Box transformer substation temperature early warning system suitable for thermal power plant
Patent Information
- Application Number
- CN202410625020.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-20
- Publication Date
- 2024-10-01
AI Technical Summary
The existing box-type transformer temperature early warning system can only trigger an early warning when the temperature reaches a set threshold, but cannot handle it automatically. Moreover, its safety and security are relatively simple, and it cannot monitor abnormal activities around the box-type transformer.
A system including a monitoring module, a temperature analysis module and an early warning processing module is designed. Through real-time monitoring of the box temperature and surrounding video activities, the temperature changes are analyzed, an abnormality evaluation index is generated, and corresponding steps are automatically executed, such as cutting off the load and adjusting heat dissipation. Components or trigger fault repairs, combined with image recognition technology to determine abnormal activities.
It improves the efficiency of automatic processing of temperature warnings, enhances safety monitoring around box-type transformers, achieves faster response and fault handling, and comprehensively improves the level of intelligent monitoring of thermal power plants.
Smart Images

Figure CN118736792A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of thermal power plant early warning, and in particular to a box transformer temperature early warning system suitable for thermal power plants. Background Art
[0002] In the daily operation of thermal power plants, it is crucial to ensure the safe and stable operation of power equipment. Among them, the box-type transformer is a key equipment for power transmission, and its internal temperature monitoring is of great significance for preventing equipment failures and ensuring the safety of the power grid.
[0003] However, the temperature warning system of the box transformer in the prior art still has the following shortcomings:
[0004] Most of them trigger an early warning when the temperature of the box transformer reaches the set threshold, and notify personnel to handle it. Personnel need to search for the cause of the temperature warning by themselves and handle it accordingly. The early warning processing efficiency is low. It cannot output the possibility of abnormal temperature of the box transformer at the current time point based on the temperature change in the set time period before the early warning, and execute the corresponding steps. The automatic processing capability is low;
[0005] It cannot be combined with the existing monitoring module of the thermal power plant to monitor abnormal activities within a set range around the box-type transformer to trigger an early warning. It can only issue an early warning for the temperature of the box-type transformer, and the safety guarantee is relatively simple.
[0006] Therefore, a temperature early warning system for box-type transformers in thermal power plants is introduced. Summary of the invention
[0007] In view of this, the present invention provides a temperature early warning system for a box transformer applicable to a thermal power plant to solve the problems raised by the above background technology.
[0008] The purpose of the present invention can be achieved through the following technical solutions: A temperature early warning system for a box transformer in a thermal power plant, comprising:
[0009] Monitoring module: It consists of a front-end video acquisition unit, a mid-end signal transmission unit, and a back-end data processing unit. Based on the above units, it monitors and records the train's entry and exit conditions and the real-time status of the box transformer, and sends out corresponding alarm signals after determining the train's travel direction;
[0010] Temperature analysis module: collects and records the temperature changes inside the box transformer in real time, sets the temperature reference threshold, and if the box transformer temperature reaches the set reference threshold at a certain time point, a temperature warning signal is triggered and sent to the warning processing module;
[0011] Early warning processing module: receives temperature early warning signals and analyzes the temperature changes within a set time period before the current temperature early warning signal is generated, and executes corresponding steps based on the results of the temperature change analysis; obtains monitoring videos of a set range around the thermal power plant transformer in real time; captures the video through the front-end video acquisition unit in the monitoring module; when a moving object is detected on the monitoring video, determines abnormal activity and executes corresponding steps.
[0012] In some embodiments, the temperature change within a set time period before the current temperature warning signal is generated is analyzed, specifically:
[0013] Extract the temperature value of the box transformer at each time point within the set time period, and substitute it into the line graph for representation, draw the value points corresponding to the box transformer temperature value at each time point in the line graph, connect the adjacent value points to obtain the change line, calculate the slope of each change line and the angle with the horizontal line respectively, when the angle between the change line and the horizontal line is an acute angle, mark the slope of the change line as a descending slope; when the angle between the change line and the horizontal line is an obtuse angle, mark it as an ascending slope; sum up all the values of the descending slope to obtain the descending value and mark it as K1, sum up all the values of the ascending slope and take the absolute value to obtain the ascending value and mark it as K2;
[0014] Connect the first numerical point in the line graph with the last numerical point in the line graph to obtain a line segment and mark the line segment as the total rate line, calculate the slope of the total rate line and the angle with the horizontal line, when the angle between the total rate line and the horizontal line is an acute angle, mark the slope of the total rate line as the total descending slope, and the value of the total descending slope is represented by the symbol M1; when the angle between the total rate line and the horizontal line is an obtuse angle, mark the slope of the total rate line as the total ascending slope, and the absolute value of the total ascending slope is represented by the symbol M2;
[0015] Calculate the vertical distance between the highest value point and the lowest value point and mark the value of the vertical distance as K3; use the formula WD = (K2 / K1) × a1 + Mi × a2 + K3 × a3 for weighted calculation to obtain the rate estimation value WD of the box transformer temperature of the thermal power plant within the set time period; where i = 1 or 2; a1, a2 and a3 are influencing weight factors.
[0016] In some embodiments, analyzing the temperature change within a set time period before the current temperature warning signal is generated further includes:
[0017] Obtain the average value of the temperature value of the box transformer at each time point in the set time period, and calculate the ratio between the average value and the reference threshold value as the difference ratio WG of the box transformer of the thermal power plant in the set time period;
[0018] Substitute the rate estimate WD and the difference ratio WG into the formula A weighted calculation is performed to obtain the abnormal evaluation index λ of the thermal power plant transformer within the set time period; where t1 and t2 are the influencing weight factors of the rate estimate WD and the difference ratio WG respectively.
[0019] In some embodiments, corresponding steps are performed based on the results of the temperature change analysis, specifically:
[0020] A reference threshold range of the abnormality assessment index λ is set, and if the abnormality assessment index λ is within the reference threshold range, a personnel search signal is generated;
[0021] When a personnel search signal is generated, the temperature change data and video images of the thermal power plant transformer in the set time period are extracted, the video images are combined with the temperature data of the transformer, and displayed on the computer unit in the monitoring room through the back-end data processing unit. The staff checks the video and the temperature change of the transformer to determine the cause of triggering the temperature warning signal and conduct further detection;
[0022] If the abnormal evaluation index λ is higher than the highest value within the reference threshold range, an operation warning signal is generated; when the operation warning signal is generated, step S1 is first executed:
[0023] S1: Check the load of the box-type transformer. If the load of the box-type transformer is abnormal, cut off the non-critical loads in the power plant at the current time. If the load of the box-type transformer is normal, execute step S2:
[0024] S2: extracting the ambient temperature data around the box transformer within a set time period; using the standard deviation formula to calculate the ambient temperature data at each time point within the set time period, taking the calculated value as the ambient value estimation of the box transformer within the set time period, and comparing the ambient value estimation with the set ambient reference threshold. If it is greater than the set ambient reference threshold, adjusting the power of the heat dissipation component in the box transformer; if it is less than the set ambient reference threshold, executing step S3;
[0025] S3: Obtain the service life of the box transformer at the current time point and the number of repairs within the service life; set weight coefficients for the service life and the number of repairs; multiply the service life and the number of repairs of the box transformer at the current time point by the set weight coefficients respectively, and then sum them to obtain the estimated aging value of the box transformer at the current time point, further match the estimated aging value of the box transformer at the current time point with the set aging value ranges, set each aging value range to correspond to the maximum continuous operation time of a box transformer, obtain the maximum continuous operation time of the box transformer corresponding to the current time point, and count the continuous operation time of the box transformer corresponding to the current time point; compare the obtained maximum continuous operation time with the continuous operation time at the current time point, if the continuous operation time is greater than the maximum continuous operation time, stop the operation of the box transformer and send a maintenance signal to the mobile terminal of the repair personnel; if the continuous operation time is less than the maximum continuous operation time, further trigger a personnel retrieval signal.
[0026] In some embodiments, executing corresponding steps based on the results of the temperature change analysis further includes:
[0027] If the abnormal evaluation index λ is lower than the lowest value within the reference threshold range, a fault warning signal is generated; when the fault warning signal is generated, step U1 is first executed;
[0028] U1: Draw a circle with the transformer in the thermal power plant as the fault circle center and the distance as the radius, select the repair personnel with the closest route within the circle, and output the possible cause of the transformer failure to the mobile terminal of the personnel; after the repair personnel arrive at the transformer site, they will conduct investigation and repair based on the possible cause of the failure. If the investigation fails, execute step U2;
[0029] U2: Get all the repairmen within the circle; the repairmen in step U1 are not included in the circle; calculate their route distance and record it as LX; further get the working years and maintenance times of each repairman, record them as LY and LG respectively;
[0030] According to the formula Calculate the optimal maintenance value YC of each repairman within the circle at the current time point; e is a preset constant with a value of 1.097; h1, h2 and h3 are the influencing weight factors of route distance LX, working years LY and maintenance times LG respectively; select the repairman with the largest optimal maintenance value YC as the problem solver, and send the specific location of the box transformer to the mobile terminal of the repairman, and the maintenance times of the repairman are increased by one.
[0031] In some embodiments, corresponding steps are performed when abnormal activities are determined, specifically:
[0032] Use image recognition technology to determine the specific type of moving objects in the current monitoring video. If the recognition result is an animal, it will be edited into video clips of corresponding lengths based on the set monitoring time period, and the video clips will be marked as animal activity clips;
[0033] Obtain the highest number of animals present, the duration of animal presence, and the closest distance between the animal and the box from the animal activity clips, and mark the highest number of animals present, the duration of animal presence, and the closest distance between the animal and the box as P1, P2, and P3, respectively; substitute P1, P2, and P3 into the formula Perform weighted calculation to obtain the animal warning index β within the set range around the box transformer in the current animal activity segment; where b1, b2 and b3 are the influence weight factors of P1, P2 and P3 respectively;
[0034] The animal warning index β within the set range around the transformer in the current animal activity segment is compared with the set reference index threshold. If it is greater than the set reference index threshold, the animal abnormality warning signal is triggered and an alarm is sent to the monitoring room. After receiving the alarm, the staff extracts the current animal activity segment and decides whether it is necessary to control the broadcasting around the transformer to send out an interference signal of the set frequency to disperse the animals.
[0035] If the mobile object recognition result is a person, the time zone information of the current recognition time point is obtained, and the obtained time zone information is compared with the working time zone of the thermal power plant. If the comparison result shows a non-working time zone, the image information of the person is further obtained, and the face information in the image information is extracted and matched with the face information of each staff member pre-stored in the database. If the match fails, an abnormal person warning signal is triggered and an alarm is sent to the monitoring room. After receiving the alarm, the staff extracts the activity clips of the abnormal person and decides whether it is necessary to control the broadcasting around the box transformer to send out a prompt voice to remind the abnormal person.
[0036] Compared with the prior art, the present invention has the following beneficial effects:
[0037] The present invention detects and handles potential problems that lead to temperature warning of the box transformer at the current time point by triggering a warning when the temperature reaches a threshold value, and executing corresponding steps based on the temperature change analysis results within a set time period before the warning is triggered. The automated processing flow improves the response speed to abnormal situations, and helps to quickly restore normal operation. It solves the problem that most of the prior arts trigger a warning when the box transformer temperature reaches a set threshold value, and notify personnel to handle it, and personnel need to retrieve the cause of the temperature warning by themselves and handle it accordingly, which leads to low warning processing efficiency.
[0038] The present invention acquires monitoring video of a set range around the thermal power plant box transformer in real time by combining with the monitoring module of the thermal power plant. When a moving object is detected on the monitoring video, abnormal activity is determined and corresponding processing is performed based on the analysis result. The problem that only the box transformer temperature can be warned in the prior art and the safety guarantee is relatively single is solved, and the intelligent level of monitoring and warning of the thermal power plant box transformer is comprehensively improved. BRIEF DESCRIPTION OF THE DRAWINGS
[0039] Further details, features and advantages of the present application are disclosed in the following description of exemplary embodiments in conjunction with the accompanying drawings, in which:
[0040] Figure 1 It is a principle block diagram of the present invention. DETAILED DESCRIPTION
[0041] Several embodiments of the present application will be described in more detail below with reference to the accompanying drawings so that those skilled in the art can implement the present application. The present application can be embodied in many different forms and purposes and should not be limited to the embodiments described herein. These embodiments are provided to make the present application comprehensive and complete, and to fully convey the scope of the present application to those skilled in the art. The embodiments do not limit the present application.
[0042] Unless otherwise defined, all terms (including technical and scientific terms) used herein have the same meaning as commonly understood by those of ordinary skill in the art to which this application belongs. It will be further understood that terms such as those defined in commonly used dictionaries should be interpreted as having a meaning consistent with their meaning in the context of the relevant art and / or this specification, and will not be interpreted in an idealized or overly formal sense, unless explicitly defined as such herein.
[0043] See also Figure 1 As shown, a temperature early warning system for a box transformer in a thermal power plant includes a monitoring module, a temperature analysis module and an early warning processing module;
[0044] The monitoring module consists of a front-end video acquisition unit, a mid-end signal transmission unit, and a back-end data processing unit. Based on the above units, it monitors and records the train's entry and exit conditions and the real-time status of the box transformer, and sends out corresponding alarm signals after determining the train's travel direction; sound and light indication devices are installed at railway crossings and monitoring rooms;
[0045] It should be noted that by real-time monitoring of the entry and exit of trains, potential safety issues can be discovered in a timely manner, such as pedestrians or vehicles that mistakenly enter restricted areas, so that preventive measures can be taken to avoid accidents. At the same time, it is not only possible to monitor the entry and exit of trains, but also to effectively monitor the box transformers in thermal power plants, thereby improving the safety management level of thermal power plants.
[0046] The front-end video acquisition unit is mainly composed of a gun camera and a high-speed dome camera;
[0047] The gun camera monitors fixed points and cannot be controlled remotely; the high-speed ball camera integrates a zoom camera, a pan / tilt head, and a pan / tilt head controller. The camera can be controlled remotely to change its azimuth, pitch, zoom, rotation, etc., thereby changing the scope of the monitoring area. At the same time, the zoom can also be used to capture close-ups; the high-speed ball can rotate 360 degrees and can zoom in and out the video, making it convenient to monitor a certain point, and it can also be used for patrols and observations. The best monitoring point should be selected according to the actual situation on site, and the lightning protection of the camera should also be considered;
[0048] The mid-end signal transmission unit uses HSWD-TV wireless video transmission to transmit video signals; the live video signals collected by the front-end camera are transmitted to the control room through the HSWD-TV module, and point-to-point or point-to-multipoint transmission can be used to avoid the trouble of wiring; the wireless communication method only requires the installation of a wireless video transmission module receiving master station in the control center, and the erection of an omnidirectional antenna at a certain height; each monitoring point is respectively installed with a wireless video transmission module sending slave station, and a directional antenna is used to correspond to the master station, and the wireless transmission of video is achieved by adjusting the antenna angle with the receiving master station;
[0049] The back-end data processing unit uses a video decoder to convert high-definition digital signals into universal analog signals; it can directly output high-definition network signals or convert them into BNC standard interfaces for easy compatibility with existing systems.
[0050] The back-end data processing unit can be divided into the following items:
[0051] The back-end display part processes the video signal sent back from the site and displays the signal on the computer unit, which is displayed by the system monitor and can also be upgraded to a seamless large-screen TV wall display. By adding large-screen display units, video matrix units, and control units, more video monitoring points can be incorporated and all monitoring images can be displayed. Each monitor displays a monitoring screen separately. Through the digital matrix setting, each monitor can patrol all monitoring screens. It can also be connected to the original monitoring system of the thermal power plant to achieve seamless transition, unified connection, and reserve expansion interfaces for future upgrades and expansions.
[0052] The back-end recording part uses a digital hard disk recorder to store video images; to ensure the quality of dynamic images, each camera image is recorded at 25 frames per second, and the video information is retained for more than 30 days; to ensure the quality of the video, the D1 (704*576) video format is used to ensure that the video image playback can achieve the D1 effect, which is conducive to the evidence collection and analysis of the event; the motion detection function is set on the digital hard disk recorder, that is, the video is stored only when there is an object moving on the monitoring screen, so as to save hard disk space and ensure that the video is stored for a longer time;
[0053] The back-end control part consists of a hard disk recorder, a digital matrix and a monitoring host. The mouse can be used to switch the monitoring screen on the hard disk recorder and control the rotation and zoom functions of the high-speed ball on the machine. The digital matrix is mainly used to switch the monitoring images in the monitors on the TV wall, and the monitoring images can be set to switch freely in the monitors, switch programs, and switch timing. The high-speed ball control is mainly operated by the mouse to realize the high-speed ball's two-point scanning, cruising, pattern scanning, setting preset points, calling preset points and other functions.
[0054] The back-end network part is connected to the local area network of the monitoring center through a network cable, allowing authorized users in the local area network to view monitoring images at any time.
[0055] The temperature analysis module collects and records the temperature changes inside the box-type transformer in real time through the temperature sensor installed inside the box-type transformer, sets the temperature reference threshold, and triggers the temperature warning signal if the box-type transformer temperature reaches the set reference threshold at a certain time point and sends it to the warning processing module;
[0056] The warning processing module is used to receive the temperature warning signal and analyze the temperature change in the set time period before the current temperature warning signal is generated, output the possibility of abnormal temperature of the box transformer at the current time point based on the analysis result, and execute the corresponding steps;
[0057] Specifically:
[0058] Extract the temperature value of the box transformer at each time point within the set time period, and substitute it into the line graph for representation, draw the value points corresponding to the box transformer temperature value at each time point in the line graph, connect the adjacent value points to obtain the change line, calculate the slope of each change line and the angle with the horizontal line respectively, when the angle between the change line and the horizontal line is an acute angle, mark the slope of the change line as a descending slope; when the angle between the change line and the horizontal line is an obtuse angle, mark it as an ascending slope; sum up all the values of the descending slope to obtain the descending value and mark it as K1, sum up all the values of the ascending slope and take the absolute value to obtain the ascending value and mark it as K2;
[0059] Connect the first numerical point in the line graph with the last numerical point in the line graph to obtain a line segment and mark the line segment as the total rate line, calculate the slope of the total rate line and the angle with the horizontal line, when the angle between the total rate line and the horizontal line is an acute angle, mark the slope of the total rate line as the total descending slope, and the value of the total descending slope is represented by the symbol M1; when the angle between the total rate line and the horizontal line is an obtuse angle, mark the slope of the total rate line as the total ascending slope, and the absolute value of the total ascending slope is represented by the symbol M2;
[0060] Calculate the vertical distance between the highest value point and the lowest value point and mark the value of the vertical distance as K3; use the formula WD = (K2 / K1) × a1 + Mi × a2 + K3 × a3 for weighted calculation to obtain the rate estimation value WD of the box transformer temperature of the thermal power plant within the set time period; where i = 1 or 2; a1, a2 and a3 are influencing weight factors, and the values are set to 1.138, 1.132 and 1.135 respectively;
[0061] It should be noted that the rate valuation WD of the box transformer temperature within the set time period of the thermal power plant is obtained through weighted calculation. The larger the rate valuation WD, the faster the temperature inside the box transformer changes, and the smaller the rate valuation WD, the more stable the temperature change inside the box transformer. This can reflect the temperature change of the box transformer before the current temperature warning signal is triggered, providing data support for subsequent analysis.
[0062] Further obtain the average value of the temperature value of the box transformer at each time point in the set time period, and calculate the ratio between the average value and the reference threshold value as the difference ratio WG of the box transformer of the thermal power plant in the set time period;
[0063] It should be noted that the smaller the difference between the difference ratio WG and the integer one, the more the temperature change within the set time period is gradually approaching the reference threshold and triggering the temperature warning signal; on the contrary, the larger the difference is, the more the box transformer temperature rises suddenly and triggers the temperature warning signal; thus reflecting the triggering status of the current box transformer temperature warning and providing a basis for subsequent evaluation.
[0064] Substitute the rate estimate WD and the difference ratio WG in the above parameters into the formula A weighted calculation is performed to obtain the abnormal evaluation index λ of the thermal power plant transformer within the set time period; where t1 and t2 are the influence weight factors of the rate estimate WD and the difference ratio WG, and their values are set to 1.129 and 1.125 respectively;
[0065] A reference threshold range of the abnormality assessment index λ is set, and if the abnormality assessment index λ is within the reference threshold range, a personnel search signal is generated;
[0066] When a personnel search signal is generated, the temperature change data and video images of the thermal power plant transformer in the set time period are extracted, the video images are combined with the temperature data of the transformer, and displayed on the computer unit in the monitoring room through the back-end data processing unit. The staff views the video and the temperature change of the transformer, determines the cause of the triggering temperature warning signal and conducts further detection; at the same time, the results of the triggered temperature warning signal and the personnel search signal are integrated into the established database for updating;
[0067] It should be noted that by integrating and updating the results of staff searches, the historical staff search results can be directly pushed when a staff search signal is subsequently generated, providing a scientific basis for subsequent processing and reducing the staff's search workload.
[0068] If the abnormal evaluation index λ is higher than the highest value within the reference threshold range, an operation warning signal is generated; when the operation warning signal is generated, step S1 is first executed:
[0069] S1: Check the load of the box-type transformer. If the load of the box-type transformer is abnormal, cut off the non-critical loads in the power plant at the current time. If the load of the box-type transformer is normal, execute step S2:
[0070] S2: extracting the ambient temperature data around the box transformer within a set time period; the collection points of the ambient temperature are selectively installed by the technicians; using the standard deviation formula to calculate the ambient temperature data at each time point within the set time period, taking the calculated value as the ambient value estimation of the box transformer within the set time period, and comparing the ambient value estimation with the set ambient reference threshold. If it is greater than the set ambient reference threshold, adjusting the power of the heat dissipation components in the box transformer; for example, adjusting the power of the heat dissipation fan and the heat sink; if it is less than the set ambient reference threshold, executing step S3;
[0071] S3: Obtain the service life of the transformer at the current time point and the number of repairs within the service life; set the weight coefficients of the service life and the number of repairs; the technician sets it based on the transformer model, and can adjust it later based on the application accuracy; multiply the service life and the number of repairs of the transformer at the current time point by the set weight coefficient, and then sum them to obtain the estimated aging value of the transformer at the current time point, and further match the estimated aging value of the transformer at the current time point with the set aging value ranges, set each aging value range to correspond to the maximum continuous operation time of a transformer, obtain the maximum continuous operation time of the transformer at the current time point, and count the continuous operation time of the transformer at the current time point; the unit of continuous operation time is set to hours; compare the obtained maximum continuous operation time with the continuous operation time at the current time point, if the continuous operation time is greater than the maximum continuous operation time, stop the transformer and send a maintenance signal to the mobile terminal of the repair personnel; if the continuous operation time is less than the maximum continuous operation time, further trigger the personnel retrieval signal;
[0072] It should be noted that the automated processing flow reduces reliance on manual monitoring and operation, reduces labor costs, improves response speed to abnormal situations, and helps to quickly resume normal operations.
[0073] If the abnormal evaluation index λ is lower than the lowest value within the reference threshold range, a fault warning signal is generated; when the fault warning signal is generated, step U1 is first executed;
[0074] U1: Draw a circle with the transformer of the thermal power plant as the center of the fault circle and the distance as the radius, select the repair personnel with the closest route within the circle, and output the possible causes of the transformer failure to the mobile terminal of the personnel; the possible causes of the failure include but are not limited to short circuit of the equipment transformer, circuit breaker failure, damage to the cooling system and damage to the insulation material, and the above causes of failure are ranked by percentage based on the specific value of the abnormal evaluation index λ; after the repair personnel arrive at the transformer site, they will check and repair based on the possible causes of the failure. If the check fails, execute step U2;
[0075] U2: Get all the repairmen within the circle; the repairmen in step U1 are not included in the circle; calculate their route distance and record it as LX; further get the working years and maintenance times of each repairman, record them as LY and LG respectively;
[0076] According to the formula Calculate the optimal maintenance value YC of each repairman within the circle at the current time point; e is a preset constant, with a value of 1.097; h1, h2 and h3 are the influence weight factors of route distance LX, working years LY and maintenance times LG, and their values are set to 1.658, 1.663 and 1.667 respectively; select the repairman with the largest optimal maintenance value YC as the problem solver, and send the specific location of the box transformer to the mobile terminal of the repairman, and the maintenance times of the repairman are increased by one;
[0077] It should be noted that based on the specific value of the abnormal assessment index, the possible causes of the fault are ranked by percentage to help maintenance personnel determine the priority of the investigation. Further, when the repair personnel fail to find the cause, the repair personnel within the circle are re-screened. By weighted calculation of the route distance, working years and maintenance times of each repair personnel, it is ensured that the selected repair personnel have the ability to independently handle specific faults, thereby improving the maintenance efficiency and success rate. At the same time, it also improves the efficiency and effectiveness of fault handling of thermal power plant box transformers, ensuring the safe, reliable and efficient operation of the power system.
[0078] The early warning processing module is also used to obtain the monitoring video of the set range around the thermal power plant box transformer in real time; it is captured by the front-end video acquisition unit in the monitoring module; when a moving object is detected on the monitoring video, it determines abnormal activity and executes the corresponding steps:
[0079] Use image recognition technology to determine the specific type of moving objects in the current monitoring video. If the recognition result is an animal, it will be edited into video clips of corresponding lengths based on the set monitoring time period, and the video clips will be marked as animal activity clips;
[0080] Obtain the highest number of animals present, the duration of animal presence, and the closest distance between the animal and the box from the animal activity clips, and mark the highest number of animals present, the duration of animal presence, and the closest distance between the animal and the box as P1, P2, and P3, respectively; substitute P1, P2, and P3 into the formula A weighted calculation is performed to obtain the animal warning index β within the set range around the transformer in the current animal activity segment; b1, b2 and b3 are the influence weight factors of P1, P2 and P3, and their values are set to 1.157, 1.148 and 1.154 respectively;
[0081] The animal warning index β within the set range around the transformer in the current animal activity segment is compared with the set reference index threshold. If it is greater than the set reference index threshold, the animal abnormality warning signal is triggered and an alarm is sent to the monitoring room. After receiving the alarm, the staff extracts the current animal activity segment and decides whether it is necessary to control the broadcasting around the transformer to send out an interference signal of the set frequency to disperse the animals.
[0082] It should be noted that based on the above, thermal power plants can more effectively manage and reduce the potential risks posed by wild animals to box-type transformer equipment, while reducing dependence on manual monitoring and improving safety and operational efficiency.
[0083] If the mobile object recognition result is a person, the time zone information of the current recognition time point is obtained, and the obtained time zone information is compared with the working time zone of the thermal power plant. If the comparison result shows a non-working time zone, the image information of the person is further obtained, the face information in the image information is extracted and matched with the face information of each staff member pre-stored in the database. If the match fails, the abnormal person warning signal is triggered and an alarm is sent to the monitoring room. After receiving the alarm, the staff extracts the activity clips of the abnormal person and decides whether it is necessary to control the broadcasting around the box transformer to send a prompt voice to remind the abnormal person; the prompt voice can be set to "You have entered a restricted area. For your safety, please leave immediately";
[0084] It should be noted that based on the above-mentioned thermal power plant, it is able to improve the monitoring capabilities of non-working hours or unauthorized personnel, timely detect potential security threats and issue early warnings, and take corresponding preventive or response measures, thereby enhancing the security protection of the entire area.
[0085] If the specific types of moving objects include humans and animals, the recognition result is determined to be a human;
[0086] It should be noted that according to the actual warning situation and effect, technicians can adjust the image recognition algorithm, warning index calculation formula and reference threshold to optimize the accuracy and efficiency of the warning system.
[0087] It also includes a data storage module for storing the above-mentioned analyzed content and data, and establishing a relevant database for real-time updating;
[0088] The preferred embodiments of the present invention disclosed above are only used to help explain the present invention. The preferred embodiments do not describe all the details in detail, nor do they limit the invention to only specific implementation methods. Obviously, many modifications and changes can be made according to the content of this specification. This specification selects and specifically describes these embodiments in order to better explain the principles and practical applications of the present invention, so that those skilled in the art can understand and use the present invention well. The present invention is limited only by the claims and their full scope and equivalents.
Claims
1. A temperature early warning system for a box transformer in a thermal power plant, characterized in that: include: Monitoring module: It consists of a front-end video acquisition unit, a mid-end signal transmission unit, and a back-end data processing unit. Based on the above units, it monitors and records the train's entry and exit conditions and the real-time status of the box transformer, and sends out corresponding alarm signals after determining the train's travel direction; Temperature analysis module: collects and records the temperature changes inside the box transformer in real time, sets the temperature reference threshold, and if the box transformer temperature reaches the set reference threshold at a certain time point, a temperature warning signal is triggered and sent to the warning processing module; Early warning processing module: receives temperature early warning signals and analyzes the temperature changes within a set time period before the current temperature early warning signal is generated, and executes corresponding steps based on the results of the temperature change analysis; obtains monitoring videos of a set range around the thermal power plant transformer in real time; captures the video through the front-end video acquisition unit in the monitoring module; when a moving object is detected on the monitoring video, determines abnormal activity and executes corresponding steps.
2. A temperature early warning system for a box transformer in a thermal power plant according to claim 1, characterized in that: Analyze the temperature changes within the set time period before the current temperature warning signal is generated, specifically: Extract the temperature value of the box transformer at each time point within the set time period, and substitute it into the line graph for representation, draw the value points corresponding to the box transformer temperature value at each time point in the line graph, connect the adjacent value points to obtain the change line, calculate the slope of each change line and the angle with the horizontal line respectively, when the angle between the change line and the horizontal line is an acute angle, mark the slope of the change line as a descending slope; when the angle between the change line and the horizontal line is an obtuse angle, mark it as an ascending slope; sum up all the values of the descending slope to obtain the descending value and mark it as K1, sum up all the values of the ascending slope and take the absolute value to obtain the ascending value and mark it as K2; Connect the first numerical point in the line graph with the last numerical point in the line graph to obtain a line segment and mark the line segment as the total rate line, calculate the slope of the total rate line and the angle with the horizontal line, when the angle between the total rate line and the horizontal line is an acute angle, mark the slope of the total rate line as the total descending slope, and the value of the total descending slope is represented by the symbol M1; when the angle between the total rate line and the horizontal line is an obtuse angle, mark the slope of the total rate line as the total ascending slope, and the absolute value of the total ascending slope is represented by the symbol M2; Calculate the vertical distance between the highest value point and the lowest value point and mark the value of the vertical distance as K3; The formula WD = (K2 / K1) × a1 + Mi × a2 + K3 × a3 is used for weighted calculation to obtain the rate estimation value WD of the box transformer temperature of the thermal power plant within the set time period; where i = 1 or 2; a1, a2 and a3 are influencing weight factors.
3. A temperature early warning system for a box transformer in a thermal power plant according to claim 2, characterized in that: Analyzing the temperature change in a set time period before the current temperature warning signal is generated, further comprising: Obtain the average value of the temperature value of the box transformer at each time point in the set time period, and calculate the ratio between the average value and the reference threshold value as the difference ratio WG of the box transformer of the thermal power plant in the set time period; Substitute the rate estimate WD and the difference ratio WG into the formula A weighted calculation is performed to obtain the abnormal evaluation index λ of the thermal power plant transformer within the set time period; where t1 and t2 are the influencing weight factors of the rate estimate WD and the difference ratio WG respectively.
4. A temperature early warning system for a box transformer in a thermal power plant according to claim 3, characterized in that: Based on the results of the temperature change analysis, corresponding steps are performed, specifically: A reference threshold range of the abnormality assessment index λ is set, and if the abnormality assessment index λ is within the reference threshold range, a personnel search signal is generated; When a personnel search signal is generated, the temperature change data and video images of the thermal power plant transformer in the set time period are extracted, the video images are combined with the temperature data of the transformer, and displayed on the computer unit in the monitoring room through the back-end data processing unit. The staff checks the video and the temperature change of the transformer to determine the cause of triggering the temperature warning signal and conduct further detection; If the abnormal evaluation index λ is higher than the highest value within the reference threshold range, an operation warning signal is generated; when the operation warning signal is generated, step S1 is first executed: S1: Check the load of the box-type transformer. If the load of the box-type transformer is abnormal, cut off the non-critical loads in the power plant at the current time. If the load of the box-type transformer is normal, execute step S2: S2: extracting the ambient temperature data around the box transformer within a set time period; using the standard deviation formula to calculate the ambient temperature data at each time point within the set time period, taking the calculated value as the ambient value estimation of the box transformer within the set time period, and comparing the ambient value estimation with the set ambient reference threshold. If it is greater than the set ambient reference threshold, adjusting the power of the heat dissipation component in the box transformer; if it is less than the set ambient reference threshold, executing step S3; S3: Obtain the service life of the box transformer at the current time point and the number of repairs within the service life; set weight coefficients for the service life and the number of repairs; multiply the service life and the number of repairs of the box transformer at the current time point by the set weight coefficients respectively, and then sum them to obtain the estimated aging value of the box transformer at the current time point, further match the estimated aging value of the box transformer at the current time point with the set aging value ranges, set each aging value range to correspond to the maximum continuous operation time of a box transformer, obtain the maximum continuous operation time of the box transformer corresponding to the current time point, and count the continuous operation time of the box transformer corresponding to the current time point; The maximum continuous operating time obtained is compared with the continuous operating time at the current time point. If the continuous operating time is greater than the maximum continuous operating time, the operation of the box transformer is stopped and a maintenance signal is sent to the mobile terminal of the repair personnel; if the continuous operating time is less than the maximum continuous operating time, a personnel retrieval signal is further triggered.
5. A temperature early warning system for a box transformer in a thermal power plant according to claim 4, characterized in that: Executing corresponding steps based on the results of the temperature change analysis further includes: If the abnormal evaluation index λ is lower than the lowest value within the reference threshold range, a fault warning signal is generated; when the fault warning signal is generated, step U1 is first executed; U1: Draw a circle with the transformer in the thermal power plant as the fault circle center and the distance as the radius, select the repair personnel with the closest route within the circle, and output the possible cause of the transformer failure to the mobile terminal of the personnel; after the repair personnel arrive at the transformer site, they will conduct investigation and repair based on the possible cause of the failure. If the investigation fails, execute step U2; U2: Get all the repairmen within the circle; the repairmen in step U1 are not included in the circle; calculate their route distance and record it as LX; further get the working years and maintenance times of each repairman, record them as LY and LG respectively; According to the formula Calculate the optimal maintenance value YC of each repairman within the circle at the current time point; e is a preset constant with a value of 1.097; h1, h2 and h3 are the influencing weight factors of route distance LX, working years LY and maintenance times LG respectively; select the repairman with the largest optimal maintenance value YC as the problem solver, and send the specific location of the box transformer to the mobile terminal of the repairman, and the maintenance times of the repairman are increased by one.
6. A temperature early warning system for a box transformer in a thermal power plant according to claim 5, characterized in that: When abnormal activities are identified, corresponding steps are executed, specifically: Use image recognition technology to determine the specific type of moving objects in the current monitoring video. If the recognition result is an animal, it will be edited into video clips of corresponding lengths based on the set monitoring time period, and the video clips will be marked as animal activity clips; Obtain the highest number of animals present, the duration of animal presence, and the closest distance between the animal and the box from the animal activity clips, and mark the highest number of animals present, the duration of animal presence, and the closest distance between the animal and the box as P1, P2, and P3, respectively; substitute P1, P2, and P3 into the formula Perform weighted calculation to obtain the animal warning index β within the set range around the box transformer in the current animal activity segment; where b1, b2 and b3 are the influence weight factors of P1, P2 and P3 respectively; The animal warning index β within the set range around the transformer in the current animal activity segment is compared with the set reference index threshold. If it is greater than the set reference index threshold, the animal abnormality warning signal is triggered and an alarm is sent to the monitoring room. After receiving the alarm, the staff extracts the current animal activity segment and decides whether it is necessary to control the broadcasting around the transformer to send out an interference signal of the set frequency to disperse the animals. If the mobile object recognition result is a person, the time zone information of the current recognition time point is obtained, and the obtained time zone information is compared with the working time zone of the thermal power plant. If the comparison result shows a non-working time zone, the image information of the person is further obtained, and the face information in the image information is extracted and matched with the face information of each staff member pre-stored in the database. If the match fails, an abnormal person warning signal is triggered and an alarm is sent to the monitoring room. After receiving the alarm, the staff extracts the activity clips of the abnormal person and decides whether it is necessary to control the broadcasting around the box transformer to send out a prompt voice to remind the abnormal person.
Citation Information
Cited By
Power station early warning method based on historical data, electronic equipment and system
CN119742915A
Self-cleaning micro flow cell for optical instrument
CN120195106A