Method for in-situ conversion exploitation of fossil energy and utilization and development of geological sequestration waste heat

Through the combined use of CO2 and O2, in-situ mining of immature/medium-low mature hydrocarbon source rocks and formation waste heat recovery are realized. Combined with the geological storage of CO2 and H2, the problems of formation waste heat utilization and environmental damage in the existing technology are solved. Efficient and clean fossil energy extraction and greenhouse gas storage have been achieved.

CN118774698APending Publication Date: 2024-10-15JILIN UNIVERSITY
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410924246.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-11
Publication Date
2024-10-15

AI Technical Summary

Technical Problem

The existing technology fails to effectively utilize the waste heat of the formation and achieve geological storage of CO2 after in-situ mining of immature/medium-low mature source rocks, and hydraulic fracturing causes damage to the environment, making it difficult to achieve green, efficient, and clean mining.

Method used

Two gases, CO2 and O2, are used to reform the reservoir through supercritical CO2 fracturing. The preheated O2 is used to trigger the formation's autogenous thermal reaction to achieve oil and gas extraction and CO2 enrichment. After the extraction is completed, CO2 and H2 are used for geological storage. Reduce environmental impact.

Benefits of technology

It achieves green, efficient and clean mining of fossil energy, reduces the environmental damage caused by hydraulic fracturing, improves mining efficiency, and reduces greenhouse gas emissions through CO2 geological storage.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118774698A_ABST
    Figure CN118774698A_ABST
Patent Text Reader

Abstract

A fossil energy in-situ conversion exploitation and geological sequestration waste heat utilization development method belongs to the technical field of fossil energy in-situ exploitation and comprises an underground fossil resource in-situ pyrolysis stage, a stratum waste heat recycling stage and a geological sequestration stage. According to the method, only CO2 and O2 are used in the implementation process, supercritical CO2 is used for fracturing the stratum in the reservoir transformation stage, preheated O2 is used for heating the stratum and triggering the self-heat-generation reaction of the stratum in the in-situ conversion stage, and therefore CO2 is enriched in the underground in-situ conversion process, in addition, CO2 is used for recycling stratum waste heat, and the utilization rate of CO2 is increased. By means of the method, green, efficient and clean mining of immature / medium-low mature hydrocarbon source rock resources is achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of in-situ mining of fossil energy, and in particular relates to an integrated process of in-situ conversion and mining of fossil energy - formation waste heat utilization - geological sealing. Background Art

[0002] Source rock is a fossil energy source rich in organic matter, which has been generated and discharged or is being discharged in geological history. Immature / medium-low mature source rock refers to an unconventional energy source with low organic matter maturity, which needs to be converted into oil and gas resources by heating and other methods. Among them, oil shale is a typical immature source rock. The main surface distillation technology currently used is to mine oil shale to the ground, heat it to about 550°C with hot gas / hot solid above 700°C under oxygen isolation conditions, so that the internal kerogen decomposes to generate oil shale oil. In view of the characteristics of my country's oil shale resources such as deep burial, thin thickness, low oil content and environmental protection requirements, in-situ conversion mining technology is considered to be an effective way to achieve the coordinated development of oil shale resource exploitation and environmental protection. In addition, in-situ conversion is also a feasible technology for the industrial development of medium-low mature shale oil and oil-rich coal.

[0003] Among the existing in-situ conversion technologies, chemical heating technology has attracted much attention because of its energy saving. A method for extracting shale oil and gas by in-situ local chemical method of oil shale (reference patent CN103790563B) proposes to heat the oxygen-containing gas and hydrocarbon gas recovered from the production well and then mix them and inject them into the production well, forming a local chemical reaction in the oil shale layer, inducing a local chain reaction to achieve thermal cracking of the oil shale and produce oil and gas. The development method of self-heating in-situ conversion of low-mature organic-rich shale (CN114017032A) proposes to inject hot air into the ground to preheat the formation locally, and then inject air at room temperature to trigger the self-heating reaction of organic matter, so as to achieve the purpose of convective heating of low-mature organic-rich shale formations. However, the above technology only recovers oil and gas resources from organic components in the formation, and does not propose a secondary utilization idea or method for the waste heat and geological body of the formation after in-situ conversion.

[0004] In the in-situ mining of immature / medium-low mature source rocks, the reservoir generally needs to be heated to above 300°C. Therefore, after the oil and gas mining is completed, the formation still maintains a high temperature. After the mining is completed, due to the discharge of organic matter, the underground rock mass will retain a large number of pores and cracks, which can provide space for the storage of CO2, H2, etc., and the upper and lower roofs and floors of the source rock reservoir are generally mudstone and other rock formations with poor permeability, which have the characteristics of caprocks. Therefore, the recovery of waste heat from the formation after the in-situ mining of immature / medium-low mature source rocks and the geological storage of CO2, H2, etc. are not only conducive to achieving the dual carbon goals, but also can further improve the industrial mining value of immature / medium-low mature source rocks.

[0005] The method of recycling CO2 to mine organic-rich shale with residual heat after in-situ conversion (CN117366890A) proposes a method of using CO2 to recover the residual heat of the formation after mining for preheating the next well group, but the patent does not involve in-situ mining methods and secondary utilization methods of formations.

[0006] In addition, for the in-situ mining of fossil energy such as immature / medium-low mature source rocks, reservoir transformation is a key technical link. However, due to the dense reservoirs and high clay content of such source rocks and the high requirements of the fracture system for in-situ mining, conventional hydraulic fracturing cannot achieve the expected results and is prone to cause great damage to the environment. Therefore, a new technology that uses less water (or no water), does not pollute the environment, does little damage to the reservoir, and has rapid flowback is urgently needed.

[0007] Therefore, the prior art urgently needs a new technical solution to solve the above problems. Summary of the invention

[0008] The technical problem to be solved by the present invention is: to provide a method for in-situ conversion and exploitation of fossil energy and utilization of waste heat from geological storage. During the implementation of this method, only two gases, CO2 and O2, are used. Supercritical CO2 is used to fracture the formation in the reservoir transformation stage. Preheated O2 is used to heat the formation and trigger the autothermal reaction of the formation in the in-situ conversion stage, thereby enriching CO2 during the underground in-situ conversion process. In addition, CO2 is used to recover the waste heat of the formation and realize the geological storage of CO2. This method realizes the green, efficient and clean exploitation of immature / medium and low mature hydrocarbon source rock resources.

[0009] In-situ conversion and exploitation of fossil energy and utilization of waste heat from geological storage, including the in-situ pyrolysis stage of underground fossil resources, the recovery and utilization stage of stratum waste heat, and the geological storage stage;

[0010] The specific steps include:

[0011] Step 1: Arrange heating wells and production wells according to the distribution and trend of the target reservoir in the mining area, perform supercritical CO2 fracturing on the target reservoir, and form a fracturing area in the target reservoir;

[0012] Step 2: Install a downhole heater in the heating well, inject oxygen into the well, and after being preheated by the downhole heater, the oxygen flows into the target reservoir to heat the kerogen in the target layer. A portion of the oil and gas reacts with the oxygen to generate CO2 and release heat at the same time. The generated oil and gas are discharged to the ground through the production well. The collected gas is separated into CO2 gas flow through the ground separation system and stored in the CO2 storage tank, and then injected back into the underground target production rock formation through the heating well. This cycle continues until the thermal cracking reaction of the target reservoir is completed, and a residual skeleton porous formation with high formation temperature, developed pores and fissures, and rich in a large number of alkaline minerals is formed in the target reaction zone;

[0013] Step 3: Take out the downhole heater inside the heating well, and use a pressurized injection device to inject the CO2 generated during the in-situ mining process and the CO2 generated by industrial production into the porous stratum of the residual skeleton through the heating well. After the gas flows through the underground high-temperature rock formation, the heated CO2 gas returns to the surface through the mining well and is recycled for heat utilization;

[0014] Step 4: When the temperature of the recovered gas in the stratum is low, the geological storage stage begins.

[0015] The geological storage phase described in step 4 includes CO2 and H2 geological storage.

[0016] The steps of CO2 geological storage include:

[0017] S1. Inject water and waste liquid generated during the in-situ mining of source rocks into the formation, so that the injected CO2, water, waste liquid and the formation residue after pyrolysis of the source rocks fully react to generate mineral precipitation;

[0018] S2. After reinjecting cementing slurry into the production well to seal the well, continue to inject CO2 into the ground until saturation is reached, and then seal the heating well;

[0019] The steps for H2 geological storage include:

[0020] S1. Close the production well, inject industrially produced H2 into the formation using a pressurized injection device, and monitor the concentration and pressure of underground hydrogen in real time through the production well. When the underground hydrogen pressure reaches 80% of the hydrogen storage design pressure, close the heating well and perform well soaking operation to allow the injected hydrogen to fully diffuse into the micro-cracks and matrix pores, so that the formation pressure between the heating well and the production well is balanced;

[0021] S2. Continue to inject H2 into the ground until the design pressure is reached, and then close the heating well;

[0022] S3. When hydrogen is needed, open the heating well or production well to extract H2; according to the working conditions, select H2 containing hydrocarbon gas, or use purification technology to obtain high-purity H2.

[0023] The underground fossil resource in-situ pyrolysis stage includes underground in-situ pyrolysis of oil shale and underground in-situ pyrolysis of low- and medium-maturity shale oil.

[0024] The heating well is arranged vertically or horizontally, and the number of the heating well and the production well is more than one.

[0025] The method for supercritical CO2 fracturing of the target formation is: fracturing the oil shale formation using supercritical CO2 carrying a proppant.

[0026] The gas temperature is relatively low, being below 60°C.

[0027] The downhole heater preheats the injected underground gas at the initial stage of exploitation. When the cracking reaction in the underground target rock formation is triggered, the heater is turned off and normal temperature gas is injected into the target reservoir. Whether the heater is turned on is determined by the composition of the gas produced by the exploitation well.

[0028] Through the above design scheme, the present invention can bring the following beneficial effects:

[0029] 1. The present invention exploits and utilizes fossil energy such as immature / medium-low mature source rocks through in-situ cracking, and uses CO2 gas to recycle the residual heat of the formation and realize the geological storage of CO2, thus realizing an innovative comprehensive utilization technology system integrating in-situ exploitation of petroleum gas resources, residual heat recovery, and CO2 / H2 geological storage. There is no need for large-scale underground mining of fossil energy, and the disturbance to the geological body of the mining area is small, which is environmentally friendly.

[0030] 2. The present invention only requires one set of drilling engineering to realize the in-situ recovery of fossil energy, the recovery and utilization of formation waste heat, and the geological storage of CO2 / H2 gas. No new drilling is required during the implementation process, which effectively reduces the implementation cost.

[0031] 3. The present invention utilizes CO2 to fracture the formation before in-situ mining, effectively reducing the damage of water-based fracturing to the formation.

[0032] 4. In the process of in-situ mining of fossil energy, the present invention injects oxygen into the system, which allows a small amount of organic matter to undergo an exothermic oxidation reaction with oxygen, providing heat for the subsequent pyrolysis of the organic matter. On the other hand, the generated CO2 is easily miscible with oil, gas, water, etc., and has the effects of reducing viscosity, improving oil-water mobility ratio, reducing interfacial tension, reducing oil density, and increasing permeability, which is conducive to improving the fluidity of oil and gas resources and their transfer efficiency in multi-scale storage spaces, and achieving the purpose of efficient oil recovery. At the same time, the present invention injects the gas products after thermal cracking of the reservoir back into the formation to participate in the thermal cracking reaction of the target rock formation, wherein the CO2 component in the reinjected gas is fixed in the underground pores during the oil and gas displacement process.

[0033] 5. After the in-situ cracking reaction is completed, the present invention utilizes the circulation of CO2 gas in the formation to realize the recovery and utilization of the residual heat of the formation.

[0034] 6. The present invention combines the in-situ mining of fossil energy, waste heat utilization and CO2 geological storage. On the one hand, CO2 is used to displace the oil and gas remaining in the formation, and on the other hand, the spatial pore structure of the formation and alkaline oxides are used to achieve geological storage of CO2, reducing the emission of greenhouse gas CO2 and improving the stability of the target rock formation after pyrolysis. BRIEF DESCRIPTION OF THE DRAWINGS

[0035] The present invention is further described below with reference to the accompanying drawings and specific embodiments:

[0036] Figure 1 It is a schematic diagram of the vertical well mining mode of the present invention.

[0037] Figure 2 This is a schematic diagram of the CO2 injection process in the geological storage stage of the present invention.

[0038] Figure 3 This is a schematic diagram of sealing the well after the geological sealing process of the present invention is completed.

[0039] Figure 4 It is a schematic diagram of the horizontal well production mode of the present invention.

[0040] Figure 5 Schematic diagram of the seven-point well pattern layout in an embodiment of the present invention.

[0041] Figure 6 This is a formation temperature distribution diagram after in-situ cracking of oil shale is completed in a seven-point well pattern with a well spacing of 30m in a specific embodiment of the present invention.

[0042] Figure 7 The porosity and permeability evolution curves of oil shale and oil shale residue after pyrolysis at different temperatures according to a specific embodiment of the present invention are shown.

[0043] 1-target reservoir; 2-heating well; 3-production well; 4-downhole heater; 5-fracturing; 6-ground separation system; 7-CO2 gas flow; 8-CO2 storage tank; 9-oxygen; 10-water; 11-waste liquid; 12-porous residual formation after reaction; 13-cementing slurry; 14-residual reservoir rich in CO2 or H2; 15-vertical and horizontal wells; 16-gas storage tank. DETAILED DESCRIPTION

[0044] Example 1: An integrated process of in-situ conversion-waste heat utilization-underground storage

[0045] The method of the present invention is divided into three stages: in-situ pyrolysis of underground resources, recovery and utilization of stratum waste heat, and geological storage.

[0046] In-situ pyrolysis exploitation of underground fossil resources includes, but is not limited to, underground in-situ pyrolysis of immature / low-mature source rocks, medium- and low-mature shale oil, oil-rich coal, etc.

[0047] The recovery and utilization of waste heat from the formation includes but is not limited to preheating the formation of the next well group, heating plastic greenhouses, heating the factory area in winter, and power generation.

[0048] The present invention first arranges at least one vertical or horizontal heating well 2 and one production well 3 according to the occurrence of underground resources, and adopts supercritical CO2 fracturing to achieve fracturing and gap creation of underground resource reservoirs and increase the fluidity of oil and gas in the reservoirs; then the injected gas is preheated by a downhole heater;

[0049] In the initial stage of the experiment, the present invention only injects pure oxygen into the ground, allowing a small amount of organic matter to undergo oxidation reaction with oxygen to provide heat for the subsequent thermal cracking of organic matter; the gas products produced during the mining process are reinjected. On the one hand, the combustible gas undergoes an oxidation exothermic reaction with the injected oxygen to provide heat for the subsequent thermal decomposition; on the other hand, the generated CO2 component plays an effective displacement role on the oil and gas products, which is beneficial to provide the fluidity of the oil and gas products;

[0050] After the in-situ cracking reaction of underground resources is completed, the present invention injects CO2 gas into the underground to realize the recovery and utilization of waste heat from the formation. According to the amount of waste heat and actual conditions, the hot gas recovered from the underground can be directly introduced into the greenhouse for heating, or a conventional waste heat recovery system on the ground can be built, or a waste heat power generation device can be built for the recovery and utilization of waste heat. When the formation temperature drops to 60°C, water and waste liquid generated in the production process are injected into the underground to form a capture and sealing system in the underground reservoir. Since the solid residue after the in-situ mining of the source rock is completed contains a large amount of alkaline minerals such as calcium oxide and magnesium oxide, it fully reacts with water and CO2 to generate insoluble solid carbonates to achieve the purpose of carbon fixation, thereby realizing the purpose of permanent underground sealing of CO2. In addition, since the source rock and the upper and lower roof and floor plates where no cracking reaction occurs have poor permeability, they can be used as natural confinement layers to ensure the safety of CO2 geological sealing.

[0051] Furthermore, the present invention can also realize geological storage of other gases that need to be stored underground, and the principle is similar to that of CO2 geological storage. Geological storage includes but is not limited to CO2 geological storage, H2 geological storage and underground energy storage.

[0052] Furthermore, the present invention can also use the solid skeleton after the in-situ mining of underground resources is completed for energy storage.

[0053] Example 2: In-situ oil shale mining and CO2 geological storage integrated process by supercritical CO2 injection

[0054] like Figure 1-3 As shown, it includes the following steps:

[0055] Step 1: Arrange a vertical heating well 2 and a production well 3 according to the distribution and direction of the target reservoir 1;

[0056] Step 2: using supercritical CO2 carrying proppant to fractur e the oil shale formation, forming a fracturing zone fracture gap 5 in the oil shale reservoir to increase the permeability of the oil shale reservoir;

[0057] Step three: Install a downhole heater 4 in the heating well 2, and introduce oxygen 9 into the injection well. After being preheated by the downhole heater 4, the room temperature oxygen 9 flows into the target reservoir 1 to heat the kerogen in the oil shale, causing it to crack and generate hydrocarbons. At the same time, a portion of the asphalt and the produced oil shale oil and gas will undergo an oxidation reaction with the oxygen to generate CO2 and release a large amount of heat. The produced oil shale oil and gas are discharged to the ground through the production well 3. The collected gas is separated into a CO2 gas flow 7 through the ground separation system 6 and reinjected into the underground oil shale layer through the heating well 2. This cycle continues until the thermal cracking reaction of the oil shale reservoir is completed; the oil shale reservoir eventually forms a post-reaction porous residual formation 12 with a high formation temperature, abundant pores and cracks developed in the formation, and rich in alkaline minerals such as calcium oxide and magnesium oxide;

[0058] Step 4: Take out the downhole heater 4 in the heating well 2, and use a pressurized injection device to inject the CO2 generated during the in-situ mining process and other industrial production into the formation 12 through the heating well 2. After the gas flows through the underground high-temperature rock formation, the heated CO2 gas returns to the surface through the production well and is recycled for heat. The CO2 gas is used to recycle the waste heat of the formation;

[0059] Step 5: When the temperature of the recovered gas in the formation is low, water 10 and waste liquid 11 generated during the in-situ mining of oil shale are injected into the formation, so that the injected CO2, water, and waste liquid react fully with the formation residue after pyrolysis of the oil shale to generate mineral precipitation, thereby achieving the purpose of carbon fixation;

[0060] Step 6: After reinjecting cementing slurry 13 into the production well to seal the well, CO2 is continuously injected into the underground until saturation is reached, and then the injection well is sealed.

[0061] The underground heater mentioned in the present invention does not need to be in working state throughout the whole process. It only needs to preheat the injected underground gas in the initial stage of mining. When the cracking reaction in the underground oil shale layer is triggered, the heater can be turned off and only normal temperature gas can be injected into the oil shale reservoir. Whether the heater needs to be turned on can be judged by the composition of the gas produced by the mining well.

[0062] The present invention only needs to inject oxygen at the initial stage of the reaction. After the cracking reaction in the underground oil shale layer is triggered, the amount of injected oxygen and the amount of reinjected gas can be adjusted according to the gas composition collected from the production well, and whether additional CO2 gas needs to be added.

[0063] Furthermore, the heating well described in this embodiment may be a vertical plus horizontal well section.

[0064] Furthermore, in this embodiment, the gas products extracted from underground in situ can be injected back into the underground oil shale reservoir through the heating well without separation, and participate in the oil shale cracking reaction until the thermal cracking reaction of the oil shale reservoir is completed.

[0065] Furthermore, the present invention can also be applied to the exploitation of medium and low-maturity shale oil resources, thereby increasing the mobilization of medium and low-maturity shale oil resources and achieving geological storage of CO2.

[0066] Example 3: Integrated process of in-situ mining of oil shale and underground hydrogen storage

[0067] like Figure 4 As shown, it includes the following steps:

[0068] Step 1: Arrange a vertical and horizontal well 15 and a production well 3 according to the distribution and trend of the target reservoir 1;

[0069] Step 2: fracturing the oil shale formation to form fractures 5 in the oil shale reservoir to increase the permeability of the oil shale reservoir;

[0070] Step three: Install a downhole heater 4 in the vertical and horizontal wells 15, and introduce oxygen 9 into the injection well. After being preheated by the downhole heater 4, the room temperature oxygen 9 flows into the oil shale reservoir 1, heating the kerogen in the oil shale to cause it to crack and generate hydrocarbons. At the same time, a portion of the asphalt and the produced oil shale oil and gas will undergo oxidation reactions with the oxygen, releasing a large amount of heat. The produced oil shale oil and gas are discharged to the ground through the production well 3. The collected gas is stabilized by the ground gas storage tank 16 and then injected back into the underground oil shale layer through the vertical and horizontal wells 15. This cycle continues until the thermal cracking reaction of the oil shale reservoir is completed; the oil shale reservoir eventually forms a porous formation with a high formation temperature, abundant pores and cracks in the formation, and a residual skeleton rich in alkaline minerals such as calcium oxide and magnesium oxide;

[0071] Step 4: Take out the downhole heater 4 in the vertical and horizontal wells 15, and use a pressurized injection device to inject the gas generated in the pyrolysis stage of the source rock into the pyrolysis formation through the vertical and horizontal wells 15 to recover the residual heat of the formation.

[0072] Step 5: When the temperature of the recovered gas in the formation is low, close the production well 3, use a pressurized injection device to inject industrially produced H2 into the formation, and monitor the concentration and pressure of underground hydrogen in real time through the production well 3. When the underground hydrogen pressure reaches 80% of the hydrogen storage design pressure, close the vertical and horizontal wells 15 and perform well soaking operations to allow the injected hydrogen to fully diffuse into the microcracks and matrix pores, so that the formation pressure between the vertical and horizontal wells 15 and the production well 3 is balanced.

[0073] Step 6: Continue to inject H2 into the ground until the design pressure is reached, and then close the vertical and horizontal wells 15.

[0074] Step 7: When hydrogen is needed, open the vertical well 15 or the production well 3 to produce H2. Depending on the working conditions, H2 containing hydrocarbon gas can be used directly, or high-purity H2 can be obtained through purification technology.

[0075] The underground heater mentioned in the present invention does not need to be in working state throughout the whole process. It only needs to preheat the injected underground gas in the initial stage of mining. When the cracking reaction in the underground oil shale layer is triggered, the heater can be turned off and only normal temperature gas can be injected into the oil shale reservoir. Whether the heater needs to be turned on can be judged by the composition of the gas produced by the mining well.

[0076] Furthermore, the heating well in this embodiment may be a vertical well.

[0077] Furthermore, in this embodiment, the hydrogen storage link can cyclically and repeatedly inject and produce H2.

[0078] Furthermore, in step five, when the underground hydrogen concentration reaches 80%, the cementing slurry 13 can be reinjected into the production well 3 to seal the well, and then H2 is continuously injected until the hydrogen storage design pressure is reached, and then the injection well 15 is closed.

[0079] The gas products extracted from underground in situ can be reinjected into the underground oil shale reservoir through the heating well without separation, and participate in the oil shale cracking reaction until the thermal cracking reaction of the oil shale reservoir is completed.

[0080] Furthermore, the present invention can also be applied to the exploitation of medium and low-maturity shale oil resources, thereby increasing the mobilization of medium and low-maturity shale oil resources and realizing the geological storage of CO2, H2, etc.

[0081] Example 4: Integrated process of in-situ mining of oil shale, waste heat utilization and CO2 geological storage using a seven-spot well pattern

[0082] like Figure 1-3 , 5, which includes the following steps:

[0083] Step 1: Based on the distribution and trend of target reservoir 1, Figure 5 The seven-point well pattern shown has a production well 3 arranged at the center, and six vertical heating wells 2 arranged around it;

[0084] Step 2: Using a heating well and a production well, supercritical CO2 carrying a proppant is used to fractur e the oil shale formation, and a fracturing zone fracture gap 5 is formed in the oil shale reservoir to increase the permeability of the oil shale reservoir;

[0085] Step three: Install a downhole heater 4 in the heating well 2, and introduce oxygen 9 into the injection well. After being preheated by the downhole heater 4, the room temperature oxygen 9 flows into the target reservoir 1 to heat the kerogen in the oil shale, causing it to crack and generate hydrocarbons. At the same time, a portion of the asphalt and the produced oil shale oil and gas will undergo oxidation reactions with the oxygen to generate CO2 and release a large amount of heat. The produced oil shale oil and gas are discharged to the ground through the production well 3. The CO2 gas flow 7 is separated from the collected gas through the ground separation system 6 and is reinjected into the underground oil shale layer through the heating well 2. This cycle continues until the temperature distribution in the thermal cracking reaction zone of the oil shale reservoir is as shown in the figure below. Figure 6 As shown, the in-situ pyrolysis reaction of the oil shale ends, and the oil shale reaction zone forms a porous residual stratum 12 with a high temperature, the local temperature can reach 850K, and the average temperature is higher than 700K ( Figure 6 ), at this time, the average porosity of the formation is 60%, and the permeability is between 0.2-0.5mD (such as Figure 7 At present, the average reservoir porosity of the saline CO2 storage projects carried out in my country is 4.5%-7%, and the average effective reservoir permeability is 0.1-0.3mD. Therefore, the strata after in-situ mining meet the physical property conditions for CO2 geological storage. In addition, minerals such as carbonates in oil shale formations are decomposed by heat during the thermal process to generate alkaline oxides mainly composed of SiO2, Al2O3 and Fe2O3, with a total content of about 80%.

[0086] Calcium carbonate: CaCO3 → CaO + CO2

[0087] Dolomite: CaMg(CO3)2→CaO+MgO+CO2

[0088] Siderite: FeCO3→FeO+CO2

[0089] Pyrite: FeS2+O2→Fe3O4+SO2

[0090] Kaolinite: Al4Si4O 10 (OH)8→2Al2O3+4SiO2+4H2O

[0091] Step 4: Take out the downhole heater 4 in the heating well 2, and use a pressurized injection device to inject the CO2 generated during the in-situ mining process and other industrial production into the formation 12 through the heating well 2. After the gas flows through the underground high-temperature rock formation, the heated CO2 gas returns to the surface through the production well and is recycled for heat utilization, realizing the recycling of waste heat from the formation using CO2 gas. A rough estimate is that per unit mining volume (mining 1m 3 Oil shale) can recover heat in 2.5×10 8 J-4.5×10 8J, equivalent to the heat release of 8.53-15.4 kg standard coal;

[0092] Step 5: When the temperature of the recovered gas in the formation is low, water 10 and waste liquid 11 generated during the in-situ mining of oil shale are injected into the formation, so that the injected CO2, water, and waste liquid react fully with the formation residue after pyrolysis of the oil shale to generate mineral precipitation, thereby achieving the purpose of carbon fixation;

[0093] Step 6: After the production well is sealed by reinjecting cementing slurry 13, CO2 is continuously injected into the underground until saturation is reached, and then the injection well is sealed. The potential storage capacity of CO2 can be simplified as the product of the effective pore volume of the reservoir after production and the CO2 density under reservoir conditions: Where: CO2 is the density of CO2 under reservoir conditions, V is the effective pore volume of the reservoir after production, is the effective coefficient. Taking the unit oil shale reservoir at a depth of 500 meters as an example, according to the pore characteristics of the formation after mining ( Figure 7 ), at this time ρ CO2 is the density of CO2 under reservoir conditions ρ CO2 =899.5kg / m 3 (5MPa, 50℃), the average porosity of the formation is 60%, and the effective coefficient is 0.7. The amount of CO2 that can be sealed after unit volume of oil shale is mined is about 378kgCO2.

[0094] The underground heater mentioned in the present invention does not need to be in working state throughout the whole process. It only needs to preheat the injected underground gas in the initial stage of mining. When the cracking reaction in the underground oil shale layer is triggered, the heater can be turned off and only normal temperature gas can be injected into the oil shale reservoir. Whether the heater needs to be turned on can be judged by the composition of the gas produced by the mining well.

[0095] The present invention only needs to inject oxygen at the initial stage of the reaction. After the cracking reaction in the underground oil shale layer is triggered, the amount of injected oxygen and the amount of reinjected gas can be adjusted according to the gas composition collected from the production well, and whether additional CO2 gas needs to be added.

[0096] Furthermore, in this embodiment, the gas products extracted from underground in situ can be injected back into the underground oil shale reservoir through the heating well without separation, and participate in the oil shale cracking reaction until the thermal cracking reaction of the oil shale reservoir is completed.

[0097] Furthermore, the present invention can also be applied to the exploitation of medium and low-maturity shale oil resources, thereby increasing the mobilization of medium and low-maturity shale oil resources and achieving geological storage of CO2.

[0098] Example 5: Porosity and permeability experiments of oil shale after pyrolysis at different temperatures

[0099] The samples used in the experiment came from the Gonglangtou mining area in Huadian, Jilin Province. Before the experiment, the samples needed to be processed into standard specimens with a diameter of 25 mm and a height of 25 mm, and wrapped with plastic wrap to prevent weathering and water loss of the samples.

[0100] In order to study the basic physical and chemical properties of solid residues at different pyrolysis temperatures, experiments were conducted at 12 temperature points, including room temperature and heating to 100°C, 200°C, 300°C, 350°C, 400°C, 450°C, 500°C, 550°C, 600°C, 650°C, 700°C and 800°C. The experiment used an OTF-1200X-50 tube furnace, and a quartz tube with an inner diameter of 50mm and a tube length of 1000mm was placed horizontally in the center of the program-controlled tube furnace. The specific steps are as follows:

[0101] (1) Place the standard sample in the center of the quartz tube and purge it with nitrogen for 20 mL min. -1 ;

[0102] (2) 5℃ min -1 The sample was slowly heated to a specific temperature at a heating rate of , and kept warm for 2 hours; gas samples were collected after 10 minutes of warming.

[0103] (3) After the furnace body is naturally cooled to room temperature, the shale oil and solid residue produced are collected.

[0104] During the entire experiment, high-purity nitrogen was always used to purge the quartz tube to prevent oxidation reactions.

[0105] For the convenience of description, the original sample is recorded as Sraw, and the samples collected at different pyrolysis temperatures are recorded as S100, S200, S300, S350, S400, S450, S500, S550, S600, S650, S700 and S800, respectively, where the numbers represent the pyrolysis temperature, such as S100 represents the solid residue collected after pyrolysis at 100°C. After the experiment, the porosity and permeability of the solid residue were tested. The porosity and permeability of the samples were measured using the AP-608 fully automatic porosity and permeability measuring instrument produced by CoreTest, USA. The experiment directly used the samples after the pyrolysis experiment (φ≈25mm), and the measuring pressure was 500PSI.

[0106] The experimental results are as follows Figure 7 shown. Figure 7The porosity and permeability of oil shale are shown in the figure as the temperature changes with the pyrolysis temperature. As can be seen from the figure, when the temperature is below 300°C, the sample structure is relatively dense, and the generated oil / gas is almost difficult to pass through. With the increase of pyrolysis temperature, the porosity of the solid residue increases rapidly to 56.8% (450°C), and finally stabilizes at about 59%. The permeability of the sample also first increases to 0.432mD (S550), and then fluctuates and rises, and finally increases to 1.3mD when the pyrolysis temperature reaches 800°C. The increase in porosity and permeability between 350 and 500°C is related to the cracking and volatilization of organic matter. When the pyrolysis temperature is higher than 600°C, the porosity does not change much, while the permeability still increases, especially at 800°C. This shows that high temperature makes the internal pore structure of the sample ordered and the connectivity is enhanced.

[0107] The above experiments have verified that the residue after pyrolysis of oil shale to produce oil is a porous structure.

Claims

1. A method for in-situ conversion and exploitation of fossil energy and utilization of waste heat from geological storage, characterized by: Including underground In-situ pyrolysis of fossil resources, recovery and utilization of stratum waste heat, and geological storage; The specific steps include: Step 1: Arrange heating wells (2) and production wells (3) according to the distribution and trend of the target reservoir (1) in the production area, perform supercritical CO2 fracturing on the target reservoir (1), and form fracture gaps (5) in the target reservoir; Step 2: Install a downhole heater (4) in the heating well (2), inject oxygen (9) into the well, and after being preheated by the downhole heater (4), the oxygen (9) flows into the target reservoir (1), heats the kerogen in the target reservoir (1), and a part of the oil and gas reacts with the oxygen to generate CO2 and release heat at the same time. The generated oil and gas is discharged to the ground through the production well (3). The collected gas is separated into a CO2 gas flow (7) through a ground separation system (6) and stored in a CO2 storage tank (8), and is then injected back into the underground target reservoir (1) through the heating well (2). This cycle is repeated until the thermal cracking reaction of the target reservoir (1) is completed, and a residual skeleton porous formation (12) with a high formation temperature, developed pores and fractures, and rich in a large amount of alkaline minerals is formed in the target reaction zone; Step 3: Take out the downhole heater (4) inside the heating well (2), and use a pressurized injection device to inject the CO2 generated during the in-situ mining process and the CO2 generated by industrial production into the residual skeleton porous formation (12) through the heating well (2). The gas flows through the underground high-temperature rock formation and heat exchange occurs. The heated CO2 gas returns to the surface through the mining well (3) and is recycled for heat utilization; Step 4: When the temperature of the recovered gas in the stratum is low, the geological storage stage begins.

2. The method for in-situ conversion and exploitation of fossil energy and utilization of geologically stored waste heat according to claim 1 is characterized by: The geological storage phase described in step 4 includes CO2 and H2 geological storage. The steps of CO2 geological storage include: S1. Injecting water (10) and waste liquid (11) generated during in-situ mining of source rocks into the formation, so that the injected CO2, water, and waste liquid fully react with the formation residue after pyrolysis of the source rocks to generate mineral precipitation; S2. After the production well (3) is reinjected with cementing slurry (13) to seal the well, CO2 is continuously injected into the underground until saturation is reached, and then the heating well (2) is sealed; The steps for H2 geological storage include: S1. Close the production well (3), inject industrially produced H2 into the formation using a pressurized injection device, and monitor the concentration and pressure of underground hydrogen in real time through the production well (3). When the underground hydrogen pressure reaches 80% of the hydrogen storage design pressure, close the heating well (2) and perform a soaking operation to allow the injected hydrogen to fully diffuse into the micro-cracks and matrix pores, so that the formation pressure between the heating well (2) and the production well (3) reaches equilibrium; S2. Continue to inject H2 into the ground until the design pressure is reached, and then close the heating well (2); S3. When hydrogen is needed, open the heating well (2) or the production well (3) to extract H2; according to the working conditions, select H2 containing hydrocarbon gas, or use purification technology to obtain high-purity H2.

3. The method for in-situ conversion and exploitation of fossil energy and utilization of geologically stored waste heat according to claim 1 is characterized by: The underground fossil resource in-situ pyrolysis stage includes underground in-situ pyrolysis of oil shale and underground in-situ pyrolysis of low- and medium-maturity shale oil.

4. The method for in-situ conversion and exploitation of fossil energy and utilization of geologically stored waste heat according to claim 1 is characterized by: The heating well (2) is arranged vertically or horizontally, and the number of the heating well (2) and the number of the production well (3) are both more than one.

5. The method for in-situ conversion and exploitation of fossil energy and utilization of geologically stored waste heat according to claim 1 is characterized by: The method for supercritical CO2 fracturing the target reservoir (1) comprises: fracturing the oil shale formation using supercritical CO2 carrying a proppant.

6. The method for in-situ conversion and exploitation of fossil energy and utilization of geologically stored waste heat according to claim 1 is characterized by: The gas temperature is relatively low, being below 60°C.

7. The method for in-situ conversion and exploitation of fossil energy and utilization of geologically stored waste heat according to claim 1 is characterized by: The downhole heater (4) preheats the injected underground gas at the initial stage of exploitation. When the cracking reaction in the underground target rock formation is triggered, the downhole heater (4) is turned off and normal temperature gas is injected into the target reservoir. Whether the downhole heater (4) is turned on is determined by the components of the gas produced by the exploitation well.