Bridge type integral traction movable template equipment

Through the design of bridge-type overall traction mobile formwork equipment, and the use of technical means such as guide rail frames, beam frames, and hoisting components, the problem of installation accuracy deviation caused by the weight of the formwork in the construction of tall and large concrete retaining wall formwork has been solved, and the quality of the concrete retaining wall has been improved. and construction safety.

CN118727749APending Publication Date: 2024-10-01CHINA RAILWAY 19 BUREAU GRP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410732606.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-06-07
Publication Date
2024-10-01

AI Technical Summary

Technical Problem

During the construction of high-size concrete retaining wall formwork, due to the heavy weight of the formwork, workers working at high altitudes and the narrow construction area, it is easy to cause deviations in the formwork installation accuracy and affect the quality of the concrete retaining wall.

Method used

A bridge-type overall traction mobile formwork equipment is designed, including guide rail frames, beam frames, lifting driving parts, hoisting components, tilt positioning components and wall-attached embedded parts. Through these components, the lifting and tilt positioning of the casting formwork can be realized to ensure that the formwork precise installation.

Benefits of technology

It effectively solves the problem of template installation accuracy deviation, improves the construction quality and construction safety of concrete retaining walls, and reduces the difficulty of workers' operations.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118727749A_ABST
    Figure CN118727749A_ABST
Patent Text Reader

Abstract

The invention relates to the field of building construction, in particular to bridge type integral traction moving formwork equipment which comprises a bridge body, a casting formwork, an inclined positioning assembly and a wall-attached embedded part, the bridge body comprises two guide rail frames and a cross beam frame, and the two guide rail frames are fixedly installed on the two sides of a retaining wall construction area; the cross beam frame is horizontally arranged, the casting formwork is hoisted at the bottom of the cross beam frame, the two sets of inclined positioning assemblies are installed on the two sets of guide rail frames correspondingly and used for positioning the inclined angle of the casting formwork, and the two sets of wall-attached embedded parts are fixedly installed at the bottoms of the two sets of guide rail frames correspondingly and used for being embedded in the bottommost layer of concrete retaining wall. By means of the bridge frame, the problems that when high and large-size concrete retaining wall formworks are constructed in the prior art, the weights of the formworks are large, the construction difficulty of workers is large, and the installation precision deviation of the formworks is likely to be caused, so that the pouring quality of concrete retaining walls is affected are solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of building construction, in particular to a bridge-type integral traction mobile template equipment. Background Art

[0002] During the construction of large-scale concrete retaining wall formworks for slope and foundation pit protection of existing highway, railway and housing construction projects, due to the heavy weight of large-scale concrete retaining wall steel formworks, workers are in a high-altitude working state when installing and reinforcing the formworks. At the same time, the narrow construction surface can easily cause deviations in the formwork installation accuracy and insufficient reinforcement, thus affecting the quality of concrete retaining wall pouring. Summary of the invention

[0003] The purpose of the present invention is to provide a bridge-type integral traction mobile formwork equipment, which is used to solve the problem that during the existing construction of high-sized concrete retaining wall formwork, due to the heavy weight of the formwork, workers are in a high-altitude working state when installing and reinforcing the formwork, and at the same time, the construction surface is narrow, which easily causes deviation in the formwork installation accuracy, thereby affecting the pouring quality of the concrete retaining wall.

[0004] To achieve the above object, the present invention provides a bridge-type integral traction mobile template equipment, comprising: The bridge frame body includes two sets of guide rail frames and a crossbeam frame. The two sets of guide rail frames are fixedly installed on both sides of the retaining wall construction area. The crossbeam frame is horizontally arranged, and its two ends are respectively slidably connected with the two sets of guide rail frames. A set of lifting driving parts are respectively installed at both ends of the crossbeam frame, and the two sets of lifting driving parts drive the crossbeam frame to rise and fall; The casting template is hoisted at the bottom of the beam frame, and a hoisting assembly is fixedly installed at the bottom of the beam frame, and the casting template is driven by the hoisting assembly to rise and fall. The tilt positioning assembly is in two groups and is respectively installed on two groups of guide rail frames, including an electric sliding seat, a positioning arm and a positioning rod. The electric sliding seat is slidably installed on the guide rail frame, one end of the positioning arm is rotatably connected to the electric sliding seat, and the other end is provided with a mounting hole. The two ends of the positioning rod are respectively fixedly connected to the two groups of positioning holes. Positioning ring buckles for the positioning rod to pass through are provided on both sides of the bottom of the casting template. The electric sliding seat is provided with a driving member for driving the positioning arm to rotate; There are two sets of wall-attached embedded parts, which are fixedly installed at the bottom of the two sets of guide rail frames respectively. The two sets of wall-attached embedded parts are used to be buried in the bottom concrete retaining wall to assist in fixing the bottom of the bridge frame body.

[0005] As a further solution of the present invention, a guide rail frame foundation is constructed at the bottom of the guide rail frame, and the bottom of the guide rail frame is fixedly connected to the guide rail frame foundation through a fixed steel plate.

[0006] As a further solution of the present invention, the lifting drive member is an electric sliding unit, and the guide rail frame is provided with a guide groove for the electric sliding unit to slide.

[0007] As a further solution of the present invention, the hoisting assembly includes multiple groups of electric hoists, which are arranged in sequence along the long side direction of the beam frame, and their hanging ropes are fixedly connected to the upper end of the casting template.

[0008] As a further solution of the present invention, the wall-attached embedded part includes a wall-attached embedded limiting groove, and the wall-attached embedded limiting groove can be detachably mounted on the guide rail frame.

[0009] As a further solution of the present invention, the driving member is an electric telescopic cylinder, one end of which is rotatably mounted on an electric sliding seat, and the other end of which is hinged to the middle of the positioning arm.

[0010] Compared with the prior art, the present invention sets a bridge frame body composed of two groups of guide rail frames and a crossbeam frame as the main support frame, and hoisted the casting template at the bottom of the crossbeam frame, and is driven to lift and lower by the hoisting assembly. The casting template is hoisted to a preset height by driving the crossbeam frame to lift and lower and cooperate with the hoisting assembly. At the same time, the position of the positioning rod is adjusted by the positioning arm, and the bottom of the bottom casting template is adjusted to realize the adjustment of the inclination angle of the casting template in the hanging state, so as to solve the problem that when constructing high-sized concrete retaining wall templates, the template is heavy, the construction is difficult for workers, and it is easy to cause template installation accuracy deviation, thereby affecting the casting quality of the concrete retaining wall. BRIEF DESCRIPTION OF THE DRAWINGS

[0011] Figure 1 It is a structural schematic diagram of a bridge-type integral traction mobile template equipment of the present invention.

[0012] Figure 2 It is a schematic structural diagram of the tilt positioning assembly of the present invention.

[0013] In the attached drawings: 1. guide rail frame; 2. crossbeam frame; 3. electric sliding unit; 4. electric hanging hoist; 5. casting formwork; 6. pre-embedded limit groove attached to the wall; 7. retaining wall foundation; 8. retaining wall; 9. guide rail frame foundation; 10. electric sliding seat; 11. positioning arm; 12. positioning rod; 13. positioning ring buckle; 14. electric telescopic rod. DETAILED DESCRIPTION

[0014] The technical solution of the present invention is further described in detail below in conjunction with specific implementation methods.

[0015] like Figure 1 and Figure 2 As shown, in an embodiment of the present invention, a bridge-type integral traction mobile template equipment comprises: The bridge frame body includes two sets of guide rail frames 1 and a crossbeam frame 2. The two sets of guide rail frames 1 are fixedly installed on both sides of the construction area of ​​the retaining wall 8. The crossbeam frame 2 is horizontally arranged, and its two ends are respectively slidably connected with the two sets of guide rail frames 1. A set of lifting driving parts are respectively installed at both ends of the crossbeam frame 2, and the two sets of lifting driving parts drive the crossbeam frame 2 to rise and fall; The casting template 5 is hoisted at the bottom of the beam frame 2. A hoisting assembly is fixedly installed at the bottom of the beam frame 2. The casting template 5 is lifted and lowered by the hoisting assembly. The tilt positioning assembly is in two groups and is respectively installed on two groups of guide rail frames 1, including an electric sliding seat 10, a positioning arm 11 and a positioning rod 12. The electric sliding seat 10 is slidably installed on the guide rail frame 1. One end of the positioning arm 11 is rotatably connected to the electric sliding seat 10, and the other end is provided with a mounting hole. The two ends of the positioning rod 12 are respectively fixedly connected to the two groups of positioning holes. The bottom of the casting template 5 is provided with positioning ring buckles 13 for the positioning rod 12 to pass through. The electric sliding seat 10 is provided with a driving member for driving the positioning arm 11 to rotate; There are two sets of wall-attached embedded parts, which are fixedly installed at the bottom of two sets of guide rail frames 1 respectively. The two sets of wall-attached embedded parts are used to be buried in the bottom concrete retaining wall 8 to assist in fixing the bottom of the bridge frame body.

[0016] During the construction of the present invention, according to the construction specifications of the retaining wall 8, the bridge frame body is erected in the construction area, and the casting template 5 is moved to the bottom of the bridge frame body, and the beam frame 2 is driven to slide down along the direction defined by the two sets of guide rail frames 1 through two sets of lifting driving members, and the casting template 5 is connected to the hanging assembly installed at the bottom of the beam frame 2, and the casting template 5 is driven to rise and fall through the hanging assembly to adjust the installation height of the casting template 5. At the same time, after the casting template 5 is hung and installed in place, the placement angle of the casting template 5 is positioned by the tilting positioning assembly to make it adapt to the casting slope of the retaining wall 8; The wall-attached embedded parts installed at the bottom of the two sets of guide rail frames 1 and the bottom layer of cast concrete are cast to improve the construction safety of casting.

[0017] like Figure 1 As shown, in the embodiment of the present invention, a guide rail frame foundation 9 is constructed at the bottom of the guide rail frame 1, and the bottom of the guide rail frame 1 is fixedly connected to the guide rail frame foundation 9 by a fixed steel plate. At the same time, when the retaining wall 8 is constructed, the retaining wall foundation 7 also needs to be constructed at the bottom of the retaining wall 8 construction area. When the bottom retaining wall 8 is constructed, the casting template 5 is hoisted and lowered to the retaining wall foundation 7 by the hoisting assembly for placement.

[0018] like Figure 1As shown, in the embodiment of the present invention, the lifting drive member is an electric sliding unit 3, and the guide rail frame 1 is provided with a guide groove for the electric sliding unit 3 to slide. The present invention preferably drives the crossbeam frame 2 to lift in the vertical direction, and then cooperates with the lifting assembly to adjust the positioning height of the casting template 5. Of course, in actual design, the electric sliding unit 3 can also be preferably replaced by other components with vertical driving capabilities, such as a gear rack linear drive assembly, etc. Furthermore, the hoisting assembly includes multiple groups of electric hanging hoists 4, and the multiple groups of electric hanging hoists 4 are arranged in sequence along the long side direction of the crossbeam frame 2, and their hanging ropes are fixedly connected to the upper end of the casting template 5. The upper side of the casting template 5 is provided with a buckle fixedly connected to the end of the hanging rope. In the present invention, the multiple groups of electric hanging hoists 4 are controlled by a controller and the hanging operation is performed simultaneously to realize the hanging support of the casting template 5.

[0019] like Figure 1 As shown, in the embodiment of the present invention, the wall-mounted embedded component includes a wall-mounted embedded limiting groove 6 , and the wall-mounted embedded limiting groove 6 can be detachably mounted on the guide rail frame 1 .

[0020] like Figure 1 and Figure 2 As shown, the driving member is an electric telescopic cylinder 14, one end of which is rotatably mounted on the electric sliding seat 10, and the other end is hinged to the middle of the positioning arm 11. The positioning arm is driven to rotate by its telescopic movement to adjust the extension stroke of the positioning rod 12. At the same time, the electric sliding seat 10 is lifted and slid to position the final position of the positioning rod.

[0021] To sum up the above, the present invention sets a bridge frame body composed of two groups of guide rail frames 1 and a beam frame 2 as the main support frame, and hoisted the casting template 5 at the bottom of the beam frame 2, and is driven to lift by the hoisting assembly. The casting template 5 is hoisted to a preset height by driving the beam frame 2 to lift and cooperate with the hoisting assembly. At the same time, the position of the positioning rod 12 is adjusted by the positioning arm 11, and the bottom of the bottom casting template 5 is adjusted to realize the adjustment of the inclination angle of the hanging casting template 5, so as to solve the problem that when constructing the existing high-sized concrete retaining wall 8 template, the template is heavy, the construction is difficult for workers, and it is easy to cause the template installation accuracy deviation, thereby affecting the casting quality of the concrete retaining wall 8.

[0022] The preferred embodiments of the present invention are described in detail above, but the present invention is not limited to the above embodiments. Various changes can be made within the knowledge scope of ordinary technicians in this field without departing from the purpose of the present invention.

Claims

1. A bridge-type integral traction mobile template equipment, characterized in that: include: The bridge frame body includes two sets of guide rail frames and a crossbeam frame. The two sets of guide rail frames are fixedly installed on both sides of the retaining wall construction area. The crossbeam frame is horizontally arranged, and its two ends are respectively slidably connected with the two sets of guide rail frames. A set of lifting driving parts are respectively installed at both ends of the crossbeam frame, and the two sets of lifting driving parts drive the crossbeam frame to rise and fall; The casting template is hoisted at the bottom of the beam frame, and a hoisting assembly is fixedly installed at the bottom of the beam frame, and the casting template is driven by the hoisting assembly to rise and fall. The tilt positioning assembly is in two groups and is respectively installed on two groups of guide rail frames, including an electric sliding seat, a positioning arm and a positioning rod. The electric sliding seat is slidably installed on the guide rail frame, one end of the positioning arm is rotatably connected to the electric sliding seat, and the other end is provided with a mounting hole. The two ends of the positioning rod are respectively fixedly connected to the two groups of positioning holes. Positioning ring buckles for the positioning rod to pass through are provided on both sides of the bottom of the casting template. The electric sliding seat is provided with a driving member for driving the positioning arm to rotate; There are two sets of wall-attached embedded parts, which are fixedly installed at the bottom of the two sets of guide rail frames respectively. The two sets of wall-attached embedded parts are used to be buried in the bottom concrete retaining wall to assist in fixing the bottom of the bridge frame body.

2. The bridge-type integral traction mobile template equipment according to claim 1 is characterized in that: A guide rail frame foundation is constructed at the bottom of the guide rail frame, and the bottom of the guide rail frame is fixedly connected to the guide rail frame foundation through a fixed steel plate.

3. The bridge-type integral traction mobile template equipment according to claim 1 is characterized in that: The lifting drive member is an electric sliding unit, and the guide rail frame is provided with a guide groove for the electric sliding unit to slide.

4. The bridge-type integral traction mobile template equipment according to claim 1 is characterized in that: The hoisting assembly comprises a plurality of groups of electric hoists, which are arranged in sequence along the long side direction of the crossbeam frame, and the hoisting ropes thereof are fixedly connected to the upper end of the casting template.

5. The bridge-type integral traction mobile template equipment according to claim 1 is characterized in that: The wall-attached embedded part comprises a wall-attached embedded limiting groove, and the wall-attached embedded limiting groove can be detachably mounted on the guide rail frame.

6. The bridge-type integral traction movable template equipment according to claim 1 is characterized in that: The driving member is an electric telescopic cylinder, one end of which is rotatably mounted on an electric sliding seat, and the other end of which is hinged to the middle of the positioning arm.