Chromatography line pollution detection method and related equipment

By constructing and adjusting the simulation model of the color registration line, the pollution situation under different working conditions is simulated, which solves the problem of inaccurate pollution detection methods in the existing method and achieves a more accurate reflection of environmental quality.

CN118734540AActive Publication Date: 2024-10-01SHENZHEN HUATU TECH CO LTD
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202410717463.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-06-04
Publication Date
2024-10-01
Estimated Expiration
2044-06-04

AI Technical Summary

Technical Problem

Existing pollution detection methods have inaccuracies in detecting pollution in automobile painting lines and cannot fully reflect environmental quality.

Method used

By constructing an initial simulation model of the color registration line and adjusting it based on historical operating data and pollution generation data, a target simulation model is generated, and simulations are performed to determine the pollution detection results under different working conditions.

Benefits of technology

It improves the accuracy of pollution detection, can reflect environmental quality more comprehensively, and solves the problem of inaccurate detection in existing methods.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118734540A_ABST
    Figure CN118734540A_ABST
Patent Text Reader

Abstract

The embodiment of the invention provides a chromatography line pollution detection method, which comprises the following steps of: constructing an initial simulation model of a chromatography line based on an equipment structure and parameters of the chromatography line; under different working conditions, first adjustment is carried out on the initial simulation model through historical operation data of the color register line, second adjustment is carried out on the initial simulation model through historical pollution generation data of the color register line, target simulation models under different working conditions are obtained, and each working condition corresponds to one target simulation model; performing analog simulation on the color register line through the corresponding target simulation model to obtain pollution simulation results under different working conditions; and on the basis of the pollution simulation result, pollution detection results of the color register line under different working conditions are determined. The method can solve the problems that the pollution detection is inaccurate and the environment quality cannot be comprehensively reflected in the existing pollution detection method.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of pollution detection, and in particular to a color line pollution detection method and related equipment. Background Art

[0002] With the rapid development of the automobile industry, automobiles have become one of the indispensable means of transportation for people. Automobile painting is one of the links in the automobile manufacturing process that consumes the most energy and produces the most three wastes. The pollution problem of the color matching line mainly comes from the painting line. For example, the waste gas generated by the volatilization of solvents during the paint drying process, the waste water in the production water of electrophoresis and the middle and upper coating circulation tank, and the paint residue generated after painting. Due to technical limitations, the existing pollution detection methods have the problem of inaccurate pollution detection and cannot fully reflect the environmental quality. Summary of the invention

[0003] The embodiment of the present invention provides a color line pollution detection method, which aims to solve the problem that the pollution detection method is inaccurate and cannot fully reflect the environmental quality. By constructing an initial simulation model of the color line according to the equipment structure and parameters of the color line, the initial simulation model is first adjusted according to the historical operation data of the color line under different working conditions, and the initial simulation model is second adjusted according to the historical pollution generation data of the color line to obtain the target simulation model under different working conditions, and the color line is simulated by the corresponding target simulation model to obtain the pollution simulation results under different working conditions, and the pollution detection results of the color line under different working conditions are determined according to the pollution detection results, so as to solve the problem that the pollution detection method is inaccurate and cannot fully reflect the environmental quality.

[0004] In a first aspect, an embodiment of the present invention provides a color line contamination detection method, the method comprising:

[0005] Based on the equipment structure and parameters of the color-coding line, an initial simulation model of the color-coding line is constructed;

[0006] Under different working conditions, the initial simulation model is first adjusted according to the historical operation data of the color line, and the initial simulation model is second adjusted according to the historical pollution generation data of the color line to obtain target simulation models of different working conditions, each working condition corresponds to a target simulation model;

[0007] The color line is simulated by the corresponding target simulation model to obtain the pollution simulation results under different working conditions;

[0008] Based on the pollution simulation result, the pollution detection result of the color matching line under different working conditions is determined.

[0009] Optionally, the step of first adjusting the initial simulation model according to the historical operation data of the color line under different working conditions includes:

[0010] Obtaining historical operating data of the color set line under various working conditions;

[0011] For each operating condition, the historical operating data is fitted or predicted in multiple dimensions to obtain multi-dimensional operating parameters, and each operating condition corresponds to one of the multi-dimensional operating parameters;

[0012] A first adjustment is performed on the initial simulation model based on the multi-dimensional operating parameters.

[0013] Optionally, the step of performing a second adjustment on the initial simulation model by generating data of historical pollution of the color line comprises:

[0014] Obtaining historical pollution generation data of the color line under various working conditions;

[0015] For each operating condition, the historical pollution generation data is divided by time period to obtain a pollution generation data sequence, each operating condition corresponds to a pollution generation data sequence, and each pollution generation data sequence includes N pollution generation data segments sorted by time period;

[0016] Considering the pollution residue, weight calculation is performed on the pollution generation data sequence to obtain the target pollution generation data sequence;

[0017] Predicting the target pollution generation data sequence through a time series prediction network to obtain predicted pollution source parameters, each operating condition corresponding to one predicted pollution source parameter;

[0018] A second adjustment is performed on the initial simulation model based on the predicted pollution source parameters.

[0019] Optionally, the step of taking into account the pollution residue and performing weight calculation on the pollution generation data sequence to obtain a target pollution generation data sequence includes:

[0020] Determine the time sequence of each of the pollution generating data segments;

[0021] According to the time sequence, the pollution weight of each of the pollution generating data segments is determined. The later the time sequence, the greater the pollution weight. The pollution weight is calculated according to the following formula:

[0022]

[0023] Among them, W i represents the pollution weight of the pollution-generating data segment at the i-th time sequence, t irepresents the time interval from the i-th time sequence to the start time, N represents the number of pollution-generated data segments, and softmax() represents the normalization function;

[0024] A weighted calculation is performed on each of the pollution generating data segments based on the pollution weight to obtain a target pollution generating data sequence.

[0025] Optionally, the step of simulating the color line by using the corresponding target simulation model to obtain the pollution simulation results under different working conditions includes:

[0026] Under the current working condition, matching the target simulation model corresponding to the working condition, each working condition corresponds to one target simulation model;

[0027] The operating parameters of the color line under the current working condition are transmitted to the target simulation model in real time, and a fourth time period is set;

[0028] The pollution simulation result of the color line in the fourth time period under the current working condition is outputted through the target simulation model.

[0029] Optionally, the target simulation model includes a historical data processing unit, a reference data processing unit and an output data processing unit, and the historical data processing unit, the data processing unit and the output data processing unit are continuous in time; the step of obtaining the pollution simulation result of the color line under the current working condition through the target simulation model data includes:

[0030] Maintaining the operating parameters in the first period unchanged by the historical data processing unit;

[0031] The reference data processing unit updates the reference operating parameters in the second time period according to the operating parameters in the first time period, keeps the reference operating parameters similar to or the same as the operating parameters in the second time period, and obtains the model prediction parameters in the second time period, the first time period is before the second time period, and the end time of the second time period is the current time or between the current time and the reference operating parameters in the second time period;

[0032] The output data processing unit updates the pollution simulation results of the fourth time period based on the operating parameters in the third time period and the model prediction parameters in the second time period. The third time period takes the current time as the end time, the length of the third time period is the same as the length of the first time period, and the fourth time period is after the third time period.

[0033] Optionally, the step of determining the pollution detection result of the color wire under different working conditions based on the pollution simulation result includes:

[0034] For the current working condition, obtain the confidence of the pollution simulation result, the confidence is output by the target simulation model, and the pollution simulation result corresponds to a confidence;

[0035] When the confidence level is less than a first confidence level threshold, the pollution detection result of the color set line under the current working condition is determined according to the pollution simulation result at the next moment;

[0036] When the confidence is greater than or equal to a first confidence threshold and less than a second confidence threshold, the pollution simulation result is compensated according to the compensation coefficient corresponding to the current working condition, and the compensated pollution simulation result is defined as the pollution detection result of the color line under the current working condition, and the second confidence threshold is greater than the first confidence threshold;

[0037] When the confidence level is greater than or equal to the second confidence level threshold, the pollution simulation result is determined as the pollution detection result of the color wire under the current working condition.

[0038] In a second aspect, an embodiment of the present invention further provides a color line contamination detection device, the color line contamination detection device comprising:

[0039] A construction module, used to construct an initial simulation model of the color set line based on the equipment structure and parameters of the color set line;

[0040] An adjustment module, used for making a first adjustment to the initial simulation model under different working conditions by using the historical operation data of the color set line, and making a second adjustment to the initial simulation model by using the historical pollution generation data of the color set line, so as to obtain target simulation models under different working conditions, each working condition corresponding to a target simulation model;

[0041] A simulation module, used to simulate the color line through the corresponding target simulation model to obtain pollution simulation results under different working conditions;

[0042] A determination module is used to determine the pollution detection results of the color matching line under different working conditions based on the pollution simulation results.

[0043] In a third aspect, an embodiment of the present invention provides an electronic device, comprising: a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor implements the steps in the color line contamination detection method provided in an embodiment of the present invention when executing the computer program.

[0044] In a fourth aspect, an embodiment of the present invention provides a computer-readable storage medium having a computer program stored thereon, and when the computer program is executed by a processor, the steps of the color line contamination detection method provided in the embodiment of the invention are implemented.

[0045] In the embodiment of the present invention, an initial simulation model of the color line is constructed based on the equipment structure and parameters of the color line; under different working conditions, the initial simulation model is first adjusted by the historical operation data of the color line, and the initial simulation model is second adjusted by the historical pollution generation data of the color line to obtain target simulation models of different working conditions, and each working condition corresponds to a target simulation model; the color line is simulated by the corresponding target simulation model to obtain pollution simulation results under different working conditions; based on the pollution simulation results, the pollution detection results of the color line under different working conditions are determined. The present invention can solve the problem that the pollution detection in the existing pollution detection method is inaccurate and cannot fully reflect the environmental quality. BRIEF DESCRIPTION OF THE DRAWINGS

[0046] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0047] Figure 1 is a flow chart of a color line contamination detection method provided by an embodiment of the present invention;

[0048] Figure 2 It is a structural schematic diagram of a color line contamination detection device provided by an embodiment of the present invention;

[0049] Figure 3 It is a structural schematic diagram of an electronic device provided by an embodiment of the present invention. DETAILED DESCRIPTION

[0050] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0051] like Figure 1 As shown, Figure 1 : is a method flow chart of a color line contamination detection method provided by an embodiment of the present invention. The color line contamination detection method comprises the steps of:

[0052] 10 1. Based on the equipment structure and parameters of the color-coding line, an initial simulation model of the color-coding line is constructed.

[0053] In an embodiment of the present invention, the above-mentioned color line contamination detection method can be applied to smart devices. The above-mentioned smart devices can be understood as smart devices that need to perform color line contamination detection, such as various types of production line terminal devices.

[0054] The above-mentioned color-coding line can be understood as a process for achieving a layered effect of different colors or materials on the surface of a vehicle. The above-mentioned equipment structure includes the components of the equipment, such as an unwinder, a sprayer, an electrophoresis device, a printer, and a winder. The above-mentioned parameters include various parameters of equipment operation, such as working speed, production efficiency, energy consumption, etc.

[0055] The above-mentioned simulation model is a dynamic simulation model, which can simulate the real production environment and equipment operation. The above-mentioned simulation model can include a three-dimensional dynamic simulation model established by using the Delmia-Quest software and a data processing model based on time series. Each equipment structure in the three-dimensional dynamic simulation model receives corresponding operating parameters, and simulates the corresponding operating state according to the corresponding operating parameters to output corresponding simulation data. The data processing model performs pollution detection according to the simulation data output by the three-dimensional dynamic simulation model.

[0056] The above initial simulation model can be understood as a simulation model used to describe the initial state and performance of the color-coding line.

[0057] It should be noted that, by constructing an initial simulation model of the color-coding line according to the equipment structure and parameters of the color-coding line, the actual production environment and equipment operation of the color-coding line, as well as the pollution generation, can be simulated.

[0058] 102. Under different working conditions, the initial simulation model is first adjusted by the historical operation data of the color line, and the initial simulation model is second adjusted by the historical pollution generation data of the color line to obtain the target simulation model of different working conditions.

[0059] In the embodiment of the present invention, each operating condition corresponds to a target simulation model.

[0060] The above-mentioned different working conditions may be different production environments, different equipment states, different operating modes, etc.

[0061] The historical operation data of the above-mentioned color-setting line can be understood as the operating parameters, performance indicators and other data of the historical color-setting line under different working conditions. By analyzing the historical operation data of the color-setting line under different working conditions, the performance of the color-setting line under various working conditions can be understood. The historical operation data of the color-setting line includes the operating speed, paint type and characteristics, etc. Under different working conditions, the operating speed of the color-setting line may be different; under different working conditions, the operation mode of the color-setting line may be different. The historical operation data of the above-mentioned color-setting line can come from the record of the actual historical generation process.

[0062] The above-mentioned historical pollution data of the color line can be understood as the pollution data generated by the historical color line under different working conditions. By analyzing the historical pollution data of the color line under different working conditions, the pollution data of the color line under different working conditions can be understood. The historical pollution data of the color line includes the types and concentrations of pollutants. Under different working conditions, the color line may generate different types of pollutants, such as paint residues, heavy metals, etc.

[0063] The first adjustment and the second adjustment are both processes for adjusting and optimizing the parameters, algorithms or structures of the data processing model in the simulation model to improve the performance of the simulation model under simulated actual working conditions and the pollution data generated. The data processing model can be a time series model based on a recurrent neural network RNN ​​or a long short-term memory network LSTM. The data processing model can be a pre-trained model, the first adjustment can be an adaptive adjustment or adaptive training to improve the generalization ability of the data processing model, and the second adjustment can be a targeted adjustment or targeted training to improve the accuracy of the data processing model for pollution detection. In a possible embodiment, the pollution detection result of the data processing model can also adjust the three-dimensional dynamic simulation model in the form of negative feedback, and the adjustment can be based on reward-based reinforcement learning, and the reward value can be the confidence of the pollution detection result. The higher the confidence, the greater the reward value.

[0064] Under different working conditions, the initial simulation model is first adjusted through the historical operation data of the color line, so that the simulation model can better simulate the performance of the color line under different working conditions. Under different working conditions, the initial simulation model is secondly adjusted through the historical pollution generation data of the color line, so that the simulation model can better simulate the pollution data of different degrees generated by the color line under different working conditions.

[0065] The above-mentioned different target simulation models can simulate the impact of different production processes, equipment parameters, environmental conditions and other factors on pollutants, thereby predicting the concentration and distribution of pollutants under different working conditions through data processing models.

[0066] It should be noted that, under different working conditions, the initial simulation model is adjusted first and second according to the historical operation data and historical pollution generation data of the color line, so as to obtain the target simulation model for different working conditions.

[0067] 103. The color line is simulated through the corresponding target simulation model to obtain the pollution simulation results under different working conditions.

[0068] In the embodiment of the present invention, the above-mentioned one target simulation model corresponds to one working condition.

[0069] Under different working conditions, the color line is simulated and data processed through the corresponding target simulation model to obtain the pollution simulation results under different working conditions.

[0070] The above pollution simulation results can be used to understand the evaluation effect of the process of simulating pollution conditions, and can be the prediction results obtained by the output of the data processing model. The pollution simulation results can predict and analyze the pollution problems that may occur in the production process.

[0071] 104. Based on the pollution simulation results, determine the pollution detection results of the color line under different working conditions.

[0072] In the embodiment of the present invention, the pollution detection results of the color wire under different working conditions can be determined according to the pollution simulation results.

[0073] The above pollution detection results are quantitative or qualitative measurements and analyses of pollutants generated during the production process. The pollution detection results are used to monitor the pollutant content in emissions such as waste gas, waste water and waste residue to ensure that the pollutant content meets environmental protection standards.

[0074] In an embodiment of the present invention, the present invention can predict the pollution simulation results under different working conditions through a simulation model, and determine the pollution detection results of the color line under different working conditions based on the pollution simulation results. The present invention can effectively improve the accuracy of pollution detection.

[0075] In the embodiment of the present invention, an initial simulation model of the color line is constructed based on the equipment structure and parameters of the color line; under different working conditions, the initial simulation model is first adjusted by the historical operation data of the color line, and the initial simulation model is second adjusted by the historical pollution generation data of the color line to obtain target simulation models of different working conditions, and each working condition corresponds to a target simulation model; the color line is simulated by the corresponding target simulation model to obtain pollution simulation results under different working conditions; based on the pollution simulation results, the pollution detection results of the color line under different working conditions are determined. The present invention can solve the problem that the pollution detection in the existing pollution detection method is inaccurate and cannot fully reflect the environmental quality.

[0076] Optionally, under different working conditions, the step of first adjusting the initial simulation model by using the historical operation data of the color line includes:

[0077] Obtain historical operating data of the color line under various operating conditions; for each operating condition, fit or predict the historical operating data in multiple dimensions to obtain multi-dimensional operating parameters, each operating condition corresponds to a multi-dimensional operating parameter; and make a first adjustment to the initial simulation model based on the multi-dimensional operating parameters.

[0078] In the embodiment of the present invention, the above working conditions can be understood as the operating state of the color matching line. Different working conditions include different production environments, different equipment states, different operation modes, etc.

[0079] The above historical operation data can come from the records of the historical actual production process. The historical operation data includes the operating parameters, performance indicators and other data of the historical color matching line under different working conditions.

[0080] The above-mentioned multiple dimensions may be temperature, pressure, speed, humidity, etc.

[0081] The above multi-dimensional operating parameters can be understood as describing the performance of the color matching line under different working conditions, which requires consideration of multiple factors and dimensions, including temperature, pressure, speed, humidity, etc. The multi-dimensional operating parameters can be used as inputs to the optimization algorithm to further optimize the production process and improve product quality and production efficiency.

[0082] For each working condition, it is necessary to fit or predict the historical operating data under that condition and extract multi-dimensional operating parameters from the historical data. The multi-dimensional parameters can reflect the performance of the color line under that condition.

[0083] The above fitting or prediction can be performed by linear regression, support vector machine, neural network and other methods.

[0084] The above-mentioned first adjustment can be understood as a process of adjusting and optimizing the parameters, algorithms or structures of the data processing model in the simulation model to improve the performance of the simulation model under simulating actual working conditions.

[0085] It should be noted that the multi-dimensional operating parameters of the initial simulation model can be adjusted and optimized through the multi-dimensional operating parameters.

[0086] Optionally, the step of performing a second adjustment on the initial simulation model by generating data based on historical pollution of the color line includes:

[0087] Obtain historical pollution generation data of the color line under various working conditions; for each working condition, divide the historical pollution generation data by time period to obtain a pollution generation data sequence, each working condition corresponds to a pollution generation data sequence, and each pollution generation data sequence includes N pollution generation data segments sorted by time period; consider the pollution residue, calculate the weight of the pollution generation data sequence, and obtain the target pollution generation data sequence; predict the target pollution generation data sequence through a time series prediction network to obtain predicted pollution source parameters, each working condition corresponds to a predicted pollution source parameter; perform a second adjustment on the initial simulation model based on the predicted pollution source parameters.

[0088] In the embodiment of the present invention, the above historical pollution generation data is the pollution data generated by the historical color line under different working conditions. The historical pollution generation data of the color line includes the type, distribution and concentration of pollutants.

[0089] The above division by time period is to divide the historical pollution generation data into certain time intervals, for example, every fifteen minutes, every 30 minutes, every hour, every day, etc.

[0090] The above pollution generation data sequence can be understood as a plurality of sequences containing a plurality of data segments. Each sequence represents pollution data in a specific time period, which can be used to analyze and predict the pollution generation of the color line under different working conditions.

[0091] The above weight calculation is used to determine the importance of different factors. The weight calculation can be performed using methods such as hierarchical analysis method and entropy method.

[0092] The above time series prediction network is a deep learning model that can process and predict time series data. The time series prediction network can be a recurrent neural network (RNN), a long short-term memory network (LSTM), a convolutional neural network (CNN), etc.

[0093] The above-mentioned predicted pollution source parameters can be various indicators related to pollutants, such as concentration, emission volume, etc.

[0094] The above-mentioned second adjustment can be understood as a process of adjusting and optimizing the parameters, algorithms or structures of the data processing model in the simulation model to improve the performance of the simulation model under simulating actual working conditions.

[0095] It should be noted that the pollution source parameters of the initial simulation model can be adjusted and optimized by predicting the pollution source parameters.

[0096] Optionally, the steps of taking into account the pollution residue and performing weight calculation on the pollution generation data sequence to obtain the target pollution generation data sequence include:

[0097] Determine the time sequence of each pollution generating data segment; determine the pollution weight of each pollution generating data segment according to the time sequence, the later the time sequence, the greater the pollution weight; the pollution weight is calculated according to the following formula:

[0098]

[0099] Among them, W i represents the pollution weight of the pollution-generating data segment at the i-th time sequence, t irepresents the time interval from the i-th time sequence to the start time, N represents the number of pollution-generating data segments, and softmax() represents the normalization function; weighted calculation is performed on each pollution-generating data segment based on the pollution weight to obtain the target pollution-generating data sequence.

[0100] In the embodiment of the present invention, the above-mentioned time sequence bit is an identifier of the position or order of a data element in a time series. In a time series, each data element has a unique time sequence bit, which is used to indicate its position in the sequence. For example, assuming there is a time series containing 10 pollution-generating data segments, these data segments will be assigned serial numbers from 1 to 10 to indicate their positions in the time series. The serial number of the first data segment is 1, the serial number of the second data segment is 2, and so on, the serial number of the tenth data segment is 10.

[0101] The pollution weight can be a ratio, a fraction or other numerical value, which is used to indicate the influence of the position of the data segment in the time series on the total pollution.

[0102] The above weighted summation can be understood as summing a set of data or vectors after weighting them according to different weights. Specifically, for each data or vector, it will be multiplied by a weight, and then all the products will be summed up to get the result.

[0103] It should be noted that, first, the position or order of each pollution generating data segment in the time series, i.e., the time sequence position, needs to be determined. Then, the pollution weight of the data segment is determined according to the time sequence position of the data segment. Next, the pollution weight of each data segment is multiplied by its corresponding pollution generating data, and then all the products are summed to obtain the target pollution generating data sequence.

[0104] Optionally, the step of simulating the color line through the corresponding target simulation model to obtain the pollution simulation results under different working conditions includes:

[0105] Under the current working conditions, match the target simulation model corresponding to the working conditions, and each working condition corresponds to a target simulation model; the operating parameters of the color line under the current working conditions are transmitted to the target simulation model in real time, and the fourth time period is set; the pollution simulation results of the color line in the fourth time period under the current working conditions are output through the target simulation model.

[0106] In the embodiment of the present invention, the fourth time period can be understood as a fourth time point or time period set in the simulation model. The fourth time period can be used to observe the performance of the color line in the fourth time period.

[0107] The above pollution simulation results can be understood as the evaluation effect of the process of simulating pollution conditions. The pollution simulation results can predict and analyze the pollution problems that may occur in the production process.

[0108] It can be understood that under the current working conditions, the target simulation model corresponding to the current working conditions is matched, and the operating parameters of the color line under the current working conditions are transmitted to the target simulation model in real time, and the fourth time period is set. The target simulation model outputs the pollution simulation results of the color line in the fourth time period written under the current working conditions according to the input operating parameters and the set fourth time period.

[0109] Optionally, the data processing model in the target simulation model may include a historical data processing unit, a reference data processing unit, and an output data processing unit, and the historical data processing unit, the reference data processing unit, and the output data processing unit are continuous in time; and the step of outputting the pollution simulation result of the color line under the current working condition through the target simulation model includes:

[0110] The operating parameters in the first time period are kept unchanged by the historical data processing unit; the reference operating parameters in the second time period are updated by the reference data processing unit according to the operating parameters in the first time period, the reference operating parameters are kept similar or the same as the operating parameters in the second time period, and the model prediction parameters in the second time period are obtained, the first time period is before the second time period, and the end time of the second time period is the current moment or between the current moments; the pollution simulation results of the fourth time period are updated by the output data processing unit according to the operating parameters in the third time period and the model prediction parameters in the second time period, the third time period takes the current moment as the end time, the length of the third time period is the same as the length of the first time period, and the fourth time period is after the third time period. The length of the second time period is the same as the length of the fourth time period.

[0111] In the embodiment of the present invention, the historical data processing unit is responsible for keeping the operating parameters in the first time period unchanged; the reference data processing unit is responsible for updating the reference operating parameters in the second time period based on the operating parameters in the first time period; and the output data processing unit is responsible for updating the pollution simulation results in the fourth time period based on the operating parameters in the third time period and the model prediction parameters in the second time period. The historical data processing unit, the reference data processing unit and the output data processing unit are continuous in time, that is, the reference data processing unit works after the historical data processing unit, and the output data processing unit works after the reference data processing unit.

[0112] The first time period can be understood as the first time point or time period set in the simulation model. The second time period can be understood as the third time point or time period set in the simulation model. The third time period can be understood as the third time point or time period set in the simulation model. The first time period is before the second time period, the end time of the second time period is the current moment or between the current moments, the third time period takes the current moment as the end time, the length of the third time period is the same as the length of the first time period, and the fourth time period is after the third time period.

[0113] It should be noted that more accurate pollution simulation results can be obtained by processing and analyzing data from different time periods.

[0114] Optionally, based on the pollution simulation result, the step of determining the pollution detection result of the color matching line under different working conditions includes:

[0115] For the current working condition, the confidence of the pollution simulation result is obtained, and the confidence is output by the target simulation model. The above pollution simulation result corresponds to a confidence; when the confidence is less than the first confidence threshold, the pollution detection result of the color line under the current working condition is determined according to the pollution simulation result at the next moment; when the confidence is greater than or equal to the first confidence threshold, and less than the second confidence threshold, the pollution simulation result is compensated according to the compensation coefficient corresponding to the current working condition, and the compensated pollution simulation result is determined as the pollution detection result of the color line under the current working condition, and the second confidence threshold is greater than the first confidence threshold; when the confidence is greater than or equal to the second confidence threshold, the pollution simulation result is determined as the pollution detection result of the color line under the current working condition.

[0116] In the embodiment of the present invention, the above confidence level can be understood as the degree of trust in the output result of the simulation model. If the confidence level is high, then it is more believed that the result is accurate; if the confidence level is low, then there is some doubt about the accuracy of the result.

[0117] The first confidence threshold and the second confidence threshold are confidence thresholds preset by the system, and the second confidence threshold is greater than the first confidence threshold.

[0118] The above compensation coefficient is determined according to the specific working conditions and simulation model, and is used to compensate the pollution simulation results. The above compensation process can be understood as the process of performing compensation calculation according to the confidence of the simulation results and the compensation coefficient when determining the pollution detection results of the color line under the current working conditions.

[0119] It should be noted that when the confidence is less than the first confidence threshold, it is necessary to determine the pollution detection result of the color line under the current working condition based on the pollution simulation result at the next moment. When the confidence is greater than or equal to the first confidence threshold, and less than the second confidence threshold, it is necessary to compensate the pollution simulation result according to the compensation coefficient corresponding to the current working condition to improve the accuracy of the detection result. The compensated pollution simulation result is the pollution detection result of the color line under the current working condition. When the confidence is greater than or equal to the second confidence threshold, the pollution simulation result can be directly used as the pollution detection result of the color line under the current working condition.

[0120] like Figure 2 As shown, an embodiment of the present invention provides a color line contamination detection device, the color line contamination detection device comprising:

[0121] A construction module 201 is used to construct an initial simulation model of the color set line based on the equipment structure and parameters of the color set line;

[0122] An adjustment module 202 is used to make a first adjustment to the initial simulation model under different working conditions by using the historical operation data of the color set line, and to make a second adjustment to the initial simulation model by using the historical pollution generation data of the color set line, so as to obtain target simulation models under different working conditions, each working condition corresponding to a target simulation model;

[0123] A simulation module 203 is used to simulate the color line through the corresponding target simulation model to obtain pollution simulation results under different working conditions;

[0124] The determination module 204 is used to determine the pollution detection results of the color matching line under different working conditions based on the pollution simulation results.

[0125] Optionally, the adjustment module 202 is also used to obtain historical operating data of the color line under various operating conditions; for each operating condition, the historical operating data is fitted or predicted in multiple dimensions to obtain multi-dimensional operating parameters, and each operating condition corresponds to one multi-dimensional operating parameter; based on the multi-dimensional operating parameters, a first adjustment is made to the initial simulation model.

[0126] Optionally, the adjustment module 202 is also used to obtain historical pollution generation data of the color line under various operating conditions; for each operating condition, the historical pollution generation data is divided into time periods to obtain a pollution generation data sequence, each operating condition corresponds to a pollution generation data sequence, and each pollution generation data sequence includes N pollution generation data segments sorted by time periods; considering pollution residuals, weight calculation is performed on the pollution generation data sequence to obtain a target pollution generation data sequence; the target pollution generation data sequence is predicted through a time series prediction network to obtain predicted pollution source parameters, each operating condition corresponds to a predicted pollution source parameter; and a second adjustment is performed on the initial simulation model based on the predicted pollution source parameters.

[0127] Optionally, the adjustment module 202 is further used to determine the time sequence of each of the pollution generating data segments; determine the pollution weight of each of the pollution generating data segments according to the time sequence, the later the time sequence, the greater the pollution weight; the pollution weight is calculated according to the following formula:

[0128]

[0129] Among them, W i represents the pollution weight of the pollution-generating data segment at the i-th time sequence, ti represents the time interval from the ith time sequence to the start time, N represents the number of pollution-generating data segments, and softmax() represents the normalization function; based on the pollution weight, weighted calculation is performed on each of the pollution-generating data segments to obtain the target pollution-generating data sequence.

[0130] Optionally, the simulation module 203 is also used to match the target simulation model corresponding to the operating condition under the current operating condition, and each operating condition corresponds to one target simulation model; transmit the operating parameters of the color line under the current operating condition to the target simulation model in real time, and set a fourth time period; output the pollution simulation result of the color line in the fourth time period under the current operating condition through the target simulation model.

[0131] Optionally, the simulation module 203 is also used to keep the operating parameters in the first time period unchanged through the historical data processing unit; update the reference operating parameters in the second time period according to the operating parameters in the first time period through the reference data processing unit, keep the reference operating parameters similar or the same as the operating parameters in the second time period, and obtain the model prediction parameters in the second time period, the first time period is before the second time period, and the end time of the second time period is the current moment or between the current moment; update the pollution simulation results of the fourth time period according to the operating parameters in the third time period and the model prediction parameters in the second time period through the output data processing unit, the third time period takes the current time as the end time, the length of the third time period is the same as the length of the first time period, and the fourth time period is after the third time period.

[0132] Optionally, the determination module 204 is also used to obtain the confidence of the pollution simulation result for the current operating condition, and the confidence is output by the target simulation model, and the above-mentioned pollution simulation result corresponds to a confidence; when the confidence is less than a first confidence threshold, the pollution detection result of the color line under the current operating condition is determined according to the pollution simulation result at the next moment; when the confidence is greater than or equal to the first confidence threshold, and less than a second confidence threshold, the pollution simulation result is compensated according to the compensation coefficient corresponding to the current operating condition, and the compensated pollution simulation result is determined as the pollution detection result of the color line under the current operating condition, and the second confidence threshold is greater than the first confidence threshold; when the confidence is greater than or equal to the second confidence threshold, the pollution simulation result is determined as the pollution detection result of the color line under the current operating condition.

[0133] The color line contamination detection device provided in the embodiment of the present invention can implement each process implemented by the color line contamination detection method in the above method embodiment, and can achieve the same beneficial effect. To avoid repetition, it will not be described here.

[0134] See also Figure 3 , Figure 3 is a schematic diagram of the structure of an electronic device provided by an embodiment of the present invention, such as Figure 3 As shown, it includes: a memory 302, a processor 301, and a computer program of a color line contamination detection method stored in the memory 302 and executable on the processor 301, wherein:

[0135] The processor 301 is used to call the computer program stored in the memory 302 and execute the following steps:

[0136] Based on the equipment structure and parameters of the color-coding line, an initial simulation model of the color-coding line is constructed;

[0137] Under different working conditions, the initial simulation model is first adjusted according to the historical operation data of the color line, and the initial simulation model is second adjusted according to the historical pollution generation data of the color line to obtain target simulation models of different working conditions, each working condition corresponds to a target simulation model;

[0138] The color line is simulated by the corresponding target simulation model to obtain the pollution simulation results under different working conditions;

[0139] Based on the pollution simulation result, the pollution detection result of the color matching line under different working conditions is determined.

[0140] Optionally, the step of first adjusting the initial simulation model according to the historical operation data of the color line under different working conditions executed by the processor 301 includes:

[0141] Obtaining historical operating data of the color set line under various working conditions;

[0142] For each operating condition, the historical operating data is fitted or predicted in multiple dimensions to obtain multi-dimensional operating parameters, and each operating condition corresponds to one of the multi-dimensional operating parameters;

[0143] A first adjustment is performed on the initial simulation model based on the multi-dimensional operating parameters.

[0144] Optionally, the step of performing a second adjustment on the initial simulation model by using the historical pollution data of the color line performed by the processor 301 includes:

[0145] Obtaining historical pollution generation data of the color line under various working conditions;

[0146] For each operating condition, the historical pollution generation data is divided by time period to obtain a pollution generation data sequence, each operating condition corresponds to a pollution generation data sequence, and each pollution generation data sequence includes N pollution generation data segments sorted by time period;

[0147] Considering the pollution residue, weight calculation is performed on the pollution generation data sequence to obtain the target pollution generation data sequence;

[0148] Predicting the target pollution generation data sequence through a time series prediction network to obtain predicted pollution source parameters, each operating condition corresponding to one predicted pollution source parameter;

[0149] A second adjustment is performed on the initial simulation model based on the predicted pollution source parameters.

[0150] Optionally, the step of taking into account the pollution residue and performing weight calculation on the pollution generation data sequence to obtain a target pollution generation data sequence executed by the processor 301 includes:

[0151] Determine the time sequence of each of the pollution generating data segments;

[0152] According to the time sequence, the pollution weight of each of the pollution generating data segments is determined. The later the time sequence, the greater the pollution weight. The pollution weight is calculated according to the following formula:

[0153]

[0154] Among them, W i represents the pollution weight of the pollution-generating data segment at the i-th time sequence, t i represents the time interval from the i-th time sequence to the start time, N represents the number of pollution-generated data segments, and softmax() represents the normalization function;

[0155] A weighted calculation is performed on each of the pollution generating data segments based on the pollution weight to obtain a target pollution generating data sequence.

[0156] Optionally, the step of simulating the color line by using the corresponding target simulation model to obtain pollution simulation results under different working conditions executed by the processor 301 includes:

[0157] Under the current working condition, matching the target simulation model corresponding to the working condition, each working condition corresponds to one target simulation model;

[0158] The operating parameters of the color line under the current working condition are transmitted to the target simulation model in real time, and a fourth time period is set;

[0159] The pollution simulation result of the color line in the fourth time period under the current working condition is outputted through the target simulation model.

[0160] Optionally, the target simulation model includes a historical data processing unit, a reference data processing unit and an output data processing unit, and the historical data processing unit, the data processing unit and the output data processing unit are continuous in time; the step of obtaining the pollution simulation result of the color line under the current working condition through the target simulation model data executed by the processor 301 includes:

[0161] Maintaining the operating parameters in the first period unchanged by the historical data processing unit;

[0162] The reference data processing unit updates the reference operating parameters in the second time period according to the operating parameters in the first time period, keeps the reference operating parameters similar to or the same as the operating parameters in the second time period, and obtains the model prediction parameters in the second time period, the first time period is before the second time period, and the end time of the second time period is the current time or between the current time and the reference operating parameters in the second time period;

[0163] The output data processing unit updates the pollution simulation results of the fourth time period based on the operating parameters in the third time period and the model prediction parameters in the second time period. The third time period takes the current time as the end time, the length of the third time period is the same as the length of the first time period, and the fourth time period is after the third time period.

[0164] Optionally, the step of determining the pollution detection result of the color wire under different working conditions based on the pollution simulation result, performed by the processor 301, includes:

[0165] For the current working condition, obtain the confidence of the pollution simulation result, the confidence is output by the target simulation model, and the pollution simulation result corresponds to a confidence;

[0166] When the confidence level is less than a first confidence level threshold, the pollution detection result of the color set line under the current working condition is determined according to the pollution simulation result at the next moment;

[0167] When the confidence is greater than or equal to a first confidence threshold and less than a second confidence threshold, the pollution simulation result is compensated according to the compensation coefficient corresponding to the current working condition, and the compensated pollution simulation result is defined as the pollution detection result of the color line under the current working condition, and the second confidence threshold is greater than the first confidence threshold;

[0168] When the confidence level is greater than or equal to the second confidence level threshold, the pollution simulation result is determined as the pollution detection result of the color wire under the current working condition.

[0169] The electronic device provided by the embodiment of the present invention can implement each process implemented by the color line contamination detection method in the above method embodiment, and can achieve the same beneficial effect. To avoid repetition, it will not be described here.

[0170] An embodiment of the present invention also provides a computer-readable storage medium, on which a computer program is stored. When the computer program is executed by a processor, the various processes of the color line contamination detection method or the application-end color line contamination detection method provided by the embodiment of the present invention are implemented, and the same technical effect can be achieved. To avoid repetition, it will not be repeated here.

[0171] A person skilled in the art can understand that all or part of the processes in the above-mentioned embodiments can be implemented by instructing the relevant hardware through a computer program, and the computer program can be stored in a computer-readable storage medium. When the program is executed, it can include the processes of the embodiments of the above-mentioned methods. The computer-readable storage medium can be a disk, an optical disk, a read-only memory (ROM) or a random access memory (RAM).

[0172] The above disclosure is only the preferred embodiment of the present invention, which certainly cannot be used to limit the scope of the present invention. Therefore, equivalent changes made according to the claims of the present invention are still within the scope of the present invention.

Claims

1. A color line contamination detection method, characterized in that: include: Based on the equipment structure and parameters of the color-coding line, an initial simulation model of the color-coding line is constructed; Under different working conditions, the initial simulation model is first adjusted by the historical operation data of the color line, and the initial simulation model is second adjusted by the historical pollution generation data of the color line to obtain target simulation models of different working conditions, each working condition corresponds to a target simulation model; the color line is simulated by the corresponding target simulation model to obtain pollution simulation results under different working conditions; Based on the pollution simulation result, the pollution detection result of the color matching line under different working conditions is determined.

2. The method according to claim 1, characterized in that The step of first adjusting the initial simulation model according to the historical operation data of the color line under different working conditions comprises: Obtaining historical operating data of the color set line under various working conditions; For each operating condition, the historical operating data is fitted or predicted in multiple dimensions to obtain multi-dimensional operating parameters, and each operating condition corresponds to one of the multi-dimensional operating parameters; A first adjustment is performed on the initial simulation model based on the multi-dimensional operating parameters.

3. The method according to claim 2, characterized in that The step of performing a second adjustment on the initial simulation model by generating data of historical pollution of the color line comprises: Obtaining historical pollution generation data of the color line under various working conditions; For each operating condition, the historical pollution generation data is divided by time period to obtain a pollution generation data sequence, each operating condition corresponds to a pollution generation data sequence, and each pollution generation data sequence includes N pollution generation data segments sorted by time period; Considering the pollution residue, weight calculation is performed on the pollution generation data sequence to obtain the target pollution generation data sequence; Predicting the target pollution generation data sequence through a time series prediction network to obtain predicted pollution source parameters, each operating condition corresponding to one predicted pollution source parameter; A second adjustment is performed on the initial simulation model based on the predicted pollution source parameters.

4. The method according to claim 3, characterized in that The step of taking into account the pollution residue and performing weight calculation on the pollution generation data sequence to obtain the target pollution generation data sequence comprises: Determine the time sequence of each of the pollution generating data segments; According to the time sequence, the pollution weight of each of the pollution generating data segments is determined. The later the time sequence, the greater the pollution weight. The pollution weight is calculated according to the following formula: Among them, W i represents the pollution weight of the pollution-generating data segment at the i-th time sequence, t i represents the time interval from the i-th time sequence to the start time, N represents the number of pollution-generated data segments, and softmax() represents the normalization function; A weighted calculation is performed on each of the pollution generating data segments based on the pollution weight to obtain a target pollution generating data sequence.

5. The method according to any one of claims 1 to 4, characterized in that The step of simulating the color line by using the corresponding target simulation model to obtain the pollution simulation results under different working conditions includes: Under the current working condition, matching the target simulation model corresponding to the working condition, each working condition corresponds to one target simulation model; The operating parameters of the color line under the current working condition are transmitted to the target simulation model in real time, and a fourth time period is set; The pollution simulation result of the color line in the fourth time period under the current working condition is outputted through the target simulation model.

6. The method according to claim 5, characterized in that The target simulation model includes a historical data processing unit, a reference data processing unit and an output data processing unit, wherein the historical data processing unit, the reference data processing unit and the output data processing unit are continuous in time; The step of outputting the pollution simulation result of the color line under the current working condition through the target simulation model comprises: Maintaining the operating parameters in the first period unchanged by the historical data processing unit; The reference data processing unit updates the reference operating parameters in the second time period according to the operating parameters in the first time period, keeps the reference operating parameters similar to or the same as the operating parameters in the second time period, and obtains the model prediction parameters in the second time period, the first time period is before the second time period, and the end time of the second time period is the current time or between the current time and the reference operating parameters in the second time period; The output data processing unit updates the pollution simulation results of the fourth time period based on the operating parameters in the third time period and the model prediction parameters in the second time period. The third time period ends at the current time, the length of the third time period is the same as the length of the first time period, and the fourth time period is after the third time period.

7. The method according to claim 6, characterized in that The step of determining the pollution detection result of the color matching line under different working conditions based on the pollution simulation result includes: For the current working condition, obtain the confidence of the pollution simulation result, the confidence is output by the target simulation model, and the pollution simulation result corresponds to a confidence; When the confidence level is less than a first confidence level threshold, the pollution detection result of the color set line under the current working condition is determined according to the pollution simulation result at the next moment; When the confidence is greater than or equal to a first confidence threshold and less than a second confidence threshold, the pollution simulation result is compensated according to a compensation coefficient corresponding to the current working condition, and the compensated pollution simulation result is determined as the pollution detection result of the color line under the current working condition, and the second confidence threshold is greater than the first confidence threshold; When the confidence level is greater than or equal to the second confidence level threshold, the pollution simulation result is determined as the pollution detection result of the color wire under the current working condition.

8. A color line contamination detection device, characterized in that: The color line pollution detection device comprises: A construction module, used to construct an initial simulation model of the color set line based on the equipment structure and parameters of the color set line; An adjustment module, used for making a first adjustment to the initial simulation model under different working conditions by using the historical operation data of the color set line, and making a second adjustment to the initial square model by using the historical pollution generation data of the color set line, so as to obtain target simulation models under different working conditions, each working condition corresponding to a target simulation model; A simulation module, used to simulate the color line through the corresponding target simulation model to obtain pollution simulation results under different working conditions; A determination module is used to determine the pollution detection results of the color matching line under different working conditions based on the pollution simulation results.

9. An electronic device, characterized in that: include: A memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor implements the steps in the color line contamination detection method as claimed in any one of claims 1 to 7 when executing the computer program.

10. A computer-readable storage medium, characterized in that: The computer-readable storage medium stores a computer program, and when the computer program is executed by a processor, the steps of the color line contamination detection method according to any one of claims 1 to 7 are implemented.

Citation Information

Patent Citations

  • Waste gas treatment system for coating color chromatography line

    CN113440976A

  • Boiler scaling fault prediction method, device, equipment and medium

    CN116738862A

  • Battery life prediction method and system, terminal device, and computer readable medium

    WO2024045567A1