Distributed energy storage optimization automatic configuration method for new energy station

Through the optimization and automatic configuration method of distributed energy storage for new energy stations, the problem of high or insufficient investment cost in the existing technology is solved, the precise configuration and economic improvement of distributed energy storage are achieved, and the development of the new energy industry is promoted. High quality development.

CN118739364APending Publication Date: 2024-10-01SHANGHAI MINGHUA ELECTRIC POWER TECH & ENG
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410754109.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-06-12
Publication Date
2024-10-01

AI Technical Summary

Technical Problem

The existing technology lacks an optimal allocation method for decentralized energy storage in new energy stations, resulting in high or insufficient investment costs and difficulty in meeting individual needs.

Method used

A decentralized energy storage optimization automatic configuration method for new energy stations is proposed, which includes collecting energy storage related data, formulating operation strategies, calculating unit size and maximum capacity, establishing an optimal configuration model, and evaluating before and after configuration through value theory changes in income to achieve optimal economical configuration throughout the life cycle.

Benefits of technology

It achieves precise configuration of distributed energy storage, improves economy, avoids over- or under-investment, improves the utilization efficiency and market flexibility of new energy stations, and promotes the high-quality development of the new energy industry.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118739364A_ABST
    Figure CN118739364A_ABST
Patent Text Reader

Abstract

The invention relates to a new energy station-oriented distributed energy storage optimization automatic configuration method. The method comprises the following steps of S1, acquiring energy storage related data; s2, formulating an energy storage operation strategy according to the data collected in the step S1; s3, calculating the scale data of the distributed energy storage monomers; s4, calculating the maximum capacity data of the station-level energy storage; s5, establishing a distributed energy storage optimal configuration model; and S6, calculating the optimal configuration number of distributed energy storage. Compared with the prior art, the method has the advantages of improving the network-related performance of the new energy, guaranteeing efficient utilization of the new energy, excavating the value of the energy storage system to the greatest extent and the like.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of energy storage technology, and in particular to a distributed energy storage optimization automatic configuration method for new energy stations. Background Art

[0002] In recent years, many provinces in my country have intensively issued policies to encourage or force the configuration of energy storage for new energy, with the scale configuration ratio ranging from 10% to 20% and the energy storage duration ranging from 1 to 4 hours. Energy storage technology has become an important supporting infrastructure for the large-scale development of new energy. However, the overall investment cost of centralized energy storage and its supporting equipment (boosting stations, transmission lines) is relatively high, and forced configuration of energy storage will further deteriorate the economic efficiency of new energy projects. Therefore, according to the market environment and actual needs of different sites, it is necessary to customize the energy storage configuration plan to avoid over-investment or under-investment.

[0003] At present, a large number of optimization methods for configuring centralized energy storage at new energy stations have been accumulated both at home and abroad. The application scenarios mainly focus on smoothing output fluctuations, tracking output curves, improving absorption capacity, enhancing transmission capacity, participating in the auxiliary service market, etc., and the main goals are to minimize the operating cost of the energy storage system, minimize the capacity of the energy storage system, or optimize the economic efficiency of the energy storage project.

[0004] Up to now, all new energy stations are equipped with centralized energy storage and connected to 35kV busbars. In 2022, China began to try the "new energy + distributed energy storage" technical path, which has the following advantages: First, it reduces the risk level. Even if an accident occurs, it can effectively control fire risks such as large-scale fires; second, it saves investment costs and makes full use of the existing land space and box transformer surplus of new energy stations. There is no need for land acquisition or supporting booster stations, which reduces approval procedures and has little impact on the ecological environment; third, it increases power generation efficiency. Distributed energy storage can increase the online power by about 2% compared with centralized energy storage; fourth, it facilitates energy storage expansion. Distributed energy storage can respond to changes in policies and profit models more quickly.

[0005] After searching, Chinese patent publication number CN114256836A discloses a capacity optimization configuration method for shared energy storage of new energy power stations, which specifically discloses S1, designing an energy storage sharing mechanism based on a distributed shared energy storage architecture of a new energy power station group; S2, establishing a distributed shared energy storage cooperative game model for a new energy power station group that considers factors such as grid-connected electricity revenue and shared energy storage revenue; S3, taking the sharing of a new energy power station group under the same collection station environment as the scenario, and taking the energy storage capacity constructed by each new energy power station as the decision variable, using the particle swarm algorithm to solve the energy storage optimization configuration result. However, this existing patent is mainly aimed at shared energy storage, and does not involve distributed energy storage. Therefore, there is currently no research on the method of configuring distributed energy storage for new energy in China. Unlike centralized energy storage, which only needs to optimize the overall configuration scale, distributed energy storage needs to additionally consider the use of new energy station box transformers to optimize the scale and number of distributed energy storage units. Summary of the invention

[0006] The purpose of the present invention is to overcome the defects of the above-mentioned prior art and provide a distributed energy storage optimization automatic configuration method for new energy stations.

[0007] The purpose of the present invention can be achieved by the following technical solutions:

[0008] According to one aspect of the present invention, a distributed energy storage optimization automatic configuration method for a new energy station is provided, the method comprising the following steps:

[0009] Step S1, collecting energy storage related data;

[0010] Step S2, formulating an energy storage operation strategy based on the data collected in step S1;

[0011] Step S3, calculating the scale data of distributed energy storage units;

[0012] Step S4, calculating the maximum capacity data of the station-level energy storage;

[0013] Step S5, establishing a distributed energy storage optimal configuration model;

[0014] Step S6, calculating the optimal configuration quantity of distributed energy storage.

[0015] As a preferred technical solution, the energy storage related data includes policy and detailed information on energy storage in the area where the new energy station is located.

[0016] As a preferred technical solution, the energy storage-related policies and detailed information include energy storage programmatic documents, new energy storage policy, grid-connected operation management implementation rules, auxiliary service management implementation rules and electricity market operation transaction rules.

[0017] As a preferred technical solution, the calculation of the distributed energy storage monomer scale data is specifically as follows:

[0018] Statistics are collected on the rated parameters and actual usage of the box-type transformers, the margin of each box-type transformer is calculated, and the maximum power of a single distributed energy storage unit is determined.

[0019] As a preferred technical solution, the calculation of the maximum capacity data of the station-level energy storage is specifically as follows:

[0020] Count the number of box-type transformers that can be deployed around the station for distributed energy storage, and calculate the maximum capacity of the station-level energy storage based on the scale of a single distributed energy storage unit.

[0021] As a preferred technical solution, the establishment of the distributed energy storage optimal configuration model is specifically as follows:

[0022] Combined with the energy storage operation strategy formulated in step S2 and the calculation data of steps S3 and S4, a configuration model with the optimal economic efficiency over the entire life cycle of energy storage is established, and the actual condition boundary of the maximum capacity of site-level energy storage is considered in the constraints. The energy storage operation strategy includes strategies to reduce wind and solar power abandonment, output curve tracking strategy, peak load market participation strategy and distributed energy storage collaborative control strategy.

[0023] As a preferred technical solution, the strategy for reducing wind and solar power abandonment is specifically:

[0024] When the new energy station receives the wind and solar power abandonment during the t1-t2 period When the command is given, the station-level energy storage is used to absorb part of the abandoned power, P t d,ave and P t c,ave They represent the average power corresponding to the available power of the station-level energy storage in period t when all the available power is discharged and charged in that period, that is,

[0025]

[0026] In the formula, SOC max With SOC min Indicates the upper and lower limits of the station-level energy storage state of charge SOC; SOC t-1 represents the SOC at time t-1; E ES Configure capacity for station-level energy storage; η c With η d It represents the charging and discharging efficiency of energy storage at the station level; Δt is the time interval;

[0027] Charging strategy P for energy storage during the wind and solar curtailment period t1-t2 t c is:

[0028] P t c ≤min{Pt c,ave ,P t cut ,P PCS},t∈[t1,t2] (3)

[0029] Where P PCS The rated power of the PCS for the site-level energy storage;

[0030] The amount of energy storage added during the wind and solar curtailment period from t1 to t2 for:

[0031]

[0032] During the idle period of the transmission channel, the reduced amount of abandoned wind and photovoltaic power will be connected to the grid to increase the income from electricity sales and carbon income. The income of the new energy station before and after the configuration of the energy storage system is set to be V1 bef With V1 aft :

[0033]

[0034] In the formula, λ sell For the on-grid electricity price;

[0035] The output curve tracking strategy is specifically as follows:

[0036] Energy storage is used to track the output curve of new energy sources to reduce the assessment penalty for the part of active power output that exceeds the change rate limit;

[0037] In a grid without energy storage system, the assessment penalty V2 bef for:

[0038]

[0039]

[0040] In the formula, λ punish A is the assessment and punishment standard; t , B t P is the power of the new energy station that exceeds the upper and lower limits in the t period; t act is the actual power in the tth period; P t lim,up , P t lim,low The upper and lower limits of the power forecast assessment for the t-th period;

[0041] After the new energy station is equipped with an energy storage system, the assessment fine V2 must be paid aft for:

[0042]

[0043] In the formula, C t , D t P is the power exceeding the upper and lower limits in the tth period after the energy storage system is configured; t c , P t d is the charging and discharging power in period t.

[0044] As a preferred technical solution, the strategy for participating in the peak load-shaving market is specifically as follows:

[0045] When receiving the peak load regulation instruction during the period t3-t4, the new energy station evaluates its own reliable peak load regulation capacity. For the new energy station, its maximum upward regulation capacity depends on the energy storage capacity, and its maximum downward regulation capacity depends on the energy storage capacity and the maximum allowable abandoned light amount:

[0046]

[0047] Where P t max,up , P t max,down P is the adjustable up-capacity and down-capacity in the t period; t max,cut is the maximum allowable amount of wind and solar power curtailment;

[0048] The market revenue before and after configuring energy storage to participate in the peak load market is V3 bef With V3 aft :

[0049]

[0050] In the formula, is the willingness to participate in the peak load-shaving market in period t; f t anc (·) is the peak load market reward and punishment function; P t anc is the actual peak load regulation in the tth period; t anc is the peak load-shaving cost in period t;

[0051] The distributed energy storage collaborative control strategy is specifically as follows:

[0052] First, the status information of distributed energy storage needs to be integrated and summarized to become site-level energy storage;

[0053]

[0054]

[0055] Where: SOC i 、Ei max , P i max , P i min , k i are the state of charge, total capacity, maximum discharge power, maximum charging power and adjustability of the i-th group of energy storage; SOC i,j , SOH i,j , k i,j They are the SOC, health state SOH, rated capacity, maximum discharge power, maximum charging power and adjustability of the jth distributed energy storage in the i-th group;

[0056] According to the same method as above, the energy storage group is further merged into a virtual centralized energy storage, and the state parameters include SOC t , P t max ;

[0057] The total power command P of the station-level energy storage control is calculated bess ;

[0058] Then, according to the status of each energy storage group, the total power command P bess Distributed to each distributed energy storage group;

[0059]

[0060] P i bess =α i ·P bess (19)

[0061] Where: P i ave is the maximum charge and discharge power of the i-th group of energy storage in the current state; is the maximum and minimum SOC of the i-th group of energy storage; is the energy storage charging and discharging efficiency; α i is the power allocation coefficient of the i-th group of energy storage; P i bess is the power instruction of the i-th group of energy storage;

[0062] Based on the status of distributed energy storage within the group, the tasks are further decomposed into each distributed energy storage unit according to the same method mentioned above.

[0063] As a preferred technical solution, the configuration model with the best economic efficiency over the entire life cycle of energy storage is specifically:

[0064] 1) Present value of construction cost of station-level energy storage system C inv for:

[0065]

[0066] In the formula, is the energy storage investment cost at the beginning of year y; The unit capacity cost of energy storage; is the PCS unit cost; P PCS E is the rated power of the station-level energy storage PCS; ES is the station-level energy storage configuration capacity; T is the planning period; ρ is the discount rate;

[0067] 2) Present value of operation and maintenance cost of station-level energy storage system C mai for:

[0068]

[0069] In the formula, is the energy storage maintenance cost in year y; a and b are the estimated ratios of energy storage capacity and power operation and maintenance costs to initial investment;

[0070] 3) The present value of the system value brought by the configuration of energy storage in the new energy power plant is V ES :

[0071]

[0072] Where V1 bef With V1 aft The revenue of the new energy station before and after the energy storage system is deployed in the first year;

[0073] 4) Fixed asset depreciation calculation of the residual value S of the energy storage at the end of the planning period ES :

[0074]

[0075] In the formula, k = {1, 4, 7} is the end of the planning period; r1 is the depreciation rate of energy storage fixed assets;

[0076] 5) Objective function

[0077] Considering the investment cost, operation cost, operation value of energy storage during the planning period and the depreciation of fixed assets at the end of the planning period, an energy storage planning model with the goal of economic optimization is established:

[0078] min f total =C inv +C mai -V ES -S ES (26)

[0079] 6) Constraints

[0080]

[0081] SOC min ≤SOC t ≤SOC max (28)

[0082]

[0083] 0≤P t cut ≤P t act (32)

[0084] E ES =ωE ES,dec (33)

[0085] E ES <E ES,max (34)

[0086] In the formula, is the charging and discharging state; ω is the number of distributed energy storage, which is the decision variable of the model; E ES,dec For the scale of a single distributed energy storage unit, decisions are made through the previous steps; E ES,max It is the maximum capacity of energy storage at the station level; SOC t is the state of charge of the station-level energy storage at the tth moment; P t c is the charging power of the station-level energy storage at the tth moment; η c is the charging efficiency of energy storage at the station level; P t d is the discharge power of the station-level energy storage at the tth moment; η d is the energy storage discharge efficiency at the station level; Δt is the time interval; P t cut is the abandoned power of the station-level energy storage at the tth moment; P t act It is the actual power of the station-level energy storage at the t moment.

[0087] As a preferred technical solution, the calculation of the optimal configuration quantity of distributed energy storage is specifically as follows:

[0088] For existing new energy stations, the optimal number of distributed energy storage is optimized based on actual historical operation data;

[0089] For newly built new energy stations, refer to the operating data of similar new energy stations in the surrounding area to optimize the optimal amount of distributed energy storage.

[0090] Compared with the prior art, the present invention has the following advantages:

[0091] 1) The present invention establishes a configuration model for the optimal economic performance of distributed energy storage throughout its life cycle, and considers actual condition boundaries such as the maximum capacity of site-level energy storage in the constraints, thereby making the configuration of distributed energy storage more accurate;

[0092] 2) The optimal configuration model of the distributed energy storage over the entire life cycle of the present invention uses value theory to evaluate the change in the revenue of the new energy station before and after the configuration of energy storage, that is, the difference between the system value with energy storage and the system value without energy storage, so as to make the configuration of distributed energy storage more economical;

[0093] 3) Count the rated parameters and actual usage of each box transformer in the new energy station, calculate the margin of each box transformer, decide the maximum power of a single distributed energy storage, count the number of box transformers that can be deployed in the surrounding distributed energy storage, calculate the maximum capacity of the station-level energy storage, and provide more accurate data basis for the configuration model;

[0094] 4) The present invention provides a method for personalized optimization of distributed energy storage configuration for new energy sites that attempt to adopt distributed energy storage technology in the future, so as to avoid overinvestment or underinvestment. In particular, the configuration method combines local policy information with market flexibility to improve the performance of new energy grid-related performance, ensure the efficient use of new energy, and maximize the value of energy storage systems;

[0095] 5) The present invention provides a new model and new ideas for the arrangement of energy storage in new energy sites, which will help promote the high-quality and large-scale development of the new energy industry. BRIEF DESCRIPTION OF THE DRAWINGS

[0096] Figure 1 It is a specific flow chart of the method of the present invention. DETAILED DESCRIPTION

[0097] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present invention.

[0098] The present invention proposes a distributed energy storage optimization configuration method for new energy stations. First, it fills the gap in related research in China. Second, it fully considers the energy storage operation strategy in the energy storage configuration stage and solves the utilization dilemma through innovative energy storage operation strategies. The national average utilization coefficient of new energy storage in 2022 is only 0.03.

[0099] like Figure 1 As shown, the method of the present invention comprises:

[0100] Step S1, collect energy storage related information. Specifically, collect energy storage related policies and rules in the area where the new energy station is located, such as: energy storage programmatic documents, new energy storage policy, grid connection operation management implementation rules, auxiliary service management implementation rules, and power market operation transaction rules.

[0101] Step S2, formulate energy storage operation strategy. Based on the above information, according to the regional environment and the personalized needs of the site, formulate energy storage operation strategy, including: tracking output curve, reducing wind and solar power abandonment, participating in peak and frequency regulation, cooperating with new energy to participate in the spot market and other application scenarios.

[0102] Step S3, calculate the scale of distributed energy storage units. Distributed energy storage is different from centralized energy storage. It does not require a supporting centralized booster station, and makes full use of the box-type transformer resources of new energy stations. Therefore, it is necessary to count the rated parameters and actual usage of the box-type transformers in new energy stations. By calculating the margin of each box-type transformer, the maximum power of a single distributed energy storage unit is determined. Generally speaking, the full-power operation time of new energy is relatively short, so the maximum power of a single distributed energy storage unit is appropriately greater than the box-type transformer margin, which will not cause waste of energy storage resources.

[0103] Step S4, calculate the maximum capacity of the station-level energy storage. Conduct an on-site survey of the box-type transformers with spare capacity and evaluate the feasibility of construction. Count the number of box-type transformers that can be deployed with distributed energy storage in the surrounding area, and calculate the maximum capacity of the station-level energy storage based on the scale of a single distributed energy storage unit. This specifically refers to the fishery-solar complementary station, because the arrangement of energy storage on the water has certain construction requirements.

[0104] Step S5, establish the optimal configuration model of distributed energy storage. Combined with the current local policies and energy storage operation strategies, establish the configuration model with the optimal economic efficiency of energy storage throughout its life cycle, and consider the actual condition boundaries such as the maximum capacity of station-level energy storage in the constraints. Use value theory to evaluate the change in the income of new energy stations before and after the configuration of energy storage, that is, the difference between the system value with energy storage and the system value without energy storage.

[0105] Step S6, calculate the optimal configuration scale of distributed energy storage. For existing new energy stations, optimize the optimal number of distributed energy storage based on actual historical operation data. For newly built new energy stations, refer to the operation data of similar new energy stations in the surrounding area to optimize the optimal number of distributed energy storage.

[0106] The specific implementation process of the present invention is as follows:

[0107] Step 1: Collect information related to energy storage.

[0108] Specifically, we collect relevant policies and rules on energy storage in the areas where new energy sites are located, such as: energy storage programmatic documents, new energy storage distribution policies, grid connection operation management implementation rules, auxiliary service management implementation rules, and electricity market operation and transaction rules.

[0109] Step 2: Develop energy storage operation strategies.

[0110] Combining application scenarios with actual needs, studying optimization plans for energy storage configuration is an important basis for project implementation.

[0111] Taking Jiangsu Province as an example, energy storage can be used to reduce the grid-connected operation assessment of new energy stations (power generation curve assessment, AGC assessment, primary frequency regulation assessment), power restriction losses and nighttime power consumption expenditure of photovoltaic power stations. According to demand, energy storage is used daily to meet the power generation curve assessment needs. When a dispatch instruction is received, it is applied to AGC, primary frequency regulation and reducing power restrictions.

[0112] Step 3: Calculate the scale of distributed energy storage units.

[0113] Distributed energy storage is different from centralized energy storage. It does not require a centralized booster station and fully utilizes the box-type transformer resources of new energy stations. Therefore, it is necessary to count the rated parameters and actual usage of the box-type transformers of new energy stations. By calculating the margin of each box-type transformer, the maximum power of a single distributed energy storage unit can be determined.

[0114] Generally speaking, the time that new energy operates at full power is short, so the maximum power of a single distributed energy storage unit is appropriately greater than the surplus capacity of the box transformer, which will not cause waste of energy storage resources.

[0115] Step 4: Calculate the maximum capacity of station-level energy storage.

[0116] Conduct on-site surveys of the remaining box-type transformers and assess the feasibility of construction. Count the number of box-type transformers that can be deployed with distributed energy storage in the surrounding area, and calculate the maximum capacity of station-level energy storage based on the scale of a single distributed energy storage unit. This specifically refers to the fishery-solar complementary station, because the deployment of energy storage on the water has certain construction requirements.

[0117] Step 5: Establish the optimal configuration model of distributed energy storage.

[0118] In combination with current local policies and energy storage operation strategies, a configuration model with the optimal economic efficiency over the entire life cycle of energy storage is established, and actual condition boundaries such as the maximum capacity of site-level energy storage are considered in the constraints.

[0119] The following optimization configuration model is provided for reference:

[0120] At present, energy storage-related policies and standards are being continuously improved. Distributed energy storage is easy to expand and can respond to changes in policies and profit models more quickly. Therefore, a configuration model with optimal energy storage economy is established for new energy sites in three planning cycles within 10 years, considering the use of energy storage to reduce wind and solar power abandonment, track output curves and participate in the peak load regulation market, and taking emergency power supply into account in the constraints.

[0121] Subsequently, value theory will be used to evaluate the changes in revenue of new energy power plants before and after the configuration of energy storage, that is, the difference between the system value with energy storage and the system value without energy storage.

[0122] (1) Strategies to reduce wind and solar power curtailment

[0123] When the new energy station receives the wind and solar power abandonment during the t1-t2 period When the command is given, the station-level energy storage can be used to absorb part of the abandoned power. t d,ave and P t c,ave It represents the average power corresponding to the available power of the station-level energy storage in period t when all the available power is discharged / charged in this period, that is,

[0124]

[0125]

[0126] In the formula, SOC max With SOC min Indicates the upper and lower limits of the station-level energy storage state of charge (SOC); SOC t-1 represents the SOC at time t-1; E ES Configure capacity for station-level energy storage; η c With η d It represents the charging and discharging efficiency of energy storage at the station level; Δt is the time interval.

[0127] Charging strategy P for energy storage during the wind and solar curtailment period t1-t2 t c for:

[0128] P t c ≤min{P t c,ave ,P t cut ,P PCS},t∈[t1,t2] (3)

[0129] Where P PCS It is the rated power of the station-level energy storage PCS.

[0130] The amount of energy storage added during the wind and solar curtailment period from t1 to t2 for:

[0131]

[0132] During the idle period of the transmission channel, the reduced amount of abandoned wind and photovoltaic power will be connected to the grid to increase the income from electricity sales and carbon income. The income of the new energy station before and after the configuration of the energy storage system is set to be V1 bef With V1aft :

[0133]

[0134] In the formula, λ sell For the on-grid electricity price.

[0135] (2) Output curve tracking strategy

[0136] Energy storage can be used to track the output curve of renewable energy to reduce assessment penalties for changes in active power output that exceed the rate of change limit.

[0137] In a grid without energy storage system, the assessment penalty V2 bef for:

[0138]

[0139] In the formula, λ punish A is the assessment and punishment standard; t , B t P is the power of the new energy station that exceeds the upper and lower limits in the t period; t act is the actual power in the tth period; P t lim,up , P t lim,low The upper and lower limits of power forecast assessment in time period t.

[0140] After the new energy station is equipped with an energy storage system, the assessment fine V2 needs to be paid aft for:

[0141]

[0142] In the formula, C t , D t P is the power exceeding the upper and lower limits in the tth period after the energy storage system is configured; t c , P t d is the charging and discharging power in period t.

[0143] (3) Participation in peak-shaving market strategies

[0144] When receiving the peak load regulation instruction from t3 to t4, the new energy station evaluates its own reliable peak load regulation capacity. For the new energy station, its maximum upward regulation capacity depends on the energy storage capacity, and its maximum downward regulation capacity depends on the energy storage capacity and the maximum allowable abandoned light amount:

[0145]

[0146] Where P t max,up, P t max,down P is the adjustable up-capacity and down-capacity in the t period; t max,cut The maximum allowable amount of wind and solar power curtailment.

[0147] The market revenue before and after configuring energy storage to participate in the peak load market is V3 bef With V3 aft :

[0148]

[0149] In the formula, ε t anc is the willingness to participate in the peak load-shaving market in period t, which is a 0-1 variable; f t anc (·) is the peak-shaving market reward and punishment function, which is related to the required peak-shaving amount and is generally a piecewise function, determined according to the rules of each region, the participation method of new energy power plants, and the notification time; P t anc is the actual peak load regulation in the tth period; t anc is the peak-shaving cost in period t, which is related to the amount of wind and solar power curtailment, assessment and penalties, etc.

[0150] (4) Distributed energy storage collaborative control strategy

[0151] First, the status information of distributed energy storage needs to be integrated and summarized into site-level energy storage.

[0152]

[0153] Where: SOC i 、E i max , P i max , P i min , k i They are the state of charge (SOC), total capacity, maximum discharge power, maximum charge power and adjustability of the i-th group of energy storage. i,j , SOH i,j , k i,j They are the SOC, state of health (SOH), rated capacity, maximum discharge power, maximum charging power and adjustability of the j-th distributed energy storage in the ith group.

[0154] According to the same method as above, the energy storage group is further merged into a virtual centralized energy storage, and the state parameters include: SOC t 、E t max , Pt max .

[0155] The total power command P of the station-level energy storage control is calculated bess (Positive value is for discharge, negative value is for charge).

[0156] Then, according to the status of each energy storage group, the total power command P bess Distributed to each distributed energy storage group.

[0157]

[0158] P i bess =α i ·P bess (19)

[0159] Where: P i ave is the maximum charge and discharge power of the i-th group of energy storage in the current state; SOC i max , SOC i min is the maximum and minimum SOC of the i-th group of energy storage; is the energy storage charging and discharging efficiency; α i is the power allocation coefficient of the i-th group of energy storage; P i bess is the power instruction of the i-th group of energy storage.

[0160] Based on the status of distributed energy storage within the group, the tasks are further decomposed into each distributed energy storage unit according to the same method mentioned above.

[0161] (5) Distributed energy storage optimization configuration model

[0162] ① Present value of construction cost of station-level energy storage system C inv for:

[0163]

[0164] In the formula, is the energy storage investment cost at the beginning of year y; The unit capacity cost of energy storage; is the unit cost of PCS; T is the planning period; ρ is the discount rate.

[0165] ② Present value of operation and maintenance cost of station-level energy storage system C mai for:

[0166]

[0167] In the formula, is the energy storage maintenance cost in the yth year; a and b are the estimated ratios of energy storage capacity and power operation and maintenance costs to the initial investment.

[0168] ③ The present value of the system value brought by the configuration of energy storage in the new energy power plant is V ES :

[0169]

[0170] ④ Fixed asset depreciation calculation of the residual value S of energy storage at the end of the planning period ES :

[0171]

[0172] Where k = {1, 4, 7} is the end of the planning period; r1 is the depreciation rate of energy storage fixed assets.

[0173] ⑤Objective function

[0174] Considering the investment cost, operation cost, operation value of energy storage during the planning period and the depreciation of fixed assets at the end of the planning period, an energy storage planning model with the goal of economic optimization is established:

[0175] min f total =C inv +C mai -V ES -S ES (26)

[0176] ⑥Constraints

[0177]

[0178] SOC min ≤SOC t ≤SOC max (28)

[0179]

[0180]

[0181]

[0182] 0≤P t cut ≤P t act (32)

[0183] E ES =ωE ES,dec (33)

[0184] E ES <E ES,max (34)

[0185] In the formula, is the charging and discharging state; ω is the number of distributed energy storage, which is the decision variable of the model; E ES,dec is the scale of a single distributed energy storage unit, which is determined by the previous steps and is therefore a model constant; E ES,max It is the maximum capacity of station-level energy storage, obtained through survey and calculation.

[0186] Step 6: Calculate the optimal configuration scale of distributed energy storage.

[0187] For existing new energy stations, the optimal number of distributed energy storage is optimized based on actual historical operation data. For newly built new energy stations, the optimal number of distributed energy storage is optimized based on the operation data of similar new energy stations in the surrounding areas.

[0188] The present invention is applicable to existing and newly built new energy sites, and forms a distributed energy storage optimization method for new energy configuration, thereby avoiding over-investment or under-investment, and can promote high-quality and large-scale development of the new energy industry.

[0189] The above is only a specific embodiment of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can easily think of various equivalent modifications or replacements within the technical scope disclosed by the present invention, and these modifications or replacements should be included in the protection scope of the present invention. Therefore, the protection scope of the present invention shall be based on the protection scope of the claims.

Claims

1. A distributed energy storage optimization automatic configuration method for new energy stations, characterized in that: The method comprises the following steps: Step S1, collecting energy storage related data; Step S2, formulating an energy storage operation strategy based on the data collected in step S1; Step S3, calculating the scale data of distributed energy storage units; Step S4, calculating the maximum capacity data of the station-level energy storage; Step S5, establishing a distributed energy storage optimal configuration model; Step S6, calculating the optimal configuration quantity of distributed energy storage.

2. According to claim 1, a distributed energy storage optimization automatic configuration method for new energy stations is characterized in that: The energy storage related data includes policy and detailed information related to energy storage in the area where the new energy station is located.

3. According to claim 2, a distributed energy storage optimization automatic configuration method for new energy stations is characterized in that: The energy storage-related policies and detailed information include energy storage programmatic documents, new energy storage policy, grid connection operation management implementation details, ancillary service management implementation details and electricity market operation transaction details.

4. According to claim 1, a distributed energy storage optimization automatic configuration method for new energy stations is characterized in that: The specific calculation data of the distributed energy storage monomer scale is: Statistics are collected on the rated parameters and actual usage of the box-type transformers, the margin of each box-type transformer is calculated, and the maximum power of a single distributed energy storage unit is determined.

5. According to claim 1, a distributed energy storage optimization automatic configuration method for new energy stations is characterized in that: The calculation data of the maximum capacity of the station-level energy storage is specifically: Count the number of box-type transformers that can be deployed around the station for distributed energy storage, and calculate the maximum capacity of the station-level energy storage based on the scale of a single distributed energy storage unit.

6. According to claim 1, a distributed energy storage optimization automatic configuration method for new energy stations is characterized in that: The specific steps of establishing the optimal configuration model of distributed energy storage are as follows: Combined with the energy storage operation strategy formulated in step S2 and the calculation data of steps S3 and S4, a configuration model with the optimal economic efficiency over the entire life cycle of energy storage is established, and the actual condition boundary of the maximum capacity of site-level energy storage is considered in the constraints. The energy storage operation strategy includes strategies to reduce wind and solar power abandonment, output curve tracking strategy, peak load market participation strategy and distributed energy storage collaborative control strategy.

7. According to claim 6, a distributed energy storage optimization automatic configuration method for new energy stations is characterized in that: The strategies to reduce wind and solar power curtailment are as follows: When the new energy station receives the wind and solar power abandonment during the t1-t2 period When the command is given, the station-level energy storage is used to absorb part of the abandoned power, P t d,ave and P t c,ave They represent the average power corresponding to the available power of the station-level energy storage in period t when all the available power is discharged and charged in that period, that is, In the formula, SOC max With SOC min Indicates the upper and lower limits of the station-level energy storage state of charge SOC; SOC t-1 represents the SOC at time t-1; E ES Allocate capacity for site-level energy storage; η c With η d It represents the charging and discharging efficiency of energy storage at the station level; Δt is the time interval; Charging strategy P for energy storage during the wind and solar curtailment period t1-t2 t c for: Where P PCS The rated power of the PCS for the site-level energy storage; The amount of energy storage added during the wind and solar curtailment period from t1 to t2 for: During the idle period of the transmission channel, the reduced amount of abandoned wind and photovoltaic power will be connected to the grid to increase the income from electricity sales and carbon income. The income of the new energy station before and after the configuration of the energy storage system is divided into V1 bef With V1 aft : In the formula, λ sell For the on-grid electricity price; The output curve tracking strategy is specifically as follows: Energy storage is used to track the output curve of new energy sources to reduce the assessment penalty for the part of active power output that exceeds the change rate limit; In a grid without energy storage system, the assessment penalty V2 bef for: In the formula, λ punish A is the assessment and punishment standard; t , B t P is the power of the new energy station that exceeds the upper and lower limits in the t period; t act is the actual power in the tth period; P t lim,up , P t lim,low The upper and lower limits of the power forecast assessment for the t-th period; After the new energy station is equipped with an energy storage system, the assessment fine V2 must be paid aft for: In the formula, C t , D t P is the power exceeding the upper and lower limits in the tth period after the energy storage system is configured; t c , P t d is the charging and discharging power in period t.

8. According to claim 7, a distributed energy storage optimization automatic configuration method for new energy stations is characterized in that: The specific strategies for participating in the peak load-shaving market are: When receiving the peak load regulation instruction during the period t3-t4, the new energy station evaluates its own reliable peak load regulation capacity. For the new energy station, its maximum upward regulation capacity depends on the energy storage capacity, and its maximum downward regulation capacity depends on the energy storage capacity and the maximum allowable abandoned light amount: Where P t max,up , P t max,down P is the adjustable up-capacity and down-capacity in the t period; t max,cut is the maximum allowable amount of wind and solar power curtailment; The market revenue before and after configuring energy storage to participate in the peak load market is V3 bef With V3 aft : In the formula, is the willingness to participate in the peak load-shaving market in period t; f t anc (·) is the peak load market reward and punishment function; P t anc is the actual peak load regulation in period t; is the peak load-shaving cost in period t; The distributed energy storage coordinated control strategy is specifically as follows: First, the status information of distributed energy storage needs to be integrated and summarized to become site-level energy storage; Where: SOC i , P i max , P i min , k i are the state of charge, total capacity, maximum discharge power, maximum charging power and adjustability of the i-th group of energy storage; SOC i,j , SOH i,j , k i,j They are the SOC, health state SOH, rated capacity, maximum discharge power, maximum charging power and adjustability of the jth distributed energy storage in the i-th group; According to the same method as above, the energy storage group is further merged into a virtual centralized energy storage, and the state parameters include SOC t , P t max ; The total power command P of the station-level energy storage control is calculated bess ; Then, according to the status of each energy storage group, the total power command P bess Distributed to each distributed energy storage group; P i bess =α i ·P bess (19) Where: P i ave is the maximum charge and discharge power of the i-th group of energy storage in the current state; is the maximum and minimum SOC of the i-th group of energy storage; is the charging and discharging efficiency of the i-th group of energy storage; α i is the power allocation coefficient of the i-th group of energy storage; P i bess is the power instruction of the i-th group of energy storage; Based on the status of distributed energy storage within the group, the tasks are further decomposed into each distributed energy storage unit according to the same method mentioned above.

9. A distributed energy storage optimization automatic configuration method for new energy stations according to claim 8, characterized in that: The optimal configuration model for the economic efficiency of energy storage throughout its life cycle is specifically: 1) Present value of construction cost of station-level energy storage system C inv for: In the formula, is the energy storage investment cost at the beginning of year y; The unit capacity cost of energy storage; is the PCS unit cost; P PCS E is the rated power of the station-level energy storage PCS; ES Allocate capacity for site-level energy storage; T is the planning period; ρ is the discount rate; 2) Present value of operation and maintenance cost of station-level energy storage system C mai for: In the formula, is the energy storage maintenance cost in year y; a and b are the estimated ratios of energy storage capacity and power operation and maintenance costs to initial investment; 3) The present value of the system value brought by the configuration of energy storage in the new energy power plant is V ES : Where V1 bef With V1 aft The revenue of the new energy station before and after the energy storage system is deployed in the first year; 4) Fixed asset depreciation calculation of the residual value S of the energy storage at the end of the planning period ES : In the formula, k = {1, 4, 7} is the end of the planning period; r1 is the depreciation rate of energy storage fixed assets; 5) Objective function Considering the investment cost, operation cost, operation value of energy storage during the planning period and the depreciation of fixed assets at the end of the planning period, an energy storage planning model with the goal of economic optimization is established: min f total =C inv +C mai -V ES -S ES (26) 6) Constraints SOC min ≤SOC t ≤SOC max (28) 0≤P t c ,P t d ≤P PCS (30) 0≤P t cut ≤P t act (32) E ES =ωE ES,dec (33) AND ES <And ES,max (34) In the formula, is the charging and discharging state; ω is the number of distributed energy storage, which is the decision variable of the model; E ES,dec For the scale of a single distributed energy storage unit, decisions are made through the previous steps; E ES,max It is the maximum capacity of energy storage at the station level; SOC t is the state of charge of the station-level energy storage at the tth moment; P t c is the charging power of the station-level energy storage at time t; η c is the energy storage charging efficiency at the station level; P t d is the discharge power of the station-level energy storage at the tth moment; η d is the energy storage discharge efficiency at the station level; Δt is the time interval; P t cut is the abandoned power of the station-level energy storage at the tth moment; P t act It is the actual power of the station-level energy storage at the t moment.

10. The method for automatically configuring distributed energy storage optimization for new energy stations according to claim 6, characterized in that: The calculation of the optimal configuration quantity of distributed energy storage is specifically as follows: For existing new energy stations, the optimal number of distributed energy storage is optimized based on actual historical operation data; For newly built new energy stations, refer to the operating data of similar new energy stations in the surrounding area to optimize the optimal amount of distributed energy storage.