Wiring fixing device and method based on intelligent power distribution engineering construction
By designing a cable fixing device for intelligent power distribution engineering, and utilizing a combination structure of support blocks and clamping rollers, the problem of inconvenient maintenance after cable installation is solved, enabling maintenance without downtime and improving maintenance efficiency and safety.
Patent Information
- Application Number
- CN202411163889.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-23
- Publication Date
- 2024-11-08
- Estimated Expiration
- 2044-08-23
AI Technical Summary
In the construction of intelligent power distribution projects, the installation of cabling makes maintenance inconvenient, especially when the cabling needs to be disassembled for instrument maintenance, which leads to downtime for maintenance.
A cable fixing device was designed, including components such as a hanger, a slide bar, a vertical frame, a support block, and a clamping roller. The cable is automatically retracted to the maintenance area by the gravity of the support block. The clamping roller extends the cable when maintenance is required and automatically retracts after maintenance is completed.
It enables instrument maintenance without stopping the machine, ensuring that the wiring is not broken, thus improving the convenience and safety of maintenance.
Smart Images

Figure CN118693621B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of cable fixing for power distribution engineering, and in particular to a cable fixing device and method based on intelligent power distribution engineering construction. Background Art
[0002] In the construction of intelligent power distribution projects, cable fixtures play a vital role. They not only ensure the neat arrangement of wires, but also ensure the safety of construction and the convenience of subsequent maintenance.
[0003] Prior art publication number CN209233372U discloses a cable arrangement device for a computer room of a cloud computing data center, through which multiple cables can be arranged at one time, which greatly improves the efficiency compared to the manual arrangement of one cable at a time, and can also control the cable arrangement quality and always maintain it at a high level, and finally can provide great convenience for maintenance personnel when inspecting the lines in the computer room, and has strong practicality;
[0004] In the prior art, when it is necessary to install the cable in the distribution box, in order to ensure that the cable is not squeezed, the length of the cable is strictly controlled. The problem with this operation method is that when it is necessary to repair electrical equipment such as instruments in the distribution box, the middle part of the cable is not easy to operate due to the limited length of the cable, and the cable needs to be disassembled. When it is necessary to repair the instrument, the cable must be separated from the instrument due to its short length, so the entire distribution project needs to be shut down for maintenance. Summary of the invention
[0005] The purpose of this section is to summarize some aspects of embodiments of the present invention and briefly introduce some preferred embodiments. Some simplifications or omissions may be made in this section and the specification abstract and the invention title of this application to avoid blurring the purpose of this section, the specification abstract and the invention title, and such simplifications or omissions cannot be used to limit the scope of the present invention.
[0006] The present invention provides a wiring fixing device and method based on intelligent power distribution engineering construction, which can solve the problem that the wiring is not easy to repair after the wiring is installed in the prior art power distribution engineering construction. The specific scheme is as follows:
[0007] On the one hand, the present invention provides a cable fixing device based on intelligent power distribution engineering construction, including a body component, the body component is used to fix the cable to the distribution box, and the body component includes:
[0008] A bracket, detachably mounted in the distribution box;
[0009] A sliding rod, fixedly connected to both ends of the hanging bracket;
[0010] A first vertical frame, both ends of which are slidably connected to the sliding rod;
[0011] A first support block, both ends of which are slidably connected to the side walls of the first vertical frame, and a first spring is connected between the two ends of the first support block and the top of the first vertical frame;
[0012] A second vertical frame, both ends of which are slidably connected to the slide rod;
[0013] A second support block, both ends of which are slidably connected to the side walls of the first vertical frame;
[0014] Wherein, the cable is sequentially arranged on the upper part of the first support block and the lower part of the second support block, and then extends to the lower part of the distribution box;
[0015] There are two clamping rollers, both ends of which are rotatably connected to the side wall of the distribution box through a torsion spring, and the two clamping rollers have a convex portion. When the convex portions on the two clamping rollers are close to each other, the cable can be clamped, and the direction of the convex portion is close to the instrument;
[0016] In the above scheme, by setting the first support block and the second support block, and winding the cable around the first support block and the second support block in sequence, in the default state, the cable can automatically retreat to the maintenance area by the gravity of the second support block, and by setting the clamping roller, when the instrument needs to be repaired, the cable can be extended outward by directly pulling the instrument outward. When the instrument maintenance is completed, the cable automatically retreats under the gravity of the second support block.
[0017] Preferably, the body assembly further comprises:
[0018] A third vertical frame, both ends of which are slidably connected to the sliding rod;
[0019] A third support block, both ends of which are fixedly mounted to the side walls of the third vertical frame by bolts;
[0020] Wherein, after passing through the lower part of the second support block, the cable continues to pass through the upper part of the third support block, and finally extends to the lower part of the distribution box through the outer side of the third support block;
[0021] In the above solution, by providing a third vertical frame and a third support block located on the third vertical frame, the cable can be further guided so that the tail end of the cable can extend to the lower part of the distribution box;
[0022] It should be noted that the gap formed by adjacent ends of the first supporting block, the second supporting block and the third supporting block is greater than or equal to the thickness of the cable.
[0023] Preferably, a cavity is provided at the lower portion of the distribution box, a controller is fixedly installed inside the cavity, a wire head is installed at the signal connection of the controller, the wire head is connected to the wiring, a partition is provided between the instrument and the main body component, the partition divides the distribution box into a working area and a maintenance area, the instrument is located in the working area, and the main body component is located in the maintenance area.
[0024] Preferably, a hook is connected to one end of the hanger close to the partition, and a hanging groove matching the hook is opened on the partition. The hanger is hung on the partition by the hook and fixed by bolts. The hanging groove can limit the hook on the partition, thereby stably fixing the hanger.
[0025] Preferably, a rotating joint and an extension rod are provided at one end of the slide rod, the extension rod is movably connected to the slide rod through the rotating joint, both ends of the rotating joint are respectively hinged to one end of the slide rod and the extension rod, a first limiting groove is provided at one end of the slide rod, a first limiting block is connected to an end of the rotating joint close to the slide rod, a second limiting block is connected to an end of the extension rod close to the rotating joint, and a second limiting groove is provided at an end of the rotating joint close to the extension rod;
[0026] In the above scheme, by arranging a rotating joint and an extension rod at one end of the sliding rod, when the third vertical frame and the second vertical frame need to move outward, the extension rod and the rotating joint can be rotated to a state horizontal with the sliding rod, thereby facilitating the support of both ends of the third vertical frame and the second vertical frame, thereby facilitating the inspection and maintenance of the inner parts of the third vertical frame and the second vertical frame.
[0027] Preferably, an inspection door is installed at one end of the distribution box, and the inspection door is movably installed with the distribution box. When the inspection door is opened, the first vertical frame, the second vertical frame and the third vertical frame on the main body assembly can slide along the sliding rod to the outside of the distribution box, so that an inspection space is formed on the side adjacent to the first vertical frame, the second vertical frame and the third vertical frame.
[0028] Preferably, the body assembly further comprises:
[0029] Upper guide rollers and lower guide rollers are arranged vertically;
[0030] The fixed block has rotation grooves at both ends, the rotation groove at the upper part of the fixed block is a long groove structure, so that the upper guide roller can slide up and down while rotating, and the rotation groove at the lower part of the fixed block is circular, so that the lower guide roller rotates;
[0031] Wherein, the upper guide roller and the lower guide roller are squeezed against each other under the action of gravity to clamp the cable arrangement;
[0032] In the above scheme, when the cable is pulled out, the upper guide roller is always pressed on the lower guide roller under the action of the gravity of the upper guide roller, thereby further pressing the cable to prevent the cable from retreating.
[0033] Preferably, a gear is fixedly connected to the same end of the two clamping rollers, and the two gears are meshed with each other. A rack is arranged above the upper gear, and one end of the rack is connected to a driving rod, and the rack is meshed with the upper gear. When the driving rod drives the rack to move in the direction of the clamping roller, the two gears can be driven to rotate synchronously, so that the raised parts of the two clamping rollers move away from each other, and the cable is retracted to the rear of the distribution box under the gravity of the second support block.
[0034] Preferably, the other end of the rack is connected to a squeezing rod, and when the driving rod drives the rack to move toward the clamping roller, the squeezing rod can be inserted under the rotating shaft at the end of the upper guide roller to push the upper guide roller upward, so that a gap is formed between the surface of the upper guide roller and the cable arrangement;
[0035] In the above scheme, when the instrument maintenance is completed, the driving rod is pressed to move the rack and the extrusion rod toward the rear of the rear distribution box, and the rack drives the gear to rotate, so that the two gears rotate, so that the protruding parts of the two clamping rollers leave the cable, and at the same time the extrusion rod is inserted into the lower part of the upper guide roller shaft to push the upper guide roller upward, so that a gap is formed between the surface of the upper guide roller and the cable, so that the cable is pulled to the rear of the distribution box under the gravity of the second support block.
[0036] On the other hand, the present invention provides a cable fixing method based on intelligent power distribution engineering construction, comprising the following steps:
[0037] S1. Prepare a hanger, a first vertical frame and a second vertical frame using metal or plastic parts, and prepare a first support block and a second support block, wherein the first support block and the second support block are slidably connected to the first vertical frame and the second vertical frame respectively;
[0038] S2, installing the hanging rack, the first vertical rack, the second vertical rack and other components mentioned in S1 at the positions where they need to be installed, so that they can be fixed to the positions to be installed, and the first vertical rack and the second vertical rack are in a vertical state;
[0039] S3, leading the cable out from the position to be installed, and passing through the lower part of the second support block and the upper part of the first support block in sequence;
[0040] After the cable is led out from the first support block in S4 and S3, the cable is inserted between the two clamping rollers, and the raised parts of the two clamping rollers are directed toward the outer end of the distribution box;
[0041] S5. Connect the cable end led out from S4 to the interface of the instrument to complete the installation.
[0042] Compared with the prior art, the present invention can achieve at least one of the following beneficial effects:
[0043] 1. By setting a first support block and a second support block, and winding the cable around the first support block and the second support block in sequence, in the default state, the cable can automatically retreat to the maintenance area by the gravity of the second support block. By setting a clamping roller, when the instrument needs to be repaired, the cable can be extended outward by directly pulling the instrument outward, thereby achieving the purpose of non-stop maintenance. When the instrument maintenance is completed, the cable automatically retreats under the gravity of the second support block. Since the cable can be adaptively extended, it can also be ensured that the cable is not broken.
[0044] 2. By arranging a rotating joint and an extension rod at one end of the sliding rod, when the third vertical frame and the second vertical frame need to move outward, the extension rod and the rotating joint can be rotated to a state horizontal with the sliding rod, thereby facilitating the support of both ends of the third vertical frame and the second vertical frame, thereby facilitating the inspection and maintenance of the inner parts of the third vertical frame and the second vertical frame.
[0045] 3. By setting the upper guide roller and the lower guide roller, when the cable is pulled out, under the action of the gravity of the upper guide roller, the upper guide roller is always pressed on the lower guide roller, thereby further pressing the cable to prevent the cable from retreating.
[0046] 4. By setting the driving rod, rack and extrusion rod, when the instrument maintenance is completed, by pressing the driving rod, the rack and extrusion rod are moved toward the rear of the rear distribution box, the rack drives the gear to rotate, and the two gears rotate, so that the raised parts of the two clamping rollers leave the cable, and at the same time the extrusion rod is inserted into the lower part of the upper guide roller shaft to lift the upper guide roller upward, so that a gap is formed between the surface of the upper guide roller and the cable, so that the cable is pulled to the rear of the distribution box under the gravity of the second support block.
[0047] Other features and advantages of the present invention will be described in the following description, and part of them will become obvious from the description, or will be understood by practicing the present invention. The purpose and other advantages of the present invention can be realized and obtained by the structures particularly pointed out in the written description and the accompanying drawings. BRIEF DESCRIPTION OF THE DRAWINGS
[0048] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the following briefly introduces the drawings required for describing the embodiments. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative labor. Among them:
[0049] Figure 1is a three-dimensional diagram of the main body component of the present invention;
[0050] Figure 2 It is a cross-sectional structural diagram of the main body assembly of the present invention when it is installed in a distribution box;
[0051] Figure 3 It is a structural diagram of the other side of the main body component of the present invention;
[0052] Figure 4 is a side view of the body assembly of the present invention;
[0053] Figure 5 It is a side view of the main body assembly of the present invention when it is unfolded;
[0054] Figure 6 It is a structural diagram of the first supporting block, the second supporting block and the third supporting block of the present invention;
[0055] Figure 7 It is a structural change diagram of the extension rod of the present invention;
[0056] Figure 8 A side view of the clamping roller and the cable arrangement of the present invention;
[0057] Fig. 9 Another side cross-sectional view of the main body assembly and the distribution box of the present invention;
[0058] Fig.10 For the present invention Fig. 9 Enlarged view of point A in the middle;
[0059] Fig.11 It is a structural diagram of the upper guide roller, the lower guide roller, the clamping roller and the rack of the present invention;
[0060] Fig.12 is a three-dimensional diagram of the driving rod of the present invention;
[0061] Fig.13 It is a diagram showing the body assembly and the extension rod of the present invention in a retracted state;
[0062] Fig.14 is a schematic diagram of the expansion of the extension rod of the present invention;
[0063] Fig.15 This is a diagram of the main body component and the extension rod of the present invention in an expanded state.
[0064] The reference numerals are as follows:
[0065] 1. Body assembly; 101. Hanging bracket; 1011. Sliding rod; 1012. Rotating joint; 1013. Extension rod; 1014. First limiting groove; 1015. First limiting block; 1016. Second limiting groove; 1017. Second limiting block; 102. Hanging buckle; 103. First vertical frame; 104. Second vertical frame; 105. Third vertical frame; 106. First support block; 107. Second Support block; 108, third support block; 109, first spring; 110, upper guide roller; 111, lower guide roller; 112, fixed block; 113, rotating groove; 114, driving rod; 115, rack; 116, clamping roller; 117, gear; 118, extrusion rod; 2, instrument; 3, distribution box; 301, cavity; 302, controller; 303, wire end; 304, inspection door; 4, wiring. DETAILED DESCRIPTION
[0066] Preferred embodiments of the present invention will be described in detail below in conjunction with the accompanying drawings, wherein the accompanying drawings constitute a part of the present invention and are used to explain the principles of the present invention together with the embodiments of the present invention.
[0067] Example 1: See Figure 1-Figure 15 This embodiment provides a cable fixing device based on intelligent power distribution engineering construction, including a main body component 1, the main body component 1 is used to fix the cable 4 to the distribution box 3, and the main body component 1 includes:
[0068] The bracket 101 is detachably mounted in the distribution box 3;
[0069] Sliding rods 1011 are fixedly connected to both ends of the rack 101;
[0070] The first vertical frame 103 has two ends slidably connected to the sliding rod 1011;
[0071] A first support block 106, both ends of which are slidably connected to the side walls of the first vertical frame 103, and a first spring 109 is connected between both ends of the first support block 106 and the top of the first vertical frame 103;
[0072] The second vertical frame 104 has two ends slidably connected to the sliding rod 1011;
[0073] The second support block 107 has two ends slidably connected to the side walls of the first vertical frame 103;
[0074] The cable 4 is sequentially arranged on the upper part of the first support block 106 and the lower part of the second support block 107, and then extends to the lower part of the distribution box 3;
[0075] There are two clamping rollers 116, both ends of which are rotatably connected to the side wall of the distribution box 3 through a torsion spring. The two clamping rollers 116 have a convex portion. When the convex portions on the two clamping rollers 116 are close to each other, the cable 4 can be clamped, and the direction of the convex portion is close to the meter 2;
[0076] In the above scheme, by setting the first support block 106 and the second support block 107, and winding the cable 4 around the first support block 106 and the second support block 107 in sequence, in the default state, by the gravity of the second support block 107, the cable 4 can automatically retreat to the maintenance area, and by setting the clamping roller 116, when the instrument 2 needs to be repaired, the cable 4 can be extended outward by directly pulling the instrument 2 outward. When the maintenance of the instrument 2 is completed, the cable 4 automatically retreats under the gravity of the second support block 107.
[0077] like Figure 3 , Figure 4 As shown, the body component 1 also includes:
[0078] The third vertical frame 105 has two ends slidably connected to the sliding rod 1011;
[0079] The third support block 108, both ends of which are fixed to the side walls of the third vertical frame 105 by bolts;
[0080] After passing through the lower part of the second support block 107, the cable 4 continues to pass through the upper part of the third support block 108, and finally extends to the lower part of the distribution box 3 through the outer side of the third support block 108;
[0081] In the above solution, by providing the third vertical frame 105 and the third support block 108 located on the third vertical frame 105, the cable 4 can be further guided so that the tail end of the cable 4 can extend to the lower part of the distribution box 3;
[0082] It should be noted that the gap formed between adjacent ends of the first support block 106 , the second support block 107 and the third support block 108 is greater than or equal to the thickness of the flat cable 4 .
[0083] like Figure 2 As shown, a cavity 301 is provided at the lower part of the distribution box 3, a controller 302 is fixedly installed inside the cavity 301, a wire head 303 is installed at the signal connection of the controller 302, the wire head 303 is connected to the cable 4, and a partition 305 is provided between the meter 2 and the main body component 1, the partition 305 divides the distribution box 3 into a working area and a maintenance area, the meter 2 is located in the working area, and the main body component 1 is located in the maintenance area.
[0084] like Figure 1As shown, the end of the hanger 101 close to the partition 305 is connected to the hook 102, and the partition 305 is provided with a hanging groove matching the hook 102 (not shown in the figure, the specific position is opened at Figure 2 The bracket 101 is connected to the partition 305 by the hook 102 and is fixed by bolts (not shown in the figure). The hanging groove can limit the hook 102 on the partition 305, so that the bracket 101 can be stably fixed.
[0085] like Figure 7 As shown, a rotating joint 1012 and an extension rod 1013 are provided at one end of the sliding rod 1011, and the extension rod 1013 is movably connected to the sliding rod 1011 through the rotating joint 1012. Both ends of the rotating joint 1012 are respectively hinged to the sliding rod 1011 and one end of the extension rod 1013. A first limiting groove 1014 is provided at one end of the sliding rod 1011, and a first limiting block 1015 is connected to the end of the rotating joint 1012 close to the sliding rod 1011, and a second limiting block 1017 is connected to the end of the extension rod 1013 close to the rotating joint 1012, and a second limiting groove 1016 is provided at the end of the rotating joint 1012 close to the extension rod 1013;
[0086] In the above scheme, by setting a rotating joint 1012 and an extension rod 1013 at one end of the sliding rod 1011, when the third vertical frame 105 and the second vertical frame 104 need to move outward, the extension rod 1013 and the rotating joint 1012 can be rotated to a state horizontal with the sliding rod 1011, thereby facilitating the support of both ends of the third vertical frame 105 and the second vertical frame 104, thereby facilitating the inspection and maintenance of the inner parts of the third vertical frame 105 and the second vertical frame 104.
[0087] like Figure 2 As shown, an inspection door 304 is installed at one end of the distribution box 3, and the inspection door 304 is movably installed with the distribution box 3. When the inspection door 304 is opened, the first vertical frame 103, the second vertical frame 104 and the third vertical frame 105 on the main body assembly 1 can slide along the sliding rod 1011 to the outside of the distribution box 3, so that an inspection space is formed on the side adjacent to the first vertical frame 103, the second vertical frame 104 and the third vertical frame 105.
[0088] like Fig.11 As shown, the body component 1 also includes:
[0089] An upper guide roller 110 and a lower guide roller 111 are arranged vertically;
[0090] The fixed block 112 has a rotation groove 113 at both ends. The rotation groove 113 at the upper part of the fixed block 112 is a long groove structure, so that the upper guide roller 110 can slide up and down while rotating. The rotation groove 113 at the lower part of the fixed block 112 is circular, so that the lower guide roller 111 rotates.
[0091] The upper guide roller 110 and the lower guide roller 111 are squeezed against each other under the action of gravity to clamp the cable 4;
[0092] In the above solution, when the cable 4 is pulled out, under the action of the gravity of the upper guide roller 110, the upper guide roller 110 is always pressed on the lower guide roller 111, thereby further pressing the cable 4 to prevent the cable 4 from retreating.
[0093] like Figure 8 , Fig. 9 , Fig.10 As shown, a gear 117 is fixedly connected to the same end of the two clamping rollers 116, and the two gears 117 are meshed with each other. A rack 115 is arranged above the upper gear 117, and one end of the rack 115 is connected to a driving rod 114, and the rack 115 is meshed with the upper gear 117. When the driving rod 114 drives the rack 115 to move toward the clamping roller 116, it can drive the two gears 117 to rotate synchronously, so that the raised parts of the two clamping rollers 116 move away from each other, so that the cable 4 is retracted to the rear of the distribution box 3 under the gravity of the second support block 107.
[0094] like Fig.11 As shown, the other end of the rack 115 is connected to a squeezing rod 118. When the driving rod 114 drives the rack 115 to move toward the clamping roller 116, the squeezing rod 118 can be inserted under the rotating shaft at the end of the upper guide roller 110 to push the upper guide roller 110 upward, so that a gap is formed between the surface of the upper guide roller 110 and the cable 4.
[0095] In the above scheme, when the meter 2 is overhauled, the driving rod 114 is pressed to move the rack 115 and the squeezing rod 118 toward the rear of the distribution box 3, and the rack 115 drives the gear 117 to rotate, so that the two gears 117 rotate, so that the protruding parts of the two clamping rollers 116 leave the cable 4, and at the same time, the squeezing rod 118 is inserted into the lower part of the rotating shaft of the upper guide roller 110, so that the upper guide roller 110 is pushed upward, so that a gap is formed between the surface of the upper guide roller 110 and the cable 4, so that the cable 4 is pulled to the rear of the distribution box 3 under the gravity of the second support block 107;
[0096] like Fig.10 , Fig.12As shown, the driving rod 114 is slidably connected with the partition 305, and an elastic plate 1141 is arranged on the top of the driving rod 114, one end of the elastic plate 1141 is fixed to the top of the driving rod 114, and by pressing the elastic plate 1141, the elastic plate 1141 can rotate around the part connected with the driving rod 114, and a clamping block 1142 is connected to the top of the elastic plate 1141, and the driving rod 114 can be clamped in the fixed position of the partition 305 through the clamping block 1142, so that when the cable 4 retreats, the driving rod 114 can always keep the position until the elastic plate 1141 is manually pressed, and then under the action of the torsion spring, the two clamping rollers 116 automatically rotate until the raised parts of the two clamping rollers 116 hold the cable 4;
[0097] In summary, in this embodiment, by providing the first support block 106, the second support block 107 and the third support block 108, the flat cable 4 can pass through the outer walls of the first support block 106, the second support block 107 and the third support block 108 in sequence in an S-shaped trajectory. Since both ends of the first support block 106, the second support block 107 and the third support block 108 have semicircular parts, the flat cable 4 is wound on the surface thereof, which can prevent the flat cable 4 from being folded and damaged.
[0098] like Fig.13 , Fig.14 , Fig.15 As shown, by pulling the third vertical frame 105, the second vertical frame 104 and the first vertical frame 103 outward (the first support block 106, the second support block 107 and the third support block 108 move synchronously), the cable 4 can be unfolded (as shown in FIG. Fig.15 As shown), it is convenient to overhaul the cable 4 and other components (specific overhauls may include dust removal, check for breakpoints, short circuits, and other problems).
[0099] Embodiment 2: The technical solution of this embodiment is different from that of Embodiment 1 in that this embodiment provides a wiring fixing method based on intelligent power distribution engineering construction, comprising the following steps:
[0100] S1. Prepare a hanger 101, a first vertical frame 103 and a second vertical frame 104 using metal parts or plastic parts, and prepare a first support block 106 and a second support block 107. The first support block 106 and the second support block 107 are slidably connected to the first vertical frame 103 and the second vertical frame 104 respectively;
[0101] S2, installing the rack 101, the first vertical rack 103, the second vertical rack 104 and other components mentioned in S1 at the positions where they need to be installed, so that they can be fixed to the positions to be installed, and the first vertical rack 103 and the second vertical rack 104 are in a vertical state;
[0102] S3, lead the flat cable 4 out from the position to be installed, and pass through the lower part of the second support block 107 and the upper part of the first support block 106 in sequence;
[0103] After the cable 4 is led out from the first support block 106 in S4 and S3, the cable 4 is inserted between the two clamping rollers 116, and the raised parts of the two clamping rollers 116 are directed toward the outer end of the distribution box 3;
[0104] S5. Connect the end of the flat cable 4 led out in S4 to the interface of the instrument 2 to complete the installation.
[0105] In the description of this specification, the description with reference to the terms "one embodiment", "example", "specific example", etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described can be combined in any one or more embodiments or examples in a suitable manner.
[0106] The preferred embodiments of the present invention disclosed above are only used to help illustrate the present invention. The preferred embodiments do not describe all the details in detail, nor do they limit the invention to the specific implementation methods described. Obviously, many modifications and changes can be made according to the content of this specification. This specification selects and specifically describes these embodiments in order to better explain the principles and practical applications of the present invention, so that those skilled in the art can understand and use the present invention well. The present invention is limited only by the claims and their full scope and equivalents.
Claims
1. A cable fixing device based on intelligent power distribution engineering construction, comprising a main body component (1), wherein the main body component (1) is used to fix a cable (4) into a distribution box (3), and is characterized in that: The main body component (1) comprises: A hanging bracket (101) is detachably mounted in the distribution box (3); A sliding rod (1011) fixedly connected to both ends of the hanging bracket (101); A first vertical frame (103), both ends of which are slidably connected to the sliding rod (1011); A first support block (106), both ends of which are slidably connected to the side walls of the first vertical frame (103), and a first spring (109) is connected between the two ends of the first support block (106) and the top of the first vertical frame (103); A second vertical frame (104), both ends of which are slidably connected to the sliding rod (1011); A second supporting block (107), both ends of which are slidably connected to the side walls of the first vertical frame (103); The cable (4) is sequentially arranged on the upper part of the first support block (106) and the lower part of the second support block (107), and then extends to the lower part of the distribution box (3); There are two clamping rollers (116), both ends of the two clamping rollers (116) are rotatably connected to the side wall of the distribution box (3) via a torsion spring, and the two clamping rollers (116) have a convex portion. When the convex portions on the two clamping rollers (116) are close to each other, the cable (4) can be clamped, and the direction of the convex portion is close to the instrument (2); A third vertical frame (105), both ends of which are slidably connected to the sliding rod (1011); A third support block (108), both ends of which are fixedly mounted to the side walls of the third vertical frame (105) by means of bolts; Wherein, after passing through the lower part of the second support block (107), the cable (4) continues to pass through the upper part of the third support block (108), and finally extends to the lower part of the distribution box (3) through the outer side of the third support block (108); An upper guide roller (110) and a lower guide roller (111) which are arranged vertically; The fixed block (112) has a rotation groove (113) at both the upper and lower ends. The rotation groove (113) at the upper part of the fixed block (112) is a long groove structure, so that the upper guide roller (110) can slide up and down while rotating. The rotation groove (113) at the lower part of the fixed block (112) is circular, so that the lower guide roller (111) can rotate. Wherein, the upper guide roller (110) and the lower guide roller (111) are pressed against each other under the action of gravity, thereby clamping the cable arrangement (4); The same end of the two clamping rollers (116) is fixedly connected to a gear (117), the two gears (117) are meshed with each other, a rack (115) is arranged above the upper gear (117), one end of the rack (115) is connected to a driving rod (114), the rack (115) is meshed with the upper gear (117), when the driving rod (114) drives the rack (115) to move in the direction of the clamping roller (116), it can drive the two gears (117) to rotate synchronously, so that the raised parts of the two clamping rollers (116) move away from each other, so that the cable (4) is retracted to the rear of the distribution box (3) under the drive of the gravity of the second support block (107); The other end of the rack (115) is connected to a squeezing rod (118). When the driving rod (114) drives the rack (115) to move in the direction of the clamping roller (116), the squeezing rod (118) can be inserted under the rotating shaft at the end of the upper guide roller (110) to push the upper guide roller (110) upward, so that a gap is formed between the surface of the upper guide roller (110) and the cable arrangement (4).
2. The cable fixing device based on intelligent power distribution engineering construction according to claim 1, characterized in that: A cavity (301) is provided at the lower part of the distribution box (3), a controller (302) is fixedly installed inside the cavity (301), a wire head (303) is installed at the signal connection of the controller (302), the wire head (303) is connected to the flat cable (4), a partition is provided between the meter (2) and the main body component (1), the partition divides the distribution box (3) into a working area and a maintenance area, the meter (2) is located in the working area, and the main body component (1) is located in the maintenance area.
3. The cable fixing device based on intelligent power distribution engineering construction according to claim 2, characterized in that: One end of the hanger (101) close to the partition is connected to a hanging buckle (102), and the partition is provided with a hanging groove matching the hanging buckle (102). The hanger (101) is hung on the partition via the hanging buckle (102) and is fixed by bolts.
4. The cable fixing device based on intelligent power distribution engineering construction according to claim 1, characterized in that: One end of the sliding rod (1011) is provided with a rotating joint (1012) and an extension rod (1013); the extension rod (1013) is movably connected to the sliding rod (1011) via the rotating joint (1012); two ends of the rotating joint (1012) are respectively hinged to one end of the sliding rod (1011) and the extension rod (1013); one end of the sliding rod (1011) is provided with a first limiting groove (1014); one end of the rotating joint (1012) close to the sliding rod (1011) is connected to a first limiting block (1015); one end of the extension rod (1013) close to the rotating joint (1012) is connected to a second limiting block (1017); and one end of the rotating joint (1012) close to the extension rod (1013) is provided with a second limiting groove (1016).
5. The cable fixing device based on intelligent power distribution engineering construction according to claim 1, characterized in that: An inspection door (304) is installed at one end of the distribution box (3), and the inspection door (304) is movably installed with the distribution box (3). When the inspection door (304) is opened, the first vertical frame (103), the second vertical frame (104), and the third vertical frame (105) on the main body component (1) can slide along the sliding rod (1011) to the outside of the distribution box (3), so that an inspection space is formed on one side adjacent to the first vertical frame (103), the second vertical frame (104), and the third vertical frame (105).
6. A method for fixing a cable arrangement based on intelligent power distribution engineering construction, using the device for fixing a cable arrangement based on intelligent power distribution engineering construction according to any one of claims 1 to 5, characterized in that: The following steps are involved: S1. A hanging rack (101), a first vertical rack (103) and a second vertical rack (104) are prepared using metal parts or plastic parts, and a first support block (106) and a second support block (107) are prepared. The first support block (106) and the second support block (107) are slidably connected to the first vertical rack (103) and the second vertical rack (104), respectively; S2, installing the hanging rack (101), the first vertical rack (103), the second vertical rack (104) and other components mentioned in S1 at positions where they need to be installed, so that they can be fixed to the positions where they are to be installed, and the first vertical rack (103) and the second vertical rack (104) are in a vertical state; S3, leading the flat cable (4) out from the position to be installed, and passing through the lower part of the second support block (107) and the upper part of the first support block (106) in sequence; After the cable (4) is led out from the first support block (106) in S4 and S3, the cable (4) is inserted between two clamping rollers (116), with the raised portions of the two clamping rollers (116) facing the outer end of the distribution box (3); S5. Connect the end of the flat cable (4) led out from S4 to the interface of the instrument (2) to complete the installation.
Citation Information
Cited By
Modularized power distribution cabinet with multi-layer flat cable structure and use method thereof
CN119787106A
A modular power distribution cabinet with a multi-layer wiring structure and its use method
CN119787106B