Cast-in-place pile embedded pipeline drainage device and drainage method
By using a compressed gas-driven drainage device in the cast-in-place pile embedded pipeline, the problem of rapid drainage during the detection period of cast-in-place pile concrete hydration heat is solved, the efficiency of cast-in-place pile quality inspection and defect processing speed are improved, and energy consumption and Construction costs.
Patent Information
- Application Number
- CN202411104099.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-13
- Publication Date
- 2024-10-01
AI Technical Summary
The existing technology makes it difficult to quickly drain the embedded pipes during the hydration heat detection period of cast-in-place pile concrete, resulting in delayed defect detection and affecting the quality assessment and repair of cast-in-place piles.
A cast-in-place pile embedded pipe drainage device is designed. It uses compressed gas as a power source to drive the discharge of water through air pressure to achieve rapid drainage. It includes a cover body, a drainage pipe and an air inlet pipe. The cover body is sealed and connected with the embedded pipe. Tracheal ventilation pump uses air pump to pressurize to achieve drainage.
It achieves rapid drainage, shortens the lead time for quality inspection of cast-in-place piles, improves the processing speed of cast-in-place pile quality defects, and reduces energy consumption and construction costs.
Smart Images

Figure CN118727796A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of bored pile quality detection, and in particular to a bored pile pre-buried pipeline drainage device and a drainage method. Background Art
[0002] Bored piles are one of the foundation forms widely used in industrial and civil construction, municipal transportation and other infrastructure construction. With the increasing requirements for pile foundation bearing capacity in marine engineering construction and super high-rise buildings, super large ports, docks, bridges and other projects, super long and large diameter bored piles are widely used. The construction quality of bored piles is a key factor in determining the use and safety performance of the upper building structure. The quality inspection of bored piles is an important link in controlling the quality of the project. Due to the characteristics of the pile-making process and the complexity of geological conditions, the quality of bored piles is not easy to control and guarantee. It is easy to have broken piles, necking, segregation, exposed reinforcement and mud inclusion during the pouring of concrete. Therefore, it is necessary to evaluate the quality of bored piles.
[0003] Mullins G and Winters D proposed a method for detecting the quality of bored piles based on the heat of concrete hydration. The temperature field generated by the heat of concrete hydration is closely related to the bored pile body and the soil around the bored pile. Using this method theory, the quality of the bored pile body can be detected and analyzed earlier and more comprehensively, including the quality of the concrete protective layer inside and outside the steel cage. It can be intervened within 48 hours after pouring to detect defects as early as possible for subsequent treatment.
[0004] In the pile body quality monitoring method using concrete hydration heat, it is necessary to pre-buried a detection pipe in the cast-in-place pile body, and the pre-buried pipe needs to be injected with water before pouring concrete to balance the pressure difference inside and outside the pre-buried pipe. However, temperature field detection requires draining the water in the pre-buried pipe. Therefore, a device that can achieve rapid drainage is urgently needed.
[0005] This section merely provides background information related to the present application and is not necessarily prior art. Summary of the invention
[0006] One of the purposes of the present invention is to avoid the shortcomings of the prior art and provide a bored pile pre-buried pipe drainage device, which aims to quickly drain the pre-buried pipe and ensure that temperature field detection can be carried out during the concrete hydration heat detection period, so that the detected defects can be dealt with as early as possible.
[0007] A second object of the present invention is to provide a drainage method using a pre-buried pipe drainage device with cast-in-place piles.
[0008] One of the purposes of the present invention is achieved through the following technical solutions:
[0009] Provided is a cast-in-place pile pre-buried pipeline drainage device, comprising a cover body, a drainage pipe and an air inlet pipe, wherein the cover body is sealed and connected to the pre-buried pipeline, the drainage pipe is inserted on the cover body and is sealed and connected to the cover body, one end of the drainage pipe penetrates into the bottom of the pre-buried pipeline, the air inlet pipe is connected to the cover body, and the air inlet pipe is used to input an air pressure.
[0010] In a possible implementation of the first aspect above, a pressure relief valve is further provided on the cover body.
[0011] In a possible implementation of the first aspect above, it also includes an exhaust valve, an air storage tank and an air pump which are sequentially connected to the air intake pipe, and the top of the air storage tank is also provided with a vent valve for pressure relief and a pressure gauge for detecting air pressure.
[0012] In a possible implementation of the first aspect above, it also includes a vehicle body and a processing device, the air pump and the air storage tank are fixed on the vehicle body, and the processing device is used to control the air pump to pressurize the air storage tank according to the size and depth of the pre-buried pipeline.
[0013] In a possible implementation of the first aspect above, the cover body is provided with a drainage hole and an air inlet hole, both ends of the drainage hole are provided with drainage joints, the drainage pipe is connected to the drainage joints, and the air inlet hole is provided with an air inlet joint, and the air inlet pipe is connected to the air inlet joint.
[0014] In a possible implementation of the first aspect above, the cover body is threadedly connected to the pre-buried pipe, and an annular sealing ring is further provided in the cover body, and the annular sealing ring is located between the cover body and the pre-buried pipe.
[0015] In a possible implementation of the first aspect, a filter box is provided at the terminal pipe opening of the drain pipe, a filter mesh for filtering is provided inside the filter box, and the filter box radially increases outward at one end away from the drain pipe.
[0016] In a possible implementation of the first aspect, the filter screen is formed by metal wires wound together, and the pores of the filter screen increase from the terminal pipe of the drain pipe toward the outside.
[0017] In a possible implementation of the first aspect above, the drainage pipe includes a plurality of vertical pipes and a hollow clamp ring; annular flanges are provided on the outer peripheries of both ends of the vertical pipes, the hollow clamp ring has two relatively free ends, adjacent vertical pipes are connected via the hollow clamp ring, a groove for clamping the annular flange is further provided in the hollow clamp ring, an annular rubber ring is further provided on the inner circumferential wall of the hollow clamp ring, adjacent vertical pipes are connected via the hollow clamp ring, and the two free ends are connected via bolts.
[0018] The present invention provides a pre-buried pipe drainage device for a bored pile, which has the following beneficial effects:
[0019] The bored pile pre-buried pipe drainage device provided by the present invention uses compressed gas as the power source for drainage through a sealed connection between a cover body and the pre-buried pipe. The compressed gas in the pre-buried pipe does work on water through gas expansion, and the internal energy is converted into mechanical energy of water, thereby achieving drainage. The air pressure is used as the power source for drainage. If the air pressure is greater than the water pressure in the pre-buried pipe, work can be continuously done on the water, and the water can be drained efficiently, so as to facilitate subsequent bored pile quality inspection and improve the intervention speed for bored pile quality defects.
[0020] The second object of the present invention is achieved by the following technical solutions:
[0021] A drainage method using the above-mentioned bored pile pre-buried pipe drainage device is provided, wherein the above-mentioned bored pile pre-buried pipe drainage device is installed on the port of the pre-buried pipe, one end of the drainage pipe penetrates into the bottom of the pre-buried pipe, and the other end extends to the drainage point, the air inlet pipe is connected to the air pump, and the air pump is started to pressurize the cover body so that the pressure in the cover body is greater than the pressure of the water in the pre-buried pipe, thereby achieving drainage; after the drainage is completed, the bored pile pre-buried pipe drainage device is recovered.
[0022] The drainage method provided by the present application may have the following beneficial effects:
[0023] (1) No compressed air is wasted during drainage, and the device for delivering compressed air does not need to run for a long time, which can greatly save energy.
[0024] (2) The drainage device has a simple structure, low cost, simple and convenient operation, simple installation and low construction cost. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] The above and other objects, features and advantages of the present application will become more apparent through a more detailed description of exemplary embodiments of the present application in conjunction with the accompanying drawings, wherein the same reference numerals generally represent the same components in the exemplary embodiments of the present application.
[0026] Figure 1 It is a structural schematic diagram of a cast-in-place pile pre-buried pipeline drainage device shown in an embodiment of the present application;
[0027] Figure 2 It is another structural schematic diagram of the cast-in-place pile pre-buried pipeline drainage device shown in the embodiment of the present application;
[0028] Figure 3 It is a schematic diagram of the structure of the gas storage tank shown in the embodiment of the present application;
[0029] Figure 4 is a schematic structural diagram of a vehicle body shown in an embodiment of the present application;
[0030] Figure 5 is a cross-sectional view of a filter box shown in an embodiment of the present application;
[0031] Figure 6 It is a schematic diagram of the assembly of the hollow clamp ring and the riser shown in the embodiment of the present application.
[0032] Reference numerals:
[0033] 1. Pre-buried pipeline; 10. Cover; 11. Drain pipe; 12. Air intake pipe; 13. Pressure relief valve; 14. Air intake valve; 15. Air storage tank; 16. Air pump; 17. Vent valve; 18. Pressure gauge; 19. Vehicle body; 20. Drain connector; 21. Air intake connector; 22. Filter box; 110. Vertical pipe; 111. Hollow clamp ring. DETAILED DESCRIPTION
[0034] The preferred embodiments of the present application will be described in more detail below with reference to the accompanying drawings. Although the preferred embodiments of the present application are shown in the accompanying drawings, it should be understood that the present application can be implemented in various forms and should not be limited by the embodiments described herein. On the contrary, these embodiments are provided to make the present application more thorough and complete, and to fully convey the scope of the present application to those skilled in the art.
[0035] In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operate in a specific orientation, and therefore should not be understood as a reference to the present invention.
[0036] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0037] In the prior art, the traditional detection methods for cast-in-place concrete piles are low-strain reflection wave method, cross-hole ultrasonic method, and core extraction method. However, the above detection methods have two shortcomings. The first is that the quality inspection can only be carried out after the concrete reaches a certain strength (generally not less than 7 days). When defects are found, it is difficult to repair the pile body; the second is that it can only detect the quality of concrete inside the steel cage of the cast-in-place pile, but cannot detect the quality of concrete outside the steel cage.
[0038] During the process of testing the quality of bored piles, the inventors found that bored piles are often deep, and external water pumps cannot pump water deeper than 10 meters. Bottom-mounted water pumps are too large to be placed in pre-buried pipes, making it difficult to meet the needs of rapid drainage of pre-buried pipes of various depths.
[0039] Therefore, in order to adapt to the bored pile quality inspection method based on concrete hydration heat, the inventor of the present application designed a device capable of quickly achieving drainage and a drainage method using the device.
[0040] In response to the above problems, the embodiments of the present application provide a bored pile pre-buried pipe drainage device and drainage method, which are intended to quickly drain the pre-buried pipe 1 and ensure that temperature field detection can be carried out during the concrete hydration heat detection period, so as to deal with the detected defects as soon as possible.
[0041] In a typical embodiment of the present invention, a pre-buried pipe drainage device for bored piles is provided, which uses compressed gas as a power source for drainage, continuously performs work on water through the expansion of the compressed gas itself, converts the internal energy of the compressed gas into the mechanical energy of water, and achieves rapid drainage. It can shorten the lead-in working time for bored pile quality inspection so that subsequent bored pile quality inspection can be carried out as soon as possible, thereby improving the processing speed of bored pile quality defects.
[0042] In one embodiment of the present invention, please refer to Figure 1 and Figure 2 , provides a cast-in-place pile pre-buried pipeline drainage device, including a cover body 10, a drainage pipe 11 and an air intake pipe 12, the cover body 10 is sealed and connected to the pre-buried pipeline 1, the drainage pipe 11 is inserted on the cover body 10 and is sealed and connected to the cover body 10, one end of the drainage pipe 11 penetrates into the bottom of the pre-buried pipeline 1, the air intake pipe 12 is connected to the cover body 10, and the air intake pipe 12 is used to input an air pressure.
[0043] Cast-in-place piles are one of the commonly used construction techniques for building bridge foundations. The use of cast-in-place pile technology can not only penetrate various unfavorable strata and place the foundation on a base with better bearing capacity, but also can be constructed underwater and reinforced by pouring concrete, thereby improving the bearing capacity of the foundation.
[0044] Generally speaking, the construction process of bored piles can be divided into several parts, including burying casing, drilling, making and installing steel cage, cleaning hole, processing and installing concrete pouring conduit, pouring concrete and quality inspection. The above construction process belongs to the existing technology, and its specific work flow and construction instructions will not be repeated here.
[0045] In the embodiment of the present application, the pre-buried pipe 1 of the cast-in-place pile pre-buried pipe drainage device needs to be installed on the steel cage so that it can be buried in the hole along with the steel cage. In the process of manufacturing the steel cage, according to the diameter of the steel cage, at least two spaced pipes, such as steel pipes, are installed on the steel cage along the axis of the steel cage, and the pipes are fixed by tie bands or steel wires to ensure that the pipe mouth of the pre-buried pipe 1 is higher than the end face of the steel cage, so as to ensure that the pipe mouth of the pre-buried pipe 1 can be exposed in the concrete after pouring the concrete, so that the cover body 10 can be installed smoothly.
[0046] In the prior art, it is generally necessary to install an acoustic detection tube in the steel cage to facilitate another quality inspection of the bored piles. In this embodiment, the acoustic detection tube can be set separately, or the pre-buried pipeline 1 can be used as a carrier for the quality inspection.
[0047] In the embodiment of the present application, the structural shape of the cover body 10 is not limited, and it is only necessary to ensure that the chamber inside the cover body 10 can be sealed and connected with the embedded pipe 1. The embedded pipe 1 is a cylindrical prefabricated steel pipe, and the chamber inside the cover body 10 is also cylindrical. The connection between the cover body 10 and the embedded pipe 1 can be sealed by threads or by flanges. The material of the cover body 10 can be metal, such as iron, aluminum, or plastic, such as polycarbonate and nylon. The top wall or side wall of the cover body 10 can be connected to the drain pipe 11 and the air inlet pipe 12. After the drain pipe 11 is connected to the cover body 10, one end of the drain pipe 11 penetrates into the bottom of the embedded pipe 1 to ensure that all the accumulated water in the embedded pipe 1 can be discharged. Compressed air (i.e., one air pressure) is input through the air inlet pipe 12, and the sealed space formed between the cover body 10 and the embedded pipe 1 is pressurized by the compressed air. When the pressure is greater than the water pressure of the embedded pipe 1, the water can be discharged from the drain pipe 11.
[0048] After the water in the pre-buried pipe 1 is basically drained, the temperature probe can be inserted into the pre-buried pipe 1 to collect the temperature of the pre-buried pipe 1, and then the temperature distribution of the pile body is inverted to realize the temperature field detection of the cast-in-place pile. After completing the temperature field detection, the pre-buried pipe 1 remains in the cast-in-place pile.
[0049] It needs to be explained that the purpose of installing the embedded pipe 1 in the steel cage and injecting water into the embedded pipe 1 is to balance the pressure difference inside and outside the embedded pipe 1, to avoid the poured concrete from squashing the embedded pipe 1 and causing it to lose its function as a temperature field detection carrier. The bored pile quality detection method based on concrete hydration heat generally uses an infrared temperature sensor. If the temperature field detection is performed without drainage, the detection result is easily distorted. Water has a certain thermal conductivity. The heat generated by the concrete during the hydration heat is transferred to the embedded pipe 1, and the heat will diffuse through the water. At the same time, the temperature sensor disturbs the water in the embedded pipe 1 during the lowering process, causing it to undergo a stronger Brownian motion, diffusing heat, resulting in a uniform temperature effect in the embedded pipe 1, which greatly interferes with the acquisition accuracy of the temperature sensor and affects the accuracy of the test results.
[0050] It should be noted that those skilled in the art can input a minimum air pressure P into the air intake pipe 12 according to the actual depth of the pre-buried pipe 1. The calculation method of the minimum working rated value can refer to the following calculation formula: the depth distance H from the top to the bottom of the pre-buried pipe 1 is obtained, the water density ρ and the gravity acceleration g are known, and the minimum air pressure input into the air intake pipe 12 is calculated as:
[0051] P=ρgH
[0052] By way of example, in order to facilitate those skilled in the art to understand the specific meaning of the above calculation formula, the depth dimensions of the pre-buried pipeline 1 of 10 meters, 20 meters, and 30 meters are given as examples below.
[0053] When the depth of the pre-buried pipeline 1 is 10 meters, the minimum air pressure is 0.1 MPa.
[0054] When the depth of the pre-buried pipeline 1 is 20 meters, the minimum air pressure is 0.2 MPa.
[0055] When the depth of the pre-buried pipeline 1 is 30 meters, the minimum air pressure is 0.3 MPa.
[0056] It should be noted that this calculation is based on ideal theoretical conditions, and in reality the minimum air pressure will be increased by other factors, such as friction in the pipeline and the impurity content in the water.
[0057] In a preferred embodiment of the present invention, a pressure relief valve 13 is further provided on the cover 10 of the above-mentioned cast-in-place pile pre-buried pipeline drainage device. After the drainage is completed, the exhaust valve is closed, and the pressure relief valve 13 is opened to relieve the pressure of the pre-buried pipeline 1, so that the drainage device can be quickly disassembled and installed in the next pre-buried pipeline 1.
[0058] In a preferred embodiment of the present invention, please refer to Figure 3The above-mentioned cast-in-place pile pre-buried pipeline drainage device also includes an exhaust valve, an air storage tank 15 and an air pump 16 which are sequentially connected to the air inlet pipe 12. The top of the air storage tank 15 is also provided with a vent valve 17 for pressure relief and a pressure gauge 18 for detecting air pressure.
[0059] The number of pre-buried pipes 1 can be set according to the diameter of the pile body of the bored pile, which can be two, three or more than four. The pre-buried pipes 1 are distributed on the steel cage at intervals to collect the temperature field distribution of the bored pile body. Therefore, in order to adapt to the needs of on-site construction and speed up the completion of the drainage work of each pre-buried pipe 1, the high-pressure gas is stored in the gas tank 15 to achieve rapid pressurized drainage, which saves the time for the air pump 16 to pressurize the pre-buried pipe 1 and improves work efficiency. Under the action of the air pump 16, the air pressure of the gas tank 15 can be maintained in a stable range. The high-pressure gas stored in the gas tank 15 is used as the power source for drainage, which can maintain a fast and stable drainage function. After the cover body 10 is installed in the pre-buried pipe 1, the high-pressure gas is delivered to the pre-buried pipe 1 by opening the exhaust valve, so that the chamber pressure formed between the cover body 10 and the pre-buried pipe 1 is greater than the hydraulic pressure of the water column, and the compressed gas converts the internal energy into the kinetic energy of water through its own expansion to achieve drainage.
[0060] In this embodiment, the pressure change of the compressed gas is related to the amount of water discharged, and the gas storage tank 15 can quickly deliver high-compression gas to the pre-buried pipeline 1 to pressurize the pre-buried pipeline 1 to achieve rapid drainage, thereby eliminating the time for the air pump 16 to pressurize the pre-buried pipeline 1, improving work efficiency, and saving energy. The air pump 16 can be powered by mains electricity or a generator.
[0061] When one of the pre-buried pipes 1 has completed drainage, the drainage device can be disassembled and installed in another pre-buried pipe 1. The pre-buried pipe 1 is quickly pressurized by the gas storage tank 15 to achieve rapid drainage.
[0062] In this embodiment, an air storage tank 15 is added to the pre-buried pipe drainage device of the bored pile, so that the pre-buried pipe 1 can be quickly drained, which can greatly shorten the lead time of temperature field detection and facilitate faster intervention and processing.
[0063] In a preferred embodiment of the present invention, in order to facilitate the management and maintenance of the drainage device so that it can be easily transported and installed on a construction site with a complex road surface, a corresponding structure is also designed in the embodiment of the present application on the basis of the above specific implementation method, please refer to Figure 4 The above-mentioned cast-in-place pile pre-buried pipeline drainage device also includes a vehicle body 19 and a processing device. The air pump 16 and the air storage tank 15 are fixed on the vehicle body 19. The processing device is used to control the air pump 16 to pressurize the air storage tank 15 according to the size and depth of the pre-buried pipeline 1.
[0064] The vehicle body 19 can be a vehicle with a cargo box such as an electric tricycle, a truck or a pickup truck. The gas tank 15 and the air pump 16 are placed on the vehicle body 19, and the drainage pipe 11, the air intake pipe 12 and other parts can be placed on the vehicle body 19, so that the operator can install and disassemble them in an orderly manner to avoid random accumulation at the construction site and affect the normal work of other personnel. After completing the installation of the drainage device, the construction personnel input the depth of the pre-buried pipeline 1 into the controller, and the processing device can obtain the depth information, collect the pressure data of the gas tank 15 through the pressure gauge 18, and automatically start and shut down the air pump 16 according to the preset value of the pressure, so as to ensure the pressure of the compressed gas delivered during drainage and avoid excessive work of the air pump 16.
[0065] In the above-mentioned drainage device, the pressure of the air storage tank 15 is pressurized to a set value by the air pump 16. Usually, the set value is 1.1 to 2 times the water column pressure.
[0066] In a preferred embodiment of the present invention, a drainage hole and an air inlet are provided on the cover body 10 of the above-mentioned cast-in-place pile pre-buried pipeline drainage device, drainage joints 20 are provided at both ends of the drainage hole, the drainage pipe 11 is connected to the drainage joint 20, the air inlet hole is provided with an air inlet joint 21, and the air inlet pipe 12 is connected to the air inlet joint 21. The drainage hole and the air inlet are provided on the cover body 10, and the drainage joint 20 is provided on the drainage hole, and the air inlet joint 21 is provided on the air inlet hole, so that the drainage pipe 11 and the air inlet pipe 12 are easily disassembled, so as to ensure that the drainage device can be stored in a smaller space, thereby improving the portability of the drainage device.
[0067] In a preferred embodiment of the present invention, the cover body 10 of the above-mentioned cast-in-place pile pre-buried pipe drainage device is threadedly connected to the pre-buried pipe 1, and an annular sealing ring is also provided in the cover body 10, and the annular sealing ring is located between the cover body 10 and the pre-buried pipe 1.
[0068] Specifically, after the cover body 10 and the embedded pipe 1 are sealed and connected multiple times by threaded connection, the connection between the cover body 10 and the embedded pipe 1 may fail to seal. Therefore, a waterproof cloth is set on the threaded end of the embedded pipe 1 or an annular sealing ring is set on the inner wall of the cover body 10 to ensure that the cover body 10 can still maintain an effective seal after being connected to the embedded pipe 1 multiple times. The embedded pipe 1 is made of prefabricated standard steel pipes, and the sections are connected by crimping rings. The embedded pipe 1 is placed at the construction site. During the transportation or dragging process, mud and stones will enter the pipe, resulting in stones blocking the drain pipe 11 when draining. Therefore, in order to avoid stones and other impurities blocking the drain pipe 11, the embodiment of the present application is based on the above-mentioned specific implementation method. A filter box 22 is set at the end of the drain pipe 11. A filter screen for filtering is set in the filter box 22. The filter box 22 is radially enlarged outward at the end away from the drain pipe 11. The pore characteristics of the filter screen are used to prevent stones and other impurities from entering the drain pipe 11.
[0069] Based on the above specific implementation methods, please refer to Figure 5 The filter screen is formed by metal wires intertwined with each other, and the pores of the filter screen increase from the end pipe of the drain pipe 11 outward. The sizes of the two ends of the filter box are different, and the pore size of the filter screen is set according to the sizes of the two ends of the filter box 22. Under this setting, larger stones are blocked by larger pores and will not block small pores, so that the filter screen can perform filtering work for a long time. After the drainage is completed and the drain pipe is pulled out, most of the stones on the filter screen can fall back onto the pre-buried pipe 1.
[0070] In a preferred embodiment of the present invention, please refer to Figure 6 The drainage pipe 11 of the above-mentioned cast-in-place pile pre-buried pipeline drainage device includes multiple vertical pipes 110 and a hollow clamp ring 111; annular flanges are provided on the outer periphery of both ends of the vertical pipe 110, and the hollow clamp ring 111 has two free ends arranged oppositely, and the adjacent vertical pipes 110 are connected by the hollow clamp ring 111, and a groove for clamping the annular flange is also provided in the hollow clamp ring 111, and an annular rubber ring is also provided on the inner peripheral wall of the hollow clamp ring 111, and the adjacent vertical pipes 110 are connected by the hollow clamp ring 111, and the two free ends are connected by bolts. The drainage pipe 11 is connected between multiple vertical pipes 110, so that a single person can also realize the assembly operation, and it has the advantage of convenient transportation.
[0071] The various embodiments in this specification are described in a progressive manner, and each embodiment focuses on the differences from other embodiments. The same or similar parts between the various embodiments can be referenced to each other.
[0072] The embodiment of the second aspect of the present invention provides a drainage method of a cast-in-place pile pre-buried pipeline drainage device, specifically:
[0073] The drainage pipe 11 is installed on the pre-buried pipe 1, with one end of the drainage pipe 11 penetrating into the bottom of the pre-buried pipe 1 and the other end extending to the drainage point. The air inlet pipe 12 is connected to the air pump 16, and the air pump 16 is started to pressurize the cover body 10 so that the pressure inside the cover body 10 is greater than the pressure of the water in the pre-buried pipe 1 to achieve drainage; after the drainage is completed, the cast-in-place pile pre-buried pipe drainage device is recovered.
[0074] Based on the above drainage method, the embodiment of the present application also provides a specific example of a drainage method using a drainage device of a pre-buried pipe 1 with a cast column:
[0075] (1) Install the embedded pipe 1 in the steel cage. The embedded method of the embedded pipe 1 is the same as that of the acoustic detection pipe. The bottom of the embedded pipe 1 is closed, and the sections are connected by crimping rings, and an external thread is reserved for the top of the embedded pipe 1. After the concrete is poured, ensure that the external thread at the top of the embedded pipe 1 is still higher than the final pouring surface.
[0076] (2) When the concrete hydration heat detection age is reached, take the first section of drainage pipe 11 with a length equal to the depth of the embedded pipe 1, connect one end of the drainage pipe 11 to the drainage joint 20 at the lower end of the cover 10, and connect the other end to the filter box, and then extend it into the embedded pipe 1. Install the cover 10 on the upper end of the embedded pipe 1.
[0077] (3) Take the second section of the drainage pipe 11, connect one end of the second section of the drainage pipe 11 to the drainage joint 20 at the upper end of the cover body 10, and extend the other end of the second section of the drainage pipe 11 to a suitable drainage point as a water outlet.
[0078] (4) One end of the air intake pipe 12 is connected to the air intake connector 21 integrated with the sealing top cover, and the other end is connected to the air pump 16.
[0079] (5) After completing the above steps, close the pressure relief valve 13 of the cover body 10. Turn on the air pump 16 so that the pressure of the air pump 16 is greater than the water column pressure.
[0080] (6) Wait until no water is discharged from the outlet of the drain pipe 11, and then turn off the air pump 16 after maintaining it for a suitable period of time.
[0081] (7) Open the pressure relief valve 13.
[0082] (8) When there is no obvious gas discharge from the pressure relief valve 13, remove the second section of the drainage pipe 11 and the air inlet pipe 12, remove the cover 10, take out the first section of the drainage pipe 11, and recover the device.
[0083] In the above embodiments, the description of each embodiment has its own emphasis. For parts that are not described in detail in a certain embodiment, please refer to the relevant description of other embodiments. Those skilled in the art should also know that the actions and modules involved in the description are not necessarily required by the present application. In addition, it can be understood that the steps in the method of the embodiment of the present application can be adjusted in order, merged and deleted according to actual needs, and the modules in the device of the embodiment of the present application can be merged, divided and deleted according to actual needs.
[0084] The embodiments of the present application have been described above, and the above description is exemplary, not exhaustive, and is not limited to the disclosed embodiments. Many modifications and changes will be apparent to those of ordinary skill in the art without departing from the scope and spirit of the described embodiments. The selection of terms used herein is intended to best explain the principles of the embodiments, practical applications, or improvements to the technology in the market, or to enable other persons of ordinary skill in the art to understand the embodiments disclosed herein.
Claims
1. A pre-buried pipe drainage device for cast-in-place piles, It is characterized in that It includes a cover body, a drain pipe and an air inlet pipe. The cover body is sealed and connected to the pre-buried pipe. The drain pipe is inserted on the cover body and sealed and connected to the cover body. One end of the drain pipe penetrates into the bottom of the pre-buried pipe. The air inlet pipe is connected to the cover body and is used to input an air pressure.
2. The pre-buried pipe drainage device for cast-in-place piles according to claim 1, It is characterized in that The cover body is also provided with a pressure relief valve.
3. The pre-buried pipe drainage device for cast-in-place piles according to claim 2, It is characterized in that It also includes an exhaust valve, an air storage tank and an air pump which are sequentially connected to the air inlet pipe. The top of the air storage tank is also provided with a vent valve for pressure relief and a pressure gauge for detecting air pressure.
4. The cast-in-place pile pre-buried pipeline drainage device according to claim 3, It is characterized in that It also includes a vehicle body and a processing device, the air pump and the air storage tank are fixedly arranged on the vehicle body, and the processing device is used to control the air pump to pressurize the air storage tank according to the size and depth of the pre-buried pipeline.
5. The cast-in-place pile pre-buried pipeline drainage device according to claim 1, It is characterized in that The cover body is provided with a drainage hole and an air inlet hole. Both ends of the drainage hole are provided with drainage joints, and the drainage pipe is connected to the drainage joints. The air inlet hole is provided with an air inlet joint, and the air inlet pipe is connected to the air inlet joint.
6. The cast-in-place pile pre-buried pipeline drainage device according to claim 5, It is characterized in that The cover body is threadedly connected to the pre-buried pipeline. An annular sealing ring is also arranged in the cover body, and the annular sealing ring is located between the cover body and the pre-buried pipeline.
7. The pre-buried pipe drainage device for cast-in-place piles according to claim 1, It is characterized in that A filter box is provided at the end pipe opening of the drain pipe, and a filter screen for filtering is provided inside the filter box. The filter box is radially enlarged outward at one end away from the drain pipe.
8. The cast-in-place pile pre-buried pipeline drainage device according to claim 7, It is characterized in that The filter screen is formed by metal wires being wound around each other, and the pores of the filter screen increase from the terminal pipe of the drain pipe outwards.
9. The cast-in-place pile pre-buried pipeline drainage device according to claim 1, It is characterized in that The drainage pipe includes multiple vertical pipes and a hollow clamp ring; annular flanges are provided on the outer peripheries of both ends of the vertical pipes, the hollow clamp ring has two relatively free ends, adjacent vertical pipes are connected by the hollow clamp ring, a groove for clamping the annular flange is also provided in the hollow clamp ring, an annular rubber ring is also provided on the inner circumferential wall of the hollow clamp ring, adjacent vertical pipes are connected by the hollow clamp ring, and the two free ends are connected by bolts.
10. A drainage method, It is characterized in that The pre-buried pipe drainage device for the injection column as claimed in any one of claims 1 to 9 is installed on the pre-buried pipe, one end of the drainage pipe penetrates into the bottom of the pre-buried pipe, the other end extends to the drainage point, and the air inlet pipe is connected to the air pump; Start the air pump to pressurize the cover body so that the pressure inside the cover body is greater than the pressure of the water in the pre-buried pipe to achieve drainage; After the drainage is completed, the cast-in-place pile pre-buried pipeline drainage device is recovered.