Cantilever positioning and mounting method for near-arch-foot section of hinge-free steel truss arch bridge

By measuring the error at the construction site of the hingeless steel truss arch bridge and simulating the adjustment of the installation position and alignment of the cantilever unit, the structural stability and stiffness problems caused by temporary construction hinges were solved, the number of brackets was reduced, the construction cost was reduced, and high efficiency was achieved Cantilever positioning installation.

CN118774028APending Publication Date: 2024-10-15CHINA RAILWAY ERYUAN ENGINEERING GROUP CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410945766.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-15
Publication Date
2024-10-15

AI Technical Summary

Technical Problem

The installation method of hingeless steel truss arch bridges has the problem that temporary construction hinges will weaken the structural stability and stiffness, or that not setting temporary hinges requires a large number of brackets, resulting in high costs and low construction efficiency.

Method used

By consolidating the arch foot chords at the construction site, measuring the translation error and rotation error angle, simulated adjustment of the installation position and alignment of the cantilever units, and installation of the cantilever units in sequence, reducing the number of brackets and avoiding reduced structural stability and high construction costs.

Benefits of technology

The stability and stiffness of the hingeless steel truss arch bridge are maintained, the swing displacement of the cantilever end under the action of live load is reduced, and the construction cost is reduced.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118774028A_ABST
    Figure CN118774028A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of bridge construction, in particular to a hinge-free steel truss arch bridge near-arch-foot section cantilever positioning and installing method which comprises the following steps that L0 is solidified on an actual construction site, and L0 is an arch foot chord member embedded section; actually measuring a translation error angle alpha 1 and a rotation error angle alpha 1 of the L0 relative to the original design line shape of the unhinged steel truss arch bridge; according to the translation error and the rotation error angle alpha 1, the line shape and the installation angle of the first-section cantilever unit are simulated and adjusted, and one end of the first-section cantilever unit is connected to L0; and S3, manufacturing the first section of cantilever unit according to the simulation adjustment result of the step S3, manufacturing the remaining cantilever units according to the original design, and sequentially installing the cantilever units to complete the cantilever positioning installation of the hinged steel truss arch bridge near-arch-foot section. By means of the method, the problems that according to an installation method of the hinge-free steel truss arch bridge in the prior art, the stability of the structure in the construction stage is not weakened, the rigidity of the structure is reduced, the swing displacement of the cantilever end under the live load effect is increased, and the construction efficiency is not affected are solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of bridge construction, and in particular to a method for positioning and installing a cantilever of a segment near an arch foot of a hingeless steel truss arch bridge. Background Art

[0002] How to ensure the accuracy of the cantilever assembly of the arch ring during the construction process of hingeless steel truss arch bridges is a key issue in ensuring the quality and safety of the bridge. Cantilever inclined stay buckle hanging construction technology is widely used in the construction of large-span hingeless steel truss arch bridges. Among them, the segment installation near the arch foot is the key part of the entire arch ring structure construction, and its assembly accuracy directly affects the stability and safety of the entire bridge. The arch ring segments of steel truss arch bridges are generally constructed by cantilever post-hanging. Each arch ring segment achieves the effect of "replacing the curve with a straight line" by setting a turning point to form the arch axis.

[0003] Existing installation methods often face problems such as complex procedures, high equipment investment, and difficult precision control. They are also greatly affected by site conditions and pose safety risks and technical challenges.

[0004] Some projects will choose to set temporary hinges at the arch foot for construction, which will need to be sealed later. This method will cause the structural system to be converted from a fixed arch to a hinged arch in the cantilever stage, which will not only increase the difficulty and cost of construction, but also weaken the stability of the structure during the construction stage, reduce the rigidity of the structure, and increase the swing displacement of the cantilever end under live load.

[0005] Some projects choose not to set up temporary hinge structures. The advantage is that the structure has good integrity. However, this method requires a large number of brackets to support the weight of at least one cantilever segment near the entire arch foot. Not only is the cost high, but the filling of the bracket platform also has a greater impact on the environment. Moreover, after the bracket that needs to be inserted into the arch seat structure is in place, it cannot be immediately poured with concrete for consolidation. It can only be temporarily fixed for a long period of time. The deep holes inside the arch seat formed by it will interfere with the construction of the arch seat and the junction piers set on the arch seat, resulting in a longer construction period. Summary of the invention

[0006] The purpose of the present invention is to overcome the problems that the installation methods of hingeless steel truss arch bridges in the prior art are: one is to set a temporary construction hinge at the arch foot, but setting a temporary construction hinge will weaken the stability of the structure during the construction stage, reduce the rigidity of the structure and increase the swing displacement of the cantilever end under the action of live load; the second is not to set a temporary hinge structure, but a large number of brackets are required to support the weight of at least one cantilever segment, and the construction efficiency is affected, and a method for positioning and installing the cantilever near the arch foot segment of a hingeless steel truss arch bridge is provided.

[0007] In order to achieve the above object, the technical solution adopted by the present invention is:

[0008] In a first aspect, the present invention provides a method for positioning and installing a cantilever near an arch foot segment of a hingeless steel truss arch bridge, comprising the following steps:

[0009] S1, consolidate L0 at the actual construction site, where L0 is the embedded section of the arch foot chord;

[0010] S2, the translation error and rotation error angle α1 of the actual measurement L0 compared to the original design line shape of the hingeless steel truss arch bridge;

[0011] S3, according to the translation error and the rotation error angle α1, simulate the adjustment of the installation position, line shape and installation angle of the first section cantilever unit, wherein one end of the first section cantilever unit is connected to L0;

[0012] S4. According to the simulation adjustment result of step S3, the first cantilever unit is manufactured, and the remaining cantilever units are manufactured according to the original design. The cantilever units are installed in sequence to complete the positioning and installation of the cantilever near the arch foot segment of the hingeless steel truss arch bridge.

[0013] Cantilever units are classified according to the internode length in hingeless steel truss arch bridges. Internode length refers to the distance between two adjacent nodes in the truss structure. The near-arch foot segment is the cantilever segment close to the arch foot, which divides the cantilever segment into several cantilever units.

[0014] The cantilever segment is divided into several cantilever units. In the subsequent construction process, the cantilever units are installed in sequence to facilitate construction. L0 is short in length and light in weight, which is easy to install. Because there will inevitably be certain errors in the construction process of installing L0, the installation position of the first section cantilever unit is simulated and adjusted to compensate for the translation error; the linearity and installation angle of the first section cantilever unit are simulated and adjusted to compensate for the rotation error angle α1, so that the end of the first section cantilever unit away from L0 coincides with the original design linearity of the hingeless steel truss arch bridge. This method has both linearity simulation adjustment and installation angle simulation adjustment, which can avoid the situation where only one of the linearity simulation adjustment or installation angle simulation adjustment exists as much as possible and cannot completely correct the deviation. Compared with the prior art that sets temporary construction hinges at the arch foot or sets a large number of brackets to support the cantilever segment, this method only needs to simulate the adjustment of the installation position, linearity and installation angle of the cantilever unit, and no redundant devices need to be set, so it will not weaken the stability of the structure during the construction stage, reduce the rigidity of the structure, and increase the swing displacement of the cantilever end under the action of live load. Furthermore, because the cantilever segments are installed sequentially according to the cantilever units, the number of brackets used to support the cantilever segments is reduced, the construction cost can be reduced, and the situation in which the brackets affect the construction efficiency can be avoided.

[0015] Preferably, when step S3 simulates the adjustment of the linear shape and installation angle of the cantilever unit in section I, it includes the following steps:

[0016] S301, make an extension line along the axis of L0, and take the simulated corner point A1′ of the first section cantilever unit on the extension line;

[0017] S302, obtaining the angle α2 between the first extension section and the connecting section, and the angle α3 between the connecting section and the cantilever tail section, wherein the first extension section is a line connecting the simulated turning point A1′ and the center point of the cantilever end, the connecting section is a line connecting the simulated turning point A1′ and the original design turning point A1, and the cantilever tail section is a line connecting the original design turning point A1 and the cantilever end center point of the first cantilever unit of the design requirement, and α1, α2 and α3 satisfy the following relationship:

[0018] α2+α3=α1-α0+180°

[0019] Among them, α0 is the original design angle value of the cantilever unit of section I; the simulated adjustment of the linear shape and installation angle of the cantilever unit of section I is completed.

[0020] The center point of the cantilever end is the point where the axis of L0 and the abutment are connected.

[0021] This simulation adjustment method is to simulate and adjust the chord of the first section cantilever unit into a three-fold form. When the first section cantilever unit has the original design corner point A1, a simulated corner point A1′ is added. In this method, the axes of the line connecting the first section cantilever unit and L0 are parallel to each other. The first section cantilever unit is connected to L0 through the first extension section, one end of the connecting section is connected to the first extension section, and the other end is connected to the cantilever tail section. The cantilever tail section is connected to the second section cantilever unit through the cantilever end center point of the first section cantilever unit required by the design, and the cantilever tail section coincides with the original design route.

[0022] Preferably, in step S301, the simulated turning point A1' is outside the assembly range of the cantilever unit in section I.

[0023] If the simulated turning point is outside the splicing range of the cantilever unit, it will not affect the connection between the cantilever unit of section I and L0, thus avoiding adverse effects on the quality of the hingeless steel truss arch bridge.

[0024] Preferably, when α1≤0.4°, the simulation of adjusting the linear shape and installation angle of the cantilever unit in the first section in step S3 includes the following steps:

[0025] S301, reduce the angle α4 between the cantilever unit of section I and L0 until the following relationship is satisfied:

[0026] α5+α4=α1-α0+180°

[0027] Among them, α0 is the original design angle value of the upper chord, and α5 is the angle value of the first cantilever unit after simulation adjustment.

[0028] S302, correspondingly simulating and adjusting the shape of the web splicing plate, the web splicing plate is used to connect the first section cantilever unit and L0, and completing the simulated adjustment of the line shape and installation angle of the first section cantilever unit.

[0029] This simulation adjustment method does not change the line shape of the two folds of the chord of the first section cantilever unit, but it is necessary to simulate the adjustment of the angle α4 between the first section cantilever unit and L0, so this simulation adjustment method is suitable for the case of a small simulation adjustment angle. The tail end of the first section cantilever unit is connected to the cantilever end center point of the first section cantilever unit required by the design, which coincides with the original design route.

[0030] Preferably, the bearing capacity margin σ of the abutment chord is determined before step S4.

[0031] The excess capacity of the arch foot chord σ is the difference between the design maximum capacity of the arch foot chord and the design value of the material strength. Because the simulated adjustment of the line shape and installation angle of the first section cantilever unit will produce eccentric additional internal forces, the excess capacity of the arch foot chord σ is designed to compensate for the corresponding eccentric additional internal forces.

[0032] Preferably, after determining the surplus bearing capacity σ of the arch foot chord, between step S3 and step S4, it also includes judging whether the simulated adjustment line shape and installation angle of the first section cantilever unit meet the corresponding bearing requirements: if the additional eccentric internal force generated by the first section cantilever unit is less than or equal to the surplus bearing capacity σ of the arch foot chord, then the line shape and installation angle of the first section cantilever unit determined in step S3 are simulated and adjusted; if it is greater than the surplus bearing capacity σ of the arch foot chord, then the line shape and installation angle of the first section cantilever unit are correspondingly simulated and adjusted until the additional eccentric internal force generated by the first section cantilever unit is less than the surplus bearing capacity σ of the arch foot chord, and the subsequent cantilever units are simulated and adjusted in sequence until the additional eccentric internal force generated by each cantilever unit with simulated adjusted line shape and installation angle is less than the surplus bearing capacity σ of the arch foot chord.

[0033] When the additional eccentric internal force generated by the first cantilever unit is not greater than the excess bearing capacity σ of the arch foot chord, the first cantilever unit is designed and manufactured according to the scheme determined in step S3, and the subsequent cantilever units are manufactured and installed according to the original design. When the additional eccentric internal force generated by the first section cantilever unit is greater than the surplus bearing capacity σ of the arch foot chord, the bending angle of the first section cantilever unit is adjusted accordingly to reduce the additional eccentric internal force generated by the first section cantilever unit, and the linear shape and installation angle of the second section cantilever unit are adjusted in simulation, and the eccentric additional internal force generated by the second section cantilever unit is judged. If it is not greater than the surplus bearing capacity σ of the arch foot chord, the linear shape and installation scheme of the first section cantilever unit and the second section cantilever unit are manufactured and installed according to the corresponding scheme, and the subsequent cantilever units are manufactured and installed according to the original design; if the additional eccentric internal force generated by the second section cantilever unit is not greater than the surplus bearing capacity σ of the arch foot chord, the above steps are repeated to simulate the adjustment of the third section cantilever unit until the additional eccentric internal force generated by the last section of all cantilever units is not greater than the surplus bearing capacity σ of the arch foot chord.

[0034] Preferably, after determining that the cantilever unit meets the corresponding load-bearing requirements, the cantilever unit with simulated adjusted linear shape and installation angle is simulated and assembled in the corresponding 3D modeling software to verify whether the cantilever unit with simulated adjusted linear shape and installation angle meets the design requirements. If it does not meet the design requirements, the corresponding cantilever unit's angle is simulated and adjusted until it meets the load-bearing requirements and design requirements.

[0035] Preferably, in step S4, the tower system is constructed while manufacturing the cantilever unit.

[0036] Because the construction of the cantilever unit is carried out after the construction of the tower system is completed, the manufacture of the cantilever unit and the construction of the tower system are carried out at the same time, which will not occupy the key lines for building the tower system and is conducive to improving construction efficiency.

[0037] Preferably, after step S4, actual linear measurement is performed again on the cantilever unit whose linear shape and installation angle have been adjusted in simulation.

[0038] In a second aspect, the present invention provides a hingeless steel truss arch bridge, which is installed and constructed using the above-mentioned cantilever positioning and installation method for the arch foot segment of the hingeless steel truss arch bridge.

[0039] A hingeless steel truss arch bridge installed and constructed using the above-mentioned cantilever positioning and installation method for the near-arch foot segment of a hingeless steel truss arch bridge will not weaken the stability of the structure during the construction phase, reduce the rigidity of the structure, or increase the swing displacement of the cantilever end under live load, and has a low construction cost.

[0040] In summary, due to the adoption of the above technical solution, the beneficial effects of the present invention are:

[0041] 1. A method for positioning and installing the cantilever near the arch foot segment of a hingeless steel truss arch bridge. L0 is consolidated at the construction site, and the translation error and rotation error angle α1 of the consolidation L0 are actually measured and obtained. The first section of the cantilever unit is simulated and adjusted according to the translation error and rotation error angle α1, and the remaining cantilever units are manufactured according to the original design and installed in sequence. Because this method simulates the linear adjustment and installation angle adjustment of the cantilever unit, it can avoid as much as possible the situation where there is only a single simulation adjustment method that makes it impossible to correct the deviation. This method only needs to simulate the adjustment of the linear shape and installation angle of the cantilever unit, and there is no need to set up additional devices. And because the cantilever segments are installed in sequence according to the cantilever units, the number of brackets used to support the cantilever segments is reduced. This method solves the problems of the existing installation methods of hingeless steel truss arch bridges, namely, that a temporary construction hinge is set at the arch foot, but the temporary construction hinge will weaken the stability of the structure during the construction stage, reduce the rigidity of the structure and increase the swing displacement of the cantilever end under the action of live load; and that a temporary hinge structure is not set, but a large number of brackets are required to support the weight of at least one cantilever segment, which affects the construction efficiency.

[0042] 2. A hingeless steel truss arch bridge is installed and constructed by using the above-mentioned cantilever positioning and installation method for the near-arch foot segment of a hingeless steel truss arch bridge. It will not weaken the stability of the structure during the construction stage, reduce the rigidity of the structure, or increase the swing displacement of the cantilever end under live load, and the construction cost is low. BRIEF DESCRIPTION OF THE DRAWINGS

[0043] Figure 1 It is a flow chart of a method for positioning and installing a cantilever near the arch foot segment of a hingeless steel truss arch bridge of the present invention;

[0044] Figure 2 It is a schematic elevation diagram of the cantilever installation of the arch foot segment of the hingeless steel truss arch bridge of the present invention;

[0045] Figure 3 It is a structural diagram of an arch foot segment cantilever simulated and adjusted in a method for positioning and installing a cantilever near an arch foot segment of a hingeless steel truss arch bridge in Example 1;

[0046] Figure 4 It is a structural diagram of an arch foot segment cantilever simulated and adjusted in a method for positioning and installing a cantilever near an arch foot segment of a hingeless steel truss arch bridge in Example 2;

[0047] Figure 5 It is a schematic diagram of the joint corner in Example 2.

[0048] Icons: 1-upper chord, 2-lower chord, 3-chord cantilever surface, 4-truss web, 11-first extension section, 12-connecting section, 13-cantilever tail section, 14-joint, 21-chord, 22-top plate splicing plate, 23-web plate splicing plate, 24-bolt, 25-angle bisector, 31-junction pier, 32-arch seat, 33-structural interface. DETAILED DESCRIPTION

[0049] The present invention is further described in detail below in conjunction with specific embodiments. However, this should not be understood as the scope of the above subject matter of the present invention being limited to the following embodiments, and all technologies realized based on the content of the present invention belong to the scope of the present invention.

[0050] Unless otherwise specified, in the description of the specific embodiments of the present invention, the terms indicating the orientation or position relationship such as "up", "down", "left", "right", "center", "inside", "outside", etc. are all based on the expression of the orientation or position relationship shown in the drawings, or are the orientation or position relationship when the invented product / equipment / device is usually used. These terms of orientation or position relationship are only for the convenience of describing the scheme of the present invention or simplifying the description in the specific embodiments, so as to facilitate the technicians to quickly understand the scheme, and do not indicate or imply that a specific device / component / element must have a specific orientation, or be constructed and operated in a specific position relationship, and therefore cannot be understood as a limitation on the present invention.

[0051] In addition, if the terms "horizontal", "vertical", "overhanging", "parallel" and the like appear, it does not mean that the corresponding devices / components / elements are required to be absolutely horizontal or vertical or overhanging or parallel, but may be slightly tilted or have deviations. For example, "horizontal" only means that its direction is more horizontal than "vertical", and does not mean that the structure must be completely horizontal, but may be slightly tilted. Alternatively, it can be simplified to mean that the corresponding devices / components / elements are set in directions such as "horizontal", "vertical", "overhanging", "parallel", etc., and can have an error / deviation of ±10% relative to the corresponding direction setting, more preferably an error / deviation within ±8%, more preferably an error / deviation within ±6%, more preferably an error / deviation within ±5%, and more preferably an error / deviation within ±4%. As long as the corresponding device / component / element is within the error / deviation range, it can still achieve its role in the scheme of the present invention.

[0052] In addition, the expressions “first”, “second”, “third”, etc., which appear in the terms, are merely used to distinguish the description of the same or similar components and should not be understood as emphasizing or implying the relative importance of specific components.

[0053] In addition, in the description of the embodiments of the present invention, "several", "plurality" and "a number" represent at least 2. It can be any number such as 2, 3, 4, 5, 6, 7, 8, 9, and even more than 9.

[0054] In addition, in the description of the technical solution of the present invention, unless otherwise clearly specified / defined / restricted, the terms "set", "install", "connect", "connected", "provided with", "laid", and "arranged" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection, and can be welding, riveting, bolting, threading, and other commonly used connection means in the field. This connection can be a mechanical connection, an electrical connection, or a communication connection; it can be a direct connection, or an indirect connection through an intermediate medium, and it can be the internal connection of two elements.

[0055] Example 1

[0056] like Figure 1 As shown, a cantilever positioning and installation method for a hingeless steel truss arch bridge near the arch foot segment adopted in this embodiment includes the following steps:

[0057] S1. Because L0 is short and light, it can be directly hoisted into place by a car crane without waiting for the cable hoisting system to be completed. L0 is manufactured according to the design drawings, transported to the construction site and hoisted into place. When constructing the arch seat 32, concrete is directly poured to consolidate L0. This can avoid the long-term reserved deep holes in the embedded section from interfering with the construction of the arch seat 32 and the junction pier 31 set on the arch seat;

[0058] S2. Due to construction interference factors such as concrete vibration, the linear shape of L0 will inevitably have certain errors. The actual linear shape of the installed L0 is measured by point cloud scanning or traditional instruments such as total stations, theodolites, etc., and error analysis is performed based on the original design drawings and measurement data to determine the translation error and rotation error angle α1 of the actual linear shape of the cantilever surface 3 caused by L0 compared with the original design requirements;

[0059] S3, according to the translation error and the rotation error angle α1, simulate the adjustment of the linear shape and installation angle of the first section cantilever unit, wherein one end of the first section cantilever unit is connected to L0, including the following steps:

[0060] S301, make an extension line along the axis of L0, and take a simulated turning point A1′ of the first section cantilever unit on the extension line, and the simulated turning point A1′ is outside the assembly range of the first section cantilever unit;

[0061] S302, obtain the angle α2 between the first extension section 11 and the connecting section 12, and the angle α3 between the connecting section 12 and the cantilever tail section 13, wherein the first extension section 11 is the line connecting the simulated corner point A1′ and the center point of the cantilever end, the connecting section 12 is the line connecting the simulated corner point A1′ and the original design corner point A1, and the cantilever tail section 13 is the line connecting the original design corner point A1 and the cantilever end center point 3 of the first section cantilever unit required by the design, and the cantilever tail section 13 coincides with the original design line shape. At this time, the line shape corresponding to the first section cantilever unit is a three-fold line shape, such as Figure 3 As shown, α1, α2 and α3 satisfy the following relationship:

[0062] α2+α3=α1-α0+180°

[0063] Among them, α0 is the original design angle value of the cantilever unit of the first section; the simulation adjustment of the linear shape and installation angle of the cantilever unit of the first section is completed;

[0064] S4. According to the simulation adjustment result of step S3, the first cantilever unit is manufactured, and the remaining cantilever units are manufactured according to the original design. The cantilever units are installed in sequence to complete the positioning and installation of the cantilever near the arch foot segment of the hingeless steel truss arch bridge.

[0065] Furthermore, the cantilever segments are divided into n cantilever units according to the inter-segment length, such as Figure 2 shown.

[0066] Furthermore, the cantilever unit in Section I already has a turning point in the original design. Figure 2 As shown, the original design turning point of the upper chord 1 is point A1, and the corresponding turning point of the lower chord 2 is point B1, and the positions of point A1 and point B1 are set correspondingly. The top surface of the arch seat 32 is provided with a junction pier 31. The position of the chord cantilever surface 3 is determined in the design. In the actual installation, it must be ensured that the positions of the two ends of each cantilever unit are consistent with the position of the chord cantilever surface 3. The center point of the cantilever end is the connection between L0 and the arch seat 32 and the interface 33 of the arch ring structure. Figure 3 The middle dotted line is the design position of the cantilever segment.

[0067] Furthermore, when the simulated turning point A1′ of the first cantilever unit is taken on the extension line in step S301, the simulated turning point A1′ is outside the assembly range of the first cantilever unit, so A1′ cannot be set at the end of the rod and should be as close to L0 as possible, thereby minimizing the distance from the simulated turning point A1′ to the design position. In the simulated adjustment method of this embodiment, the axis of the first extension section 11 and L0 coincide.

[0068] Furthermore, the bearing capacity surplus σ of the arch foot chord is determined before step S4. The bearing capacity surplus σ of the arch foot chord is the difference between the design maximum bearing capacity of the arch foot chord and the design value of the material strength. Because the simulated adjustment of the linear shape and installation angle of the first section cantilever unit will generate eccentric additional internal force, the bearing capacity surplus σ of the arch foot chord is designed to compensate for the corresponding eccentric additional internal force. In actual construction, σ is generally taken as 20MPa.

[0069] Furthermore, after the arch foot chord bearing capacity surplus σ is designed, between step S3 and step S4, it also includes judging whether the simulated adjustment line shape and installation angle of the first section cantilever unit meet the corresponding bearing requirements: if the additional eccentric internal force generated by the first section cantilever unit is less than or equal to the arch foot chord bearing capacity surplus σ, that is, the arch foot chord bearing capacity surplus σ can compensate for the additional eccentric internal force generated by the first section cantilever unit, then the line shape and installation angle of the first section cantilever unit determined in step S3 are simulated and adjusted; if it is greater than the arch foot chord bearing capacity surplus σ, the manufacturing line shape eccentricity of the first section cantilever unit is appropriately reduced until the additional eccentric internal force generated by the first section cantilever unit is less than the arch foot chord bearing capacity surplus σ, and the subsequent cantilever units are simulated and adjusted in sequence according to the same method until the additional eccentric internal force generated by each cantilever unit with simulated adjusted line shape and installation angle is less than the arch foot chord bearing capacity surplus σ. Preferably, the subsequent cantilever unit adjustment method is adjusted according to the adjustment method corresponding to the first section cantilever unit.

[0070] Furthermore, after determining that the cantilever unit meets the corresponding load-bearing requirements, the cantilever unit with simulated adjusted line shape and installation angle is simulated for assembly in the corresponding 3D modeling software to verify whether the cantilever unit with simulated adjusted line shape and installation angle meets the design requirements. If it does not meet the design requirements, the corresponding cantilever unit's angle is simulated and adjusted until it meets the load-bearing requirements and design requirements.

[0071] Furthermore, in step S4, the tower system is built while the cantilever unit, especially the first section cantilever unit, is manufactured. Because the construction of the cantilever unit is after the tower system is built, the manufacture of the cantilever unit and the construction of the tower system are carried out at the same time, which will not occupy the key lines for building the tower system and is conducive to improving construction efficiency. The first section cantilever unit is manufactured to avoid affecting the subsequent actual assembly as much as possible.

[0072] Furthermore, after step S4, the cantilever unit whose linear shape and installation angle have been adjusted in simulation is measured again in actual linear shape. It is ensured that the linear position and rotation angle of the cantilever surface 3 of the installed near-arch foot suspension segment meet the design requirements, and the rear suspension segment can return to the normal cantilever installation process to ensure that the arch ring is smoothly closed and the linear shape meets the design requirements.

[0073] During the simulation adjustment, this embodiment can first simulate the adjustment of the upper chord rod 1 corresponding to the first section cantilever unit, and then simulate the adjustment of the lower chord rod 2 corresponding to the upper chord rod 1; it can also first simulate the adjustment of the lower chord rod 2 corresponding to the first section cantilever unit, and then simulate the adjustment of the upper chord rod 1 accordingly.

[0074] Example 2

[0075] A method for positioning and installing a cantilever near the arch foot of a hingeless steel truss arch bridge is substantially the same as that of Example 1, except that:

[0076] When α1≤0.4°, the simulation of adjusting the linear shape and installation angle of the first cantilever unit in step S3 includes the following steps:

[0077] S301, reducing the angle α4 between the first section cantilever unit and L0 at the joint 14 between the first section cantilever unit and L0 until the following relationship is satisfied:

[0078] α5+α4=α1-α0+180°

[0079] Among them, α0 is the original design angle value of the upper chord 1, and α5 is the angle value after simulation adjustment of the first section cantilever unit.

[0080] S302, such as Figure 4 and Figure 5 As shown, the shape of the web splicing plate 23 is adjusted in a corresponding simulation. The web splicing plate 23 is used to connect the first section cantilever unit and L0, so as to complete the simulated adjustment of the linear shape and installation angle of the first section cantilever unit.

[0081] This simulation adjustment method does not change the line shape of the two folds of the chord of the first section cantilever unit, but requires a change in the connection angle α4 between the first section cantilever unit and the embedded section L0 of the arch foot chord 21. Therefore, this simulation adjustment method is suitable for situations where the simulation adjustment angle is small. The tail end of the first section cantilever unit is connected to the center point of the cantilever end of the first section cantilever unit required by the design, and coincides with the original design route. When simulating the adjustment, this embodiment can first simulate the adjustment of the upper chord 1 corresponding to the first section cantilever unit, and then simulate the adjustment of the lower chord 2 corresponding to the upper chord 1; it can also simulate the adjustment of the lower chord 2 corresponding to the first section cantilever unit first, and then simulate the adjustment of the upper chord 1 accordingly.

[0082] The specific adjustment diagram of the web splicing plate 23 is shown in Figure 5 The web splicing plate 23 is provided with a plurality of through holes ( Figure 5(not shown), a plurality of through holes are arranged in a rectangular array, and bolts 24 pass through the through holes, so that the first section cantilever unit and L0 are connected. Because the angle between the first section cantilever unit and L0 is α4, and α4 is at the top, the corresponding angle at the bottom is 180°-α4. The angle between the connection line of the bolt 24 on the web splicing plate 23 (from the bottom plate to the bottom plate) and the bisector 25 of the angle corresponding to the bottom is (180°-α4) / 2. Top plate splicing plates 22 are provided at the upper and lower parts of the first section cantilever unit and L0, and the bolts 24 pass through the screw holes of the top plate splicing plate 22, so that the first section cantilever unit and L0 are more tightly connected.

[0083] Example 3

[0084] A hingeless steel truss arch bridge is constructed using a cantilever positioning and installation method for a hingeless steel truss arch bridge near the arch foot segment as described in Example 1 or Example 2. It will not weaken the stability of the structure during the construction phase, reduce the rigidity of the structure, or increase the swing displacement of the cantilever end under live load, and has a low construction cost.

[0085] The above are only preferred embodiments of the present invention and are not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A method for positioning and installing a cantilever near the arch foot of a hingeless steel truss arch bridge. It is characterized in that The following steps are included: S1. Consolidation at the actual construction site 0 , where L 0 It is the embedded section of the arch foot chord; S2, actual measurement L 0 Compared with the original design line shape of the hingeless steel truss arch bridge, the translation error and rotation error angle α 1 ; S3, according to the translation error and rotation error angle α 1 , simulate the adjustment of the installation position, line shape and installation angle of the first section cantilever unit, where one end of the first section cantilever unit is connected to L 0 ; S4. According to the simulation adjustment result of step S3, the first cantilever unit is manufactured, and the remaining cantilever units are manufactured according to the original design. The cantilever units are installed in sequence to complete the positioning and installation of the cantilever near the arch foot segment of the hingeless steel truss arch bridge.

2. According to the method for positioning and installing the cantilever of the arch foot section of a hingeless steel truss arch bridge according to claim 1, It is characterized in that Step S3 simulates the adjustment of the linear shape and installation angle of the first-stage cantilever unit, and includes the following steps: S301, along L 0 The axis of is used as an extension line, and the simulated turning point A1′ of the cantilever unit of section I is taken on the extension line; S302: Obtaining the angle α between the first extension section (11) and the connection section (12) 2 , the angle α between the connecting section (12) and the cantilever tail section (13) 3 , wherein the first extension section (11) is the line connecting the simulated corner point A1′ and the center point of the cantilever end, the connection section (12) is the line connecting the simulated corner point A1′ and the original design corner point A1, and the cantilever tail section (13) is the line connecting the original design corner point A1 and the cantilever end center point (3) of the first cantilever unit of the design requirement, α 1 , α 2 and α 3 Satisfies the following relationship: α 2 +α 3 =α 1 -α 0 +180° Among them, α 0 is the original design angle value of the cantilever unit of section I; complete the simulated adjustment of the linear shape and installation angle of the cantilever unit of section I.

3. According to the method for positioning and installing the cantilever of the arch foot section of a hingeless steel truss arch bridge according to claim 2, It is characterized in that In step S301, the simulated turning point A1′ is outside the assembly range of the cantilever unit of section I.

4. According to the method for positioning and installing the cantilever of the arch foot section of a hingeless steel truss arch bridge according to claim 1, It is characterized in that When α 1 When the angle of the cantilever unit is ≤0.4°, the following steps are included in step S3 when simulating the adjustment of the linear shape and installation angle of the first cantilever unit: S301, reduce the cantilever unit of section I and L 0 The angle α 4 , until the following relationship is satisfied: α 5 +α 4 =α 1 -α 0 +180° Among them, α 0 is the original design angle of the upper chord (1), α 5 The angle value after simulation adjustment for the cantilever unit in section I S302, correspondingly simulate and adjust the shape of the web splicing plate (23), the web splicing plate (23) is used to connect the first section cantilever unit and L 0 , complete the simulated adjustment of the linear shape and installation angle of the first section cantilever unit.

5. A method for positioning and installing a cantilever near the arch foot section of a hingeless steel truss arch bridge according to any one of claims 1 to 4, It is characterized in that Before step S4, the bearing capacity margin σ of the abutment chord is determined.

6. A cantilever positioning and installation method for a hingeless steel truss arch bridge near the arch foot segment according to any one of claim 5, It is characterized in that After determining the surplus bearing capacity σ of the arch foot chord, between step S3 and step S4, it also includes judging whether the simulated adjustment line shape and installation angle of the first section cantilever unit meet the corresponding bearing requirements: if the additional eccentric internal force generated by the first section cantilever unit is less than or equal to the surplus bearing capacity σ of the arch foot chord, then simulate the adjustment according to the line shape and installation angle of the first section cantilever unit determined in step S3; if it is greater than the surplus bearing capacity σ of the arch foot chord, then simulate the adjustment of the line shape and installation angle of the first section cantilever unit accordingly until the additional eccentric internal force generated by the first section cantilever unit is less than the surplus bearing capacity σ of the arch foot chord, and simulate the adjustment of subsequent cantilever units in turn until the additional eccentric internal force generated by each cantilever unit with simulated adjusted line shape and installation angle is less than the surplus bearing capacity σ of the arch foot chord.

7. According to claim 6, a cantilever positioning and installation method for a hingeless steel truss arch bridge near the arch foot segment, It is characterized in that After determining that the cantilever unit meets the corresponding load-bearing requirements, simulate the assembly of the cantilever unit with adjusted linear shape and installation angle in the corresponding 3D modeling software to verify whether the cantilever unit with adjusted linear shape and installation angle meets the design requirements. If it does not meet the design requirements, simulate the adjustment of the corresponding cantilever unit's angle until it meets the load-bearing and design requirements.

8. A method for positioning and installing a cantilever near the arch foot section of a hingeless steel truss arch bridge according to any one of claims 1 to 4, It is characterized in that In step S4, the tower system is constructed while manufacturing the cantilever unit.

9. A method for positioning and installing a cantilever near the arch foot section of a hingeless steel truss arch bridge according to any one of claims 1 to 4, It is characterized in that After step S4, the actual linear measurement is performed again on the cantilever unit whose linear shape and installation angle have been adjusted in simulation.

10. A hingeless steel truss arch bridge, It is characterized in that The installation construction is carried out by adopting a cantilever positioning and installation method for the arch foot segment of a hingeless steel truss arch bridge as described in any one of claims 1 to 9.