Bridge pier bearing platform steel jacket box anti-collision system and construction method thereof
By assembling steel boxes to form annular anti-collision components, the problem of cumbersome construction of anti-collision components on the bridge pier cap and occupying water areas is solved, achieving convenient installation and high stability, and reducing the impact on the passage of ships.
Patent Information
- Application Number
- CN202410603727.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-15
- Publication Date
- 2024-10-01
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The construction of the anti-collision components of the existing bridge pier caps is cumbersome and subsequent replacement is difficult. It also occupies navigable waters and affects the passage of ships.
A number of steel casings are assembled into annular anti-collision components, which are fixed on the inside of the bridge pier cap through embedded parts. Adjacent steel casings are connected through connectors to form an expanded angle, which is convenient for installation and disassembly. The box is equipped with water-permeable holes, limit protrusions and hanging legs to improve stability and impact resistance.
It simplifies the installation and replacement process of anti-collision components, reduces the occupation of navigation waters, improves the stability and impact resistance of anti-collision components, and reduces the risk of damage to the bridge pier cap.
Smart Images

Figure CN118727666A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of anti-collision systems, and in particular to a bridge pier cap steel casing anti-collision system and a construction method thereof. Background Art
[0002] With the continuous development of the transportation industry, large-scale cross-sea bridges are also increasing. During the construction of cross-sea bridges, anti-collision components are usually installed around the piers to reduce the possibility of subsequent ships colliding with the piers while sailing on the water, causing damage to the piers and affecting the safety of the pier structure.
[0003] At present, the anti-collision components of bridge pier caps are mainly of two structures: anti-collision artificial islands and anti-collision pile groups. The anti-collision artificial islands are constructed by casting large concrete components in the water area around the piers. The cast concrete components are used to limit the collision of ships with the pier caps, so as to provide anti-collision protection for the pier caps. The anti-collision pile groups are constructed by injecting a number of steel anti-collision casings in the water area outside the pier caps, so as to provide anti-collision protection for the pier caps.
[0004] With regard to the above-mentioned related technologies, the above-mentioned two forms of anti-collision components, on the one hand, are complicated and inconvenient to construct, and are difficult to replace after being damaged by subsequent ship collisions; on the other hand, anti-collision components such as artificial islands and anti-collision pile groups will inevitably occupy part of the navigable waters, affecting the daily passage of ships; therefore, there is room for improvement. Summary of the invention
[0005] In order to facilitate the disassembly, assembly and replacement of anti-collision components of bridge pier caps while reducing the occupation of normal navigable waters by anti-collision components, the present application provides a bridge pier cap steel casing anti-collision system and a construction method thereof.
[0006] The present application provides a bridge pier cap steel casing anti-collision system and a construction method thereof, which adopts the following technical solutions: A bridge pier cap steel casing anti-collision system, comprising an annular anti-collision component arranged around the outside of the pier cap; the annular anti-collision component is assembled from a plurality of steel casings; the steel casings are fixed to the inside of the pier cap by a plurality of embedded parts, and the adjacent steel casings are connected by a plurality of connectors; the inner cavity of the steel casing is also vertically provided with a plurality of annular ribs, the outer peripheral side of the annular ribs is welded and fixed to the inner peripheral side of the steel casing; the splicing surfaces at both ends of the closed section steel casing in the annular anti-collision component form an outward expansion angle.
[0007] By adopting the above technical scheme, the annular anti-collision component assembled by a number of steel casings is used to protect the bridge pier cap, so as to reduce the situation where subsequent ships passing on the water surface directly hit the bridge pier cap and cause damage to the bridge pier cap. Compared with traditional artificial islands and flip components such as flip pile groups, the subsequent steel casings are simpler and more convenient to install, which is convenient for the subsequent disassembly, assembly and replacement of steel casings, and there is no need to occupy normal navigable waters, which reduces the impact of anti-collision components on the daily passage of ships; the adjacent steel casings are connected by a number of connecting parts, which is conducive to improving the connection integrity of the adjacent steel casings, thereby improving the overall stability of the annular anti-collision component; an outward expansion angle is formed by the splicing surfaces at both ends of the closing section steel casing, and when the closing section steel casing is subsequently installed, the closing section steel casing can be first hoisted into the flared end of its installation position, and then the closing section steel casing can be horizontally moved into place, which is convenient for the installation of the closing section steel casing.
[0008] Preferably, the connecting parts include connecting bolts, which are passed through the joint surfaces at the adjacent ends of the adjacent steel casings, and the tail ends of the connecting bolts are threadedly connected with connecting nuts; a number of manholes are opened on the top of the steel casings, and a number of straight ladders are set up in the inner cavity of the steel casings corresponding to the manholes, and the straight ladders extend to the bottom of the corresponding manholes.
[0009] By adopting the above technical solution, adjacent steel casings can be connected and fixed by connecting parts to improve the connection integrity of adjacent steel casings; through the provision of manholes and ladders, it is convenient for operators to go back and forth inside the steel casing through the manholes and ladders, which facilitates the installation of connecting parts.
[0010] Preferably, the embedded part includes a fixing sleeve and a fixing bolt; the fixing sleeve is embedded in the outer side of the pier cap, and the fixing bolt is penetrated through the inner box wall of the steel casing and threadedly connected to the fixing sleeve.
[0011] By adopting the above technical solution, when installing the steel casing, after the steel casing is hoisted into place, the fixing bolts are passed through the box wall inside the steel casing and threadedly connected to the threaded sleeve buried on the outside of the pier cap, so that the steel casing can be fixed to the outside of the pier cap through the embedded parts.
[0012] Preferably, a plurality of limiting protrusions are protruding from the top of the inner side of the steel casing, and the bottom side of the limiting protrusions and the side of the steel casing facing the pier cap are both in contact with the pier cap via rubber pads.
[0013] By adopting the above technical scheme, it is beneficial to provide a number of support points for the steel casing through the limiting protrusions, thereby reducing the situation where the deadweight load of the steel casing is entirely applied to the embedded parts, which makes the embedded parts easy to be damaged; by setting the rubber pad, soft contact between the steel casing and the pier cap is achieved; at the same time, when the steel casing is subsequently hit by a ship, part of the impact force can be absorbed by the rubber pad, making the pier cap less likely to be damaged.
[0014] Preferably, the steel casing is provided with a plurality of water-permeable holes.
[0015] By adopting the above technical solution, on the one hand, when the steel casing is subsequently hoisted, seawater enters into the interior of the steel casing through the water-permeable holes on the steel casing, so that the steel casing will not be difficult to lower due to the buoyancy of seawater, thereby facilitating the positioning of the steel casing; on the other hand, the water-permeable holes can reduce the impact of seawater on the steel casing, thereby making the steel casing less likely to be damaged by the impact of seawater.
[0016] Preferably, a plurality of hanging legs are vertically connected to the top of the inner side of the steel casing, and a plurality of hanging screws are pre-embedded in the pier cap corresponding to the plurality of hanging legs. The hanging legs are all provided with hanging holes, and the hanging legs are hung on the corresponding hanging screws through the hanging holes.
[0017] By adopting the above technical scheme, on the one hand, when hoisting the steel casing, the hanging legs are hung on the hanging screws corresponding to the pier cap through the hanging holes, so as to realize temporary positioning of the steel casing, reduce the difficulty of positioning the steel casing during installation due to factors such as waves, and facilitate the subsequent fixing of the steel casing to the outer side of the pier cap through embedded parts. On the other hand, after the steel casing is subsequently installed and fixed on the outer side of the pier cap, the cooperation between the hanging legs and the hanging rods can be used to assist in supporting the steel casing, so as to reduce the situation where the deadweight load of the steel casing is concentrated on the embedded parts between the steel casing and the pier cap.
[0018] Preferably, a construction method of a bridge pier cap steel casing anti-collision system comprises the following steps: S1: Preparation for hoisting and splicing of steel casing: Move the crane ship and the transport ship loaded with steel casing to the hoisting construction site and anchor them: S2: Hoisting of the starting section steel casing: After the starting section steel casing on the transport ship is hoisted to the corresponding installation position outside the bridge pier cap by a crane ship, the starting section steel casing is fixed to the outside of the bridge pier cap by embedded parts; S3: repeat step S1; S4: Hoisting of the intermediate steel casing: Starting from the initial steel casing, the corresponding intermediate steel casings on the transport ship are hoisted to the corresponding installation positions on the outside of the pier cap by the crane ship in a clockwise or counterclockwise construction sequence, and then the intermediate steel casings are fixed to the outside of the pier cap by embedded parts; S5: repeat step S1; S6: Hoisting of the closing section steel casing: After the closing section steel casing on the transport ship is hoisted to the corresponding installation position outside the pier cap by a crane ship, the closing section steel casing is fixed to the outside of the pier cap by embedded parts; S7: Connect adjacent steel casings through connectors.
[0019] By adopting the above technical solution, a number of steel casings installed and fixed on the outside of the pier cap are used to form an annular anti-collision component to provide anti-collision protection for the pier cap, thereby reducing the situation in which the pile foundation piers cause damage to the pier cap during the movement of subsequent ships.
[0020] Preferably, in step S6, the specific steps are as follows: S6.1: Installation of traction equipment: Several winches are installed on the upper surface of the pier cap towards the installation position of the closing section steel casing; S6.2: Hoisting of the closing section steel casing: Hoist the closing section steel casing into the opening of the corresponding installation position by means of a crane ship and make the bottom of the closing section steel casing higher than the water surface; S6.3: Connection of traction equipment: Connect the winch cable to the upper surface of the steel casing of the closing section; S6.4: Closing section steel casing traction: The closing section steel casing is moved toward the pier cap by winding up the cable with the winch and assisting with the crane ship, until the inner side of the closing section steel casing abuts against the pier cap; S6.5: Closing section steel casing placement: lower the closing section steel casing by crane ship until the closing section steel casing is completely placed; S6.6: Fix the closing section steel casing to the outside of the pier cap by embedded parts.
[0021] By adopting the above technical solution, due to the factors of the installation position of the closing section steel casing, the closing section steel casing is hoisted from top to bottom, which is difficult to hoist and the steel casings are prone to collision, resulting in damage to the steel casing. By hoisting the steel casing to the flared end of the installation position of the closing section steel casing first, and then wedging the closing section steel casing to the installation position of the closing section steel casing through the coordination of the traction equipment and the crane ship, it is helpful to reduce the difficulty of the steel casing falling into place, reduce the collision of the closing section steel casing with the adjacent steel casing during the hoisting process, and realize the rapid hoisting of the closing section steel casing in place.
[0022] In summary, the present application includes at least one of the following beneficial technical effects: 1. A number of steel casings are assembled to form an annular anti-collision component to realize anti-collision enclosure of the bridge pier cap. On the one hand, it reduces the situation where the anti-collision component excessively occupies the navigable waters and affects the normal passage of ships. On the other hand, the overall installation of the anti-collision component is relatively simple, which is convenient for the subsequent disassembly, assembly and replacement of the anti-collision component after it is damaged.
[0023] 2. A number of water-permeable holes are opened in the steel casing. When the steel casing is installed on the outside of the pier cap, seawater can enter the steel casing through the water-permeable holes, reducing the difficulty in positioning the steel casing due to the buoyancy of seawater. At the same time, after the steel casing is subsequently installed and fixed on the outside of the pier cap, the impact of seawater on the steel casing can be reduced through the water-permeable holes, making the steel casing less susceptible to damage.
[0024] 3. The hanging legs on the top of the inner side of the steel casing are hung on the embedded hanging screws of the pier cap through the hanging holes. When hoisting the steel casing, the hanging legs can be hung through the hanging holes to achieve temporary positioning of the steel casing, which is convenient for fixing the steel casing to the outside of the steel casing through embedded parts later; at the same time, the hanging legs can be used to assist in supporting the steel casing, thereby facilitating the steel casing to be more firmly installed on the outside of the pier cap. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] Figure 1 It is a schematic diagram used to illustrate a bridge pier cap in an embodiment of the present application.
[0026] Figure 2 It is a schematic diagram for illustrating the positions of the annular anti-collision component and the support platform in an embodiment of the present application.
[0027] Figure 3 It is a schematic diagram of the structure of the steel casing of the long side section of the pier cap used in the embodiment of the present application.
[0028] Figure 4 It is a schematic diagram of the structure of the steel casing of the short side section of the pier cap in the embodiment of the present application.
[0029] Figure 5 It is a schematic diagram used to illustrate the connection structure between the steel casing and the pedestal in the embodiment of the present application.
[0030] Figure 6 yes Figure 5 Enlarged schematic diagram of part A in the middle.
[0031] Figure 7 It is a schematic diagram of the local structure of adjacent steel casing connection pieces used in the embodiment of the present application.
[0032] Figure 8 It is a schematic diagram of the state of hoisting the closing section steel casing in an embodiment of the present application.
[0033] Description of reference numerals: 1. Bridge pier cap; 2. Annular anti-collision member; 20. Steel casing; 201. Water-permeable hole; 202. Annular rib; 21. Lifting ear; 22. Limiting protrusion; 23. Rubber pad; 3. Fixing sleeve; 31. Fixing bolt; 4. Hanging leg; 41. Hanging screw; 42. Locking nut; 5. Connecting bolt; 51. Connecting nut; 6. Bracket; 61. Winch. DETAILED DESCRIPTION
[0034] The following is combined with Figure 1-8 This application is described in further detail.
[0035] In this embodiment, refer to Figure 1 The pier cap 1 is in the shape of a long hexagon.
[0036] The embodiment of the present application discloses a bridge pier cap steel casing anti-collision system and a construction method thereof.
[0037] Reference Figure 1 and Figure 2 A bridge pier cap steel casing anti-collision system includes an annular anti-collision component 2 arranged around the outer periphery of the pier cap 1, the annular anti-collision component 2 is assembled from a plurality of steel casings 20, the side of the steel casing 20 facing the pier cap 1 is the inner side of the steel casing 20, and the inner side of the steel casing 20 is fixed to the outer side of the pier cap 1 through a plurality of embedded parts.
[0038] Reference Figures 2 to 4 The inner circumference of the annular anti-collision component 2 is matched with the outer circumference of the pier cap 1; the splicing surfaces at both ends of the steel casing box 20 located at the long side of the pier cap 1 are arranged in parallel, and the splicing surfaces at both ends of the steel casing box 20 located at the short side of the steel casing box 20 form an outward expansion angle. In this embodiment, in the annular anti-collision component 2, the starting end steel casing box 20 is the steel casing box 20 at a long side of the pier cap 1, and the closing section steel casing box 20 is the steel casing box 20 at a short side of the pier cap 1. The starting section steel casing box 20 is adjacent to the closing section steel casing box 20.
[0039] Reference Figure 5 and Figure 6 The embedded parts include a fixing sleeve 3 and a fixing bolt 31. The fixing sleeve 3 is embedded and fixed on the outside of the bridge pier cap 1. The fixing bolt 31 is passed through the inner wall of the steel casing 20 and is threadedly connected to the fixing sleeve 3, so that the steel casing 20 is fixed to the outer periphery of the bridge pier cap 1 through the embedded parts. The inner wall of the steel casing 20 is provided with a first through hole for the fixing bolt 31 to pass through.
[0040] Reference Figure 7 , the adjacent ends of the adjacent steel casings 20 are connected by a plurality of connecting pieces, which is conducive to improving the connection integrity of the adjacent steel casings 20. The connecting piece includes a connecting bolt 5 and a connecting nut 51. The connecting bolt 5 is inserted through the splicing surface of the adjacent end of the adjacent steel casing 20, and the connecting nut 51 is threadedly connected to the tail end of the connecting bolt 5 and is tightly pressed against the splicing surface of the steel casing 20, so as to realize the connection of the adjacent steel casing 20 through the connecting piece. The splicing surface of the steel casing 20 is provided with a through hole corresponding to the connecting bolt 5 for the connecting bolt 5 to be inserted.
[0041] Several manholes (not shown in the figure) are opened on the top of the steel casing 20, and several straight ladders (not shown in the figure) are welded and fixed in the steel casing 20 corresponding to the several manholes. The tops of the straight ladders extend below the manholes, and the straight ladders are located on the inner wall of the steel casing 20. Through the above arrangement, it is convenient for construction personnel to go back and forth in the steel casing 20 through the manholes and the straight ladders to install the connectors and embedded parts.
[0042] Reference Figure 1 and Figure 8 A plurality of water permeable holes 201 are provided on the steel casing 20. Through the provision of the water permeable holes 201, when the steel casing 20 is subsequently hoisted to the installation position, seawater can enter the steel casing 20 through the water permeable holes 201, thereby reducing the difficulty in positioning the steel casing 20 due to the buoyancy of seawater. At the same time, after the steel casing 20 is subsequently installed and fixed on the outer periphery of the pier cap 1, the steel casing 20 can reduce the impact of waves and the like through the water permeable holes 201, which is beneficial to improving the impact resistance of the steel casing 20 and making the steel casing 20 less susceptible to damage. On the other hand, it is beneficial to reduce the overall weight of the steel casing 20 through the plurality of water permeable holes 201, thereby reducing the difficulty of subsequent hoisting of the steel casing 20 to a certain extent.
[0043] A plurality of lifting ears 21 are welded and fixed on the top of the steel casing 20 to facilitate the subsequent connection between the lifting device on the lifting equipment and the steel casing 20.
[0044] Reference Figure 5 and Figure 6 A plurality of annular ribs 202 are vertically connected to the interior of the steel casing 20, and the outer peripheral side of the annular ribs 202 is welded and fixed to the inner peripheral side of the steel casing 20, so as to improve the overall strength and rigidity of the steel casing 20 through the plurality of annular ribs 202, so that the steel casing 20 is not easily deformed and damaged.
[0045] A plurality of limiting protrusions 22 are convexly arranged on the top of the inner side of the steel casing 20, and the bottom of the limiting protrusions 22 and the inner side of the steel casing 20 are both in contact with the pier cap 1 through a plurality of rubber pads 23. Through the above arrangement, the limiting protrusions 22 can be used to assist in supporting the steel casing 20, thereby reducing the situation where the automatic load on the steel casing 20 acts on the fixing bolts 31 of the embedded parts after the subsequent installation and fixing of the steel casing 20, so that the fixing bolts 31 are not easily deformed and damaged. Through the arrangement of the rubber pads 23, soft contact between the steel casing 20 and the pier cap 1 is achieved, reducing the situation where the steel casing 20 and the pier cap 1 collide during installation, resulting in damage to the pier cap 1. At the same time, part of the impact can be absorbed by the rubber pads 23, which is conducive to the annular anti-collision member 2 to better protect the pier cap 1 from collision.
[0046] A plurality of hanging legs 4 are also vertically arranged on the top of the inner side of the steel casing 20, and the hanging legs 4 are welded and fixed on the limiting protrusions 22; a plurality of hanging screws 41 are vertically pre-embedded and fixed corresponding to the hanging legs 4 on the upper surface of the pier cap 1; hanging holes are opened on the hanging legs 4 and the hanging legs 4 are hung on the corresponding hanging screws 41 through the hanging holes. Through the above arrangement, by utilizing the cooperation between the hanging legs 4 and the hanging screws 41, on the one hand, when the steel casing 20 is subsequently hoisted, the hanging rod is first hung on the hanging screws 41 through the hanging holes, so as to first perform the preliminary positioning of the steel casing 20 and limit the shaking of the steel casing 20 and the difficulty in positioning; on the other hand, after the steel casing 20 is subsequently fixed to the outside of the pier cap 1 through the embedded parts, the steel casing 20 can be auxiliary supported by the cooperation between the hanging rod and the hanging screws 41, so as to reduce the situation where the dead weight load of the steel casing 20 is concentrated on the fixing bolts 31 of the embedded parts. A locking nut 42 is threadedly connected to the top of the hanging screw rod 41 , and the locking nut 42 is tightly pressed against the top of the hanging leg 4 to limit the displacement of the hanging leg 4 .
[0047] A construction method for a bridge pier cap steel box anti-collision system, referring to Figures 5 to 8 , the specific steps are as follows: S1: Preparation for hoisting and splicing of the steel casing 20: Move the crane ship and the transport ship loaded with the steel casing 20 to the hoisting construction site and then anchor and position; before the transport ship transports the steel casing 20, load the steel casing 20 in advance according to the installation sequence; S2: Hoisting of the starting section steel casing 20: The specific steps are as follows: S2.1: Connect the crane ship's lifting device to the lifting lug 21 on the starting section steel casing 20 through a cable; S2.2: After the starting section steel casing 20 on the transport ship is hoisted to the upper side of the installation position corresponding to the outer periphery of the bridge pier cap 1 by means of a crane ship, the starting section steel casing 20 is lowered until the hanging legs 4 are hung on the corresponding hanging screws 41 through the hanging holes, and the limiting protrusions 22 are in contact with the upper surface of the bridge pier cap 1, so that the starting section steel casing 20 is hoisted to the installation position; S2.3: Embedded parts installation: The installer wears diving equipment and enters the steel casing 20 through the manhole and the ladder, inserts the fixing bolt 31 through the corresponding first through-hole on the inner side of the steel casing 20 and threads it into the fixing sleeve 3.
[0048] S3: Repeat step S1.
[0049] S4: Hoisting of the middle section steel casing 20: Starting from the starting section steel casing 20, the middle section steel casing 20 is hoisted in a clockwise construction sequence. The specific steps are as follows: S4.1: Connect the crane ship sling to the lifting lug 21 on the middle section steel casing 20 through a cable; S4.2: After the intermediate steel casing 20 on the transport ship is hoisted to the upper side of the installation position corresponding to the outer periphery of the bridge pier cap 1 by means of a crane ship, the intermediate steel casing 20 is lowered until the hanging legs 4 of the intermediate steel casing 20 are hung on the corresponding hanging screws 41 through the hanging holes, and the limiting protrusions 22 of the intermediate steel casing 20 are abutted against the upper surface of the bridge pier cap 1, so that the steel casing 20 is hoisted to the corresponding installation position; S4.3: Embedded parts installation: The installer wears diving equipment and enters the steel casing 20 through the manhole and the ladder, inserts the fixing bolt 31 through the corresponding first through-hole on the inner side of the steel casing 20 and makes it threadedly connected with the fixing sleeve 3; S4.4: Repeat steps S4.1-S4.2 until the installation of the remaining intermediate steel casings 20 is completed.
[0050] S5: Repeat step S1.
[0051] S6: Hoisting of the closing section steel casing 20: The specific steps are as follows: S6.1: Installation of traction equipment: A support 6 is provided on the upper surface of the pier cap 1 facing the installation position of the closing section steel casing 20, and two sets of winches 61 are provided on the top of the support 6; in actual construction, the number of winches 61 can be increased or decreased according to actual needs; S6.2: Hoisting of the closing section steel casing 20: After the crane ship hoisting device is connected to the lifting lug 21 on the closing section steel casing 20 through a cable, the closing section steel casing 20 is hoisted into the expanded opening of the installation position of the closing section steel casing 20 by the crane ship and the bottom of the closing section steel casing 20 is raised above the water surface; so as to reduce the shaking of the closing section steel casing 20 caused by the waves, and at the same time facilitate the subsequent insertion of the hanging legs 4 of the closing section steel casing 20 into the corresponding hanging screws 41.
[0052] S6.3: Connection of traction equipment: Connect the cable of the hoist 61 to the lifting lug 21 on the upper surface of the closing section steel casing 20; S6.4: The closing section steel casing 20 is pulled by winding up the cables with two sets of winches 61 and cooperating with the crane ship to assist in moving the closing section steel casing 20, so as to pull the closing section steel casing 20 toward the pier cap 1 until the inner side of the closing section steel casing 20 abuts against the outer periphery of the pier cap 1; the closing section steel casing 20 is wedged into the corresponding installation position, so as to facilitate the rapid positioning of the closing section steel casing 20.
[0053] S6.5: The closing section steel casing 20 is placed in position: the closing section steel casing 20 is lowered by a crane ship, and the winch 61 is used to release the cable until the hanging legs 4 of the closing section steel casing 20 are hung on the corresponding hanging screws 41 through the hanging holes, and the limiting protrusions 22 of the closing section steel casing 20 are abutted against the upper surface of the pier cap 1, so that the closing section steel casing 20 is placed in position.
[0054] S6.6: Installation of embedded parts: The installer wears diving equipment and enters the closing section steel casing 20 through the manhole and the vertical ladder, inserts the fixing bolt 31 through the corresponding first through-hole on the inner side of the steel casing 20 and makes it threadedly connected with the fixing sleeve 3.
[0055] S7: Connect adjacent steel casings 20 through connecting parts. The specific steps are as follows: The installer wears diving equipment and enters the steel casing 20 through the manhole and the vertical ladder, and connects the splicing surfaces of the adjacent ends of the adjacent steel casings 20 through the connecting bolts 5 and the connecting nuts 51.
[0056] S8: Remove the traction equipment on the pier cap 1.
[0057] S9: Screw the locking nut 42 into the top end of the hanging screw 41.
[0058] The present application installs a number of steel casings 20 on the periphery of the pier cap 1, and utilizes the several steel casings 20 to form an annular anti-collision component 2 to maintain the pier cap 1, while reducing the occupation of the annular anti-collision component 2 on normal waters and reducing the impact of the annular anti-collision component 2 on the passage of ships. At the same time, the annular anti-collision component 2 is easy to disassemble and assemble as a whole, and is convenient for disassembly, assembly and replacement after subsequent damage.
[0059] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. A bridge pier cap steel casing anti-collision system, characterized by: The invention comprises an annular anti-collision component (2) arranged around the outer periphery of a bridge pier cap (1); the annular anti-collision component (2) is assembled from a plurality of steel casings (20); the steel casings (20) are fixed to the inner side of the bridge pier cap (1) by a plurality of embedded parts, and adjacent steel casings (20) are connected by a plurality of connecting parts; the inner cavity of the steel casing (20) is also vertically provided with a plurality of annular ribs (202), and the outer peripheral side of the annular ribs (202) is welded and fixed to the inner peripheral side of the steel casing (20); the splicing surfaces at both ends of the closed section steel casing (20) in the annular anti-collision component (2) form an outward expansion angle.
2. The bridge pier cap steel casing anti-collision system according to claim 1 is characterized by: The connecting member comprises a connecting bolt (5), the connecting bolt (5) is passed through the joint surface of the adjacent steel casing (20), and the tail end of the connecting bolt (5) is threadedly connected with a connecting nut (51); a plurality of manholes are opened on the top of the steel casing (20), and a plurality of straight ladders are arranged in the inner cavity of the steel casing (20) corresponding to the plurality of manholes, and the straight ladders extend to the bottom of the corresponding manholes.
3. The bridge pier cap steel casing anti-collision system according to claim 1 is characterized by: The embedded parts include a fixing sleeve (3) and a fixing bolt (31); the fixing sleeve (3) is embedded in the outer peripheral side of the pier cap (1), and the fixing bolt (31) is penetrated through the inner box wall of the steel casing (20) and is threadedly connected to the fixing sleeve (3).
4. The bridge pier cap steel casing anti-collision system according to claim 3 is characterized by: The top of the inner side of the steel casing (20) is provided with a plurality of limiting protrusions (22), and the bottom side of the limiting protrusions (22) and the side of the steel casing (20) facing the pier cap (1) are both in contact with the pier cap (1) via rubber pads (23).
5. The bridge pier cap steel casing anti-collision system according to claim 1 is characterized by: The steel casing (20) is provided with a plurality of water-permeable holes (201).
6. The bridge pier cap steel casing anti-collision system according to claim 4 is characterized by: The top of the inner side of the steel casing (20) is also vertically connected to a plurality of hanging legs (4), and the pier cap (1) is pre-embedded with a plurality of hanging screws (41) corresponding to the hanging legs (4), and the hanging legs (4) are all provided with hanging holes, and the hanging legs (4) are hung on the corresponding hanging screws (41) through the hanging holes.
7. A construction method for a bridge pier cap steel casing anti-collision system according to any one of claims 1 to 6, characterized in that: The following steps are involved: S1: Preparation work for hoisting and splicing of steel casing (20): Move the crane ship and the transport ship loaded with the steel casing (20) to the hoisting construction site and then drop anchor and position them: S2: Hoisting of the starting section steel casing (20): hoisting the starting section steel casing (20) on the transport ship to the installation position corresponding to the outer periphery of the bridge pier cap (1) by a crane ship, and fixing the starting section steel casing (20) on the outer side of the bridge pier cap (1) by embedded parts; S3: repeat step S1; S4: hoisting the intermediate steel casing (20): starting from the initial steel casing (20), in a clockwise or counterclockwise construction sequence, the corresponding intermediate steel casing (20) on the transport ship is hoisted to the corresponding installation position on the periphery of the bridge pier cap (1) by a crane ship, and then the intermediate steel casing (20) is fixed to the periphery of the bridge pier cap (1) by embedded parts; S5: repeat step S1; S6: Hoisting of the closing section steel casing: hoisting the closing section steel casing on the transport ship to the installation position corresponding to the outer periphery of the bridge pier cap (1) by a crane ship, and fixing the closing section steel casing (20) to the outer periphery of the bridge pier cap (1) by embedded parts; S7: Connect adjacent steel casings (20) via connecting pieces.
8. The construction method of the bridge pier cap steel casing anti-collision system according to claim 7 is characterized by: In step S6, the specific steps are as follows: S6.1: Installation of traction equipment: a plurality of winches (61) are supported on one side of the upper surface of the pier cap (1) facing the installation position of the closing section steel casing (20); S6.2: Hoisting of the closing section steel casing (20): hoisting the closing section steel casing (20) into the opening of the corresponding installation position by a crane ship and making the bottom of the closing section steel casing (20) higher than the water surface; S6.3: traction equipment connection: connect the cable of the hoist (61) to the upper surface of the closing section steel casing (20); S6.4: Pulling of the closing section steel casing (20): The closing section steel casing (20) is pulled in by the winch (61) while the cable is reeled in with the help of a crane ship to pull the closing section steel casing (20) toward the bridge pier cap (1) until the inner side of the closing section steel casing (20) abuts against the bridge pier cap (1); S6.5: The closing section steel casing (20) is placed in position: the closing section steel casing (20) is lowered by a crane ship until the closing section steel casing is completely placed in position; S6.6: The closing section steel casing (20) is fixed to the outer periphery of the pier cap (1) by means of embedded parts.
Citation Information
Patent Citations
SUPPORT PILLAR PROTECTION SYSTEM
BR102014008530A2
Passive ship collision prevention section and ship collision prevention buffer device applied to bridge structure
CN113216052A
Fabricated anti-collision facility for water area pier
CN113846606A
Anti-collision facility
CN115354623A
Pillar anti-collision device
CN116676924A