A water intake head construction method
Through the construction method of shore prefabrication and overall floating and sinking, the difficulty and safety risk problems of traditional water intake head construction under deep water conditions are solved, fast, safe and environmentally friendly water intake head installation is achieved, and construction efficiency is improved. and return on investment.
Patent Information
- Application Number
- CN202411124125.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-16
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2044-08-16
AI Technical Summary
The traditional water intake head construction method has problems such as difficulty in construction, high safety risks, large investment, and environmental pollution under deep water conditions, especially when constructing in the middle of the lake.
The construction method of shore prefabrication and overall floating and sinking is adopted. Through the steps of building cofferdam, prefabricated water intake head, floating, hoisting, sinking and backfilling, the hollow reinforced concrete structure and floating bag are used to realize the water intake head. Quickly install and sink, reducing environmental impact.
It reduces environmental pollution and safety risks during the construction process, improves investment efficiency, simplifies the construction process, and reduces construction costs.
Smart Images

Figure CN118653542B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of water intake engineering, and in particular relates to a water intake head construction method. Background Art
[0002] The water intake head generally refers to the facilities set up in rivers, lakes, ponds, and reservoirs, which take water through submerged or semi-submerged water intake grilles and transport it to the water intake pipe. Traditional water intake heads are generally set up on the shore and implemented by cofferdam excavation. The cofferdam construction at a deeper water level not only requires large investment and construction risks, but also has a certain impact on the water quality of the lake during construction.
[0003] At present, in order to ensure the safety of water supply, the water intake head of the reservoir is generally set in the center of the lake. Due to the deeper water and thicker silt in the center of the lake, the construction of underwater cofferdams becomes more difficult, the construction safety risk increases, the construction period increases, and the investment increases.
[0004] Therefore, it is necessary to provide an improved technical solution to address the above-mentioned deficiencies in the prior art. Summary of the invention
[0005] The purpose of the present invention is to overcome the deficiencies in the above-mentioned prior art. The present application provides a water intake head construction method, especially a construction method for prefabricating the water intake head on the shore and floating and sinking it as a whole.
[0006] In order to achieve the above object, the present invention provides the following technical solutions:
[0007] A water intake head construction method for a water intake system, wherein the improvement is that the construction method comprises the following steps:
[0008] Step S1: Select a prefabrication site at the water intake head; build a cofferdam around the prefabrication site, and level and compact the prefabrication site;
[0009] Step S2: prefabricate the water intake head; the water intake head is a hollow box, and the water intake head includes: a hollow box made of reinforced concrete; a strip through hole is arranged above each side wall of the box as a water inlet; a plurality of partitions are evenly arranged at the water inlet as a water inlet grille; a partition is arranged in the middle of the box to divide the interior of the water intake head into two inner chambers; a circular through hole is arranged on the same side of the outer wall of the two inner chambers, respectively, as a reserved opening for the gravity pipe; and two through holes are also arranged on the top plate of the water intake head as inspection openings;
[0010] Step S3: excavating the installation area of the water intake head, including: step S3-1 excavating the foundation pit of the water intake head installation area; and step S3-2 underwater leveling the bottom of the foundation pit;
[0011] Step S4: floating the water intake head, including:
[0012] Step S4-1, calculate the water intake head floatation and determine the floatation bag specifications;
[0013] Step S4-2, tying up the floating bag; the floating bag includes a buoy; the floating bag is installed parallel to the ground on both sides of the water intake head;
[0014] Step S4-3, trial floating;
[0015] Step S4-4, floating transportation, using a transport boat to tow the water intake head to a designated location.
[0016] Step S5: After the water intake head reaches the designated position, the water intake head is hoisted by a crane ship:
[0017] Step S5-1, assembling a crane ship, the crane ship includes a first crane ship and a second crane ship; the first crane ship is a 35T assembly crane ship, including a first pontoon group assembled from 8 pontoons of different specifications; and a first lifting device arranged on the first pontoon group, constituting the first crane ship; the second crane ship is a 30T assembly crane ship, including a second pontoon group assembled from 8 pontoons of different specifications; and a second lifting device arranged on the second pontoon group, constituting the second crane ship;
[0018] Step S5-2, hoisting the water intake head, including step S5-2-1, fixing the first crane ship and the second crane ship; step S5-2-2, positioning the central axis of the water intake head: two winches are set on the first crane ship and the second crane ship, and the central axis is positioned by using a sealing cable to the top angle of the water intake head by a cross intersection method;
[0019] Step S6, water intake head installation;
[0020] The method comprises the steps of S6-1, preparing for sinking the water intake head; placing a float in the box of the water intake head, and welding a light square tube with a scale on the float; setting a steel plate covering the inspection hole on the top plate of the water intake head, and setting four steel pipes on the steel plate as two water inlet pipes and two exhaust pipes; every two steel pipes are connected to the inside of the water intake head through an inspection port; the light square tube can extend from the exhaust pipe, and the water level in the water intake head box can be obtained through the scale;
[0021] Step S6-2, sinking operation of the water intake head, including: injecting water into the water intake head in batches, and the water intake head sinks autonomously as the amount of water injected increases; after sinking to a preset placement position, releasing the buoyancy bag;
[0022] Step S7, backfilling the water intake head, includes S7-1, selecting backfill materials; S7-2, adopting the backfill method to carry out water riprap.
[0023] Preferably, step S1 comprises:
[0024] Step S1-1, the prefabrication site is set at the shore and close to the pump house used by the water intake system; the cofferdam construction at the prefabrication site includes: using excavation equipment to pile up the fill used for the cofferdam from both sides of the cofferdam to the middle of the cofferdam and rolling and compacting it until the fill is gathered from both sides of the cofferdam to the middle of the cofferdam, and the prefabrication site is constructed in a circular manner to finally form fill; the fill also includes: forming a water-facing slope with a slope of 1:1 on the side close to the shore; forming a water-receiving slope with a slope of 1:1 on the side away from the shore;
[0025] Step S1-2, leveling and compacting the prefabrication site includes: constructing a drainage ditch on both sides of the prefabrication site toward the lake surface, constructing a foundation water pit downstream of each drainage ditch, and using an automatic drainage system to pump and drain water from the prefabrication site; after drainage, leveling the ground of the prefabrication site and constructing a concrete cushion layer.
[0026] Preferably, step S3 includes:
[0027] Step S3-1: excavation of the foundation pit of the water intake head installation area includes layered stepped excavation; the layered stepped excavation divides the cross section of the water intake head installation area into 4 steps from high to low, and the thickness of each step is 1 meter; the width of the highest step is the widest, and the width of the step becomes narrower layer by layer as the height of the step decreases, and finally forms an inverted slope with a slope ratio of 1:2.5;
[0028] Step S3-2 underwater leveling includes: using a foundation pit leveling device to perform underwater trimming on the uneven bottom of the foundation pit; the foundation pit leveling device includes: a leveling track, two leveling tracks are placed in parallel; the leveling track is controlled by a water-outlet steel wire rope controlled by an engineering vessel; bagged gravel is laid under the leveling track according to design requirements; a leveling scraper connects the two leveling tracks, slides on the leveling tracks, and fills the foundation pit with gravel to level it.
[0029] Preferably, step S4-1 includes:
[0030] Step S4-1-1, obtaining the buoyancy per meter of the water intake head and the self-buoyancy of the water intake head according to the size of the water intake head;
[0031] Step S4-1-2, calculating the draft depth of the water intake head;
[0032] Step S4-1-3, determine the specifications of the floating bag and calculate the floating draft when the water intake head is equipped with the bag.
[0033] Preferably, step S5-1 includes:
[0034] Step S5-1-1, hoisting the first pontoon assembly;
[0035] Step S5-1-2, assembling the first pontoon group; setting an I-shaped groove at the center of the two width sides of each pontoon; setting multiple I-shaped grooves at the two length sides of each pontoon according to the design requirements, and the I-shaped grooves of two adjacent pontoons are matched with each other; installing a pin matching the shape of the I-shaped groove in the I-shaped groove; the length of the pin matches the height of each pontoon;
[0036] Step S5-1-3, hoisting the second pontoon assembly;
[0037] Step S5-1-4, assembling the second pontoon group; the steps for assembling the second pontoon group are the same as the steps for assembling the first pontoon group.
[0038] Preferably, step S5-2-1 comprises: the first crane ship uses two anchor cables arranged at the bow of the first crane ship and two anchor cables arranged at the stern of the first crane ship to perform figure-eight anchoring; the second crane ship uses two anchor cables arranged at the bow of the second crane ship and two anchor cables arranged at the stern of the second crane ship to perform figure-eight anchoring;
[0039] Step S5-2-2 includes placing two winches on both sides of the center line of the first crane ship in the length direction, the first sealing cable connects the winch on the left side of the first crane ship and the right top corner of the water intake head close to the first crane ship; the second sealing cable connects the winch on the right side of the first crane ship and the left top corner of the water intake head close to the first crane ship; the intersection of the two sealing cables of the first crane ship is the first intersection; and placing the two winches on both sides of the center line of the second crane ship in the length direction, the third sealing cable connects the winch on the left side of the second crane ship and the right top corner of the water intake head close to the second crane ship; the fourth sealing cable connects the winch on the right side of the second crane ship and the left top corner of the water intake head close to the second crane ship; the intersection of the two sealing cables of the second crane ship is the second intersection, and the line connecting the first intersection and the second intersection is the center line of the water intake head.
[0040] Preferably, step S6-1 also includes: the four steel pipes are connected with angle steels; a row of first angle steels parallel to the top surface of the water intake head is arranged to connect the four steel pipes in sequence, and the first angle steels are arranged at an upper position of the four steel pipes; two crossed second angle steels are arranged between two adjacent steel pipes; and an inclined third angle steel is also arranged on each steel pipe, one end of the third angle steel is connected to the steel plate, and the other end of the third angle steel is connected to the steel pipe.
[0041] Preferably, step S6-2 includes:
[0042] Step S6-2-1, the water injection amount of the water intake head reaches one third of the height of the water intake head box;
[0043] Step S6-2-2, the water injection amount of the water intake head reaches two-thirds of the height of the water intake head box;
[0044] Step S6-2-3, continue to inject water into the water intake head until the water level in the water intake head is 0.3 meters away from the top plate of the water intake head; a water level travel sensor is arranged in each cabin, and the water level travel sensor is connected to the controller through a water level control line arranged in the exhaust pipe; the controller receives the water level signal from the water level travel sensor, and then controls the water pump to pump water;
[0045] Step S6-2-4, when the water intake head sinks to a height of 30 cm from the preset placement position, check the position of the water intake head and sink it into place after confirming that it is correct;
[0046] Step S6-2-5, after confirming that the water intake head has sunk into place, continue to inject water into the water intake head box until the water tank is full of water; after the water tank is full of water, release the pressure of the floating bag; wait until the air pressure of the floating bag is completely released, and then remove the floating bag.
[0047] Preferably, step S7-2 includes: step S7-2-1, calculating the amount of rock throwing; step S7-2-2, first throwing rocks at the bottom corner of the water intake head box, and then throwing some rocks upstream in turn, measuring the distance of the influence of flow velocity on the falling rocks, and then throwing the remaining rocks.
[0048] Beneficial effects:
[0049] This application reduces environmental pollution during the construction of the water intake head, reduces safety risks caused by deep water levels, and improves the efficiency of the use of investment funds. BRIEF DESCRIPTION OF THE DRAWINGS
[0050] The drawings constituting a part of the present application are used to provide a further understanding of the present invention. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation of the present invention. Among them:
[0051] Figure 1 It is a schematic cross-sectional diagram of the prefabricated cofferdam for the water intake head involved in the present invention;
[0052] Figure 2 It is a schematic plan view of the cofferdam for the water intake project involved in the present invention;
[0053] Figure 3 This is a schematic diagram of a water intake head model involved in the present invention;
[0054] Figure 4 This is one of the schematic diagrams of blocking the water inlet grille at the water intake head according to the present invention;
[0055] Figure 5 This is the second schematic diagram of the blocking of the water inlet grille at the water intake head according to the present invention;
[0056] Figure 6 This is a schematic diagram of plugging the reserved opening of the gravity pipe involved in the present invention;
[0057] Figure 7 It is a schematic diagram of layered step-type excavation of a foundation pit involved in the present invention;
[0058] Figure 8 It is a schematic diagram of a foundation pit leveling device according to the present invention;
[0059] Fig. 9 It is a schematic diagram of bundling the floating bladders involved in the present invention;
[0060] Fig.10 This is a schematic diagram of the connection of the first buoyancy tank group according to the present invention;
[0061] Fig.11 This is a schematic diagram of the connection of the second buoyancy tank group involved in the present invention;
[0062] Fig.12 This is one of the schematic diagrams of the water intake head hoisting involved in the present invention;
[0063] Fig.13 This is the second schematic diagram of the water intake head hoisting according to the present invention;
[0064] Fig.14 This is one of the schematic diagrams for installing the water inlet pipe and the exhaust pipe of the water intake head according to the present invention;
[0065] Fig.15 This is the second schematic diagram of the installation of the water inlet pipe and the exhaust pipe of the water intake head according to the present invention;
[0066] Fig.16 This is the third schematic diagram of the installation of the water inlet pipe and the exhaust pipe of the water intake head involved in the present invention;
[0067] Fig.17 This is a schematic diagram of water level control at the water intake head involved in the present invention;
[0068] Fig.18 This is a cross-sectional view of the backfill of the water intake head involved in the present invention;
[0069] Among them, 1. Water intake head; 1-1. Water inlet; 1-2. Partition; 1-3. Reserved opening for gravity pipe; 1-4. Inspection opening; 1-5. Water inlet grille; 1-6. Grille steel plate; 1-7. Top plate lifting ring; 1-8. Bottom plate lifting ring; 1-9. Bolt; 1-10. Waterproof casing; 2-1. Leveling track; 2-2. Outlet wire rope; 2-3. Bag of gravel; 2-4. Leveling scraper; 3. Floating bag; 4- 1. No. 1 pontoon of the first pontoon group; 4-2. No. 2 pontoon of the first pontoon group; 4-3. No. 3 pontoon of the first pontoon group; 4-4. No. 4 pontoon of the first pontoon group; 4-5. No. 5 pontoon of the first pontoon group; 4-6. No. 6 pontoon of the first pontoon group; 4-7. No. 7 pontoon of the first pontoon group; 4-8. No. 8 pontoon of the first pontoon group; 4-9. I-shaped groove; 5-1. No. 1 pontoon of the second pontoon group; 5-2. No. 2 pontoon of the second pontoon group ; 5-3, pontoon No. 3 of the second pontoon group; 5-4, pontoon No. 4 of the second pontoon group; 5-5, pontoon No. 5 of the second pontoon group; 5-6, pontoon No. 6 of the second pontoon group; 5-7, pontoon No. 7 of the second pontoon group; 5-8, pontoon No. 8 of the second pontoon group; 6, cofferdam; 6-1, earthbag; 6-2, drainage ditch; 6-3, foundation water pit; 6-4, displacement and settlement monitoring point; 7, first crane ship; 8, second crane ship; 9, anchor cable ; 10. Steel wire rope; 11-1. First sealing cable; 11-2. Second sealing cable; 11-3. Third sealing cable; 11-4. Fourth sealing cable; 12. Steel plate; 13. Steel pipe; 14. First angle steel; 15. Second angle steel; 16. Third angle steel; 17. Water level travel sensor; 18. Water level control line; 19. Controller; 20. Water pump; 21. Power supply; 22. Reserved space; 23. Riprap filling area. DETAILED DESCRIPTION
[0070] The technical solutions in the embodiments of the present invention are described clearly and completely below. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. All other embodiments obtained by ordinary technicians in this field based on the embodiments of the present invention belong to the scope of protection of the present invention.
[0071] In the description of the present invention, the terms "longitudinal", "lateral", "upper", "lower", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings. They are only for the convenience of describing the present invention and do not require that the present invention must be constructed and operated in a specific orientation. Therefore, they should not be understood as limitations on the present invention. The terms "connected" and "connected" used in the present invention should be understood in a broad sense. For example, they can be fixed connections or detachable connections; they can be directly connected or indirectly connected through intermediate components. For ordinary technicians in this field, the specific meanings of the above terms can be understood according to specific circumstances.
[0072] The present invention will be described in detail below with reference to the accompanying drawings and in combination with embodiments. It should be noted that the embodiments and features in the embodiments of the present invention can be combined with each other without conflict.
[0073] like Figure 1 and Figure 2 As shown, the present application relates to a water intake head construction method, the improvement of which is that the water intake head construction method comprises the following steps:
[0074] Step S1: Select a prefabrication site at the water head; build a cofferdam 6 around the prefabrication site, and level and compact the prefabrication site.
[0075] Preferably, in step S1-1, the prefabrication site is located on the shore near the pump house used in the water intake project; the cofferdam is filled around the prefabrication site. Specifically. The prefabrication site is located on the shore near the pump house used in the water intake project, and the cofferdam is filled with earth. Figure 1 As shown, the cofferdam is built around the prefabrication site at the water intake head, which can be understood as building a cofferdam 6 around the prefabrication site, and the cross section of the cofferdam is roughly trapezoidal. During the construction, the excavator pushes and rolls the fill from both sides of the cofferdam to the middle of the river channel until the fill converges from both sides to the middle. The slope of the water-facing surface is 1:1, that is, the ratio of the vertical height of the slope to the horizontal distance is 1:1. A layer of earthbags 6-1 is laid on the slope of the water-facing surface to prevent the impact of lake water and wind and waves, and the slope of the back water surface is also 1:1.
[0076] Step S1-2: After the cofferdam is filled, the prefabrication site is leveled and compacted. Figure 2 As shown, two 30cm×30cm×40m drainage ditches 6-2 are constructed from both sides of the preset position of the water intake head toward the lake surface, and two 1m×1m foundation water pits 6-3 are constructed downstream of the drainage ditch 6-2. The automatic drainage system is used to pump and drain water. After drainage, the ground is leveled and the concrete cushion layer is prepared before the subsequent steps of the main construction of the water intake head are carried out. At the same time, a displacement settlement monitoring point 6-4 is set every 20m at the center of the top surface of the cofferdam to monitor the settlement of the cofferdam.
[0077] Step S2: prefabricate the water intake head; Figure 3 As shown, the water intake head 1 is a box-type structure, including: a hollow box body made of reinforced concrete; a strip through hole is arranged above the side wall of the box body as a water inlet 1-1; a partition 1-2 is arranged in the middle of the box body to divide the interior of the water intake head into two inner chambers; a circular through hole is arranged on the outer wall of each inner chamber on the same side as a reserved opening 1-3 for the gravity pipe; two through holes are also arranged on the top plate of the water intake head as inspection openings 1-4 for the subsequent installation of the water inlet pipe and the exhaust pipe.
[0078] Preferably, a plurality of partitions are evenly arranged at the water inlet 1-1 as water inlet grilles 1-5; the water inlet grilles are blocked with grille steel plates 1-6 during the floating period; and the reserved openings of the gravity pipes are blocked with blind plates during the floating period.
[0079] Preferably, a bottom plate lifting ring is provided on the bottom plate of the water intake head box body for connecting with the buoyancy bag in the subsequent steps; and four top plate lifting rings are provided on the top plate of the water intake head box body for connecting with the first crane ship and the second crane ship in the subsequent steps. Figure 3 As shown, two top plate lifting rings 1-7 are respectively arranged on both sides of the upper surface of the box body of the water intake head; and bottom plate lifting rings 1-8 are evenly arranged on both sides of the bottom plate of the water intake head.
[0080] Specifically, the spacing of the grilles at the water inlet should be determined according to the actual situation, generally based on the water intake and floating objects in the lake. Figure 4 and Figure 5 As shown, the water inlet grille is blocked by a grille steel plate 1-6; a rubber plate is also required between the grille steel plate 1-6 and the box body to strengthen the blocking strength of the grille steel plate 1-6. At the same time, bolts 1-9 are used to fix the grille steel plate 1-6 to the side wall of the box body. Figure 6 As shown, a waterproof sleeve 1-10 matching the diameter of the reserved opening 1-3 of the gravity pipe is provided; a blind plate is provided on the end face of the waterproof sleeve for sealing, and a tic-tac-toe bracket is made on the blind plate with channel steel.
[0081] Step S3: excavation of the installation area of the water intake head, including step S3-1 excavation of the foundation pit and step S3-2 underwater leveling of the bottom of the foundation pit.
[0082] Preferably, step S3-1 of foundation pit excavation includes excavating by width in layers and steps using an excavator. Specifically, the bottom elevation of the water intake head installation involved in this application is 4m, the bottom elevation of the foundation pit is 3.7m, and the thickness of the replacement gravel is 30cm. According to the geological survey and measurement report, the riverbed geological conditions in the excavation area are silt layer, weathered rock layer, and medium-weathered mud sandstone from top to bottom. The lake bottom elevation is 8.4m, and the excavation depth is 4.5m, which is medium-weathered mud sandstone. In view of this geological condition, this application chooses to adopt layered and stepped excavation to excavate the water intake head installation area.
[0083] like Figure 7 As shown, the layered stepped excavation divides the cross-section of the water intake head installation area into four steps from high to low, and the thickness of each step is about 1 meter; the width of the highest step is the widest, and the width of the step becomes narrower layer by layer as the height of the step decreases, eventually forming a reverse slope with a slope ratio of 1:2.5.
[0084] Step S3-2 underwater leveling includes: using the foundation pit leveling device to trim the uneven bottom of the foundation pit, and controlling the flatness of the underwater excavation and the thickness of the gravel laying through the measuring rope or sonar measurement data, so as to ensure that the acceptance of the foundation pit and the needs of pipeline installation are met.
[0085] Specifically, after the foundation pit of the water intake head installation area is formed, the bottom and slope of the foundation pit should be repaired and leveled underwater. Divers go into the water and use the foundation pit leveling device to repair the uneven areas of the foundation pit to meet the use requirements. Figure 8 As shown, according to the engineering requirements and the particularity of water, this application adopts the "sample track method", that is, the foundation pit leveling device is used to level the foundation pit. The foundation pit leveling device includes: a leveling track 2-1, that is, a track composed of channel steel, and two leveling tracks are placed in parallel; the leveling track 2-1 is controlled by a water outlet wire rope 2-2 controlled by an engineering ship; bagged gravel 2-3 is laid under the leveling track according to the design requirements; the leveling scraper 2-4 connects the two leveling tracks, and the leveling scraper is a grid formed by splicing multiple steel pipes, which can slide on the leveling track. The leveling scraper 2-4 in the embodiment of the present application has 4 grids. Specifically, the two sides of the engineering ship are used to position the leveling track 2-1 and put it into the water, and the water-outlet wire rope 2-2 is used to control the leveling track. The diver uses the bagged gravel 2-3 in the water to adjust the leveling height. After the leveling track 2-1 is positioned and installed, the water engineering ship is directed to use a guide tube to unload the gravel and use a leveling scraper to fill the foundation pit with gravel and level it until the flatness and gravel laying thickness required by the design are achieved. At this point, the foundation pit construction of the water intake head installation area is completed.
[0086] Step S4: floating water intake head;
[0087] The water intake head involved in this application adopts a prefabricated reinforced concrete structure, which is prefabricated as a whole on the shore and installed by floating once. After calculation, the volume of the reinforced concrete structure water intake head involved in this application is: 9.45m long x 9.1m wide x 5.6m high, the concrete volume of the water intake head box is 134 cubic meters, that is, the concrete consumption is about 134m³, and the weight of the water intake head box is about 348.4T (tons), that is, the total weight of the water intake head is about 348.4T (tons); the box is transported to the design location by floating as a whole, and is lifted by two crane ships and slowly sunk to the design elevation with water injection.
[0088] Step S4 includes: step S4-1, calculating the water intake head floatation and determining the floatation bag specifications;
[0089] Step S4-1-1, obtain the buoyancy per meter of the water intake head and the self-buoyancy of the water intake head according to the size of the water intake head:
[0090] The buoyancy of the water intake head for every 1 meter of water is:
[0091] ;
[0092] in, is the density of water, with a value of 10 3 Kg / m 3 ; g represents a constant, which is the ratio of gravity to mass, and its value is 10N / kg, 1N is equal to 0.1kg, that is, 1kg is 10N; The displacement is the water head immersion depth of 1 meter;
[0093] The self-buoyancy of the water intake head is:
[0094] ; Wherein, V is the discharge volume of the water intake head;
[0095] Step S4-1-2, calculating the draft depth of the water intake head;
[0096] Calculate the water intake head weight G1: ;in, The amount of concrete used for water intake head: 134m³; Density of steel-concrete: 2.6×10 3 Kg / m 3 .
[0097] Calculate the water intake head box water entry height: The water intake head box body's water entry height is less than its own height, indicating that the water intake head box body will float on the water by itself;
[0098] According to the above calculation, it can be known that when the water intake head is sealed, the buoyancy of the water intake head is greater than the deadweight of the water intake head, that is, That is, when the water intake head is not tied to the floating bag, the water intake head floats above the water surface about , underwater draft of water intake head: .
[0099] Step S4-1-3, determine the specifications of the floating bladder and calculate the floating draft when the water intake head is equipped with the floating bladder:
[0100] Assuming that two floating bags with a buoyancy of 50T or 100T are selected for floating, the deadweight G2 of the water intake head with the floating bag is: G2=G1-100T=(348.4T-100T)=248.2T; among which, the deadweight G1 of the water intake head is 3484KN=348.4T. The floating draft of the water intake head with the floating bag is: 248.2T / 85.99T×1m=2.88m, that is, when two floating bags with a buoyancy of 50T are tied for floating, the draft of the water intake head is about 2.88m, which can also meet the floating requirements. In order to ensure the floating stability and sinking safety of the water intake head when the riverbed water depth and water level are uncertain during the rainy season, this application selects two 100T floating bags to be tied to the bottom plate lifting ring of the water intake head to reduce the draft of the water intake head and use the immersed pipe groove for floating.
[0101] Step S4-2, tying the floating bag; the floating bag 3 includes a buoy; Fig. 9 As shown, the floating bag 3 is installed parallel to the ground on both sides of the water intake head. Specifically, each floating bag is fixed to the bottom plate ring 1-8 of the water intake head by 6 30T×10m slings.
[0102] Step S4-3, trial floating.
[0103] Specifically, use an air compressor to fill the two floating bags with gas to a pressure between 0.1Mpa and 0.2Mpa to meet the underwater load of 100T. Turn off the air compressor to check whether the floating bags and air supply pipes and valves are firmly connected and there are no leaks. After ensuring that the floating bags and air supply system are normal, fill the cofferdam with water for a test floatation, and the test floatation time shall be no less than 24 hours.
[0104] Step S4-4, floating transportation, using a transport boat to tow the water intake head to a designated location.
[0105] After the trial float is correct, the cofferdam will be excavated and the water intake head will be floated. Before floating, the width and depth of the trench will be measured, and the areas with insufficient draft depth and width will be supplemented. During the supplementary excavation, divers and construction machinery are strictly prohibited from working at the same time. After the excavation depth and width meet the safe driving requirements for the water intake head floating transportation, the cofferdam will be opened for the water floating of the water intake head.
[0106] During the floating process, keep an eye on the pressure of the air gauges of the floating bags on both sides. If any abnormality is found, replenish the air pressure in time or stop floating immediately. First, level the pressure of the floating bags on both sides. If one of the floating bags is confirmed to be damaged, stop floating immediately. Use two crane ships to assist in lifting and leveling to replace the underwater floating bags. After all the through holes of the actual water intake head are blocked, it can float on the water surface. That is, the underwater draft of the water intake head is 4.05 meters without the floating bag tied to it, and it will not sink to the bottom of the water.
[0107] Step S5: After the water intake head reaches the designated position, a crane ship is used to lift the water intake head.
[0108] Step S5-1, assembling a crane ship, the crane ship includes a first crane ship and a second crane ship; the first crane ship is a 35T assembly crane ship, including a first pontoon group assembled from 8 pontoons of different specifications; and a first lifting device is arranged on the first pontoon group to form a first crane ship 7; the second crane ship is a 30T assembly crane ship, including a second pontoon group assembled from 8 pontoons of different specifications; and a second lifting device is arranged on the second pontoon group to form a second crane ship 8;
[0109] Step S5-1-1, hoisting the first pontoon assembly. Specifically, Fig.10 As shown, the first pontoon group includes pontoon No. 4-4 of the first pontoon group and pontoon No. 5-5 of the first pontoon group, which are located in the middle position and arranged parallel and close to each other; pontoon No. 1-1 of the first pontoon group and pontoon No. 2-2 of the first pontoon group placed side by side are simultaneously connected to pontoon No. 4-4 of the first pontoon group; pontoon No. 7-7 of the first pontoon group and pontoon No. 8-8 of the first pontoon group placed side by side are simultaneously connected to pontoon No. 5-5 of the first pontoon group; The pontoon 4-3 of the first pontoon group 3 is arranged between the pontoon 4-1 of the first pontoon group 1 and the pontoon 4-7 of the first pontoon group 7, and is connected to the pontoon 4-4 of the first pontoon group 4 and the pontoon 4-5 of the first pontoon group 5; the pontoon 4-6 of the first pontoon group 6 is arranged between the pontoon 4-2 of the first pontoon group 2 and the pontoon 4-8 of the first pontoon group 8, and is connected to the pontoon 4-4 of the first pontoon group 4 and the pontoon 4-5 of the first pontoon group 5;
[0110] When lifting the first pontoon group, firstly lift pontoon 4-4 of the first pontoon group and pontoon 4-5 of the first pontoon group into the water by the crane on the shore, and then lift pontoon 4-2 of the first pontoon group, pontoon 4-6 of the first pontoon group and pontoon 4-8 of the first pontoon group, and finally lift pontoon 4-1 of the first pontoon group, pontoon 4-3 of the first pontoon group and pontoon 4-7 of the first pontoon group.
[0111] Step S5-1-2, assembling the first pontoon group.
[0112] When the first pontoon, namely the first pontoon group No. 4 pontoon 4-4, is hoisted into the water, one end of the mooring cable is anchored to the shore, and the other end of the mooring cable is fixedly connected to the No. 4 pontoon. When other pontoons are subsequently hoisted into the water, they are all connected to each other with mooring cables to prevent them from being impacted by the water flow and drifting away. Among them, the mooring cable can be a common mooring cable in the market, which is used to safely and firmly tie the ship to the dock, floating bag, dock or other cable on the ship.
[0113] After all the pontoons are hoisted, pull the mooring rope to move the pontoons, bring all the pontoons close to each other and connect and install them. The connection positions of the pontoons are the top and bottom of the pontoons.
[0114] The bottom of the pontoon is connected by an I-shaped pin or structural welding. An I-shaped groove is set on the side of the pontoon, and the I-shaped pin is inserted into the original I-shaped groove of the pontoon. The I-shaped pin falls into the bottom of the groove to complete the connection of the bottom of each pontoon.
[0115] An I-shaped groove is set at the center position of the two width sides of each pontoon; multiple I-shaped grooves are set on the two length sides of each pontoon according to design requirements, and the I-shaped grooves of two adjacent pontoons are matched with each other to ensure the connection strength of adjacent pontoons.
[0116] Specifically, Fig.10 As shown, the two I-shaped grooves on the length sides of the first pontoon No. 6 pontoon 4-6 need to match the I-shaped grooves on the width sides of the first pontoon No. 5 pontoon 4-5 and the first pontoon No. 4 pontoon 4-4; the I-shaped grooves on the length sides of the first pontoon No. 2 pontoon 4-2 and the first pontoon No. 1 pontoon 4-1 need to match the I-shaped grooves on the length sides of the first pontoon No. 4 pontoon 4-4.
[0117] The two I-shaped grooves on the length side of the first pontoon No. 3 pontoon 4-3 need to match the I-shaped grooves on the width side of the first pontoon No. 5 pontoon 4-5 and the first pontoon No. 4 pontoon 4-4; the I-shaped grooves on the length side of the first pontoon No. 8 pontoon 4-8 and the first pontoon No. 7 pontoon 4-7 need to match the I-shaped grooves on the length side of the first pontoon No. 5 pontoon 4-5.
[0118] Step S5-1-3, hoisting the second pontoon assembly. Fig.11 As shown, the second pontoon group includes a second pontoon group No. 4 pontoon 5-4 and a second pontoon group No. 5 pontoon 5-5 which are located in the middle position and arranged parallel and close to each other; a second pontoon group No. 1 pontoon 5-1 and a second pontoon group No. 2 pontoon 5-2 are respectively arranged at two corner points of the length side of the second pontoon group No. 4 pontoon 5-4; a second pontoon group No. 7 pontoon 5-7 and a second pontoon group No. 8 pontoon 5-5 are respectively arranged at two corner points of the length side of the second pontoon group No. 5 pontoon 5-5. 8; pontoon No. 3 5-3 of the second pontoon group is arranged between pontoon No. 1 5-1 of the second pontoon group and pontoon No. 7 5-7 of the second pontoon group, and is also connected to pontoon No. 4 5-4 of the second pontoon group and pontoon No. 5 5 of the second pontoon group; pontoon No. 6 5-6 of the second pontoon group is arranged between pontoon No. 2 5-2 of the second pontoon group and pontoon No. 8 5-8 of the second pontoon group, and is also connected to pontoon No. 4 5-4 of the second pontoon group and pontoon No. 5 5 of the second pontoon group.
[0119] When the second pontoon group is lifted, the crane on the shore first lifts pontoon No. 4 5-4 of the second pontoon group and pontoon No. 5-5 of the second pontoon group into the water, and then lifts pontoon No. 3 5-3 of the second pontoon group, pontoon No. 1 5-1 of the second pontoon group, pontoon No. 7 5-7 of the second pontoon group, and finally lifts pontoon No. 6 5-6 of the second pontoon group, pontoon No. 2 5-2 of the second pontoon group and pontoon No. 8 5-8 of the second pontoon group.
[0120] Step S5-1-4, assembling the second pontoon group. The steps of assembling the second pontoon group are the same as the steps of assembling the first pontoon group. A person skilled in the art can assemble the second pontoon group according to the steps of assembling the first pontoon group.
[0121] Step S5-2, hoisting the water intake head;
[0122] Step S5-2-1, fix the first crane ship and the second crane ship; the first crane ship and the second crane ship are both fixed by using two anchor cables arranged at the bow and two anchor cables arranged at the stern for figure eight anchoring.
[0123] like Fig.12 As shown, the water intake head is hoisted by two crane ships with two 100-ton buoyancy bags. After the water intake head is floated to the designed position by a tugboat, the first crane ship and the second crane ship both use four anchor cables to fix it in the front and rear figure eight anchors. That is, the first crane ship uses two anchor cables set at the bow of the first crane ship and two anchor cables set at the stern of the first crane ship to fix it in the figure eight anchor; the second crane ship uses two anchor cables set at the bow of the second crane ship and two anchor cables set at the stern of the second crane ship to fix it in the figure eight anchor. Specifically, as Fig.13 As shown, an anchor cable 9 is respectively placed at the left corner of the bow and the right corner of the bow of the first crane ship and the second crane ship to the left oblique front of the bow and the right oblique front of the bow; an anchor cable 9 is respectively placed at the left corner of the stern and the right corner of the stern of the first crane ship and the second crane ship to the left oblique rear of the stern and the right oblique rear of the stern. The two anchor cables placed at the bow and the two anchor cables placed at the stern form an inverted figure eight shape. The intersection angle of the two anchor cables constituting the figure eight anchor is controlled between 30° and 60°, which can not only suppress the swaying of the crane ship, but also increase the combined gripping force of the anchor cables.
[0124] Step S5-2-2, positioning the central axis of the water intake head.
[0125] After the water intake head is floated in place and the two crane ships are positioned, a Φ50mm*8m steel wire rope is set on each top plate lifting ring of the water intake head, a total of four steel wire ropes 10. The steel wire rope set on the top plate lifting ring close to the first crane ship is connected to the hook of the first crane ship; the steel wire rope set on the top plate lifting ring close to the second crane ship is connected to the hook of the second crane ship.
[0126] After the connection, two winches are installed on each crane ship to seal the cables and use the cross intersection method to position the center axis of the top angle of the water intake head, so as to control the installation accuracy of the water intake head before it sinks.
[0127] Specifically, Fig.13 As shown, two winches are placed on both sides of the center line of the first crane ship in the length direction, and the first sealing cable 11-1 connects the winch on the left side of the first crane ship and the right top corner of the water intake head close to the first crane ship; the second sealing cable 11-2 connects the winch on the right side of the first crane ship and the left top corner of the water intake head close to the first crane ship; the intersection of the two sealing cables of the first crane ship is the first intersection. At the same time, two winches are placed on both sides of the center line of the second crane ship in the length direction. The third sealing cable 11-3 connects the winch on the left side of the second crane ship and the right top corner of the water intake head close to the second crane ship; the fourth sealing cable 11-4 connects the winch on the right side of the second crane ship and the left top corner of the water intake head close to the second crane ship; the intersection of the two sealing cables of the second crane ship is the second intersection, and the line connecting the first intersection and the second intersection is the center line of the water intake head, so that the center line of the water intake head and the center lines of the two crane ships are in a straight line, so that the position of the water intake head can be corrected. After the rigging is installed, a trial hoisting should be carried out. During the trial hoisting, the positioning and re-measurement should be carried out and the anchor cables of the floating crane used should be checked to see if they are consistent. After the construction conditions are met, the water-filling and water intake head sinking operation can be carried out.
[0128] Step S6, water intake head installation.
[0129] Step S6-1 is to prepare for the sinking of the water intake head, including: placing a float in the box of the water intake head, and welding a light square tube with a scale on the float; setting a steel plate covering the inspection hole on the top plate of the water intake head, and setting two water inlet pipes and two exhaust pipes on the steel plate; each inspection hole is connected to a water inlet pipe and an exhaust pipe; the light square tube can extend from the exhaust pipe to obtain the water level in the water intake head box.
[0130] The two inspection holes on the top of the water intake head are covered with a 10mm thick steel plate 12 as a blocking plate. Four steel pipes 13 are set on the steel plate to penetrate the steel plate as two water inlet pipes and two exhaust pipes; each inspection hole is connected to a water inlet pipe and an exhaust pipe. The water inlet pipe and the exhaust pipe are welded to the steel plate. Figures 14 to 16As shown, the four steel pipes 13 are connected by angle steels. Preferably, a row of first angle steels 14 parallel to the top surface of the water intake head is provided to connect the four steel pipes in sequence, and are provided at a position slightly above the four steel pipes; two cross second angle steels 15 are provided between two adjacent steel pipes to strengthen the connection strength of the steel pipes. At the same time, an inclined third angle steel 16 is provided on each steel pipe. The third angle steel 16 serves as a diagonal brace, one end of which is connected to the steel plate and the other end is connected to the steel pipe.
[0131] Specifically, two water inlet pipes and two exhaust pipes are welded on the steel plate. The connections and diagonal braces between the steel pipes are made of angle steel of the same specification, and all connection points are welded. Before setting the sealing plate, a float is placed in the box of the water intake head, and a light square tube is welded on the float. The square tube is marked with red paint as a scale. It is necessary to ensure that the float with the light square tube floats on the water surface. The scale extends from the exhaust pipe, and the length of the scale is greater than the length of the exhaust pipe. The water level in the water intake head box can be obtained through the scale on the float, which can then be used to control the water injection volume.
[0132] Step S6-2 is the sinking operation of the water intake head, including: injecting water into the water intake head in batches, and the water intake head sinks autonomously as the amount of water injected increases; after sinking to the placement position, the floating bag is released.
[0133] like Fig.17 As shown, a water level sensor 17 is also required to be installed in each cabin, and the water level sensor is connected to a controller 19 through a water level control line 18 installed in a steel pipe 13 (exhaust pipe); the controller 19 receives the water level signal of the water level sensor 17, and then controls the water pump to pump water. The power is provided by an external power supply 21.
[0134] The water intake head box is filled with water using two water pumps 20 pairs through two water inlet pipes to simultaneously fill the two compartments to ensure that the lifting points of the water intake head box are evenly stressed. It is strictly forbidden to directly open the hole plug to let water in, to prevent the lifting ship from becoming unstable due to uneven water inflow. The sinking operation of the water intake head is divided into five steps:
[0135] Step S6-2-1, the water injection volume of the water intake head reaches one third of the height of the water intake head box. Specifically, the water injection height is one third of the height of the water intake head box, and the two compartments of the water intake head are injected with water simultaneously. After the first injection, it is left to stand for observation for 10 minutes, and the second injection is performed after no abnormal conditions are found;
[0136] Step S6-2-2, the water injection volume of the water intake head reaches two-thirds of the height of the water intake head box. Specifically, the water injection height is one-third of the height of the water intake head box, and the water injection volume reaches two-thirds of the height of the water intake head box. The two compartments of the water intake head are injected with water simultaneously. After the second injection, it is left to stand for observation for 10 minutes. If there is no abnormality, the third injection is carried out;
[0137] Step S6-2-3, continue to inject water into the water intake head until the water level is 0.3 meters from the top plate of the water intake head, as the reserved space 22, that is, a space with a height of 0.30 meters is reserved. Specifically, after the third water injection, a height of 0.3 meters needs to be reserved from the top plate of the water intake head, that is, 0.3 meters of gas is reserved. The reserved part of the water intake head space can be used to increase the underwater self-buoyancy, thereby reducing the lifting force required by the crane ship.
[0138] Among them, water level stroke sensors 17 are set at the bottom of the water tank and at a height of 0.30 meters from the top plate to ensure the spatial accuracy of the reserved 0.3-meter height. When the water level reaches 0.30 meters from the top plate, the water level stroke sensor transmits the water level signal to the controller 18 through the water level control line. The controller controls the water pump and stops water injection to ensure the reserved space in the water intake head box.
[0139] Step S6-2-4, when the water intake head box sinks to about 30cm above the placement position, send divers into the water to check the placement, including the positioning of the water intake head and the placement angle, etc. After confirmation, sink it into place. To ensure safe operation, during the lowering of the water intake head, divers are not allowed to operate in the area directly below the horizontal projection of the water intake head.
[0140] Step S6-2-5, after confirming that it has sunk into place, slowly fill the water tank with water. After the water tank is filled with water, slowly release the pressure of the floating bag and then take it out. Specifically, after sinking into place, the diver uses a level to cooperate with the surveyor on the water to measure the verticality of the board walls around the water intake head box, and uses a sonar detector to re-measure to ensure the horizontal and vertical accuracy of the water intake head. After ensuring that the water intake head is accurately positioned, first remove the steel wire rope of the crane ship. When removing the floating bag, first release the air pressure of the floating bag, slowly release the pressure of the floating bag, and wait until the air pressure of the floating bag is completely released and then remove the floating bag with the cooperation of the crane ship and the diver. Safety ropes should be set up for underwater construction to keep the communication above and below the water unblocked.
[0141] Step S7: Backfill the water intake head.
[0142] Step S7-1, selecting backfill material.
[0143] The design strength of the stone is MU30, the particle size is 200-400mm; the particle size of crushed stone is 20-40mm; the particle size of sand and pebble is 20-40mm. The stone riprap used in this application is hard, without weathering peeling layer or cracks, and the stone surface is free of dirt, slag and other impurities. The stone used for the surface has uniform color, and the physical and mechanical indicators of the stone meet the construction design requirements.
[0144] Step S7-2, using the dumping method to carry out water riprap.
[0145] Step S7-2-1, calculate the amount of riprap. Specifically, before riprap construction, draw a riprap area grid map according to the riprap area, and calculate the riprap amount of each grid in the riprap area grid map. Quantitative riprap is performed on the riprap area corresponding to each grid. Before riprap, it is also necessary to measure the basic conditions of the riprap area such as water depth, flow velocity, and cross-sectional shape. If necessary, the riprap displacement law is mastered through experiments.
[0146] Step S7-2-2, using the excavation equipment to carry out the stone throwing method on the water. Specifically, first transport the excavation vessel carrying the excavation equipment and the anchor machine equipment to the designated location, throw the anchor underwater through the anchor machine, and insert the anchor into the underwater soil by its own weight to fix the excavation vessel. Then, bring the transport ship transporting gravel and boulders close to the excavation vessel, and connect the transport ship and the excavation vessel with a cable to prevent the transport ship from moving away from the excavation vessel when throwing stones.
[0147] Throw the rocks from the most controllable position and then spread out in sequence. When the water is deep and turbulent, first throw rocks at the bottom corner of the water intake head box, then throw some rocks upstream in sequence, and then throw the remaining rocks after measuring the distance affected by the flow velocity on the falling rocks.
[0148] When throwing stones, the flatness and thickness of the stones should be measured in time. Only when the measurement reaches the design standard can they be moved to the new throwing area. When throwing gravel on the base, first throw it to 200mm below the design elevation. Two divers will use a scraper to level the uneven surface again to reach the design elevation. Fig.18 As shown, a reverse slope riprap filling area 23 is finally formed on both sides of the water intake head. Thus, the paving work of the entire foundation pit is completed, meeting the requirements of the subsequent construction process.
[0149] The above are only preferred embodiments of the present invention and are not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention are within the scope of protection of the pending claims of the present invention.
Claims
1. A water intake head construction method for a water intake system, characterized in that: The construction method comprises the following steps: Step S1: selecting a prefabrication site for the water intake head; building a cofferdam around the prefabrication site, and leveling and compacting the prefabrication site; Step S2: prefabricate a water intake head; the water intake head is a hollow box, and the water intake head comprises: a hollow box made of reinforced concrete; a strip through hole is arranged above each side wall of the box as a water inlet; a plurality of partitions are evenly arranged at the water inlet as a water inlet grille; a partition is arranged in the middle of the box to divide the interior of the water intake head into two inner chambers; a circular through hole is arranged on the same side of the outer wall of the two inner chambers, respectively, as a reserved opening for the gravity pipe; and two through holes are also arranged on the top plate of the water intake head as inspection openings; Step S3: excavating the installation area of the water intake head, including: step S3-1 excavating a foundation pit in the installation area of the water intake head; and step S3-2 underwater leveling the bottom of the foundation pit; Step S4: floating the water intake head, comprising: Step S4-1, calculate the water intake head floatation and determine the floatation bag specifications; Step S4-2, tying up the floating bag; the floating bag includes a buoy; the floating bag is installed parallel to the ground on both sides of the water intake head; Step S4-3, trial floating; Step S4-4, floating transportation, using a transport boat to tow the water intake head to a designated location; Step S5: After the water intake head reaches the designated position, the water intake head is hoisted by a crane ship: Step S5-1, assembling a crane ship, the crane ship includes a first crane ship and a second crane ship; the first crane ship is a 35T assembly crane ship, including a first pontoon group assembled from 8 pontoons of different specifications; and a first lifting device arranged on the first pontoon group, constituting the first crane ship; the second crane ship is a 30T assembly crane ship, including a second pontoon group assembled from 8 pontoons of different specifications; and a second lifting device arranged on the second pontoon group, constituting the second crane ship; Step S5-2, hoisting the water intake head, including step S5-2-1, fixing the first crane ship and the second crane ship; step S5-2-2, positioning the central axis of the water intake head: two winches are set on the first crane ship and the second crane ship, and the central axis is positioned by using a sealing cable to the top angle of the water intake head by a cross intersection method; Step S6, water intake head installation; The method comprises the steps of S6-1, preparing for sinking the water intake head; placing a float in the box of the water intake head, and welding a light square tube with a scale on the float; arranging a steel plate covering the inspection hole on the top plate of the water intake head, and arranging four steel pipes on the steel plate as two water inlet pipes and two exhaust pipes; every two of the steel pipes are connected to the inside of the water intake head through one of the inspection holes; the light square tube can extend from the exhaust pipe, and the water level in the box of the water intake head can be obtained through the scale; Step S6-2, sinking operation of the water intake head, including: injecting water into the water intake head in batches, and the water intake head sinks autonomously as the amount of water injected increases; after sinking to a preset placement position, releasing the buoyancy bag; Step S7, backfilling the water intake head, includes S7-1, selecting backfill materials; S7-2, adopting the backfill method to perform water riprap.
2. The water intake head construction method according to claim 1, characterized in that: The step S1 comprises: Step S1-1, the prefabrication site is set at the shore and close to the pump house used by the water intake system; the construction of the cofferdam at the prefabrication site includes: using excavation equipment to pile up the fill used for the cofferdam from both sides of the cofferdam to the middle of the cofferdam and rolling and compacting it until the fill is gathered from both sides of the cofferdam to the middle of the cofferdam, and the prefabrication site is constructed in a circular manner to finally form fill; the fill also includes: forming a water-facing slope with a slope of 1:1 on the side close to the shore; forming a water-receiving slope with a slope of 1:1 on the side away from the shore; Step S1-2, leveling and compacting the prefabrication site includes: constructing a drainage ditch on both sides of the prefabrication site toward the lake surface, constructing a foundation water pit downstream of each drainage ditch, and using an automatic drainage system to pump and drain water from the prefabrication site; after drainage, leveling the ground of the prefabrication site and constructing a concrete cushion layer.
3. The water intake head construction method according to claim 1, characterized in that: The step S3 comprises: Step S3-1: excavation of the foundation pit of the water intake head installation area includes layered stepped excavation; the layered stepped excavation divides the cross section of the water intake head installation area into 4 steps from high to low, and the thickness of each step is 1 meter; the width of the highest step is the widest, and the width of the step becomes narrower layer by layer as the height of the step decreases, and finally forms an inverted slope with a slope ratio of 1:2.5; Step S3-2 underwater leveling includes: using a foundation pit leveling device to perform underwater trimming on the uneven bottom of the foundation pit; the foundation pit leveling device includes: a leveling track, two of the leveling tracks are placed in parallel; the leveling track is controlled by a water-outlet steel wire rope controlled by an engineering vessel; bagged gravel is laid under the leveling track according to design requirements; a leveling scraper connects the two leveling tracks, slides on the leveling tracks, and fills the foundation pit with gravel to level it.
4. The water intake head construction method according to claim 1, characterized in that: The step S4-1 comprises: Step S4-1-1, obtaining the buoyancy per meter of the water intake head and the self-buoyancy of the water intake head according to the size of the water intake head; Step S4-1-2, calculating the draft depth of the water intake head; Step S4-1-3, determine the specifications of the floating bag and calculate the floating draft when the water intake head is equipped with the bag.
5. The water intake head construction method according to claim 1, characterized in that: The step S5-1 comprises: Step S5-1-1, hoisting the first pontoon assembly; Step S5-1-2, assembling the first pontoon group; setting an I-shaped groove at the center position of the two width sides of each pontoon; setting multiple I-shaped grooves at the two length sides of each pontoon according to design requirements, and the I-shaped grooves of two adjacent pontoons are matched with each other; installing a pin matching the shape of the I-shaped groove in the I-shaped groove; the length of the pin matches the height of each pontoon; Step S5-1-3, hoisting the second pontoon assembly; Step S5-1-4, assembling the second pontoon group; the steps for assembling the second pontoon group are the same as the steps for assembling the first pontoon group.
6. The water intake head construction method according to claim 1, characterized in that: The step S5-2-1 comprises: the first crane ship uses two anchor cables arranged at the bow of the first crane ship and two anchor cables arranged at the stern of the first crane ship to perform figure-eight anchoring; the second crane ship uses two anchor cables arranged at the bow of the second crane ship and two anchor cables arranged at the stern of the second crane ship to perform figure-eight anchoring; The step S5-2-2 includes: placing two winches on both sides of the center line of the first crane ship in the length direction, the first sealing cable connects the winch on the left side of the first crane ship and the right top corner of the water intake head close to the first crane ship; the second sealing cable connects the winch on the right side of the first crane ship and the left top corner of the water intake head close to the first crane ship; the intersection of the two sealing cables of the first crane ship is the first intersection; and placing the two winches on both sides of the center line of the second crane ship in the length direction, the third sealing cable connects the winch on the left side of the second crane ship and the right top corner of the water intake head close to the second crane ship; the fourth sealing cable connects the winch on the right side of the second crane ship and the left top corner of the water intake head close to the second crane ship; the intersection of the two sealing cables of the second crane ship is the second intersection, and the line connecting the first intersection and the second intersection is the center line of the water intake head.
7. The water intake head construction method according to claim 1, characterized in that: The step S6-1 also includes: the four steel pipes are connected with angle steels; a row of first angle steels parallel to the top surface of the water intake head are arranged to connect the four steel pipes in sequence, and the first angle steels are arranged at the upper position of the four steel pipes; two crossed second angle steels are arranged between two adjacent steel pipes; and an inclined third angle steel is arranged on each steel pipe, one end of the third angle steel is connected to the steel plate, and the other end of the third angle steel is connected to the steel pipe.
8. The water intake head construction method according to claim 1, characterized in that: The step S6-2 comprises: Step S6-2-1, the water injection amount of the water intake head reaches one third of the height of the water intake head box; Step S6-2-2, the water injection amount of the water intake head reaches two-thirds of the height of the water intake head box; Step S6-2-3, continue to inject water into the water intake head until the water level in the water intake head is 0.3 meters away from the top plate of the water intake head; a water level travel sensor is arranged in each cabin, and the water level travel sensor is connected to the controller through a water level control line arranged in the exhaust pipe; the controller receives the water level signal from the water level travel sensor, and then controls the water pump to pump water; Step S6-2-4, when the water intake head sinks to a height of 30 cm from the preset placement position, check the position of the water intake head and sink it into place after confirming that it is correct; Step S6-2-5, after confirming that the water intake head has sunk into place, continue to inject water into the water intake head box until the water tank is full of water; after the water tank is full of water, release the pressure of the floating bag; wait until the air pressure of the floating bag is completely released, and then remove the floating bag.
9. The water intake head construction method according to claim 1, characterized in that: The step S7-2 includes: step S7-2-1, calculating the amount of rock throwing; step S7-2-2, first throwing rocks at the bottom corner of the water intake head box, and then throwing some rocks upstream in sequence, measuring the distance affected by the flow velocity on the falling rocks, and then throwing the remaining rocks.