Project cost measuring and calculating method and device for automobile industry
By constructing a project cost prediction model and splitting the projects to be predicted into bids, the problem of inaccurate cost prediction in the existing technology is solved, the accuracy and reliability of automobile project cost estimation are achieved, and project management costs are reduced.
Patent Information
- Application Number
- CN202410810370.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-21
- Publication Date
- 2024-10-01
AI Technical Summary
Existing project cost calculation methods lack scientific basis and are difficult to accurately reflect the actual cost composition and changing trends of automobile projects, resulting in inaccurate cost forecasts.
By collecting historical automobile project data, we build a project cost prediction model, split the project to be forecast into multiple bids, and use the model to find and update the costs of each bid to form the forecast cost of the project and ensure the accuracy and reliability of cost calculations. .
It improves the accuracy and reliability of project cost estimation, forms the lowest estimated cost of the project, and helps reduce automobile project management costs.
Smart Images

Figure CN118735561A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of project management, and provides a method and a device for calculating project cost in the automobile industry. Background Art
[0002] With the continuous development of my country's social economy, the number of large, medium and small enterprises has increased. Most enterprises achieve the growth of corporate value by continuously carrying out projects, and in the process of project development, they continuously improve their products and services to adapt to market development.
[0003] With the rapid development of the automotive industry, the automotive industry involves the management of hundreds or thousands of projects, and project cost control is crucial for enterprises. In order to ensure the profitability of related projects, enterprises need to predict the costs of each stage of the project before signing the project contract.
[0004] Existing project cost estimation methods are often based on the experience of project managers. This method of project cost estimation lacks scientific basis and has the problem of difficulty in accurately reflecting the actual cost structure and changing trends of the project. Summary of the invention
[0005] In view of this, the present application provides a project cost estimation method for the automotive industry, aiming to improve the above-mentioned problems.
[0006] Specifically, the following technical solutions are included:
[0007] On the one hand, an embodiment of the present application provides a project cost estimation method for the automotive industry, the method comprising:
[0008] (1) Collect historical project data of historical automobile projects, split the collected historical project data, and form project cost samples;
[0009] (2) Based on the automobile projects, the project cost samples are classified and a project cost prediction model is constructed for each type of automobile project. The project cost prediction model uses the bidding sections that make up the corresponding type of automobile project as nodes, and the nodes record the minimum cost of the corresponding bidding section;
[0010] (3) determining the automobile project type to which the current automobile project to be predicted belongs, and reading the project cost prediction model of the automobile project type;
[0011] (4) The automobile project to be predicted is divided into multiple sections to be predicted, and the cost of each section to be predicted is searched in the read project cost prediction model to form the predicted cost of the automobile project to be predicted.
[0012] In some embodiments of the present invention, the method for constructing a project cost prediction model is specifically as follows:
[0013] (21) Obtain a sample of all project costs for this type of automotive project;
[0014] (22) For each project cost Yi, perform the following operations: extract all the bid sections that constitute the project cost sample Yi and put them into the bid section set B, extract one bid section Bj from the bid section set B in turn, and perform the following steps for each bid section Bj:
[0015] Check whether section Bj exists in the project cost prediction model corresponding to the automobile project type. If the detection result is no, section Bj is used as a new node of the corresponding project cost prediction model, and the cost of section Bj in the project cost sample data is added to the node. If the detection result is yes, check whether the cost of section Bj in the project cost sample is lower than the cost in the corresponding project cost prediction model. If the detection result is yes, the cost of section Bj in the corresponding project cost prediction model is updated to the cost of section Bj in the project cost sample.
[0016] In some embodiments of the present invention, when it is detected that the predicted bid section does not exist in the read project cost prediction model, the bid section to be predicted is used as a new node in the project cost prediction model, and the corresponding bid section cost is assigned to the new node.
[0017] In some embodiments of the present invention, after step (4), the method further includes:
[0018] (5) After the automobile project to be predicted is completed, all the bidding sections and their actual costs that constitute the automobile project are obtained to form a new project cost sample, which is used to update the project cost prediction model for the automobile project type.
[0019] In some embodiments of the present invention, the updating process of the project cost prediction model is specifically as follows:
[0020] Find the cost of all the bid sections in the sample of the project in the project cost prediction model of the automobile project type;
[0021] For bidding sections whose actual costs are lower than the corresponding node costs in the project cost prediction model, the costs of the bidding sections in the project cost prediction model will be updated to the actual costs. For bidding sections whose actual costs are higher than the corresponding node costs in the project cost prediction model, the costs of the nodes in the project cost prediction model will be kept unchanged.
[0022] In some embodiments of the present invention, for a bid section whose actual cost is higher than the corresponding node cost in the project cost prediction model, the bid section is marked in the corresponding automobile project, and the actual cost of the bid section and the time when the actual cost occurred are recorded.
[0023] In some embodiments of the present invention, after all predicted bid sections constituting the automobile project to be predicted are obtained, it is detected whether there is a mark in the predicted bid section. If there is, the cost of the marked bid section is determined. The cost determination process of the marked bid section is specifically as follows:
[0024] Monitor the cost change trend of the marked section. If the cost of the marked section shows an upward trend, fit the cost increase curve of the marked section with the recorded cost of the marked section as the vertical axis and time as the horizontal axis, and determine the current cost of the marked section based on the cost increase curve.
[0025] On the other hand, an embodiment of the present application provides a project cost estimation device for the automotive industry, the device comprising:
[0026] The project splitting unit, the bid section cost prediction unit, the project cost prediction unit, the model updating unit and the storage unit are connected in sequence, and the bid section cost prediction unit is connected to the storage unit, wherein:
[0027] The project splitting unit is used to split the automobile project to be predicted into multiple bid sections to be predicted;
[0028] The bidding section cost prediction unit is used to obtain the costs of all predicted bidding sections;
[0029] The project cost forecasting unit is used to calculate the sum of the costs of the forecasted bidding sections to form the forecasted cost of the automobile project to be forecasted;
[0030] The model updating unit is used to update the cost of the bid section corresponding to the existing node in the project cost prediction model or to add a new node to the project cost prediction model and record the cost of the bid section corresponding to the new node;
[0031] A storage unit is used to store project cost prediction models of various automobile projects.
[0032] In some embodiments of the present invention, the bid section cost prediction unit includes:
[0033] The bid section detection module, the bid section cost reading module and the bid section cost setting module connected to the bid section detection module, wherein:
[0034] The section detection module is used to detect whether the predicted section exists in the project cost prediction model of the corresponding automobile project. If so, the section cost reading module directly reads the cost of the node where the predicted section is located from the corresponding project cost prediction model. If not, the cost of the predicted node is set through the section cost setting module, and the project cost prediction model of the corresponding automobile project is updated through the model updating unit.
[0035] In some embodiments of the present invention, the device further comprises:
[0036] A data acquisition unit connected to the model updating unit;
[0037] After the automobile project to be predicted is completed, the data collection unit collects the actual costs of all predicted sections of the automobile project, and the model updating unit updates the cost of the node where the predicted section is located in the corresponding project cost prediction model based on the actual cost of the predicted section, and updates it to the minimum cost of the section corresponding to the node.
[0038] The present invention constructs a project cost prediction model for different automobile projects through a large amount of project cost sample data. The project cost prediction model includes various bidding sections of this type of automobile project and the historical lowest costs of the bidding sections. The automobile project to be predicted is divided into several bidding sections, and then the costs corresponding to these bidding sections are found from the project cost prediction model to form the estimated cost of the project. This provides a basis for the accuracy and reliability of project cost estimation, and forms the lowest estimated cost of the project, which is beneficial to reducing the project management cost of the automobile. BRIEF DESCRIPTION OF THE DRAWINGS
[0039] In order to more clearly illustrate the technical solutions in the embodiments of the present application, the drawings required for use in the description of the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.
[0040] Figure 1 A flow chart of a project cost estimation method for the automotive industry provided by an embodiment of the present invention;
[0041] Figure 2 A schematic diagram of the structure of a project cost estimation device for the automotive industry provided by an embodiment of the present invention;
[0042] The above drawings have shown clear embodiments of the present application, which will be described in more detail later. These drawings and text descriptions are not intended to limit the scope of the present application in any way, but to illustrate the concept of the present application to those skilled in the art by referring to specific embodiments. DETAILED DESCRIPTION
[0043] The following will be combined with the drawings in the embodiments of the present application to clearly and completely describe the technical solutions in the embodiments of the present application. Obviously, the described embodiments are part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.
[0044] Figure 1 A flow chart of a method for calculating project cost in the automotive industry provided by an embodiment of the present invention, the method comprising the following steps:
[0045] (1) Collect historical project data of historical automobile projects, clean and split the collected historical project data to form project cost samples, which include the bid sections that make up the project and the cost of each bid section;
[0046] Cleaning of project data includes: removing irrelevant data, deleting abnormal data, etc., and splitting the cleaned project data. In the automotive project, some projects can be split into multiple bids, and some smaller projects have no bids. For historical projects without bids, there is no need to split the historical projects. Directly treat the historical projects as basic units and record the costs of the historical projects. Therefore, the specific method for splitting project data is as follows:
[0047] Check whether there is a bid section in the historical project. If the check result is yes, split the historical project into multiple bid sections and record the cost of each bid section. If there is no bid section in the historical project, record the cost of the historical project.
[0048] (2) Based on the automobile projects, the project cost samples are classified and a project cost prediction model is constructed for each type of automobile project. The project cost prediction model uses the bidding sections that make up the corresponding project type as nodes, and the nodes record the historical lowest cost of the corresponding bidding section;
[0049] The present invention classifies automobile projects into: tooling and molds, KD packaging, logistics and transportation, equipment, spare parts, infrastructure projects, advertising, intelligent manufacturing, R&D consulting, steel, and petrochemicals. A project cost prediction model is constructed for each of the above automobile projects. The construction method of the project cost prediction model is as follows:
[0050] (21) Obtain a sample of all project costs for this type of automotive project;
[0051] (22) For each project cost Yi, perform the following operations: extract all the bid sections that constitute the project cost sample Yi and put them into the bid section set B, extract a bid section Bj from the bid section set B in turn, and perform the following steps for the bid section Bj:
[0052] (221) Detect whether the bid section Bj exists in the project cost prediction model corresponding to the automobile project type;
[0053] (222) If the test result is negative, then the bid section Bj and its cost in the project cost sample data are added to the corresponding project cost prediction model, that is, the bid section Bj is used as a new node of the corresponding project cost prediction model, and the cost of the bid section Bj in the project cost sample data is added to the node;
[0054] (223) If the test result is yes, then check whether the cost of section Bj in the project cost sample is lower than the cost in the corresponding project cost prediction model. If the test result is yes, then update the cost of section Bj in the corresponding project cost prediction model to the cost of section Bj in the project cost sample. If the test result is no, there is no need to update the corresponding project cost prediction model.
[0055] (23) All the project cost sample data of this type of automobile project are traversed in sequence to form a project cost prediction model for this type of automobile project. If there are new project cost samples of this type of automobile project added later, the project cost prediction model for this type of automobile project will continue to be updated.
[0056] (3) determining the automobile project type to which the automobile project to be predicted belongs, and reading the project cost prediction model of the automobile project type;
[0057] (4) The automobile project to be predicted is divided into multiple sections to be predicted, and the cost of each section to be predicted is searched in the read project cost prediction model. The sum of the costs of all the sections to be predicted that constitute the automobile project to be predicted constitutes the predicted cost of the automobile project to be predicted.
[0058] In an embodiment of the present invention, the automobile project to be tested is split into several bid sections, and the bid sections split from the predicted automobile project are the bid sections to be predicted. After obtaining all the bid sections to be predicted that constitute the project to be predicted, each bid section to be predicted is checked in turn to see whether it exists in the project cost prediction model of the automobile project type. If it exists, the cost of the corresponding bid section to be predicted is directly read. If it does not exist, the bid section to be predicted is used as a new node in the project cost prediction model of the automobile project type, and a cost is assigned to the bid section corresponding to the new node. The cost can be estimated manually.
[0059] In the embodiment of the present invention, after step (4), the following steps are further included:
[0060] (5) After the automobile project to be predicted is completed, all the bidding sections and their actual costs that constitute the automobile project are obtained to form a new project cost sample, which is used to update the project cost prediction model for the automobile project type.
[0061] In the embodiment of the present invention, the updating process of the project cost prediction model is as follows:
[0062] The costs of all the bid sections that make up the project cost sample are searched in the project cost prediction model for the automobile project type; for the bid section whose actual cost is lower than the corresponding node cost, the cost of the bid section in the project cost prediction model is updated to the actual cost; for the bid section whose actual cost is higher than the corresponding node cost in the project cost prediction model, the cost of the node in the project cost prediction model is kept unchanged; all the bid sections in the new project cost sample are traversed to complete the update of the project cost prediction model for the automobile project type.
[0063] In an embodiment of the present invention, for a bidding section whose actual cost is higher than the corresponding node cost in the project cost prediction model, the bidding section is marked in the corresponding automobile project, and the actual cost of the bidding section and the time when the actual cost occurred are recorded. Since the labor cost of bidding sections with a high degree of correlation is constantly rising, if the cost prediction of such bidding sections is always carried out based on the principle of lowest cost, the predicted cost is not in line with market laws. For bidding sections with a high degree of correlation with electronic products, due to the development of science and technology, their costs show a downward trend. At this time, it is more reasonable to use the principle of lowest cost to predict the cost of such bidding sections.
[0064] Based on this, after the automobile project to be predicted is split to obtain the predicted bid sections of the automobile project to be predicted, the present invention detects whether there are marks in the predicted bid sections. If none of them exist, the project cost prediction of the automobile project to be predicted is completed based on step (4). If so, for the unmarked bid sections, the cost of the corresponding predicted bid sections is read from the project cost prediction model. For the marked bid sections, the cost of the marked bid sections is determined based on the following method. The cost determination process of the marked bid sections is as follows:
[0065] Monitor the cost change trend of the marked section. If the cost of the marked section shows an upward trend, fit the cost increase curve of the marked section with the recorded cost of the marked section as the vertical axis and time as the horizontal axis, and determine the current cost of the marked section based on the cost increase curve.
[0066] Of course, it is also possible that some predicted sections do not exist in the corresponding project cost prediction model. In this case, the predicted section serves as a new node of the corresponding project cost prediction model and is given an estimated cost as the initial cost.
[0067] The present invention constructs a project cost prediction model for different automobile projects through a large amount of project cost sample data. The project cost prediction model includes various bidding sections of this type of automobile project and the historical lowest costs of the bidding sections. The automobile project to be predicted is divided into several bidding sections, and then the costs corresponding to these bidding sections are found from the project cost prediction model to form the estimated cost of the project. This provides a basis for the accuracy and reliability of project cost estimation, and forms the lowest estimated cost of the project, which is beneficial to reducing the project management cost of the automobile.
[0068] Figure 2 A schematic diagram of the structure of a project cost estimation device for the automotive industry provided by an embodiment of the present invention. For ease of description, only the parts related to the embodiment of the present invention are shown. The device includes:
[0069] The project splitting unit, the bid section cost prediction unit, the project cost prediction unit, the model updating unit and the storage unit are connected in sequence, and the bid section cost prediction unit is connected to the storage unit, wherein:
[0070] The project splitting unit is used to split the automobile project to be predicted into multiple bid sections to be predicted;
[0071] The bidding section cost prediction unit is used to obtain the costs of all predicted bidding sections;
[0072] The project cost forecasting unit is used to calculate the sum of the costs of the forecasted bidding sections to form the forecasted cost of the automobile project to be forecasted;
[0073] The model updating unit is used to update the cost of the section corresponding to the existing node in the project cost prediction model or to add a new node in the project cost prediction model and record the cost of the section corresponding to the new node. The construction process of the project cost prediction model is the same as the cost estimation method of the above-mentioned automotive industry project and will not be repeated here.
[0074] The storage unit is used to store project cost prediction models of various types of automobile projects. The project cost prediction models are constructed based on project cost sample data of corresponding types of automobile projects.
[0075] In an embodiment of the present invention, the bid section cost prediction unit includes: a bid section detection module, a bid section cost reading module connected to the bid section detection module, and a bid section cost setting module, wherein:
[0076] The section detection module is used to detect whether the predicted section exists in the project cost prediction model of the corresponding automobile project. If so, the section cost reading module directly reads the cost of the node where the predicted section is located from the corresponding project cost prediction model. If not, the cost of the predicted node is set through the section cost setting module, and the project cost prediction model of the corresponding automobile project is updated through the model updating unit.
[0077] In an embodiment of the present invention, the device further comprises: a data acquisition unit connected to the model updating unit;
[0078] After the automobile project to be predicted is completed, the data collection unit collects the actual costs of all predicted sections of the automobile project. The model updating unit updates the cost of the node where the predicted section is located in the corresponding project cost prediction model based on the actual cost of the predicted section, updates it to the minimum cost of the section corresponding to the node, and updates it to the storage unit.
[0079] Unless otherwise defined, all technical terms used in the embodiments of the present application have the same meanings as commonly understood by those of ordinary skill in the art.
[0080] Those skilled in the art will readily appreciate other embodiments of the present application after considering the specification and practicing the present application disclosed herein. The present application is intended to cover any variations, uses or adaptations of the present application, which follow the general principles of the present application and include common knowledge or customary techniques in the art that are not disclosed in the present application. The specification and examples are intended to be exemplary only.
[0081] It should be understood that the present application is not limited to the precise structures that have been described above and shown in the drawings, and that various modifications and changes may be made without departing from the scope thereof. The scope of the present application is limited only by the appended claims.
Claims
1. A project cost estimation method for the automotive industry, characterized in that: The method comprises: (1) Collect historical project data of historical automobile projects, split the collected historical project data, and form project cost samples; (2) Based on the automobile projects, the project cost samples are classified and a project cost prediction model is constructed for each type of automobile project. The project cost prediction model uses the bidding sections that make up the corresponding type of automobile project as nodes, and the nodes record the minimum cost of the corresponding bidding section; (3) determining the automobile project type to which the current automobile project to be predicted belongs, and reading the project cost prediction model of the automobile project type; (4) The automobile project to be predicted is divided into multiple sections to be predicted, and the cost of each section to be predicted is searched in the read project cost prediction model to form the predicted cost of the automobile project to be predicted.
2. The project cost estimation method for the automotive industry as claimed in claim 1, characterized in that: The construction method of the project cost prediction model is as follows: (21) Obtain a sample of all project costs for this type of automotive project; (22) For each project cost Yi, perform the following operations: extract all the bid sections that constitute the project cost sample Yi and put them into the bid section set B, extract one bid section Bj from the bid section set B in turn, and perform the following steps for each bid section Bj: Check whether section Bj exists in the project cost prediction model corresponding to the automobile project type. If the detection result is no, section Bj is used as a new node of the corresponding project cost prediction model, and the cost of section Bj in the project cost sample data is added to the node. If the detection result is yes, check whether the cost of section Bj in the project cost sample is lower than the cost in the corresponding project cost prediction model. If the detection result is yes, the cost of section Bj in the corresponding project cost prediction model is updated to the cost of section Bj in the project cost sample.
3. The project cost estimation method for the automotive industry as claimed in claim 1, characterized in that: When it is detected that the predicted bid section does not exist in the read project cost prediction model, the bid section to be predicted is used as a new node in the project cost prediction model, and the corresponding bid section cost is assigned to the new node.
4. The project cost estimation method for the automotive industry as claimed in claim 1, characterized in that: After step (4), the method further includes: (5) After the automobile project to be predicted is completed, all the bidding sections and their actual costs that constitute the automobile project are obtained to form a new project cost sample, which is used to update the project cost prediction model for the automobile project type.
5. The project cost estimation method for the automotive industry as claimed in claim 4, characterized in that: The update process of the project cost forecast model is as follows: Find the cost of all the bid sections in the sample of the project in the project cost prediction model of the automobile project type; For bidding sections whose actual costs are lower than the corresponding node costs in the project cost prediction model, the costs of the bidding sections in the project cost prediction model will be updated to the actual costs. For bidding sections whose actual costs are higher than the corresponding node costs in the project cost prediction model, the costs of the nodes in the project cost prediction model will be kept unchanged.
6. The project cost estimation method for the automotive industry as claimed in claim 5, characterized in that: For the bidding section whose actual cost is higher than the corresponding node cost in the project cost prediction model, mark the bidding section in the corresponding automobile project, and record the actual cost of the bidding section and the time when the actual cost occurred.
7. The project cost estimation method for the automotive industry as claimed in claim 6, characterized in that: After obtaining all the forecast bid sections constituting the automobile project to be forecasted, it is detected whether there is a mark in the forecast bid section. If so, the cost of the marked bid section is determined. The cost determination process of the marked bid section is as follows: Monitor the cost change trend of the marked section. If the cost of the marked section shows an upward trend, fit the cost increase curve of the marked section with the recorded cost of the marked section as the vertical axis and time as the horizontal axis, and determine the current cost of the marked section based on the cost increase curve.
8. A project cost estimation device for the automobile industry, characterized in that: The device comprises: The project splitting unit, the bid section cost prediction unit, the project cost prediction unit, the model updating unit and the storage unit are connected in sequence, and the bid section cost prediction unit is connected to the storage unit, wherein: The project splitting unit is used to split the automobile project to be predicted into multiple bid sections to be predicted; The bidding section cost prediction unit is used to obtain the costs of all predicted bidding sections; The project cost forecasting unit is used to calculate the sum of the costs of the forecasted bidding sections to form the forecasted cost of the automobile project to be forecasted; The model updating unit is used to update the cost of the bid section corresponding to the existing node in the project cost prediction model or to add a new node to the project cost prediction model and record the cost of the bid section corresponding to the new node; A storage unit is used to store project cost prediction models of various automobile projects.
9. The project cost estimation device for the automobile industry as claimed in claim 8, characterized in that: The bidding section cost forecasting unit includes: The bid section detection module, the bid section cost reading module and the bid section cost setting module connected to the bid section detection module, wherein: The section detection module is used to detect whether the predicted section exists in the project cost prediction model of the corresponding automobile project. If so, the section cost reading module directly reads the cost of the node where the predicted section is located from the corresponding project cost prediction model. If not, the cost of the predicted node is set through the section cost setting module, and the project cost prediction model of the corresponding automobile project is updated through the model updating unit.
10. The project cost estimation device for the automobile industry as claimed in claim 8, characterized in that: The device also includes: A data acquisition unit connected to the model updating unit; After the automobile project to be predicted is completed, the data collection unit collects the actual costs of all predicted sections of the automobile project, and the model updating unit updates the cost of the node where the predicted section is located in the corresponding project cost prediction model based on the actual cost of the predicted section, and updates it to the minimum cost of the section corresponding to the node.
Citation Information
Patent Citations
Real estate cost data processing method and device, computer equipment and storage medium
CN113095963A
Cost prediction method, modeling method of cost prediction model and electronic equipment
CN117217784A
Enhanced project predictor
US7949663B1