Hydraulic sand blasting rock drilling system and using method

Through the hydraulic sandblasting rock drilling system, high-pressure water flow and sand are used to erode and break the rock, which solves the efficiency and safety problems of the existing rock drill on rocks with developed cleats, high hardness or high abrasiveness, and achieves high efficiency and automation. Drilling of blastholes.

CN118774597AInactive Publication Date: 2024-10-15FUJIAN WATERJET SCIENTIFIC RESEARCH INSTITUTE CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410964108.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-18
Publication Date
2024-10-15
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

When existing rock drills are drilling rocks, it is difficult to form regular blast holes when encountering rocks with developed cleats, rocks with high hardness or high abrasiveness, and the impact force transmitted by the bit is weakened when the depth is large, affecting efficiency and safety.

Method used

A hydraulic sandblasting rock drilling system is used to use hydraulic cylinders, pulleys, rails, sandblasting actuators and other components to use high-pressure water flow and sand particles for erosion and crushing, and accurately control the position and angle of the nozzle to form blastholes with suitable diameter and depth.

Benefits of technology

It improves the rock drilling efficiency and the regularity of the inner wall of the blasthole, reduces human intervention, has a high degree of system automation, has an overload protection function, and is suitable for specific working conditions.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118774597A_ABST
    Figure CN118774597A_ABST
Patent Text Reader

Abstract

The invention provides a hydraulic sand blasting rock drilling system and a using method. The hydraulic sand blasting rock drilling system comprises a lifting hydraulic cylinder, a pulley block, a track, a heavy hinge, a transmission chain, a sand blasting executing mechanism, an electric control system, a hydraulic station, a high-pressure flow divider, a sand adding device, a high-pressure plunger pump and a water supply system. Rock is broken through the strong erosion capacity of hydraulic sand blasting, the operation efficiency is high, the position of a sand blasting flushing pipe can be accurately changed in a hydraulic and electric control mode, and therefore a plurality of shot holes with certain diameters and depths are dug in the rock wall, and a foundation is provided for follow-up explosive installation for blasting; the system has the advantages that the whole system is high in automation degree, and excessive manual intervention is not needed; the sand blasting nozzle runs stably, the speed is accurate and controllable, the inner wall of a shot hole is regular and free of obvious recesses or bulges, and subsequent explosive filling is facilitated; and an overload protection function is preset, so that the system redundancy is high.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the fields of mine development, tunnel excavation and mountain blasting, and in particular to a hydraulic sandblasting rock drilling system and a use method thereof. Background Art

[0002] In the fields of mining development, tunneling, mountain blasting, etc., it is often necessary to drill holes in rocks for loading explosives and blasting the rocks, so as to complete the mining of stone (or ore) and other stone works; the usual way to drill holes is to use a rock drill to operate on the rock; the operation mode of the rock drill is based on the impact crushing principle, the piston performs high-frequency reciprocating motion, continuously impacts the drill tail, and under the action of the impact force, the sharp wedge-shaped drill head crushes the rock and drills it into a certain depth. This method is mature, reliable and widely used, but in many specific working conditions, there are the following problems:

[0003] (1) When drilling in a rock with developed cleats, if the drilling direction of the drill bit is parallel to the cleat direction of the rock, under the action of stress, the rock will crack along the cleats or even collapse into the blasthole, making it difficult to form a relatively regular circular blasthole, affecting the loading of explosives;

[0004] (2) When the rock is extremely hard or abrasive, the operating efficiency or service life of the drill bit will be sharply reduced, ultimately affecting the rock drilling efficiency;

[0005] (3) When the depth of the drill hole is large, the required drill bit length is also large. Since the piston of the rock drill performs high-frequency reciprocating motion, it is necessary to continuously impact the drill tail and the drill bit. The long drill bit has a large mass and a large inertia force during high-frequency vibration, which often leads to a sharp weakening of the impact force ultimately transmitted to the rock.

[0006] In summary, it is necessary to develop a flexible drilling technology that can overcome rigidity with softness, so as to replace the hard-on-hard drilling method of the rock drill under specific working conditions. The present invention is proposed for this purpose. Summary of the invention

[0007] The technical problem to be solved by the present invention is to provide a hydraulic sandblasting rock drilling system and a method of use in view of the above-mentioned defects in the prior art. The rock is broken by the powerful erosion ability of hydraulic sandblasting, and the position of the sandblasting flushing pipe is changed, so as to drill a plurality of blastholes with a certain diameter and depth on the rock wall, providing a basis for the subsequent installation of explosives for blasting.

[0008] According to the present invention, a hydraulic sandblasting rock drilling system is provided, comprising: two lifting hydraulic cylinders, a pulley block, a track, a heavy-duty hinge, a transmission chain, a sandblasting actuator, an electronic control system, a hydraulic station, a high-pressure diverter, a sand adding device, a high-pressure plunger pump, and a water supply system; the pulley block is installed at both ends of the track, and the transmission chain forms a closed-loop transmission through the pulley block and the active sprocket; the two lifting hydraulic cylinders are arranged in parallel, the main shaft of each lifting hydraulic cylinder is hinged to a heavy-duty hinge, and the heavy-duty hinge is placed in a hollow groove of the track, and the hollow groove on the track limits the running direction of the heavy-duty hinge to the up and down moving direction; the sandblasting actuator is arranged on the track, so that the track provides a running track for the sandblasting actuator; the hydraulic station controls the lifting and lowering of the lifting hydraulic cylinder to drive the lifting and lowering of the track, thereby driving the lifting and lowering of the sandblasting actuator. The sandblasting actuator can move left and right on the track so as to drill blastholes at different positions in the left and right directions. The hydraulic station controls the extension and retraction of the small multi-stage hydraulic cylinder in the sandblasting actuator, thereby driving the extension and retraction of the sandblasting assembly. The electronic control system is used to control the start and stop of the hydraulic station and the high-pressure plunger pump, and control the rotation working parameters of the servo motor in the sandblasting actuator. The servo motor drives the rotating arm to move, thereby changing the angle of the sandblasting assembly. The water supply system is used to provide water without sand to the high-pressure plunger pump, which pressurizes the water to a predetermined value and then delivers it to the sand adding device, which adds cutting sand to the high-pressure water in proportion to form a two-phase mixed liquid, and then delivers the two-phase mixed liquid to the porous nozzle in the sandblasting assembly to form a sand-containing water flow.

[0009] Preferably, the lifting hydraulic cylinder is a multi-stage hydraulic cylinder.

[0010] Preferably, the sandblasting actuator includes a sandblasting assembly, a small multi-stage hydraulic cylinder, a rotating arm, a supporting frame, a driving sprocket, a caster, a sprocket-driven hydraulic motor, a servo motor, a bearing, and a caster shaft; wherein two small multi-stage hydraulic cylinders are arranged on opposite sides of the rotating arm, respectively, the sandblasting assembly is arranged at the end of the small multi-stage hydraulic cylinder, the supporting frame supports the rotating arm, and the driving sprocket and the caster are arranged on the supporting frame; the sandblasting assembly includes a porous nozzle, a carbide protective cap, a transmission screw, a limit bearing, a guard plate connecting bolt, a guard plate, a driving gear, a gear-driven hydraulic motor, a rotating water tail, and a driven gear; wherein the porous nozzle protected by the carbide protective cap is arranged at the end of the transmission screw, the driving gear is driven by the gear-driven hydraulic motor, the guard plate is connected to the limit bearing through the guard plate connecting bolt, the rotating water tail is arranged at the tail of the transmission screw, and the driving gear and the driven gear are used to install the transmission screw.

[0011] Preferably, during the erosion process, the gear-driven hydraulic motor in the sandblasting assembly rotates at a preset speed, driving the driving gear to rotate, and through meshing transmission, driving the driven gear to rotate, and the driven gear is meshed with the transmission screw through a trapezoidal thread, thereby converting the rotational motion of the driven gear into a linear translational motion of the transmission screw, driving the porous nozzle to gradually enter the blasthole eroded on the rock wall, and the porous nozzle continues to enter until the preset drilling depth is reached; the rotating water tail is used to shield the rotational motion of the transmission screw inside it, thereby connecting it to the water-sand delivery pipe.

[0012] Preferably, the high-pressure plunger pump is connected to the water supply system through a low-pressure water pipe, the high-pressure plunger pump is connected to the sand adding device through a high-pressure hose, the sand adding device is connected to the high-pressure diverter through a high-pressure hose, the high-pressure diverter divides the high-pressure sand-containing water flow into two streams, and is connected to the rotating water tail in the sandblasting actuator through a high-pressure hose.

[0013] Preferably, the lifting hydraulic cylinder is connected to the hydraulic station through hydraulic hoses, the small multi-stage hydraulic cylinders in the sandblasting actuator are connected to the hydraulic station through hydraulic hoses, the sprocket-driven hydraulic motor is connected to the hydraulic station through hydraulic hoses, and the gear-driven hydraulic motor in the sandblasting assembly is connected to the hydraulic station through hydraulic hoses.

[0014] Preferably, the servo motor in the sandblasting actuator is connected to the electronic control system via a shielded cable, and the hydraulic station and the high-pressure plunger pump are connected to the electronic control system via power cables, respectively.

[0015] According to the present invention, a method for using the hydraulic sandblasting rock drilling system is also provided, comprising: using the hydraulic sandblasting rock drilling system to perform blasthole drilling below the track and to perform blasthole drilling above the track.

[0016] Preferably, performing sub-track blasthole drilling comprises:

[0017] The main shaft of the lifting hydraulic cylinder is fully retracted, the electronic control system is turned on, the servo motor is driven to rotate to the preset angle and then stopped to allow the rotating arm to reach the preset position, and then the hydraulic station is turned on to extend the main shaft of the driving multi-stage hydraulic cylinder, thereby driving the sandblasting component to extend to the preset position. If the position is not accurate, the sprocket drive hydraulic motor is turned on to drive the active sprocket to rotate, and the position of the sandblasting actuator is adjusted through the closed loop composed of the track, pulley block and transmission chain until the sandblasting component is adjusted to the precise excavation position;

[0018] Then, the high-pressure plunger pump is turned on to pressurize the clean water delivered by the water supply system and pump it into the sand adding device. The sand adding device adds the cutting sand into the high-pressure water in proportion to form a two-phase mixed liquid. The two-phase mixed liquid is then transported to the porous nozzle in the sand blasting component to form multiple high-speed sand-containing water flows to erode and crush the rock wall.

[0019] After a shallow hole that meets the diameter requirements is formed on the rock wall, the gear-driven hydraulic motor is turned on to drive the active gear to rotate, which in turn drives the driven gear to rotate. Under the action of the trapezoidal thread transmission, the transmission screw slowly enters the previously formed shallow hole, and gradually a blasthole with a certain depth is excavated on the rock wall.

[0020] Preferably, performing above-track blasthole drilling comprises:

[0021] Turn on the hydraulic station to control the main shaft of the lifting hydraulic cylinder to extend; turn on the electronic control system, drive the servo motor to rotate to the preset angle and then stop to make the rotating arm reach the preset position, then drive the main shaft of the multi-stage hydraulic cylinder to extend, and then drive the sandblasting component to extend to the preset position. If the position is not accurate, turn on the sprocket drive hydraulic motor to drive the active sprocket to rotate, and adjust the position of the sandblasting actuator through the closed loop composed of the track, pulley block and transmission chain until the sandblasting component is adjusted to the precise excavation position;

[0022] Then, the high-pressure plunger pump is turned on to pressurize the clean water delivered by the water supply system and pump it into the sand adding device. The sand adding device adds the cutting sand into the high-pressure water in proportion to form a two-phase mixed liquid. The two-phase mixed liquid is then transported to the porous nozzle in the sand blasting component to form multiple high-speed sand-containing water flows to erode and crush the rock wall.

[0023] After a shallow hole that meets the diameter requirements is formed on the rock wall, the gear-driven hydraulic motor is turned on to drive the active gear to rotate, which in turn drives the driven gear to rotate. Under the action of the trapezoidal thread transmission, the transmission screw slowly enters the previously formed shallow hole, and gradually a blasthole with a certain depth is excavated on the rock wall.

[0024] The beneficial effects of the present invention include at least the following:

[0025] (1) The overall system has a high degree of automation and does not require excessive human intervention;

[0026] (2) The powerful erosion ability of hydraulic sandblasting is used to drill blastholes, which has high operating efficiency;

[0027] (3) The sandblasting nozzle runs smoothly, the speed is precisely controllable, and the inner wall of the blasthole is regular without obvious depressions or protrusions, which is conducive to the subsequent loading of explosives;

[0028] (4) It has a preset overload protection function and a high degree of system redundancy. BRIEF DESCRIPTION OF THE DRAWINGS

[0029] A more complete understanding of the present invention and its attendant advantages and features will be more readily appreciated by reference to the following detailed description taken in conjunction with the accompanying drawings, in which:

[0030] Figure 1The overall schematic diagram of the hydraulic sandblasting rock drilling system according to the preferred embodiment of the present invention is schematically shown;

[0031] Figure 2 A schematic diagram of a track structure according to a preferred embodiment of the present invention is schematically shown;

[0032] Figure 3 A schematic diagram of a blasthole drilling method under a track according to a preferred embodiment of the present invention is schematically shown;

[0033] Figure 4 A schematic diagram of a blasthole drilling method above a track according to a preferred embodiment of the present invention is schematically shown;

[0034] Figure 5 A schematic diagram of a sandblasting pipeline connection method according to a preferred embodiment of the present invention is schematically shown;

[0035] Figure 6 A schematic diagram of the connection between the hydraulic control pipeline and the electric control cable according to a preferred embodiment of the present invention is shown schematically;

[0036] Figure 7 Schematically showing a front view of a sandblasting actuator according to a preferred embodiment of the present invention;

[0037] Figure 8 Schematically showing a side view of a sandblasting actuator according to a preferred embodiment of the present invention;

[0038] Fig. 9 The schematic diagram of the structure of the sandblasting assembly according to the preferred embodiment of the present invention is shown schematically.

[0039] Description of reference numerals:

[0040] Lifting hydraulic cylinder 1, pulley block 2, track 3, heavy hinge 4, transmission chain 5, sandblasting actuator 6, electronic control system 7, hydraulic station 8, high-pressure diverter 9, sand adding device 10, high-pressure plunger pump 11, water supply system 12, sandblasting assembly 6-1, small multi-stage hydraulic cylinder 6-2, rotating arm 6-3, supporting frame 6-4, driving sprocket 6-5, caster 6-6, sprocket drive hydraulic motor 6-7, servo motor 6-8, bearing 6-9, caster shaft 6-10, porous nozzle 6-1-1, carbide protective cap 6-1-2, transmission screw 6-1-3, limit bearing 6-1-4, guard plate connecting bolt 6-1-5, guard plate 6-1-6, driving gear 6-1-7, gear drive hydraulic motor 6-1-8, rotating water tail 6-1-9, driven gear 6-1-10.

[0041] It should be noted that the drawings are used to illustrate the present invention, rather than to limit the present invention. Note that the drawings showing the structures may not be drawn to scale. In addition, in the drawings, the same or similar elements are marked with the same or similar reference numerals. DETAILED DESCRIPTION

[0042] In order to make the contents of the present invention clearer and easier to understand, the contents of the present invention are described in detail below in conjunction with specific embodiments and drawings.

[0043] Reference Figure 1 , Figure 7 , Figure 8 The hydraulic sandblasting rock drilling system according to the preferred embodiment of the present invention includes: two lifting hydraulic cylinders 1, a pulley block 2, a track 3, a heavy hinge 4, a transmission chain 5, a sandblasting actuator 6, an electronic control system 7, a hydraulic station 8, a high-pressure diverter 9, a sand adding device 10, a high-pressure plunger pump 11, and a water supply system 12.

[0044] Among them, the pulley block 2 is installed at both ends of the track 3, and the transmission chain 5 forms a closed-loop transmission through the pulley block 2 and the driving sprocket 6-5.

[0045] The lifting hydraulic cylinder 1 is a multi-stage hydraulic cylinder, which is used in limited spaces such as underground mines, and can obtain a large stroke while shortening the overall dimensions.

[0046] Two lifting hydraulic cylinders 1 are arranged in parallel, and the main shaft of each lifting hydraulic cylinder 1 is hinged to a heavy hinge 4, and the heavy hinge 4 is placed in the hollow groove 3-2 of the track 3, and the hollow groove 3-2 on the track 3 limits the running direction of the heavy hinge 4 to the up and down movement direction.

[0047] The sandblasting actuator 6 is arranged on the rail 3 , so that the rail 3 provides a running track for the sandblasting actuator 6 .

[0048] The hydraulic station 8 controls the lifting of the lifting hydraulic cylinder 1 to drive the track 3 to move up and down, and then drive the sandblasting actuator 6 to move up and down, so as to perform blasthole drilling at different heights; at the same time, the sandblasting actuator 6 can move left and right on the track 3, so as to perform blasthole drilling at different positions in the left and right directions.

[0049] The hydraulic station 8 controls the extension and retraction of the small multi-stage hydraulic cylinder 6-2 in the sandblasting actuator 6, thereby driving the extension and retraction of the sandblasting assembly 6-1, further expanding the operating range of the sandblasting assembly 6-1.

[0050] The electronic control system 7 is used to control the start and stop of the hydraulic station 8 and the high-pressure plunger pump 11, and at the same time control the rotation working parameters of the servo motor 6-8 in the sandblasting actuator 6 (for example, the working parameters include parameters such as rotation angle, rotation direction, and rotation speed). The servo motor 6-8 drives the rotating arm 6-3 to move, thereby changing the angle of the sandblasting component 6-1 and expanding the operating range.

[0051] The water supply system 12 is used to provide sand-free water to the high-pressure plunger pump 11. The high-pressure plunger pump 11 pressurizes the water to a predetermined value and then transports it to the sand adding device 10. The sand adding device 10 adds cutting sand to the high-pressure water in proportion to form a two-phase mixed liquid. The two-phase mixed liquid is then transported to the porous nozzle 6-1-1 in the sandblasting assembly 6-1 to form multiple high-speed sand-containing water flows to erode and crush the rock wall.

[0052] Therefore, the present invention breaks rocks through the powerful erosion ability of hydraulic sandblasting, has high operating efficiency, and can accurately change the position of the sandblasting pipe through hydraulic and electric control, so as to open a plurality of blastholes with a certain diameter and depth on the rock wall, providing a basis for the subsequent installation of explosives for blasting; its beneficial effects are: the whole system has a high degree of automation and does not require excessive human intervention; the sandblasting nozzle runs smoothly, the speed is accurately controllable, the inner wall of the blasthole is regular without obvious depressions or protrusions, which is conducive to the subsequent loading of explosives; it is preset with an overload protection function, and the system has a large redundancy.

[0053] In a specific embodiment, the sandblasting actuator 6 includes a sandblasting assembly 6-1, a small multi-stage hydraulic cylinder 6-2, a rotating arm 6-3, a support frame 6-4, a driving sprocket 6-5, a caster 6-6, a sprocket-driven hydraulic motor 6-7, a servo motor 6-8, a bearing 6-9, and a caster shaft 6-10; wherein two small multi-stage hydraulic cylinders 6-2 are respectively arranged on opposite sides of the rotating arm 6-3, the sandblasting assembly 6-1 is arranged at the end of the small multi-stage hydraulic cylinder 6-2, the support frame 6-4 supports the rotating arm 6-3, and the driving sprocket 6-5 and the caster 6-6 are arranged on the support frame 6-4.

[0054] The sandblasting assembly 6-1 includes a porous nozzle 6-1-1, a carbide protective cap 6-1-2, a transmission screw 6-1-3, a limit bearing 6-1-4, a guard plate connecting bolt 6-1-5, a guard plate 6-1-6, a driving gear 6-1-7, a gear-driven hydraulic motor 6-1-8, a rotating water tail 6-1-9, and a driven gear 6-1-10; wherein the porous nozzle 6-1-1 protected by the carbide protective cap 6-1-2 is arranged at the end of the transmission screw 6-1-3, the driving gear 6-1-7 is driven by the gear-driven hydraulic motor 6-1-8, the guard plate 6-1-6 is connected to the limit bearing 6-1-4 through the guard plate connecting bolt 6-1-5, the rotating water tail 6-1-9 is arranged at the tail of the transmission screw 6-1-3, and the driving gear 6-1-7 and the driven gear 6-1-10 are used to install the transmission screw 6-1-3.

[0055] During the erosion process, the gear-driven hydraulic motor 6-1-8 in the sandblasting assembly 6-1 rotates at a preset speed, driving the driving gear 6-1-7 to rotate, and through meshing transmission, driving the driven gear 6-1-10 to rotate. The driven gear 6-1-10 is meshed with the transmission screw 6-1-3 through a trapezoidal thread, thereby converting the rotational motion of the driven gear 6-1-10 into a linear translational motion of the transmission screw 6-1-3, driving the porous nozzle 6-1-1 to gradually enter the blasthole eroded on the rock wall. The porous nozzle 6-1-1 continues to enter until the preset drilling depth is reached; the function of the rotating water tail 6-1-9 is to shield the rotational motion of the transmission screw 6-1-3 inside it, so that it can be connected to the water-sand conveying pipe A4.

[0056] (1) Specific embodiment of drilling a blasthole below a track

[0057] Reference Figure 1-Figure 3 as well as Figure 5-Figure 9 The high-pressure plunger pump 11 is connected to the water supply system 12 through a low-pressure water pipe A1, the high-pressure plunger pump 11 is connected to the sand adding device 10 through a high-pressure hose A2, the sand adding device 10 is connected to the high-pressure diverter 9 through a high-pressure hose A3, the high-pressure diverter 9 divides the high-pressure sand-containing water flow into two streams, and is connected to the rotating water tail 6-1-9 in the sandblasting actuator 6 through a high-pressure hose A4.

[0058] The lifting hydraulic cylinder 1 is connected to the hydraulic station 8 through hydraulic hoses B6 and B7 respectively, the small multi-stage hydraulic cylinder 6-2 in the sandblasting actuator 6 is connected to the hydraulic station 8 through hydraulic hoses B2 and B4 respectively, the sprocket drive hydraulic motor 6-7 is connected to the hydraulic station 8 through the hydraulic hose B5, and the gear drive hydraulic motor 6-1-8 in the sandblasting component 6-1 is connected to the hydraulic station 8 through hydraulic hoses B1 and B3 respectively.

[0059] The servo motors 6 - 8 in the sandblasting actuator 6 are connected to the electronic control system 7 via the shielded cable C1 , and the hydraulic station 8 and the high-pressure plunger pump 11 are connected to the electronic control system 7 via power cables C2 and C3 , respectively.

[0060] When drilling the blasthole below the track 3, the main shaft of the lifting hydraulic cylinder 1 is fully retracted, the electronic control system 7 is turned on, and the servo motor 6-8 is driven to rotate to a preset angle and then stop, that is, the rotating arm 6-3 reaches the preset position, and then the hydraulic station 8 is turned on, the main shaft of the driving multi-stage hydraulic cylinder 6-2 is extended, and then the sandblasting component 6-1 is driven to extend to the preset position. If the position is not accurate, the sprocket drive hydraulic motor 6-7 is turned on to drive the active sprocket 6-5 to rotate, and the position of the sandblasting actuator 6 is adjusted through the closed loop composed of the track 3, the pulley block 2 and the transmission chain 5 until the sandblasting component 6-1 is adjusted to the precise drilling position; then the high-pressure plunger pump 11 is turned on to pressurize the clean water transported in the water supply system 12 and pump it into the sand adding device 10, and the sand adding device 10 is driven according to the pressure. The cutting sand is added to the high-pressure water in a certain proportion to form a two-phase mixed liquid, and then the two-phase mixed liquid is transported to the porous nozzle 6-1-1 in the sandblasting component 6-1 to form multiple high-speed sand-containing water flows to erode and break the rock wall; after a period of fixed-point erosion, a shallow hole that meets the diameter requirements is formed on the rock wall, and then the gear-driven hydraulic motor 6-1-8 is turned on to drive the driving gear 6-1-7 to rotate, and then the driven gear 6-1-10 is driven to rotate. Under the action of the trapezoidal thread transmission, the transmission screw 6-1-3 slowly enters the previously formed shallow hole, and gradually excavates a blasthole with a certain depth on the rock wall; when the transmission screw 6-1-3 drives the porous nozzle 6-1-1 to continue to move forward in the blasthole, the returning high-speed water flow will cause damage to the porous nozzle 6-1-1. Therefore, the porous nozzle 6-1-1 is installed in the carbide protective cap 6-1-2 for protection.

[0061] If the multi-hole nozzle 6-1-1 moves forward too fast and hits the bottom of the blasthole, the thrust will be fed back to the meshing point between the transmission screw 6-1-3 and the driven gear 6-1-10, which will increase the rotation resistance of the driving gear 6-1-7 and the gear-driven hydraulic motor 6-1-8, that is, the driving pressure of the gear-driven hydraulic motor 6-1-8 increases, and the pressure is obtained by the hydraulic station 8. At this time, the hydraulic station 8 controls the gear-driven hydraulic motor 6-1-8 to stop rotating, thereby stopping the multi-hole nozzle 6-1-1 from moving forward. At this time, the working state of the multi-hole nozzle 6-1-1 is "point erosion". When the depth of the blasthole deepens, the gear hydraulic motor 6-1-8 is turned on to continue to drive the multi-hole nozzle 6-1-1 to the preset depth. After the blasthole is excavated, the gear-driven hydraulic motor 6-1-8 is driven in the reverse direction, and the transmission screw 6-1-3 pulls the multi-hole nozzle 6-1-1 out of the blasthole and restores it to its original state.

[0062] Subsequently, the electronic control system 7 is restarted to drive the servo motor 6-8 to rotate until the angle is changed and then stop, that is, the rotating arm 6-3 reaches the preset position, and then the hydraulic station 8 is turned on to extend the main shaft of the driven multi-stage hydraulic cylinder 6-2, thereby driving the sandblasting component 6-1 to extend to the next preset position. If the position is not accurate, the sprocket drive hydraulic motor 6-7 can also be turned on to drive the active sprocket 6-5 to rotate, and the position of the sandblasting actuator 6 is adjusted through the closed loop composed of the track 3, the pulley block 2 and the transmission chain 5 until the sandblasting component 6-1 is adjusted to the next excavation position.

[0063] (2) Specific embodiment when drilling blastholes above the track

[0064] Reference Figure 1 , Figure 4-Figure 9 The high-pressure plunger pump 11 is connected to the water supply system 12 through a low-pressure water pipe A1, the high-pressure plunger pump 11 is connected to the sand adding device 10 through a high-pressure hose A2, the sand adding device 10 is connected to the high-pressure diverter 9 through a high-pressure hose A3, the high-pressure diverter 9 divides the high-pressure sand-containing water flow into two streams, and is connected to the rotating water tail 6-1-9 in the sandblasting actuator 6 through a high-pressure hose A4.

[0065] The lifting hydraulic cylinder 1 is connected to the hydraulic station 8 through hydraulic hoses B6 and B7 respectively, the small multi-stage hydraulic cylinder 6-2 in the sandblasting actuator 6 is connected to the hydraulic station 8 through hydraulic hoses B2 and B4 respectively, the sprocket drive hydraulic motor 6-7 is connected to the hydraulic station 8 through hydraulic hose B5, and the gear drive hydraulic motor 6-1-8 in the sandblasting assembly 6-1 is connected to the hydraulic station 8 through hydraulic hoses B1 and B3 respectively;

[0066] The servo motors 6 - 8 in the sandblasting actuator 6 are connected to the electronic control system 7 via the shielded cable C1 , and the hydraulic station 8 and the high-pressure plunger pump 11 are connected to the electronic control system 7 via power cables C2 and C3 , respectively.

[0067] When drilling the blasthole above the track 3, the hydraulic station 8 is turned on to control the extension of the main shaft of the lifting hydraulic cylinder 1. It should be noted that the extension distance of the main shafts of the two lifting hydraulic cylinders 1 can be the same or different; the electronic control system 7 is turned on to drive the servo motor 6-8 to rotate to a preset angle and then stop, that is, the rotating arm 6-3 reaches the preset position, and then the main shaft of the driving multi-stage hydraulic cylinder 6-2 is extended, thereby driving the sandblasting component 6-1 to extend to the preset position. If the position is not accurate, the sprocket drive hydraulic motor 6-7 is turned on to drive the active sprocket 6-5 to rotate, and the closed loop composed of the track 3, the pulley block 2 and the transmission chain 5 is turned on. The position of the sandblasting actuator 6 is adjusted by a ring until the sandblasting component 6-1 is adjusted to the precise excavation position; then the high-pressure plunger pump 11 is turned on to pressurize the clean water transported from the water supply system 12 and pump it into the sand adding device 10, and the sand adding device 10 adds the cutting sand to the high-pressure water in proportion to form a two-phase mixed liquid, which is then transported to the multi-hole nozzle 6-1-1 in the sandblasting component 6-1 to form multiple high-speed sand-containing water flows to erode and break the rock wall; after a period of fixed-point erosion, a shallow hole that meets the diameter requirements is formed on the rock wall, and then the gear-driven hydraulic motor 6-1-8 is turned on to drive the main The driving gear 6-1-7 rotates, thereby driving the driven gear 6-1-10 to rotate. Under the action of the trapezoidal thread transmission, the driving screw 6-1-3 slowly enters the previously formed shallow hole, and gradually excavates a blasthole with a certain depth on the rock wall; when the driving screw 6-1-3 drives the porous nozzle 6-1-1 to continue to advance in the blasthole, the returning high-speed water flow will cause damage to the porous nozzle 6-1-1. Therefore, the porous nozzle 6-1-1 is installed in the carbide protective cap 6-1-2 for protection; if the porous nozzle 6-1-1 advances too fast and presses against the bottom of the blasthole, the thrust will be fed back to the driving screw The meshing point between the gear 6-1-3 and the driven gear 6-1-10 leads to an increase in the rotational resistance of the driving gear 6-1-7 and the gear-driven hydraulic motor 6-1-8, that is, the driving pressure of the gear-driven hydraulic motor 6-1-8 increases, and the pressure is obtained by the hydraulic station 8. At this time, the hydraulic station 8 controls the gear-driven hydraulic motor 6-1-8 to stop rotating, thereby stopping the multi-hole nozzle 6-1-1 from moving forward. At this time, the working state of the multi-hole nozzle 6-1-1 is "point erosion". When the depth of the blasthole deepens, the gear hydraulic motor 6-1-8 is turned on to continue to drive the multi-hole nozzle 6-1-1 to the preset depth. After the blasthole is excavated, the gear-driven hydraulic motor 6-1-8 is driven in the reverse direction, and the transmission screw 6-1-3 pulls the multi-hole nozzle 6-1-1 out of the blasthole and restores it to its original state.

[0068] Subsequently, the electronic control system 7 is restarted to drive the servo motor 6-8 to rotate until the angle is changed and then stop, that is, the rotating arm 6-3 reaches the preset position, and then the hydraulic station 8 is turned on to extend the main shaft of the driven multi-stage hydraulic cylinder 6-2, thereby driving the sandblasting component 6-1 to extend to the next preset position. If the position is not accurate, the sprocket drive hydraulic motor 6-7 can also be turned on to drive the active sprocket 6-5 to rotate, and the position of the sandblasting actuator 6 is adjusted through the closed loop composed of the track 3, the pulley block 2 and the transmission chain 5 until the sandblasting component 6-1 is adjusted to the next excavation position.

[0069] The beneficial effects of the present invention include at least the following:

[0070] (1) The overall system has a high degree of automation and does not require excessive human intervention;

[0071] (2) The powerful erosion ability of hydraulic sandblasting is used to drill blastholes, which has high operating efficiency;

[0072] (3) The sandblasting nozzle runs smoothly, the speed is precisely controllable, and the inner wall of the blasthole is regular without obvious depressions or protrusions, which is conducive to the subsequent loading of explosives;

[0073] (4) It has a preset overload protection function and a high degree of system redundancy.

[0074] It should be noted that, unless otherwise specified, the terms "first", "second", "third", etc. in the specification are only used to distinguish the various components, elements, steps, etc. in the specification, and are not used to indicate the logical relationship or sequential relationship between the various components, elements, steps, etc.

[0075] It is to be understood that, although the present invention has been disclosed as a preferred embodiment, the above embodiment is not intended to limit the present invention. For any person skilled in the art, without departing from the scope of the technical solution of the present invention, the technical content disclosed above can be used to make many possible changes and modifications to the technical solution of the present invention, or modified into equivalent embodiments of equivalent changes. Therefore, any simple modification, equivalent change and modification made to the above embodiments according to the technical essence of the present invention without departing from the content of the technical solution of the present invention still falls within the scope of protection of the technical solution of the present invention.

Claims

1. A hydraulic sandblasting rock drilling system, characterized in that: include: Two lifting hydraulic cylinders, pulley blocks, tracks, heavy-duty hinges, transmission chains, sandblasting actuators, electronic control systems, hydraulic stations, high-pressure diverters, sand-feeding devices, high-pressure plunger pumps, and water supply systems; the pulley blocks are installed at both ends of the track, and the transmission chain forms a closed-loop transmission through the pulley blocks and the active sprocket; the two lifting hydraulic cylinders are arranged in parallel, and the main shaft of each lifting hydraulic cylinder is hinged to a heavy-duty hinge, and the heavy-duty hinge is placed in the hollow groove of the track, and the hollow groove on the track limits the running direction of the heavy-duty hinge to the up and down movement direction; the sandblasting actuator is arranged on the track, so that the track provides a running track for the sandblasting actuator; the hydraulic station controls the lifting and lowering of the lifting hydraulic cylinder to drive the lifting and lowering of the track, and then drives the lifting and lowering of the sandblasting actuator, so as to carry out operations at different heights. Blast hole drilling; the sandblasting actuator can move left and right on the track so as to perform blast hole drilling at different positions in the left and right directions; the hydraulic station controls the extension and retraction of the small multi-stage hydraulic cylinder in the sandblasting actuator, thereby driving the extension and retraction of the sandblasting assembly; the electronic control system is used to control the start and stop of the hydraulic station and the high-pressure plunger pump, and control the rotation working parameters of the servo motor in the sandblasting actuator, and the servo motor drives the rotating arm to move, thereby changing the angle of the sandblasting assembly; the water supply system is used to provide sand-free water to the high-pressure plunger pump, and the high-pressure plunger pump pressurizes the water to a predetermined value and then transports it to the sand adding device, which adds cutting sand to the high-pressure water in proportion to form a two-phase mixed liquid, and then transports the two-phase mixed liquid to the porous nozzle in the sandblasting assembly to form a sand-containing water flow.

2. The hydraulic sandblasting rock drilling system according to claim 1, characterized in that: The lifting hydraulic cylinder is a multi-stage hydraulic cylinder.

3. The hydraulic sandblasting rock drilling system according to claim 1 or 2, characterized in that: The sandblasting actuator includes a sandblasting assembly, a small multi-stage hydraulic cylinder, a rotating arm, a supporting frame, a driving sprocket, a caster, a sprocket-driven hydraulic motor, a servo motor, a bearing, and a caster shaft; wherein two small multi-stage hydraulic cylinders are arranged on opposite sides of the rotating arm, respectively, the sandblasting assembly is arranged at the end of the small multi-stage hydraulic cylinder, the supporting frame supports the rotating arm, and the driving sprocket and the caster are arranged on the supporting frame; the sandblasting assembly includes a porous nozzle, a carbide protective cap, a transmission screw, a limit bearing, a guard plate connecting bolt, a guard plate, a driving gear, a gear-driven hydraulic motor, a rotating water tail, and a driven gear; wherein the porous nozzle protected by the carbide protective cap is arranged at the end of the transmission screw, the driving gear is driven by the gear-driven hydraulic motor, the guard plate is connected to the limit bearing through the guard plate connecting bolt, the rotating water tail is arranged at the tail of the transmission screw, and the driving gear and the driven gear are used to install the transmission screw.

4. The hydraulic sandblasting rock drilling system according to claim 1 or 2, characterized in that: During the erosion process, the gear-driven hydraulic motor in the sandblasting assembly rotates at a preset speed, driving the driving gear to rotate, and through meshing transmission, driving the driven gear to rotate. The driven gear is meshed with the transmission screw through a trapezoidal thread, thereby converting the rotational motion of the driven gear into a linear translational motion of the transmission screw, driving the porous nozzle to gradually enter the blasthole eroded on the rock wall. The porous nozzle continues to enter until the preset drilling depth is reached; the rotating water tail is used to shield the rotational motion of the transmission screw inside it, thereby connecting it to the water-sand delivery pipe.

5. The hydraulic sandblasting rock drilling system according to claim 1 or 2, characterized in that: The high-pressure plunger pump is connected to the water supply system through a low-pressure water pipe, the high-pressure plunger pump is connected to the sand adding device through a high-pressure hose, the sand adding device is connected to the high-pressure diverter through a high-pressure hose, the high-pressure diverter divides the high-pressure sand-containing water flow into two streams, and is connected to the rotating water tail in the sandblasting actuator through a high-pressure hose.

6. The hydraulic sandblasting rock drilling system according to claim 1 or 2, characterized in that: The lifting hydraulic cylinder is connected to the hydraulic station through hydraulic hoses, the small multi-stage hydraulic cylinders in the sandblasting actuator are connected to the hydraulic station through hydraulic hoses, the sprocket-driven hydraulic motor is connected to the hydraulic station through hydraulic hoses, and the gear-driven hydraulic motor in the sandblasting assembly is connected to the hydraulic station through hydraulic hoses.

7. The hydraulic sandblasting rock drilling system according to claim 1 or 2, characterized in that: The servo motor in the sandblasting actuator is connected to the electronic control system through a shielded cable, and the hydraulic station and the high-pressure plunger pump are connected to the electronic control system through power cables respectively.

8. The method for using the hydraulic sandblasting rock drilling system according to claim 1 or 2, characterized in that: The hydraulic sandblasting rock drilling system is used to perform blasthole drilling below the track and blasthole drilling above the track.

9. The method of use according to claim 8, characterized in that: Performing blasthole drilling below track includes: The main shaft of the lifting hydraulic cylinder is fully retracted, the electronic control system is turned on, the servo motor is driven to rotate to the preset angle and then stopped to allow the rotating arm to reach the preset position, and then the hydraulic station is turned on to extend the main shaft of the driving multi-stage hydraulic cylinder, thereby driving the sandblasting component to extend to the preset position. If the position is not accurate, the sprocket drive hydraulic motor is turned on to drive the active sprocket to rotate, and the position of the sandblasting actuator is adjusted through the closed loop composed of the track, pulley block and transmission chain until the sandblasting component is adjusted to the precise excavation position; Then, the high-pressure plunger pump is turned on to pressurize the clean water delivered by the water supply system and pump it into the sand adding device. The sand adding device adds the cutting sand into the high-pressure water in proportion to form a two-phase mixed liquid. The two-phase mixed liquid is then transported to the porous nozzle in the sand blasting component to form multiple high-speed sand-containing water flows to erode and crush the rock wall. After a shallow hole that meets the diameter requirements is formed on the rock wall, the gear-driven hydraulic motor is turned on to drive the active gear to rotate, which in turn drives the driven gear to rotate. Under the action of the trapezoidal thread transmission, the transmission screw slowly enters the previously formed shallow hole.

10. The method of use according to claim 8 or 9, characterized in that: Performing above-rail blasthole drilling includes: Turn on the hydraulic station to control the main shaft of the lifting hydraulic cylinder to extend; turn on the electronic control system, drive the servo motor to rotate to the preset angle and then stop to make the rotating arm reach the preset position, then drive the main shaft of the multi-stage hydraulic cylinder to extend, and then drive the sandblasting component to extend to the preset position. If the position is not accurate, turn on the sprocket drive hydraulic motor to drive the active sprocket to rotate, and adjust the position of the sandblasting actuator through the closed loop composed of the track, pulley block and transmission chain until the sandblasting component is adjusted to the precise excavation position; Then, the high-pressure plunger pump is turned on to pressurize the clean water delivered by the water supply system and pump it into the sand adding device. The sand adding device adds the cutting sand into the high-pressure water in proportion to form a two-phase mixed liquid. The two-phase mixed liquid is then transported to the porous nozzle in the sand blasting component to form multiple high-speed sand-containing water flows to erode and crush the rock wall. After a shallow hole that meets the diameter requirements is formed on the rock wall, the gear-driven hydraulic motor is turned on to drive the active gear to rotate, which in turn drives the driven gear to rotate. Under the action of the trapezoidal thread transmission, the transmission screw slowly enters the previously formed shallow hole.