Assembly type wind power tower drum

By designing the prefabricated wind power tower and using installation components and connectors to protect the main body of the tower, the problem of tower damage during the installation process is solved, the structural strength and assembly efficiency are improved, and precise docking and stable connection are achieved.

CN118757328AActive Publication Date: 2024-10-11HUANENG CLEAN ENERGY RES INST +2
View PDF 8 Cites 0 Cited by

Patent Information

Application Number
CN202410996809.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-24
Publication Date
2024-10-11
Estimated Expiration
2044-07-24

AI Technical Summary

Technical Problem

Wind power towers are easily damaged during installation, affecting structural strength and assembly efficiency.

Method used

A prefabricated wind power tower is designed, which uses a combination of installation components and connectors. The tower body is connected to the installation components through the connectors. Gravity is used to insert the lower end of the tower body into the installation cavity to protect the tower body from damage. And precise docking is achieved through docking components and adjustment parts to improve connection stability.

Benefits of technology

It effectively protects the structural strength of the wind power tower, improves the efficiency and accuracy of the installation process, and ensures the stability and assembly efficiency of the tower body's underground installation on site.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118757328A_ABST
    Figure CN118757328A_ABST
Patent Text Reader

Abstract

The invention discloses an assembly type wind power tower drum which comprises a tower drum main body and an installation assembly, a first through hole and a second through hole are formed in the lower end of the tower drum main body, the first through hole and the second through hole are arranged at intervals in the vertical direction, and the first through hole is adjacent to the lower end of the tower drum main body; the mounting part is provided with a mounting cavity extending in the vertical direction, at least part of the lower end of the tower drum body can be inserted into the mounting cavity, the connecting part is arranged on the mounting part and used for connecting the mounting part and the tower drum body, the tower drum body has a first position and a second position, the connecting part is connected with the tower drum body through the first penetrating hole in the first position, and the connecting part is connected with the tower drum body through the second penetrating hole in the second position. The connecting piece is connected with the tower drum body through the second penetrating hole. The assembly type wind power tower drum has the advantages of being high in structural strength and high in assembly efficiency.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of wind turbine towers, and in particular to an assembled wind turbine tower. Background Art

[0002] Wind power generation refers to converting the kinetic energy of wind into electrical energy. Wind power generation equipment needs to be installed outdoors. Wind power equipment includes wind power towers and wind turbine blades. The wind power tower is used to support the wind turbine blades.

[0003] In the related art, when installing a wind turbine tower, the lower end of the wind turbine tower is usually buried underground first for stable installation. However, during the burying process, the lower end of the wind turbine tower is easily damaged, affecting the structural strength and assembly efficiency of the wind turbine tower. Summary of the invention

[0004] The present invention aims to solve one of the technical problems in the related art at least to a certain extent. To this end, an embodiment of the present invention provides an assembled wind power tower.

[0005] The assembled wind power tower of the embodiment of the present invention comprises:

[0006] A tower body, wherein the lower end of the tower body has a first through hole and a second through hole, the first through hole and the second through hole are arranged at intervals in the up-down direction, and the first through hole is adjacent to the lower end of the tower body;

[0007] The mounting assembly includes a mounting member and a connecting member, the mounting member has a mounting cavity extending along the up-down direction, at least a portion of the lower end of the tower body can be inserted into the mounting cavity, the connecting member is arranged on the mounting member to connect the mounting member and the tower body, the tower body has a first position and a second position, in the first position, the connecting member is connected to the tower body through the first through hole, and in the second position, the connecting member is connected to the tower body through the second through hole.

[0008] For the assembled wind turbine tower of the embodiment of the present invention, when the tower body is installed, the tower body and the mounting part are first connected by a connecting piece and the tower body is located in a first position. After the mounting part is buried underground, the connecting piece is removed, and the tower body can move downward under the action of its own gravity and inserted into the installation cavity. At this time, the tower body is located in the second position, and the tower body and the mounting part are then connected by a connecting piece, so that the tower body and the mounting part are firmly connected. Therefore, during the installation of the tower body, the mounting part can protect the tower body, so that the lower end of the tower body is not easily damaged, thereby ensuring the structural strength of the tower body, facilitating on-site underground installation of the tower body, and ensuring assembly efficiency.

[0009] In some embodiments, the assembled wind turbine tower further comprises:

[0010] A docking tube, which is arranged at the upper end of the tower body and connected to the tower body;

[0011] A docking assembly is arranged between the tower body and the docking barrel to align the docking barrel and the tower body.

[0012] In some embodiments, the docking assembly includes:

[0013] A docking seat, at least a portion of which abuts against the tower body and the docking tube;

[0014] A first clamping member and a second clamping member, wherein the first clamping member and the second clamping member are respectively arranged on both sides of the docking seat and are arranged opposite to each other, one end of the first clamping member is rotatably connected to the docking seat, and one end of the second clamping member is rotatably connected to the docking seat, a clamping space is formed between the first clamping member and the second clamping member, and the tower body is arranged in the clamping space;

[0015] An adjusting member is disposed on the docking seat and connected to the first clamping member and the second clamping member, and is used to adjust the first clamping member and the second clamping member to rotate relative to the docking seat to adjust the size of the clamping space.

[0016] In some embodiments, the adjustment member comprises:

[0017] a first adjusting member, wherein the number of the first adjusting members is two, and the two first adjusting members are arranged at intervals along the up-down direction, wherein one of the first adjusting members is connected to the top surface of the first clamping member, and the other of the first adjusting members is connected to the bottom surface of the first clamping member;

[0018] The second adjusting member includes two second adjusting members, which are spaced apart in the up-down direction, wherein one of the second adjusting members is connected to the top surface of the second clamping member, and the other second adjusting member is connected to the bottom surface of the second clamping member.

[0019] In some embodiments, the first adjusting member comprises:

[0020] Sprockets, there are two sprockets, the two sprockets are arranged on the docking seat and spaced apart along a first direction, the first direction is orthogonal to the up-down direction, and the sprockets can rotate around the up-down direction relative to the docking seat;

[0021] A chain belt, the chain belt is arranged around the two sprockets and meshed with the sprockets, the sprockets rotate around the up-down direction to drive the chain belt to rotate around the up-down direction;

[0022] A connecting rod, one end of which is connected to the chain belt and meshed with the chain belt, and the chain belt rotates around the up-down direction to drive the connecting rod to move along the first direction;

[0023] A pull rod, one end of which is rotatably connected to the connecting rod, and the other end of which is rotatably connected to the first clamping member, wherein the connecting rod moves along the first direction to drive the pull rod to move, thereby driving the first clamping member to rotate relative to the docking seat;

[0024] A driving member is connected to one of the sprockets to drive one of the sprockets to rotate around the up-down direction.

[0025] In some embodiments, a side surface of the first clamping member adjacent to the second clamping member is a concave surface convex toward and away from the second clamping member, and a side surface of the second clamping member adjacent to the first clamping member is a concave surface convex toward and away from the first clamping member.

[0026] In some embodiments, the connector includes:

[0027] A connecting plate, the connecting plate being arranged on the upper end of the mounting member, the connecting plate having a connecting hole, and the connecting hole may correspond to the first through hole or the second through hole;

[0028] A connecting rod is inserted into the connecting hole and the first through hole or the second through hole.

[0029] In some embodiments, the assembled wind turbine tower also includes a plug-in, which is arranged at the lower end of the tower body and extends along the up and down directions. A positioning groove is provided in the installation cavity. When the tower body is in the second position, the plug-in can be inserted into the positioning groove and adapt to the positioning groove.

[0030] In some embodiments, the mounting member comprises:

[0031] An underground portion, wherein the underground portion is suitable for being buried underground, and a flange is provided at the lower end of the underground portion, and the flange is arranged around the circumference of the underground portion;

[0032] The mounting portion is arranged at the upper end of the buried portion, and the mounting cavity is formed on the mounting portion.

[0033] In some embodiments, the assembled wind turbine tower further includes an assembly component, and the assembly component includes:

[0034] A track and a slider, wherein the track is arranged on the docking tube and surrounds the circumference of the docking tube, and the slider is slidably installed in the track;

[0035] A ground-inserting nail and a fixed pulley, wherein the ground-inserting nail is inserted into the ground, and the fixed pulley is arranged on the ground-inserting nail;

[0036] A cable, one end of which is connected to the slider, and the other end of which passes through the fixed pulley. BRIEF DESCRIPTION OF THE DRAWINGS

[0037] Figure 1 It is a schematic diagram of an assembled wind turbine tower according to an embodiment of the present invention.

[0038] Figure 2 It is a schematic diagram of the assembled wind turbine tower from another perspective according to an embodiment of the present invention.

[0039] Figure 3 It is an exploded schematic diagram of the connection between the tower body and the mounting assembly of the assembled wind power tower according to an embodiment of the present invention.

[0040] Figure 4 It is a schematic diagram of a docking assembly of an assembled wind turbine tower according to an embodiment of the present invention.

[0041] Figure 5 It is a cross-sectional view of the installation assembly of the assembled wind power tower according to an embodiment of the present invention.

[0042] Reference numerals: 1, tower body; 11, first through hole; 12, second through hole; 2, mounting assembly; 21, mounting member; 211, mounting cavity; 212, positioning groove; 213, buried part; 214, mounting part; 215, flange; 22, connecting member; 221, connecting plate; 2211, connecting hole; 222, connecting rod; 3, docking tube; 4, docking assembly; 41, docking seat; 42, first clamp Holding member; 43, second clamping member; 44, adjusting member; 441, first adjusting member; 4411, sprocket; 4412, chain belt; 4413, connecting rod; 4414, pull rod; 4415, driving member; 442, second adjusting member; 45, clamping space; 46, frame; 5, plug-in; 6, assembly component; 61, track; 62, slider; 63, ground nail; 64, fixed pulley; 65, cable. DETAILED DESCRIPTION

[0043] Embodiments of the present invention are described in detail below, and examples of the embodiments are shown in the accompanying drawings. The embodiments described below with reference to the accompanying drawings are exemplary and intended to be used to explain the present invention, but should not be understood as limiting the present invention.

[0044] like Figure 1-Figure 5As shown, the assembled wind power tower of the embodiment of the present invention comprises a tower body 1 and a mounting assembly 2. The tower body 1 extends in the up-down direction, and the lower end of the tower body 1 has a first through hole 11 and a second through hole 12, the first through hole 11 and the second through hole 12 are arranged at intervals in the up-down direction, and the first through hole 11 is adjacent to the lower end of the tower body 1.

[0045] Specifically, there are multiple first through-holes 11, which are arranged at intervals around the circumference of the tower body 1. There are also multiple second through-holes 12, which are arranged at intervals around the circumference of the tower body 1, and the multiple second through-holes 12 correspond to the multiple first through-holes 11 one by one.

[0046] The mounting assembly 2 includes a mounting member 21 and a connecting member 22. The mounting member 21 extends in the up-down direction, and has a mounting cavity 211 extending from the upper end of the mounting member 21 toward the lower end of the mounting member 21. At least a portion of the lower end of the tower body 1 can be inserted into the mounting cavity 211, and the connecting member 22 is provided on the mounting member 21 for connecting the mounting member 21 and the tower body 1.

[0047] The tower body 1 has a first position and a second position. In the first position, the connecting member 22 is connected to the tower body 1 through the first through hole 11. In the second position, the connecting member 22 is connected to the tower body 1 through the second through hole 12.

[0048] For the assembled wind power tower of the embodiment of the present invention, when the tower body 1 is installed, the tower body 1 and the mounting member 21 are first connected by the connecting member 22 and the tower body 1 is located in the first position. After the mounting member 21 is buried underground, the connecting member 22 is removed, and the tower body 1 can move downward under the action of its own gravity and be inserted into the installation cavity 211. At this time, the tower body 1 is located in the second position, and then the tower body 1 and the mounting member 21 are connected by the connecting member 22, so that the tower body 1 and the mounting member 21 are firmly connected. Therefore, during the installation of the tower body 1, the mounting member 21 can protect the tower body 1, so that the lower end of the tower body 1 is not easily damaged, thereby ensuring the structural strength of the tower body 1, facilitating the on-site underground installation of the tower body 1, and ensuring the assembly efficiency.

[0049] In some embodiments, the assembled wind turbine tower further includes a docking tube 3 and a docking assembly 4. The docking tube 3 extends in the up-down direction, and is disposed at the upper end of the tower body 1 and connected to the tower body 1. The docking assembly 4 is disposed between the tower body 1 and the docking tube 3, so as to align the docking tube 3 with the tower body 1, thereby improving the accuracy of the connection between the docking tube 3 and the tower body 1.

[0050] In some embodiments, the docking assembly 4 includes a docking seat 41, a first clamping member 42, a second clamping member 43, and an adjusting member 44. At least part of the docking seat 41 abuts against the tower body 1 and the docking tube 3. Specifically, the upper end of the docking seat 41 abuts against the outer circumference of the docking tube 3, and the lower end of the docking seat 41 abuts against the outer circumference of the tower body 1.

[0051] The first clamping member 42 and the second clamping member 43 are respectively arranged on both sides of the docking seat 41 and are arranged opposite to each other. One end of the first clamping member 42 is rotatably connected to the docking seat 41, and one end of the second clamping member 43 is rotatably connected to the docking seat 41. A clamping space 45 is formed between the first clamping member 42 and the second clamping member 43, and the tower body 1 is arranged in the clamping space 45.

[0052] Specifically, the first clamping member 42 and the second clamping member 43 are rotatably connected to the docking seat 41 through the torsion spring shaft. The tower body 1 and the docking sleeve 3 are clamped by the first clamping member 42 and the second clamping member 43, which further improves the accuracy of the connection between the docking sleeve 3 and the tower body 1, so that the tower body 1 and the docking sleeve 3 are firmly connected.

[0053] The adjusting member 44 is disposed on the docking seat 41 and connected to the first clamping member 42 and the second clamping member 43 . The adjusting member 44 is used to adjust the first clamping member 42 and the second clamping member 43 to rotate relative to the docking seat 41 to adjust the size of the clamping space 45 .

[0054] Specifically, by adjusting the size of the clamping space 45, the connection between the docking tube 3 and the tower body 1 is clamped, thereby improving the stability of the connection between the docking tube 3 and the tower body 1. In addition, the size of the clamping space 45 is adjustable, so that the docking assembly 4 can be used for tower bodies 1 and docking tubes 3 of different specifications and sizes, thereby improving the applicability of the docking assembly 4.

[0055] In some embodiments, the docking assembly 4 further includes a frame 46 , which is disposed on the docking seat 41 , and the adjusting member 44 is disposed on the frame 46 .

[0056] In some embodiments, the adjusting member 44 includes a first adjusting member 441 and a second adjusting member 442. There are two first adjusting members 441, and the two first adjusting members 441 are arranged at intervals in the up-down direction, wherein one first adjusting member 441 is connected to the top surface of the first clamping member 42, and the other first adjusting member 441 is connected to the bottom surface of the first clamping member 42. The provision of the two first adjusting members 441 improves the controllability of the first adjusting member 441 on the first clamping member 42, so that the first adjusting member 441 controls the first clamping member 42 with higher precision.

[0057] There are two second adjusting members 442, which are arranged at intervals in the up-down direction, one of which is connected to the top surface of the second clamping member 43, and the other is connected to the bottom surface of the second clamping member 43. The provision of the two second adjusting members 442 improves the controllability of the second adjusting member 442 on the second clamping member 43, so that the second adjusting member 442 can control the second clamping member 43 with higher accuracy.

[0058] In some embodiments, the first adjusting member 441 and the second adjusting member 442 have the same structure, and the first adjusting member 441 is taken as an example for description.

[0059] The first adjusting member 441 includes a sprocket 4411, a chain belt 4412, a connecting rod 4413, a pull rod 4414 and a driving member 4415. There are two sprockets 4411, which are arranged on the docking seat 41 and spaced apart along a first direction, the first direction is orthogonal to the up-down direction, and the sprockets 4411 can rotate in the up-down direction relative to the docking seat 41. Specifically, one of the sprockets 4411 is a driving wheel and is connected to the driving member 4415, and the driving member 4415 is used to drive the sprocket 4411 to rotate in the up-down direction, and the other sprocket 4411 is a driven wheel.

[0060] The chain belt 4412 is arranged around the two sprocket wheels 4411 and meshed with the sprocket wheels 4411. The sprocket wheels 4411 rotate in the up-down direction to drive the chain belt 4412 to rotate in the up-down direction. One end of the connecting rod 4413 is connected to the chain belt 4412 and meshed with the chain belt 4412. The chain belt 4412 rotates in the up-down direction to drive the connecting rod 4413 to move in the first direction. One end of the pull rod 4414 is rotatably connected to the connecting rod 4413, and the other end of the pull rod 4414 is rotatably connected to the first clamping member 42. The connecting rod 4413 moves in the first direction to drive the pull rod 4414 to move, thereby driving the first clamping member 42 to rotate relative to the docking seat 41.

[0061] Specifically, the driving member 4415 drives one of the sprockets 4411 to rotate in the up-down direction, and the sprocket 4411 drives the other sprocket 4411 to rotate in the up-down direction through the chain belt 4412. One end of the connecting rod 4413 is arranged on the side of the chain belt 4412 away from the second adjusting member 442, so as to move along the first direction with the rotation of the chain belt 4412. When the connecting rod 4413 moves in the first direction, it pulls the pull rod 4414 to control the movement of the first clamping member 42, so as to clamp and connect the connection between the tower body 1 and the docking tube 3 through the first clamping member 42 and the second clamping member 43.

[0062] The working principle of the docking assembly 4 is as follows: the driving member 4415 drives one of the sprockets 4411 to rotate in the up and down directions, which can drive the chain belt 4412 to rotate in the up and down directions, so as to pull the connecting rod 4413 to move, and then pull the pull rod 4414 to move, and then pull the first clamping member 42 and the second clamping member 43 to expand through the pull rod 4414. After the first clamping member 42 and the second clamping member 43 are expanded, the docking tube 3 and the tower body 1 are docked. After the tower body 1 and the docking tube 3 are docked, the pull rod 4414 is pulled by pulling the connecting rod 4413. The pull rod 4414 pushes the first clamping member 42 and the second clamping member 43 to tighten, so as to clamp the connection between the tower body 1 and the docking tube 3, and clamp the docking position, thereby increasing the stability of the assembly connection. Moreover, the working principle is simple, easy to operate, and easy to implement.

[0063] In some embodiments, the side surface of the first clamping member 42 adjacent to the second clamping member 43 is a concave surface convex toward and away from the second clamping member 43 , and the side surface of the second clamping member 43 adjacent to the first clamping member 42 is a concave surface convex toward and away from the first clamping member 42 .

[0064] Specifically, the concave surface of the first clamping member 42 and the concave surface of the second clamping member 43 can be adapted to the outer wall surface of the tower body 1 or the outer wall surface of the docking tube 3, so that the contact area between the first clamping member 42 and the second clamping member 43 and the tower body 1 or the docking tube 3 is increased, and the assembly and docking of the tower body 1 and the docking tube 3 can be better completed by the first clamping member 42 and the second clamping member 43, further increasing the stability of the assembly connection between the tower body 1 and the docking tube 3.

[0065] In some embodiments, the connecting member 22 includes a connecting plate 221 and a connecting rod 222. The connecting plate 221 is disposed at the upper end of the mounting member 21, and has a connecting hole 2211 thereon, and the connecting hole 2211 may correspond to the first through hole 11 or the second through hole 12. The connecting rod 222 is disposed in the connecting hole 2211 and the first through hole 11 or the second through hole 12.

[0066] Specifically, the cross section of the connecting plate 221 is trapezoidal, and the end of the connecting plate 221 with a smaller cross section is adjacent to the mounting cavity 211. There are multiple connecting plates 221, and the multiple connecting plates 221 are arranged at intervals around the circumference of the mounting member 21. The multiple connecting plates 221 correspond one-to-one to the multiple first through holes 11. There are also multiple connecting rods 222, and the multiple connecting rods 222 correspond one-to-one to the multiple connecting plates 221.

[0067] When the mounting member 21 is buried underground, at least part of the lower end of the tower body 1 is inserted into the mounting cavity 211 so that the first through hole 11 corresponds to the connecting hole 2211, and the connecting rod 222 passes through the connecting hole 2211 and the first through hole 11 in sequence so that the tower body 1 is located in the first position. The upper end of the mounting member 21 can protect the lower end of the tower body 1, so that the lower end of the tower body 1 is not easily damaged.

[0068] After the mounting member 21 is buried, the connecting rod 222 is pulled out from the connecting hole 2211, and the tower body 1 moves downward under the action of its own gravity so that the second through hole 12 corresponds to the connecting hole 2211. The connecting rod 222 passes through the connecting hole 2211 and the second through hole 12 in sequence, and the tower body 1 is located in the second position, so that the tower body 1 is firmly installed in the mounting member 21 and the operation process is simple.

[0069] In some embodiments, the assembled wind turbine tower further includes a plug-in 5, which is disposed at the lower end of the tower body 1 and extends in the up-down direction. A positioning groove 212 is disposed in the installation cavity 211, and when the tower body 1 is in the second position, the plug-in 5 can be inserted into the positioning groove 212 and fit with the positioning groove 212.

[0070] Specifically, the cross section of the plug 5 is a cross. The positioning groove 212 is located at the bottom of the installation cavity 211 and has a cross cross section. When the tower body 1 is in the second position, the plug 5 is inserted into the positioning groove 212, and the positioning groove 212 can limit the tower body 1, so that the tower body 1 is installed firmly in the installation cavity 211 and is not easy to rotate.

[0071] In some embodiments, the mounting member 21 includes an underground portion 213 and an installation portion 214. The underground portion 213 is suitable for being buried underground, and a flange 215 is provided at the lower end of the underground portion 213. The flange 215 is arranged around the circumference of the underground portion 213, so that the underground portion 213 is more firmly buried underground. The installation portion 214 is provided at the upper end of the underground portion 213, and the installation cavity 211 is formed on the installation portion 214.

[0072] Specifically, when the mounting member 21 is installed, the mounting portion 214 and the buried portion 213 are both buried underground, and the cross-sectional area of ​​the buried portion 213 is smaller than the cross-sectional area of ​​the mounting portion 214, so that the mounting member 21 is installed more firmly underground.

[0073] In some embodiments, the assembled wind turbine tower further includes an assembly component 6, which is suitable for use with a lifting device (not shown) to ensure that the wind turbine tower is stable when lifted.

[0074] The assembly component 6 includes a track 61, a slider 62, a ground-inserting nail 63, a fixed pulley 64 and a cable 65. The track 61 is arranged on the docking tube 3 and is arranged around the circumference of the docking tube 3. The slider 62 is slidably installed in the track 61. The ground-inserting nail 63 is inserted into the ground, and the fixed pulley 64 is arranged on the ground-inserting nail 63. One end of the cable 65 is connected to the slider 62, and the other end of the cable 65 passes through the fixed pulley 64.

[0075] Specifically, there are multiple sliders 62, and the multiple sliders 62 are all slidably mounted on the slide rail. There are multiple ground nails 63, multiple fixed pulleys 64 and multiple cables 65, and the multiple ground nails 63, multiple fixed pulleys 64 and multiple cables 65 correspond to each other.

[0076] During the hoisting and erecting process of the wind turbine tower, the other end of the cable 65 is pulled in the direction away from the wind turbine tower, and the wind turbine tower is erected in cooperation with the hoisting device to prevent the wind turbine tower from shaking too much during hoisting, thereby ensuring the stability of the wind turbine tower and improving the efficiency of on-site assembly and installation of the wind turbine tower.

[0077] In the description of the present invention, it is to be understood that the terms “center”, “longitudinal”, “lateral”, “length”, “width”, “thickness”, “up”, “down”, “front”, “back”, “left”, “right”, “vertical”, “horizontal”, “top”, “bottom”, “inside”, “outside”, “clockwise”, “counterclockwise”, “axial”, “radial”, “circumferential”, etc., indicating orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as limiting the present invention.

[0078] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In the description of the present invention, the meaning of "plurality" is at least two, such as two, three, etc., unless otherwise clearly and specifically defined.

[0079] In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral one; it can be a mechanical connection, an electrical connection, or communication with each other; it can be a direct connection, or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements, unless otherwise clearly defined. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0080] In the present invention, unless otherwise clearly specified and limited, a first feature being "above" or "below" a second feature may mean that the first and second features are in direct contact, or the first and second features are in indirect contact through an intermediate medium. Moreover, a first feature being "above", "above" or "above" a second feature may mean that the first feature is directly above or obliquely above the second feature, or simply means that the first feature is higher in level than the second feature. A first feature being "below", "below" or "below" a second feature may mean that the first feature is directly below or obliquely below the second feature, or simply means that the first feature is lower in level than the second feature.

[0081] In the present invention, the terms "one embodiment", "some embodiments", "examples", "specific examples", or "some examples" etc. mean that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the described specific features, structures, materials or characteristics may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, without contradiction.

[0082] Although the above embodiments have been shown and described, it is to be understood that the above embodiments are exemplary and are not to be construed as limitations on the present invention. Changes, modifications, substitutions and variations of the above embodiments by those of ordinary skill in the art are all within the scope of protection of the present invention.

Claims

1. An assembled wind power tower, characterized in that: include: A tower body (1), wherein the lower end of the tower body (1) has a first through hole (11) and a second through hole (12), the first through hole (11) and the second through hole (12) are arranged at intervals in the up-down direction, and the first through hole (11) is adjacent to the lower end of the tower body (1); A mounting assembly (2), the mounting assembly (2) comprising a mounting member (21) and a connecting member (22), the mounting member (21) having a mounting cavity (211) extending along the up-down direction, at least a portion of the lower end of the tower body (1) being insertable into the mounting cavity (211), the connecting member (22) being arranged on the mounting member (21) for connecting the mounting member (21) and the tower body (1), the tower body (1) having a first position and a second position, in the first position, the connecting member (22) being connected to the tower body (1) via the first through hole (11), and in the second position, the connecting member (22) being connected to the tower body (1) via the second through hole (12).

2. The assembled wind turbine tower according to claim 1, characterized in that: Also includes: A docking tube (3), wherein the docking tube (3) is arranged at the upper end of the tower body (1) and is connected to the tower body (1); A docking assembly (4) is provided between the tower body (1) and the docking cylinder (3) to align the docking cylinder (3) and the tower body (1).

3. The assembled wind turbine tower according to claim 2, characterized in that: The docking assembly (4) comprises: A docking seat (41), at least a portion of which abuts against the tower body (1) and the docking tube (3); a first clamping member (42) and a second clamping member (43), wherein the first clamping member (42) and the second clamping member (43) are respectively arranged on both sides of the docking seat (41) and are arranged opposite to each other, one end of the first clamping member (42) is rotatably connected to the docking seat (41), and one end of the second clamping member (43) is rotatably connected to the docking seat (41), a clamping space (45) is formed between the first clamping member (42) and the second clamping member (43), and the tower body (1) is arranged in the clamping space (45); An adjusting member (44) is disposed on the docking seat (41) and is connected to the first clamping member (42) and the second clamping member (43). The adjusting member (44) is used to adjust the first clamping member (42) and the second clamping member (43) to rotate relative to the docking seat (41) to adjust the size of the clamping space (45).

4. The assembled wind power tower according to claim 3, characterized in that: The adjusting member (44) comprises: A first adjusting member (441), wherein the number of the first adjusting members (441) is two, and the two first adjusting members (441) are arranged at intervals along the up-down direction, wherein one of the first adjusting members (441) is connected to the top surface of the first clamping member (42), and the other of the first adjusting members (441) is connected to the bottom surface of the first clamping member (42); A second adjusting member (442), wherein there are two second adjusting members (442), and the two second adjusting members (442) are arranged at intervals in the up-down direction, wherein one of the second adjusting members (442) is connected to the top surface of the second clamping member (43), and the other second adjusting member (442) is connected to the bottom surface of the second clamping member (43).

5. The assembled wind power tower according to claim 4, characterized in that: The first adjusting member (441) comprises: Sprockets (4411), there are two sprockets (4411), the two sprockets (4411) are arranged on the docking seat (41) and are spaced apart along a first direction, the first direction is orthogonal to the up-down direction, and the sprockets (4411) can rotate around the up-down direction relative to the docking seat (41); A chain belt (4412), wherein the chain belt (4412) is arranged around the two sprockets (4411) and meshes with the sprockets (4411), and the sprockets (4411) rotate in the up-down direction to drive the chain belt (4412) to rotate in the up-down direction; a connecting rod (4413), one end of which is connected to the chain belt (4412) and meshed with the chain belt (4412), and the chain belt (4412) rotates around the up-down direction to drive the connecting rod (4413) to move along the first direction; A pull rod (4414), one end of the pull rod (4414) is rotatably connected to the connecting rod (4413), and the other end of the pull rod (4414) is rotatably connected to the first clamping member (42), and the connecting rod (4413) moves along the first direction to drive the pull rod (4414) to move, thereby driving the first clamping member (42) to rotate relative to the docking seat (41); A driving member (4415), wherein the driving member (4415) is connected to one of the sprockets (4411) to drive one of the sprockets (4411) to rotate around the up-down direction.

6. The assembled wind power tower according to claim 3, characterized in that: The side surface of the first clamping member (42) adjacent to the second clamping member (43) is a concave surface convex toward and away from the second clamping member (43), and the side surface of the second clamping member (43) adjacent to the first clamping member (42) is a concave surface convex toward and away from the first clamping member (42).

7. The assembled wind power tower according to claim 1, characterized in that: The connecting member (22) comprises: a connecting plate (221), the connecting plate (221) being arranged at the upper end of the mounting member (21), the connecting plate (221) having a connecting hole (2211), the connecting hole (2211) being able to correspond to the first through hole (11) or the second through hole (12); A connecting rod (222), wherein the connecting rod (222) is inserted into the connecting hole (2211) and the first through hole (11) or the second through hole (12).

8. The assembled wind power tower according to claim 1, characterized in that: It also includes a plug-in (5), which is arranged at the lower end of the tower body (1) and extends along the up-down direction. A positioning groove (212) is provided in the installation cavity (211). When the tower body (1) is in the second position, the plug-in (5) can be inserted into the positioning groove (212) and fit with the positioning groove (212).

9. The assembled wind power tower according to claim 1, characterized in that: The mounting member (21) comprises: An underground portion (213), the underground portion (213) being suitable for being buried underground, a flange (215) being provided at the lower end of the underground portion (213), and the flange (215) being arranged around the circumference of the underground portion (213); A mounting portion (214), wherein the mounting portion (214) is disposed at the upper end of the buried portion (213), and the mounting cavity (211) is formed on the mounting portion (214).

10. The assembled wind power tower according to claim 2, characterized in that: It also includes an assembly component (6), the assembly component (6) including: A track (61) and a slider (62), wherein the track (61) is arranged on the docking tube (3) and surrounds the circumference of the docking tube (3), and the slider (62) is slidably installed in the track (61); A ground-inserting nail (63) and a fixed pulley (64), wherein the ground-inserting nail (63) is inserted into the ground, and the fixed pulley (64) is arranged on the ground-inserting nail (63); A cable (65), one end of which is connected to the slider (62), and the other end of which passes through the fixed pulley (64).

Citation Information

Patent Citations

  • Fan foundation and construction method

    CN117166525A

  • Clamping assembly and tower drum hoisting equipment

    CN117509404A

  • Tower foundation and wind generating set

    CN210135037U

  • Tower drum and self-lifting equipment of tower drum

    CN211666851U

  • Fabricated wind power tower drum with pier columns at bottom

    CN213981057U