Method for identifying and confirming side lobe of transponder
By identifying and confirming the side lobe signal of the ground transponder in the on-board train control system, combined with the speed information and lobe width difference, the problem of side lobe misjudgment in the existing technology is solved, and the train positioning accuracy and installation reliability are improved. , lowering costs and thresholds.
Patent Information
- Application Number
- CN202410789090.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-18
- Publication Date
- 2024-10-01
AI Technical Summary
Existing technology has misjudgments in identifying and eliminating side lobe signals of ground transponders, which affects train positioning accuracy, and has high installation requirements, resulting in high installation threshold and cost.
By incorporating side lobe processing into the on-board train control system, calculating the lobe envelope width of the transponder based on train speed information, identifying side lobes based on the width difference and distribution characteristics between the side lobe and the main lobe, and confirming its correctness through integration, reducing False positive rate.
It improves the accuracy and reliability of train positioning accuracy and side lobe identification, reduces installation requirements and costs, and provides intelligent basic information for equipment operation and maintenance.
Smart Images

Figure CN118722784A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of train control in the railway industry, and in particular to how to more reasonably identify ground transponder side lobes generated by external environment and installation factors during the application of a BTM. Background Art
[0002] With the rapid development of domestic rail transit application technology, accurate positioning and precise parking of trains have become a basic consensus among users. As an on-board device that provides basic positioning information for trains, the accuracy of the positioning information of transponder products directly affects the positioning of trains.
[0003] The transponder products that complete the train positioning function include on-board equipment BTM and ground transponders. The on-board equipment BTM includes a transponder receiving antenna (arranged at the bottom of the vehicle) and a transponder transmission module (arranged in the carriage cabinet), hereinafter referred to as BTM (transponder on-board query device). The ground transponder is arranged at a specific position according to the relevant parameters of the engineering design. When the transponder antenna of the on-board BTM passes the ground transponder, it activates the ground transponder through electromagnetic energy. The activated ground transponder sends an uplink signal to the on-board antenna. The on-board antenna transmits the uplink information to the transponder transmission module through a cable. The transponder transmission module processes the signal, parses the message content and calculates the position of the transponder, and sends the above information to the subsequent on-board train control equipment to realize the identification and positioning of the ground transponder.
[0004] Based on the electromagnetic field distribution characteristics, the activated transponder will generate three energy envelope lobes, namely the front side lobe, the main lobe, and the rear side lobe. Among them, the main lobe has the widest energy envelope distribution and the strongest energy. It is located in the center of the physical transponder and is the most accurate as a positioning reference signal. The front side lobe is located in front of the main lobe (the direction of the train passing) and is completely consistent with the code source information of the main lobe. Therefore, it is technically difficult to filter out the front side lobe, which has a greater impact on the train positioning accuracy (up to 480mm). The rear side lobe is located behind the main lobe and can be filtered out by comparing the code source (if it is consistent with the main lobe, it will be filtered out). In general, the installation height (distance from the ground) of the vehicle-mounted antenna is controlled by engineering and technical means so that the antenna can only receive the signal of the main lobe of the transponder and filter out the side lobe signal. In this way, the precise position of the transponder can be calculated through the main lobe signal.
[0005] As for the transponder sidelobe, although it can be eliminated through engineering installation in theory, due to the transponder installation environment and the vibration during train operation (which affects the distance between the antenna and the ground transponder), the BTM will also recognize the sidelobe and use the sidelobe signal as the reference positioning information of the transponder, which directly affects the positioning of the train. Summary of the invention
[0006] In order to solve the above problems, the present invention proposes a method for identifying and confirming the side lobe of a transponder.
[0007] The present invention proposes a method for identifying and confirming the side lobe of a transponder. The method incorporates side lobe processing into the entire on-board train control system, calculates the lobe envelope width of the transponder in combination with train speed information, and identifies the side lobe according to the width difference between the side lobe envelope and the main lobe envelope; at the same time, the side lobe is further confirmed according to the distribution characteristics of the side lobe and the main lobe;
[0008] The BTM performs preliminary calibration of the transponder lobe through sidelobe identification;
[0009] If the BTM end identifies the lobe as a side lobe, the velocity is integrated starting from the center initially marked as the side lobe;
[0010] If the integrated distance Ld does not exceed the threshold D max When the transponder lobe with the same code source content is received, it is confirmed that the sidelobe mark is correct; for the integral distance Ld exceeding the threshold D max , still no transponder lobe with the same code source content is received, it is confirmed that the side lobe is marked incorrectly and should be the main lobe;
[0011] If the BTM identifies the lobe as the main lobe, the subsequent transponder lobes with the same code source content are considered to be the rear side lobes of the transponder; after the confirmation is completed, the transponder information is reported to the subsequent on-board train control system.
[0012] The present invention thus brings about the following technical effects: the BTM end improves the train positioning accuracy of the on-board train control system end by identifying and confirming the side lobes of the transponder respectively, and at the same time, the reconfirmation of the side lobes by the on-board train control system end can further improve the accuracy and reliability of the system's side lobe identification; it can reduce the engineering installation requirements and standards of on-site antennas and transponders, lower the installation threshold, and save installation and debugging costs; it can accurately understand the working status and installation environment of the ground transponder, and provide basic information for the intelligent operation and maintenance of equipment. BRIEF DESCRIPTION OF THE DRAWINGS
[0013] Figure 1 Schematic diagram of the spatial distribution of the front side lobe, main lobe and rear side lobe of the transponder;
[0014] Figure 2 The corresponding relationship between the transponder lobe and the identification signal (TTL level);
[0015] Figure 3 This is the TTL level correspondence diagram of the front side lobe and main lobe of the transponder; DETAILED DESCRIPTION
[0016] In order to make the technical solution of the present invention more clear, the present invention is further described in detail below with reference to the accompanying drawings.
[0017] In the past, the side lobes of the transponder were processed by comparing the content of the transponder lobe message. This inevitably mistakenly took the side lobes as the main lobes, directly affecting the BTM's positioning accuracy of the transponder.
[0018] The method of the present invention incorporates sidelobe processing into the entire on-board train control system, calculates the lobe envelope width of the transponder by combining the train speed information, and identifies the sidelobe based on the width difference between the sidelobe envelope and the main lobe envelope; at the same time, the sidelobe is further confirmed based on the distribution characteristics of the sidelobe and the main lobe to ensure the accuracy of sidelobe identification.
[0019] According to the inherent difference in the energy range of the main lobe and the side lobe (generally, under normal engineering installation conditions, the main lobe has a range of 530mm to 670mm, and the side lobe has a range of ≤300mm), the BTM detects a valid energy envelope signal and starts integrating the velocity, and stops integrating after detecting an invalid energy envelope signal. The integration result is the width of the transponder lobe envelope. By thresholding the lobe width (Lm min ,Ls max ) judgment, preliminarily identify the side lobe, and at the same time, the auxiliary code source content and the order of the side lobe (train running direction) can distinguish the front side lobe and the rear side lobe. See the attached Figure 1 .
[0020] The BTM performs preliminary calibration of the transponder lobe through sidelobe identification. However, abnormal effective transponder envelope width caused by external environmental factors or problems with the ground transponder itself can lead to calibration errors in sidelobe identification (i.e., misjudging the main lobe as a sidelobe). To avoid this, the BTM needs to confirm the identified sidelobe.
[0021] If the BTM identifies the lobe as a side lobe through the identification method, the velocity is integrated from the center initially marked as the side lobe. When the integrated distance exceeds the threshold (the maximum distance D between the front side lobe and the center of the main lobe), the velocity is integrated. max , each transponder is slightly different. Take our transponder as an example, D max According to laboratory statistics, it is 480mm), if the transponder lobe with the same code source content is still not received, it is confirmed that the side lobe mark is wrong and should be the main lobe; if the transponder lobe with the same code source content is received within the threshold range, it is confirmed that the side lobe mark is correct.
[0022] If the BTM identifies the lobe as the main lobe through the identification method, the subsequent transponder lobes with the same code source content are considered to be the rear side lobes of the transponder. After the confirmation is completed, the transponder information is reported to the subsequent on-board train control system. The confirmation operation is based on the premise of meeting the timeliness of the transponder information.
[0023] In order to improve the accuracy and reliability of sidelobe confirmation, it is necessary to add the same confirmation method on the on-board train control system to reconfirm the sidelobe.
[0024] 1. Sidelobe Identification
[0025] It is necessary to integrate the transponder envelope according to the speed information, calculate the envelope width, and preliminarily mark the lobe type according to the width range of the main lobe and side lobe. This identification method is performed at the front-end BTM end.
[0026] Attached Figure 2 As shown in the figure, after the BTM antenna receives the transponder energy envelope signal, the BTM front-end hardware analog signal processing module will convert the envelope signal into a TTL level of the corresponding range width according to a certain threshold (a high level is above the threshold, and a low level is below the threshold). The BTM end uses the TTL level signal as the basic basis for identifying the side lobe.
[0027] Attached Figure 2 As shown, the BTM end starts to integrate and accumulate the speed from the leading edge of the TTL level part [t0, V(t0)] (its speed mileage reference information comes from the subsequent train control on-board equipment) until the integration is stopped at the trailing edge of the TTL level part [t1, V(t1)]. The integration result at this time is the transponder lobe length.
[0028] Right now:
[0029]
[0030] If the integral result Lm∈[Lm min ,∞), where [Lm min ,∞) is the main lobe envelope length range of the transponder, then this lobe can be considered as the main lobe, where Lm min It is the minimum value of the main lobe envelope length of the transponder.
[0031] If the integral result Lm∈(0,Ls max ], where (0,Ls max ] is the range of the sidelobe envelope length of the transponder, then this lobe can be considered as a sidelobe. If no lobe with the same code source content is identified before the sidelobe is identified, then this lobe can be considered as a front sidelobe. If the main lobe with the same code source content has been identified before the sidelobe is identified, then this lobe can be considered as a rear sidelobe, where Ls max is the maximum value of the transponder sidelobe envelope length.
[0032] When L∈(Ls max ,Lm min ), it can be considered that the main lobe envelope width is too small due to the abnormal transponder energy. Therefore, the envelope width does not meet the normal main lobe envelope range [Lmmin ,∞) are marked as side lobes.
[0033] 2. Sidelobe confirmation
[0034] In order to avoid sidelobe recognition errors caused by abnormalities, the marked sidelobe needs to be further confirmed. This confirmation method is implemented at the front-end BTM end and the back-end train control system end.
[0035] 2.1BTM side lobe confirmation
[0036] The BTM end realizes the front-end confirmation of the front side lobe and the rear side lobe. The specific method is as follows:
[0037] As attached Figure 3 As shown, after the BTM identifies the front side lobe, it starts to integrate the speed from the center point of the front side lobe, and the integrated distance Ld is accumulated, that is, the driving distance is calculated.
[0038] When the integral distance Ld∈[D max ,∞)(Ld is the distance between the main lobe and the side lobe center of the transponder, where D max =480mm), if no lobe with the same code source content is detected, the previous side lobe mark is considered to be erroneous, adjusted to the main lobe, and the transponder message information and position information are reported to the subsequent on-board train control.
[0039] When the integral distance Ld∈(0,D max )(The distance between the main lobe and the side lobe center of the transponder, where D max =480mm), a lobe with the same message content is detected and the lobe length meets the main lobe length range, then this side lobe identification mark is considered correct, and after the subsequent main lobe identification is completed, the transponder message information and position information are reported to the subsequent on-board train control system, and the front side lobe related information is recorded through the internal BTM recording unit.
[0040] Generally, the identification and confirmation of the rear side lobe is simple, which mainly involves comparing the code source content with the code source content of the main lobe. If they are consistent, it is considered to be the rear side lobe, and the rear side lobe related information is recorded through the internal BTM recording unit.
[0041] 2.2 Side lobe reconfirmation at the onboard train control terminal
[0042] The on-board train control system realizes the post-stage reconfirmation of the front side lobe and the rear side lobe. The specific method is the same as the side lobe confirmation method of the BTM end in 2.1, that is, the on-board train control system receives the balise lobe information (lobe center position, balise message, balise envelope signal) from the BTM end, and calculates the train travel distance from the center point of the lobe. When the integrated distance exceeds the threshold, that is, Ld∈[D max,∞), if the transponder lobe information with the same message content is still not received, it is considered that the previous side lobe mark is wrong and is adjusted to the main lobe; on the contrary, if the integral distance Ld∈(0,D max ), if the transponder lobe information with the same message content is received, it is considered that the sidelobe identification mark is correct and the newly received transponder lobe is the main lobe.
[0043] The above is only a preferred implementation case of this new solution, and is not intended to limit the protection scope of this new solution. Any modification, equivalent replacement, improvement, etc. made within the spirit and principles of this new solution should be included in the protection scope of this new solution.
Claims
1. A method for transponder sidelobe identification and confirmation, It is characterized in that The method incorporates sidelobe processing into the entire on-board train control system, calculates the lobe envelope width of the transponder in combination with train speed information, and identifies the sidelobe based on the width difference between the sidelobe envelope and the main lobe envelope; and further confirms the sidelobe based on the distribution characteristics of the sidelobe and the main lobe; The BTM performs preliminary calibration of the transponder lobe through sidelobe identification; If the BTM end identifies the lobe as a side lobe, the velocity is integrated starting from the center initially marked as the side lobe; If the integrated distance Ld does not exceed the threshold D max When the transponder lobe with the same code source content is received, it is confirmed that the sidelobe mark is correct; for the integral distance Ld exceeding the threshold D max , still no transponder lobe with the same code source content is received, it is confirmed that the side lobe is marked incorrectly and should be the main lobe; If the BTM identifies the lobe as the main lobe, the subsequent transponder lobes with the same code source content are considered as the transponder rear side lobes; After confirmation is completed, the transponder information will be reported to the subsequent on-board train control system.
2. The method according to claim 1, It is characterized in that The sidelobe identification of the method refers to the inherent difference in the energy range of the main lobe and the side lobe. The BTM end starts to integrate the speed after detecting the valid signal of the energy envelope, and stops integrating after detecting the invalid signal of the energy envelope. The integration result is the width value of the transponder lobe envelope. The sidelobe is preliminarily identified by judging the threshold of the lobe width. At the same time, the sequence of the auxiliary code source content and the sidelobe can distinguish the front sidelobe from the rear sidelobe.
3. The method according to claim 2, It is characterized in that After the main lobe is identified, the balise message information and location information are reported to the subsequent onboard train control system, and the front side lobe related information is recorded through the internal BTM recording unit; The rear side lobe identification confirmation is to compare the code source content with the code source content of the main lobe. If they are consistent, it is considered to be the rear side lobe. The rear side lobe related information is recorded through the internal BTM recording unit.
4. The method according to claim 1, It is characterized in that The threshold D max It is the maximum distance between the front side lobe and the center point of the main lobe.
5. The method according to claim 1, It is characterized in that In order to improve the accuracy and reliability of sidelobe confirmation, the same confirmation method is added to the on-board train control system to reconfirm the sidelobe.
6. The method according to claim 5, It is characterized in that The on-board train control system realizes the post-stage reconfirmation of the front side lobe and the rear side lobe; The on-board train control system receives the transponder lobe information from the BTM end, and calculates the driving distance by integration from the center point of the lobe. When the integrated distance exceeds Ld∈[D max ,∞), if the transponder lobe information with the same message content is still not received, it is considered that the previous side lobe marking is wrong and adjusted to the main lobe; if the integral distance Ld∈(0,D max ), if the transponder lobe information with the same message content is received, it is considered that the sidelobe identification mark is correct and the newly received transponder lobe is the main lobe.
Citation Information
Cited By
BTM transponder signal main lobe and side lobe identification and positioning method and device
CN122667094A