Movable semi-automatic bent cap supporting system and construction technology thereof

Through the mobile semi-automatic cover beam support system, the hydraulic system is used to realize height micro-adjustment, which simplifies the erection and dismantling process of the cover beam support system, solves the problems of cumbersome processes and high safety risks in traditional construction, and improves construction efficiency and quality. .

CN118756582APending Publication Date: 2024-10-11THE 3RD ENG CO LTD OF CHINA RAILWAY 16TH BUREAU GRP CO LTD +1
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202410955827.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-17
Publication Date
2024-10-11

AI Technical Summary

Technical Problem

In the construction of traditional double-column bridge pier cap beams, the erection and removal of brackets is cumbersome, with high safety risks, long construction period, and large material waste, which affects construction efficiency and quality.

Method used

A mobile semi-automatic cover beam support system is designed, including a mobile device system, a main support structure, a truss structure, a formwork component and a hydraulic system. The hydraulic system realizes height micro-adjustment, simplifies the erection and dismantling process of the support system, and improves construction. Efficiency and safety.

Benefits of technology

It achieves rapid disassembly and efficient movement of the support system, reduces the construction period and safety risks, improves construction quality and efficiency, and reduces material waste.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118756582A_ABST
    Figure CN118756582A_ABST
Patent Text Reader

Abstract

The movable type semi-automatic bent cap supporting system comprises a moving device system, a supporting main body structure, a truss structure, a formwork assembly and a hydraulic system, the supporting main body structure is connected with the upper portion of a moving device through a flange plate, and the truss structure is welded to the top of the supporting main body structure; the hydraulic system is fixedly arranged on the outer side of the moving device, and the formwork assembly is arranged on the sliding rail. By means of the moving device, rapid circulation and moving fine adjustment of the system are achieved through the moving device system, the height fine adjustment oil-saving cylinder controlled by the hydraulic system is arranged and used for final height adjustment, the accuracy of the height adjustment oil-saving cylinder is greatly improved, meanwhile, the construction efficiency is improved, the construction period is shortened firstly, and the safety risk is reduced to a certain degree.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of bridge construction, and in particular to a mobile semi-automatic cap beam support system and a construction process thereof. Background Art

[0002] With the growth of population and the acceleration of urbanization, the demand for transportation has shown a growing trend. In order to meet the growing demand for transportation, bridges, as important transportation infrastructure, have been continuously expanded in scale and quantity. Especially in urban areas, in order to ease traffic congestion, large bridge projects such as viaducts and cross-river and cross-sea bridges have gradually increased. At the same time, bridge construction plays an important role in promoting economic development, can drive the development of related industries, can promote the development of regional economy, strengthen the connection and communication between regions, and promote the coordinated development of regional economy. Bridge engineering consists of multiple parts, among which the cap beam construction is an especially important part, and its construction quality will directly affect the final quality of bridge construction. As an important cap beam structure, the large cantilever prestressed cap beam has a complex structure and high construction quality and safety requirements. At the same time, because its construction process is relatively cumbersome, it has a certain degree of impact on the construction period and quality. In the entire cap beam construction process, the support system erection is an extremely important link, which is also the first link. It has the characteristics of large workload, large consumption of manpower and material resources, high safety risks, and high technical and quality requirements. The process, quality and progress of the system erection will directly affect the safety risk factor, quality level and production progress of the entire cap beam construction.

[0003] In the traditional cast-in-place construction of the cap beam of a double-column bridge pier, a ground-mounted full-height bracket is often used as a temporary bracket load-bearing structure. Formwork installation, steel bar binding, prestressed pipe installation, concrete pouring and other work are all carried out on the bracket. When adjusting the template elevation, padding is done under the template rack. When the template is removed after the concrete pouring is completed, the padding is removed, and the template rack is lowered before the template is removed.

[0004] The traditional double-column bridge cap uses the full-frame support method for cast-in-place construction, which requires the erection of a large number of steel pipe supports. The installation and removal of the support requires a large workload, a long time for high-altitude operations, high safety risks, and a long period for the installation and removal of the support. In addition, the support must be preloaded once each time it is erected. The construction cost is high and affects the construction period. When adjusting the template elevation, steel or steel plates are placed under the template rack. The work is relatively cumbersome, and due to the large number of padding points, it is difficult to check all of them to ensure that all pads are densely padded, which poses a major safety hazard. When removing the formwork after pouring, the steel or steel plates of the full-frame support need to be completely removed. The removal amount is large and time-consuming. When removing the steel or steel plate padding, oxygen acetylene flame cutting is often required. The padding can only be used once, resulting in large material waste and high safety risks.

[0005] In response to the above problems, the present invention provides a mobile semi-automatic cap beam support system with easy disassembly and assembly, high efficiency, guaranteed quality, low safety risk factor and controllable cost. Summary of the invention

[0006] The present invention provides a mobile semi-automatic cap beam support system which is convenient for assembly and disassembly, high in efficiency, guaranteed in quality, low in safety risk factor and controllable in cost.

[0007] The purpose of the present invention is to provide a mobile semi-automatic cap beam support system, including a mobile device system, a supporting main structure, a truss structure, a formwork assembly, a hydraulic system, and a flange. The supporting main structure is connected to the upper part of the mobile device through the flange, the truss structure is welded to the top of the supporting main structure, the hydraulic system is fixedly arranged on the outside of the mobile device, and the formwork assembly is arranged on the slide rail.

[0008] Furthermore, the moving device system includes a moving wheel, a slide rail and a fixed block, the fixed block is arranged on one side of the moving wheel, and the moving wheel is arranged on the slide rail.

[0009] Furthermore, the formwork assembly includes a bottom formwork, a side formwork, an end formwork, a sliding device, a movable slide rail, a movable foot bolt, a bolt support, a fixed anchor bolt, a tensioning concave-convex platform and a detachable bell mouth. The bottom formwork is laid on the truss structure, the side formwork is spliced ​​on the top of the bottom formwork, the sliding device and the movable slide rail are arranged at the bottom of the side formwork, the side formwork is connected to the sliding device, and a movable foot bolt and a bolt support are provided at the connection between the side formwork and the sliding device. The end formwork is fixed to the upper part of the bottom formwork and the end of the side formwork by bolts, and a fixed anchor bolt is provided between the sliding device and the truss structure.

[0010] Furthermore, the hydraulic system includes a hydraulic oil tank, a hydraulic control switch, a height fine-adjustment hydraulic cylinder and a height adjustment hydraulic cylinder. The hydraulic oil tank is provided with a hydraulic control switch, the height hydraulic adjustment cylinder is arranged in the middle of the supporting main structure, and the height fine-adjustment hydraulic cylinder is arranged on the moving wheel.

[0011] Furthermore, the truss structure includes an articulated movable adjustment block, a welded cross beam and a protective enclosure. The movable articulated adjustment block is arranged in the middle of the truss structure, the welded cross beam is arranged at the top of the truss structure, and the protective enclosure is arranged around the top of the truss structure.

[0012] Furthermore, the supporting body structure includes a supporting body adjusting block, a limiting pin and a casing jacking column, and the supporting body adjusting block, the limiting pin and the casing jacking column are all arranged in the middle of the supporting body structure.

[0013] A mobile semi-automatic cover beam support system construction process, the construction process comprises the following steps:

[0014] Step 1: Replace the ground. Before setting up the system, replace the original ground with a depth of 1.5-2 meters. The replacement material is bluestone.

[0015] Step 2: The system is transported to the bridge site and preliminarily assembled in two parts, the left and right parts. The supporting main structure is connected to the upper part of the mobile device through a flange. The various parts of the supporting main structure are connected with flange anchor bolts. The truss structure is welded to the top part of the supporting main structure to form an integral fixed structure with it.

[0016] Step 3: The system is initially positioned and fixed. After the surveying team completes the surveying and setting out work, three cranes, one main and two auxiliary, are used to drag the system along the pre-laid track to the designed position. The fixed blocks are installed to fix the coordinates of the entire system. The movable hinged adjustment blocks of the spliced ​​truss structure are hoisted and spliced. The two-part system is formed into a whole. Finally, the height adjustment is completed by the height adjustment hydraulic cylinder and the top lifting column, and the limit pin is fixed;

[0017] Step 4: Preload and calculate the elastic deformation. The crane hoists the precast block. When loading, the total weight of the preload is 110% of the total weight of the cap beam concrete. The preloading is carried out in four levels, namely 0→60%→80%→100%→110%. The load is applied symmetrically and evenly from the mid-span to both ends. During observation, each level of loading is observed once. Load to 110% and observe continuously for 48 hours, once every 2 hours. Unloading can be carried out only after the settlement value is stable and enters a convergence state. Otherwise, the observation should be extended until the settlement value is stable and enters a convergence state. Each level of unloading is observed once, and each observation should be recorded in time. During unloading, the settlement value of the same measuring point is stable and enters a convergence state before unloading. Unloading is the reverse process of loading, and unloading is carried out layer by layer from both ends to the mid-span from top to bottom; unloading is carried out in four levels, namely 110%→100%→80%→60%→0. Preloading removes non-elastic deformation factors, calculates elastic deformation, and sets pre-camber value;

[0018] Step 5: After the system is finally positioned and fixed, the surveying team completes the surveying and setting out work, and refers to the measured elevation and pre-camber value, and makes fine adjustments to the height through the height fine-adjustment hydraulic cylinder;

[0019] Step 6: Hoist and lay the bottom formwork. Use two cranes, one main and one auxiliary, to hoist and lay the bottom formwork accurately.

[0020] Step seven, lifting and binding of steel bars. After completing the roughening work on the top of the pier and the system inspection, two semi-finished cap beam steel cages are lifted by two cranes, one main and one auxiliary, and the straight thread sleeve connection is carried out on site, as well as subsequent steel bar binding, cooling and maintenance pipeline laying, corrugated pipe fixing, and steel strand insertion work.

[0021] Step 8: Assemble the end formwork, sliding device and side formwork. After the steel bar inspection is completed, the end formwork is hoisted by two cranes, one main and one auxiliary, to complete the fixation of the end formwork and the steel strand. The sliding device is hoisted and fixed to the truss. The side formwork is hoisted and spliced. The side formwork is connected to the sliding device through a movable foot bolt and fixed to the end formwork with bolts. The position of the sliding device is fixed by fixing anchor bolts between the sliding device and the truss structure, and the sliding device and the side formwork are supported by bolts.

[0022] Step 9: Concrete pouring: After the surveying team completes the template re-measurement and the supervisor reports the inspection, concrete pouring begins. During the pouring process, the supply and quality of concrete must be guaranteed, and the vibration must be in place. After the pouring is completed, water cooling and maintenance should be carried out in time;

[0023] Step 10: Remove part of the formwork. After the concrete strength reaches the standard, remove the formwork, release the bolts fixing the end formwork, loosen the anchor bolts between the sliding device and the truss structure, push the sliding device and the side formwork away from the cap beam, loosen the bolts supporting the sliding device and the side formwork, close the side formwork, and remove the side formwork, sliding device, and end formwork in sequence;

[0024] Step 11. Remove the bottom formwork and dismantle and transport the system. After the concrete strength reaches the standard and the pouring days meet the requirements, the height adjustment hydraulic cylinder and the height fine-adjustment hydraulic cylinder are used to return the oil and shrink. The overall height of the system is lowered, the bottom formwork is hoisted and removed, and the truss structure movable hinged adjustment block is hoisted and removed. At this time, the system becomes two parts again. If the next pier site is nearby, it can be dragged to the next pier site after the mobile device fixed block is folded. If it is far away, it will be completely disassembled and loaded for transportation.

[0025] The present invention has the following advantages: the present invention realizes rapid system circulation and mobile fine-tuning through a mobile device system, and is provided with a height fine-tuning cylinder controlled by a hydraulic system for final height adjustment, which greatly improves its accuracy, and also improves construction efficiency, first shortens construction period, and reduces safety risks to a certain extent.

[0026] The main support structure of the present invention is provided with a main support adjustment block with a unit height of 4 meters in the middle, as well as a sleeve-type lifting column, a height-adjusting hydraulic cylinder and a limit pin controlled by a hydraulic system. The adjustment range is 0-4 meters, which makes the system have good compatibility and practicality, and is suitable for the construction of large cantilever cap beams of the same standard but different heights.

[0027] The truss structure of the present invention is provided with a welded crossbeam on the top to replace the movable distribution beam on the top of the traditional support system, greatly improving the installation efficiency and stability of the system. Protective enclosures are provided around the top to improve safety performance.

[0028] The template of the present invention is connected to the sliding device through a movable foot bolt, so that the entire side template can be moved in the direction of approaching and moving away from the cap beam to open and close the side template, thereby improving the efficiency of demolding. A bolt top support is provided between the middle and upper part of the side template and the sliding device to fix the side template, thereby improving the safety quality factor and reducing the risk of mold expansion. A fixed anchor bolt is provided between the sliding device and the truss to fix the sliding device and the side template. BRIEF DESCRIPTION OF THE DRAWINGS

[0029] Figure 1 It is a structural schematic diagram of the present invention;

[0030] Figure 2 is a side view of the present invention;

[0031] In the figure: 1. Side mold; 2. Truss structure; 3. Height adjustment hydraulic cylinder; 4. Casing jacking column; 5. Support body adjustment block; 6. Limit pin; 7. Support body structure; 8. Moving device; 9. Moving wheel; 10. Height fine adjustment hydraulic cylinder; 11. Hydraulic control switch; 12. Hydraulic system; 13. Hydraulic oil tank; 14. Fixed block; 15. Bolt support; 16. Movable foot bolt; 17. Fixed anchor bolt; 18. Sliding device; 19. Slide rail; 20. Welded crossbeam; 21. Removable bell mouth; 22. Tensioning concave and convex platform; 23. End mold; 24; Bottom mold; 25. Protective enclosure; 26. Articulated movable adjustment block; 27. Flange. DETAILED DESCRIPTION

[0032] The present invention provides a mobile semi-automatic cap beam support system, including a mobile device 8 system, a supporting main structure, a truss structure 2, a formwork assembly, a hydraulic system 12, and a flange 27. The supporting main structure 5 is connected to the upper part of the mobile device 8 through the flange 27, the truss structure 2 is welded to the top of the supporting main structure 5, the hydraulic system 12 is fixedly arranged on the outside of the mobile device 8, and the formwork assembly is arranged on the slide rail 19.

[0033] In this embodiment, the moving device 8 system includes a moving wheel 9 , a slide rail 19 and a fixed block 14 . The fixed block 14 is arranged on one side of the moving wheel 9 , and the moving wheel 9 is arranged on the slide rail 19 .

[0034] In this embodiment, the formwork assembly includes a bottom form 24, a side form 1, an end form 23, a sliding device 18, a movable slide rail 19, a movable foot bolt 16, a bolt support 15, a fixed anchor bolt 17, a tensioning concave-convex platform 22 and a detachable bell mouth 21. The bottom form 24 is laid on the truss structure 2, the side form 1 is spliced ​​on the top of the bottom form 24, the sliding device 18 and the movable slide rail 19 are arranged at the bottom of the side form 1, the side form 1 is connected to the sliding device 18, and a movable foot bolt 16 and a bolt support 15 are provided at the connection between the side form 1 and the sliding device 18. The end form 23 is fixed to the upper part of the bottom form 24 and the end of the side form 1 by bolts, and a fixed anchor bolt 17 is provided between the sliding device 18 and the truss structure 2.

[0035] In this embodiment, the hydraulic system 12 includes a hydraulic oil tank 13, a hydraulic control switch 11, a height fine-adjustment hydraulic cylinder 10 and a height adjustment hydraulic cylinder 3. The hydraulic oil tank 13 is provided with a hydraulic control switch 11, the height hydraulic cylinder 3 is arranged in the middle of the supporting main structure 5, and the height fine-adjustment hydraulic cylinder 10 is arranged on the moving wheel 9.

[0036] In this embodiment, the truss structure 2 includes an articulated movable adjustment block 26, a welded cross beam 20 and a protective enclosure 25. The articulated adjustment block is arranged in the middle of the truss structure 2, the welded cross beam 20 is arranged at the top of the truss structure 2, and a protective enclosure 25 is arranged around the top of the truss structure 2.

[0037] In this embodiment, the supporting body structure includes a supporting body adjustment block 5, a limiting pin 6 and a casing jacking column 4, and the supporting body adjustment block 5, the limiting pin 6 and the casing jacking column 4 are all arranged in the middle of the supporting body structure.

[0038] A mobile semi-automatic cover beam support system construction process, the construction process comprises the following steps:

[0039] Step 1: Replace the ground. Before setting up the system, replace the original ground with a depth of 1.5-2 meters. The replacement material is bluestone.

[0040] Step 2: The system is transported to the bridge site, and the left and right parts are preliminarily assembled. The supporting main structure 5 is connected to the upper part of the mobile device 8 through the flange 27. The various parts of the supporting main structure are connected with flange anchor bolts. The truss structure 2 is welded to the top part of the supporting main structure to form an integral fixed structure with it.

[0041] Step 3: The system is initially positioned and fixed. After the surveying team completes the surveying and setting out work, three cranes, one main and two auxiliary, are used to drag the system along the pre-laid track to the designed position. The fixed blocks 14 are placed to fix the coordinates and orientation of the entire system. The spliced ​​truss structure 2 movable hinged adjustment block is hoisted and spliced. The two-part system forms a whole. Finally, the height adjustment is completed by the height adjustment hydraulic cylinder 3 and the top lifting column, and the limit pin 6 is fixed;

[0042] Step 4: Preload and calculate the elastic deformation. The crane hoists the precast block. When loading, the total weight of the preload is 110% of the total weight of the cap beam concrete. The preloading is carried out in four levels, namely 0→60%→80%→100%→110%. The load is applied symmetrically and evenly from the mid-span to both ends. During observation, each level of loading is observed once. Load to 110% and observe continuously for 48 hours, once every 2 hours. Unloading can be carried out only after the settlement value is stable and enters a convergence state. Otherwise, the observation should be extended until the settlement value is stable and enters a convergence state. Each level of unloading is observed once, and each observation should be recorded in time. During unloading, the settlement value of the same measuring point is stable and enters a convergence state before unloading. Unloading is the reverse process of loading, and unloading is carried out layer by layer from both ends to the mid-span from top to bottom; unloading is carried out in four levels, namely 110%→100%→80%→60%→0. Preloading removes non-elastic deformation factors, calculates elastic deformation, and sets pre-camber value;

[0043] Step 5: After the system is finally positioned and fixed, the surveying team completes the surveying and setting out work, and refers to the measured elevation and the pre-camber value, and performs height fine-tuning through the height fine-tuning hydraulic cylinder 10;

[0044] Step 6: Hoist and lay the bottom formwork 24. Use two cranes, one main and one auxiliary, to hoist and lay the bottom formwork 24 accurately.

[0045] Step seven, lifting and binding of steel bars. After completing the roughening work on the top of the pier and the system inspection, two semi-finished cap beam steel cages are lifted by two cranes, one main and one auxiliary, and the straight thread sleeve connection is carried out on site, as well as subsequent steel bar binding, cooling and maintenance pipeline laying, corrugated pipe fixing, and steel strand insertion work.

[0046] Step 8: Assemble the end form 23, the sliding device 18 and the side form 1. After the steel bar inspection is completed, the end form 23 is hoisted by two cranes, one main and one auxiliary, to complete the fixation of the end form 23 and the steel strands. The sliding device 18 is hoisted and fixed to the truss. The side form 1 is hoisted and spliced. The side form 1 is connected to the sliding device 18 through the movable foot bolt 16 and bolted to the end form 23. The position of the sliding device 18 is fixed by fixing anchor bolts 17 between the sliding device 18 and the truss structure 2, and the sliding device 18 and the side form 1 are supported by bolts 15;

[0047] Step 9: Concrete pouring: After the surveying team completes the template re-measurement and the supervisor reports the inspection, concrete pouring begins. During the pouring process, the supply and quality of concrete must be guaranteed, and the vibration must be in place. After the pouring is completed, water cooling and maintenance should be carried out in time;

[0048] Step 10: Remove part of the formwork. After the concrete strength reaches the standard, remove the formwork, release the bolts fixing the end form 23, loosen the fixing anchor bolts 17 between the sliding device 18 and the truss structure 2, push the sliding device 18 and the side form 1 away from the cap beam, loosen the bolt support 15 between the sliding device 18 and the side form 1, close the side form 1 plate, and remove the side form 1, sliding device 18, and end form 23 in sequence;

[0049] Step 11, remove the bottom formwork 24 and the transportation system. After the concrete strength reaches the standard and the pouring days meet the requirements, return the oil and shrink it. Through the height adjustment hydraulic cylinder 3 and the height fine-adjustment hydraulic cylinder 13, lift and remove the bottom formwork 24, and lift and remove the movable hinged adjustment block of the truss structure 2. At this time, the system becomes two parts again. If the next pier site is nearby, it can be dragged to the next pier site after the mobile device 8 fixed block 14 is folded. If it is far away, it will be completely disassembled and loaded for transportation.

[0050] Although the specific implementation of the present invention is described in detail in conjunction with the drawings, it should not be understood as limiting the scope of protection of this patent. Within the scope described in the claims, various modifications and variations that can be made by those skilled in the art without creative work still fall within the scope of protection of this patent.

Claims

1. A mobile semi-automatic cap beam support system, comprising a mobile device system, a supporting main structure, a truss structure, a template assembly, a hydraulic system, and a flange, characterized in that: The supporting main structure is connected to the upper part of the mobile device through flange anchor bolts, the truss structure is welded to the top of the supporting main structure, the hydraulic system is fixedly arranged on the outer side of the mobile device, and the template assembly is arranged on the slide rail.

2. A mobile semi-automatic cap beam support system as claimed in claim 1, characterized in that: The moving device system comprises a moving wheel, a slide rail and a fixed block, wherein the fixed block is arranged on one side of the moving wheel, and the moving wheel is arranged on the slide rail.

3. A mobile semi-automatic cap beam support system as claimed in claim 1, characterized in that: The formwork assembly includes a bottom form, a side form, an end form, a sliding device, a movable slide rail, a movable foot bolt, a bolt support, a fixed anchor bolt, a tensioning concave-convex platform and a detachable bell mouth. The bottom form is laid on a truss structure, the side form is spliced ​​on the top of the bottom form, the sliding device and the movable slide rail are arranged at the bottom of the side form, the side form is connected to the sliding device, and a movable foot bolt and a bolt support are provided at the connection between the side form and the sliding device. The end form is fixed to the upper part of the bottom form and the end of the side form by bolts, and a fixed anchor bolt is provided between the sliding device and the truss structure.

4. A mobile semi-automatic cap beam support system as claimed in claim 1, characterized in that: The hydraulic system includes a hydraulic oil tank, a hydraulic control switch, a height fine-adjustment hydraulic cylinder and a height adjustment hydraulic cylinder. The hydraulic oil tank is provided with a hydraulic control switch, the height hydraulic adjustment cylinder is arranged in the middle of the supporting main structure, and the height fine-adjustment hydraulic cylinder is arranged on the moving wheel.

5. A mobile semi-automatic cap beam support system as claimed in claim 1, characterized in that: The truss structure includes an articulated movable adjustment block, a welded crossbeam and a protective enclosure. The articulated adjustment block is arranged in the middle of the truss structure, the welded crossbeam is arranged at the top of the truss structure, and the top of the truss structure is surrounded by protective enclosures.

6. The mobile semi-automatic cap beam support system as claimed in claim 1, characterized in that: The supporting body structure comprises a supporting body adjusting block, a limiting pin and a casing jacking column, and the supporting body adjusting block, the limiting pin and the casing jacking column are all arranged in the middle of the supporting body structure.

7. A mobile semi-automatic cap beam support system construction process, characterized in that: The construction process comprises the following steps: Step 1: Replace the ground. Before setting up the system, replace the original ground with a depth of 1.5-2 meters. The replacement material is bluestone. Step 2: The system is transported to the bridge site and preliminarily assembled in two parts, the left and right parts. The supporting main structure is connected to the upper part of the mobile device through a flange. The various parts of the supporting main structure are connected with flange anchor bolts. The truss structure is welded to the top part of the supporting main structure to form an integral fixed structure with it. Step 3: The system is initially positioned and fixed. After the surveying team completes the surveying and setting out work, three cranes, one main and two auxiliary, are used to drag the system along the pre-laid track to the designed position. The fixed blocks are installed to fix the coordinates of the entire system. The movable hinged adjustment blocks of the spliced ​​truss structure are hoisted and spliced. The two-part system is formed into a whole. Finally, the height adjustment is completed by the height adjustment hydraulic cylinder and the top lifting column, and the limit pin is fixed; Step 4: Preload and calculate the elastic deformation. The crane hoists the precast block. When loading, the total weight of the preload is 110% of the total weight of the cap beam concrete. The preloading is carried out at four levels, namely 0→60%→80%→100%→110%. The load is applied symmetrically and evenly from the mid-span to both ends. During observation, each level of loading is observed once. When loaded to 110%, continuous observation is carried out for 48 hours, once every 2 hours. Unloading can be carried out only after the settlement value is stable and enters a convergence state. Otherwise, the observation should be extended until the settlement value is stable and enters a convergence state. Each level of unloading is observed once, and each observation should be recorded in time. During unloading, the settlement value of the same measuring point is stable and enters a convergence state before unloading. Unloading is the reverse process of loading, and unloading is carried out layer by layer from both ends to the mid-span from top to bottom; unloading is carried out at four levels, namely 110%→100%→80%→60%→0. Preloading removes non-elastic deformation factors, calculates elastic deformation, and sets pre-camber value; Step 5: After the system is finally positioned and fixed, the surveying team completes the surveying and setting out work, and refers to the measured elevation and pre-camber value, and makes fine adjustments to the height through the height fine-adjustment hydraulic cylinder; Step 6: Hoist and lay the bottom formwork. Use two cranes, one main and one auxiliary, to hoist and lay the bottom formwork accurately. Step seven, lifting and binding of steel bars. After completing the roughening work on the top of the pier and the system inspection, two semi-finished cap beam steel cages are lifted by two cranes, one main and one auxiliary, and the straight thread sleeve connection is carried out on site, as well as subsequent steel bar binding, cooling and maintenance pipeline laying, corrugated pipe fixing, and steel strand insertion work. Step 8: Assemble the end formwork, sliding device and side formwork. After the steel bar inspection is completed, the end formwork is hoisted by two cranes, one main and one auxiliary, to complete the fixation of the end formwork and the steel strand. The sliding device is hoisted and fixed to the truss. The side formwork is hoisted and spliced. The side formwork is connected to the sliding device through a movable foot bolt and fixed to the end formwork with bolts. The sliding device is fixed in position with the truss structure by fixing anchor bolts, and the sliding device and the side formwork are supported by bolts. Step 9: Concrete pouring: After the surveying team completes the template re-measurement and the supervisor reports the inspection, concrete pouring begins. During the pouring process, the supply and quality of concrete must be guaranteed, and the vibration must be in place. After the pouring is completed, water cooling and maintenance should be carried out in time; Step 10: Remove part of the formwork. After the concrete strength reaches the standard, remove the formwork, release the bolts fixing the end formwork, loosen the anchor bolts between the sliding device and the truss structure, push the sliding device and the side formwork away from the cap beam, loosen the bolts supporting the sliding device and the side formwork, close the side formwork, and remove the side formwork, sliding device, and end formwork in sequence; Step 11. Remove the bottom formwork and dismantle and transport the system. After the concrete strength reaches the standard and the pouring days meet the requirements, the height adjustment hydraulic cylinder and the height fine-adjustment hydraulic cylinder are used to return the oil and shrink. The overall height of the system is lowered, the bottom formwork is hoisted and removed, and the truss structure movable hinged adjustment block is hoisted and removed. At this time, the system becomes two parts again. If the next pier site is nearby, it can be dragged to the next pier site after the mobile device fixed block is folded. If it is far away, it will be completely disassembled and loaded for transportation.