Small-clear-distance shield receiving construction method and system for upper-soft lower-hard stratum

By reinforcing the foundation, removing anchors and reinforced concrete waist beams, forming honeycomb cores, and setting up large pipe sheds for grouting during the construction of small-clearance tunnels with soft and hard strata above and below, the problems of tunnel segment deformation and thrust increase were solved. Problems have been solved to achieve the improvement of construction safety quality and the conditions for the smooth exit of the shield tunnel.

CN118774853APending Publication Date: 2024-10-15POWERCHINA RAILWAY CONSTR
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411043455.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-31
Publication Date
2024-10-15

AI Technical Summary

Technical Problem

In urban subway construction, especially in the construction of small-clearance tunnels with soft upper and hard composite strata, it is difficult to effectively control tunnel segment deformation and shield exit thrust with existing technology, making it difficult to guarantee safety and quality.

Method used

The end of the receiving well is isolated and sealed, the foundation is reinforced, the anchors and reinforced concrete waist beams are removed, a honeycomb core is formed, and a large pipe shed is set up for grouting treatment to reduce the thrust and resist the lateral surrounding rock pressure. Through the synchronous grouting system Fill the segment gaps to ensure smooth exit of the shield.

Benefits of technology

It effectively controls the deformation of the tunnel segment, reduces the thrust during the exit stage of the shield, ensures construction safety and quality, and provides conditions for the shield to exit smoothly.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118774853A_ABST
    Figure CN118774853A_ABST
Patent Text Reader

Abstract

According to the small-clear-distance shield receiving construction method and system for the upper-soft and lower-hard stratum, large pipe sheds are arranged at the positions 15-25 cm outside the outer contour line of a preceding tunnel and within the range of 45 degrees above and below the horizontal line of the circle center, so that lateral surrounding rock pressure transmitted in the shield tunneling process of a following tunnel can be effectively resisted, and segment deformation of the preceding formed tunnel is controlled; rock in a receiving end tunnel portal steel ring is subjected to coring, a breakable honeycomb structure is formed, and the thrust of a shield tunneling stage is reduced; the reinforced concrete suspended piles are cut off by pulling out anchoring parts and a water drill, obstacles such as reinforced concrete waist beams and steel pipe piles are removed, and conditions are created for smooth crossing of a shield.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of urban subway construction, and in particular relates to a shield receiving construction method and a construction system for a small clear distance shield in an upper soft and lower hard stratum. Background Art

[0002] In urban subway construction, construction in composite strata with soft upper and hard lower is often encountered. Affected by the limitation of urban underground space, there are more and more tunnels with small clearance. The overlying geological lithology of composite strata is Quaternary full Pleistocene and semi-Pleistocene soft soil strata, and the underlying geological lithology is strongly (fully) weathered, moderately weathered and slightly weathered rock. The lithology is very different and the construction is difficult, especially in mechanical excavation construction. The safety and quality of construction in composite strata are more difficult to control than those in homogeneous strata, and some safety and quality accidents often occur. Therefore, it is necessary to conduct further research on various complex working conditions of composite strata with soft upper and hard lower, such as shield reception under small clearance conditions of less than 1D.

[0003] For example, the Chinese invention patent application number CN201810679561.7 discloses a full-section water-rich sand layer shield receiving construction method for tunnel construction, wherein the tunnel shield end area is provided with a water-stop curtain, and an inner drainage well is drilled inside the water-stop curtain. The method comprises:

[0004] Driving three-axis mixing piles in the shield end area;

[0005] An outer drainage well is set outside the water-stop curtain;

[0006] A vacuum pump is arranged in the inner precipitation well;

[0007] The well cover of the inner drainage well is sealed and connected with the well pipe of the inner drainage well to form a vacuum inner drainage well;

[0008] Propelling the shield machine through the water-stop curtain until the shield machine reaches the tunnel portal position;

[0009] Perform tunnel door demolition construction by using the shield machine;

[0010] The shield machine is pushed through the tunnel gate until it is pushed onto the shield receiving bracket to complete the shield receiving.

[0011] The above-mentioned prior art firstly sets up an outer drainage well outside the water-stop curtain, then sets up a vacuum drainage pump in the inner drainage well in the end area of ​​the shield, and seals and connects the manhole cover of the inner drainage well with the well pipe of the inner drainage well to form a vacuum inner drainage well, so as to ensure the safe reception of the shield. However, the following technical problems exist in the actual reception construction:

[0012] During shield tunneling, as tunneling progresses, the tunnel segments deform, affecting the progress of receiving;

[0013] If the tunnel gate at the receiving end is not treated, the thrust during the shield tunneling phase will increase, which is not conducive to the shield tunneling.

[0014] Based on the above technical problems existing in the prior art, the present invention proposes a shield receiving construction method and construction system with small clearance in upper soft and lower hard strata. Summary of the invention

[0015] The purpose of the present invention is to provide a shield receiving construction method and a construction system with a small clearance in soft upper and hard lower strata in view of the deficiencies in the prior art.

[0016] The present invention adopts the following technical solution:

[0017] A shield receiving construction method with small clearance in upper soft and lower hard strata, comprising:

[0018] Step 1: Isolate and seal the groundwater at the end of the receiving well, and drill a drainage well between the two tunnels;

[0019] Step 2, strengthening the foundation of the receiving well end;

[0020] Step 3, remove the anchors in the foundation pit rock and soil inside the tunnel ring;

[0021] Step 4, cutting off the reinforced concrete waist beams at the positions of bored piles and steel pipe piles intruding into the tunnel along the edge of the tunnel portal steel ring, and chiseling off the reinforced concrete waist beams with a breaker hammer;

[0022] Step 5, chiseling off the surface layer of shotcrete at the bottom of the tunnel gate ring, cutting and welding the steel pipe piles in the tunnel gate steel ring;

[0023] Step 6, drilling cores in the shield tunnel portal steel ring to form a honeycomb, and the drilling and coring adopts a plum blossom-shaped drilling arrangement;

[0024] Step 7: When the shield arrives at the receiving area, use channel steel to longitudinally tighten the rear 20 rings of segments for reinforcement; when the shield passes through the subsequent tunnel, a large pipe shed is built 15 to 25 cm from the outer contour of the preceding tunnel and within 45° above and below the horizontal line of the center of the circle, and grouting is carried out.

[0025] Furthermore, in step 1, a row of high-pressure jet grouting piles is used to isolate and seal the groundwater, wherein the high-pressure jet grouting piles are constructed using a triple pipe method.

[0026] Furthermore, in step 1, the water-cement ratio of the grouting cement slurry for the high-pressure jet jet pile is 0.9-1.1, the cement content is 25%-40%, and the gravel layer content is not less than 550kg per linear meter.

[0027] Furthermore, in step 1, the precipitation operation is started 3 to 5 days before the shield machine arrives.

[0028] Furthermore, in step 2, the end reinforcement adopts triple tube method high pressure rotary jet pile reinforcement, the reinforcement grouting slurry is pure cement slurry, the water-cement ratio is 0.9-1.1, the cement content is 25-40%, and the gravel layer content is not less than 550kg per linear meter.

[0029] Furthermore, step 2 includes: constructing two rows of bored cast-in-place piles with a rotary drill at the crawler crane station of the lifting equipment, and constructing two foundation beams on the bored cast-in-place piles to meet the bearing capacity requirements of the crawler crane equipment.

[0030] Further, step 3 includes:

[0031] Drill holes around the anchor according to the designed incident angle. The number of holes drilled is 2 to 3, and the drilling depth is not less than half of the designed length of the anchor.

[0032] According to the designed bearing capacity of the anchor, use a through-type jack to pull out the anchor in the rock layer of the foundation pit.

[0033] Furthermore, in step 3, after drilling, the through-type jack is installed on the rod of the anchor, the rod is fixed with a tool anchor and a clip, and the cylinder is pressurized. As the jack cylinder moves, the tool anchor and the clip clamp the rod, and the force is continuously applied, so that the rod will be slowly pulled out.

[0034] Furthermore, in step 3, if it is difficult to pull out the anchor, the drilling hole is deepened and / or the number of peripheral drilling holes is increased.

[0035] Furthermore, in step 5, the steel pipe pile cutting elevation should be at least 5 to 10 cm lower than the portal steel ring.

[0036] Furthermore, in step 6, the core length is 50 to 80 cm, and the spacing of the drill holes is 50 to 70 cm.

[0037] Furthermore, in step 7, measurement and verification are performed before the shield arrives to control the axis deviation, single-loop correction amount and excavation parameters to reduce the thrust.

[0038] Furthermore, in step 7, the penetration rate, rotation speed and torque are controlled; the synchronous grouting is controlled, the secondary grouting is performed, and the secondary grouting pressure is controlled.

[0039] Furthermore, in step 7, the diameter of the large pipe rack is φ108 mm, the spacing is 400-500 mm, and the length is the influence range of the numerical simulation of small-spacing shield advancement.

[0040] Furthermore, in step 7, the grouting slurry is a 1:1 pure cement slurry.

[0041] Further, step 7 includes:

[0042] A reinforced concrete receiving arc guide platform is constructed on the bottom plate of the receiving well. The elevation of the reinforced concrete receiving arc guide platform is lower than the receiving elevation. The horizontal deviation and elevation deviation of the guide rail installation are set. The front end of the guide rail is cut into a wedge shape by cutting welding and is flush with the concrete surface of the guide platform.

[0043] Install a temporary rubber curtain sealing device on the steel ring of the tunnel portal. After the shield machine is exposed from the cutterhead, stop the cutterhead rotation. When the reinforced concrete receiving arc guide platform is pushed forward, tighten the temporary rubber curtain sealing device every time two rings are pushed forward. Use the synchronous grouting system to inject cement-water-glass double liquid slurry to fill the outer annular gap of the segment.

[0044] After the last ring of segments is assembled, tighten the rubber cord temporary sealing device to make it fit tightly against the outer arc surface of the segment, and perform synchronous grouting and secondary grouting filling on the tunnel door ring through the grouting holes of the segment to seal the tunnel door.

[0045] A shield receiving construction system with small clearance in soft upper and hard lower strata, comprising:

[0046] Hoisting out shaft: after receiving, the shield machine is hoisted out from the hoisting out shaft;

[0047] The retaining piles are supported on the well wall of the hoisted well;

[0048] TRD water-stop curtain, set outside the retaining piles;

[0049] The high-pressure jet-jet pile water-stop curtain is set at the end of the receiving well and overlaps with the TRD water-stop curtain of the hoisting well foundation pit;

[0050] The foundation beam is set at the end of the receiving shaft, spanning the leading tunnel and the trailing tunnel, and is used for the crawler crane to stand;

[0051] Bearing piles are set at the end of the receiving well and overlapped with the foundation beam;

[0052] The large pipe rack is set 15 to 25 cm outside the outer contour line of the advance tunnel.

[0053] Furthermore, the construction system also includes anchors anchored in the foundation pit rock and soil within the tunnel gate ring.

[0054] Furthermore, the construction system also includes steel pipe piles, which are fixedly arranged on the well wall of the supporting hoisting well below the retaining piles.

[0055] Furthermore, the construction system also includes a reinforced concrete locking foot waist beam, which is arranged on the top of the steel pipe pile and supports the toe of the retaining pile together with the steel pipe pile.

[0056] Furthermore, the construction system also includes a guide platform and a guide rail fixed on the guide platform, and the shield machine exits the tunnel along the guide rail.

[0057] The beneficial effects of the present invention are:

[0058] 1. The shield receiving construction method with small clearance in soft upper and hard lower strata of the present invention sets up a large pipe shed 15 to 25 cm outside the outer contour line of the leading tunnel and within 45° above and below the horizontal line of the center of the circle, which can effectively resist the lateral surrounding rock pressure transmitted during the shield excavation process of the following tunnel and control the deformation of the pipe segment of the leading tunnel;

[0059] 2. The shield receiving construction method with small clearance in soft upper and hard lower strata of the present invention coring the rock inside the steel ring of the receiving end tunnel door forms an easily broken honeycomb structure, which reduces the thrust of the shield in the tunnel exit stage and provides favorable conditions for the shield to exit the tunnel smoothly;

[0060] 3. The shield receiving construction method with small clearance in soft upper and hard lower strata of the present invention creates conditions for smooth passage of the shield by removing anchors and drilling out reinforced concrete hanging piles, removing reinforced concrete waist beams and steel pipe piles and other obstacles. BRIEF DESCRIPTION OF THE DRAWINGS

[0061] Figure 1 This is a schematic plan view of a receiving terminal in an embodiment of the present invention;

[0062] Figure 2 It is a longitudinal cross-sectional schematic diagram of a receiving terminal in an embodiment of the present invention;

[0063] Figure 3 It is a schematic cross-sectional view of a receiving end in an embodiment of the present invention.

[0064] In the figure, 1-pre-tunnel, 2-rear tunnel, 3-high-pressure rotary jet pile water-stop curtain, 4-bearing piles, 5-foundation beam, 6-dewatering well, 7-large pipe shed, 8-TRD water-stop curtain, 9-guard piles, 10-lifting well, 11-anchors, 12-steel pipe piles, 13-guide rails, 14-guide platform. DETAILED DESCRIPTION

[0065] In order to more clearly understand the above-mentioned purposes, features and advantages of the present invention, the present application is further described in detail below in conjunction with the accompanying drawings and specific implementation methods. It should be noted that the embodiments of the present application and the features in the embodiments can be combined with each other without conflict.

[0066] Example

[0067] The shield receiving construction method with small clearance in upper soft and lower hard strata comprises:

[0068] Step 1: Isolate and seal the groundwater at the end of the receiving well, dig a dewatering well between the two tunnels, and start the dewatering operation 3 to 5 days before the shield machine arrives;

[0069] Step 2, strengthening the foundation of the receiving well end;

[0070] Step 3, removing the anchors in the foundation pit rock and soil inside the tunnel ring;

[0071] Step 4, cutting off the reinforced concrete waist beams at the positions of bored piles and steel pipe piles intruding into the tunnel along the edge of the tunnel portal steel ring, and chiseling off the reinforced concrete waist beams with a breaker hammer;

[0072] Step 5: Chisel off the surface sprayed concrete at the bottom, cut and weld the steel pipe piles in the steel ring of the tunnel gate, and the cutting elevation of the steel pipe piles should be no less than 5 to 10 cm lower than the steel ring of the tunnel gate;

[0073] Step 6: Drill cores in the shield tunnel portal steel ring to form a honeycomb, with a core length of 50 to 80 cm, a borehole spacing of 50 to 70 cm, and a plum blossom-shaped drilling arrangement for core drilling;

[0074] Step 7: When the shield arrives at the receiving area, use channel steel to longitudinally tighten the rear 20 rings of segments for reinforcement; when the shield passes through the subsequent tunnel, a large pipe shed is built 15 to 25 cm outside the outer contour of the preceding tunnel and within 45° above and below the horizontal line of the center of the circle.

[0075] As a specific implementation method, in step 1, a row of high-pressure jet grouting piles is used to isolate and seal the groundwater at the periphery of the tunnel within 12m of the receiving well end. The high-pressure jet grouting piles are constructed using a triple pipe method. For example, the pile diameter is φ800, the spacing is @550, and the length of the high-pressure jet grouting piles into the strong (completely) weathered rock layer is not less than 1.5m;

[0076] The water-cement ratio of high-pressure jet grouting cement slurry is 0.9-1.1, the cement content is 25-40%, and the gravel layer content is not less than 550kg per linear meter;

[0077] To improve the properties of cement slurry, appropriate admixtures and additives can be added;

[0078] A well point dewatering well is drilled between the two tunnels. The diameter of the well is φ600 and the well depth is not less than 0.5m into the medium-weathered rock.

[0079] As a specific implementation, in step 2, under the crawler crane position of the lifting equipment, a rotary drill is used to construct two rows of 8 bored piles, exemplarily, the borehole diameter is φ800, and the pile length is 6 to 8 m;

[0080] Construct two foundation beams on bored piles to ensure safe hoisting of shield dismantling machine;

[0081] After the shield is hoisted out, the foundation beams and piles within 2.5m below the ground will be chiseled out.

[0082] As a specific implementation, in step 3, according to the designed length of the anchor, a pneumatic drill or a down-the-hole drill is used to drill holes around the anchor at a designed incident angle, the number of holes drilled is 2 to 3, and the drilling depth is not less than half of the designed length of the anchor cable, wherein the holes are drilled around the anchor;

[0083] Select a through-type jack according to the designed bearing capacity of the anchor, and use the through-type jack to pull out the anchor in the rock formation of the foundation pit. Specifically, after drilling, install the through-type jack on the anchor rod, fix the rod with a tool anchor and a clip, and slowly pressurize the cylinder. As the jack cylinder moves, the tool anchor and the clip clamp the rod, and continue to apply force. When the jack traction force exceeds the friction force and anchoring force of the rod, the rod will be slowly pulled out;

[0084] In actual construction, if it is difficult to pull out, it is necessary to continue to deepen the drilling hole or increase the number of surrounding drilling holes to reduce friction and pull out the anchor smoothly;

[0085] The anchor is an anchor cable or an anchor rod.

[0086] As a specific implementation method, in step 5, the surface sprayed concrete is chiseled off at the bottom of the tunnel gate ring, and the steel pipe piles in the tunnel gate steel ring are cut off by oxygen acetylene cutting welding. The cutting elevation of the steel pipe piles should be at least 5 to 10 cm lower than the tunnel gate steel ring.

[0087] As a specific implementation method, in step 6, a water drill is used to drill a core in the steel ring of the shield tunnel portal to form a honeycomb, and the core length is 50 to 80 cm;

[0088] The drilling spacing is 50 to 70 cm, and a plum blossom shape arrangement is adopted.

[0089] As a specific implementation, in step 7, the shield is measured and checked before arriving, for example, the axis deviation is controlled at ±40mm, the single ring correction amount is not more than 3mm, the excavation parameters are controlled, the thrust is reduced to 5000-7000KN, the penetration is 3-5mm, the speed is 1.8-2.3rpm, and the torque is 1000-2000KN.m;

[0090] Control synchronous grouting and carry out secondary grouting in time. For example, the secondary grouting pressure is controlled at 0.3-0.5Mpa;

[0091] The grouting material is a cement-based composite material, the main components of which are cement, admixtures and additives. The initial setting time of the grouting slurry is 2 to 4 hours, the consolidation rate is not less than 98%, and it has a certain water resistance and dispersion to ensure that the backfill behind the wall is full. The stone strength is not less than 0.5MPa at 24 hours and not less than 2.5Mpa at 28 days.

[0092] Use No. 10 channel steel to longitudinally tighten the 20 ring segments to reinforce them to prevent the segments from loosening and affecting the waterproof effect;

[0093] When the shield of the following tunnel passes through, a φ108 large pipe shed is set 15 to 25 cm outside the outer contour of the leading tunnel and within 45° above and below the horizontal line of the center of the circle. The spacing between the pipe sheds is 40 to 50 cm, and the length of the pipe shed is within the small clear distance range of less than 0.3D to 0.4D, which is determined according to the type and grade of the surrounding rock to prevent the shield excavation of the following tunnel from affecting the leading tunnel and causing deformation;

[0094] A reinforced concrete receiving arc guide platform is constructed on the bottom plate of the receiving well. For example, its elevation is slightly lower than the receiving elevation by 2 cm. The horizontal deviation of the guide rail installation is ±10 mm, and the elevation deviation is ±15 mm. The front end of the guide rail is cut into a wedge shape by cutting welding, and the concrete surface of the guide platform is flush.

[0095] Install a temporary rubber curtain sealing device on the steel ring of the tunnel portal. After the shield machine is exposed from the cutterhead, stop the cutterhead rotation. When pushing the upper arc guide platform forward, tighten the temporary sealing device of the tunnel portal every time two rings are pushed forward. Use the synchronous grouting system to inject cement-water-glass double liquid slurry to fill the annular gap outside the segment to ensure the correct posture of the segment.

[0096] After the last ring of segments is assembled, tighten the temporary sealing device of the tunnel gate to make the curtain rubber plate fit tightly against the outer arc surface of the segment, and perform synchronous grouting and secondary grouting filling on the tunnel gate ring through the grouting holes of the segment to seal the tunnel gate.

[0097] The shield receiving construction system with small clearance in soft upper and hard lower strata includes:

[0098] The shield machine is hoisted out of the hoisting shaft 10 after receiving the shield machine;

[0099] The retaining piles 9 are supported on the wall of the hoisting well 10;

[0100] TRD water-stop curtain 8, arranged on the periphery of the retaining pile 9;

[0101] High-pressure jet-jet pile water-stop curtain 3 is arranged at the end of the receiving well and overlapped with the TRD water-stop curtain 8;

[0102] A foundation beam 5 is arranged at the end of the receiving well and spans the leading tunnel 1 and the trailing tunnel 2;

[0103] A bearing pile 4, arranged at the end of the receiving well and overlapped with the foundation beam 5;

[0104] The large pipe rack 7 is arranged 15 to 25 cm outside the outer contour line of the advance tunnel 1 .

[0105] The construction system also includes an anchor 11 anchored in the foundation pit rock and soil within the tunnel gate ring.

[0106] The construction system further comprises a steel pipe pile 12 , which is fixedly arranged between the tunnel portal and the wall of the hoisting shaft 10 .

[0107] The construction system further includes a guide platform 14 and a guide rail 13 fixed on the guide platform 14 , and the shield machine exits the tunnel along the guide rail 13 .

[0108] The present invention is not limited by the above embodiments. The above embodiments and descriptions are only for explaining the principle of the present invention. Without departing from the spirit and scope of the present invention, the present invention may be subject to various changes and improvements, which are within the scope of the present invention to be protected. The scope of protection of the present invention is defined by the appended claims.

Claims

1. A shield receiving construction method with small clearance in soft upper and hard lower strata, characterized in that: include: Step 1: Isolate and seal the groundwater at the end of the receiving well, and drill a drainage well between the two tunnels; Step 2, strengthening the foundation of the receiving well end; Step 3, remove the anchors in the foundation pit rock and soil inside the tunnel ring; Step 4, cutting off the reinforced concrete waist beams at the positions of bored piles and steel pipe piles intruding into the tunnel along the edge of the tunnel portal steel ring, and chiseling off the reinforced concrete waist beams with a breaker hammer; Step 5, chiseling off the surface layer of shotcrete at the bottom of the tunnel gate ring, cutting and welding the steel pipe piles in the tunnel gate steel ring; Step 6, drilling cores in the shield tunnel portal steel ring to form a honeycomb, and the drilling and coring adopts a plum blossom-shaped drilling arrangement; Step 7: When the shield arrives at the receiving area, use channel steel to longitudinally tighten the rear 20 rings of segments for reinforcement; when the shield passes through the subsequent tunnel, a large pipe shed is built 15 to 25 cm outside the outer contour of the preceding tunnel and within 45° above and below the horizontal line of the center of the circle, and grouting is carried out.

2. The shield receiving construction method with small clearance in upper soft and lower hard strata according to claim 1 is characterized in that: In step 1, a row of high-pressure jet grouting piles is used to isolate and seal the groundwater, wherein the high-pressure jet grouting piles are constructed using a triple pipe method.

3. The shield receiving construction method with small clearance in upper soft and lower hard strata according to claim 1 or 2, characterized in that: In step 1, the water-cement ratio of the grouting cement slurry for the high-pressure jet jet pile is 0.9-1.1, the cement content is 25-40%, and the gravel layer content is not less than 550kg per linear meter.

4. The shield receiving construction method with small clearance in upper soft and lower hard strata according to claim 1 is characterized in that: Step 2 includes: the end is reinforced by triple-tube method high-pressure rotary jet piles, and two rows of bored piles are constructed by rotary drilling at the crawler crane station of the lifting equipment, and two foundation beams are constructed on the bored piles.

5. The shield receiving construction method with small clearance in upper soft and lower hard strata according to claim 1 is characterized in that: Step 3 includes: Drill holes around the anchor according to the designed incident angle. The number of holes drilled is 2 to 3, and the drilling depth is not less than half of the designed length of the anchor. According to the designed bearing capacity of the anchor, use a through-type jack to pull out the anchor in the rock layer of the foundation pit.

6. The shield receiving construction method with small clearance in upper soft and lower hard strata according to claim 5 is characterized in that: In step 3, after drilling, install the through-type jack on the rod of the anchor, fix the rod with the tool anchor and the clip, pressurize the cylinder, and as the jack cylinder moves, the tool anchor and the clip clamp the rod, and the force is continuously applied, so that the rod will be slowly pulled out.

7. The shield receiving construction method with small clearance in upper soft and lower hard strata according to claim 6 is characterized in that: In step 3, if the anchor is difficult to pull out, deepen the drill hole and / or increase the number of surrounding drill holes.

8. The shield receiving construction method with small clearance in upper soft and lower hard strata according to claim 1 is characterized in that: In step 7, measurement and verification are carried out before the shield arrives to control the axis deviation, single-loop correction amount and excavation parameters and reduce the thrust.

9. The shield receiving construction method with small clearance in upper soft and lower hard strata according to claim 1 or 8, characterized in that: Step 7 includes: A reinforced concrete receiving arc guide platform is constructed on the bottom plate of the receiving well. The elevation of the reinforced concrete receiving arc guide platform is lower than the receiving elevation. The horizontal deviation and elevation deviation of the guide rail installation are set. The front end of the guide rail is cut into a wedge shape by cutting welding and is flush with the concrete surface of the guide platform. Install a temporary rubber curtain sealing device on the steel ring of the tunnel portal. After the shield machine is exposed from the cutterhead, stop the cutterhead rotation. When the reinforced concrete receiving arc guide platform is pushed forward, tighten the temporary rubber curtain sealing device every time two rings are pushed forward. Use the synchronous grouting system to inject cement-water-glass double liquid slurry to fill the outer annular gap of the segment. After the last ring of segments is assembled, tighten the rubber cord temporary sealing device to make it fit tightly against the outer arc surface of the segment, and perform synchronous grouting and secondary grouting filling on the tunnel door ring through the grouting holes of the segment to seal the tunnel door.

10. A shield receiving construction system with small clearance in soft upper and hard lower strata, characterized in that: include: Hoisting out shaft: after receiving, the shield machine is hoisted out from the hoisting out shaft; The retaining piles are supported on the well wall of the hoisted well; TRD water-stop curtain, set outside the retaining piles; The high-pressure jet-jet pile water-stop curtain is set at the end of the receiving well and overlaps with the TRD water-stop curtain of the hoisting well foundation pit; The foundation beam is set at the end of the receiving shaft, spanning the leading tunnel and the trailing tunnel, and is used for the crawler crane to stand; Bearing piles are set at the end of the receiving well and overlapped with the foundation beam; The large pipe rack is set 15 to 25 cm outside the outer contour line of the advance tunnel.