A square-shaped slope-fixing structure and construction method thereof
By using square-format slope structure and flow adjustment parts in the construction of planting blankets, the problems of unfixed fixation, difficult construction and uneven soil covering are solved, the resistance to wind corrosion and flush resistance is enhanced, and self-rescue is provided for planting blankets. Function, improves slope protection effect and safety.
Patent Information
- Application Number
- CN202411203537.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-30
- Publication Date
- 2024-11-22
- Estimated Expiration
- 2044-08-30
AI Technical Summary
The existing planting blankets are not firmly fixed during construction, difficult to construct, uneven soil covering, insufficient anti-solution ability and lack self-rescue function, resulting in poor slope protection effect and affecting soil and water conservation and life safety.
The square-format solid slope structure is adopted, and the separation piers and flow adjustment parts are set along the slope surface, and the planting blanket is fixed using waste tires and concrete bases, and evenly covering and watering is achieved through guide rails and spraying components, providing a climbing structure to enhance resistance. Wind erosion, anti-smoking and self-rescue functions.
The fixing effect and wind corrosion resistance of the planted blanket are improved, the construction difficulty is reduced, and the independent adjustment of slope runoff is achieved, ensuring the windproof, thermal insulation and moisture conservation effects of the planted blanket are provided, and the climbing and self-rescue function is provided for unexpected falls into the water.
Smart Images

Figure CN118704498B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of slope protection, and in particular to a grid slope consolidation structure and a construction method thereof. Background Art
[0002] Vegetation blanket, also known as ecological blanket, environmental protection blanket, plant fiber blanket, anti-scouring blanket, is a natural high-strength slope protection greening material. It is laid on the slope to make it green and beautiful. It is a kind of anti-scouring slope protection greening material made of grass seeds, reinforced nets, natural plant fibers, geotextiles, etc. through advanced equipment. It is an ideal slope protection greening material for river ecological management, reservoir dam protection, etc., and is currently being used more and more in the field of water conservancy projects.
[0003] Reference Figure 1 The construction process of vegetation blanket includes slope cleaning - laying and anchoring of vegetation blanket - covering with soil - watering and maintenance. The current construction process still has the following technical problems: ① When fixing the vegetation blanket, anchor nails are mostly used for fixing. For some slopes with loose soil, the fixing effect is limited and it is easy to have the problem of loose fixation; ② When laying and anchoring the vegetation blanket on the inclined slope, the construction workers usually use the top of the slope to carry out the operation, which has the common problems of inconvenience, time-consuming and labor-intensive construction; ③ After the vegetation blanket is laid, it needs to be covered with soil to improve the windproof, heat preservation and moisture retention effects. However, the current construction method is to lay and cover the soil in a large area (large area), which is difficult to ensure uniform covering of soil and is prone to uneven thickness, which is not conducive to the subsequent germination and growth of grass seeds, and also has a certain impact on the overall slope protection effect. ④When the current vegetation blanket slope protection is in use, the amount of rainfall during rain varies, and the slope runoff formed is also different. Excessive runoff will cause a large scouring force on the slope, causing soil and water loss; if a corresponding blocking structure is set up, the impact of water flow can be slowed down and soil and water loss can be reduced, but it will also cause the runoff speed of slope water to decrease and the drainage to slow down. Slow drainage can also easily cause excessive immersion of the slope, which can easily lead to negative problems such as water accumulation and disintegration, landslides, etc.; therefore, how to coordinate and balance and achieve the autonomous regulation of slope runoff is of great significance to ensure the slope protection effect of the vegetation blanket. ⑤Slope protection not only affects the anti-scouring performance of the slope, but also affects people's life safety. Most of the current slope protection does not have a climbing structure, does not have the function of climbing and self-rescue when falling into the water, and cannot provide life safety protection for those who accidentally fall into the water.
[0004] It can be seen that the vegetation blanket slope protection system still has some technical problems to a greater or lesser extent. In view of the above pain points, how to reasonably improve it to enhance the ability to regulate slope runoff, enhance the slope's resistance to wind erosion and scour, reduce construction difficulty, and provide self-rescue functions for falling into water and climbing, etc., requires in-depth research. Summary of the invention
[0005] The present invention aims to solve one of the technical problems in the related art at least to a certain extent. To this end, the present invention proposes a grid slope consolidation structure and a construction method thereof.
[0006] The technical solution of the present invention to solve the technical problem is:
[0007] In the first aspect, the technical solution proposes a grid-type slope-fixing structure, comprising:
[0008] A plurality of rows of partition piers are arranged transversely along the slope surface, and the partition piers divide the slope surface into a plurality of transversely arranged transverse laying units; the partition piers include a plurality of waste tires arranged at intervals, and concrete is poured inside the waste tires to form a concrete base; a sleeve with an internal thread is pre-buried on the top of the waste tire, and the sleeve is fixedly connected to the concrete base; the concrete base is connected to a tension screw, and both ends of the tension screw extend outside the concrete base;
[0009] A vegetation blanket is laid in the transverse laying unit; a vertical first threaded rod is threadedly connected to the tension screw, and an edge strip is arranged between the first threaded rod and the vegetation blanket, and the edge strip is pressed on the edge of the vegetation blanket to press and fix the edge of the vegetation blanket on the slope; each transverse laying unit is also provided with a plurality of U-shaped plates, and a plurality of second threaded rods are threadedly connected to the U-shaped plates along the length direction to press and fix the blanket surface of the vegetation blanket; the two ends of the U-shaped plates are detachably connected to the ends of the corresponding tension screws; a square fixing area is constructed between adjacent U-shaped plates.
[0010] Preferably, a flow regulating member is further provided in the area between adjacent waste tires, and the flow regulating member includes a rotating shaft connected to the slope, and two groups of baffles are rotatably connected to the rotating shaft, and compression springs are connected between the baffles, and a "V"-shaped structure is formed between the baffles; in the initial state, under the elastic force of the compression spring, the baffles are in contact with the edges of the waste tires, and small flow holes are formed between the baffles and the waste tires; when the slope runoff reaches the design value, the water flow will flush the baffles, the compression springs are compressed, the two groups of baffles are close to each other, the baffles are no longer in contact with the edges of the waste tires, and a large flow channel is formed.
[0011] Preferably, through holes are opened at both ends of the U-shaped plate, one end of the tension screw passes through the through hole, and the tension screw is threadedly connected with two sets of nuts to clamp and fix the ends of the U-shaped plate.
[0012] Preferably, it also includes a guide rail arranged along the slope direction as a climbing structure for climbing from the bottom of the slope to the top of the slope; the guide rail is arranged on the top of the waste tire, and a fastening bolt is provided on the guide rail, and the bottom end of the fastening bolt is threadedly connected to the sleeve.
[0013] Preferably, a slide groove is provided on the guide rail, and a vertical vertical zone unit is formed between two adjacent guide rails; a moving member is provided between adjacent guide rails; and the moving member can slide up and down along the guide rail.
[0014] Preferably, the movable part is a scraping assembly, which is used to achieve uniform soil covering on the surface of the vegetation blanket; the scraping assembly includes a scraper, the top of the scraper is connected to a bracket, the top of the bracket is connected to a crossbeam, both ends of the crossbeam are connected to dovetail sliders, the slide groove is a dovetail groove, and the dovetail slider is detachably slidably connected to the dovetail groove.
[0015] Preferably, the movable part is a spraying assembly, which is used to achieve watering and maintenance of the vegetation blanket; the spraying assembly includes a spraying plate, both ends of which are connected to wheels, and the wheels can slide along the slide groove; the bottom of the spraying plate has a plurality of nozzles, and the spraying plate is provided with a water inlet.
[0016] In a second aspect, the present invention further proposes a construction method of a grid-shaped slope-fixing structure, comprising the following steps:
[0017] S1, repair the slope surface;
[0018] S2, according to the design plan, bury several rows of waste tires arranged horizontally on the slope; the waste tires in each row are arranged at intervals;
[0019] S3, build concrete base:
[0020] Formwork is set up on both sides of each waste tire, and the formworks are connected and fixed by tension screws; a hole is opened on the top of the waste tire as a pouring port; concrete is poured into the waste tire through the pouring port; a sleeve with internal thread is embedded at the pouring port; the demoulding concrete base and the waste tire together form a partition pier; the area between two adjacent rows of partition piers forms a horizontal laying unit;
[0021] S4, after the concrete curing is completed, a concrete base is formed; the formwork is removed, the tension screws are retained, and the tension screws are connected to the solidified concrete;
[0022] S5, cutting the vegetation blanket, and laying the cut vegetation blanket in the horizontal laying unit;
[0023] S6, a vertical threaded hole is pre-opened on the tension screw rod, and the first threaded rod is installed through the threaded hole;
[0024] S7, Vegetation Blanket Edge Fixation:
[0025] Install side strips at the upper and lower edges of the vegetation blanket, press the side strips on the edge of the vegetation blanket, screw the first threaded rod, press the side strips downward, and achieve pressing and fixing the edge of the vegetation blanket;
[0026] S8, Vegetation blanket surface fixation:
[0027] A plurality of U-shaped plates with second threaded rods are fixedly bolted to corresponding tensioning screw rods; the second threaded rods are tightened, and the bottom ends of the second threaded rods are pressed downward to hold and fix the surface of the vegetation blanket; a grid fixing area is constructed between adjacent U-shaped plates.
[0028] Preferably, the method further includes S9, wherein the surface of the vegetation blanket is evenly covered with soil, and the specific process is as follows:
[0029] S91, installing a guide rail on the top of the waste tire, wherein the guide rail is arranged along the slope direction; a vertical area is formed between two adjacent guide rails;
[0030] S92, the vertical area is used as a soil covering area, and soil is covered on the surface of the vegetation blanket in the soil covering area;
[0031] S93, homogenizing the soil covering: installing a soil scraping assembly between two adjacent guide rails; adjusting the distance between the scraper and the vegetation blanket, and using the distance as the thickness of the soil covering; moving the soil scraping assembly up and down to level the soil in the soil covering area, and ensuring that the thickness of the soil covering at each point is consistent.
[0032] Preferably, the method further includes S10, watering and curing the surface of the vegetation blanket, and the specific process is as follows:
[0033] S101, after the soil is evenly covered, the scraping assembly is removed; then the spraying assembly is installed on the guide rail, the water inlet of the spray plate is connected to the water pump through a hose, the water pump is started, and the spray plate is slid up and down along the guide rail to achieve watering maintenance of the vegetation blanket.
[0034] The above technical solution has the following advantages or beneficial effects:
[0035] 1. The present invention adopts the idea of dividing piers to divide the slope into several horizontal laying units, changing the original large-area construction into small-area independent construction, reducing the construction difficulty; the dividing piers are in the form of waste tires and concrete bases, which are reliable and easy to construct; the tension screws retained after demolding are used as the installation base point, which can facilitate the construction of the edge of the vegetation blanket and the fixation of the blanket surface, thereby quickly constructing a grid fixed area, the vegetation blanket has a good fixation effect, and high wind and scour resistance.
[0036] 2. The present invention is equipped with a vertically arranged guide rail, and the setting of the guide rail has three functions. First, it can be used as a climbing structure. People who accidentally fall into the water can grasp the guide rail to climb, so that the slope protection also has a self-rescue function; second, a vertical area is formed between the vertically arranged guide rails. In the soil covering stage, the guide rails are used in conjunction with the scraper assembly to uniformly treat the soil covering to ensure that the soil covering thickness at each point is consistent, which can effectively improve the windproof, heat-insulating and moisture-retaining functions of the vegetation blanket, and is beneficial to the subsequent germination and growth of grass seeds, thereby obtaining a better greening coverage rate; third, a vertical area is formed between the vertically arranged guide rails. In the maintenance stage, the guide rails are used in conjunction with the spraying assembly, and the spraying assembly is moved up and down to achieve uniform watering, saving time and effort.
[0037] 3. In the present invention, flow regulating parts are installed between waste tires, which can form small flow holes and large flow channels with different flow capacities in cooperation with the waste tires, so as to realize autonomous regulation according to the size of the slope runoff. When the slope runoff is small, water is discharged from the small flow holes, so that the drainage speed is slowed down, so as to facilitate full absorption by plants; when the slope runoff is large, water will break through the baffle, and the water will be discharged from the large flow channel, so as to accelerate the drainage speed, so as to prevent excessive soaking. BRIEF DESCRIPTION OF THE DRAWINGS
[0038] The accompanying drawings are used to provide further understanding of the present invention and constitute a part of the specification. They are used to explain the present invention together with the embodiments of the present invention and do not constitute a limitation of the present invention.
[0039] Figure 1 It is a cross-sectional view of the vegetation blanket after laying in the prior art.
[0040] Figure 2 It is a three-dimensional diagram of the grid-type slope-fixing structure proposed in the first embodiment.
[0041] Figure 3 yes Figure 2 The structural stereogram of the Chinese-style slope-stabilizing structure after omitting the slope.
[0042] Figure 4 It is a schematic diagram of the separate structure of the concrete base and the formwork after pouring.
[0043] Figure 5 yes Figure 2 Main view of the Chinese-style slope-stabilizing structure (anchor bars omitted).
[0044] Figure 6 It is a structural schematic diagram of a single set of U-shaped plates connected to waste tires.
[0045] Figure 7 It is a three-dimensional diagram of the grid-type slope-fixing structure proposed in the second embodiment.
[0046] Figure 8 yes Figure 7 Schematic diagram of the enlarged structure of area A in the middle.
[0047] Fig. 9 It is the main view of the structure of the matching relationship between the waste tire and the flow regulating part.
[0048] Fig.10 It is a top view of the connection structure between the flow regulating member and the waste tire in the initial state.
[0049] Fig.11 It is a top view of the connection structure between the flow regulating member and the waste tire after the compression spring is compressed.
[0050] Fig.12 It is a three-dimensional diagram of the grid-shaped slope-fixing structure proposed in the third embodiment.
[0051] Fig.13 It is a schematic diagram of the split structure of the connection relationship between the guide rail and the waste tire.
[0052] Fig.14 This is a partial enlarged view of the coordination between the spray plate and the guide rail.
[0053] Fig.15 This is an enlarged view of the guide rail segment structure.
[0054] Fig.16 It is a structural diagram of the cooperation relationship between the scraper assembly and the guide rail.
[0055] Description of reference numerals:
[0056] 1. Slope; 2. Slope surface; 3. Waste tire; 301. Tension screw; 302. Sleeve; 303. Concrete base; 304. Formwork; 305. Anchor bar; 4. Vegetation blanket; 401. Anchor nail; 5. Edge strip; 6. U-shaped plate; 601. Second threaded rod; 602. Nut; 7. First threaded rod; 8. Flow regulating member; 801. Baffle; 802. Rotating shaft; 803. Compression spring; 804. Small flow hole; 9. Horizontal laying unit; 10. Winch; 11. Rope; 12. Guide rail; 1201. Fastening bolt; 121. Slide; 13. Spraying plate; 14. Scraper; 141. Bracket; 15. Crossbeam; 16. Dovetail slider. DETAILED DESCRIPTION
[0057] In order to make the purpose, features and advantages of the present invention more obvious and easy to understand, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the embodiments described below are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0058] It should be noted that, in the description of the present invention, terms such as "up", "down", "left", "right", "inside" and "outside" indicating directions or positional relationships are based on the directions or positional relationships shown in the drawings. This is merely for the convenience of description and does not indicate or imply that the device or element must have a specific orientation, be constructed and operated in a specific orientation. Therefore, it should not be understood as a limitation on the present invention.
[0059] In addition, it should be noted that in the description of the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected" and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, or it can be the internal communication of two components. For those skilled in the art, the specific meanings of the above terms in the present invention can be understood according to the specific circumstances.
[0060] Embodiment 1:
[0061] The existing construction process of the vegetation blanket 4 includes slope cleaning - laying and anchoring the vegetation blanket 4 - covering with soil - watering and curing. The vegetation blanket is usually fixed with anchor nails 401. Figure 1 , Figure 1 It is a cross-sectional view of the vegetation blanket after laying in the prior art.
[0062] In view of the defects of the existing technology, reference Figure 2 - Figure 6 This embodiment proposes a grid-type slope consolidation structure for slope 1 treatment, which includes:
[0063] A plurality of rows of partition piers are arranged transversely along the slope 2, and the partition piers divide the slope 2 into a plurality of transversely arranged transverse laying units 9, and the area between two adjacent rows of partition piers is recorded as the transverse laying unit 9; the partition piers include a plurality of waste tires 3 arranged at intervals, and concrete is poured inside the waste tires 3 to form a concrete base 303; in order to improve stability, a plurality of anchor bars 305 can be inserted at the bottom of the waste tires 3, and the top of the anchor bars 305 is connected to the concrete; a sleeve 302 with an internal thread is pre-buried at the top of the waste tire 3, and the sleeve 302 is fixedly connected to the concrete base 303; the concrete base 303 is connected to a tension screw 301, and both ends of the tension screw 301 extend outside the concrete base 303 and are arranged in an outcrop shape.
[0064] The vegetation blanket 4 is laid in the horizontal laying unit 9; the vegetation blanket 4, also known as ecological blanket, environmentally friendly vegetation blanket, plant fiber blanket, anti-scouring vegetation blanket, is a natural high-strength slope protection greening material, which is laid on the slope to be green and beautiful. It is a kind of anti-scouring slope protection greening material made of grass seeds, reinforced nets, natural plant fibers, geotextiles, etc. through advanced equipment. It is an ideal slope protection greening material for river ecological management, reservoir dam protection, etc.
[0065] Features of Vegetation Carpet 4:
[0066] (1) The three-layer structure of the growth substrate, fiber net and ecological cloth is bonded together with non-toxic glue for plants. This makes the product lighter, the grass seeds and fertilizers are evenly bonded, and it is not easy to leak during construction. The construction is more convenient and can be standardized and mass-produced in factories, ensuring the uniformity of product quality and the germination rate of plants. (2) The grass seeds can be selected flexibly to adapt to the different climatic growth conditions in various regions. (3) It contains special soil conditioners and water retaining agents, which improve the plant growth environment and reduce the cost of later maintenance. (4) The construction is simple and saves more than 3 times the construction period compared with traditional bank protection and soil erosion prevention technologies. (5) The project cost is low, which is 1 / 3 to 1 / 2 of the traditional technology, which can effectively reduce the project cost.
[0067] A vertical first threaded rod 7 is threadedly connected to the tension screw 301, and an edge strip plate 5 is arranged between the first threaded rod 7 and the vegetation blanket 4. The edge strip plate 5 is pressed on the edge of the vegetation blanket 4 and is used to press and fix the edge of the vegetation blanket 4 on the slope 2; each horizontal laying unit 9 is also provided with a plurality of U-shaped plates 6, and a plurality of second threaded rods 601 are threadedly connected to the U-shaped plates 6 along the length direction, which are used to press and fix the blanket surface of the vegetation blanket 4; the two ends of the U-shaped plate 6 are detachably connected to the corresponding ends of the tension screw 301. In this embodiment, the detachable connection method can be wire binding fixation, bolting, etc.; a square fixing area is constructed between adjacent U-shaped plates 6.
[0068] In this embodiment, the connection between the U-shaped plate 6 and the tension screw 301 is as follows:
[0069] Through holes are formed at both ends of the U-shaped plate 6 , and one end of the tension screw 301 passes through the through hole. The tension screw 301 is threadedly connected with two sets of nuts 602 to clamp and fix the ends of the U-shaped plate 6 .
[0070] The construction method of the square fixed area is as follows:
[0071] S1, repair the slope 2 of slope 1; before repair, it is necessary to investigate the slope 2, because the location of the slope 2 and the surrounding environmental conditions will affect the effect of the vegetation construction method, so relevant information should be mastered in advance: (1) Topography. Altitude, slope gradient, shape. (2) Surrounding vegetation. Investigate the vegetation around the slope 2. (3) The original condition of the surrounding slope 2. Greening conditions (degradation, vegetation invasion, soil erosion, etc.).
[0072] S2, according to the design plan, several rows of waste tires 3 are buried in the slope 2 in a horizontal arrangement; the waste tires 3 in each row are arranged at intervals.
[0073] S3, constructing a concrete base 303:
[0074] Formworks 304 are respectively set up on both sides of each waste tire 3, and the formworks 304 are connected and fixed by tension screws 301; a hole is opened on the top of the waste tire 3 as a pouring port; concrete is poured into the waste tire 3 through the pouring port; a sleeve 302 with an internal thread is pre-buried at the pouring port; the demoulded concrete base 303 and the waste tire 3 together form a partition pier; the area between two adjacent rows of partition piers forms a horizontal paving unit 9.
[0075] S4, after the concrete curing is completed, the concrete base 303 is formed; the formwork 304 is removed, and the tension screw 301 is retained, and the tension screw 301 is connected to the solidified concrete as a whole.
[0076] S5, cutting the vegetation blanket 4, and laying the cut vegetation blanket 4 in the horizontal laying unit 9; when laying, the vegetation blanket 4 is spread from top to bottom along the slope 2, so that the vegetation blanket 4 is in full contact with the slope 2, and it should not be too tight or too loose. It should be noted that the seeds of the vegetation blanket 4 should be based on the climate and soil characteristics along the line, using tree species and grass species suitable for local growth, simulating the local natural vegetation structure, and using the diversity of plant communities to promote the stability of vegetation.
[0077] S6, a vertical threaded hole is pre-opened on the tension screw rod 301, and the first threaded rod 7 is installed through the threaded hole.
[0078] S7, Vegetation Blanket 4 Edge Fixation:
[0079] The side strips 5 are installed at the upper and lower edges of the vegetation blanket 4, and the side strips 5 are pressed on the edge of the vegetation blanket 4. The first threaded rod 7 is screwed to press the side strips 5 downward to achieve the pressing and fixing of the edge of the vegetation blanket 4.
[0080] S8, Vegetation Blanket 4 surface fixation:
[0081] A plurality of U-shaped plates 6 with second threaded rods 601 are bolted and fixed to corresponding tension screws 301; the specific method is, taking fixing one end of the U-shaped plate 6 as an example, first screwing a nut 602 on the corresponding tension screw 301, through holes are opened at both ends of the U-shaped plate 6, and then the through hole at one end is sleeved on the tension screw 301, and then screwing a nut 602, and using two sets of nuts 602 to achieve clamping and fixing of the U-shaped plate 6.
[0082] The second threaded rod 601 is tightened, and the bottom end of the second threaded rod 601 is pressed downward to hold and fix the surface of the vegetation blanket 4 ; a grid fixing area is constructed between adjacent U-shaped plates 6 .
[0083] It should be noted that, for the tension screw rods 301 that are not needed, the exposed parts can be cut off; of course, they can also be not cut, which can be selected according to the actual situation.
[0084] Ideas:
[0085] The present invention adopts the idea of dividing piers to divide the slope 2 into several horizontal laying units 9, changing the original large-area construction into small-area independent construction, thereby reducing the construction difficulty; the dividing piers are in the form of waste tires 3 and concrete bases 303, which are reliably fixed and simple to construct; the tension screws 301 retained after demolding are used as the installation base point, which can conveniently construct the edge of the vegetation blanket 4 and the fixation of the blanket surface, thereby quickly constructing a grid fixed area, and the vegetation blanket 4 has a good fixing effect and high wind and scour resistance, which can ensure that before the plants reach a stable and lush state, they will not be harmed by soil erosion and can grow for a long time.
[0086] Embodiment 2:
[0087] Reference Figure 7 - Fig.11 As shown, based on the first embodiment, as a further optimization, it also includes the following:
[0088] A flow regulating member 8 is also provided in the area between adjacent waste tires 3. The flow regulating member 8 includes a rotating shaft 802 connected to the slope 2, and two groups of baffles 801 are rotatably connected to the rotating shaft 802. Compression springs 803 are connected between the baffles 801, and a "V"-shaped structure is formed between the baffles 801; in the initial state, under the elastic force of the compression spring 803, the baffle 801 contacts the edge of the waste tire 3, and a small flow hole 804 is formed between the baffle 801 and the waste tire 3; when the runoff of the slope 2 reaches the design value, the water flow will flush the baffle 801, the compression spring 803 is compressed, the two groups of baffles 801 are close to each other, and the baffle 801 is no longer in contact with the edge of the waste tire 3, forming a large flow channel.
[0089] During watering maintenance or light rain, the runoff volume of the slope 2 is small, and the water can quickly flow away from the small flow hole 804; when encountering heavy rain or rainstorm, due to the blocking effect of the dividing pier, water accumulation is likely to occur if the drainage is not timely. When the water volume reaches a certain value, the runoff water of the slope 2 will overcome the pressure of the compression spring 803 and break open the baffle 801, and the baffle 801 will no longer contact the edge of the waste tire 3. At this time, the opening and closing degree between the two sets of baffles 801 becomes smaller, and the distance between the baffle 801 and the waste tire 3 increases, which can accelerate the drainage.
[0090] In this way, the slope 2 can be autonomously adjusted according to the size of the slope 2 runoff. When the slope 2 runoff is small, water is discharged from the small flow hole 804 to slow down the drainage speed, which is conducive to full absorption by plants; when the slope 2 runoff is large, water will break through the baffle 801 and be discharged from the large flow channel to speed up the drainage speed to prevent excessive soaking.
[0091] Embodiment three:
[0092] Reference Fig.13 - Fig.16 On the basis of the first or second embodiment, the invention further comprises a guide rail 12 arranged along the slope 2, the guide rail 12 being arranged on the top of the waste tire 3, the guide rail 12 being provided with a screw hole, the screw hole being penetrated with a fastening bolt 1201, and the bottom end of the fastening bolt 1201 being threadedly connected with the sleeve 302. One aspect of the guide rail 12 is that it can be used as a climbing structure for climbing from the bottom of the slope to the top of the slope, so that when someone accidentally falls into the water, he can climb to save himself, and can provide life safety protection for the person who accidentally falls into the water.
[0093] As an optimized technical solution, considering that the guide rail 12 is only used for climbing and its function is too single, in order to increase the diversity of the functions of the guide rail 12, a slide groove 121 is opened on the guide rail 12, and a vertical vertical zone unit is formed between two adjacent guide rails 12; a moving part is arranged between adjacent guide rails 12; and the moving part can slide up and down along the guide rail 12.
[0094] In this embodiment, the moving part has two structural forms, namely a scraping component and a spraying component.
[0095] When the moving part is a soil scraping assembly, it is used to achieve uniform soil covering on the surface of the vegetation blanket 4; the soil scraping assembly includes a scraper 14, a bracket 141 is connected to the top of the scraper 14, a crossbeam 15 is connected to the top of the bracket 141, dovetail sliders 16 are connected to both ends of the crossbeam 15, the slide 121 is a dovetail groove, and the dovetail slider 16 is detachably connected to the dovetail groove. When soil scraping is required, the soil scraping assembly is connected to the guide rail 12, and the soil scraping assembly is moved up and down to achieve uniform soil covering.
[0096] When the movable part is a spraying assembly, it is used to achieve watering and maintenance of the vegetation blanket 4; the spraying assembly includes a spraying plate 13, and wheels are connected to both ends of the spraying plate 13, and the wheels can slide along the slide groove 121. Here, the shape of the slide groove 121 includes but is not limited to a U-shape or a dovetail groove; a plurality of nozzles are provided at the bottom of the spraying plate 13, and the spraying plate 13 is provided with a water inlet; when watering maintenance is required, the water inlet is connected to the water pump through a hose, the water pump is started, and the spraying plate 13 is moved up and down at the same time, so as to achieve uniform watering.
[0097] In order to facilitate the movement of the spray plate 13 , in this embodiment, a winch 10 is provided at a position close to the top of the slope 2 or directly at the top of the slope. The winch 10 is provided with a rope 11 , one end of which is connected to the spray plate 13 .
[0098] This embodiment proposes a construction method of a grid slope-fixing structure, comprising the following steps:
[0099] On the basis of the above S1 to S8, S9 is also included, where the surface of the vegetation blanket 4 is evenly covered with soil. The specific process is as follows:
[0100] S91, installing a guide rail 12 on the top of the waste tire 3, wherein the guide rail 12 is arranged along the slope 2; a vertical area is formed between two adjacent guide rails 12;
[0101] S92, the vertical area is used as a soil covering area, and soil is covered on the surface of the vegetation blanket 4 in the soil covering area;
[0102] S93, homogenize the soil covering: install a soil scraping assembly between two adjacent guide rails 12; adjust the distance between the scraper 14 and the vegetation blanket 4, and use this distance as the thickness of the soil covering; move the soil scraping assembly up and down to scrape and level the soil in the soil covering area to ensure that the soil covering thickness at each point is consistent.
[0103] And S10, vegetation blanket 4 blanket surface watering maintenance, the specific process is as follows:
[0104] S101, after the uniform soil covering is completed, the scraping assembly is removed; then the spraying assembly is installed on the guide rail 12, the water inlet of the spray plate is connected to the water pump through a hose, the water pump is started, and the spray plate is slid up and down along the guide rail 12 to achieve watering maintenance of the vegetation blanket 4.
[0105] Application results:
[0106] In this embodiment, a vertically arranged guide rail 12 is installed. With the guide rail 12 as the base point, a variety of functions can be formed. The setting of the guide rail 12 has three functions. First, it can be used as a climbing structure. People who accidentally fall into the water can grasp the guide rail 12 to climb, so that the slope protection also has a self-rescue function; second, a vertical area is formed between the vertically arranged guide rails 12. In the soil covering stage, the guide rail 12 is used in conjunction with the scraper assembly to uniformly treat the soil covering to ensure that the soil covering thickness at each point is consistent, which can effectively improve the windproof, heat-insulating and moisture-retaining functions of the vegetation blanket 4, and is beneficial to the subsequent germination and growth of grass seeds, thereby obtaining a better green coverage rate; third, a vertical area is formed between the vertically arranged guide rails 12. In the maintenance stage, the guide rail 12 is used in conjunction with the spraying assembly. The spraying assembly is moved up and down to achieve uniform watering, saving time and effort.
[0107] As the country attaches great importance to the ecological environment, energy conservation and emission reduction, and the recovery of rivers and lakes, the concept of ecological management of the environment and restoration of the natural appearance has promoted the continuous development of ecological management technology. Vegetation blanket 4 provides a good reference solution for slope 2 management due to its technical characteristics, design, and simplicity of construction. Compared with traditional slope protection products, although the erosion resistance of vegetation blanket 4 is low, it can be mass-produced in factories, has low cost, simple construction, and good greening effect. It can be seen that new vegetation products have broad application prospects in the ecological management of slope protection.
[0108] Although the above describes the specific implementation mode of the invention in conjunction with the drawings, it is not intended to limit the scope of protection of the invention. Based on the technical solution of the present invention, various modifications or variations that can be made by those skilled in the art without creative work are still within the scope of protection of the present invention.
Claims
1. A grid-type slope-fixing structure, characterized in that: include: A plurality of rows of partition piers are arranged transversely along the slope surface (2), and the partition piers divide the slope surface (2) into a plurality of transversely arranged transverse laying units (9); the partition piers include a plurality of waste tires (3) arranged at intervals, and concrete is poured inside the waste tires (3) to form a concrete base (303); a sleeve (302) with an internal thread is pre-buried at the top of the waste tire (3), and the sleeve (302) is fixedly connected to the concrete base (303); the concrete base (303) is connected to a tension screw (301), and both ends of the tension screw (301) extend outside the concrete base (303); A vegetation blanket (4) is laid in the transverse laying unit (9); a vertical first threaded rod (7) is threadedly connected to the tension screw (301); an edge strip (5) is provided between the first threaded rod (7) and the vegetation blanket (4); the edge strip (5) is pressed on the edge of the vegetation blanket (4) to press and fix the edge of the vegetation blanket (4) on the slope (2); each transverse laying unit (9) is also provided with a plurality of U-shaped plates (6), and the U-shaped plates (6) are threadedly connected along the length direction. A plurality of second threaded rods (601) are connected to the U-shaped plate (6) for pressing and fixing the surface of the vegetation blanket (4); the two ends of the U-shaped plate (6) are detachably connected to the ends of the corresponding tension screw rods (301); a grid fixing area is formed between adjacent U-shaped plates (6); through holes are provided at both ends of the U-shaped plate (6), one end of the tension screw rod (301) passes through the through hole, and the tension screw rod (301) is threadedly connected to two sets of nuts (602) to clamp and fix the ends of the U-shaped plate (6); A flow regulating member (8) is also provided in the area between adjacent waste tires (3), the flow regulating member (8) comprising a rotating shaft (802) connected to the slope (2), two groups of baffles (801) being rotatably connected to the rotating shaft (802), a compression spring (803) being connected between the baffles (801), and a "V"-shaped structure being formed between the baffles (801); in an initial state, under the elastic force of the compression spring (803), the baffles (801) are in contact with the edge of the waste tire (3), and a small flow hole (804) is formed between the baffles (801) and the waste tire (3); when the runoff of the slope (2) reaches a design value, the water flow will flush the baffles (801), the compression spring (803) will be compressed, the two groups of baffles (801) will be close to each other, the baffles (801) and the edge of the waste tire (3) will no longer be in contact, and a large flow passage will be formed; It also includes a guide rail (12) arranged along the slope surface (2) as a climbing structure for achieving climbing from the bottom of the slope to the top of the slope; the guide rail (12) is arranged on the top of the waste tire (3), and a fastening bolt (1201) is provided on the guide rail (12), and the bottom end of the fastening bolt (1201) is threadedly connected to the sleeve (302).
2. A grid-type slope-fixing structure according to claim 1, characterized in that: The guide rail (12) is provided with a sliding groove (121), and a vertical vertical zone unit is formed between two adjacent guide rails (12); a moving member is provided between adjacent guide rails (12); and the moving member can slide up and down along the guide rail (12).
3. A grid-type slope-fixing structure according to claim 2, characterized in that: The movable part is a soil scraping assembly, which is used to achieve uniform soil covering on the surface of the vegetation blanket (4); the soil scraping assembly comprises a scraper (14), the top of the scraper (14) is connected to a bracket (141), the top of the bracket (141) is connected to a crossbeam (15), both ends of the crossbeam (15) are connected to dovetail sliders (16), the slide groove (121) is a dovetail groove, and the dovetail slider (16) is detachably connected to the dovetail groove in a sliding manner.
4. A grid-type slope-fixing structure according to claim 2, characterized in that: The movable part is a spraying assembly, which is used to realize watering and maintenance of the vegetation blanket (4); the spraying assembly comprises a spraying plate (13), and wheels are connected to both ends of the spraying plate (13), and the wheels can slide along the slide groove (121); the bottom of the spraying plate (13) has a plurality of spray heads, and the spraying plate (13) is provided with a water inlet.
5. A construction method of a grid-type slope-fixing structure, characterized in that: The grid-shaped slope-fixing structure according to any one of claims 2 to 4 comprises the following steps: S1, repairing the slope surface (2) of the slope body (1); S2, according to the design plan, burying a plurality of rows of waste tires (3) arranged horizontally on the slope (2); the waste tires (3) in each row are arranged at intervals; S3, constructing the concrete base (303): Formworks (304) are respectively supported on both sides of each waste tire (3), and the formworks (304) are connected and fixed by tension screws (301); a hole is opened at the top of the waste tire (3) to serve as a pouring port; concrete is poured into the waste tire (3) through the pouring port; a sleeve (302) with an internal thread is embedded at the pouring port; the demoulded concrete base (303) and the waste tire (3) together form a partition pier; the area between two adjacent rows of partition piers forms a transverse laying unit (9); S4, after the concrete curing is completed, a concrete base (303) is formed; the formwork (304) is removed, the tension screw (301) is retained, and the tension screw (301) is connected to the solidified concrete as a whole; S5, cutting the vegetation blanket (4), and laying the cut vegetation blanket (4) in the transverse laying unit (9); S6, a vertical threaded hole is pre-opened on the tension screw rod (301), and a first threaded rod (7) is installed through the threaded hole; S7, Vegetation blanket (4) edge fixing: Installing side strips (5) at the upper and lower edges of the vegetation blanket (4), the side strips (5) are pressed against the edge of the vegetation blanket (4), and the first threaded rod (7) is screwed to press the side strips (5) downward, thereby achieving pressing and fixing the edge of the vegetation blanket (4); S8, Vegetation blanket (4) blanket surface fixation: Bolting and fixing a plurality of U-shaped plates (6) with second threaded rods (601) to corresponding tensioning screw rods (301); tightening the second threaded rods (601), and pressing the bottom ends of the second threaded rods (601) downward to hold and fix the surface of the vegetation blanket (4); and constructing a grid fixing area between adjacent U-shaped plates (6); The process also includes S9, where the surface of the vegetation blanket (4) is evenly covered with soil, and the specific process is as follows: S91, installing a guide rail (12) on the top of the waste tire (3), wherein the guide rail (12) is arranged along the slope (2); a vertical area is formed between two adjacent guide rails (12); S92, the vertical area is used as a soil covering area, and soil is covered on the surface of the vegetation blanket (4) in the soil covering area; S93, performing a uniform treatment on the covering soil: installing a scraping assembly between two adjacent guide rails (12); adjusting the distance between the scraper (14) and the vegetation blanket (4), with the distance being used as the thickness of the covering soil; and moving the scraping assembly up and down to scrape and level the covering soil in the covering area, thereby ensuring that the thickness of the covering soil at each point is consistent.
6. The construction method of a grid slope-fixing structure according to claim 5, characterized in that: The process also includes S10, watering and curing the surface of the vegetation blanket (4), and the specific process is as follows: S101, after the soil is evenly covered, the scraping assembly is removed; then the spraying assembly is installed on the guide rail (12), the water inlet of the spraying plate (13) is connected to the water pump through a hose, the water pump is started, and the spraying plate slides up and down along the guide rail (12) to achieve watering maintenance of the vegetation blanket (4).