Installation method of high-altitude TBM rockburst tunnel formwork trolley
By adopting the split modular design and suspension method of TBM rock blast tunnel formwork trolley installation method in tunnel projects in high-altitude areas, the problems of manpower occupation and slow construction progress are solved, and the construction efficiency and installation speed are improved.
Patent Information
- Application Number
- CN202410754101.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-12
- Publication Date
- 2024-10-01
AI Technical Summary
In tunnel projects in high-altitude areas, the installation process of TBM rock blast tunnel formwork trolleys has led to increased manpower occupation, blocked wind, water and electricity in the tunnel, and slowed down the construction progress, which has affected the construction efficiency and speed.
The installation method of high-altitude TBM rock blast tunnel formwork trolley is adopted, including temporary track laying, main structure assembly, fabric system installation, gantry crane lifting and installation steps of belt conveyor and formwork. It is simplified by split modular design and suspension method. The installation process reduces manpower usage and improves construction efficiency.
This method assembles the trolley in the assembly hole, increases the assembly space, reduces the reduction in the TBM excavation rate and the impact of the slag discharge of the belt conveyor caused by the trolley assembly, improves the construction efficiency, and simplifies the water pipes and pipes through suspension. Cable fixation reduces labor requirements.
Smart Images

Figure CN118728422A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of tunnel lining construction equipment installation, and in particular to an installation method for a high-altitude TBM rock burst tunnel template trolley. Background Art
[0002] Due to national strategic planning, more and more tunnel projects are built in plateau mountainous areas. Construction projects in plateau mountainous areas are widely faced with problems such as high labor costs and high work intensity. In order to increase the construction speed, large machinery or integrated excavation machinery such as TBM and shield machines are widely used in construction in this area. This method is less affected by rock burst geology and significantly improves the construction speed compared to traditional drilling and blasting excavation. The daily excavation footage is 3-4 times that of traditional drilling and blasting. However, the progress of tunnel construction does not depend solely on the excavation speed. The lining link after the excavation process needs to be coordinated with the excavation progress. At present, in order to meet the construction progress and construction speed of TBM excavation, template trolleys suitable for TBM rock burst tunnels are usually used for construction. However, in order to ensure the smooth progress of TBM excavation construction during the installation of the template trolley, and to avoid problems such as manpower occupation, lack of wind, water and electricity in the tunnel and slow construction progress caused by the installation of the template trolley, the installation method of the template trolley in the tunnel is worth studying. Summary of the invention
[0003] In order to solve the above technical problems, the present invention provides a method for installing a high-altitude TBM rock burst tunnel template trolley.
[0004] The following technical solutions are specifically adopted.
[0005] A method for installing a template trolley for a high-altitude TBM rockburst tunnel is designed, which includes the following assembly steps: temporary track laying, main structure assembly, material distribution system installation, gantry crane lifting, belt conveyor and template installation. The temporary track is laid on the left side of the assembly hole, and a transport vehicle channel is reserved.
[0006] Preferably, the assembly of the main structure includes the following steps:
[0007] S1: Transporting each component into the hole: transport each component into the hole according to its assembly order and place it on both sides of the hole;
[0008] S2: Gantry assembly: Assemble the gantry beams and columns to form the gantry, and assemble the gantry's traveling system. During the specific installation, a 300t gantry crane is used to lift the front and rear columns separately. When one column is installed, it is stably supported by a temporary support mechanism to ensure the stability of the gantry, and then the gantry beams and traveling system are assembled.
[0009] S3: Installation of the upper longitudinal beam and the lower longitudinal beam: After the upper longitudinal beam and the lower longitudinal beam are hoisted by a 300t gantry crane, they are moved to the portal frames at both ends, and the ends of the upper longitudinal beam and the lower longitudinal beam are fixedly installed on the portal frames, and then the temporary support mechanism is removed;
[0010] S4: sequentially install the short beam between the upper longitudinal beam and the lower longitudinal beam, the supporting body between the upper longitudinal beam and the lower longitudinal beam, the door beam and the working platform on the column;
[0011] S6: Install the hydraulic system and connect the power supply, run it without load, and operate the travel system so that it can move forward and backward.
[0012] Preferably, the temporary support mechanism includes embedded bolts embedded in the ground and steel wire ropes connected between the columns and the embedded bolts, and the embedded bolts are located on both sides of the columns.
[0013] Preferably, the installation steps of the material distribution system include assembling the translation mechanism, the jacking cylinder, the left and right side trusses, and the upper frame legs in sequence, using a 300t gantry crane to lift the hanging beam to a suitable height, and installing it on the upper longitudinal beam, and then installing the truss heightening seat. After the material distribution system platform is installed in place, the main machine of the material distribution system is lifted onto the platform of the material distribution system, and all bolts of the installed components are tightened.
[0014] Preferably, the gantry crane lifting includes laying a track in the middle of the assembly hole according to the span of the trolley, adjusting the track height using square wood or steel supports under the track, fixing the track, measuring the left and right center lines and diagonals, and then using a 300t gantry crane to move the installed integral gantry onto the track.
[0015] Preferably, the belt conveyor and template installation steps include:
[0016] S1: After the overall installation of the platform is completed, remove the sling on the belt conveyor and place it on the trolley platform for fixing;
[0017] S2: Use a 300t gantry crane to hoist the first side template to both sides of the working platform, fix the first side template, connect and fix the first side template to the gantry through the support screw and the connecting plate, and after the first side template is fixed, hoist the first top template, connect and fix the first top template to the left and right trusses, strengthen the fixing effect through the support screw, and fix the connection between the first top template and the first side template by welding;
[0018] S3: After installing the first side template and the first top template, observe whether the first side template and the first top template are aligned, and adjust them in time to keep them flush;
[0019] S5: Install the second side formwork and the second top formwork in sequence according to the above steps, then install the remaining accessories, install the water pipe bracket, water pipe suspension bracket, cable bracket, and install the air duct, water pipe, and cable. After the installation is completed, drive to the main tunnel.
[0020] The beneficial effects of the present invention are:
[0021] Compared with the previous method of assembling the TBM lining trolley in the tunnel, the present invention uses the TBM assembly hole to assemble the trolley, which increases the assembly space to a certain extent. It is assembled on one side of the tunnel first, and after the assembly is completed, the overall gantry is moved to the position of the trolley track laid in the tunnel, which reduces the factors of the TBM excavation rate reduction caused by the trolley assembly and the influence of the belt conveyor slag discharge, and improves the construction efficiency. In addition, the present invention uses a suspension method to fix the water pipe and set the water pipe bracket, which effectively improves the steps of removing the water pipe, moving the cable and stopping the air during the movement of the trolley, and reduces labor. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] Figure 1 It is the overall flow chart of the present invention;
[0023] Figure 2 It is a schematic diagram of the overall structure of the present invention;
[0024] Figure 3 It is a side view structural schematic diagram of the present invention;
[0025] Figure 4 Lay location map for temporary track;
[0026] Figure 5 It is a schematic diagram of the temporary support mechanism of the gantry;
[0027] Figure 6 This is the main assembly view of the lining trolley structure;
[0028] Figure 7 It is a schematic diagram of the lining trolley material distribution system;
[0029] Figure 8 This is the installation diagram of the lining trolley material distribution system;
[0030] Fig. 9 It is a schematic diagram of the installation of the side formwork and top formwork of the lining trolley;
[0031] The numbers in the figure are: 1 temporary track, 2 door beam, 3 gantry crane, 4 column, 5 front walking mechanism, 6 rear walking mechanism, 7 main machine of cloth system, 8 upper longitudinal beam, 9 lower longitudinal beam, 10 support body, 11 short beam, 12 translation mechanism, 13 lifting cylinder, 14 truss, 15 hanging beam, 16 truss heightening seat, 17 first side formwork, 18 second side formwork, 21 belt conveyor, 22 water pipe bracket, 23 cable bracket, 25 supporting screw, 26 connecting plate, 27 water pipe suspension bracket, 28 second top formwork, 29 second side formwork. DETAILED DESCRIPTION
[0032] The preferred embodiments of the present invention are described below in conjunction with the accompanying drawings. It should be understood that the preferred embodiments described herein are only used to illustrate and explain the present invention, and are not used to limit the present invention.
[0033] Example 1
[0034] A method for installing a high-altitude TBM rock burst tunnel template trolley, such as Figures 1 to 9 As shown, the assembly steps include:
[0035] S1: Temporary track laying: The temporary track is laid on the left side of the assembly hole, and a transport vehicle channel is reserved;
[0036] S2: Assembling the main structure, including the following steps:
[0037] a). Transport each component into the hole: transport each component into the hole according to its assembly sequence and place them on both sides of the hole;
[0038] b). Gantry assembly: Assemble the door beam 2 and the column 4 to form the door frame, and assemble the walking system of the door frame. During the specific installation, use a 300t gantry crane 3 to lift the front and rear columns 4 respectively. When one is installed, it is stably supported by a temporary support mechanism to ensure the stability of the door frame. The temporary support mechanism includes embedded bolts embedded in the ground, and a steel wire rope 30 connected between the column 4 and the embedded bolts. The embedded bolts are located on both sides of the column 4. Then the door beam and the walking system are formed. The walking system includes a front walking mechanism 5 and a rear walking mechanism 6, which are respectively installed at the bottom of the corresponding column 4.
[0039] c) Installation of upper and lower longitudinal beams: After hoisting the upper and lower longitudinal beams 8 and 9 using the 300t gantry crane 3, move them to the portal frames at both ends, and fix the ends of the upper and lower longitudinal beams 8 and 9 on the portal frames, and then remove the temporary support mechanism;
[0040] d) Install the short beam 11 between the upper longitudinal beam 8 and the lower longitudinal beam 9, the support body 10 between the upper longitudinal beam 8 and the lower longitudinal beam 9, the door beam 2 and the working platform 19 on the column 4 in sequence;
[0041] e). Install the hydraulic system and connect the power supply, run it without load, and operate the travel system so that it can move forward and backward.
[0042] S3: Installation of the material distribution system: specifically, assembling the translation mechanism 12, the lifting cylinder 13, the left and right trusses 14, and the upper frame legs 20 in sequence, using the 300t gantry crane 3 to lift the hanging beam 15 to a suitable height, and install it on the upper longitudinal beam 8, and then install the truss heightening seat 16. After the material distribution system platform is installed in place, the main machine 7 of the material distribution system is lifted onto the platform of the material distribution system, and all bolts of the installed components are tightened.
[0043] S4: Gantry crane lifting: Specifically, it includes laying the track in the middle of the assembly hole according to the span of the trolley, using square wood or steel supports under the track to adjust the track height, fixing the track, measuring the left and right center lines and diagonals, and then temporarily fixing it, and then using a 300t gantry crane 3 to move the above-mentioned installed integral gantry onto the track.
[0044] S5: Belt conveyor and template installation: The specific installation steps include the following:
[0045] a). After the overall installation of the rack is completed, remove the sling on the belt conveyor 21 and place it on the trolley platform for fixing;
[0046] b) Use the 300t gantry crane 3 to hoist the first side template 17 to both sides of the working platform 19, fix the first side template 17, connect and fix the first side template 17 to the gantry through the support screw 25 and the connecting plate 26, and after the first side template 17 is fixed, hoist the first top template 18, connect and fix the first top template 18 to the left and right trusses 14, and strengthen the fixing effect through the support screw 25. The connection between the first top template 18 and the first side template 17 is fixed by welding;
[0047] c) After installing the first side template 17 and the first top template 18, observe whether the first side template 17 and the first top template 18 are aligned, and adjust them in time to keep them flush;
[0048] d). Install the second side formwork 29 and the second top formwork 28 in sequence according to the above steps, then install the remaining auxiliary devices and install the water pipe bracket 22, water pipe hanger 27, cable bracket 23, and install the air duct, water pipe, and cable. After the installation is completed, drive to the main tunnel.
[0049] The template trolley of the present invention adopts a split modular design, which changes the classic gate pillar structure and distributes the trolley load on a large number of legs, facilitating the loading and unloading of trolley components and later assembly. The installation process is simplified by simplifying the structure and setting up specialized functional areas, and the TBM excavation construction is ensured to proceed smoothly during the installation process. The template trolley installation method can greatly avoid problems such as manpower occupation, lack of air, water and electricity in the tunnel, and slow construction progress caused by the installation of the template trolley.
[0050] Finally, it should be noted that the above is only a preferred embodiment of the present invention and is not intended to limit the present invention. Although the present invention has been described in detail with reference to the aforementioned embodiments, it is still possible for those skilled in the art to modify the technical solutions described in the aforementioned embodiments or to make equivalent substitutions for some of the technical features therein. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A method for installing a high-altitude TBM rock burst tunnel template trolley, characterized in that: The following assembly steps are included: temporary track laying, main structure assembly, material distribution system installation, gantry crane lifting, belt conveyor and formwork installation. The temporary track is laid on the left side of the assembly hole, and a transport vehicle channel is reserved.
2. The method for installing a high-altitude TBM rock burst tunnel template trolley according to claim 1, characterized in that: The assembly of the main structure includes the following steps: S1: Transporting each component into the hole: transport each component into the hole according to its assembly order and place it on both sides of the hole; S2: gantry assembly: assemble the gantry beam (2) and the column (4) to form the gantry, and assemble the traveling system of the gantry. During the specific installation, a 300t gantry crane (3) is used to lift the front and rear columns (4) respectively. When one column is installed, it is stably supported by a temporary support mechanism to ensure the stability of the gantry, and then the gantry beam and the traveling system are assembled; S3: Installation of the upper longitudinal beam and the lower longitudinal beam: After the upper longitudinal beam (8) and the lower longitudinal beam (9) are hoisted by a 300t gantry crane (3), they are moved to the portal frames at both ends, and the ends of the upper longitudinal beam (8) and the lower longitudinal beam (9) are fixedly installed on the portal frames, and then the temporary supporting mechanism is removed; S4: sequentially installing the short beam (11) between the upper longitudinal beam (8) and the lower longitudinal beam (9), the supporting body (10) between the upper longitudinal beam (8) and the lower longitudinal beam (9), the door beam (2) and the working platform (19) on the column (4); S6: Install the hydraulic system and connect the power supply, run it without load, and operate the travel system so that it can move forward and backward.
3. The method for installing a high-altitude TBM rock burst tunnel template trolley according to claim 2, characterized in that: The temporary support mechanism comprises embedded bolts embedded in the ground, and a steel wire rope (30) connected between the column (4) and the embedded bolts, wherein the embedded bolts are located on both sides of the column (4).
4. The method for installing a high-altitude TBM rock burst tunnel template trolley according to claim 1, characterized in that: The installation steps of the material distribution system include assembling the translation mechanism (12), the lifting cylinder (13), the left and right trusses (14), and the upper frame legs (20) in sequence, using a 300t gantry crane (3) to lift the hanging beam (15) to a suitable height, and installing it on the upper longitudinal beam (8), and then installing the truss heightening seat (16). After the material distribution system platform is installed in place, the material distribution system host (7) is lifted onto the material distribution system platform, and all bolts of the installed components are tightened.
5. The method for installing a high-altitude TBM rock burst tunnel template trolley according to claim 1, characterized in that: The gantry crane lifting process includes laying the track in the middle of the assembly hole according to the span of the trolley, adjusting the track height using square wood or steel supports under the track, fixing the track, measuring the left and right center lines and diagonals, and temporarily fixing them. Then, a 300t gantry crane (3) is used to move the installed integral gantry onto the track.
6. The method for installing a high-altitude TBM rock burst tunnel template trolley according to claim 1, characterized in that: The steps for installing the belt conveyor and template include: S1: After the overall installation of the frame is completed, the sling on the belt conveyor (21) is removed and placed on the trolley platform for fixing; S2: Using a 300t gantry crane (3), hoist the first side formwork (17) to both sides of the working platform (19), fix the first side formwork (17), connect and fix the first side formwork (17) to the portal frame through a support screw (25) and a connecting plate (26), after the first side formwork (17) is fixed, hoist the first top formwork (18), connect and fix the first top formwork (18) to the left and right side trusses (14), strengthen the fixing effect through a support screw (25), and fix the connection between the first top formwork (18) and the first side formwork (17) by welding; S3: After installing the first side template (17) and the first top template (18), observe whether the first side template (17) and the first top template (18) are aligned, and adjust them in time to keep them flush; S5: Install the second side formwork (29) and the second top formwork (28) in sequence according to the above steps, then install the remaining auxiliary devices and install the water pipe bracket (22), the water pipe suspension bracket (27), the cable bracket (23), and install the air duct, water pipe, and cable. After the installation is completed, drive to the main tunnel.