Coal mine fully-mechanized mining method, coal mine fully-mechanized mining system, equipment and storage medium
Patent Information
- Application Number
- CN202410948559.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-16
- Publication Date
- 2024-10-15
Smart Images

Figure CN118774774A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of coal mining, and specifically to a coal mine fully-mechanized mining method, a coal mine fully-mechanized mining system, equipment and a storage medium. Background Art
[0002] With technological advancements, demand for coal mining is increasing. Typically, fully mechanized coal mining faces consist of equipment such as shearers, hydraulic supports, and scraper conveyors. Operators operate the shearers through electro-hydraulic control systems or direct controls, ensuring continuous mining. However, due to the varying types of coal mines and the need for tailored production control methods for each coal seam's varying occurrence conditions, automated mining practices are inefficient and can lead to safety issues during the mining process. Summary of the Invention
[0003] The purpose of the embodiments of the present application is to provide a coal mine comprehensive mining method, coal mine comprehensive mining system, equipment and storage medium, at least to solve the problem that the mining efficiency of coal mines may be low due to different types of coal mines and safety problems may arise during the mining process.
[0004] In a first aspect, an embodiment of the present application provides a fully-mechanized coal mining method, the fully-mechanized coal mining method comprising: Obtaining geological information of a target coal mine, wherein the target coal mine includes a fully-mechanized mining face and a transport roadway corresponding to the fully-mechanized mining face, wherein the transport roadway is used for transporting coal, personnel, and vehicles in the fully-mechanized mining face, and wherein the geological information includes a geological information map of the fully-mechanized mining face and a geological information map of the transport roadway, wherein the geological information map of the transport roadway represents the actual size, actual coal seam roof and floor curves, and actual shape of the roadway, and the geological information map of the fully-mechanized mining face represents the actual size of the fully-mechanized mining face; Obtaining the actual size of the shearer drum, the actual size of the hydraulic support, the actual size of the scraper conveyor, and the actual size and rigidity constraint conditions of other equipment on the fully mechanized mining working face; A mining planning model is constructed based on the geological information of the target coal mine, the actual size of the shearer drum, the actual size of the hydraulic support, the actual size of the scraper conveyor, and the actual size and rigidity constraints of other equipment on the fully mechanized mining face, wherein the mining planning model includes a coal mine model, a shearer model, a haulage roadway model, a hydraulic support model, and a scraper conveyor model, and the shearer model, the haulage roadway model, the hydraulic support model, and the scraper conveyor model are all located within the coal mine model; Determining a production cutting model for the shearer model to cut the coal mine model based on the mining planning model; According to the production cutting model, the shearer drum is controlled to cut the coal mine at the fully mechanized mining working face.
[0005] Optionally, determining the production cutting model of the coal mining model by the coal mining machine model based on the mining planning model includes: Determining a production cutting model for a first cut of the coal mining model by the shearer model based on the mining planning model; Based on the production cutting model of the first cut, the production cutting model of each cut after the first cut when the coal mining machine model cuts the coal mine model is determined.
[0006] Optionally, determining the production cutting model of the first cut of the coal mining model by the coal mining machine model based on the mining planning model includes: Determining a preset production cutting model for a first cut of the coal mining model by the coal mining machine model based on the mining planning model; comparing the preset production cutting pattern of the first cutter with the stored standard production cutting pattern; If the preset production cutting model of the first knife is consistent with the standard production cutting model, the preset production cutting model of the first knife is used as the production cutting model of the first knife; If the preset production cutting model of the first knife is inconsistent with the standard production cutting model, the preset production cutting model of the first knife is adjusted according to the received adjustment instruction until the preset production cutting model of the first knife is consistent with the standard production cutting model.
[0007] Optionally, determining the production cutting model of the first cut of the coal mining model by the coal mining machine model based on the mining planning model includes: Determining the highest and lowest positions of the coal seam to be mined in the target coal mine based on the geological information map of the fully mechanized mining working face; Determining a mining curve of the shearer drum based on the actual size of the shearer drum, the actual size of the hydraulic support, the actual size of the scraper conveyor, and the actual sizes of other equipment on the fully mechanized mining face; Based on the highest position, the lowest position and the mining curve of the coal seam to be mined, a production cutting model of the first knife is determined.
[0008] Optionally, the information map of the transport tunnel further represents the undulation size of the bottom of the transport tunnel.
[0009] In a second aspect, an embodiment of the present application provides a fully-mechanized coal mining system, the fully-mechanized coal mining system comprising a coal shearer, a hydraulic support, and a controller, wherein the coal shearer is electrically connected to the controller; The controller includes: A first acquisition module is configured to acquire geological information of a target coal mine, wherein the target coal mine includes a fully-mechanized mining face and a transport roadway corresponding to the fully-mechanized mining face, wherein the transport roadway is used for transporting coal, and for personnel and vehicles to travel in the fully-mechanized mining face. The geological information includes a geological information map of the fully-mechanized mining face and a geological information map of the transport roadway, wherein the geological information map of the transport roadway represents the actual size, actual coal seam roof and floor curves, and actual shape of the roadway, and the geological information map of the fully-mechanized mining face represents the actual size of the fully-mechanized mining face. The second acquisition module is used to obtain the actual size of the coal mining machine drum, the actual size of the hydraulic support, the actual size of the scraper conveyor, and the actual size and rigidity constraint conditions of other equipment on the fully mechanized mining working face; a construction module, configured to construct a mining planning model based on geological information of the target coal mine, actual dimensions of the shearer drum, actual dimensions of the hydraulic support, actual dimensions of the scraper conveyor, and actual dimensions and rigid constraints of other equipment in the fully mechanized mining working face, wherein the mining planning model includes a coal mine model, a shearer model, a haulage roadway model, a hydraulic support model, and a scraper conveyor model, and the shearer model, the haulage roadway model, the hydraulic support model, and the scraper conveyor model are all located within the coal mine model; A determination module, configured to determine a production cutting model for the coal mining machine model based on the mining planning model; A control module is used to control the coal mining machine drum to cut the coal mine in the fully mechanized mining working face according to the production cutting model.
[0010] In a third aspect, an embodiment of the present application provides an electronic device comprising a processor and a memory, wherein the memory stores programs or instructions that can be run on the processor, and when the programs or instructions are executed by the processor, the steps of the coal mine comprehensive mining method as described in any one of the first aspects above are implemented.
[0011] In a fourth aspect, an embodiment of the present application provides a storage medium storing a program or instruction, which, when executed by a processor, implements the steps of the coal mine comprehensive mining method as described in the first aspect above.
[0012] In a fifth aspect, an embodiment of the present application provides a chip, which includes a processor and a communication interface, the communication interface and the processor are coupled, and the processor is used to run programs or instructions to implement the method described in the first aspect.
[0013] In a sixth aspect, an embodiment of the present application provides a computer program product, which is stored in a storage medium and executed by at least one processor to implement the method described in the first aspect.
[0014] In the embodiment of the present application, by obtaining the geological information of the target coal mine, the target coal mine includes a fully mechanized mining face and a transport tunnel corresponding to the fully mechanized mining face, the transport tunnel is used for coal transportation, personnel and vehicle travel in the fully mechanized mining face, the geological information includes a geological information map of the fully mechanized mining face and a geological information map of the transport tunnel, the geological information map of the transport tunnel represents the actual size, actual coal seam roof and floor curves and actual shape of the transport tunnel, the geological information map of the fully mechanized mining face represents the actual size of the fully mechanized mining face; the actual size of the shearer drum, the actual size of the hydraulic support, the actual size of the scraper conveyor and the actual size and shape of other equipment of the fully mechanized mining face are obtained. Rigid constraints; based on the geological information of the target coal mine, the actual size of the shearer drum, the actual size of the hydraulic support, the actual size of the scraper conveyor, and the actual size and rigid constraints of other equipment on the fully mechanized mining face, a mining planning model is constructed, and the mining planning model includes a coal mine model, a coal shearer model, a transport tunnel model, a hydraulic support model, and a scraper conveyor model, and the coal shearer model, the transport tunnel model, the hydraulic support model, and the scraper conveyor model are all located inside the coal mine model; based on the mining planning model, a production cutting model for the coal shearer model to cut the coal mine model is determined; according to the production cutting model, the coal shearer drum is controlled to cut the coal seam on the fully mechanized mining face. That is, in the embodiment of the present application, it is equivalent to determining the production cutting model for the target coal mine in advance, and subsequently controlling the operation of the coal shearer based on the production cutting model. This mining method can not only adapt to the actual conditions of the target coal mine, but also effectively avoid collisions between various equipment in the coal mine during the mining process, that is, on the premise of improving the mining efficiency of the target coal mine, it can ensure the safe mining of the target coal mine. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] Figure 1 A flow chart showing a fully mechanized coal mining method provided in an embodiment of the present application; Figure 2 A schematic diagram showing a fully mechanized coal mining system provided in an embodiment of the present application; Figure 3 A schematic diagram showing an electronic device provided in an embodiment of the present application; Figure 4 A schematic diagram showing the hardware structure of an electronic device provided in an embodiment of the present application. DETAILED DESCRIPTION
[0016] The following will be combined with the accompanying drawings in the embodiments of the present application to clearly describe the technical solutions in the embodiments of the present application. Obviously, the embodiments described are part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field are within the scope of protection of this application.
[0017] The terms "first," "second," and the like in the specification and claims of this application are used to distinguish similar objects, and are not used to describe a specific order or precedence. It should be understood that the terms used in this manner are interchangeable where appropriate, so that the embodiments of this application can be implemented in an order other than that illustrated or described herein, and that the objects distinguished by "first," "second," and the like are generally of the same type, and do not limit the number of objects; for example, the first object can be one or more. In addition, the term "and / or" in the specification and claims refers to at least one of the connected objects, and the character " / " generally indicates that the objects connected are in an "or" relationship.
[0018] The human body image analysis method provided in the embodiment of the present application is described in detail below through specific embodiments and their application scenarios in conjunction with the accompanying drawings. Reference Figure 1 , shows a flow chart of a coal mine fully mechanized mining method provided by the embodiment of the present application. Figure 1 As shown, the coal mine fully mechanized mining method includes: Step 101: Obtain geological information of the target coal mine. The target coal mine includes a fully mechanized mining face and a transport tunnel corresponding to the fully mechanized mining face. The transport tunnel is used for transporting coal, personnel, and vehicles in the fully mechanized mining face. The geological information includes a geological information map of the fully mechanized mining face and a geological information map of the transport tunnel. The geological information map of the transport tunnel represents the actual size, actual coal seam roof and floor curves, and actual shape of the transport tunnel. The geological information map of the fully mechanized mining face represents the actual size of the fully mechanized mining face.
[0019] The geological information map of the fully mechanized mining face may include a sketch of the fully mechanized mining face and a 3D map of the fully mechanized mining face. Furthermore, the transport roadway may include a track-following roadway and a transport roadway, and the geological information map of the transport roadway may include a sketch of the track-following roadway, a sketch of the transport roadway, a 3D map of the track-following roadway, and a 3D map of the transport roadway.
[0020] In addition, the geological information map of the transport tunnel includes a sketch of the track tunnel, a sketch of the transport tunnel, a three-dimensional map of the track tunnel, and a three-dimensional map of the transport tunnel. The actual size of the transport tunnel, the actual coal seam roof and floor curves, and the actual shape of the transport tunnel can be directly obtained from these maps. Among them, the actual coal seam roof and floor curves include the roof curve of the actual coal seam and the floor curve of the actual coal seam.
[0021] In addition, the fully mechanized mining working face includes a three-dimensional diagram of the fully mechanized mining working face, so that the actual size of the fully mechanized mining working face can be directly obtained from the three-dimensional diagram of the fully mechanized mining working face.
[0022] That is, through step 101, it is equivalent to obtaining the geological information of the target coal mine, and the geological information can characterize the actual size and actual shape of the transportation tunnel in the target coal mine, and the actual size of the comprehensive mining working face, which is equivalent to obtaining the actual size of the target coal mine, making it easier to subsequently build a model based on the actual size.
[0023] Additionally, in some implementations, the geological information map of the transport tunnel further characterizes the undulation size of the bottom of the transport tunnel.
[0024] By determining the undulating size of the bottom of the transport tunnel, it is equivalent to determining the undulating curve of the bottom of the transport tunnel. When constructing the model, the constructed model can more realistically restore the specific structure inside the target coal seam.
[0025] Step 102: Obtain the actual size of the shearer drum, the actual size of the hydraulic support, the actual size of the scraper conveyor, and the actual size and rigidity constraint conditions of other equipment in the fully mechanized mining working face.
[0026] For example, a shearer has a drum, so the actual dimensions of the shearer can be directly determined based on the shearer's design drawings, and thus the actual dimensions of the shearer's drum. Similarly, the actual dimensions of the hydraulic support can be directly determined based on the hydraulic support's design drawings, the actual dimensions of the scraper conveyor can be directly determined based on the scraper conveyor's design drawings, and the actual dimensions of other equipment in the fully mechanized mining face can be determined based on the design drawings. Furthermore, the rigidity constraints of other equipment can be determined based on their mechanical characteristics.
[0027] Step 103: Based on the geological information of the target coal mine, the actual size of the shearer drum, the actual size of the hydraulic support, the actual size of the scraper conveyor, and the actual size and rigid constraints of other equipment in the fully mechanized mining working face, a mining planning model is constructed. The mining planning model includes a coal mine model, a coal shearer model, a haulage roadway model, a hydraulic support model, and a scraper conveyor model. The coal shearer model, the haulage roadway model, the hydraulic support model, and the scraper conveyor model are all located inside the coal mine model.
[0028] Among them, after determining the geological information of the target coal mine, the actual size of the coal mining machine drum and the actual size of the hydraulic support, the actual size of the scraper conveyor, and the actual size and rigid constraints of other equipment in the comprehensive mining working face, it is equivalent to determining the necessary data for building the model, and these data can accurately represent the internal structure of the target coal mine. The mining planning model constructed can be highly consistent with the target coal mine, thereby accurately reflecting the specific structure inside the target coal mine.
[0029] Step 104: Based on the mining planning model, determine a production cutting model for the shearer model to cut the coal mine model.
[0030] Among them, after the mining planning model is determined, the mining planning model can be reflected in the actual coal mine. The operation of the actual coal mining machine can determine the production cutting model of the coal mining model by the coal mining machine model based on the mining planning model.
[0031] In addition, in some implementations, step 104 may be implemented as follows: based on the mining planning model, determining the production cutting model of the first cut of the coal mining machine model cutting the coal mine model; based on the production cutting model of the first cut, determining the production cutting model of each cut after the first cut of the coal mining machine cutting the coal mine model.
[0032] The mining planning model can be used to determine the production cutting model for the first cut of the coal mining model by the shearer. This is equivalent to determining how the shearer will cut the coal in the actual coal mine in actual production. Based on the production cutting model for the first cut, the production cutting model for each subsequent cut can be determined. This is equivalent to determining the production cutting model for each cut of the coal mining model by the shearer model, that is, determining the actual cutting method of the coal mining machine.
[0033] In addition, in some implementations, the implementation method for determining the production cutting model of the first cut of the coal mining machine cutting the coal mine can be: based on the mining planning model, determine the preset production cutting model of the first cut of the coal mining machine cutting the coal mine; compare the preset production cutting model of the first cut with the stored standard production cutting model; if the preset production cutting model of the first cut is consistent with the standard production cutting model, then use the preset production cutting model of the first cut as the production cutting model of the first cut; if the preset production cutting model of the first cut is inconsistent with the standard production cutting model, adjust the preset production cutting model of the first cut according to the received adjustment instruction until the preset production cutting model of the first cut is consistent with the standard production cutting model.
[0034] The stored standard production cutting model can be a pre-stored standard production cutting model, and the standard production cutting model can be established based on data from multiple coal mines. Specifically, the actual sizes of multiple coal mines can be collected in advance, and the operating data of the coal mining machines in multiple coal mines when mining the coal mines can be collected. The operating data includes how the first knife cuts when the coal mining machine cuts the coal mine, and how each subsequent knife cuts. In this process, the operator can adjust the operation of the coal mining machine based on his own experience, that is, the operator operates the coal mining machine based on his own experience and the size of the coal mine so that the coal mining machine cuts the coal mine. In an embodiment of the present application, the operating data of the coal mining machines in multiple coal mines are collected in advance, and the types of multiple coal mines are collected in advance. Then, the types of multiple coal mines, the actual sizes of multiple coal mines, and the operating data of the coal mining machines in different coal mines are stored, and the actual sizes of multiple coal mines and the operating data of the coal mining machines in different coal mines are used to train the actual mining model. The actual mining model can be any of the existing neural network models. The trained neural network model is tested. If the neural network model meets the requirements, the operating model of each cut during the operation of the shearer can be stored in the neural network model, and each operating model during the operation of the shearer can be used as a standard production cutting model. Therefore, in this embodiment of the application, the preset production cutting model of the first cut can be compared with the operating model of the first cut of the shearer in the neural network model, that is, with the standard production cutting model.
[0035] If the preset production cutting model of the first cut is consistent with the standard production cutting model, the preset production cutting model of the first cut is used as the production cutting model of the first cut; if the preset production cutting model of the first cut is inconsistent with the standard production cutting model, an adjustment instruction can be received to adjust the preset production cutting model of the first cut. The operator can input the adjustment instruction through a key or a display screen, and the operator can receive the adjustment instruction to adjust the preset production cutting model of the first cut.
[0036] In addition, in an embodiment of the present application, after receiving an adjustment instruction and adjusting the preset production cutting model of the first cutter, the preset production cutting model of the first cutter can be stored, that is, the adjustment operation indicated by the adjustment instruction is stored, and the preset production cutting model of the first cutter after adjustment is stored, so that when other coal mines are subsequently mined, the stored preset production cutting model of the first cutter can be used as a new standard production cutting model.
[0037] In addition, in some implementations, the implementation method of determining the production cutting model of the first cut of the coal mining machine in cutting the coal mine based on the mining planning model can be: based on the geological information map of the comprehensive mining working face, determine the highest and lowest positions of the coal seam to be mined in the target coal mine; based on the actual size of the coal mining machine drum, the actual size of the hydraulic support, the actual size of the scraper conveyor and the actual size of other equipment on the comprehensive mining working face, determine the mining curve of the coal mining machine drum; based on the highest position, lowest position and mining curve of the coal seam to be mined, determine the production cutting model of the first cut.
[0038] Among them, the geological information map of the fully mechanized mining face can represent the actual coal seam roof and floor curves in the target coal mine, thereby determining the highest and lowest positions of the coal seam to be mined. The mining curve of the shearer drum can then be determined based on the actual dimensions of the shearer drum, the actual dimensions of the hydraulic support, the actual dimensions of the scraper conveyor, and the actual dimensions of other equipment in the fully mechanized mining face. Specifically, after determining the highest and lowest positions of the coal seam to be mined, it is equivalent to determining the maximum operating range of the shearer model. The maximum range has a maximum mining position and a minimum mining position. The maximum mining position can be the coal seam curve height, the hydraulic support height, or the shearer height, with the minimum value of these three being the highest position. The lowest mining position can be the maximum value of the minimum coal seam curve height, the minimum hydraulic support height, and the minimum shearer height being the lowest position. The lowest mining position corresponds to the cutting bottom line of the shearer cutting the coal mine.
[0039] In addition, the mining curve of the shearer drum can be determined based on the actual size of the shearer drum, the actual size of the hydraulic support, the actual size of the scraper conveyor, and the actual size of other equipment in the fully mechanized mining face. The mining curve includes the performance constraint curve of the shearer, the size of the shearer, and the cutting curve of the shearer cutting the coal mine. The production cutting model of the first cut can then be determined based on the highest and lowest positions of the coal seam to be mined and the mining curve. Specifically, the performance constraint curve of the shearer in the mining curve can be used to determine the range within which the shearer can operate based on its own mechanical properties. The cutting curve of the shearer cutting the coal mine can be used to determine the actual operating range of the shearer. This allows the operation of the shearer to be adjusted to avoid collisions between the shearer and equipment such as the hydraulic support. That is, the production cutting model of the first cut of the shearer is determined under the premise of avoiding shearer collisions.
[0040] Step 105: According to the production cutting model, the shearer drum is controlled to cut the coal in the fully mechanized mining face.
[0041] After the production cutting model is determined, the shearer drum can be controlled to cut the coal in the fully mechanized mining face according to the production cutting model.
[0042] In the embodiment of the present application, by obtaining the geological information of the target coal mine, the target coal mine includes a fully mechanized mining face and a transport tunnel corresponding to the fully mechanized mining face, the transport tunnel is used for coal transportation, personnel and vehicle travel in the fully mechanized mining face, the geological information includes a geological information map of the fully mechanized mining face and a geological information map of the transport tunnel, the geological information map of the transport tunnel represents the actual size, actual coal seam roof and floor curves and actual shape of the transport tunnel, the geological information map of the fully mechanized mining face represents the actual size of the fully mechanized mining face; the actual size of the shearer drum, the actual size of the hydraulic support, the actual size of the scraper conveyor and the actual size and shape of other equipment of the fully mechanized mining face are obtained. Rigid constraints; based on the geological information of the target coal mine, the actual size of the shearer drum, the actual size of the hydraulic support, the actual size of the scraper conveyor, and the actual size and rigid constraints of other equipment on the fully mechanized mining face, a mining planning model is constructed, and the mining planning model includes a coal mine model, a coal shearer model, a transport tunnel model, a hydraulic support model, and a scraper conveyor model, and the coal shearer model, the transport tunnel model, the hydraulic support model, and the scraper conveyor model are all located inside the coal mine model; based on the mining planning model, a production cutting model for the shearer model to cut the coal mine model is determined; according to the production cutting model, the shearer drum is controlled to cut the coal mine on the fully mechanized mining face. That is, in the embodiment of the present application, it is equivalent to determining the production cutting model for the target coal mine in advance, and subsequently controlling the operation of the coal shearer based on the production cutting model. This mining method can not only adapt to the actual conditions of the target coal mine, but also effectively avoid collisions between various equipment in the coal mine during the mining process, that is, on the premise of improving the mining efficiency of the target coal mine, it can ensure the safe mining of the target coal mine. The embodiment of the present application provides a coal mine fully-mechanized mining system, the coal mine fully-mechanized mining system 200 includes a coal shearer, a hydraulic support, and a controller, the coal shearer is electrically connected to the controller; like Figure 2 As shown, the controller includes: The first acquisition module 201 is used to acquire geological information of a target coal mine. The target coal mine includes a fully-mechanized mining face and a corresponding transport roadway. The transport roadway is used for transporting coal, personnel, and vehicles in the fully-mechanized mining face. The geological information includes a geological information map of the fully-mechanized mining face and a geological information map of the transport roadway. The geological information map of the transport roadway indicates the actual size, actual coal seam roof and floor curves, and actual shape of the roadway. The geological information map of the fully-mechanized mining face indicates the actual size of the fully-mechanized mining face. The second acquisition module 202 is used to obtain the actual size of the shearer drum, the actual size of the hydraulic support, the actual size of the scraper conveyor, and the actual size and rigidity constraint conditions of other equipment in the fully mechanized mining working face; A construction module 203 is configured to construct a mining planning model based on geological information of the target coal mine, the actual dimensions of the shearer drum, the actual dimensions of the hydraulic support, the actual dimensions of the scraper conveyor, and the actual dimensions and rigidity constraints of other equipment in the fully mechanized mining face. The mining planning model includes a coal mine model, a shearer model, a haulage roadway model, a hydraulic support model, and a scraper conveyor model, and the shearer model, the haulage roadway model, the hydraulic support model, and the scraper conveyor model are all located within the coal mine model. A determination module 204 is configured to determine a production cutting model for the coal mining machine model based on the mining planning model; The control module 205 is used to control the shearer drum to cut coal in the fully mechanized mining face according to the production cutting model.
[0043] In the embodiment of the present application, by obtaining the geological information of the target coal mine, the target coal mine includes a fully mechanized mining face and a transport tunnel corresponding to the fully mechanized mining face, the transport tunnel is used for coal transportation, personnel and vehicle travel in the fully mechanized mining face, the geological information includes a geological information map of the fully mechanized mining face and a geological information map of the transport tunnel, the geological information map of the transport tunnel represents the actual size, actual coal seam roof and floor curves and actual shape of the transport tunnel, the geological information map of the fully mechanized mining face represents the actual size of the fully mechanized mining face; the actual size of the shearer drum, the actual size of the hydraulic support, the actual size of the scraper conveyor and the actual size and shape of other equipment of the fully mechanized mining face are obtained. Rigid constraints; based on the geological information of the target coal mine, the actual size of the shearer drum, the actual size of the hydraulic support, the actual size of the scraper conveyor, and the actual size and rigid constraints of other equipment on the fully mechanized mining face, a mining planning model is constructed, and the mining planning model includes a coal mine model, a coal shearer model, a transport tunnel model, a hydraulic support model, and a scraper conveyor model, and the coal shearer model, the transport tunnel model, the hydraulic support model, and the scraper conveyor model are all located inside the coal mine model; based on the mining planning model, a production cutting model for the shearer model to cut the coal mine model is determined; according to the production cutting model, the shearer drum is controlled to cut the coal mine on the fully mechanized mining face. That is, in the embodiment of the present application, it is equivalent to determining the production cutting model for the target coal mine in advance, and subsequently controlling the operation of the coal shearer based on the production cutting model. This mining method can not only adapt to the actual conditions of the target coal mine, but also effectively avoid collisions between various equipment in the coal mine during the mining process, that is, on the premise of improving the mining efficiency of the target coal mine, it can ensure the safe mining of the target coal mine. Alternatively, as Figure 3As shown, an embodiment of the present application also provides an electronic device 300, including a processor 301 and a memory 302, wherein the memory 302 stores a program or instruction that can be run on the processor 301, and when the program or instruction is executed by the processor 301, each step of the above-mentioned coal mine comprehensive mining method embodiment is implemented, and the same technical effect can be achieved. To avoid repetition, it will not be repeated here.
[0044] It should be noted that the electronic devices in the embodiments of the present application include the mobile electronic devices and non-mobile electronic devices mentioned above. Figure 4 A schematic diagram of the hardware structure of an electronic device implementing an embodiment of the present application.
[0045] The electronic device 1000 includes but is not limited to components such as a radio frequency unit 1001 , a network module 1002 , an audio output unit 1003 , an input unit 1004 , a sensor 1005 , a display unit 1006 , a user input unit 1007 , an interface unit 1008 , a memory 1009 , and a processor 1010 .
[0046] Those skilled in the art will understand that the electronic device 1000 may also include a power supply (such as a battery) to power each component. The power supply can be logically connected to the processor 1010 through a power management system, so that functions such as charging, discharging, and power consumption management can be managed through the power management system. Figure 4 The electronic device structure shown in the figure does not constitute a limitation on the electronic device. The electronic device may include more or fewer components than shown in the figure, or combine certain components, or arrange the components differently, which will not be repeated here.
[0047] Among them, the processor 1010 is used to obtain geological information of the target coal mine, which includes a fully mechanized mining face and a transport tunnel corresponding to the fully mechanized mining face. The transport tunnel is used for coal transportation, personnel and vehicle travel in the fully mechanized mining face. The geological information includes a geological information map of the fully mechanized mining face and a geological information map of the transport tunnel. The geological information map of the transport tunnel represents the actual size, actual coal seam roof and floor curves and actual shape of the transport tunnel. The geological information map of the fully mechanized mining face represents the actual size of the fully mechanized mining face; obtain the actual size of the shearer drum, the actual size of the hydraulic support, the actual size of the scraper conveyor and the actual size and shape of other equipment on the fully mechanized mining face. Rigid constraints; based on the geological information of the target coal mine, the actual size of the shearer drum, the actual size of the hydraulic support, the actual size of the scraper conveyor, and the actual size of other equipment in the fully mechanized mining face and the rigid constraints, a mining planning model is constructed, and the mining planning model includes a coal mine model, a coal shearer model, a transport tunnel model, a hydraulic support model, and a scraper conveyor model, and the coal shearer model, the transport tunnel model, the hydraulic support model, and the scraper conveyor model are all located inside the coal mine model; based on the mining planning model, the production cutting model of the coal shearer model cutting the coal mine model is determined; according to the production cutting model, the coal shearer drum is controlled to cut the coal mine in the fully mechanized mining face.
[0048] In the embodiment of the present application, by obtaining the geological information of the target coal mine, the target coal mine includes a fully mechanized mining face and a transport tunnel corresponding to the fully mechanized mining face, the transport tunnel is used for coal transportation, personnel and vehicle travel in the fully mechanized mining face, the geological information includes a geological information map of the fully mechanized mining face and a geological information map of the transport tunnel, the geological information map of the transport tunnel represents the actual size, actual coal seam roof and floor curves and actual shape of the transport tunnel, the geological information map of the fully mechanized mining face represents the actual size of the fully mechanized mining face; the actual size of the shearer drum, the actual size of the hydraulic support, the actual size of the scraper conveyor and the actual size and shape of other equipment of the fully mechanized mining face are obtained. Rigid constraints; based on the geological information of the target coal mine, the actual size of the shearer drum, the actual size of the hydraulic support, the actual size of the scraper conveyor, and the actual size and rigid constraints of other equipment on the fully mechanized mining face, a mining planning model is constructed, and the mining planning model includes a coal mine model, a coal shearer model, a transport tunnel model, a hydraulic support model, and a scraper conveyor model, and the coal shearer model, the transport tunnel model, the hydraulic support model, and the scraper conveyor model are all located inside the coal mine model; based on the mining planning model, a production cutting model for the shearer model to cut the coal mine model is determined; according to the production cutting model, the shearer drum is controlled to cut the coal mine on the fully mechanized mining face. That is, in the embodiment of the present application, it is equivalent to determining the production cutting model for the target coal mine in advance, and subsequently controlling the operation of the coal shearer based on the production cutting model. This mining method can not only adapt to the actual conditions of the target coal mine, but also effectively avoid collisions between various equipment in the coal mine during the mining process, that is, on the premise of improving the mining efficiency of the target coal mine, it can ensure the safe mining of the target coal mine.
[0049] Optionally, the processor 1010 is further configured to: Determining a production cutting model for a first cut of the coal mining model by the shearer based on the mining planning model; Based on the production cutting model of the first cut, the production cutting model of each cut after the first cut in which the coal mining machine cuts the coal mine model is determined.
[0050] Optionally, the processor 1010 is further configured to: Determining a preset production cutting model for a first cut of the coal mining model by the coal mining machine model based on the mining planning model; comparing the preset production cutting pattern of the first cutter with the stored standard production cutting pattern; If the preset production cutting model of the first knife is consistent with the standard production cutting model, the preset production cutting model of the first knife is used as the production cutting model of the first knife; If the preset production cutting model of the first knife is inconsistent with the standard production cutting model, the preset production cutting model of the first knife is adjusted according to the received adjustment instruction until the preset production cutting model of the first knife is consistent with the standard production cutting model.
[0051] Optionally, the processor 1010 is further configured to: Determining the highest and lowest positions of the coal seam to be mined in the target coal mine based on the geological information map of the fully mechanized mining working face; Determining a mining curve of the shearer drum based on the actual size of the shearer drum, the actual size of the hydraulic support, the actual size of the scraper conveyor, and the actual sizes of other equipment on the fully mechanized mining face; Based on the highest position, the lowest position and the mining curve of the coal seam to be mined, a production cutting model of the first knife is determined.
[0052] Optionally, the geological information map of the transport tunnel also represents the undulation size of the bottom of the transport tunnel.
[0053] In the embodiment of the present application, by obtaining the geological information of the target coal mine, the target coal mine includes a fully mechanized mining face and a transport tunnel corresponding to the fully mechanized mining face, the transport tunnel is used for coal transportation, personnel and vehicle travel in the fully mechanized mining face, the geological information includes a geological information map of the fully mechanized mining face and a geological information map of the transport tunnel, the geological information map of the transport tunnel represents the actual size, actual coal seam roof and floor curves and actual shape of the transport tunnel, the geological information map of the fully mechanized mining face represents the actual size of the fully mechanized mining face; the actual size of the shearer drum, the actual size of the hydraulic support, the actual size of the scraper conveyor and the actual size and shape of other equipment of the fully mechanized mining face are obtained. Rigid constraints; based on the geological information of the target coal mine, the actual size of the shearer drum, the actual size of the hydraulic support, the actual size of the scraper conveyor, and the actual size and rigid constraints of other equipment on the fully mechanized mining face, a mining planning model is constructed, and the mining planning model includes a coal mine model, a coal shearer model, a transport tunnel model, a hydraulic support model, and a scraper conveyor model, and the coal shearer model, the transport tunnel model, the hydraulic support model, and the scraper conveyor model are all located inside the coal mine model; based on the mining planning model, a production cutting model for the shearer model to cut the coal mine model is determined; according to the production cutting model, the shearer drum is controlled to cut the coal mine on the fully mechanized mining face. That is, in the embodiment of the present application, it is equivalent to determining the production cutting model for the target coal mine in advance, and subsequently controlling the operation of the coal shearer based on the production cutting model. This mining method can not only adapt to the actual conditions of the target coal mine, but also effectively avoid collisions between various equipment in the coal mine during the mining process, that is, on the premise of improving the mining efficiency of the target coal mine, it can ensure the safe mining of the target coal mine.
[0054] It should be understood that in this embodiment of the present application, the input unit 1004 may include a graphics processing unit (GPU) 10041 and a microphone 10042. The GPU 10041 processes image data of still images or videos captured by an image capture device (e.g., a camera) in video capture mode or image capture mode. The display unit 1006 may include a display panel 10061, which may be configured in the form of a liquid crystal display, an organic light-emitting diode, or the like. The user input unit 1007 includes a touch panel 10071 and at least one of other input devices 10072. The touch panel 10071, also known as a touch screen, may include a touch analysis device and a touch controller. Other input devices 10072 may include, but are not limited to, a physical keyboard, function keys (such as volume control keys, on / off keys, etc.), a trackball, a mouse, and a joystick, which are not described in detail here.
[0055] Memory 1009 can be used to store software programs and various data. Memory 1009 may primarily include a first storage area for storing programs or instructions and a second storage area for storing data. The first storage area may store an operating system, applications or instructions required for at least one function (such as sound playback or image playback), and the like. Furthermore, memory 1009 may include volatile memory or non-volatile memory, or both. Non-volatile memory may be read-only memory (ROM), programmable read-only memory (PROM), erasable programmable read-only memory (EPROM), electrically erasable programmable read-only memory (EEPROM), or flash memory. The volatile memory may be a random access memory (RAM), a static random access memory (SRAM), a dynamic random access memory (DRAM), a synchronous dynamic random access memory (SDRAM), a double data rate synchronous dynamic random access memory (DDRSDRAM), an enhanced synchronous dynamic random access memory (ESDRAM), a synchronous link dynamic random access memory (SLDRAM), and a direct memory bus random access memory (DRRAM). The memory 1009 in the embodiment of the present application includes but is not limited to these and any other suitable types of memory.
[0056] Processor 1010 may include one or more processing units. Optionally, processor 1010 integrates an application processor and a modem processor. The application processor primarily handles operations related to the operating system, user interface, and application programs, while the modem processor primarily processes wireless communication signals, such as a baseband processor. It is understood that the modem processor may not be integrated into processor 1010. An embodiment of the present application provides a computer program product, which is stored in a storage medium. The program product is executed by at least one processor to implement the various processes of the embodiment of the above-mentioned coal mine comprehensive mining method, and can achieve the same technical effect. To avoid repetition, it will not be repeated here. It should be noted that, in this article, the terms "comprise", "include" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device comprising a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, an element defined by the statement "comprises a ..." does not exclude the presence of other identical elements in the process, method, article or device comprising the element. In addition, it should be noted that the scope of the methods and devices in the embodiments of the present application is not limited to performing functions in the order shown or discussed, and may also include performing functions in a substantially simultaneous manner or in the opposite order according to the functions involved. For example, the described method may be performed in an order different from that described, and various steps may also be added, omitted, or combined. In addition, the features described with reference to certain examples may be combined in other examples.
[0057] Through the description of the above embodiments, those skilled in the art can clearly understand that the above-mentioned embodiment methods can be implemented by means of software plus the necessary general hardware platform. Of course, they can also be implemented by hardware, but in many cases the former is a better embodiment. Based on this understanding, the technical solution of this application, or the part that contributes to the existing technology, can be embodied in the form of a computer software product. This computer software product is stored in a storage medium (such as ROM / RAM, magnetic disk, optical disk), and includes a number of instructions for enabling a terminal (which can be a mobile phone, computer, server, or network device, etc.) to execute the methods described in each embodiment of this application. The embodiments of the present application are described above in conjunction with the accompanying drawings, but the present application is not limited to the above-mentioned specific implementation methods. The above-mentioned specific implementation methods are merely illustrative and not restrictive. Under the guidance of this application, ordinary technicians in this field can also make many forms without departing from the purpose of this application and the scope of protection of the claims, all of which are within the protection of this application.
Claims
1. A coal mine fully mechanized mining method, characterized in that: The coal mine fully mechanized mining method comprises: Acquire geological information of a target coal mine, wherein the target coal mine includes a fully mechanized mining face and a transport lane corresponding to the fully mechanized mining face, wherein the transport lane is used for transporting coal, personnel and vehicles of the fully mechanized mining face, and wherein the geological information includes a geological information map of the fully mechanized mining face and a geological information map of the transport lane, wherein the geological information map of the transport lane represents the actual size, actual coal seam roof and floor curves and actual shape of the transport lane, and the geological information map of the fully mechanized mining face represents the actual size of the fully mechanized mining face; Obtaining the actual size of the coal mining machine drum, the actual size of the hydraulic support, the actual size of the scraper conveyor, and the actual size and rigidity constraint conditions of other equipment of the fully mechanized mining working face; According to the geological information of the target coal mine, the actual size of the shearer drum, the actual size of the hydraulic support, the actual size of the scraper conveyor, and the actual size and rigid constraints of other equipment of the fully mechanized working face, a mining planning model is constructed, and the mining planning model includes a coal mine model, a coal shearer model, a transport tunnel model, a hydraulic support model, and a scraper conveyor model, and the coal shearer model, the transport tunnel model, the hydraulic support model, and the scraper conveyor model are all located inside the coal mine model; Based on the mining planning model, determining a production cutting model for the coal mining model to be cut by the coal mining machine model; According to the production cutting model, the coal mining machine drum is controlled to cut the coal seam at the fully mechanized mining working face.
2. The fully mechanized coal mining method according to claim 1, characterized in that: Determining the production cutting model of the coal mining model by the coal mining machine model based on the mining planning model includes: Based on the mining planning model, determining a production cutting model of a first cut of the coal mining machine cutting the coal mine model; Based on the production cutting model of the first cut, the production cutting model of each cut after the first cut of the coal mining machine cutting the coal mine model is determined.
3. The coal mine fully mechanized mining method according to claim 2, characterized in that: Determining the production cutting model of the first cut of the coal mining machine cutting the coal mine model based on the mining planning model includes: Based on the mining planning model, determining a preset production cutting model for the first cut of the coal mining model by the coal mining machine model; comparing the preset production cutting model of the first cutter with the stored standard production cutting model; If the preset production cutting model of the first knife is consistent with the standard production cutting model, the preset production cutting model of the first knife is used as the production cutting model of the first knife; If the preset production cutting model of the first knife is inconsistent with the standard production cutting model, the preset production cutting model of the first knife is adjusted according to the received adjustment instruction until the preset production cutting model of the first knife is consistent with the standard production cutting model.
4. The coal mine fully mechanized mining method according to claim 2, characterized in that: Determining the production cutting model of the first cut of the coal mining machine cutting the coal mine model based on the mining planning model includes: Based on the geological information map of the fully mechanized mining working face, determining the highest position and the lowest position of the coal seam to be mined in the target coal mine; Determine the mining curve of the shearer drum based on the actual size of the shearer drum, the actual size of the hydraulic support, the actual size of the scraper conveyor and the actual size of other equipment on the fully mechanized mining face; Based on the highest position, the lowest position of the coal seam to be mined and the mining curve, a production cutting model of the first knife is determined.
5. The fully mechanized coal mining method according to claim 1, characterized in that: The geological information map of the transport tunnel also characterizes the undulation size of the bottom of the transport tunnel.
6. A coal mine fully mechanized mining system, characterized in that: The coal mine fully mechanized mining system comprises a coal mining machine, a hydraulic support and a controller, wherein the coal mining machine is electrically connected to the controller; The controller comprises: A first acquisition module is used to acquire geological information of a target coal mine, wherein the target coal mine includes a fully-mechanized mining face and a transport lane corresponding to the fully-mechanized mining face, wherein the transport lane is used for coal transportation, personnel and vehicle travel in the fully-mechanized mining face, and wherein the geological information includes a geological information map of the fully-mechanized mining face and a geological information map of the transport lane, wherein the geological information map of the transport lane represents the actual size, actual coal seam roof and floor curves and actual shape of the lane, and the geological information map of the fully-mechanized mining face represents the actual size of the fully-mechanized mining face; The second acquisition module is used to obtain the actual size of the coal mining machine drum, the actual size of the hydraulic support, the actual size of the scraper conveyor, and the actual size and rigidity constraint conditions of other equipment of the fully mechanized mining working face; A construction module is used to construct a mining planning model according to the geological information of the target coal mine, the actual size of the coal mining machine drum, the actual size of the hydraulic support, the actual size of the scraper conveyor, and the actual size and rigid constraint conditions of other equipment of the fully mechanized working face, and the mining planning model includes a coal mine model, a coal mining machine model, a transportation tunnel model, a coal mining machine model, a hydraulic support model, and a scraper conveyor model, and the coal mining machine model, the transportation tunnel model, the coal mining machine model, the hydraulic support model, and the scraper conveyor model are all located inside the coal mine model; A determination module, used for determining a production cutting model of the coal mining machine model for cutting the coal mine based on the mining planning model; A control module is used to control the coal mining machine drum to cut the coal mine at the fully mechanized mining working face according to the production cutting model.
7. A device, characterized in that: It includes a processor and a memory, wherein the memory stores programs or instructions that can be run on the processor, and when the programs or instructions are executed by the processor, the steps of the coal mine comprehensive mining method as described in any one of claims 1 to 5 are implemented.
8. A storage medium, characterized in that: The storage medium stores programs or instructions, and when the programs or instructions are executed by the processor, the steps of the coal mine comprehensive mining method described in any one of claims 1-5 are implemented.