Working face head-on directional long-distance pre-pressure-relief drilling construction method
Through the head-on long-distance pre-pressure relief drilling construction method in the working face, the drill cuttings method is used to monitor the impact risk and adjust the drilling layout, which solves the interference problem of gas extraction and pressure relief construction in high-gas mines, and improves the efficiency of gas extraction. The mining efficiency and coal seam pressure relief efficiency improve the efficiency and safety of mine excavation.
Patent Information
- Application Number
- CN202410989531.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-23
- Publication Date
- 2024-10-15
AI Technical Summary
In mines with high gas and rock pressure, the construction of gas drainage drilling and pressure relief drilling is prone to mutual interference and frequent personnel mobilization, which affects the efficiency of excavation. In addition, the risk of rock burst and gas disaster accidents is high. A method is needed To improve the gas drainage rate and coal seam pressure relief efficiency, and reduce construction interference and personnel transfer.
The construction method of long-distance pre-pressure relief drilling in a head-on direction of the working face is adopted, the impact risk is monitored through the drill cuttings method, the drilling dust rate index is determined based on the hole depth and roadway height ratio, and the layout, depth and spacing of the pressure relief drilling are adjusted to ensure that the coal The body is within the pressure relief range to reduce construction interference, and the pressure relief boreholes are used as gas drainage boreholes.
It improves the gas extraction rate and coal seam pressure relief efficiency, reduces construction interference and personnel mobilization, improves tunnel excavation efficiency, reduces project volume and capital investment, and enhances mine safety production.
Smart Images

Figure CN118774594A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a working face head-on directional long-distance pre-pressure relief drilling construction method, belonging to the technical field of coal mine safety production. Background Art
[0002] As coal mining begins to move deeper, high-stress and high-gas mines are increasing. The rock strata in deep mines accumulate greater deformation energy, and the roof also accumulates greater elastic energy during mining. High-stress areas are easily formed in fault areas, which provide conditions for dynamic pressure phenomena. Furthermore, the presence of high gas directly affects the physical properties and deformation properties of coal and rock masses, and the gas pressure acts on the coal and rock masses in the form of volume force, which promotes the occurrence of rock bursts. Moreover, when rock bursts occur, they are accompanied by a large amount of gas gushing out, which is easy to cause other disasters and accidents. In order to reduce the possibility of disasters and improve the safety of mine mining, at present, in high-gas and rock burst mines, it is necessary to construct head and gas extraction holes to control rock burst and gas disasters during working face excavation and mining. During the construction process, the phenomenon of through holes may cause air leakage, which in turn affects the gas extraction effect. Secondly, due to the impact of anti-bumping restrictions, the number of personnel who can enter the tunnel for pressure relief construction is limited, which may also lead to the delay of the pressure relief project; the construction of a large number of pressure relief holes and gas extraction holes will cause mutual interference and frequent personnel transfers, thereby affecting the excavation efficiency, which is not conducive to improving the efficiency of mine excavation and alleviating the tense situation of follow-up.
[0003] Based on the above problems, how to provide a new method that can effectively unload coal seam pressure while improving gas extraction rate, and reduce mutual interference and personnel transfer between gas extraction drilling and pressure relief drilling construction processes, thereby greatly improving tunnel excavation efficiency, is the research direction required by the present invention. Summary of the invention
[0004] In view of the problems existing in the above-mentioned prior art, the present invention provides a method for constructing a long-distance directional pre-pressure relief drilling hole at the working face, which can effectively relieve coal seam pressure while improving the gas extraction rate, and reduce the mutual interference and personnel transfer between the gas extraction drilling and pressure relief drilling construction processes, thereby greatly improving the tunnel excavation efficiency.
[0005] In order to achieve the above object, the technical solution adopted by the present invention is: a working face head-on directional long-distance pre-pressure relief drilling construction method, the specific steps are:
[0006] A. Determine the drilling layout method: During the tunnel excavation, the drill cuttings method is used for monitoring, and the impact hazard drill dust rate index of the drill cuttings method is determined according to the current tunnel hole depth and tunnel height ratio; before excavation, the drill cuttings method is used to conduct a test within a certain range in front of the head:
[0007] ① If the drill dust rate obtained in this test does not reach the impact hazard drill dust rate index, two long-distance pressure relief holes perpendicular to the head-on wall and parallel to each other shall be constructed within the range of the head-on test. The two long-distance pressure relief holes shall be symmetrically arranged on both sides of the neutral line of the roadway;
[0008] ② If the drill dust rate obtained in this test reaches the drill dust rate index of impact hazard, three long-distance pressure relief boreholes perpendicular to the head-on wall and parallel to each other shall be constructed within the range of the head-on test. One of the long-distance pressure relief boreholes shall be located on the neutral line of the tunnel and higher than the other two long-distance pressure relief boreholes. The other two long-distance pressure relief boreholes shall be located symmetrically on both sides of the neutral line of the tunnel.
[0009] ③ If there are frequent coal cannons or dynamic phenomena with high pressure during the detection process, five long-distance pressure relief boreholes perpendicular to the head-on wall and parallel to each other are constructed within the detection range in the head-on direction. Two of the long-distance pressure relief boreholes are symmetrically arranged on both sides of the neutral line of the tunnel to form the first arrangement; the other three long-distance pressure relief boreholes are equally spaced and the middle long-distance pressure relief borehole is on the neutral line of the tunnel. The three long-distance pressure relief boreholes are at the same height to form the second arrangement, which is lower than the first arrangement;
[0010] B. Determine the drilling depth: Use the comprehensive index method and multi-factor coupling method to evaluate and divide the impact hazard of a certain range in front of the head detected in step A, determine the lengths of weak, medium and strong impact hazard areas along the excavation direction, and determine the depth of each long-distance pressure relief borehole in step A according to the length of each hazard area, and ensure that the coal body within 10m in front of the head is within the pressure relief range during the next construction after excavation;
[0011] C. Adjust the drilling diameter: adjust the drilling diameter according to the actual situation of the mine;
[0012] D. Adjust the horizontal spacing of the boreholes: adjust the horizontal spacing of the boreholes according to the actual situation of the mine;
[0013] E. Pressure relief construction in front of the head: according to the drilling layout, drilling depth, drilling diameter and drilling spacing of this pressure relief construction determined in steps A to D, pressure relief construction is carried out in the detection range in front of the head; after completion, excavation is carried out from the head to the front until the next pressure relief construction is required, and excavation is stopped, and pressure relief construction is carried out again after repeating steps A to D at the current head position, and this cycle is repeated until the entire tunnel excavation construction is completed; the pressure relief borehole constructed above can also be used as a gas extraction borehole for gas extraction.
[0014] Further, in step ①, the horizontal spacing between the two long-distance pressure relief boreholes is 1.2 to 1.5 m, and the distance between them and the tunnel floor is 0.5 to 1.5 m; in step ②, the horizontal spacing between the two long-distance pressure relief boreholes symmetrically located on both sides of the tunnel neutral line is 1.2 to 1.5 m, and the distance h1 between them and the tunnel floor is 1.2 to 1.5 m, the distance h2 between the long-distance pressure relief borehole on the tunnel neutral line and the tunnel floor is 1.6 to 2.0 m, and the height difference D between h1 and h2 is h The horizontal spacing between the two long-distance pressure relief boreholes in the first row in step ③ is 1.2-1.5m, and the distance between them and the bottom plate of the tunnel is 1.6-2.0m. The horizontal spacing between the three long-distance pressure relief boreholes in the second row is half of the horizontal spacing of the first row, and the distance between them and the bottom plate of the tunnel is 1.2-1.5m, and the height difference between the first row and the second row is 0.4-0.6m.
[0015] Furthermore, the specific judgment criteria for the dynamic phenomenon of frequent coal blasting or high pressure in step ③ are: if the drill dust rate detected during the construction process of the drilling cuttings method reaches the impact hazard drill dust rate index, and the borehole is accompanied by abnormal noise, spalling and obvious vibration of coal or rock, it is determined to be a dynamic phenomenon of frequent coal blasting or high pressure.
[0016] Furthermore, in step A, the impact risk drill dust rate index of the drill cuttings method is determined according to the hole depth to height ratio of the current tunnel, specifically:
[0017] When the hole depth to tunnel height ratio a<1.5, the impact hazard drilling powder rate index b≥1.5 is determined;
[0018] When the hole depth to tunnel height ratio is 1.5≤a≤3, the impact hazard drilling powder rate index b≥2 is determined;
[0019] When the hole depth to tunnel height ratio a>3, the impact hazard drilling powder rate index b≥3 is determined.
[0020] Further, the depth of each long-distance pressure relief borehole is determined in step B as follows:
[0021] Further, the step C is specifically as follows: setting the initial borehole diameter to 0.1-0.2 m, adjusting the borehole diameter according to the actual situation of the mine, and the specific formula for adjusting the long-distance pressure relief borehole diameter is:
[0022]
[0023] Where: p is the coefficient of expansion and takes 1.2 to 1.5, then Take 1.73~2.44; R0 is the initial diameter of the drilling hole, R b To adjust the rear drilling diameter.
[0024] Further, the step D is specifically as follows: the range of the horizontal spacing of the pressure relief boreholes is 1 to 3 m, and the horizontal spacing of the boreholes is adjusted according to the actual situation of the mine. The specific formula is:
[0025]
[0026] Where: d is the horizontal spacing of the boreholes, in meters (m); β is the hole collapse coefficient, β≥1; is the drill diameter for drilling construction, in meters (m); h is the tunnel height, in meters (m); In order to effectively relieve pressure, the strain rate is set to 1.5%, 1.0% and 0.8% for strong, medium and weak impact risk areas respectively, which can effectively prevent and control impact rock pressure.
[0027] Compared with the prior art, the present invention first determines the impact hazard drill dust rate index, uses the drill cuttings method to conduct a detection within a certain range in front of the head, compares the detected drill dust rate with the index, and combines whether dynamic phenomena occur during the detection process to divide it into three situations, each of which corresponds to a pressure relief drilling layout method; then, according to the impact hazard assessment and classification in front of the head, the depth of the pressure relief borehole is determined; finally, according to the actual situation of the mine, the diameter of the pressure relief borehole and the horizontal spacing of the pressure relief borehole are adjusted, so that pressure relief construction is carried out within the detection range in front of the head according to the obtained pressure relief drilling parameters. The present invention determines the corresponding pressure relief drilling hole layout mode and parameters according to different situations, and the pressure relief drilling holes can be used as gas extraction drilling holes for gas extraction, which can effectively relieve coal seam pressure while improving the gas extraction rate, and reduces the engineering workload of pressure relief drilling hole construction and the mutual interference between multiple construction processes such as gas extraction drilling holes and pressure relief drilling holes in the excavation working face, reduces the investment in personnel and funds, improves mine excavation efficiency, and alleviates the tense situation of connection, which is of great significance to the safe production of coal mines. BRIEF DESCRIPTION OF THE DRAWINGS
[0028] Figure 1 It is a schematic diagram of the overall process of the present invention;
[0029] Figure 2 It is a schematic diagram of the drilling arrangement in step ① of the present invention;
[0030] Figure 3 It is a schematic diagram of the drilling arrangement in step ② of the present invention;
[0031] Figure 4 It is a schematic diagram of the drilling arrangement in step ③ of the present invention. DETAILED DESCRIPTION
[0032] The present invention will be further described below.
[0033] like Figure 1 As shown, the specific steps of the present invention are:
[0034] A. Determine the drilling layout method: During the tunnel excavation, the drill cuttings method is used for monitoring, and the impact hazard drill dust rate index of the drill cuttings method is determined according to the hole depth and height ratio of the current tunnel. Specifically, when the hole depth and height ratio a<1.5, the impact hazard drill dust rate index b≥1.5 is determined; when the hole depth and height ratio is 1.5≤a≤3, the impact hazard drill dust rate index b≥2 is determined; when the hole depth and height ratio a>3, the impact hazard drill dust rate index b≥3 is determined; before excavation, the drill cuttings method is used to detect a certain range in front of the head:
[0035] ① If the drill dust rate obtained in this test does not reach the impact hazard drill dust rate index, two long-distance pressure relief holes perpendicular to the head-on wall and parallel to each other are constructed within the range of the head-on test. The two long-distance pressure relief holes are symmetrically arranged on both sides of the neutral line of the tunnel. Figure 2 As shown; the horizontal spacing d between the two long-distance pressure relief boreholes is 1.2 to 1.5 m, and the distance h between the two long-distance pressure relief boreholes and the tunnel floor is 0.5 to 1.5 m;
[0036] ② If the drill dust rate obtained in this test reaches the impact hazard drill dust rate index, three long-distance pressure relief holes perpendicular to the head-on wall and parallel to each other are constructed within the range of the head-on test. One of the long-distance pressure relief holes is located on the neutral line of the tunnel and is higher than the other two long-distance pressure relief holes. The other two long-distance pressure relief holes are symmetrically located on both sides of the neutral line of the tunnel. Figure 3 As shown; the horizontal spacing d between the two long-distance pressure relief boreholes symmetrically located on both sides of the neutral line of the tunnel is 1.2-1.5m, and the distance h1 between the long-distance pressure relief borehole on the neutral line of the tunnel and the tunnel bottom plate is 1.2-1.5m, the distance h2 between the long-distance pressure relief borehole on the neutral line of the tunnel and the tunnel bottom plate is 1.6-2.0m, and the height difference D between h1 and h2 h 0.4~0.6m;
[0037] ③ If the dynamic phenomenon of frequent coal blasting or high pressure occurs during the detection process, the specific judgment criteria are as follows: if the drill dust rate obtained during the construction process of the drilling cuttings method reaches the impact hazard drill dust rate index, and the borehole is accompanied by abnormal noise, spalling and obvious vibration of coal or rock, it is determined to be a dynamic phenomenon of frequent coal blasting or high pressure; then five long-distance pressure relief boreholes perpendicular to the head-on wall and parallel to each other are constructed within the range of the head-on forward detection, two of which are symmetrically arranged on both sides of the neutral line of the tunnel to form a first arrangement; the other three long-distance pressure relief boreholes are equally spaced and the middle long-distance pressure relief borehole is on the neutral line of the tunnel, and the three long-distance pressure relief boreholes are at the same height to form a second arrangement, and the second arrangement is lower than the first arrangement. Figure 4As shown; the horizontal spacing d between the two long-distance pressure relief boreholes in the first arrangement is 1.2-1.5m, and the distance h3 between the boreholes and the tunnel floor is 1.6-2.0m, the horizontal spacing between the three long-distance pressure relief boreholes in the second arrangement is 0.5d, and the distance h4 between the boreholes and the tunnel floor is 1.2-1.5m, and the height difference D between the first arrangement and the second arrangement is h1 It is 0.4~0.6m.
[0038] B. Determine the drilling depth: Use the comprehensive index method and multi-factor coupling method to evaluate and divide the impact hazard of a certain range in front of the head detected in step A, determine the lengths of weak, medium and strong impact hazard areas along the excavation direction, and determine the depth of each long-distance pressure relief borehole in step A according to the length of each hazard area, and ensure that the coal body within 10m in front of the head is within the pressure relief range during the next construction after excavation;
[0039] C. Adjust the borehole diameter: adjust the borehole diameter according to the actual situation of the mine, specifically: set the initial borehole diameter to 0.1-0.2m, and adjust the borehole diameter according to the actual situation of the mine. The specific formula for adjusting the long-distance pressure relief borehole diameter is:
[0040]
[0041] Where: p is the coefficient of expansion and takes 1.2 to 1.5, then Take 1.73~2.44; R0 is the initial diameter of the drilling hole, R b To adjust the rear drilling diameter.
[0042] D. Adjust the horizontal spacing of boreholes: adjust the horizontal spacing of boreholes according to the actual situation of the mine. Specifically, the range of the horizontal spacing of pressure relief boreholes is 1 to 3m. Adjust the horizontal spacing of boreholes according to the actual situation of the mine. The specific formula is:
[0043]
[0044] Where: d is the horizontal spacing of the boreholes, in meters (m); β is the hole collapse coefficient, β≥1; is the drill diameter for drilling construction, in meters (m); h is the tunnel height, in meters (m); In order to effectively relieve pressure, the strain rate is set to 1.5%, 1.0% and 0.8% for strong, medium and weak impact risk areas respectively, which can effectively prevent and control impact rock pressure.
[0045] E. Pressure relief construction in front of the head: according to the drilling layout, drilling depth, drilling diameter and drilling spacing of this pressure relief construction determined in steps A to D, pressure relief construction is carried out in the detection range in front of the head; after completion, excavation is carried out from the head to the front until the next pressure relief construction is required, and excavation is stopped, and pressure relief construction is carried out again after repeating steps A to D at the current head position, and this cycle is repeated until the entire tunnel excavation construction is completed. The pressure relief boreholes constructed above can also be used as gas extraction boreholes for gas extraction.
[0046] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the principle of the present invention. These improvements and modifications should also be regarded as the scope of protection of the present invention.
Claims
1. A method for constructing a long-distance pre-pressure relief drilling hole in a working face, characterized in that: The specific steps are: A. Determine the drilling layout method: During the tunnel excavation, the drill cuttings method is used for monitoring, and the impact hazard drill dust rate index of the drill cuttings method is determined according to the current tunnel hole depth and tunnel height ratio; before excavation, the drill cuttings method is used to conduct a test within a certain range in front of the head: ① If the drill dust rate obtained in this test does not reach the impact hazard drill dust rate index, two long-distance pressure relief holes perpendicular to the head-on wall and parallel to each other shall be constructed within the range of the head-on test. The two long-distance pressure relief holes shall be symmetrically arranged on both sides of the neutral line of the roadway; ② If the drill dust rate obtained in this test reaches the drill dust rate index of impact hazard, three long-distance pressure relief boreholes perpendicular to the head-on wall and parallel to each other shall be constructed within the range of the head-on test. One of the long-distance pressure relief boreholes shall be located on the neutral line of the tunnel and higher than the other two long-distance pressure relief boreholes. The other two long-distance pressure relief boreholes shall be located symmetrically on both sides of the neutral line of the tunnel. ③ If there are frequent coal cannons or dynamic phenomena with high pressure during the detection process, five long-distance pressure relief boreholes perpendicular to the head-on wall and parallel to each other are constructed within the detection range in the head-on direction. Two of the long-distance pressure relief boreholes are symmetrically arranged on both sides of the neutral line of the tunnel to form the first arrangement; the other three long-distance pressure relief boreholes are equally spaced and the middle long-distance pressure relief borehole is on the neutral line of the tunnel. The three long-distance pressure relief boreholes are at the same height to form the second arrangement, which is lower than the first arrangement; B. Determine the drilling depth: Use the comprehensive index method and multi-factor coupling method to evaluate and divide the impact hazard of a certain range in front of the head detected in step A, determine the length of weak, medium and strong impact hazard areas along the excavation direction, and determine the depth of each long-distance pressure relief borehole in step A according to the total length of each hazard area, and ensure that the coal body within 10m in front of the head is within the pressure relief range during the next construction after excavation; C. Adjust the drilling diameter: adjust the drilling diameter according to the actual situation of the mine; D. Adjust the horizontal spacing of the boreholes: adjust the horizontal spacing of the boreholes according to the actual situation of the mine; E. Pressure relief construction in front of the head: According to the drilling layout, drilling depth, drilling diameter and drilling spacing of this pressure relief construction determined in steps A to D, pressure relief construction is carried out in the detection range in front of the head; after completion, excavation is carried out from the head to the front until the next pressure relief construction is required, and excavation is stopped, and steps A to D are repeated at the current head position and pressure relief construction is carried out again, and this cycle is repeated until the entire tunnel excavation construction is completed.
2. According to the working face head-on directional long-distance pre-pressure relief drilling construction method of claim 1, it is characterized in that: In step ①, the horizontal spacing between the two long-distance pressure relief boreholes is 1.2 to 1.5 m, and the distance between them and the tunnel floor is 0.5 to 1.5 m; in step ②, the horizontal spacing between the two long-distance pressure relief boreholes symmetrically located on both sides of the tunnel neutral line is 1.2 to 1.5 m, and the distance h1 between them and the tunnel floor is 1.2 to 1.5 m, the distance h2 between the long-distance pressure relief borehole on the tunnel neutral line and the tunnel floor is 1.6 to 2.0 m, and the height difference D between h1 and h2 is h The horizontal spacing between the two long-distance pressure relief boreholes in the first row in step ③ is 1.2-1.5m, and the distance between them and the bottom plate of the tunnel is 1.6-2.0m. The horizontal spacing between the three long-distance pressure relief boreholes in the second row is half of the horizontal spacing of the first row, and the distance between them and the bottom plate of the tunnel is 1.2-1.5m, and the height difference between the first row and the second row is 0.4-0.6m.
3. The method for constructing a long-distance pre-pressure relief drilling hole on a working face according to claim 1 is characterized in that: The specific judgment criteria for the dynamic phenomenon of frequent coal blasting or high pressure in step ③ are: if the drill dust rate detected during the construction process of the drilling cuttings method reaches the impact hazard drill dust rate index, and the borehole is accompanied by abnormal noise, spalling and obvious vibration of coal or rock, it is determined to be a dynamic phenomenon of frequent coal blasting or high pressure.
4. The method for constructing a long-distance pre-pressure relief drilling hole on a working face according to claim 1 is characterized in that: In step A, the impact risk drill dust rate index of the drill cuttings method is determined according to the hole depth to height ratio of the current tunnel, specifically: When the hole depth to tunnel height ratio a<1.5, the impact hazard drilling powder rate index b≥1.5 is determined; When the hole depth to tunnel height ratio is 1.5≤a≤3, the impact hazard drilling powder rate index b≥2 is determined; When the hole depth to tunnel height ratio a>3, the impact hazard drilling powder rate index b≥3 is determined.
5. The method for constructing a long-distance pre-pressure relief drilling hole on a working face according to claim 1 is characterized in that: The step C specifically includes: setting the initial borehole diameter to 0.1-0.2 m, adjusting the borehole diameter according to the actual situation of the mine, and the specific formula for adjusting the long-distance pressure relief borehole diameter is: Where: p is the coefficient of expansion and takes 1.2 to 1.5, then Take 1.73~2.44; R0 is the initial diameter of the drilling hole, R b To adjust the rear drilling diameter.
6. The method for constructing a long-distance pre-pressure relief drilling hole on a working face according to claim 1 is characterized in that: The step D is specifically as follows: the range of the horizontal spacing of the pressure relief boreholes is 1 to 3 m, and the horizontal spacing of the boreholes is adjusted according to the actual situation of the mine. The specific formula is: Where: d is the horizontal spacing of the boreholes; β is the hole collapse coefficient, β≥1; is the diameter of the drill bit used in drilling construction; h is the height of the tunnel; In order to effectively relieve pressure, the strain rate is set to 1.5%, 1.0% and 0.8% for strong, medium and weak impact risk areas respectively, which can effectively prevent and control impact rock pressure.
Citation Information
Patent Citations
Actual-measurement comprehensive evaluation method for impact risk
CN104239691A
Coal mine rock burst risk grading prediction method based on drilling cutting monitoring
CN112418494A
Method for preventing rock burst through tunneling roadway cut-through
CN113266360A
Coal seam directional long drill hole arrangement method giving consideration to gas pre-extraction and tunneling roadway pressure relief
CN117345327A