Offshore wind power hydrogen production safety evaluation method

By combining the risk matrix analysis of wind fluctuations and hydrogen production-related indicators, the safety evaluation problem of hydrogen leakage and explosion in offshore wind power hydrogen production is solved, achieving safe operation of the system and effective assessment of accident risks.

CN118691069APending Publication Date: 2024-09-24CNOOC RONGFENG ENERGY CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410574950.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-05-10
Publication Date
2024-09-24

AI Technical Summary

Technical Problem

During the hydrogen production process of offshore wind power, due to the fluctuation of wind and the special properties of hydrogen, the concentration of hydrogen and oxygen is unstable, and hydrogen leakage, combustion or explosion is prone to occur, and there is a lack of effective safety evaluation methods.

Method used

An offshore wind power hydrogen production safety evaluation method is adopted. By collecting and sorting wind fluctuation index data, combined with the input current and gas concentration of the hydrogen production electrolyzer, the weight coefficient is used for risk assessment, and the risk matrix analysis algorithm is used to determine the cause of the accident. Possibility and severity of consequences, dynamically adjust weight coefficients for system re-evaluation.

Benefits of technology

It achieves a comprehensive risk assessment of the offshore wind power hydrogen production system, provides more accurate safety evaluation results, reduces the possibility and consequences of accidents, and ensures safe operation of the system.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118691069A
    Figure CN118691069A
Patent Text Reader

Abstract

The invention discloses an offshore wind power hydrogen production safety evaluation method which comprises the following steps: S1, collecting and sorting wind power volatility index data; s2, performing safety evaluation on the whole system by taking the selected data as indexes of safety evaluation; s3, obtaining a risk level unit; and S4, safety reevaluation is carried out in combination with the field data and the evaluation result. According to the method, related safety indexes of the hydrogen production side are considered, wind power fluctuation indexes are fused, a comprehensive risk level unit can be obtained according to the operation condition, and then safety evaluation is carried out. According to the evaluation method, an advanced algorithm is adopted for calculation and judgment, the evaluation result is more accurate, and the evaluation method plays a great role in safe operation of the system.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of risk assessment, and in particular relates to a safety assessment method for offshore wind power hydrogen production. Background Art

[0002] As a new type of green hydrogen production method, the safety of offshore wind power generation coupled with water electrolysis has always attracted much attention. Due to the volatility of wind power and the special physical and chemical properties of hydrogen, the concentration of hydrogen and oxygen in the hydrogen production process is unstable, and hydrogen leakage is very likely to occur in the actual operation of hydrogen production stations.

[0003] Hydrogen has a low explosion limit and a low minimum ignition energy, which makes it very easy for hydrogen to burn or even explode after leakage. Scientifically and correctly evaluating the safety of the entire offshore wind power hydrogen production system can not only determine in advance whether hydrogen will leak and issue an early warning to ensure the safe operation of the system, but is also an important measure to reduce the consequences of accidents.

[0004] Currently, there is no safety assessment method for offshore wind power hydrogen production in the existing technology. Summary of the invention

[0005] The problem to be solved by the present invention is to provide a safety evaluation method for offshore wind power hydrogen production. The method mainly incorporates the volatility of wind power generation as an important reference indicator for safety evaluation into the overall safety evaluation system, realizes the effective coupling of the two, and provides an important reference for the safe operation of the entire system.

[0006] In order to solve the above technical problems, the technical solution adopted by the present invention is: a safety evaluation method for offshore wind power hydrogen production, comprising the following steps:

[0007] S1: Collect and organize wind power fluctuation index data;

[0008] S2: Use the selected data as safety evaluation indicators to conduct safety evaluation on the entire system;

[0009] S3: Derive the risk level unit;

[0010] S4: Conduct safety reassessment based on on-site data and assessment results.

[0011] Furthermore, in S1, the wind fluctuation index includes wind speed and wind direction, and the data also includes input current of the hydrogen production electrolyzer, oxygen concentration in hydrogen, and hydrogen concentration in oxygen.

[0012] Further, the S2 comprises the following steps:

[0013] S21: normalize the input current of the electrolyzer, oxygen concentration in hydrogen, hydrogen concentration in oxygen and wind power fluctuation index and multiply them by different weight coefficients to conduct risk assessment and judgment;

[0014] S22: Dynamically adjust the weight coefficient according to the risk level unit results and conduct system re-evaluation.

[0015] Furthermore, the calculation formula of S21 is as follows:

[0016] L=(w1*μ1+w2*μ2+w3*μ3+w4*μ4) / ∑wi,w4<0.5; L=1,w4≥0.5

[0017] Where L is the probability of an accident; w1, w2, w3, w4, ∑wi=1 are different weight coefficients; μ1=I1 / I0, μ2=V1 / V O , μ3=V2 / V H , μ4=P4 / P0, where I0 is the input current reference value, V O is the reference value of oxygen concentration in hydrogen, V H is the reference value of hydrogen concentration in oxygen, and P0 is the reference value of wind fluctuation index.

[0018] Furthermore, in S3, the risk level is determined by using a risk matrix analysis algorithm, and the formula is as follows:

[0019] R=L*S

[0020] Among them, R is the risk value, L is the possibility of an accident; and S is the severity of the consequences of the accident.

[0021] Furthermore, R is the risk value, which is a combination of the possibility of an accident and the consequences of the incident, and is divided into five levels: A1, B2, C3, D4, and E5; L is divided into five levels: 1-5; S is the severity of the consequences of the accident, and is divided into levels 1-5; the larger the R value, the more dangerous the system is and the greater the risk.

[0022] Furthermore, when w4>0.5, the level of R is determined to be the highest level of E5;

[0023] When R is at levels A1 and B2, no re-evaluation is required; when R is at levels C3, D4, and E5, a systematic re-evaluation is required.

[0024] Furthermore, the present invention also provides a device for running the above data processing method.

[0025] Furthermore, the present invention also provides a device, comprising a memory, a processor, and an algorithm stored in the memory and executable on the processor, wherein the processor implements the above-mentioned data processing method when executing the computer program.

[0026] Furthermore, the present invention also provides a computer-readable storage medium, wherein the computer-readable storage medium stores a computer algorithm, and the computer algorithm implements the above-mentioned data processing when executed by a processor.

[0027] The advantages and positive effects of the present invention are:

[0028] The present invention not only considers the relevant safety indicators of the hydrogen production side, but also integrates the wind power volatility indicators, and can derive a comprehensive risk level unit according to the operation conditions, and then conduct a safety evaluation. The evaluation method of the present invention uses advanced algorithms for calculation and judgment, and the evaluation results are more accurate, which plays a great role in the safe operation of the system. BRIEF DESCRIPTION OF THE DRAWINGS

[0029] Figure 1 It is an overall flow chart of an embodiment of the present invention. DETAILED DESCRIPTION

[0030] The technical solution of the present invention will be described clearly and completely below in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0031] In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc., indicating the orientation or positional relationship, are based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first", "second", and "third" are used for descriptive purposes only, and cannot be understood as indicating or implying relative importance.

[0032] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0033] The embodiments of the present invention are further described below in conjunction with the accompanying drawings:

[0034] like Figure 1 As shown, a safety assessment method for offshore wind power hydrogen production includes the following steps:

[0035] S1: Collect and organize wind power volatility index data. Preferably, the data also includes the input current of the hydrogen production electrolyzer, the oxygen concentration in hydrogen, and the hydrogen concentration in oxygen. Among them, wind power volatility indicators include wind speed and wind direction, etc. These indicators determine the current size of wind power generation, and also determine whether volatility will occur and thus affect the input current size of the electrolyzer. According to this indicator, a safety evaluation can also be performed directly. According to the size of the wind speed and the safety operation indicators of the system, different scales of water electrolysis for hydrogen production are carried out. This is to adjust the scale of hydrogen production according to the input. When the wind speed is too high, in order to ensure the safety of the system, water electrolysis for hydrogen production is not carried out under this working condition.

[0036] The size of the generated current directly determines the input current of the hydrogen production electrolyzer, which in turn determines the amount of hydrogen produced. The input current of the electrolyzer, the oxygen concentration in hydrogen, and the hydrogen concentration in oxygen are three important indicators for system safety evaluation, which are used to evaluate the safety of the system.

[0037] S2: Use the selected data as safety evaluation indicators to conduct safety evaluation of the entire system. Specifically, use advanced algorithms for analysis and evaluation, use different weight coefficients to conduct risk evaluation and judgment on the input current of the electrolyzer, oxygen concentration in hydrogen, hydrogen concentration in oxygen, and wind power volatility indicators, and dynamically adjust the weight coefficients according to the risk level unit results to conduct system re-evaluation.

[0038] Specifically, the input current I1 of the electrolyzer, the oxygen concentration in hydrogen V1, the hydrogen concentration in oxygen V2 and the wind volatility index P4 are first normalized and then multiplied by different weight coefficients (w1, w2, w3, w4, ∑wi=1) for risk assessment and judgment. The weight coefficients are dynamically adjusted according to the risk level unit results, and the system is re-evaluated.

[0039] L is the probability of an accident, L = (w1*μ1+w2*μ2+w3*μ3+w4*μ4) / ∑wi, w4<0.5; L = 1, w4> = 0.5. Where μ1 = I1 / I0, μ2 = V1 / V O , μ3=V2 / V H , μ4=P4 / P0, where I0, V O 、V H , P0 are the design reference values ​​of input current, oxygen concentration in hydrogen, hydrogen concentration in oxygen and wind fluctuation index respectively.

[0040] S3: Derive the risk level unit. Specifically, the risk level unit calculates the risk level through an embedded algorithm and displays it in the form of a digital dashboard to facilitate judgment by operators.

[0041] Specifically, the risk level is judged by the risk matrix analysis algorithm (LS), R = L*S, where R is the risk value, which is the combination of the possibility of an accident and the consequences of the event, and is divided into five levels: A1, B2, C3, D4, and E5; L is divided into five levels: 1-5; S is the severity of the consequences of the accident, and is divided into levels 1-5; the larger the R value, the greater the danger of the system and the greater the risk.

[0042] When w4>0.5, the level of R is determined to be E5, the highest level.

[0043] When R is A1 and B2, no re-evaluation is required. When R is C3, D4, and E5, a system re-evaluation is required.

[0044] S4: After determining the risk level, conduct a safety re-evaluation of the system based on on-site data and evaluation results.

[0045] Specifically, the above risk judgment is explained with an example. For example, if w4=0.6>0.5, L=1, which means the risk is very high and it is not suitable for hydrogen production. Because the wind force at sea is very strong and the wind turbine is very unstable, hydrogen production is very likely to cause electrolyzer failure, so it is not suitable for hydrogen production at this time. Figure 1 As shown, it is necessary to return to continue to judge the value of w4 until w4<0.5, and then judge the risk level.

[0046] The advantages and positive effects of the present invention are:

[0047] The present invention not only considers the relevant safety indicators of the hydrogen production side, but also integrates the wind power volatility indicators, and can derive a comprehensive risk level unit according to the operation conditions, and then conduct a safety evaluation. The evaluation method of the present invention uses advanced algorithms for calculation and judgment, and the evaluation results are more accurate, which plays a great role in the safe operation of the system.

[0048] The above is a detailed description of an embodiment of the present invention, but the content is only a preferred embodiment of the present invention and cannot be considered to limit the scope of implementation of the present invention. All equivalent changes and improvements made within the scope of the present invention should still fall within the scope of the patent coverage of the present invention.

Claims

1. A safety assessment method for offshore wind power hydrogen production, Features: The following steps are included: S1: Collect and organize wind power fluctuation index data; S2: Use the selected data as safety evaluation indicators to conduct safety evaluation on the entire system; S3: derive the risk level unit; S4: Conduct safety reassessment based on on-site data and assessment results.

2. A safety assessment method for offshore wind power hydrogen production according to claim 1, Features: In S1, the wind fluctuation index includes wind speed and wind direction, and the data also includes input current of the hydrogen production electrolyzer, oxygen concentration in hydrogen, and hydrogen concentration in oxygen.

3. A safety assessment method for offshore wind power hydrogen production according to claim 1 or 2, Features: The S2 comprises the following steps, S21: normalize the input current of the electrolyzer, oxygen concentration in hydrogen, hydrogen concentration in oxygen and wind power fluctuation index and multiply them by different weight coefficients to conduct risk assessment and judgment; S22: Dynamically adjust the weight coefficient according to the risk level unit results and conduct system re-evaluation.

4. A safety assessment method for offshore wind power hydrogen production according to claim 3, Features: The calculation formula of S21 is as follows, L=(w1*μ1+w2*μ2+w3*μ3+w4*μ4) / ∑wi,w4<0.5; L=1,w4≥0.5 Where L is the probability of an accident; w1, w2, w3, w4, ∑wi=1 are different weight coefficients; μ1=I 1 / I 0 ,μ2=V 1 / V O , μ3=V 2 / V H , μ4=P 4 / P 0 , where I 0 is the input current reference value, V O is the reference value of oxygen concentration in hydrogen, V H is the reference value of hydrogen concentration in oxygen, P 0 It is the benchmark value of wind fluctuation index.

5. A safety assessment method for offshore wind power hydrogen production according to claim 1 or 2, Features: In S3, the risk level is determined by using a risk matrix analysis algorithm, and the formula is as follows: R=L*S, Among them, R is the risk value, L is the possibility of an accident; and S is the severity of the consequences of the accident.

6. A safety assessment method for offshore wind power hydrogen production according to claim 5, Features: R is the risk value, which is a combination of the probability of an accident and the consequences of the incident, and is divided into five levels: A1, B2, C3, D4, and E5. L is divided into five levels from 1 to 5; S is the severity of the accident consequences, which is divided into 1-5 levels; the larger the R value, the more dangerous the system is and the greater the risk.

7. A safety assessment method for offshore wind power hydrogen production according to claim 6, Features: When w4>0.5, the level of R is determined to be the highest level of E5; When R is at levels A1 and B2, no re-evaluation is required; when R is at levels C3, D4, and E5, a systematic re-evaluation is required.

8. A device, Features: Run the data processing method according to any one of claims 1 to 7.

9. A device comprising a memory, a processor, and an algorithm stored in the memory and executable on the processor, Features: When the processor executes the computer program, the data processing method according to any one of claims 1 to 7 is implemented.

10. A computer-readable storage medium storing a computer algorithm, It is characterized in that When the computer algorithm is executed by a processor, the data processing according to any one of claims 1 to 7 is implemented.