Through the method of cross-comparing and fusion calibration of multi-source data, combined with PID control and average deviation calculation, the accuracy and stability of the edge work of the unmanned road roller is solved, and efficient control of continuous edge work in multiple work areas is achieved.
Patent Information
- Application Number
- CN202411150596.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-21
- Publication Date
- 2024-11-05
- Estimated Expiration
- 2044-08-21
AI Technical Summary
In the construction of unmanned road rollers, it is difficult to achieve accurate and flexible control of edge operations. Traditional methods rely on edge coordinates of design files and require high accuracy of edge sensors. It is difficult to achieve continuous edge operations in multiple work areas, resulting in control errors and Instability.
By obtaining edge coordinate information in the design file, dividing multiple compaction work areas, combining real-time paving area coordinate data and edge detection data, multi-source data cross-comparison and fusion calibration methods are used, and PID control based on pre-sighting points is used and multiple average deviation calculation methods to realize continuous edge work in multiple work areas.
It improves the reliability and stability of the welting operation, reduces error control, and realizes the accuracy of welting rolling and the continuity of multi-working operations.
Smart Images

Figure CN118672275B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of road construction, and in particular to a control method for edge-following operation of an unmanned roller. Background Art
[0002] During the unmanned construction process, the edge of the paving area needs to be touched, which is a difficult part of unmanned control. The edge operation requires that the roller's operating wheels are as close to the paving edge as possible to ensure compaction quality, while also preventing the operating wheels from rolling over the curbstones or the outside of the edge to damage construction facilities.
[0003] The traditional manual edge rolling mode can adjust the position of the working wheel at any time by visual inspection. However, in the unmanned driving scenario, the current perception equipment and control methods are difficult to achieve the accuracy and flexibility of manual observation, so most of them only rely on the edge coordinates in the design file for control. However, due to the accuracy limitations of the controller, the error limitations of the positioning sensor, and even the error between the paving area of the paver and the design area, this type of control method is difficult to truly fit the actual construction conditions, and it is impossible to accurately and flexibly realize the unmanned driving edge rolling operation.
[0004] In addition, existing technologies mostly rely on real-time edge status detection to achieve real-time control of the roller, but this method has extremely high requirements on the precision of the edge sensor and the accuracy of compaction control, and requires a large number of calibration tests for each automatic driving roller, which makes it difficult to promote and apply on a large scale.
[0005] Therefore, it is urgent to design a control method for the edge operation of an unmanned roller to solve the problems existing in the above-mentioned prior art. Summary of the invention
[0006] In view of the above defects or improvement needs of the prior art, the present invention provides a control method for the edge-following operation of an unmanned roller, which aims to realize continuous edge-following operation in multiple work areas and improve the reliability and stability of the edge-following operation control.
[0007] In order to achieve the above object, the present invention adopts the following technical solutions:
[0008] A first aspect of the present invention provides a method for controlling an unmanned roller to perform an edge-following operation, the method comprising the following steps:
[0009] Step S1: Obtain the design file of the area to be compacted by the unmanned roller, extract the coordinate information of the compaction boundary, and construct the edge coordinate vector that needs to be compacted ;
[0010] Step S2: According to the compaction boundary coordinate information, the area to be compacted is divided into 1 to n compaction work areas along the compaction direction, and the edge coordinate vector Split into ~ coordinate vectors;
[0011] Step S3: Obtain the coordinate information of the center point of the area paved by the paver, and calculate the coordinate vector of the paving edge on the side to be paved according to the paving width , and match them according to the starting and ending points of the compaction work area, split into coordinate vectors ~ ;
[0012] Step S4: When the unmanned roller enters the first work area and performs the edge operation, calculate and The average deviation , determine the threshold , by comparing the average deviation and threshold The target edge coordinate vector of the edge control in the first work area is determined by the criterion for tracking. The tracking of the unmanned roller for edge operation adopts PID control based on the preview point. During the edge operation, the distance between the edge of the rolling wheel and the paving boundary is calculated in real time through the edge detection sensor to form the distance vector of the first work area. ;
[0013] Step S5: When the unmanned roller completes the operation in the first work area and is about to enter the second work area, the target edge coordinate vector of the second work area is determined according to the criteria in step S4. , then according to the distance vector calculated in step S4 Offset in the opposite direction to form an updated edge coordinate vector , the driverless roller is based on the edge coordinate vector Carry out the edging work in the second work area;
[0014] Step S6: When the unmanned roller completes the operation in the 2nd to n-1th work area and is about to enter the 3rd to nth work area, the edge coordinate vector is calculated according to step S5 , and perform the welt operation.
[0015] As an embodiment of the present application, the edge coordinate vector in step S1 It is a series of discrete coordinate points with an interval of 0.1m~1m.
[0016] As an embodiment of the present application, the compaction work area in step S2 is rectangular, with a length of 20-40 m, and adjacent compaction work areas have an overlapping area in the length direction, and the length of the overlapping area is 2-10 m.
[0017] As an embodiment of the present application, in step S3, the coordinate information of the center point of the paved area of the paver is continuously obtained by a positioning module installed on the paver, and the length of the center point of the paver from the edge of the screed plate in the direction of the edging operation is measured, and the paving edge coordinate vector is calculated by translation according to the coordinates of the center point. .
[0018] As an embodiment of the present application, in step S4, by comparing the average deviation and threshold The criteria for determining the target edge coordinate vector of the edge control in the first work area for tracking include:
[0019] like ,by As the target edge coordinate vector ;
[0020] like ,by As the target edge coordinate vector .
[0021] As an embodiment of the present application, the and The average deviation The calculation method uses one of the Manhattan distance, Chebyshev distance, and Euclidean distance.
[0022] As an embodiment of the present application, the edge detection sensor used in step S4 to calculate the distance between the edge of the rolling wheel and the paving boundary in real time adopts one of an image, a laser radar, and a laser ranging sensor.
[0023] As an embodiment of the present application, the target edge coordinate vector in step S5 is According to the distance vector When calculating the offset in the opposite direction, first calculate the target edge coordinate vector and the distance vector Align and transform the distance vector Resample so that its dimension is the same as the target edge coordinate vector Consistent.
[0024] The beneficial effects of the present invention are:
[0025] 1. The present invention combines design file data, real-time paving coordinate data and roller edge detection data, and realizes continuous edge operation in multiple work areas through multi-source data cross-comparison and fusion calibration, thereby improving the reliability of edge operation control; compared with the traditional control method that only relies on the vehicle-end edge detector, error control is easier and more reliable;
[0026] 2. The present invention divides the area to be compacted into 1 to n compaction work areas along the compaction direction according to the compaction boundary coordinate information, which is in line with the "multi-work area" operation mode of existing unmanned compaction. The error status of the current work area operation is used as the control parameter of the next work area operation, which can realize the timely correction of the edge control model, increase reliability, and improve the accuracy of the edge rolling of the unmanned roller;
[0027] 3. The present invention provides a variety of average deviation calculation methods. In different operating scenarios, the most suitable deviation calculation model can be compared and selected to improve the stability of the edge control of the unmanned roller. BRIEF DESCRIPTION OF THE DRAWINGS
[0028] Figure 1 A technical solution flow chart of a method for controlling an unmanned roller side-to-side operation provided in an embodiment of the present invention;
[0029] Figure 2 A schematic diagram of compaction work area division of a method for controlling an unmanned roller's edge-adjacent operation provided in an embodiment of the present invention;
[0030] Figure 3 A schematic diagram of a field test of a control method for an unmanned roller following the edge operation provided in an embodiment of the present invention;
[0031] Figure 4 The error distribution measured results of the unmanned roller working along the edge in the embodiment of the present invention.
[0032] In the figure: 1. Area to be compacted; 2. Paver; 3. Unmanned roller; 4. Rolling edge in the design document; 5. Rolling edge of paving; 6. Rolling edge of actual operation. DETAILED DESCRIPTION
[0033] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0034] It should be noted that all directional indications (such as up, down, left, right, front, back, etc.) in the embodiments of the present invention are only used to explain the relative position relationship, movement status, etc. between the components under a certain specific posture (as shown in the accompanying drawings). If the specific posture changes, the directional indication will also change accordingly.
[0035] In the present invention, unless otherwise clearly specified and limited, the terms "connection", "fixation", etc. should be understood in a broad sense. For example, "fixation" can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements, unless otherwise clearly defined. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0036] In addition, if there are descriptions involving "first", "second", etc. in the embodiments of the present invention, the descriptions of "first", "second", etc. are only used for descriptive purposes and cannot be understood as indicating or implying their relative importance or implicitly indicating the number of technical features indicated. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In addition, the meaning of "and / or" appearing in the full text includes three parallel schemes. Taking "A and / or B" as an example, it includes scheme A, or scheme B, or a scheme that satisfies both A and B. In addition, the technical solutions between the various embodiments can be combined with each other, but it must be based on the ability of ordinary technicians in the field to implement. When the combination of technical solutions is contradictory or cannot be implemented, it should be deemed that such a combination of technical solutions does not exist and is not within the scope of protection required by the present invention.
[0037] Reference Figures 1 to 4 The first aspect of the present invention provides a method for controlling an unmanned roller to follow the edge of an operation, the method comprising the following steps:
[0038] Step S1: Obtain the design file of the area to be compacted by the unmanned roller, extract the coordinate information of the compaction boundary, and construct the edge coordinate vector that needs to be compacted , the edge coordinate vector A series of discrete coordinate points, the coordinate point format can be one of the coordinate formats such as WGS84 and CGC2000. In this embodiment, WGS84 coordinates are used, and the edge coordinate data in the design file is extracted, and then obtained through coordinate conversion and interpolation calculation, wherein the coordinate point interval is 0.1m~1m;
[0039] Step S2: According to the compaction boundary coordinate information, the area to be compacted is divided into 1 to n compaction work areas along the compaction direction, such as Figure 2 As shown, the edge coordinate vector Split into ~ coordinate vectors, the compaction work area is set as a rectangle with a length of 20-40m. In this embodiment, the length of the compaction work area is set to 30m. Adjacent compaction work areas have overlapping areas in the length direction, and the length of the overlapping area is 2-10m. In order to avoid local under-pressure, the compaction work areas usually need to have a certain overlap in the length direction. In this embodiment, the basic overlapping length is set to 5m, the minimum is not less than 2m, and the maximum is not more than 10m. The above considerations are mainly based on the road line shape of the working area. If the working area is a straight line segment, the overlapping length is 5m; if the working area is a curved segment, the curved segment needs to be divided into multiple continuous broken line segments first, and the adjacent work areas divided in this way will have a certain angle, and the length of the overlapping area needs to be controlled within 2m-10m.
[0040] Step S3: Obtain the coordinate information of the center point of the area paved by the paver, and calculate the coordinate vector of the paving edge on the side to be paved according to the paving width , and match them according to the starting and ending points of the compaction work area, split into coordinate vectors ~ Specifically, the coordinate information of the center point of the paved area of the paver is continuously obtained through the positioning module installed on the paver, and the length of the center point of the paver from the edge of the screed plate in the direction of the edging operation is measured, and the paving edge coordinate vector is calculated by translation based on the coordinates of the center point. .
[0041] Among them, due to the operating error of the paver, the actual paving edge and the designed edge may not completely match, so it is necessary to compare and correct it in combination with the real-time positioning data of the paver. In this embodiment, the positioning module installed on the paver can obtain the center point coordinate information in real time. Then, by measuring the distance L between the center point of the paver and the edge of the screed on the side of the rolling edge, and performing a translation calculation based on the length, the paving edge coordinate vector can be obtained. .
[0042] Step S4: When the unmanned roller enters the first work area and performs the edge operation, calculate and The average deviation , determine the threshold , by comparing the average deviation and threshold The target edge coordinate vector of the edge control in the first work area is determined according to the criterion for tracking. When the unmanned roller performs edge tracking according to the determined boundary coordinate vector, the tracking of the unmanned roller along the edge adopts PID control based on the preview point, that is, according to the current coordinate position of the working wheel of the unmanned roller, the deviation between it and the boundary coordinate vector is calculated, the next target point is determined, and according to the deviation, PID control or fuzzy PID control is adopted to adjust the steering angle of the roller to realize edge tracking operation.
[0043] During the edge-adhering operation, the edge-adhering detection sensor calculates the distance between the edge of the rolling wheel and the paving boundary in real time to form the distance vector of the first work area. The edge detection sensor used to calculate the distance between the edge of the rolling wheel and the paving boundary in real time adopts one of the image, laser radar, and laser ranging sensors. Specifically, in this embodiment, the edge detection sensor adopts a laser ranging-based mode, and returns the distance between the current roller steel wheel and the side through laser ranging to form a distance vector coordinate D to represent the error between the actual trajectory of the edge operation and the preset trajectory;
[0044] Specifically, by comparing the average deviation and threshold The criteria for determining the target edge coordinate vector of the edge control in the first work area for tracking include:
[0045] like ,by As the target edge coordinate vector ;
[0046] like ,by As the target edge coordinate vector .
[0047] Among them, the and The average deviation The calculation method adopts one of Manhattan distance, Chebyshev distance and Euclidean distance; specifically, in this embodiment, Chebyshev distance is used to represent and The average deviation , and set the threshold =0.2m, that is, when the maximum deviation between the design boundary and the paving boundary of the paver reaches more than 20cm, it is considered that the unmanned roller should follow the measured boundary of the paver and perform the edge operation; otherwise, it should follow the design boundary to perform the edge operation.
[0048] Specifically, the present invention provides a variety of average deviation calculation methods, and in different operating scenarios, the most suitable deviation calculation model can be compared and selected to improve the stability of the edge control of the unmanned roller.
[0049] Step S5: When the unmanned roller completes the operation in the first work area and is about to enter the second work area, the average deviation is compared in step S4. and threshold The target edge coordinate vector of the second working area is determined by the criterion , then according to the distance vector calculated in step S4 Offset in the opposite direction to form an updated edge coordinate vector , the driverless roller is based on the edge coordinate vector Execute the edge-adhering operation in the second work area; the target edge coordinate vector According to the distance vector When calculating the offset in the opposite direction, you need to first calculate the target edge coordinate vector and the distance vector Align and transform the distance vector Resample so that its dimension is the same as the target edge coordinate vector Consistent.
[0050] Step S6: When the unmanned roller completes the operation in the 2nd to n-1th work area and is about to enter the 3rd to nth work area, the edge coordinate vector is calculated according to step S5 , and perform the welt operation.
[0051] Specifically, the present invention combines design file data, real-time paving coordinate data and roller edge detection data, and realizes continuous edge operation in multiple work areas through multi-source data cross-comparison and fusion calibration methods, thereby improving the reliability of edge operation control; compared with the traditional control method that only relies on the vehicle-end edge detector, error control is easier and more reliable.
[0052] According to the above steps, actual measurements are carried out at the test site. Figure 3 The figure shows a schematic diagram of the field test, including a paver 2 with continuous positioning information collection and an unmanned roller 3 for compaction operation, wherein the paver 2 is equipped with a positioning module, and the unmanned roller 3 is equipped with a positioning module and an edge detection sensor. First, the design file of the area to be compacted 1 of the unmanned roller 3 is obtained, and the edge coordinate vector of the area to be compacted 1 is determined according to the rolling edge 4 of the design file. At the same time, the positioning information of the paver 2 is obtained in real time, and the coordinate vector of the paving edge is constructed according to the paved rolling edge 5. On this basis, combined with the detection results of the edge sensor of the unmanned roller 3, the compaction edge error is analyzed, and the coordinate vector of the rolling edge 6 of the actual operation is corrected.
[0053] Figure 4 The figure shows the test effect of the tracking error of edge rolling. The cumulative test mileage is 90m (including 3 work areas in total). In the first work area, since the control error of the unmanned roller itself could not be corrected, the maximum tracking error reached more than 20cm. From the second work area onwards, the tracking error was controlled within 7cm, realizing the timely correction of the edge control model and increasing the reliability. This shows that the method proposed in the present invention has a good effect on improving the accuracy of edge rolling.
[0054] If the above functions are implemented in the form of software functional units and sold or used as independent products, they can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of the present invention, or the part that contributes to the prior art or the part of the technical solution, can be embodied in the form of a software product. The computer software product is stored in a storage medium, including several instructions for a computer device (which can be a personal computer, a server, or a network device, etc.) to perform all or part of the steps of the method described in each embodiment of the present invention. The aforementioned storage medium includes: U disk, mobile hard disk, read-only memory (ROM, Read-Only Memory), random access memory (RAM, Random Access Memory), disk or optical disk, etc., which can store program code.
[0055] It will be appreciated by those skilled in the art that embodiments of the present invention may be provided as methods, systems, or computer program products. Therefore, the present invention may take the form of a complete hardware embodiment, a complete software embodiment, or an embodiment combining software and hardware. Moreover, the present invention may take the form of a computer program product implemented on one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) containing computer-usable program codes. The schemes in the embodiments of the present invention may be implemented in various computer languages, for example, object-oriented programming language Java and literal scripting language JavaScript, etc.
[0056] The present invention is described with reference to flowcharts and / or block diagrams of methods, devices (systems), and computer program products according to embodiments of the present invention. It should be understood that each process and / or block in the flowchart and / or block diagram, as well as the combination of processes and / or blocks in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing device to produce a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the processes in the flowchart and / or block diagram. Figure 1A process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.
[0057] These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer-readable memory produce an article of manufacture comprising an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.
[0058] These computer program instructions can also be loaded onto a computer or other programmable data processing device so that a series of operating steps are executed on the computer or other programmable device to produce a computer-implemented process, thereby providing instructions for implementing the process in the computer or other programmable device. Figure 1 A process or multiple processes and / or boxes Figure 1 The steps for the functions specified in one or more boxes.
[0059] Although the preferred embodiments of the present invention have been described, those skilled in the art may make other changes and modifications to these embodiments once they have learned the basic creative concept. Therefore, the appended claims are intended to be interpreted as including the preferred embodiments and all changes and modifications that fall within the scope of the present invention.
[0060] Obviously, those skilled in the art can make various changes and modifications to the present invention without departing from the spirit and scope of the present invention. Thus, if these modifications and variations of the present invention fall within the scope of the claims of the present invention and their equivalents, the present invention is also intended to include these modifications and variations.
[0061] The above descriptions are only some preferred embodiments of the present disclosure and an explanation of the technical principles used. Those skilled in the art should understand that the scope of the invention involved in the embodiments of the present disclosure is not limited to the technical solutions formed by a specific combination of the above technical features, but should also cover other technical solutions formed by any combination of the above technical features or their equivalent features without departing from the above inventive concept. For example, the above features are replaced with (but not limited to) technical features with similar functions disclosed in the embodiments of the present disclosure.
Claims
1. A control method for an unmanned roller to operate along the edge, characterized in that: The method comprises the following steps: Step S1: Obtain the design file of the area to be compacted by the unmanned roller, extract the coordinate information of the compaction boundary, and construct the edge coordinate vector that needs to be compacted ; Step S2: According to the compaction boundary coordinate information, the area to be compacted is divided into 1 to n compaction work areas along the compaction direction, and the edge coordinate vector Split into ~ coordinate vectors; Step S3: Obtain the coordinate information of the center point of the area paved by the paver, and calculate the coordinate vector of the paving edge on the side to be paved according to the paving width , and match them according to the starting and ending points of the compaction work area, split into coordinate vectors ~ ; Step S4: When the unmanned roller enters the first work area and performs the edge operation, calculate and The average deviation , determine the threshold , by comparing the average deviation and threshold The target edge coordinate vector of the edge control in the first work area is determined by the criterion for tracking. The tracking of the unmanned roller for edge operation adopts PID control based on the preview point. During the edge operation, the distance between the edge of the rolling wheel and the paving boundary is calculated in real time through the edge detection sensor to form the distance vector of the first work area. ; Step S5: When the unmanned roller completes the operation in the first work area and is about to enter the second work area, the average deviation is compared in step S4. and threshold The target edge coordinate vector of the second working area is determined by the criterion , then according to the distance vector calculated in step S4 Offset in the opposite direction to form an updated edge coordinate vector , the driverless roller is based on the edge coordinate vector Carry out the edging work in the second work area; Step S6: When the unmanned roller completes the operation in the 2nd to n-1th work area and is about to enter the 3rd to nth work area, the edge coordinate vector is calculated according to step S5 , and perform welt work; In step S4, by comparing the average deviation and threshold The criteria for determining the target edge coordinate vector of the edge control in the first work area for tracking include: like ,by As the target edge coordinate vector ; like ,by As the target edge coordinate vector .
2. The control method for the unmanned roller's edge-adjacent operation according to claim 1, characterized in that: The edge coordinate vector in step S1 It is a series of discrete coordinate points with an interval of 0.1m~1m.
3. The control method for the unmanned roller's edge-adjacent operation according to claim 1, characterized in that: In step S2, the compaction work area is rectangular and has a length of 20-40 m. Adjacent compaction work areas have an overlapping area in the length direction, and the length of the overlapping area is 2-10 m.
4. The control method for the unmanned roller's edge-adjacent operation according to claim 1, characterized in that: In step S3, the coordinate information of the center point of the paved area of the paver is continuously obtained by a positioning module installed on the paver, and the length of the center point of the paver from the edge of the screed plate in the direction of the edging operation is measured. The paving edge coordinate vector is calculated by translation based on the coordinates of the center point. .
5. The control method for the unmanned roller's edge-adjacent operation according to claim 1, characterized in that: Said and The average deviation The calculation method uses one of the Manhattan distance, Chebyshev distance, and Euclidean distance.
6. The control method for the unmanned roller's edge-adjacent operation according to claim 1, characterized in that: The edge detection sensor used in step S4 to calculate the distance between the edge of the rolling wheel and the paving boundary in real time is one of an image sensor, a laser radar, and a laser ranging sensor.
7. The control method for the unmanned roller's edge-adjacent operation according to claim 1, characterized in that: The target edge coordinate vector in step S5 According to the distance vector When calculating the offset in the opposite direction, first calculate the target edge coordinate vector and the distance vector Align and transform the distance vector Resample so that its dimension is the same as the target edge coordinate vector Consistent.