Automatic execution system and method for process of entering ethylene cracking furnace hearth steam into quench tower
Through the automatic execution system, the status confirmation and intelligent control of the process of cutting the ethylene cracking furnace furnace steam into the quench tower solves the parameter fluctuation problem caused by manual operation, improves the cutting efficiency and safety, and ensures the stability of the system.
Patent Information
- Application Number
- CN202310372670.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2023-04-10
- Publication Date
- 2024-10-15
- Estimated Expiration
- 2043-04-10
AI Technical Summary
During the process of cutting the furnace steam of the ethylene cracking furnace into the quenching tower, due to manual operation, the cutting parameters fluctuate greatly, resulting in low efficiency, poor stability and insufficient safety, which poses great safety risks.
Design an automatic execution system, including a status confirmation module before switching into the quench tower, an intelligent control module and an execution module. By confirming the initial parameters, it controls the key parameters such as the single-tube dilution steam flow rate in the furnace, the negative pressure in the cracking furnace furnace and the fuel gas. calorific value to ensure the stability and safety of the process of cutting into the quench tower.
It improves the efficiency and safety of the quench tower process, avoids parameter fluctuations, ensures stable operation of the system, and reduces safety hazards.
Smart Images

Figure CN118772912A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of petrochemical industry, and in particular to an automatic execution system and method for a process in which furnace steam of an ethylene cracking furnace is cut into a quenching tower. Background Art
[0002] Ethylene is an important basic raw material for petrochemical industry, and is also one of the petrochemical products with the largest demand and production volume. Its output, scale and technical level indicate the development level of a country's petrochemical industry. The tubular cracking furnace is used for hydrocarbon cracking and is the core device for producing ethylene. It determines the production capacity, stable operation and overall energy consumption of the entire ethylene device. When hydrocarbons undergo steam cracking reaction in the radiation section of the tubular cracking furnace, coke will accumulate on the inner wall of the furnace tube due to secondary reactions such as polymerization and condensation in the radiation section, forming coke. When the temperature of the outer wall of the furnace tube in the radiation section or the outlet temperature of the quench boiler reaches the production limit or the pressure difference before and after the venturi tube reaches the production limit due to coking, it will seriously affect the production of ethylene, and cause problems such as a decrease in ethylene yield, increased energy consumption, and shortened furnace tube life, and even affect production safety. Therefore, in the actual production process, furnace coking must be carried out regularly to ensure normal production. After the furnace coking or maintenance is completed, it is usually necessary to cut the furnace steam into the quench tower.
[0003] At present, the cutting process of most ethylene cracking furnaces in China is still controlled manually. Manually cutting the furnace steam of the cracking furnace into the quenching tower requires frequent operation by technical personnel. It is not only labor-intensive, inefficient, and has a high error rate, but also completely relies on personal experience and the responsibility of the operator. It is also difficult to accurately control the key parameters of the cutting-in process, such as the negative pressure in the furnace of the cracking furnace, which can easily cause large fluctuations in the key parameters of the cutting-in, thereby causing system instability and posing a major safety hazard.
[0004] Therefore, there is an urgent need for an automatic execution system and method for the process of cutting the furnace steam of an ethylene cracking furnace into a quenching tower. Summary of the invention
[0005] The present invention aims to solve the problem that in the prior art, the process of cutting in the furnace steam of an ethylene cracking furnace into a quenching tower is operated manually based on experience, which easily leads to large fluctuations in parameters such as the furnace negative pressure of the cracking furnace during the process of cutting in the quenching tower, and there are problems of low cutting efficiency, poor system stability and safety. An automatic execution system and method for the process of cutting in the furnace steam of an ethylene cracking furnace into a quenching tower are provided.
[0006] In order to achieve the above-mentioned object, the present invention provides, in a first aspect, an automatic execution system for the process of cutting in the furnace steam of an ethylene cracking furnace into a quenching tower, the system comprising:
[0007] A state confirmation module before cutting into the quench tower is used to confirm the initial parameters before the cracking furnace steam cuts into the quench tower, and when the initial parameters are within the initial range, it indicates that the quench tower can be cut in, and when the initial parameters are not within the initial range, an alarm is issued;
[0008] The intelligent control module for the process of furnace steam cutting into the quench tower is used to control the key parameters of cutting into the quench tower and issue control instructions, wherein the key parameters of cutting into the quench tower include the flow rate of furnace single tube dilution steam, the negative pressure of the cracking furnace, the calorific value of the fuel gas and the ultra-high pressure steam temperature;
[0009] The furnace steam cutting-in quenching tower execution module is used to cut in the quenching tower according to the control instructions of the furnace steam cutting-in quenching tower process intelligent control module during the quenching tower cutting-in stage.
[0010] Preferably, when the initial parameter is not within the initial range, an alarm is issued, which specifically includes:
[0011] When the initial parameters are not within the initial range, an alarm is issued for one or more initial parameters that are not within the initial range.
[0012] Preferably, the initial parameters include furnace single-tube dilution steam flow, cracking furnace outlet temperature, ultra-high pressure steam temperature, cracking furnace furnace negative pressure, furnace single-tube dimethyl disulfide injection amount, quench tower oil pump outlet pressure, quench tower quench oil level and fuel gas calorific value.
[0013] Preferably, the initial range of the furnace single-tube dilution steam flow rate is 3500-5500 kg / h, the initial range of the cracking furnace outlet temperature is 710-780°C, the initial range of the ultra-high pressure steam temperature is 480-525°C, the initial range of the cracking furnace negative pressure is -45--20 Pa, the initial range of the furnace single-tube dimethyl disulfide injection amount is 1-20 kg / h, the initial range of the oil pump outlet pressure of the quench tower is 1.1-2 MPa, the initial range of the quench oil level of the quench tower is 45-55%, and the initial range of the calorific value of the fuel gas is 11-13 MW.
[0014] Preferably, the cracking furnace includes at least one three-valve shut-off system, which includes a furnace cracking gas valve, a coke cleaning bypass valve and a furnace coke cleaning valve, wherein the furnace cracking gas valve and the coke cleaning bypass valve are linked by a mechanical mechanism, and when the furnace cracking gas valve is opened, the coke cleaning bypass valve is closed, and when the furnace cracking gas valve is closed, the coke cleaning bypass valve is opened.
[0015] Preferably, during the quenching tower stage, key parameters are controlled and control instructions are issued, specifically including:
[0016] Controlling the flow rate of the furnace single-tube dilution steam to remain unchanged based on its initial flow rate, and controlling the temperature of the ultra-high pressure steam to remain unchanged based on its initial temperature;
[0017] In the first stage, the furnace coke clearing valve is controlled to be fully closed at the first coke clearing valve rate. When the furnace coke clearing valve is fully closed, the furnace cracking gas valve is controlled to be fully opened at the first cracking valve rate, so that the furnace steam is cut out of the furnace and enters the quenching tower. When the furnace negative pressure of the cracking furnace drops to the first furnace negative pressure on the basis of its initial negative pressure, the furnace negative pressure of the cracking furnace is controlled to rise to the second furnace negative pressure at the first negative pressure rate on the basis of the first furnace negative pressure, and is maintained for a first set time after rising to the second furnace negative pressure; at the same time, the calorific value of the fuel gas is controlled to drop to the first preset calorific value at the first preset calorific value rate on the basis of its initial calorific value;
[0018] In the second stage, after the cracking furnace negative pressure is maintained for a first set time based on the second furnace negative pressure, the cracking furnace negative pressure is controlled to rise to the initial negative pressure of the cracking furnace negative pressure at a second negative pressure rate based on the second furnace negative pressure.
[0019] Preferably, the first furnace negative pressure is -180 to -130Pa, the second furnace negative pressure is -70 to -40Pa, the first negative pressure rate is 15 to 35Pa / min, the second negative pressure rate is 0.5 to 15Pa / min, the first cracking valve rate is 10 to 40% / min, the first decoking valve rate is 20 to 60% / min, the first preset calorific value rate is 0.2 to 2MW / min, the first preset calorific value is 6 to 10MW, and the first setting time is 1 to 30min.
[0020] Preferably, the cracking furnace comprises at least one furnace.
[0021] Preferably, the system further comprises an operation navigation function module for providing operation prompts at the stage of cutting into the quenching tower according to the control instructions of the intelligent control module for the process of cutting into the quenching tower of the furnace steam.
[0022] Preferably, before the first stage, the operation navigation function module prompts to turn the high-high interlock of the cracking furnace negative pressure to bypass;
[0023] After the second stage, the operation navigation function module prompts to adjust the raw material blind plate and the quench oil blind plate to a perforated plate, open the oil cooler quench oil regulating valve, and check the cracking furnace status.
[0024] Preferably, the system also includes a process key parameter monitoring and alarm module, which is used to monitor the process key parameters when entering the quench tower stage, and to alarm when the process key parameters exceed a preset range.
[0025] Preferably, the key process parameters include cracking furnace outlet temperature, furnace single tube dilution steam flow, fuel gas calorific value, fuel gas pressure, cracking furnace furnace pressure, Venturi rear pressure, VHS drum liquid level, ultra-high pressure steam temperature, ultra-high pressure steam pressure and cracking furnace cross section temperature.
[0026] Preferably, the monitoring of the key process parameters and the alarming when the key process parameters exceed a preset range specifically include:
[0027] When one or more of the key process parameters exceeds a first preset range, an alarm is issued;
[0028] When one or more of the process key parameters exceed the second preset range, the process key parameters exceeding the second preset range are adjusted to within the first preset range according to a preset ratio based on their current values, and an alarm is issued.
[0029] Preferably, the upper limit value of the second preset range is greater than the upper limit value of the first preset range, the lower limit value of the second preset range is less than the lower limit value of the first preset range, and the preset ratio is ±0.1% to 10%.
[0030] Preferably, the system also includes a process alarm optimization management module, which is used to automatically shield the cracking furnace operation instrument alarm after entering the quench tower stage, and make the cracking furnace operation instrument alarm activation prompt light turn red; after the quench tower stage is completed, the cracking furnace operation instrument alarm is automatically enabled, and the cracking furnace operation instrument alarm activation prompt light turns green.
[0031] Preferably, the types of cracking furnace operation instrument alarms include high oxygen content alarm of cross-section flue gas, bottom fuel heat load ratio alarm, side wall fuel heat load ratio alarm, cracking furnace liquid phase feed flow alarm, cracking furnace gas phase feed flow alarm, quench oil flow alarm, total feed amount alarm, furnace tube gas raw material flow alarm, furnace tube liquid raw material flow alarm, gas raw material pressure alarm, liquid raw material pressure alarm, quencher outlet temperature alarm, inlet burnt gas temperature adjustment alarm, cracking gas temperature alarm and Venturi pressure difference alarm.
[0032] Preferably, the system also includes a deep learning function module for learning the control advantages and disadvantages of each key entry parameter in the quenching tower stage based on experience values and big data, and deriving the optimal control values of the key entry parameters in the quenching tower stage.
[0033] In order to achieve the above-mentioned object, the second aspect of the present invention provides a method for automatically executing the process of cutting in the furnace steam of an ethylene cracking furnace into a quenching tower. The method is implemented using the system, and the method comprises:
[0034] A state confirmation module before cutting into the quench tower is used to confirm the initial parameters before the cracking furnace steam cuts into the quench tower, and when the initial parameters are within the initial range, it indicates that the quench tower can be cut in, and when the initial parameters are not within the initial range, an alarm is issued;
[0035] An intelligent control module for the process of furnace steam cutting into the quench tower is used to control key cutting parameters and issue control instructions during the cutting into the quench tower stage, wherein the key cutting parameters include furnace single tube dilution steam flow, cracking furnace negative pressure, fuel gas calorific value and ultra-high pressure steam temperature;
[0036] A furnace steam cutting-in quenching tower execution module is adopted. During the cutting-in quenching tower stage, the quenching tower is cut in according to the control instruction of the furnace steam cutting-in quenching tower process intelligent control module.
[0037] According to the above technical scheme, based on the system, in the actual application process, by confirming the state before cutting into the quenching tower, and then controlling the key parameters of cutting in during the cutting-in stage of the quenching tower through the intelligent control module of the furnace steam cutting-in quenching tower process, and executing the corresponding operations according to the control instructions through the furnace steam cutting-in quenching tower execution module, the stability of the system in the process of furnace steam cutting into the quenching tower can be effectively improved, and it has the advantages of high cutting-in efficiency and high safety. BRIEF DESCRIPTION OF THE DRAWINGS
[0038] Figure 1 It is a flow chart of the automatic execution system of the process of cutting the furnace steam of the ethylene cracking furnace into the quenching tower. DETAILED DESCRIPTION
[0039] The specific implementation of the embodiment of the present invention is described in detail below in conjunction with the accompanying drawings. It should be understood that the specific implementation described here is only used to illustrate and explain the embodiment of the present invention, and is not used to limit the embodiment of the present invention.
[0040] The first aspect of the present invention provides an automatic execution system for the process of cutting steam from the furnace of an ethylene cracking furnace into a quench tower, such as Figure 1 As shown, the automatic execution system of the process of cutting the furnace steam of the ethylene cracking furnace into the quenching tower includes:
[0041] A state confirmation module before cutting into the quench tower is used to confirm the initial parameters before the cracking furnace steam cuts into the quench tower, and when the initial parameters are within the initial range, it indicates that the quench tower can be cut in, and when the initial parameters are not within the initial range, an alarm is issued;
[0042] The intelligent control module for the process of furnace steam cutting into the quench tower is used to control the key parameters of cutting into the quench tower and issue control instructions, wherein the key parameters of cutting into the quench tower include the flow rate of furnace single tube dilution steam, the negative pressure of the cracking furnace, the calorific value of the fuel gas and the ultra-high pressure steam temperature;
[0043] The furnace steam cutting-in quenching tower execution module is used to cut in the quenching tower according to the control instructions of the furnace steam cutting-in quenching tower process intelligent control module during the quenching tower cutting-in stage.
[0044] In the present invention, the furnace steam cutting-in quenching tower execution module is used to cut in during the cutting-in quenching tower stage according to the control instructions of the furnace steam cutting-in quenching tower process intelligent control module. Specifically, it controls various key cutting-in parameters to reach set values during the cutting-in quenching tower stage according to the control instructions, thereby realizing the cutting-in of the quenching tower.
[0045] According to the above technical scheme, based on the system, in the actual application process, by confirming the state before cutting into the quenching tower, and then controlling the key parameters of cutting in during the cutting-in stage of the quenching tower through the intelligent control module of the furnace steam cutting-in quenching tower process, and executing the corresponding operations according to the control instructions through the furnace steam cutting-in quenching tower execution module, the stability of the system in the process of furnace steam cutting into the quenching tower can be effectively improved, and it has the advantages of high cutting-in efficiency and high safety.
[0046] The automatic execution system of the process of cutting in the quench tower of the ethylene cracking furnace steam of the present invention, in a preferred embodiment, when the initial parameter is not within the initial range, an alarm is issued, specifically comprising:
[0047] When the initial parameters are not within the initial range, an alarm is issued for one or more initial parameters that are not within the initial range.
[0048] In a specific embodiment, the initial parameters include the furnace single-tube dilution steam flow rate, the cracking furnace outlet temperature, the ultra-high pressure steam temperature, the cracking furnace furnace negative pressure, the furnace single-tube dimethyl disulfide injection amount, the quenching tower oil pump outlet pressure, the quenching tower quenching oil level and the fuel gas calorific value.
[0049] In a more specific embodiment, the initial range of the furnace single-tube dilution steam flow rate is 3500-5500 kg / h, preferably the initial range is 3800-4500 kg / h, the initial range of the cracking furnace outlet temperature is 710-780°C, preferably the initial range is 715-750°C, the initial range of the ultra-high pressure steam temperature is 480-525°C, preferably the initial range is 505-520°C, the initial range of the cracking furnace negative pressure is -45--20Pa, preferably the initial range is -35--25Pa, the initial range of the furnace single-tube dimethyl disulfide injection amount is 1-20kg / h, preferably the initial range is 3-6kg / h, the initial range of the oil pump outlet pressure of the quench tower is 1.1-2MPa, the initial range of the quench oil level of the quench tower is 45-55%, and the initial range of the calorific value of the fuel gas is 11-13MW. This ensures that all preparations are ready before the cracking furnace steam enters the quench tower, especially that the key initial parameters are within the initial range, thereby ensuring the accuracy and stability of the process of entering the quench tower.
[0050] The automatic execution system of the process of cutting in the furnace steam of the ethylene cracking furnace into the quenching tower of the present invention, in a specific embodiment, the cracking furnace includes at least one set of three-valve cut-off system, the three-valve cut-off system includes a furnace cracking gas valve, a coke cleaning bypass valve and a furnace coke cleaning valve, wherein the furnace cracking gas valve and the coke cleaning bypass valve are linked by a mechanical mechanism, when the furnace cracking gas valve is opened, the coke cleaning bypass valve is closed, and when the furnace cracking gas valve is closed, the coke cleaning bypass valve is opened.
[0051] In a more specific embodiment, during the quenching tower stage, the key parameters are controlled and control instructions are issued, specifically including:
[0052] Controlling the flow rate of the furnace single-tube dilution steam to remain unchanged based on its initial flow rate, and controlling the temperature of the ultra-high pressure steam to remain unchanged based on its initial temperature;
[0053] In the first stage, the furnace coke clearing valve is controlled to be fully closed at the first coke clearing valve rate. When the furnace coke clearing valve is fully closed, the furnace cracking gas valve is controlled to be fully opened at the first cracking valve rate, so that the furnace steam is cut out of the furnace and enters the quenching tower. When the furnace negative pressure of the cracking furnace drops to the first furnace negative pressure on the basis of its initial negative pressure, the furnace negative pressure of the cracking furnace is controlled to rise to the second furnace negative pressure at the first negative pressure rate on the basis of the first furnace negative pressure, and is maintained for a first set time after rising to the second furnace negative pressure; at the same time, the calorific value of the fuel gas is controlled to drop to the first preset calorific value at the first preset calorific value rate on the basis of its initial calorific value;
[0054] In the second stage, after the cracking furnace negative pressure is maintained for a first set time based on the second furnace negative pressure, the cracking furnace negative pressure is controlled to rise to the initial negative pressure of the cracking furnace negative pressure at a second negative pressure rate based on the second furnace negative pressure.
[0055] Further in a more specific embodiment, the first furnace negative pressure is -180 to -130Pa, preferably -140 to -160Pa, the second furnace negative pressure is -70 to -40Pa, preferably -45 to -60Pa, the first negative pressure rate is 15 to 35Pa / min, preferably 20 to 30Pa / min, the second negative pressure rate is 0.5 to 15Pa / min, preferably 1 to 8Pa / min, the first cracking valve rate is 10 to 40% / min, preferably 20 to 30% / min, the first decoking valve rate is 20 to 60% / min, preferably 35 to 45% / min, the first preset calorific value rate is 0.2 to 2MW / min, preferably 0.8 to 1.2MW / min, the first preset calorific value is 6 to 10MW, and the first setting time is 1 to 30min.
[0056] In an embodiment of the present invention, by controlling the furnace single-tube dilution steam flow rate, the cracking furnace furnace negative pressure, the fuel gas calorific value and the ultra-high pressure steam temperature, and making them change linearly during the entire quenching tower stage, the problem of manual cutting into the quenching tower based on experience, resulting in large fluctuations in parameters such as the cracking furnace negative pressure, which in turn leads to unplanned shutdown of the ethylene unit, is effectively solved. At the same time, compared with manual cutting into the quenching tower based on experience, the efficiency of cutting into the quenching tower and the safety of the system during the cutting into the quenching tower are greatly improved.
[0057] In a preferred embodiment of the automatic execution system of the process of cutting in the furnace steam of the ethylene cracking furnace into the quenching tower of the present invention, the cracking furnace comprises at least one furnace.
[0058] In an embodiment of the present invention, when the cracking furnace is not a single furnace, specifically, for example, when the cracking furnace has two furnaces, refer to the first stage and perform the same operation on the other furnace. Further, for example, when the cracking furnace has more than two furnaces, perform the same operation on the other furnaces until all the furnaces have been operated and then perform the second stage.
[0059] The automatic execution system of the process of cutting in the furnace steam of the ethylene cracking furnace into the quenching tower of the present invention, in a preferred embodiment, the system also includes an operation navigation function module, which is used to provide operation prompts at the stage of cutting in the quenching tower according to the control instructions of the intelligent control module of the process of cutting in the furnace steam into the quenching tower.
[0060] In a specific embodiment, before the first stage, the operation navigation function module prompts to turn the cracking furnace negative pressure high-high interlock to bypass;
[0061] After the second stage, the operation navigation function module prompts to adjust the raw material blind plate and the quench oil blind plate to a perforated plate, open the oil cooler quench oil regulating valve, and check the cracking furnace status.
[0062] In the embodiment of the present invention, the operation navigation function module further provides operation prompts according to the control instructions of the intelligent control module for the process of cutting into the quenching tower during the cracking furnace cutting into the quenching tower, which can further effectively improve the system safety and cutting efficiency during the cutting process. More specifically, a cracking furnace status inspection module can be further provided to inspect the status of the cracking furnace after the cutting is completed, thereby ensuring safety.
[0063] The automatic execution system of the ethylene cracking furnace furnace steam cutting into the quenching tower process of the present invention, in a preferred embodiment, the system also includes a process key parameter monitoring and alarm module, which is used to monitor the process key parameters during the cutting into the quenching tower stage and to alarm when the process key parameters exceed a preset range.
[0064] In a specific embodiment, the key process parameters include cracking furnace outlet temperature, furnace single tube dilution steam flow, fuel gas calorific value, fuel gas pressure, cracking furnace furnace pressure, Venturi tube back pressure, VHS drum liquid level, ultra-high pressure steam temperature, ultra-high pressure steam pressure and cracking furnace cross section temperature.
[0065] In another specific implementation, the monitoring of the key process parameters and the alarming when the key process parameters exceed a preset range specifically include:
[0066] When one or more of the key process parameters exceeds a first preset range, an alarm is issued;
[0067] When one or more of the process key parameters exceed the second preset range, the process key parameters exceeding the second preset range are adjusted to within the first preset range according to the preset ratio based on their current values, and an alarm is issued. The upper limit value of the second preset range is greater than the upper limit value of the first preset range, the lower limit value of the second preset range is less than the lower limit value of the first preset range, and the preset ratio is ±0.1% to 10%.
[0068] In an embodiment of the present invention, taking the ultra-high pressure steam temperature in the process key parameter as an example, the first preset range is 480-525°C, and the second preset range is 470-530°C. When the process key parameter monitoring and alarm module detects that the ultra-high pressure steam temperature is 475°C, an alarm is issued; when the process key parameter monitoring and alarm module further detects that the ultra-high pressure steam temperature is 460°C, the ultra-high pressure steam temperature is expanded to within the first preset range at a ratio of 0.1% to 10% on the basis of 460°C, and an alarm is issued, thereby improving the safety of the system during the entire cut-in process.
[0069] Furthermore, the process key parameter monitoring and alarm module can set the alarm display status according to the priority, and the alarm sound and light signals should be easy to distinguish. For example, when the ultra-high pressure steam temperature exceeds the first preset range, a first-level alarm is used, and when the ultra-high pressure steam temperature exceeds the second preset range, a second-level alarm is performed. Specifically, the first-level alarm uses black text on a yellow background, flashing, and low-frequency sound, and the second-level alarm uses black text on an orange background, flashing, and medium-frequency sound. The boundary values of the first preset range and the second preset range should not overlap with the instrument range of the alarm device of the process key parameter monitoring and alarm module, and should be set within 10% to 90% of the maximum range of the instrument.
[0070] The automatic execution system of the ethylene cracking furnace furnace steam cutting into the quench tower process of the present invention, in a preferred embodiment, the system also includes a process alarm optimization management module, which is used to automatically shield the cracking furnace operation instrument alarm after entering the quench tower stage, and make the cracking furnace operation instrument alarm activation prompt light turn red; after the quench tower stage is completed, the cracking furnace operation instrument alarm is automatically enabled, and the cracking furnace operation instrument alarm activation prompt light turns green.
[0071] In a specific embodiment, the types of cracking furnace operation instrument alarms include high oxygen content alarm of cross-section flue gas, bottom fuel heat load ratio alarm, side wall fuel heat load ratio alarm, cracking furnace liquid phase feed flow alarm, cracking furnace gas phase feed flow alarm, quench oil flow alarm, total feed amount alarm, furnace tube gas raw material flow alarm, furnace tube liquid raw material flow alarm, gas raw material pressure alarm, liquid raw material pressure alarm, quench cooler outlet temperature alarm, inlet burnt gas temperature adjustment alarm, cracking gas temperature alarm and Venturi pressure difference alarm.
[0072] In an embodiment of the present invention, through the cut-in process alarm optimization management module, it is convenient for operators to know whether the alarm is enabled normally during actual use, avoiding interference from invalid alarms and affecting the efficiency of the cracking furnace steam cut-in quenching tower process.
[0073] In a preferred embodiment, the automatic execution system of the ethylene cracking furnace steam cutting-in quenching tower process of the present invention further includes a deep learning function module for learning the control advantages and disadvantages of each of the key cutting-in parameters in the cutting-in quenching tower stage based on experience and big data, and deriving the optimal control values of the key cutting-in parameters in the cutting-in quenching tower stage, thereby ensuring the stability of the cutting-in process and improving the efficiency to the greatest extent.
[0074] The second aspect of the present invention provides a method for automatically executing the process of cutting in the furnace steam of an ethylene cracking furnace into a quenching tower. The method is implemented using the system, and the method comprises:
[0075] A state confirmation module before cutting into the quench tower is used to confirm the initial parameters before the cracking furnace steam cuts into the quench tower, and when the initial parameters are within the initial range, it indicates that the quench tower can be cut in, and when the initial parameters are not within the initial range, an alarm is issued;
[0076] An intelligent control module for the process of furnace steam cutting into the quench tower is used to control key cutting parameters and issue control instructions during the cutting into the quench tower stage, wherein the key cutting parameters include furnace single tube dilution steam flow, cracking furnace negative pressure, fuel gas calorific value and ultra-high pressure steam temperature;
[0077] A furnace steam cutting-in quenching tower execution module is adopted. During the cutting-in quenching tower stage, the quenching tower is cut in according to the control instruction of the furnace steam cutting-in quenching tower process intelligent control module.
[0078] In the present invention, by confirming the state before cutting into the quench tower, the key parameters of the cutting-in are controlled by the intelligent control module of the furnace steam cutting-in quench tower process at the stage of cutting into the quench tower, and the furnace steam cutting-in quench tower execution module performs corresponding operations according to the control instructions, which can effectively improve the stability of the system during the process of furnace steam cutting into the quench tower, and has the advantages of high cutting efficiency and high safety.
[0079] The automatic execution system of the process of cutting the furnace steam of the ethylene cracking furnace into the quenching tower of the present invention, in a specific embodiment, the system is composed of a human-computer interaction interface and a program control system, so that online control is realized through a combination of DCS configuration based on the field distributed control system and upper computer server programming. At the same time, in order to realize the automatic execution of the process of cutting the furnace steam of the ethylene cracking furnace into the quenching tower, it is necessary to deploy an independent server in the industrial control network, and the execution program of the process of cutting the furnace steam of the ethylene cracking furnace into the quenching tower performs data exchange through the OPC DA interface of the OPC server of Emerson DCS to obtain the value or status of the relevant parameters. In order to ensure the safe operation of the DCS system, an industrial-grade firewall is added between the system server and the communication interface. By configuring the corresponding rule strategy, deep isolation protection of the DCS control system is realized, the virus transmission path is cut off, and the normal, safe and stable operation of the DCS production control system of the device is ensured. The industrial firewall has built-in private communication protocols of various mainstream automation product manufacturers, which can achieve non-disturbance access to mainstream automation products such as Honeywell DCS, Yokogawa DCS, Emerson DCS and other systems, as well as servers or databases such as OPC SERVER, IP21 / PHD / PI.
[0080] Among them, the interface design of the human-computer interaction interface includes function buttons such as parameter "setting", cracking furnace status "confirmation", program "run", run "pause", run "continue", run "stop", parameter "alarm" to realize the human-computer interaction function. Specifically, during use, click the "parameter setting" button to view the default values of each control parameter of the process, and manually set the program key parameter control threshold and the upper and lower limit preset values of the key parameters according to actual production needs; click the "cracking furnace status confirmation" button to complete the status confirmation work before the furnace steam cuts into the quenching tower, and the interface jumps to the furnace steam cut-in quenching tower operation interface, otherwise the furnace steam will be turned off. The program for cutting into the quench tower cannot run; click the "Run Program" button, and the furnace steam cutting into the quench tower program starts running; click "Pause", the system stops the next step of the program, and the control values of the parameters of the furnace steam cutting into the quench tower program remain at the current values. Click "Continue", and the program will continue according to the current execution steps; click "Stop" manually, the system stops the automatic furnace steam cutting into the quench tower program of the cracking furnace and switches to manual operation; click "Alarm Button", the human-computer interaction interface switches to the alarm interface, you can view the system alarm status in detail, and you can choose whether to enable the alarm shielding function during the furnace steam cutting into the quench tower process as needed.
[0081] Furthermore, the functions of the human-machine interface also include system operation status display, system operation buttons, key parameter trend charts and system alarm prompt information. Among them, the human-machine interface is designed with function buttons such as "Run", "Stop", "Pause", "Continue", and "Parameter Setting". During the system operation, the user can execute the above function buttons at any time according to the actual operation of the ethylene unit and the compressor.
[0082] The present invention will be described in detail below through examples, but the protection scope of the present invention is not limited thereto.
[0083] Example 1
[0084] Based on an ethylene cracking furnace with a production capacity of 140,000 tons / year, the present invention is used as follows Figure 1 The automatic execution system of the process of cutting the furnace steam of the ethylene cracking furnace into the quenching tower is implemented as shown. Specifically, the system includes:
[0085] A state confirmation module before cutting into the quench tower is used to confirm the initial parameters before the cracking furnace steam cuts into the quench tower, and when the initial parameters are within the initial range, it indicates that the quench tower can be cut in, and when the initial parameters are not within the initial range, an alarm is issued;
[0086] The intelligent control module for the process of furnace steam cutting into the quench tower is used to control the key parameters of cutting into the quench tower and issue control instructions, wherein the key parameters of cutting into the quench tower include the flow rate of furnace single tube dilution steam, the negative pressure of the cracking furnace, the calorific value of the fuel gas and the ultra-high pressure steam temperature;
[0087] The furnace steam cutting-in quenching tower execution module is used to cut in the quenching tower according to the control instructions of the furnace steam cutting-in quenching tower process intelligent control module during the quenching tower cutting-in stage.
[0088] Specifically, when the initial parameter is not within the initial range, an alarm is issued, which specifically includes:
[0089] When the initial parameters are not within the initial range, an alarm is issued for one or more of the initial parameters that are not within the initial range; the initial parameters include furnace single-tube dilution steam flow, cracking furnace outlet temperature, ultra-high pressure steam temperature, cracking furnace furnace negative pressure, furnace single-tube dimethyl disulfide injection amount, quenching tower oil pump outlet pressure, quenching oil liquid level of quenching tower and fuel gas calorific value; the furnace single-tube dilution steam flow is 4500kg / h, the cracking furnace outlet temperature is 720°C, the ultra-high pressure steam temperature is 510°C, the cracking furnace negative pressure is -30Pa, the furnace single-tube dimethyl disulfide injection amount is 5kg / h, the quenching tower oil pump outlet pressure is 1.3MPa, the quenching oil liquid level of the quenching tower is 50%, and the fuel gas calorific value is 12MW.
[0090] The cracking furnace comprises at least one three-valve cut-off system, which comprises a furnace cracking gas valve, a coke-cleaning bypass valve and a furnace coke-cleaning valve, wherein the furnace cracking gas valve and the coke-cleaning bypass valve are linked by a mechanical mechanism, and when the furnace cracking gas valve is opened, the coke-cleaning bypass valve is closed, and when the furnace cracking gas valve is closed, the coke-cleaning bypass valve is opened;
[0091] In the stage of cutting into the quench tower, the key parameters of cutting into are controlled and control instructions are issued, which specifically include:
[0092] Controlling the flow rate of the furnace single-tube dilution steam to remain unchanged based on its initial flow rate, and controlling the temperature of the ultra-high pressure steam to remain unchanged based on its initial temperature;
[0093] In the first stage, the furnace coke clearing valve is controlled to be fully closed at the first coke clearing valve rate. When the furnace coke clearing valve is fully closed, the furnace cracking gas valve is controlled to be fully opened at the first cracking valve rate, so that the furnace steam is cut out of the furnace and enters the quenching tower. When the furnace negative pressure of the cracking furnace drops to the first furnace negative pressure on the basis of its initial negative pressure, the furnace negative pressure of the cracking furnace is controlled to rise to the second furnace negative pressure at the first negative pressure rate on the basis of the first furnace negative pressure, and is maintained for a first set time after rising to the second furnace negative pressure; at the same time, the calorific value of the fuel gas is controlled to drop to the first preset calorific value at the first preset calorific value rate on the basis of its initial calorific value;
[0094] In the second stage, after the negative pressure in the furnace of the cracking furnace is maintained for a first set time on the basis of the second negative pressure in the furnace, the negative pressure in the furnace of the cracking furnace is controlled to increase to the initial negative pressure of the negative pressure in the furnace of the cracking furnace at a second negative pressure rate on the basis of the second negative pressure in the furnace;
[0095] The first furnace negative pressure is -150Pa, the second furnace negative pressure is -50Pa, the first negative pressure rate is 25Pa / min, the second negative pressure rate is 4Pa / min, the first cracking valve rate is 25% / min, the first decoking valve rate is 40% / min, the first preset calorific value rate is 0.5MW / min, the first preset calorific value is 8MW, and the first setting time is 5min.
[0096] In the actual application process, before cutting into the quench tower, the state confirmation module before cutting into the quench tower confirms the initial parameters. When the initial parameters are within the initial range, it indicates that the quench tower can be cut in. Then the intelligent control module of the furnace steam cutting into the quench tower process controls the furnace single-tube dilution steam flow rate to remain unchanged on the basis of 4500kg / h, and the ultra-high pressure steam temperature to remain unchanged on the basis of 510℃. In the first stage, the furnace coke cleaning valve is controlled to be fully closed at a rate of 40% / min. When the furnace coke cleaning valve is completely closed, the furnace cracking gas valve is controlled to be fully opened at a rate of 25% / min, so that the furnace steam (dilution steam) is cut out of the furnace and enters the quench tower. When the negative pressure in the cracking furnace is based on its initial negative pressure of -30Pa, After dropping to the first furnace negative pressure of -150Pa, the negative pressure in the cracking furnace is controlled to rise to the second furnace negative pressure of -50Pa at a rate of 25Pa / min on the basis of the first furnace negative pressure of -150Pa, and is maintained for 5min after rising to -50Pa; at the same time, during this period, the calorific value of the fuel gas is controlled to drop to the first preset calorific value of 8MW at a rate of 0.5MW / min on the basis of the initial calorific value of 12MW; in the second stage, after the negative pressure in the cracking furnace is maintained for 5min on the basis of the second furnace negative pressure of -50Pa, the negative pressure in the cracking furnace is controlled to rise to the initial negative pressure of -30Pa of the cracking furnace at a rate of 4Pa / min on the basis of the second furnace negative pressure of -50Pa, and the rapid cooling is completed.
[0097] After testing, it is found that the automatic execution system of the process of furnace steam of the ethylene cracking furnace entering the quench tower of the present invention is used. In actual application, the state before cutting into the quench tower is confirmed by the state confirmation module before cutting into the quench tower, which can be used to ensure that the furnace steam of the cracking furnace can normally cut into the quench tower and ensure the accuracy of subsequent cutting. The key cutting parameters are controlled by the intelligent control module of the process of furnace steam cutting into the quench tower, which can avoid drastic fluctuations of the key cutting parameters during the cutting process, causing system instability. The system has the advantages of high cutting efficiency, small fluctuations of key cutting parameters, high stability and high safety.
[0098] Example 2
[0099] Refer to Example 1, except that the cracking furnace includes at least two furnaces.
[0100] After testing, it is found that the automatic execution system of the process of furnace steam of the ethylene cracking furnace entering the quench tower of the present invention is used. In actual application, the state before cutting into the quench tower is confirmed by the state confirmation module before cutting into the quench tower, which can be used to ensure that the furnace steam of the cracking furnace can normally cut into the quench tower and ensure the accuracy of subsequent cutting. The key cutting parameters are controlled by the intelligent control module of the process of furnace steam cutting into the quench tower, which can avoid drastic fluctuations of the key cutting parameters during the cutting process, causing system instability. The system has the advantages of high cutting efficiency, small fluctuations of key cutting parameters, high stability and high safety.
[0101] Example 3
[0102] Refer to Example 2 for implementation, except that the first cracking valve rate is 20% / min, the first decoking valve rate is 35% / min, the first preset calorific value rate is 0.4MW / min, and the first preset calorific value is 7MW.
[0103] After testing, it is found that the automatic execution system of the process of furnace steam of the ethylene cracking furnace entering the quench tower of the present invention is used. In actual application, the state before cutting into the quench tower is confirmed by the state confirmation module before cutting into the quench tower, which can be used to ensure that the furnace steam of the cracking furnace can normally cut into the quench tower and ensure the accuracy of subsequent cutting. The key cutting parameters are controlled by the intelligent control module of the process of furnace steam cutting into the quench tower, which can avoid drastic fluctuations of the key cutting parameters during the cutting process, causing system instability. The system has the advantages of high cutting efficiency, small fluctuations of key cutting parameters, high stability and high safety.
[0104] Example 4
[0105] Refer to Example 2 for implementation, except that the first cracking valve rate is 20% / min, the first decoking valve rate is 45% / min, the first preset calorific value rate is 0.6MW / min, and the first preset calorific value is 6MW.
[0106] After testing, it is found that the automatic execution system of the process of furnace steam of the ethylene cracking furnace entering the quench tower of the present invention is used. In actual application, the state before cutting into the quench tower is confirmed by the state confirmation module before cutting into the quench tower, which can be used to ensure that the furnace steam of the cracking furnace can normally cut into the quench tower and ensure the accuracy of subsequent cutting. The key cutting parameters are controlled by the intelligent control module of the process of furnace steam cutting into the quench tower, which can avoid drastic fluctuations of the key cutting parameters during the cutting process, causing system instability. The system has the advantages of high cutting efficiency, small fluctuations of key cutting parameters, high stability and high safety.
[0107] Example 5
[0108] Refer to Example 2 for implementation, except that the first cracking valve rate is 30% / min, the first decoking valve rate is 45% / min, the first preset calorific value rate is 0.6MW / min, and the first preset calorific value is 7MW.
[0109] After testing, it is found that the automatic execution system of the process of furnace steam of the ethylene cracking furnace entering the quench tower of the present invention is used. In actual application, the state before cutting into the quench tower is confirmed by the state confirmation module before cutting into the quench tower, which can be used to ensure that the furnace steam of the cracking furnace can normally cut into the quench tower and ensure the accuracy of subsequent cutting. The key cutting parameters are controlled by the intelligent control module of the process of furnace steam cutting into the quench tower, which can avoid drastic fluctuations of the key cutting parameters during the cutting process, causing system instability. The system has the advantages of high cutting efficiency, small fluctuations of key cutting parameters, high stability and high safety.
[0110] Example 6
[0111] The implementation is carried out with reference to Example 2, except that the system further includes an operation navigation function module for providing operation prompts at the stage of cutting into the quenching tower according to the control instructions of the intelligent control module of the process of cutting into the quenching tower by the furnace steam; before the first stage, the operation navigation function module prompts to turn the high-high interlock of the negative pressure in the cracking furnace to bypass;
[0112] After the second stage, the operation navigation function module prompts to adjust the raw material blind plate and the quench oil blind plate to a perforated plate, open the oil cooler quench oil regulating valve, and check the cracking furnace status.
[0113] According to tests, the cutting efficiency and the safety during the cutting process can be further improved compared with Example 2.
[0114] Example 7
[0115] The implementation is carried out with reference to Example 6, except that the system further includes a process key parameter monitoring and alarm module, which is used to monitor the process key parameters when entering the quench tower stage, and to alarm when the process key parameters exceed the preset range; the process key parameters include the cracking furnace outlet temperature, the furnace single tube dilution steam flow rate, the fuel gas calorific value, the fuel gas pressure, the cracking furnace pressure, the Venturi tube rear pressure, the VHS drum liquid level, the ultra-high pressure steam temperature, the ultra-high pressure steam pressure and the cracking furnace cross section temperature.
[0116] According to testing, the safety during the cutting process can be further improved compared with Example 6.
[0117] Example 8
[0118] The method is implemented with reference to Example 7, except that the key process parameters are monitored, and an alarm is issued when the key process parameters exceed a preset range, specifically including:
[0119] When one or more of the key process parameters exceeds a first preset range, an alarm is issued;
[0120] When one or more of the key process parameters exceed the second preset range, the key process parameters exceeding the second preset range will be adjusted to within the first preset range according to a preset ratio based on their current values, and an alarm will be issued; the upper limit value of the second preset range is greater than the upper limit value of the first preset range, and the lower limit value of the second preset range is less than the lower limit value of the first preset range, and the preset ratio is ±0.1% to 10%.
[0121] According to testing, the safety during the cutting process can be further improved compared with Example 7.
[0122] Example 9
[0123] The implementation is carried out with reference to Example 8, which is different from the implementation in that the system also includes a process alarm optimization management module, which is used to automatically shield the cracking furnace operation instrument alarm after entering the quench tower stage, and make the cracking furnace operation instrument alarm activation prompt light turn red; after the quench tower stage is completed, the cracking furnace operation instrument alarm is automatically enabled, and the cracking furnace operation instrument alarm activation prompt light turns green; the types of cracking furnace operation instrument alarms include high oxygen content alarms in the cross-section flue gas, bottom fuel heat load ratio alarms, side wall fuel heat load ratio alarms, cracking furnace liquid phase feed flow alarms, cracking furnace gas phase feed flow alarms, quench oil flow alarms, total feed amount alarms, furnace tube gas raw material flow alarms, furnace tube liquid raw material flow alarms, gas raw material pressure alarms, liquid raw material pressure alarms, quench cooler outlet temperature alarms, inlet burnt gas temperature adjustment alarms, cracking gas temperature alarms and Venturi pressure difference alarms.
[0124] According to the test, the cutting efficiency can be further improved compared with the embodiment 8.
[0125] Example 10
[0126] The system is implemented with reference to Example 9, but differs therefrom in that the system also includes a deep learning function module for learning the control advantages and disadvantages of each key entry parameter in the quenching tower stage based on experience and big data, and deriving the optimal control values of the key entry parameters in the quenching tower stage.
[0127] According to testing, the cutting efficiency, stability and safety during the cutting process can be further improved compared with Example 9.
[0128] The automatic execution system and method of the process of furnace steam cutting into a quenching tower of an ethylene cracking furnace provided by the present invention can effectively improve the stability of the system in the process of furnace steam cutting into a quenching tower by confirming the state before cutting into the quenching tower, and then controlling the key cutting parameters in the stage of cutting into the quenching tower through an intelligent control module of the process of furnace steam cutting into the quenching tower, and performing corresponding operations according to control instructions through an execution module of furnace steam cutting into the quenching tower, thereby having the advantages of high cutting efficiency and high safety.
[0129] The preferred embodiments of the present invention are described in detail above with reference to the accompanying drawings, but the present invention is not limited thereto. Within the technical concept of the present invention, the technical solution of the present invention can be subjected to a variety of simple modifications. In order to avoid unnecessary repetition, the present invention will not further describe various possible combinations. However, these simple modifications and combinations should also be regarded as the contents disclosed by the present invention and belong to the protection scope of the present invention.
Claims
1. An automatic execution system for the process of cutting the furnace steam of an ethylene cracking furnace into a quench tower, It is characterized in that The system includes: A state confirmation module before cutting into the quench tower is used to confirm the initial parameters before the cracking furnace steam cuts into the quench tower, and when the initial parameters are within the initial range, it indicates that the quench tower can be cut in, and when the initial parameters are not within the initial range, an alarm is issued; The intelligent control module for the process of furnace steam cutting into the quench tower is used to control the key parameters of cutting into the quench tower and issue control instructions, wherein the key parameters of cutting into the quench tower include the flow rate of furnace single tube dilution steam, the negative pressure of the cracking furnace, the calorific value of the fuel gas and the ultra-high pressure steam temperature; The furnace steam cutting-in quenching tower execution module is used to cut in the quenching tower according to the control instructions of the furnace steam cutting-in quenching tower process intelligent control module during the quenching tower cutting-in stage.
2. The system according to claim 1, It is characterized in that When the initial parameter is not within the initial range, an alarm is issued, specifically including: When the initial parameters are not within the initial range, an alarm is issued for one or more initial parameters that are not within the initial range.
3. The system according to claim 1 or 2, It is characterized in that The initial parameters include furnace single-tube dilution steam flow, cracking furnace outlet temperature, ultra-high pressure steam temperature, cracking furnace furnace negative pressure, furnace single-tube dimethyl disulfide injection amount, quench tower oil pump outlet pressure, quench tower quench oil level and fuel gas calorific value.
4. The system according to claim 3, It is characterized in that The initial range of the furnace single-tube dilution steam flow rate is 3500-5500 kg / h, the initial range of the cracking furnace outlet temperature is 710-780°C, the initial range of the ultra-high pressure steam temperature is 480-525°C, the initial range of the cracking furnace negative pressure is -45--20 Pa, the initial range of the furnace single-tube dimethyl disulfide injection amount is 1-20 kg / h, the initial range of the oil pump outlet pressure of the quench tower is 1.1-2 MPa, the initial range of the quench oil level of the quench tower is 45-55%, and the initial range of the calorific value of the fuel gas is 11-13 MW.
5. The system according to claim 1 or 4, It is characterized in that The cracking furnace includes at least one three-valve cut-off system, which includes a furnace cracking gas valve, a coke cleaning bypass valve and a furnace coke cleaning valve, wherein the furnace cracking gas valve and the coke cleaning bypass valve are linked by a mechanical mechanism. When the furnace cracking gas valve is opened, the coke cleaning bypass valve is closed, and when the furnace cracking gas valve is closed, the coke cleaning bypass valve is opened.
6. The system according to claim 5, It is characterized in that In the stage of cutting into the quench tower, the key parameters of cutting into are controlled and control instructions are issued, which specifically include: Controlling the flow rate of the furnace single-tube dilution steam to remain unchanged based on its initial flow rate, and controlling the temperature of the ultra-high pressure steam to remain unchanged based on its initial temperature; In the first stage, the furnace coke clearing valve is controlled to be fully closed at the first coke clearing valve rate. When the furnace coke clearing valve is fully closed, the furnace cracking gas valve is controlled to be fully opened at the first cracking valve rate, so that the furnace steam is cut out of the furnace and enters the quenching tower. When the furnace negative pressure of the cracking furnace drops to the first furnace negative pressure on the basis of its initial negative pressure, the furnace negative pressure of the cracking furnace is controlled to rise to the second furnace negative pressure at the first negative pressure rate on the basis of the first furnace negative pressure, and is maintained for a first set time after rising to the second furnace negative pressure; at the same time, the calorific value of the fuel gas is controlled to drop to the first preset calorific value at the first preset calorific value rate on the basis of its initial calorific value; In the second stage, after the cracking furnace negative pressure is maintained for a first set time based on the second furnace negative pressure, the cracking furnace negative pressure is controlled to rise to the initial negative pressure of the cracking furnace negative pressure at a second negative pressure rate based on the second furnace negative pressure.
7. The system according to claim 6, It is characterized in that The first furnace negative pressure is -180 to -130Pa, the second furnace negative pressure is -70 to -40Pa, the first negative pressure rate is 15 to 35Pa / min, the second negative pressure rate is 0.5 to 15Pa / min, the first cracking valve rate is 10 to 40% / min, the first decoking valve rate is 20 to 60% / min, the first preset calorific value rate is 0.2 to 2MW / min, the first preset calorific value is 6 to 10MW, and the first setting time is 1 to 30min.
8. The system according to claim 6, It is characterized in that The cracking furnace comprises at least one furnace.
9. The system according to claim 6, It is characterized in that The system also includes an operation navigation function module, which is used to provide operation prompts at the stage of cutting into the quenching tower according to the control instructions of the intelligent control module of the furnace steam cutting into the quenching tower process.
10. The system according to claim 9, It is characterized in that Before the first stage, the operation navigation function module prompts to turn the cracking furnace negative pressure high interlock to bypass; After the second stage, the operation navigation function module prompts to adjust the raw material blind plate and the quench oil blind plate to a perforated plate, open the oil cooler quench oil regulating valve, and check the cracking furnace status.
11. The system according to claim 1, It is characterized in that The system also includes a process key parameter monitoring and alarm module, which is used to monitor the process key parameters when entering the quench tower stage, and to alarm when the process key parameters exceed a preset range.
12. The system according to claim 11, It is characterized in that The key process parameters include cracking furnace outlet temperature, furnace single tube dilution steam flow, fuel gas calorific value, fuel gas pressure, cracking furnace pressure, Venturi rear pressure, VHS drum liquid level, ultra-high pressure steam temperature, ultra-high pressure steam pressure and cracking furnace cross section temperature.
13. The system according to claim 11, It is characterized in that The monitoring of the key process parameters and the alarming when the key process parameters exceed the preset range specifically include: When one or more of the key process parameters exceeds a first preset range, an alarm is issued; When one or more of the process key parameters exceed the second preset range, the process key parameters exceeding the second preset range are adjusted to within the first preset range according to a preset ratio based on their current values, and an alarm is issued.
14. The system according to claim 13, It is characterized in that The upper limit value of the second preset range is greater than the upper limit value of the first preset range, the lower limit value of the second preset range is less than the lower limit value of the first preset range, and the preset ratio is ±0.1% to 10%.
15. The system according to claim 1, It is characterized in that The system also includes a process alarm optimization management module, which is used to automatically shield the cracking furnace operation instrument alarm after entering the quench tower stage, and make the cracking furnace operation instrument alarm activation prompt light turn red; After the quench tower stage is completed, the cracking furnace operation instrument alarm is automatically enabled, and the cracking furnace operation instrument alarm enable prompt light turns green.
16. The system according to claim 15, It is characterized in that The types of cracking furnace operation instrument alarms include high oxygen content alarm of cross-section flue gas, bottom fuel heat load ratio alarm, side wall fuel heat load ratio alarm, cracking furnace liquid phase feed flow alarm, cracking furnace gas phase feed flow alarm, quench oil flow alarm, total feed amount alarm, furnace tube gas raw material flow alarm, furnace tube liquid raw material flow alarm, gas raw material pressure alarm, liquid raw material pressure alarm, quencher outlet temperature alarm, inlet burnt gas temperature adjustment alarm, cracking gas temperature alarm and Venturi pressure difference alarm.
17. The system according to claim 6, It is characterized in that The system also includes a deep learning function module for learning the control advantages and disadvantages of each key entry parameter in the quench tower stage based on experience values and big data, and deriving the optimal control values of the key entry parameters in the quench tower stage.
18. A method for automatically executing the process of cutting the furnace steam of an ethylene cracking furnace into a quenching tower, It is characterized in that The method is implemented using the system described in any one of claims 1 to 17, and the method comprises: A state confirmation module before cutting into the quench tower is used to confirm the initial parameters before the cracking furnace steam cuts into the quench tower, and when the initial parameters are within the initial range, it indicates that the quench tower can be cut in, and when the initial parameters are not within the initial range, an alarm is issued; An intelligent control module for the process of furnace steam cutting into the quench tower is used to control key cutting parameters and issue control instructions during the cutting into the quench tower stage, wherein the key cutting parameters include furnace single tube dilution steam flow, cracking furnace negative pressure, fuel gas calorific value and ultra-high pressure steam temperature; A furnace steam cutting-in quenching tower execution module is adopted. During the cutting-in quenching tower stage, the quenching tower is cut in according to the control instruction of the furnace steam cutting-in quenching tower process intelligent control module.
Citation Information
Patent Citations
Waste and old tire cracking, recovery and treatment system and method
CN108998069A
Ethylene device cracking furnace outlet pipeline switching system
CN211847818U
Process and draft control system for use in cracking a heavy hydrocarbon feedstock in a pyrolysis furnace
SG127069A1
Method of automatic control of launching and stopping process of pyrolysis furnaces
SU881111A1