Combined forepoling construction method for unfavorable geology shallow buried section of tunnel

By adopting the combined advanced support method in the shallow buried section of the tunnel with poor geology, combined with the combined construction of advanced large pipe sheds, annular guide pits and advanced small pipes/anchors, the problems of shallow burial depth and poor surrounding rock stability in mountain tunnel construction are solved. problem, achieving the effects of safe construction, fast speed and small over-excavation.

CN118704518APending Publication Date: 2024-09-27HUANENG LANCANG RIVER HYDROPOWER CO LTD +2
View PDF 0 Cites 2 Cited by

Patent Information

Application Number
CN202410833169.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-06-26
Publication Date
2024-09-27

AI Technical Summary

Technical Problem

Due to the shallow burial depth and poor physical and mechanical properties of the loose surrounding rock, the excavation and support construction of the entrance and exit of the mountain tunnel can easily cause roof collapse, surface subsidence or slope landslides, endangering the safety of construction personnel and equipment. Existing advanced support The protective method has long construction period, poor applicability or poor grouting effect.

Method used

A combined advanced support construction method is adopted for the shallow buried section of the tunnel with poor geology, including excavation of the open tunnel section, pouring of concrete for the arch, advanced large pipe shed construction, surface grouting, reserved core soil excavation of the annular guide pit, and advanced small conduits. The advanced support combined with advanced anchor rods is cycled until it passes through the shallow buried section of the tunnel with poor geology.

Benefits of technology

It achieves the effects of safe, fast construction and small over-excavation, reduces the impact of the shortcomings of respective support methods, speeds up the construction progress and ensures safety, and reduces the amount of over-excavation in the shallow buried section of the tunnel with poor geology.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118704518A
    Figure CN118704518A
Patent Text Reader

Abstract

The invention discloses a tunnel unfavorable geology shallow buried section combined type advance support construction method. The tunnel unfavorable geology shallow buried section combined type advance support construction method comprises the following steps that a tunnel open cut tunnel section is excavated, cover arch concrete is poured, and advance large pipe shed construction is conducted; after advanced large pipe shed grouting is completed, ground surface grouting construction is carried out after coagulation is carried out for a preset duration; excavating and supporting construction of a shallow-buried section hole body is conducted, and excavation is conducted through an annular pilot tunnel core soil reserving method; a lap joint section with the length of 5 m is arranged at the tail end of the ultra-large pipe shed, and advance support construction of an advance small guide pipe and advance anchor rod combination is conducted from the starting point of the long lap joint section; and the advance support construction step of the combination of the advance small guide pipe and the advance anchor rod is circularly carried out until the tunnel unfavorable geological shallow buried section is penetrated. The combined forepoling construction method for the unfavorable geological shallow-buried section of the tunnel has the advantages that construction is safe and rapid, and the overbreak amount of the unfavorable geological shallow-buried section of the tunnel is small.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of underground tunnel construction, and in particular to a combined advance support construction method for a shallow buried section of a tunnel with poor geological conditions. Background Art

[0002] The excavation and support construction of mountain tunnel entrances and exits is often prone to collapse and roof caving, ground subsidence or slope landslides due to shallow burial depth, poor physical and mechanical properties of loose surrounding rock, and poor stability, endangering the safety of construction personnel and equipment.

[0003] Usually, shallow buried sections of tunnels with poor geological conditions are supported by one of the following types: large pipe sheds, small pipes for advanced grouting, or advanced anchor rods. Among them: the advantage of large pipe sheds is that they are the most stable and reliable, but the disadvantage is that the construction period is long and the applicability is poor in small radius turning sections; the advantage of small pipes for advanced grouting is that the grouting effect is good, but the disadvantage is that the construction disturbance is large and it is difficult to drill holes in damaged areas; the advantage of advanced anchor rods is that the construction is convenient, and self-propelled hollow grouting anchor rods can be used in broken areas where it is difficult to drill holes, but the disadvantage is that the grouting effect is poor. Advantages of advanced support. Summary of the invention

[0004] The present invention aims to solve at least one of the technical problems in the related art to a certain extent. To this end, an embodiment of the present invention proposes a combined advance support construction method for a shallow buried section of a tunnel with poor geological conditions, which has the advantages of safety, high construction speed, and small over-excavation of the shallow buried section of the tunnel with poor geological conditions.

[0005] According to the combined advance support construction method for a shallow buried section of a tunnel with poor geological conditions, the combined advance support construction method for a shallow buried section of a tunnel with poor geological conditions comprises the following steps:

[0006] Dig the open tunnel section, pour the arch concrete and carry out the advanced large pipe shed construction;

[0007] After the advanced large pipe shed grouting is completed, the surface grouting construction will be carried out after the preset setting time;

[0008] Carry out excavation and support construction of the shallow buried tunnel body, and use the ring-shaped pilot pit reserved core soil method for excavation;

[0009] A 5m long overlap section is set at the end of the super-large pipe rack, and the advanced support construction of the advanced small pipe and advanced anchor combination is carried out from the starting point of the long overlap section;

[0010] The advance support construction steps of the advance small guide tube and advance anchor combination are repeated until the shallow buried section with poor geological conditions in the tunnel is passed.

[0011] The combined advance support construction method for the shallow buried section of the tunnel with poor geological conditions according to the embodiment of the present invention has the advantages of safety, fast construction speed, and small over-excavation of the shallow buried section of the tunnel with poor geological conditions. The present application has the following advantages: the combined advance support system can reduce the influence of the shortcomings of each support, speed up the construction progress of the shallow buried section of the tunnel with poor geological conditions and ensure safety, and reduce the over-excavation of the shallow buried section of the tunnel with poor geological conditions.

[0012] In some embodiments, in the advance support construction steps of the combination of an advance small pipe and an advance anchor rod, a first cycle of advance small pipe is applied; after the grouting of the advance small pipe is completed, a preset time of waiting for solidification is allowed to continue the next cycle of excavation and support operations in the annular guide pit; in the third cycle, an advance anchor rod is applied and overlapped with the advance small pipe to form a double-layer advance support structure; after the grouting of the advance anchor rod is completed, a preset time of waiting for solidification is allowed to continue the next cycle of excavation and support operations until the shallow buried section with poor geological conditions of the tunnel is passed.

[0013] In some embodiments, after the excavation of the annular guide pit is completed, the face of the annular guide pit is sealed with shotcrete, which is sprayed twice with an initial spraying thickness of 1 cm. The re-spraying is carried out after the installation of the advance small guide tube or the advance anchor rod is completed and before grouting, with a re-spraying thickness of 3 to 5 cm.

[0014] In some embodiments, the advance small guide tube is installed with a jacking auxiliary device, and the jacking auxiliary device includes a jacking auxiliary sleeve, an inner bracket and an outer bracket. The inner bracket is located on the inner side of the first end of the jacking auxiliary sleeve, and the outer bracket is connected to the outer wall of the first end of the jacking auxiliary sleeve. The second end of the jacking auxiliary sleeve cooperates with a hand drill impactor.

[0015] In some embodiments, after the advancement small catheter is pushed in, a pressure valve is installed at the end of the advancement small catheter.

[0016] In some embodiments, after the sealed concrete of the face is initially set, the grouting pump pressurizes the small advance conduit for grouting. After the grouting reaches the final hole pressure and maintains the pressure for 15 minutes, the pressure valve is closed to end the grouting operation.

[0017] In some embodiments, the advance anchor rods are arranged at an annular spacing of 30 cm within 120° of the vault and an elevation angle of 20° to 30°.

[0018] In some embodiments, the steel pipes of the advanced large pipe shed are arranged within 120° of the arch with a circumferential spacing of 40 cm, and the angle between the axis of the steel pipe and the outer edge of the lining is 1° to 3°.

[0019] In some embodiments, the root canal drilling and grouting step in the surface grouting construction step includes the following steps:

[0020] Infusion 3m 3Cement mortar, control the diffusion radius;

[0021] Infusion 3m 3 Cement paste to ensure consolidation effect;

[0022] After the cement paste is poured, if the grouting pressure and injection flow rate still have no obvious changes, the hole will be left for setting;

[0023] Re-pouring is carried out after waiting for setting for 8 hours, and cement mortar and cement paste are repeatedly poured and waited for setting;

[0024] If the grouting cannot be closed after two re-pourings, the cement mortar pouring will be repeated until the hole is completed.

[0025] In some embodiments, the reserved core soil ring height is controlled at 2.0 to 2.5 m in the shallow buried tunnel excavation and support construction steps, the excavation advance of each cycle is controlled according to the spacing of an I-beam arch frame, and the system support closely follows the excavation face. BRIEF DESCRIPTION OF THE DRAWINGS

[0026] Figure 1 It is a flowchart of the steps of a combined advance support construction method for a shallow buried section of a tunnel with poor geological conditions according to an embodiment of the present invention.

[0027] Figure 2 It is a structural schematic diagram of a pipe jacking auxiliary device for a combined advance support construction method for a shallow buried section of a tunnel with poor geological conditions according to an embodiment of the present invention.

[0028] Figure 3 It is a side view schematic diagram of a pipe jacking auxiliary device of a combined advance support construction method for a shallow buried section of a tunnel with poor geological conditions according to an embodiment of the present invention.

[0029] Figure 4 This is a diagram of the collapse site.

[0030] Figure 5 It is a schematic diagram of the position relationship of the collapsed cavity.

[0031] Figure 6 The invention relates to a small advance guide tube for construction of a combined advance support construction method for a shallow buried section of a tunnel with poor geological conditions according to an embodiment of the present invention.

[0032] Figure 7 The invention relates to a shotcrete-sealed tunnel face according to a combined advance support construction method for a shallow buried section of a tunnel with poor geological conditions in an embodiment of the present invention.

[0033] Figure numerals: 1. auxiliary sleeve for jacking pipe; 2. inner bracket; 3. outer bracket; 4. small advance guide tube; 5. reinforcing plate; 6. hand drill impactor. DETAILED DESCRIPTION

[0034] Embodiments of the present invention are described in detail below, and examples of the embodiments are shown in the accompanying drawings. The embodiments described below with reference to the accompanying drawings are exemplary and intended to be used to explain the present invention, but should not be understood as limiting the present invention.

[0035] According to the combined advance support construction method for a shallow buried section of a tunnel with poor geological conditions, the combined advance support construction method for a shallow buried section of a tunnel with poor geological conditions comprises the following steps:

[0036] Dig the open tunnel section, pour the arch concrete and carry out the advanced large pipe shed construction;

[0037] After the advanced large pipe shed grouting is completed, the surface grouting construction will be carried out after the preset setting time;

[0038] Carry out excavation and support construction of the shallow buried tunnel body, and use the ring-shaped pilot pit reserved core soil method for excavation;

[0039] A 5m long overlap section is set at the end of the super-large pipe rack, and the advanced support construction of the advanced small pipe 4 and the advanced anchor rod combination is carried out from the starting point of the long overlap section;

[0040] The advance support construction steps of the advance small guide tube 4 and the advance anchor rod combination are repeated until the shallow buried section of the tunnel with poor geological conditions is passed.

[0041] The combined advance support construction method for the shallow buried section of the tunnel with poor geological conditions according to the embodiment of the present invention has the advantages of fast construction progress and small over-excavation of the shallow buried section of the tunnel with poor geological conditions. The present application has the following advantages: the combined advance support system can reduce the influence of the shortcomings of each support, speed up the construction progress of the shallow buried section of the tunnel with poor geological conditions and ensure safety, and reduce the over-excavation of the shallow buried section of the tunnel with poor geological conditions.

[0042] In some embodiments, in the advance support construction steps of the combination of the advance small pipe 4 and the advance anchor rod, the first cycle of the advance small pipe 4 is applied; after the grouting of the advance small pipe 4 is completed, the preset time of waiting for solidification is continued to carry out the next cycle of excavation and support operations in the annular guide pit; in the third cycle, the advance anchor rod is applied and overlapped with the advance small pipe 4 to form a double-layer advance support structure; after the grouting of the advance anchor rod is completed, the preset time of waiting for solidification is carried out to carry out the next cycle of excavation and support operations until the shallow buried section with poor geological conditions of the tunnel is passed.

[0043] Specifically, after the grouting of the advance small duct 4 is completed, wait for 2 hours to solidify before continuing the next cycle of excavation and support operations in the annular guide pit. The advance anchor rods used in the third cycle (the third I-beam arch frame) are advance self-propelled hollow grouting anchor rods. After the grouting of the advance anchor rods is completed, wait for 2 hours to solidify before continuing the next cycle of excavation and support construction. When repeating the construction steps, first install an I-beam arch frame, construct the system anchor rods, and then carry out the steps of applying the advance small duct 4, grouting the advance small duct 4, applying the advance anchor rods, grouting the advance anchor rods, and excavation and support construction.

[0044] In some embodiments, after the excavation of the annular guide pit is completed, the face of the annular guide pit is sealed with shotcrete, which is sprayed twice with an initial spraying thickness of 1 cm. The re-spraying is carried out after the installation of the advance small guide tube 4 or the advance anchor rod is completed and before grouting, with a re-spraying thickness of 3 to 5 cm.

[0045] Specifically, C25 shotcrete is used to seal the annular pilot tunnel face, with an initial spraying thickness of about 1 cm to achieve a stable face effect. The re-spraying is carried out after the installation of the advance small guide tube 4 or the advance anchor rod is completed and before grouting to achieve the effect of sealing the face, preventing leakage, and achieving pressurized grouting.

[0046] In some embodiments, the advance small guide tube 4 is installed with a jacking auxiliary device, which includes a jacking auxiliary sleeve 1, an inner bracket 2 and an outer bracket 3. The inner bracket 2 is located on the inner side of the first end of the jacking auxiliary sleeve 1, and the outer bracket 3 is connected to the outer wall of the first end of the jacking auxiliary sleeve 1. The second end of the jacking auxiliary sleeve 1 cooperates with a hand drill impactor 6.

[0047] Specifically, the pipe jacking auxiliary device sleeves the advance small guide tube 4 into the pipe jacking auxiliary sleeve 1, one end of the advance small guide tube 4 is connected to the hand-held pneumatic drill impactor 6, and the other end of the advance small guide tube 4 is tightly attached to the rock surface through the sleeve cross reinforcement plate 5. The pipe jacking auxiliary sleeve 1 adopts a DN73×4mm seamless steel pipe, which is used to correct the pipe jacking direction of the impactor. The inner bracket 2 adopts a 1cm thick Q235 steel plate, which is about 4cm wide and 10cm long. It is welded to the inside of the end of the pipe jacking auxiliary sleeve 1, and four pieces are arranged in a cross shape to correct the drilling direction of the advance small guide tube 4. The outer bracket 3 adopts a 1cm thick Q235 steel plate welded to the bottom of the end of the pipe jacking auxiliary sleeve 1, and four pieces are arranged in a cross shape to stabilize the auxiliary sleeve and prevent it from tilting; a reinforcement plate 5 is welded to the bottom of the advance small guide tube 4, and a 1cm thick Q235 annular steel pad is welded to the bottom of the small guide tube to prevent the small guide tube from being damaged during the impactor jacking process; the hand-held pneumatic drill impactor 6 is used to jack the small guide tube.

[0048] In some embodiments, after the leading small conduit 4 is pushed in, a pressure valve is installed at the end of the leading small conduit 4 .

[0049] Specifically, the welding pressure valve facilitates the control of the grouting pressure of the leading small conduit 4 .

[0050] In some embodiments, after the sealed concrete of the face has initially set, the grouting pump pressurizes the small advance conduit 4 for grouting. After the grouting reaches the final hole pressure and the pressure is stabilized for 15 minutes, the pressure valve is closed to end the grouting operation.

[0051] Specifically, the water-cement ratio of the cement slurry in the grouting pump is 1:1 (mass ratio), and the final hole pressure is 1.0 MPa.

[0052] In some embodiments, the advance anchors are arranged at an annular spacing of 30 cm within 120° of the vault and at an elevation angle of 20° to 30°.

[0053] Specifically, a single advance anchor rod is 4.5 m long, and the overlapped portion of the advance anchor rod and the first-circulation advance small guide tube 4 forms a combined double-layer advance support structure.

[0054] In some embodiments, the steel pipes of the advanced large pipe shed are arranged within 120° of the arch at a circumferential spacing of 40 cm, and the angle between the axis of the steel pipe and the outer edge of the lining is 1° to 3°.

[0055] Specifically, the steel pipes of the advance large pipe shed are DN108×6mm steel flower pipes with a length of 35m, and the advance large pipe shed is constructed using a crawler anchor drilling rig.

[0056] In some embodiments, the step of drilling a root canal and making a hole for grouting in the surface grouting construction step includes the following steps:

[0057] Infusion 3m 3 Cement mortar, control the diffusion radius;

[0058] Infusion 3m 3 Cement paste to ensure consolidation effect;

[0059] After the cement paste is poured, if the grouting pressure and injection flow rate still have no obvious changes, the hole will be left for setting;

[0060] Re-pouring is carried out after waiting for setting for 8 hours, and cement mortar and cement paste are repeatedly poured and waited for setting;

[0061] If the grouting cannot be closed after two re-pourings, the cement mortar pouring will be repeated until the hole is completed.

[0062] Specifically, the principle of "sequential encryption" is adopted for hole making and grouting. The ratio of cement mortar is 0.8:1:0.2, and the ratio of cement paste is 0.8:1. The first re-grouting is carried out after waiting for 8 hours to set. The construction sequence is still in accordance with the three steps of pouring cement mortar, cement paste, and waiting for setting if there is still no obvious change in grouting pressure and injection flow. If the grouting cannot be closed after two re-groutings, it is necessary to notify the on-site supervision engineer and use 3m 3 Mortar pouring is one cycle.

[0063] In some embodiments, the reserved core soil ring height is controlled at 2.0 to 2.5 m in the shallow buried tunnel excavation and support construction steps, the excavation advance of each cycle is controlled according to the spacing of an I-beam arch frame, and the system support closely follows the excavation face.

[0064] Specifically, after the grouting of the large pipe shed is completed, wait for one day to solidify, and then start the surface grouting construction of the tunnel section with a burial depth of less than 10m. Use a hydraulic crawler drill to make a hole for the root canal, use a 127×4.5 steel pipe to make a hole, insert a 90×3.0 steel flower pipe, and finally use a hydraulic pipe puller to pull out the root canal. Example 1

[0065] The combined advance support construction method for the shallow buried section of the tunnel with poor geological conditions provided by the present invention has been successfully applied to the emergency rescue diversion project of the GS tunnel in the LCJ left bank ice-water accumulation body (L5 highway). The entrance section of the tunnel is mainly composed of alluvial (Qal) sand and gravel with block crushed stone and part of it is fill, with a thickness of 9m-30m, belonging to the Quaternary covering soil layer, which has poor physical and mechanical properties relative to the proposed project and belongs to the V-level surrounding rock. The proposed tunnel passes under the existing rural road, and the shallowest burial depth is only 5.5m. It includes the following steps:

[0066] The open tunnel section of the tunnel was excavated, the arch concrete was poured, and the crawler anchor drilling rig was used to construct the advanced large pipe shed. The parameters of the advanced large pipe shed are: DN108×6mm steel flower pipe, length 35m, ring distance 40cm, arch top 120° arrangement, and the angle between the steel pipe axis and the outer edge of the lining is 1°~3°.

[0067] After the grouting of the advanced large pipe shed is completed, wait for one day to solidify before starting the surface grouting construction of the tunnel section with a burial depth of less than 10m. A hydraulic crawler drill is used to make the root canal hole, a 127×4.5 steel pipe is used to make the hole, a 90×3.0 steel flower pipe is inserted, and finally a hydraulic pipe pulling machine is used to pull out the root canal.

[0068] After the construction of the advance large pipe shed is completed, the excavation and support construction of the shallow buried section of the tunnel is carried out. The excavation is carried out by using the ring-shaped pilot pit reserved core soil method. The height of the reserved core soil ring is controlled at 2.0 to 2.5 meters. The excavation advance of each cycle is controlled according to the spacing of an I-beam arch frame. The system support closely follows the excavation face.

[0069] A 5m long overlap section is set at the end of the advance large pipe shed, and the advance support composed of 4 advance small pipes + advance anchor rods is constructed from the starting point of the overlap section. The overlap process is as follows:

[0070] ① Start from the starting point of the overlap section. After the excavation of the annular pilot pit is completed, C25 shotcrete is immediately used to seal the annular pilot pit face, and the construction is carried out in two stages: the first initial shotcrete with a thickness of 1 cm; the second shotcrete is carried out after the installation of the advance small guide tube 4 or the advance anchor rod is completed and before grouting, and the second shotcrete thickness is 3 to 5 cm.

[0071] ②After the initial spraying of C25 concrete on the face is completed, install an I-beam arch frame and construct system anchor rods.

[0072] ③Construct the first cycle of the advance small conduit 4. Put the advance small conduit 4 into the auxiliary sleeve, connect one end to the hand-held pneumatic drill impactor 6, and the other end is close to the rock surface through the sleeve cross reinforcement plate 5. Use the hand-held pneumatic drill to push the entire small conduit into the broken surrounding rock. Construction parameters of the advance small conduit 4: use DN48×6mm steel flower pipe, single length 4.5m, ring distance 30cm, arch top 120° arrangement, upper elevation angle 5°~12°.

[0073] ④ After the small advance conduit 4 is pushed in, a pressure valve is welded at the end of the small conduit.

[0074] ⑤Re-spray C25 closed concrete with a thickness of 3 to 5 cm.

[0075] ⑥ After the initial setting of the C25 closed concrete on the face, a grouting pump is used to pressurize the small lead pipe 4. The construction parameters are: cement slurry water-cement ratio 1:1 (mass ratio), and the final hole pressure is 1.0Mpa. After the grouting reaches the final hole pressure and the pressure is stabilized for 15 minutes, the pressure valve is closed to end the grouting operation.

[0076] ⑦ After the small-diameter grouting is completed, wait for 2 hours for solidification before continuing the next cycle of excavation and support operations in the annular guide pit.

[0077] ⑧ The third cycle (the third I-beam arch frame) is constructed with advance anchor rods. The construction parameters are as follows: self-propelled hollow grouting anchor rods are used, with a single length of 4.5m, a ring distance of 30cm, an arch top arrangement of 120°, an upward elevation angle of 20°~30°, and a combined double-layer advance support structure is formed with the overlapping part of the first cycle advance small guide tube 4.

[0078] ⑨ After the advance anchor grouting is completed, wait for 2 hours for the setting to proceed with the next cycle of excavation and support construction.

[0079] Repeat steps ②-⑨ until the tunnel is completely penetrated through the shallow buried section with poor geological conditions.

[0080] The combined advance support construction method for the shallow buried section of the tunnel with poor geological conditions has been successfully applied in the shallow buried section of the L5 highway entrance. The application results are as follows:

[0081] The entrance of L5 highway tunnel passes under the poor geological body of GS village mixed accumulation body and part of the filling road section. The tunnel enters from the Quaternary loose accumulation body at the foot of the slope. The physical and mechanical properties of loose rocks are poor. The shallow buried section of the tunnel entrance passes under the rural road of GS village. The intersection of L5 highway tunnel and the road into the village is K0+068 (tunnel design elevation 2115.28m), the design elevation of the road into the village is 2128m, the burial depth is 12.72 meters, and the burial depth above the arch is 5.5 meters. At the same time, the tunnel section K0+075~K0+100 passes under residential houses. The tunnel design elevation is 2116 meters, the design elevation of residential houses is 2136 meters, the burial depth is 20 meters, and the burial depth above the arch is 12.5 meters.

[0082] The shallow buried section of the entrance is designed with a DN108×6mm advance large pipe shed to assist in entering the cave, with a length of 35m (to pile number K0+089), a circumferential spacing of 40cm, and arranged within the 120° range of the arch. The advance support design of the V-level surrounding rock tunnel body section and the broken zone without long pipe shed support in the cave adopts 4 advance small pipes with an outer diameter of 42mm, a wall thickness of 4.0mm, and a length of 450cm, with a circumferential spacing of 30cm, arranged within the 120° range of the arch, and two steel arch frames per cycle.

[0083] According to the approved construction plan, the shallow buried section of the L5 highway tunnel entrance adopts the four-step method of reserved core soil in the circular pilot pit. Small collapses and falling blocks frequently occur during the excavation and support process, and the average over-excavation of unfavorable geology reaches 152cm. On January 7, 2024, the tunnel entrance excavation and support reached the vicinity of the K0+77.5 pile number. The excavation of the heading face has passed through the surface grouting coverage area. During the continued excavation, a large-scale collapse occurred in the right spandrel of the tunnel. Specific situation: A gravel structure interlayer (about 5cm thick) with an inclination of about 30° on the heading face loosened, and the loose body under the structural layer at the right spandrel slid into the cave with a natural slope ratio of about 45°, forming a wedge-shaped collapse cavity with a bottom width of 1.5-2.0m and a depth of about 6.6m.

[0084] After the collapse occurred, the combined advance support construction method was adopted from pile number K0+77.5 to the end of the shallow buried section with poor geology at pile number K0+120, which greatly improved the safety performance of the tunnel. The over-excavation of the shallow buried section with poor geology was reduced from an average of 152cm before implementation to 52cm. No landslide accidents occurred during the construction process, and the safety of the construction workers was effectively guaranteed.

[0085] In the description of the present invention, it is to be understood that the terms “center”, “longitudinal”, “lateral”, “length”, “width”, “thickness”, “up”, “down”, “front”, “back”, “left”, “right”, “vertical”, “horizontal”, “top”, “bottom”, “inside”, “outside”, “clockwise”, “counterclockwise”, “axial”, “radial”, “circumferential”, etc., indicating orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as limiting the present invention.

[0086] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In the description of the present invention, the meaning of "plurality" is at least two, such as two, three, etc., unless otherwise clearly and specifically defined.

[0087] In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral one; it can be a mechanical connection, an electrical connection, or communication with each other; it can be a direct connection, or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements, unless otherwise clearly defined. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0088] In the present invention, unless otherwise clearly specified and limited, a first feature being "above" or "below" a second feature may mean that the first and second features are in direct contact, or the first and second features are in indirect contact through an intermediate medium. Moreover, a first feature being "above", "above" or "above" a second feature may mean that the first feature is directly above or obliquely above the second feature, or simply means that the first feature is higher in level than the second feature. A first feature being "below", "below" or "below" a second feature may mean that the first feature is directly below or obliquely below the second feature, or simply means that the first feature is lower in level than the second feature.

[0089] In the present invention, the terms "one embodiment", "some embodiments", "examples", "specific examples", or "some examples" etc. mean that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the described specific features, structures, materials or characteristics may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, without contradiction.

[0090] Although the embodiments of the present invention have been shown and described above, it is to be understood that the above embodiments are illustrative and are not to be construed as limitations on the present invention. Changes, modifications, substitutions and variations of the above embodiments by those of ordinary skill in the art are all within the scope of protection of the present invention.

Claims

1. A combined advance support construction method for shallow buried sections of tunnels with poor geological conditions, characterized in that: The following steps are involved: Dig the open tunnel section, pour the arch concrete and carry out the advanced large pipe shed construction; After the advanced large pipe shed grouting is completed, the surface grouting construction will be carried out after the preset setting time; Carry out excavation and support construction of the shallow buried tunnel body, and use the ring-shaped pilot pit reserved core soil method for excavation; A 5m long overlap section is set at the end of the super-large pipe rack, and the advanced support construction of the advanced small pipe and advanced anchor combination is carried out from the starting point of the long overlap section; The advance support construction steps of the advance small guide tube and advance anchor combination are repeated until the shallow buried section with poor geological conditions in the tunnel is passed.

2. The combined advance support construction method for shallow buried sections of tunnels with poor geological conditions according to claim 1 is characterized in that: In the advance support construction steps of the combination of advance small pipes and advance anchors, the first cycle of advance small pipes is applied; after the grouting of the advance small pipes is completed, a preset time is waited for solidification before continuing the next cycle of excavation and support operations in the annular guide pit; in the third cycle, advance anchors are applied and overlapped with the advance small pipes to form a double-layer advance support structure; after the grouting of the advance anchors is completed, a preset time is waited for solidification before continuing the next cycle of excavation and support operations until the shallow buried section of the tunnel with poor geological conditions is passed.

3. The combined advance support construction method for shallow buried sections of tunnels with poor geological conditions according to claim 2 is characterized in that: After the excavation of the annular pilot pit is completed, the face of the annular pilot pit is sealed with shotcrete, which is sprayed twice with an initial spraying thickness of 1 cm. The re-spraying is carried out after the installation of the advance small guide tube or the advance anchor rod is completed and before grouting with a re-spraying thickness of 3 to 5 cm.

4. The combined advance support construction method for shallow buried sections of tunnels with poor geological conditions according to claim 2 is characterized in that: The advance small guide tube is sleeved with a pipe jacking auxiliary device for installation. The pipe jacking auxiliary device includes a pipe jacking auxiliary sleeve, an inner bracket and an outer bracket. The inner bracket is located on the inner side of the first end of the pipe jacking auxiliary sleeve, the outer bracket is connected to the outer wall of the first end of the pipe jacking auxiliary sleeve, and the second end of the pipe jacking auxiliary sleeve cooperates with a hand pneumatic drill impactor.

5. The combined advance support construction method for shallow buried sections of tunnels with poor geological conditions according to claim 4 is characterized in that: After the leading small conduit is pushed in, a pressure valve is installed at the end of the leading small conduit.

6. The combined advance support construction method for shallow buried sections of tunnels with poor geological conditions according to claim 5 is characterized in that: After the sealed concrete of the face has initially set, the grouting pump pressurizes and injects grout into the advance small conduit. After the grouting reaches the final hole pressure and the pressure is stabilized for 15 minutes, the pressure valve is closed to end the grouting operation.

7. The combined advance support construction method for shallow buried sections of tunnels with poor geological conditions according to claim 2 is characterized in that: The advance anchor rods are arranged at an annular spacing of 30 cm within 120° of the arch and an upward elevation angle of 20° to 30°.

8. The combined advance support construction method for shallow buried sections of tunnels with poor geological conditions according to claim 1 is characterized in that: The steel pipes of the advanced large pipe shed are arranged within 120° of the arch at a circumferential spacing of 40 cm, and the angle between the axis of the steel pipe and the outer edge of the lining is 1° to 3°.

9. The combined advance support construction method for shallow buried sections of tunnels with poor geological conditions according to claim 1 is characterized in that: The root canal drilling and hole grouting step in the surface grouting construction step includes the following steps: Infusion 3m 3 Cement mortar, control the diffusion radius; Infusion 3m 3 Cement paste to ensure consolidation effect; After the cement paste is poured, if the grouting pressure and injection flow rate still have no obvious changes, the hole will be left for setting; Re-pouring is carried out after waiting for setting for 8 hours, and cement mortar and cement paste are repeatedly poured and waited for setting; If the grouting cannot be closed after two re-pourings, the cement mortar pouring will be repeated for one cycle until the hole is completed.

10. The combined advance support construction method for shallow buried sections of tunnels with poor geological conditions according to claim 1 is characterized in that: In the construction steps of excavation and support of the shallow buried section of the tunnel, the reserved core soil ring height is controlled at 2.0 to 2.5 m. The excavation advance of each cycle is controlled according to the spacing of an I-beam arch frame, and the system support closely follows the excavation face.

Citation Information

Cited By

  • Excavating and supporting method and system for seriously extruded and deformed hole section of soft rock tunnel

    CN121296149A

  • A method and system for excavating and supporting a severely squeezed and deformed section of a soft rock tunnel

    CN121296149B