BIM-based fabricated building data collaborative management method and system
By introducing the central management unit and task scheduling unit on the BIM collaboration platform, the storage and real-time data monitoring of construction project information models are realized, which solves the problem of high information transmission and communication costs in the existing technology and improves the collaborative management of construction projects. Efficiency and data consistency.
Patent Information
- Application Number
- CN202410746205.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-11
- Publication Date
- 2024-10-11
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The existing BIM collaboration platform takes a long time and costs a lot in information transmission and communication, and it is difficult to effectively manage the data and tasks of construction projects, resulting in low efficiency in collaborative management of construction projects.
A BIM-based prefabricated building data collaborative management system is designed, including a BIM platform, a central management unit, a data monitoring unit and a task scheduling unit. Through the BIM platform's visual display, authority management module, data interaction interface, and file management module , database management module, data analysis module and monitoring data feedback module to realize the storage, management, real-time data monitoring and task scheduling of construction project information models.
It improves the efficiency of data collaborative management of construction projects, reduces the time and cost of information transmission and communication, and ensures timely management of construction progress and data consistency and reliability.
Smart Images

Figure CN118760665A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of construction, and in particular to the field of collaborative management systems for prefabricated building data. Background Art
[0002] BIM is the abbreviation of Building Information Modeling. It is a digital building design and management method that creates, maintains and shares various information of building projects to achieve project coordination, visualization and optimization. BIM uses three-dimensional models to integrate architectural design, structural design, mechanical and electrical engineering and other related information, so that all parties involved can work together better, reduce errors and conflicts, and improve the efficiency and quality of the project; the technical background of the prefabricated building data collaborative management system mainly involves the integration of building data collaborative management technology, BIM technology and other auxiliary functions, aiming to reduce the time cost of communication and coordination for all parties involved and improve the overall efficiency of the project.
[0003] This experimental team has been browsing and studying a large number of relevant records and materials for the relevant technologies of BIM and prefabricated building data collaborative management for a long time. At the same time, it relies on relevant resources and conducts a large number of relevant experiments. After a large number of searches, it is found that there are existing technologies such as JP2020096647, US20130303193A1, US09525976B2 and CN109191577B. For example, a distributed BIM collaborative platform in the prior art includes: a platform host, an architectural design team node, a structural design team node, a mechanical and electrical pipeline design team node, a construction team node, a construction team node and a survey team node connected to the platform host, and each team node is connected to multiple work nodes; the platform host is used to integrate, process and store all models, data and information of the project. After the integration is completed, the latest data, information and models are updated to all team nodes, and an interface for docking with external users is provided. The team node includes a model integration module, a collision detection module and a bandwidth monitoring module, and the work node includes a design module. Such a BIM collaborative platform has low working efficiency, and the time and cost of information transmission and communication are high.
[0004] The present invention is made in order to effectively solve the problems in this field, such as the difficulty in targeted collaborative management of prefabricated building data and engineering process management. Summary of the invention
[0005] The purpose of the present invention is to propose a BIM-based prefabricated building data collaborative management method and system to address the deficiencies in the current prior art.
[0006] In order to overcome the shortcomings of the prior art, the present invention adopts the following technical solutions:
[0007] The prefabricated building data collaborative management system includes a BIM platform for storing and managing building project information models, a central management unit connected to the BIM platform for managing and maintaining BIM model data, a data monitoring unit connected to the central management unit for acquiring real-time data during the construction process, and a task scheduling unit connected to the central management unit for dispatching tasks to project managers based on assembly information and process flow in the BIM model;
[0008] The BIM platform includes a visual display that allows users to intuitively view and manage building models and project progress, a rights management module that controls the access rights of different users to BIM models and system functions, and a data interaction interface for participants to collaboratively edit and update BIM models on their personal computers or tablets. Participants include architects, project managers, supervision engineers, and project managers.
[0009] The central management unit includes: a file management module that stores and manages BIM models and is connected to the BIM platform, a database management module that is connected to the file management module and records updates and modifications to each BIM model version data, a data analysis module that is connected to the database management module and analyzes and processes BIM model data, and a monitoring data feedback module that is connected to the data monitoring unit and the data analysis module and analyzes data obtained by the data monitoring unit; the data analysis module automatically generates a primary task list based on the BIM model.
[0010] Optionally, the task scheduling unit includes a task allocator connected to the data analysis module and the BIM platform, which allocates tasks to corresponding project managers according to specific task arrangements; a resource allocator connected to the task allocator and the BIM platform, which performs resource scheduling according to a final task list; and a task manager connected to the data monitoring unit, the task allocator, and the BIM platform to track task progress.
[0011] Optionally, the central management unit acts as a host computer and is responsible for the overall scheduling and management of other units.
[0012] Optionally, the processing flow of the BIM model by the central management unit includes the following steps:
[0013] Step S1: The architect uploads the identity information to the authority management module, and after obtaining the authority, sends the BIM model data to the file management module through the data interaction interface;
[0014] Step S2: the file management module parses the BIM model data to extract geometric information in the model, and sends the geometric information and updated BIM model data to the database management module;
[0015] Step S3: the database management module BIM model performs version control, records the modification history of the model and the differences between different versions, so as to facilitate traceability and management;
[0016] Step S4: When the user selects the automatic task assignment option on the BIM platform, the database management module sends the latest version of the BIM model to the data analysis module;
[0017] Step S5: The data analysis module analyzes and counts the latest version of the BIM model to obtain the engineering task volume. The project manager selects the project manager on the BIM platform to assign tasks based on project requirements and resource availability, and sends the specific task arrangements to the task scheduling unit;
[0018] Step S6: the task scheduling unit assigns the task to the corresponding project manager according to the specific task arrangement;
[0019] Step S7: the data monitoring unit continuously monitors the monitoring data of the construction site and sends it to the monitoring data feedback module;
[0020] Step S8: The monitoring data feedback module analyzes the monitoring data, preliminarily evaluates the deviation between the actual construction progress and the planned progress, and provides corresponding reports and visualization charts, and sends the results to the BIM platform to help the project manager manage and adjust the progress;
[0021] Step S9: Before the construction machinery and equipment enter the site, the project manager uploads the identity information to the authority management module to obtain the authority, and submits the list of equipment entering the site on the BIM platform. The list of equipment entering the site includes the type, specification, quantity, technical performance, equipment status, and entry time of the equipment entering the site;
[0022] Step S10: After the construction machinery and equipment enter the site, the supervision engineer checks the working status of the machinery and equipment, uploads the identity information to the authority management module to obtain authority, and completes the security log recording on the BIM platform.
[0023] The beneficial effects achieved by the present invention are:
[0024] 1. By using the prefabricated building data collaborative management system, the storage, management and maintenance of the construction project information model, as well as real-time data monitoring and task scheduling can be realized, thereby improving the efficiency of data collaborative management of construction projects and reducing the time and cost of information transmission and communication.
[0025] 2. Through the data monitoring unit and monitoring data feedback module, the monitoring data of the construction site can be continuously monitored, and the deviation between the actual construction progress and the planned progress can be analyzed and evaluated, problems can be discovered in time, and corresponding reports and visual charts can be provided to help project managers manage and adjust the progress.
[0026] 3. Through the permission management module and data interaction interface of the BIM platform, participants can collaboratively edit and update BIM models on their personal computers or tablets, improving the efficiency of communication and collaboration between different participants and reducing the risk of information transmission and misunderstanding.
[0027] 4. The file management module and database management module of the central management unit can perform version control and record modification history of the BIM model, facilitate model traceability and management, and ensure data consistency and reliability of the project. BRIEF DESCRIPTION OF THE DRAWINGS
[0028] The present invention can be further understood from the following description in conjunction with the accompanying drawings. The components in the figures are not necessarily drawn to scale, but the emphasis is placed on illustrating the principles of the embodiments. In different views, the same reference numerals designate corresponding parts.
[0029] Figure 1 It is a modular schematic diagram of the prefabricated building data collaborative management system of the present invention.
[0030] Figure 2 It is a modular schematic diagram of the BIM platform of the present invention.
[0031] Figure 3 It is a modular schematic diagram of the task scheduling unit of the present invention.
[0032] Figure 4 It is a flow chart of the central management unit of the present invention.
[0033] Figure 5 It is a flowchart of the sampling step in the second embodiment of the present invention.
[0034] Description of the accompanying drawings: 1-BIM platform; 2-file management module; 3-database management module; 4-data analysis module; 5-monitoring data feedback module; 6-data monitoring unit; 7-task scheduling unit; 8-architect; 9-project manager; 10-supervising engineer; 11-project manager; 12-data interaction interface; 13-authority management module; 14-visual display; 15-central management unit. DETAILED DESCRIPTION
[0035] In order to make the purpose, technical solutions and advantages of the present invention clearer, the present invention is further described in detail in conjunction with its embodiments below; it should be understood that the specific embodiments described herein are only used to explain the present invention and are not used to limit the present invention. For those skilled in the art, other systems, methods and / or features of the present embodiment will become apparent after reviewing the following detailed description. It is intended that all such additional systems, methods, features and advantages are included in this specification, included within the scope of the present invention, and protected by the appended claims. Additional features of the disclosed embodiments are described in the following detailed description, and these features will be apparent from the following detailed description.
[0036] The same or similar numbers in the drawings of the embodiments of the present invention correspond to the same or similar parts; in the description of the present invention, it should be understood that if the terms "upper", "lower", "left", "right" and the like indicate the orientation or position relationship based on the orientation or position relationship shown in the drawings, it is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or component referred to must have a specific orientation. It is constructed and operated in a specific orientation. Therefore, the terms describing the position relationship in the drawings are only used for illustrative purposes and cannot be understood as a limitation on this patent. For ordinary technicians in this field, the specific meanings of the above terms can be understood according to specific circumstances.
[0037] Embodiment 1:
[0038] This embodiment constructs a BIM-based prefabricated building data collaborative management method and system;
[0039] The prefabricated building data collaborative management system includes a BIM platform for storing and managing building project information models, a central management unit connected to the BIM platform for managing and maintaining BIM model data, a data monitoring unit connected to the central management unit for acquiring real-time data during the construction process, and a task scheduling unit connected to the central management unit for dispatching tasks to project managers based on assembly information and process flow in the BIM model;
[0040] The BIM platform includes a visual display that allows users to intuitively view and manage building models and project progress, a rights management module that controls the access rights of different users to BIM models and system functions, and a data interaction interface for participants to collaboratively edit and update BIM models on their personal computers or tablets. Participants include architects, project managers, supervision engineers, and project managers.
[0041] The central management unit includes: a file management module that stores and manages BIM models and is connected to the BIM platform, a database management module that is connected to the file management module and records updates and modifications to each BIM model version data, a data analysis module that is connected to the database management module and analyzes and processes BIM model data, and a monitoring data feedback module that is connected to the data monitoring unit and the data analysis module and analyzes data obtained by the data monitoring unit; the data analysis module automatically generates a primary task list based on the BIM model.
[0042] The task scheduling unit includes a task allocator connected to the data analysis module and the BIM platform to allocate tasks to corresponding project managers according to specific task arrangements; a resource allocator connected to the task allocator and the BIM platform to schedule resources according to a final task list; and a task manager connected to the data monitoring unit, the task allocator, and the BIM platform to track task progress.
[0043] The central management unit serves as a host computer and is responsible for the overall scheduling and management of other units.
[0044] The processing flow of the BIM model by the central management unit includes the following steps:
[0045] Step S1: The architect uploads the identity information to the authority management module through the BIM platform, and after obtaining the authority, sends the BIM model data to the file management module through the data interaction interface;
[0046] Step S2: the file management module parses the BIM model data to extract geometric information in the model, and sends the geometric information and updated BIM model data to the database management module;
[0047] Step S3: The database management module performs version control on the BIM model, and records the modification history of the model and the differences between different versions for traceability and management;
[0048] Step S4: When the user selects the automatic task assignment option on the BIM platform, the database management module sends the latest version of the BIM model to the data analysis module;
[0049] Step S5: The data analysis module analyzes and counts the latest version of the BIM model to obtain the engineering task volume. The project manager selects the project manager on the BIM platform to assign tasks based on project requirements and resource availability, and sends the specific task arrangements to the task scheduling unit;
[0050] Step S6: the task scheduling unit assigns the task to the corresponding project manager according to the specific task arrangement;
[0051] Step S7: the data monitoring unit continuously monitors the monitoring data of the construction site and sends it to the monitoring data feedback module;
[0052] Step S8: The monitoring data feedback module analyzes the monitoring data, preliminarily evaluates the deviation between the actual construction progress and the planned progress, and provides corresponding reports and visualization charts, and sends the results to the BIM platform to help the project manager manage and adjust the progress;
[0053] Step S9: Before the construction machinery and equipment enter the site, the project manager uploads the identity information to the authority management module to obtain the authority, and submits the list of equipment entering the site on the BIM platform. The list of equipment entering the site includes the type, specification, quantity, technical performance, equipment status, and entry time of the equipment entering the site;
[0054] Step S10: After the construction machinery and equipment enter the site, the supervision engineer checks the working status of the machinery and equipment, uploads the identity information to the authority management module to obtain authority, and completes the security log recording on the BIM platform.
[0055] This embodiment uses the prefabricated building data collaborative management system to achieve storage, management and maintenance of construction project information models, as well as real-time data monitoring and task scheduling, thereby improving the efficiency of data collaborative management of construction projects and reducing the time and cost of information transmission and communication.
[0056] Embodiment 2:
[0057] This embodiment should be understood to include all the features of any of the above embodiments, and further improve upon them. Figure 1-5 , but also:
[0058] The data monitoring unit includes a displacement sensor for monitoring the deformation and displacement of the building structure, a temperature sensor for monitoring the temperature change at the construction site, a humidity sensor for monitoring the average humidity at the construction site, an average wind speed sensor for measuring the average wind speed at the construction site, a pressure sensor for monitoring the pressure change of the building structure, an acceleration sensor for monitoring the vibration and vibration of the building structure, a sound sensor for monitoring the noise level, a gas sensor for monitoring the air quality and gas concentration, an electric power monitoring device for monitoring the power consumption, a video monitoring device for monitoring the safety of the construction site and the video of the construction progress, and a data acquisition device connected to the displacement sensor, temperature sensor, humidity sensor, wind speed sensor, pressure sensor, acceleration sensor, sound sensor, gas sensor, electric power monitoring device, and video monitoring device, and used to collect and record monitoring data.
[0059] The supervision engineer remotely accesses the video surveillance equipment on a personal computer or tablet computer through a data interaction interface. After the construction machinery and equipment enter the site, the supervision engineer checks the working status of the machinery and equipment, uploads the identity information to the authority management module to obtain the authority, and completes the security log record on the BIM platform;
[0060] Construction machinery and equipment include, but are not limited to, excavators, loaders, cranes, drilling machines, graders, roadbed machinery, compactors, and concrete machines.
[0061] After the supervision engineer completes the safety log record, the project manager can conduct a random inspection of the safety log. The steps for random inspection are as follows:
[0062] Step S21: The project manager selects a checklist of a certain device in the safety log on the BIM platform, for example, a specific excavator is selected as the inspection target;
[0063] Step S22: The project manager remotely accesses the video monitoring device on a personal computer or tablet computer through a data interaction interface, watches the current operating status of the excavator, compares the current operating status of the excavator with the items on the checklist, and determines whether there is any non-conformity with the items on the checklist. If there is any non-conformity, execute step S23; if there is no non-conformity, execute step S27;
[0064] Step S23: generating an abnormality report or warning on the BIM platform, indicating which items do not conform to the actual operating conditions of the excavator, providing corresponding suggestions or repair measures, and sending the report to the supervision engineer's personal computer or tablet through the data interaction interface;
[0065] Step S24: The supervision engineer contacts the maintenance personnel to follow up and perform repair and maintenance work according to the suggestions or repair measures provided in the abnormal report to ensure the normal operation of the excavator;
[0066] Step S25: The supervision engineer uploads the identity information to the authority management module to obtain authority, and updates the maintenance record of the excavator on the BIM platform, including the repaired items, the used parts and materials, and the maintenance time;
[0067] Step S26: After the maintenance is completed, execute step S22;
[0068] Step S27: Generate a qualified log report on the BIM platform.
[0069] This embodiment can continuously monitor the monitoring data of the construction site through the data monitoring unit and the monitoring data feedback module, analyze and evaluate the deviation between the actual construction progress and the planned progress, discover problems in time and provide corresponding reports and visual charts to help project managers manage and adjust the progress.
[0070] Embodiment three:
[0071] This embodiment should be understood to include all the features of any of the above embodiments, and further improve upon them. Figure 1-5 The video monitoring equipment includes a 3D structured light camera for acquiring an actual three-dimensional point cloud model of a building at a construction site; the central management unit also includes a method for predicting the work progress on the kth day, specifically including the following steps:
[0072] S31. The 3D structured light camera sends the actual 3D point cloud model acquired to the data analysis module; the data analysis module performs voxel segmentation on the BIM model and the actual 3D point model to obtain a voxel w of the BIM model. The voxel set A={A1,A2,A3...A w} and the v individual element set B={B1,B2,B3...B v};
[0073] S32. Calculate the total amount of work completed on day (k-1) as Where e is the total amount of work to be completed, which can be estimated based on the task list;
[0074] S33. The factors that affect the actual workload are: human resources, materials, weather, and equipment. The corresponding influences of the above factors are ε1, ε2, ε3, and ε4, thereby establishing an influence set ε = (ε1, ε2, ε3, ε4);
[0075] S34. Obtain the reported human resource parameter Y for the kth day 1k , material parameter Y 2k , weather parameter Y 3k , equipment parameter Y 4k The parameters can be preset by the project manager or supervision engineer according to the construction site conditions. For example, the k-1 day work report, personnel leave information, weather forecast to obtain the k-day material quantity and quality, equipment quantity and quality, human resources quantity and distribution, weather data, the system normalizes and quantifies this information to obtain the material parameter Y 2k , equipment parameter Y 4k , human resource parameter Y 1k , weather parameter Y 3k ;
[0076] S35. Obtain the standard value a of human resource parameters 1k , the standard value a of material parameters 2k , the standard value a of weather parameters 3k , the standard value a of equipment parameters 4k , and all the above-mentioned standard values of parameters are obtained by those skilled in the art through a limited number of experiments;
[0077] S36. Obtain the predicted work index for the k-th day When δ k < P, it indicates that the predicted work effect on the k-th day does not meet the requirements, and step S7 is executed; otherwise, step S8 is executed;
[0078] S37. Obtain the minimum predicted parameter index:
[0079] If the calculation result is then the central management unit sends information on the need to adjust human resources to the task scheduling unit;
[0080] If the calculation result is then the central management unit sends information on the need to adjust materials to the task scheduling unit;
[0081] If the calculation result is then the central management unit sends information on the need to adjust the engineering project to the task scheduling unit. Adjusting the engineering project adaptable to the environment can avoid the problem that the project stagnates due to deteriorating weather and affects the progress. For example, if construction is carried out in rainy days, the special construction plan for the rainy season is executed;
[0082] If the calculation result is then the central management unit sends information on the need to adjust equipment to the task scheduling unit;
[0083] S38. Calculate the predicted workload G for the k-th day k = δ k × F k , where F k is the target workload for the k-th day, which can be estimated according to the task list;
[0084] The predicted work progress for the k-th day is
[0085] The monitoring data feedback module sends the total amount of work completed on the (k - 1)-th day, the predicted work index δ k for the k-th day, the predicted workload for the k-th day, and the predicted work progress for the k-th day calculated above to the BIM platform to help the project manager manage and adjust the progress.
[0086] This embodiment calculates the total amount of work for the day through video monitoring equipment and a data analysis module, and predicts the workload and work progress for the next day, thereby helping the project manager to manage and adjust the progress.
[0087] The present invention realizes the storage, management and maintenance of the information model of the construction project, as well as the monitoring and task scheduling of real-time data by using the prefabricated building data collaborative management system, improves the data collaborative management efficiency of the construction project, and reduces the time and cost of information transmission and communication. Through the data monitoring unit and the monitoring data feedback module, the monitoring data of the construction site is continuously monitored, and the deviation between the actual situation of the construction progress and the planned progress is analyzed and evaluated, and problems are found in time and corresponding reports are provided to help the project manager to manage and adjust the progress. Through the authority management module and data interaction interface of the BIM platform, participants can collaboratively edit and update the BIM model on a private computer or computer tablet, improve the communication and collaboration efficiency between different participants, and reduce the risk of information transmission and misunderstanding. The file management module and the database management module of the central management unit perform version control and record the modification history of the BIM model, facilitate the tracing and management of the model, ensure the data consistency and reliability of the project, and solve the problem that it is difficult to have targeted collaborative management of prefabricated building data and engineering process management in this neighborhood. The present invention effectively improves the efficiency of collaborative management of building data in this field, and reduces the time and cost of information transmission and communication.
[0088] Although the present invention has been described above with reference to various embodiments, it should be understood that many changes and modifications may be made without departing from the scope of the present invention. That is, the methods, systems and devices discussed above are examples. Various configurations may appropriately omit, replace or add various processes or components. For example, in alternative configurations, the method may be performed in an order different from the order described, and / or various components may be added, omitted and / or combined. Moreover, the features described with respect to certain configurations may be combined in various other configurations, such as different aspects and elements of the configurations may be combined in a similar manner. In addition, the elements therein may be updated as the technology develops, i.e., many elements are examples and do not limit the scope of the present disclosure or claims.
[0089] Specific details are given in the specification to provide a thorough understanding of the exemplary configurations including implementations. However, the configurations can be practiced without these specific details. For example, well-known circuits, processes, algorithms, structures, and techniques have been shown without unnecessary details to avoid obscuring the configurations. This description provides only example configurations and does not limit the scope, applicability, or configurations of the claims. On the contrary, the foregoing description of the configurations will provide those skilled in the art with an enabling description for implementing the described techniques. Various changes may be made to the functions and arrangements of the elements without departing from the spirit or scope of the present disclosure.
[0090] In summary, it is intended that the above detailed description is considered to be illustrative rather than restrictive, and it should be understood that the above embodiments should be understood to be only used to illustrate the present invention and not to limit the scope of protection of the present invention. After reading the contents of the present invention, the technician can make various changes or modifications to the present invention, and these equivalent changes and modifications also fall within the scope defined by the claims of the present invention.
Claims
1. A BIM-based prefabricated building data collaborative management system, characterized in that: The prefabricated building data collaborative management system includes a BIM platform for storing and managing building project information models, a central management unit connected to the BIM platform for managing and maintaining BIM model data, a data monitoring unit connected to the central management unit for acquiring real-time data during the construction process, and a task scheduling unit connected to the central management unit for dispatching tasks to project managers based on assembly information and process flow in the BIM model; The BIM platform includes a visual display that allows users to intuitively view and manage building models and project progress, a rights management module that controls the access rights of different users to BIM models and system functions, and a data interaction interface for participants to collaboratively edit and update BIM models on their personal computers or tablets. Participants include architects, project managers, supervision engineers, and project managers. The central management unit includes: a file management module that stores and manages BIM models and is connected to the BIM platform, a database management module that is connected to the file management module and records updates and modifications to each BIM model version data, a data analysis module that is connected to the database management module and analyzes and processes BIM model data, and a monitoring data feedback module that is connected to the data monitoring unit and the data analysis module and analyzes data obtained by the data monitoring unit; the data analysis module automatically generates a primary task list based on the BIM model.
2. The prefabricated building data collaborative management system according to claim 1, characterized in that: The task scheduling unit includes a task allocator connected to the data analysis module and the BIM platform to allocate tasks to corresponding project managers according to specific task arrangements; a resource allocator connected to the task allocator and the BIM platform to schedule resources according to a final task list; and a task manager connected to the data monitoring unit, the task allocator, and the BIM platform to track task progress.
3. The prefabricated building data collaborative management system according to claim 2, characterized in that: The central management unit serves as a host computer and is responsible for the overall scheduling and management of other units.
4. A method for collaborative management of prefabricated building data based on BIM, applied to the collaborative management system for prefabricated building data as claimed in claim 3, characterized in that: The processing flow of the BIM model by the central management unit includes the following steps: Step S1: The architect uploads the identity information to the authority management module, and after obtaining the authority, sends the BIM model data to the file management module through the data interaction interface; Step S2: the file management module parses the BIM model data to extract geometric information in the model, and sends the geometric information and updated BIM model data to the database management module; Step S3: the database management module BIM model performs version control, records the modification history of the model and the differences between different versions, so as to facilitate traceability and management; Step S4: When the user selects the automatic task assignment option on the BIM platform, the database management module sends the latest version of the BIM model to the data analysis module; Step S5: The data analysis module analyzes and counts the latest version of the BIM model to obtain the engineering task volume. The project manager selects the project manager on the BIM platform to assign tasks based on project requirements and resource availability, and sends the specific task arrangements to the task scheduling unit; Step S6: the task scheduling unit assigns the task to the corresponding project manager according to the specific task arrangement; Step S7: the data monitoring unit continuously monitors the monitoring data of the construction site and sends it to the monitoring data feedback module; Step S8: The monitoring data feedback module analyzes the monitoring data, preliminarily evaluates the deviation between the actual construction progress and the planned progress, and provides corresponding reports and visualization charts, and sends the results to the BIM platform to help the project manager manage and adjust the progress; Step S9: Before the construction machinery and equipment enter the site, the project manager uploads the identity information to the authority management module to obtain the authority, and submits the list of equipment entering the site on the BIM platform. The list of equipment entering the site includes the type, specification, quantity, technical performance, equipment status, and entry time of the equipment entering the site; Step S10: After the construction machinery and equipment enter the site, the supervision engineer checks the working status of the machinery and equipment, uploads the identity information to the authority management module to obtain authority, and completes the security log recording on the BIM platform.
Citation Information
Patent Citations
A distributed BIM collaboration platform
CN109191577B
Charged particle ray treatment device
JP2020096647A
BIM-aware location based application
US20130303193A1
BIM-aware location based application
US9525976B2
Building engineering progress supervision system based on artificial intelligence
CN116681250A
Cited By
Monitoring method for ultraviolet curing repair construction of drainage pipe network
CN118997304A
Fabricated building collaborative design method and system based on BIM
CN119579112A
Engineering collaborative management system based on BIM
CN119809292A
Concrete MiC modular connection analysis system and deformation monitoring method
CN120489054A
A concrete MiC modular connection analysis system and deformation monitoring method
CN120489054B