering, and require a large amount of inspection work.

Method used

The steel plate cage is manufactured using a fully automated production line. It is formed into an integrated steel plate cage section through laser cutting and stamping, and the outer flange is added to increase friction. The complete steel plate cage is then formed by welding.

Benefits of technology

It improves processing efficiency, reduces manual labor, lowers the inspection requirements after the steel plate cage is lowered into the hole, and enhances the deformation resistance of the steel plate cage.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118650386B_ABST
    Figure CN118650386B_ABST
Patent Text Reader

Abstract

The application discloses a kind of steel plate cage manufacturing methods based on perfusion pile, belong to pile foundation reinforcement cage processing technical field, it is characterized in that, first, integrated steel plate cage section is made, then multiple integrated steel plate cage sections are butted together, and steel plate cage is formed;The steel plate cage section is the cylindrical cage structure that is enclosed by a piece of steel plate with multiple grouting material through holes distributed on surface;Outward flange is provided at the left and right sides of grouting material through hole, and the axis direction of outward flange and steel plate cage section is perpendicular.The steel plate of the application replaces steel bar, and this processing technology lays a foundation for realizing full automation machining with reduced manual participation;The application not only solves the problems of low production efficiency and large manual labor of existing steel plate cage, but also the integrated steel plate cage section made by the application has strong anti-deformation ability, simultaneously reduces the construction requirements when being put into hole, greatly reduces the detection process after being put into hole, and reduces detection labor.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of pile foundation reinforcement cage processing technology, specifically a method for manufacturing steel plate cages based on cast-in-place piles. Background Technology

[0002] The pile foundation reinforcement cage is a commonly used foundation support structure in building engineering, supporting the weight of buildings and other structures, and playing a crucial role. A pile foundation reinforcement cage generally consists of foundation bars, connecting bars, hanging bars, and tie bars. Foundation bars are the main supporting part of the pile foundation reinforcement cage and are also the key part bearing the weight of the building. Foundation bars require larger diameter steel bars to ensure their load-bearing capacity. Connecting bars are structural parts in the pile foundation reinforcement cage that connect adjacent bars, ensuring the integrity of the reinforcement cage. Connecting bars have a moderate diameter and require anchoring technology to firmly connect them to the concrete after pouring. Hanging bars are fixed-spacing parts in the pile foundation reinforcement cage, used to ensure the consistency of the overall spacing of the reinforcement cage. The number and diameter of hanging bars are selected according to actual design requirements, and a certain number of hanging bars are usually required to ensure the stability of the entire reinforcement cage. Tie bars are the key part of the pile foundation reinforcement cage that bears horizontal loads, and usually require larger diameter steel bars. Tie bars must be set at certain intervals to bear the horizontal loads generated by the building and ensure the stability of the entire structure.

[0003] In addition to the parts mentioned above, the pile foundation reinforcement cage also includes components such as clasps and support bars. The inclusion of these components helps to improve the overall strength and stability of the pile foundation reinforcement cage.

[0004] The fabrication of existing pile foundation reinforcement cages is sometimes done manually and sometimes semi-automatically. Given the structure of the pile foundation reinforcement cage, there is currently no fully automated fabrication equipment. Therefore, the fabrication of existing pile foundation reinforcement cages not only requires a large investment of human capital but also takes a long time. Furthermore, improper placement of the existing pile foundation reinforcement cage into the pile hole can cause deformation. After the reinforcement cage is placed into the pile hole, it must be inspected to ensure it meets the following requirements: 1. The length of the reinforcement cage below the bottom of the pile cap is ±100mm, measured with a ruler; 2. The diameter of the reinforcement cage is ±10mm, measured with a ruler; 3. The spacing of the main reinforcement bars is ±10mm, measured at least 5 locations; 4. The spacing of the reinforcing bars is ±20mm, measured at least 5 locations; 5. The spacing of the stirrups or spiral reinforcement bars is ±20mm, measured at least 5 locations; 6. The verticality of the reinforcement cage is 1%, measured with a plumb line.

[0005] Based on the above situation, it is necessary to improve the pile foundation reinforcement cage. Under the premise of ensuring its bearing capacity, how to improve the manufacturing efficiency, reduce the amount of manual labor, effectively prevent the deformation of the pile foundation reinforcement cage, and reduce the amount of inspection work after the pile hole is lowered are the problems that need to be solved. Summary of the Invention

[0006] The purpose of this invention is to provide a method for manufacturing steel plate cages based on cast-in-place piles that can improve processing efficiency and reduce the capital investment in manpower.

[0007] To solve the above-mentioned technical problems, the technical solution adopted by the present invention is as follows: A method for manufacturing steel plate cages based on cast-in-place piles involves first fabricating integrated steel plate cage sections, and then joining multiple integrated steel plate cage sections together to form a steel plate cage. The steel plate cage section is a cylindrical cage-like structure formed by enclosing a steel plate with multiple grout passage holes distributed on its surface. Outward flanges are provided on the left and right sides of the grout passage holes, and the outward flanges are perpendicular to the axial direction of the steel plate cage section. The outward flanges are used to increase the friction between the steel plate cage and the grout.

[0008] Furthermore, the method for manufacturing the integrated steel plate cage section includes the following steps: Step S1: Select plate material: Determine the thickness of the plate material based on the required bearing capacity of the cast-in-place pile; Step S2: Draw the outline cutting lines and flange cutting lines of each grouting material through hole on the surface of the plate on the computer. Step S3: Laser cutting of grouting material through holes: The laser head of the laser equipment is used to cut the grouting material through holes, and the outline of the grouting material through holes is used as the laser cutting trajectory of the laser head. Step S4, Laser cutting of the flange: The left and right flange cutting lines at the four corners of the grout passage holes are used as the laser cutting trajectory of the laser head. Multiple laser heads are used to perform laser cutting at the four corners of a row of grout passage holes on the steel plate surface. After the laser cutting is completed, the area between the two left flange cutting lines on the steel plate surface is the left flange area, and the area between the two right flange cutting lines on the steel plate surface is the right flange area. Step S5: The driving roller moves the steel plate one station: Under the action of the driving roller, the steel plate moves intermittently. After the laser cutting of the flange is completed, the driving roller drives the steel plate to move one station. The length of the station is the row spacing of the grouting material through hole matrix array. Step S6, Outer Flanging Processing: Using multiple stamping die sets on the stamping machine, the left and right flanged areas at a row of grouting material through holes on the steel plate are stamped respectively to form an outer flange; Step S7, Steel plate rolled into a cylinder: After the outer flange of all the grouting material through holes in the matrix array on the steel plate is processed, the steel plate is transported to the steel cylinder forming machine and rolled into a cylindrical structure, forming a weld between the two sides of the cylindrical structure. Step S8, Welding: Use a welding machine to weld along the weld seam to complete the fabrication of the integrated steel plate cage section.

[0009] Furthermore, the method for connecting multiple integrated steel plate cage sections is as follows: determine the length of the integrated steel plate cage according to the depth of the pile hole, determine the number of integrated steel plate cage sections according to the length of the integrated steel plate cage, and connect the first and last ends of each integrated steel plate cage section in sequence. Use electric heating elements to preheat the welding point area at the first and last ends of the integrated steel plate cage section. After preheating to the set temperature, start welding the joint welding point area between the first and last ends of each integrated steel plate cage section to form a complete steel plate cage.

[0010] Furthermore, the welding method used for the joint weld area between the first and last ends of the integrated steel plate cage section is to use WPS-763 MIG welding material and GFL-71NI welding material, with a heating temperature greater than 150 degrees Celsius.

[0011] Furthermore, in step S1, the thickness of the board is 8-20mm.

[0012] Further, in step S2, the method for drawing the outline cutting line and flange cutting line of each grouting material through hole is as follows: After drawing the outline cutting line of each grouting material through hole according to the design distribution of the grouting material through hole, draw a straight line to the left at the two corners on the left side of the outline cutting line of the grouting material through hole as the left flange cutting line, and draw a straight line to the right at the two corners on the right side of the outline cutting line of the grouting material through hole as the right flange cutting line.

[0013] Furthermore, the design distribution of the grouting material through holes is as follows: multiple grouting material through holes are square holes of the same size, and the square holes form a matrix array of multiple rows and columns on the surface of the steel plate. The number of grouting material through holes in a row along the circumference of the integrated steel plate cage is 8-12, and the spacing between adjacent grouting material through holes in the circumference direction is 20-40mm; the spacing between adjacent grouting material through holes along the axis of the integrated steel plate cage is 15-25mm.

[0014] Furthermore, in step S3, multiple laser heads are used to laser cut a row of grouting material through holes on the surface of the steel plate, and the laser cutting of all the grouting material through holes in the row by the multiple laser heads is performed synchronously.

[0015] Furthermore, among the relevant parameters of the laser equipment during laser cutting, the laser power is 80W; the repetition frequency is 75kHz; and the scanning speed is 185mm / s.

[0016] Furthermore, among the relevant parameters of the laser equipment during laser cutting, the spot overlap rate is 88%.

[0017] The beneficial effects of this invention are as follows: This invention uses steel plates instead of reinforcing bars. This processing technology lays the foundation for fully automated machining with reduced manual intervention. This invention not only solves the problems of low efficiency and high manual labor in the production of existing steel plate cages, but also the integrated steel plate cage section made by this invention has strong resistance to deformation. At the same time, it reduces the construction requirements when lowering the cage into the hole, greatly simplifies the inspection process after lowering the cage into the hole, and reduces the amount of inspection labor. Attached Figure Description

[0018] Figure 1 This is a schematic diagram of the steel plate cage of the present invention; Figure 2 This is a flowchart of the integrated steel plate cage section manufacturing method of the present invention; Figure 3 for Figure 2 A schematic diagram of the cut edge after flanging; Figure 4 for Figure 3 An enlarged view of point A shown. Detailed Implementation

[0019] To enable those skilled in the art to better understand the technical solutions of the present invention, the present invention will be further described in detail below with reference to the accompanying drawings and specific embodiments. It should be noted that, in the absence of conflict, the embodiments and features in the embodiments of this application can be combined with each other.

[0020] In the description of this invention, it should be understood that the terms "center," "longitudinal," "lateral," "length," "width," "thickness," "upper surface," "lower surface," "front," "rear," "left," "right," "vertical," "horizontal," "top," "bottom," "inner," "outer," "forward," "reverse," "axial," "radial," and "circumferential" indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings. They are used only for the convenience of describing this invention and simplifying the description, and are not intended to indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation. Therefore, they should not be construed as limitations on this invention.

[0021] like Figure 1 As shown, a method for manufacturing a steel plate cage based on cast-in-place piles involves first fabricating integrated steel plate cage sections, and then joining multiple integrated steel plate cage sections together to form a steel plate cage. Each steel plate cage section is a cylindrical cage-like structure formed by enclosing a steel plate with multiple grout passage holes 1 distributed on its surface. Outwardly turned flanges 7 are provided on the left and right sides of the grout passage holes 1, and these flanges are perpendicular to the axial direction of the steel plate cage section. These flanges are used to increase the friction between the steel plate cage and the grout. The multiple grout passage holes 1 are square holes of the same size, forming a multi-row, multi-column matrix array on the surface of the steel plate.

[0022] The method for connecting multiple integrated steel plate cage sections is as follows: The length of the integrated steel plate cage is determined according to the pile hole depth. Based on the length of the integrated steel plate cage, the number of integrated steel plate cage sections is determined. The ends of each integrated steel plate cage section are then connected sequentially. Electric heating elements are used to preheat the weld areas at the ends of the integrated steel plate cage sections to the set temperature. After preheating, welding begins at the joint weld areas between the ends of each integrated steel plate cage section to form a complete steel plate cage. The welding method uses WPS-763 Oxygen Dioxide welding material, GFL-71NI welding material, and a heating temperature greater than 150 degrees Celsius.

[0023] like Figure 2 As shown, the manufacturing method of the integrated steel cage section includes the following steps: Step S1: Select plate material: Determine the thickness of the plate material according to the bearing capacity required for the cast-in-place pile. The thickness of the plate material should be between 8-20mm.

[0024] Step S2, the method for drawing the outline cutting line and flange cutting line of each grouting material through hole is as follows: According to the design distribution of the grouting material through holes, after drawing the outline cutting line of each grouting material through hole, draw a straight line to the left at the two corners on the left side of the outline cutting line of the grouting material through hole as the left flange cutting line, and draw a straight line to the right at the two corners on the right side of the outline cutting line of the grouting material through hole as the right flange cutting line.

[0025] The design distribution of the grouting material through holes is as follows: multiple grouting material through holes are square holes of the same size, forming a matrix array of multiple rows and columns on the surface of the steel plate. The number of grouting material through holes in a row along the circumference of the integrated steel plate cage is 8-12, and the spacing between adjacent grouting material through holes in the circumference direction is 20-40mm; the spacing between adjacent grouting material through holes along the axis of the integrated steel plate cage is 15-25mm.

[0026] The number of grouting material penetration holes in the circumferential direction of the integrated steel plate cage section is determined based on the bearing capacity arrangement and grouting distribution. The number of grouting material penetration holes should not be too few, as this will affect the distribution of grouting material in the pile hole; conversely, the number of grouting material penetration holes should not be too many, as this will affect the bearing capacity of the steel plate cage.

[0027] Step S3: Laser cutting of grouting material through holes: The laser head of the laser equipment is used to cut the grouting material through holes, and the outline of the grouting material through holes is used as the laser cutting trajectory of the laser head. The relevant parameters of the laser equipment during laser cutting are as follows: laser power is 80W; repetition frequency is 75kHz; scanning speed is 185mm / s; and spot overlap rate is 88%.

[0028] To improve work efficiency, the laser equipment can be equipped with multiple laser heads. These multiple laser heads can be used to laser cut a row of grouting material through holes on the surface of the steel plate, and the laser cutting of all the grouting material through holes in a row by the multiple laser heads is carried out simultaneously.

[0029] Step S4, Laser Cutting of Flanged Edges: The left flanging cutting line 2 and the right flanging cutting line 3 at the four corners of the grout passage holes 1 are used as the laser cutting trajectory of the laser head. Multiple laser heads are used to perform laser cutting at the four corners of a row of grout passage holes on the surface of the steel plate 6. After laser cutting, the area between the two left flanging cutting lines 2 on the steel plate surface is designated as the left flanging area 4, and the area between the two right flanging cutting lines 3 on the steel plate surface is designated as the right flanging area 5. Figure 3 , 4 As shown.

[0030] Step S5: The driving roller moves the steel plate one station: Under the action of the driving roller, the steel plate moves intermittently. After the laser cutting of the flange is completed, the driving roller drives the steel plate to move one station. The length of the station is the row spacing of the grouting material through hole matrix array.

[0031] Step S6, Outer Flanging Processing: Using multiple stamping die sets on the stamping machine, the left and right flange areas at a row of grouting material through holes on the steel plate are stamped respectively to form the outer flange 7.

[0032] Step S7: Steel plate rolled into a cylinder: After the outer flange processing of all the grouting material through holes in the matrix array on the steel plate surface is completed, the steel plate is conveyed to the steel cylinder forming machine, and the steel plate is rolled into a cylindrical structure, forming a weld between the two sides of the cylindrical structure. The steel cylinder forming machine is also called a steel plate rolling machine.

[0033] Step S8, Welding: Use a welding machine to weld along the weld seam to complete the fabrication of the steel plate cage section.

[0034] An outward flange 7 is added at the grouting material penetration hole on the surface of the steel plate cage section to increase the friction between the steel plate cage section and the pile foundation concrete.

[0035] Working principle: This invention uses steel plates instead of reinforcing bars, thus enabling the following processing steps: cutting grouting material through holes → flanging and cutting → external flanging → steel plate rolling into cylinders → welding, all of which can be completed by equipment. This lays the foundation for fully automated machining with reduced manual intervention. This invention not only solves the problems of low efficiency and high manual labor in the production of existing steel plate cages, but also the integrated steel plate cage section made by this invention has strong resistance to deformation, while reducing the construction requirements when lowering it into the hole.

[0036] Furthermore, after the steel plate cage is lowered into the pile hole, only verticality needs to be checked with a plumb line; the following traditional checks are no longer required: 1. Length of the reinforcing cage below the pile cap bottom ±100mm, measured with a ruler; 2. Diameter of the reinforcing cage ±10mm, measured with a ruler; 3. Spacing of main reinforcement ±10mm, measured at least 5 locations with a ruler; 4. Spacing of reinforcing bars ±20mm, measured at least 5 locations with a ruler; 5. Spacing of stirrups or spiral reinforcement ±20mm, measured at least 5 locations with a ruler. It is evident that the steel plate cage produced using this invention significantly simplifies the inspection process after lowering it into the pile hole, reducing the workload of inspection.

[0037] Furthermore, those skilled in the art can combine and integrate the different embodiments or examples described herein, as well as the features of those embodiments or examples, without contradiction. Although embodiments of the present invention have been shown and described above, it is understood that the above embodiments are exemplary and should not be construed as limiting the present invention. Those skilled in the art can make changes, modifications, substitutions, and variations to the above embodiments within the scope of the present invention.

Claims

1. A method for fabricating a steel plate cage based on cast-in-place piles, characterized in that, First, an integrated steel plate cage section is fabricated, and then multiple integrated steel plate cage sections are joined together to form a steel plate cage. The steel plate cage section is a cylindrical cage-like structure formed by enclosing a steel plate with multiple grout passage holes distributed on its surface. Outward flanges are provided on the left and right sides of the grout passage holes, and the outward flanges are perpendicular to the axial direction of the steel plate cage section. The outward flanges are used to increase the friction between the steel plate cage and the grout. The manufacturing method of the integrated steel plate cage section includes the following steps: Step S1: Select plate material: Determine the thickness of the plate material based on the required bearing capacity of the cast-in-place pile; Step S2: Draw the outline cutting lines and flange cutting lines of each grouting material through hole on the surface of the plate on the computer. Step S3: Laser cutting of grouting material through holes: The laser head of the laser equipment is used to cut the grouting material through holes, and the outline of the grouting material through holes is used as the laser cutting trajectory of the laser head. Step S4, Laser cutting of the flange: The left and right flange cutting lines at the four corners of the grout passage holes are used as the laser cutting trajectory of the laser head. Multiple laser heads are used to perform laser cutting at the four corners of a row of grout passage holes on the steel plate surface. After the laser cutting is completed, the area between the two left flange cutting lines on the steel plate surface is the left flange area, and the area between the two right flange cutting lines on the steel plate surface is the right flange area. Step S5: The driving roller moves the steel plate one station: Under the action of the driving roller, the steel plate moves intermittently. After the laser cutting of the flange is completed, the driving roller drives the steel plate to move one station. The length of the station is the row spacing of the grouting material through hole matrix array. Step S6, Outer Flanging Processing: Using multiple stamping die sets on the stamping machine, the left and right flanged areas at a row of grouting material through holes on the steel plate are stamped respectively to form an outer flange; Step S7, Steel plate rolled into a cylinder: After the outer flange of all the grouting material through holes in the matrix array on the steel plate is processed, the steel plate is transported to the steel cylinder forming machine and rolled into a cylindrical structure, forming a weld between the two sides of the cylindrical structure. Step S8, Welding: Use a welding machine to weld along the weld seam to complete the fabrication of the integrated steel plate cage section.

2. The method for fabricating a steel plate cage based on cast-in-place piles according to claim 1, characterized in that: The method for connecting multiple integrated steel plate cage sections is as follows: determine the length of the integrated steel plate cage according to the depth of the pile hole, determine the number of integrated steel plate cage sections according to the length of the integrated steel plate cage, and connect the first and last ends of each integrated steel plate cage section in sequence. Use electric heating elements to preheat the welding point area at the first and last ends of the integrated steel plate cage section. After preheating to the set temperature, start welding the joint welding point area between the first and last ends of each integrated steel plate cage section to form a complete steel plate cage.

3. The method for fabricating a steel plate cage based on cast-in-place piles according to claim 2, characterized in that: The welding method used for the joint weld area between the first and last ends of the integrated steel plate cage section is to use WPS-763 MIG welding material and GFL-71NI welding material, with a heating temperature greater than 150 degrees Celsius.

4. The method for fabricating a steel plate cage based on cast-in-place piles according to claim 1, characterized in that: In step S1, the thickness of the board is 8-20mm.

5. The method for fabricating a steel plate cage based on cast-in-place piles according to claim 1, characterized in that: In step S2, the method for drawing the outline cutting line and flange cutting line of each grouting material through hole is as follows: After drawing the outline cutting line of each grouting material through hole according to the design distribution of the grouting material through hole, draw a straight line to the left at the two corners on the left side of the outline cutting line of the grouting material through hole as the left flange cutting line, and draw a straight line to the right at the two corners on the right side of the outline cutting line of the grouting material through hole as the right flange cutting line.

6. The method for fabricating a steel plate cage based on cast-in-place piles according to claim 5, characterized in that: The design distribution of the grouting material through holes is as follows: multiple grouting material through holes are square holes of the same size, forming a matrix array of multiple rows and columns on the surface of the steel plate. The number of grouting material through holes in a row along the circumference of the integrated steel plate cage is 8-12, and the spacing between adjacent grouting material through holes in the circumference direction is 20-40mm; the spacing between adjacent grouting material through holes along the axis of the integrated steel plate cage is 15-25mm.

7. The method for fabricating a steel plate cage based on cast-in-place piles according to claim 1, characterized in that: In step S3, multiple laser heads are used to laser cut a row of grouting material through holes on the surface of the steel plate, and the laser cutting of all the grouting material through holes in the row by the multiple laser heads is carried out synchronously.

8. The method for fabricating a steel plate cage based on cast-in-place piles according to claim 1, characterized in that: The relevant parameters of the laser equipment during laser cutting are as follows: laser power 80W; repetition frequency 75kHz; scanning speed 185mm / s.

9. The method for fabricating a steel plate cage based on cast-in-place piles according to claim 8, characterized in that: Among the relevant parameters of laser equipment during laser cutting, the spot overlap rate is 88%.