Combined installation construction method for boiler unit overheating system
Through scientific and reasonable combined installation and construction methods, the safety and efficiency issues during the installation process of the boiler unit overheating system are solved, ensuring the correct position and sealing of each component, and achieving a safe and efficient installation effect.
Patent Information
- Application Number
- CN202411038468.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-31
- Publication Date
- 2024-10-15
AI Technical Summary
How to ensure the safety and efficiency of the boiler unit superheating system during the installation process is an issue that needs to be solved urgently.
Adopt a combined installation and construction method, including equipment inspection, ball passing, ground assembly, hanging device installation, wall superheater installation, low temperature, medium temperature, high temperature superheater installation, pipe row adjustment, sealing and anti-wear device science Proper steps are taken to ensure the correct position and sealing of each component.
Through systematic installation steps, the safety and efficiency of the installation process are improved, ensuring the correct assembly and sealing of the boiler unit superheating system, meeting the requirements of safety and efficiency.
Smart Images

Figure CN118775852A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of boiler units, in particular to a combined installation and construction method for a boiler unit superheating system. Background Art
[0002] The superheating system designed for the boiler unit mainly includes cyclone separators and return devices, high-temperature superheaters, low-temperature superheaters, wall-wrapped superheaters, medium-temperature superheaters, ceiling superheaters, and inlet and outlet headers, connecting pipes, desuperheaters, etc. of each level of superheating system.
[0003] However, how to ensure safety and efficiency during the installation of the boiler unit superheating system is a technical problem that needs to be solved urgently in this field. Summary of the invention
[0004] The purpose of the present invention is to overcome the above technical deficiencies and provide a combined installation and construction method for a boiler unit superheating system to achieve safe and efficient installation of the boiler unit superheating system.
[0005] In order to achieve the above technical objectives, the present invention adopts the following technical solutions:
[0006] According to one aspect of the present invention, a combined installation construction method for a boiler unit superheating system is provided, which is characterized by comprising:
[0007] Step 1: Superheater assembly, installation and construction procedures;
[0008] Step 2: Assembly and installation of cyclone separator and return device;
[0009] The step one specifically includes: equipment inspection, ball passing, ground assembly, hanging device installation, wall-wrapped superheater installation, low-temperature superheater installation, medium-temperature superheater installation, high-temperature superheater installation, superheater tube row installation, adjustment, superheater sealing, and anti-wear device installation.
[0010] Furthermore, the hanging device installation specifically includes:
[0011] After the installation and alignment of the furnace roof steel structure is completed, the overheating system hanging device can be installed with the roof beam, hanger beam, or separately by using a lifting machine. Before hanging the hanger, number the hanger on the ground, and try to match the nut with the hanger thread and thread. When hanging the hanger, apply black lead powder or spray molybdenum disulfide on the threaded part of the hanger. If the thread of the hanger is damaged during the hoisting process, repair it in time to ensure a smooth connection with the nut. After the hanger is hoisted into place, add a cap to lock the nut or tie it with wire to prevent free rotation and falling off. After the superheater hanger is installed and adjusted, spot weld the nut at the nut, spot weld one place, when installing the hanger, the welding of the pin should ensure that there is a certain gap between the ear plate and the lap plate, and the total gap on both sides of each hanger is different, and the total gap must be guaranteed according to the drawing.
[0012] Furthermore, the wall-wrapped superheater installation specifically includes:
[0013] Ground combination:
[0014] According to the on-site hoisting capacity and construction conditions, the wall components are divided into: the front wall and the rear wall are divided into two components according to the manufacturer's supply section, and the lower section component is combined with the lower header; the middle partition wall is divided into two components, and the upper and lower components each have a header; the top wall is combined into the front and rear components; the right wall is divided into two components, and the upper and lower components each have a header; the left wall is composed of upper and lower headers and pipe screens combined into a whole for hoisting;
[0015] The assembly order is rear wall, right wall, middle partition wall, top wall, front wall, and left wall;
[0016] Before assembly, place all the pipe rows on each side wall on the assembly rack with the fire side facing downwards, spot weld the fins between the pipe rows firmly, check the opening and diagonal angles, and cut the joints at the corresponding joint positions when formally assembled;
[0017] All pipe rows should be placed according to the identification numbers on the general drawing, and pay attention to their front and back, up and down, left and right directions. Check the drawings to confirm whether the positions of each door hole are correct to prevent incorrect placement of pipe rows;
[0018] After the pipe row is checked diagonally and found to be correct, the limit blocks are welded on the assembly frame along the length direction to fix it;
[0019] Before the header is connected, the inside should be cleaned and the vertical and horizontal center lines should be marked. Before the header is connected, it should be reinforced and the reinforcement should be firm and reliable.
[0020] Installation of furnace wall accessories: Before assembly, all parts should be counted and their appearance quality checked against the drawings. Alloy parts should be spectrally confirmed for material and stored in categories. Alloy parts should be installed in the correct position during installation and should not be installed incorrectly. During installation, attention should be paid to the seal between the heated surface and the correct installation position and direction. When installing the sootblower box, the casing should be vertical to the pipe row. The door holes are all castings and should be prevented from collision damage during installation.
[0021] Temporary facilities for hoisting wall components:
[0022] Except for the upper part of the front wall and the upper part of the middle partition wall, all other components must be welded with lifting lugs on the upper and lower parts. Each component is supported by 4 lifting lugs.
[0023] Wall installation dimension review and marking:
[0024] Taking the elevation line of the boiler steel frame as the benchmark, mark the elevation line of the header on the middle partition wall on the steel frame column; mark the vertical and horizontal positioning dimensions: mark the center line of the furnace, check whether the position of each hanger beam is consistent with the drawing size according to the symmetric center line of the boiler and the center line of the furnace, and mark the installation center line to ensure that the error is within the range required by the specification; mark the wall installation dimension line based on the symmetric center line of the boiler and the center line of the furnace, and ensure that the error is within the range required by the specification;
[0025] Wall installation and alignment:
[0026] First, align the right side wall and the middle partition wall. After aligning and reinforcing the vertical and horizontal positioning dimensions of the upper header and aligning the pipe row joints, use channel steel to reinforce the entire assembly.
[0027] After the alignment of the middle partition wall is completed, the top wall is divided into two pieces for secondary hoisting, alignment, and welding. After the hanging device is installed and adjusted in place, the front and rear wall are reset for the second time, alignment, welding, and reinforcement work is carried out; the left wall is aligned after the low pass and low re-hoisting is completed;
[0028] Hoisting of left wall assembly:
[0029] The tower crane and crawler crane are used to lift it up. After it is erected, the left wall assembly is lifted up by the tower crane alone, airdropped into the rear furnace, and temporarily suspended under the plate beam. Two steel wire ropes are used as the hanging rope, and four strands are stressed.
[0030] Front wall hoisting:
[0031] Prepare the components on the front wall and the components under the front wall, first hoist the lower components and then the upper components; use tower crane and crawler crane to lift and erect them, and then use the tower crane to lift the components on the front wall separately, drop them into the rear furnace, and temporarily hang them under the plate beam. The upper component hanging rope uses two φ28, L=30m steel wire ropes, four strands of force, and the lower component hanging rope uses two φ41, L=30m steel wire ropes, four strands of force;
[0032] Ceiling wall hoisting:
[0033] After the top wall assembly is completed, it is hoisted separately by a tower crane. After all the wall superheaters are hoisted, the secondary plate beam and the corresponding hanger beam are restored. Then, the rear wall assembly is formally put in place, the middle partition wall assembly is formally put in place, the front wall assembly is formally put in place, and the left wall is temporarily suspended;
[0034] Rigid beam installation:
[0035] Inventory of rigid beam equipment and accessories:
[0036] The rigid beams should be counted and numbered before installation. If there is a distinction between the front and back, the front and back parts should be distinguished according to the drawings. The upper and lower sides of each rigid beam should be determined. Check whether the rigid beam is consistent with the design on the drawings and whether the layout of the vertical reinforcement is correct.
[0037] Rigid beam ground combination:
[0038] The rigid beams for the wall are assembled on the ground, and the rigid beams are assembled strictly according to the technical requirements of the drawings. The tension plates and connectors of the rigid beams can be pre-installed on the attached wall when assembled on the ground;
[0039] According to the elevation of the rigid beam, convert it into the relative distance between the rigid beams and the rigid beams and the pipe row, and then draw lines on the pipe row. When drawing lines, pay attention to the unity of the reference line and draw the expansion zero point of the wall at the same time;
[0040] Horizontal rigid beam installation:
[0041] The rigid beam is fixed by inserting the ear plate welded on the tube bank into the rigid beam connector. There is a gap between the angle steel of the rigid beam connector and the ear plate on the rigid beam. The tension plate or the collecting plate is installed before installing the rigid beam connector.
[0042] Installation of vertical rigid beams:
[0043] There is a vertical rigid beam in the upper area of the two side walls respectively. The upper part of the vertical rigid beam is connected to the top wall balancing device through a connecting piece, and the lower part is connected to the mounting piece with a bolt piece;
[0044] Installation of corner fixtures:
[0045] The corner connection of the rigid beams is fixed by pins, and the installation of the corners is carried out after the wall is aligned;
[0046] Guide installation:
[0047] The installation of the guide device must be carried out after the wall alignment is completed. One end of the guide device is welded and fixed to the rigid beam, and the other end is welded and fixed to the steel beam;
[0048] After the rigid beam is installed, the wall is aligned, and the overall inspection and acceptance by the supervisor is completed, the temporary hanging ears are cut off and polished, and the temporary hanging facilities are removed in time;
[0049] Wall area sealing device:
[0050] The sealing of the wall area includes: the sealing device at the bottom of the wall, the through-wall seal of the wall superheater, the through-wall seal of the low-temperature reheater, and the top seal of the wall; the sealing of the wall area is composed of comb plates and steel plates welded together; the sealing box should be filled with insulation or refractory materials.
[0051] Furthermore, the low temperature superheater installation specifically includes:
[0052] Pipe row combination:
[0053] First, weld the positioning angle steel on the assembly frame according to the drawings, with no less than 4 angle steels on each side to ensure the assembly size; ensure that the first and second tube groups of the vertical section of the low-temperature superheater are assembled, and every 2 tube groups are assembled into one assembly, among which the first and second tube groups of the low-temperature superheater are assembled into 73 assemblies. Before the tube rows are aligned, confirm that the assembly is consistent with the requirements of the drawings according to the drawing numbers, and install the superheater anti-wear device on the ground. After the tube rows are assembled, they are uniformly numbered and then placed in the order of hoisting to prevent misplacement or random placement;
[0054] Low temperature superheater hoisting:
[0055] Before installing the low-pass, the left wall must be reserved. The two upper and lower tube rows of the low-pass must be assembled and then hoisted. When assembling and hoisting the tube rows, use the factory-supplied pipe panel lifting tools. Use tower cranes and crawler cranes to lift them upright. After erecting them, use the tower crane to lift the low-temperature superheater assembly alone, drop it into the rear furnace, and then use the electric hoist hook arranged under the ceiling to officially put the low-pass in place.
[0056] Furthermore, the installation of the medium temperature superheater specifically includes:
[0057] Tube row combination
[0058] Assemble the inlet and outlet distribution headers and tube panels of the medium-temperature superheater on the ground;
[0059] The installation of the sealing plugs between the tube panels must be completed before the tube panels are aligned. After each single tube panel is assembled, the sealing device must be installed before the header can be aligned. When installing the sealing device, the direction must be distinguished. After the tube panels are aligned, the pins in the pin area must be welded according to the drawing requirements;
[0060] Medium temperature superheater hoisting:
[0061] The medium-temperature superheaters consist of 8 groups, which are airdropped into place from the furnace top;
[0062] Temporary hanging of header: The lower header of the medium-temperature superheater needs to be temporarily hung outside the front wall of the water-cooled wall in advance, and the interface can be made after the screen tube row passes through the front water;
[0063] Use a glass tube level to measure whether both ends of the header are level, and use a plumb bob to check whether the header is aligned; use a glass tube level to measure the center elevation of the header and the elevation of the support surface of the assembly frame. The center elevation of the header is higher than the elevation of the support surface of the assembly frame, and the value should be equal to the radius of the pipe; after alignment, use electric welding and angle steel to reinforce the header; use an angle grinder and a grinding head to grind the welding grooves of the connecting pipes and pipe rows on the header; clean the oil and rust on the welds until the metallic luster is revealed; use a ruler to align the header. Check the size of the large and small diagonal dimensions of the box and the tube row to make the tube row perpendicular to the header; confirm the number, positive and negative directions of the tube row according to the drawing before docking; draw the position lines of the two pipes on the assembly frame according to the positions of the outermost tube seats on both sides of the header. After the diagonal check of the tube row is correct, weld the limit blocks on the assembly frame along the length direction to prevent the tube row from shifting and deforming during the docking process. After the tube panel is assembled, the pin area specified on the drawing must be welded with pins;
[0064] Installation of medium-temperature superheater tube row: The assembled tube row of the medium-temperature superheater is hoisted by a single tower crane using the header lifting ears or directly bundling with a small header. The medium-temperature superheater is composed of 8 groups in total, which are dropped into place from the furnace top. After the tube panel passes through the front wall, it is aligned with the previously temporarily hung lower header, and attention should be paid to monitoring the alignment process. The alignment fall chain can be loosened only after the heat treatment of the weld is completed.
[0065] Furthermore, the superheater pipe installation specifically includes:
[0066] After the alignment of the superheater tube row and the header is completed, the welding work of the superheater tube group and the header can be carried out. After the welding is completed, the gaps between the low-temperature superheater and the wall-clad superheater, the medium-temperature superheater and the water-cooled wall, the high-temperature superheater and the water-cooled wall, and the tube rows are inspected to meet the requirements of the drawings.
[0067] Furthermore, in step 2, the installation of the material return device specifically includes:
[0068] The valve body of the return device is installed. The three return devices are arranged under the three cyclone separators respectively and supported on the boiler steel frame. After the positioning line of the return device is drawn, some steel beams at this position are slowly installed. After the return device is installed in place, it is installed. The installation adopts loose parts lifting and combined installation is carried out at the installation position. The valve body of the return device is pre-stored with a tower crane. After the combination is aligned, the riser and compensator of the return device are pre-stored and temporarily fixed. After the cyclone separator is installed, sealing welding is carried out. The return pipe of the return device is pre-stored and aligned for welding. The return pipe is pre-stored from bottom to top.
[0069] Furthermore, in step 2, the installation of the cyclone separator specifically includes:
[0070] Pipeline ball:
[0071] Pass the balls through the cyclone separator tube screen and clean the header;
[0072] Choose the appropriate diameter of the steel ball for the ball-passing test. After the ball-passing test is completed, count and collect the steel balls in time, seal them and make a visa.
[0073] Combination installation of straight section and cone section tube screen of cyclone separator:
[0074] The cyclone separator tube screen is composed of an inlet straight tube screen, a straight tube screen and a cone tube screen; there are 3 sets of inlet straight tube screens; there are 3 sets of straight tube screens; the cone tube screen is divided into an upper cone tube screen and a lower cone tube screen, the upper cone tube screen is divided into 3 sets, and the lower cone tube screen is divided into 3 sets;
[0075] The cyclone separator tube screen assembly method is ground assembly according to the inlet straight tube screen, straight tube screen, upper cone tube screen and lower cone tube screen. Its assembly method is consistent with that of the wall-wrapped superheater. However, because it is a membrane screen with an arc, in order to ensure that the assembly components meet the requirements of the drawings and specifications, additional support, brackets and other temporary measures are required during assembly.
[0076] After the assembly is completed, use a tower crane to hoist it, and crawler crane to lift it together; after hoisting it into place, close the seams and seal it according to the dimensions on the drawing; when closing the upper header of the cyclone separator, ensure the parallelism and concentric verticality of the header to avoid the overall distortion of the tube screen; after welding and installing it with the upper header, weld it with the lower header of the cyclone separator. The hoisting method refers to the wall-wrapped superheater;
[0077] Pre-installation of the inlet and outlet flues of the cyclone separator and the steam cooling flue;
[0078] The inlet flue of the cyclone separator is pre-stored. There are a total of 3 inlet flues in this unit. They are pre-stored with a tower crane and temporarily suspended under the steel beam. The hanging wire rope is protected with asbestos cloth, and the flue is protected again with round steel. Before the inlet flue of the cyclone separator is pre-stored, the upper and lower headers of the cyclone separator have been welded before leaving the factory, so it is impossible to conduct a ball inspection on the pipe row. Only the upper and lower headers of the cyclone separator can be inspected. The inside of the header is inspected with an endoscope and purged with compressed air. After confirming that the inside is clean, the pre-storage hoisting can be carried out.
[0079] The cyclone separator outlet flue is designed with 3 parts in total and is arranged on the upper part of the central tube. Before installation, it is pre-stored on the steel beam together with the central tube by a tower crane and temporarily reinforced by spot welding with channel steel. It will be installed in place after the central tube is installed in place.
[0080] A total of 3 sets of steam-cooled flue units are designed. During installation, loose parts and rigid beams are used for hoisting, and then the whole assembly is carried out after they are in place;
[0081] Cyclone separator center tube pre-storage:
[0082] The center tube of the cyclone separator is pre-stored. There are a total of 3 pieces in this unit. Before installation, the alloy parts need to be spectrally tested to confirm the material. A tower crane is used for pre-storage and it is temporarily stored on a steel beam and temporarily reinforced with channel steel spot welding. After the pre-storage of the straight section and cone section assembly of the cyclone separator is completed, the center tube of the cyclone separator will be officially installed.
[0083] The combined installation construction method of the boiler unit superheating system provided by the present invention has scientific and reasonable settings of various steps, ensuring a safe and efficient installation process. BRIEF DESCRIPTION OF THE DRAWINGS
[0084] Figure 1 A schematic diagram of left wall hoisting of a combined installation construction method of a boiler unit superheating system is provided in accordance with an embodiment of the present invention;
[0085] Figure 2 A schematic diagram of the positions of the components hanging points on the front wall of a combined installation construction method of a boiler unit superheating system according to an embodiment of the present invention;
[0086] Figure 3 The diagram is a schematic diagram of hoisting a low-temperature superheater that can implement a combined installation construction method for a boiler unit superheating system provided by an embodiment of the present invention.
[0087] In the figure:
[0088] 1-upper header; 2-rigid beam; 3-lower header; 4-80t tower crane hook; 5-280t crawler crane hook; 6-φ38 wire rope; 7-single pulley; 8-φ42 wire rope; 9-front wall assembly; 10-φ19 wire rope; 11-φ15 wire rope. DETAILED DESCRIPTION
[0089] In order to enable those skilled in the art to better understand the solution of the present application, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present application.
[0090] An embodiment of the present invention provides a combined installation construction method for a boiler unit superheating system, which specifically includes:
[0091] 1. Introduction to the overall process
[0092] 1.1 Superheater construction process
[0093] Equipment inspection, ball passing, ground assembly → installation of hanging device in rear smoke shaft area → temporary throwing of lower and upper components of rear wall → temporary throwing of lower and upper components of right wall → hoisting and alignment of right wall → hoisting and throwing of upper middle partition wall (with header) → hoisting and throwing of lower middle partition wall (with header) → temporary throwing of left wall → throwing of lower and upper components of front wall → installation of hanging beams for slow installation of rear ceiling → installation of hanging beams for slow installation of middle partition wall → formal reset of middle partition wall components → hoisting of pipe screen of rear ceiling wall → alignment and welding of pipe screen of rear wall → installation of hanging beams for slow installation of front ceiling → hoisting of pipe screen of front wall → front wall Align and weld the ceiling pipe screen → hoist the front wall into place → hoist the rear wall into place → reset and align the front wall for welding → reset and align the rear wall for welding → align the front, rear, right and middle partition walls and temporarily reinforce them → (hoist the economizer tube group first) hoist the low-pass serpentine tube row → hoist and insert the low-pass outlet header, medium-pass inlet header and high-pass outlet mixing header into the gear → (hoist the medium and high-temperature superheater tube rows into place) → hoist and drop the superheater connecting pipes (saturated steam outlet pipe, medium-pass inlet and outlet connecting pipes, low-pass to medium-pass connecting pipes, medium-pass to high-pass connecting pipes, superheater outlet duct) for welding.
[0094] 1.2 Construction process of cyclone separator and return device
[0095] Construction preparation → Equipment inventory and inspection → Installation of return material device → Cyclone separator tube screen ball passing → Inlet flue pre-storage → Cyclone separator inlet straight section, straight section and cone section tube screen combination welding and installation → Inlet flue installation → Center tube installation → Sealing device installation → Overall alignment and acceptance.
[0096] Below, as an example, the above steps 1.1 and 1.2 are specifically introduced.
[0097] 2. Header marking
[0098] Mark the header according to the superheating system header drawing, draw the center line for installation alignment on both sides of the header and make sample holes; review the existing holes of the manufacturer, and re-mark any inaccuracies.
[0099] 3. Installation of hanging device
[0100] After the installation and alignment of the furnace roof steel structure is completed, the overheating system hanging device can be installed separately with the top plate beam or by using a lifting machine. Before the hanger is hoisted, the hanger should be numbered on the ground, and the nut should be matched with the hanger thread to find problems in time. When the hanger is hoisted, apply black lead powder (or spray molybdenum disulfide) on the threaded part of the hanger to prevent rust and inability to adjust. If the thread of the hanger is damaged during the hoisting process, it must be repaired in time to ensure smooth connection with the nut. After the hanger is hoisted into place, add locking nuts or tie them with wire in time to prevent the screw from rotating and slipping. Spot weld the nuts of the superheater hanger after installation and adjustment. When installing the hanger, the welding of the pin shaft should ensure that there is a certain gap between the ear plate and the lap plate, and the gap on both sides of each hanger must be guaranteed according to the drawings.
[0101] 4. Wall-mounted superheater installation
[0102] 4.1 Ground combination
[0103] According to the on-site hoisting capacity and construction conditions, the wall components are divided as follows: the front wall and the rear wall are divided into two components according to the manufacturer's supply section, and the lower section component is combined with the lower header; the middle partition wall is divided into two components, and the upper and lower components each have a header; the top wall is combined into the front and rear components; the right wall is divided into two components, and the upper and lower components each have a header; the left wall is composed of upper and lower headers and pipe screens combined into a whole for hoisting.
[0104] 4.2 Combination Order
[0105] Back wall → right wall → middle wall → top wall → front wall → left wall
[0106] 4.3 Before assembly, place all the tube rows on each side wall on the assembly rack with the fire side facing downwards. Spot weld the fins between the tube rows firmly. Check the opening and diagonal angles. Cut the corresponding joints when formally assembling.
[0107] 4.4 All pipe rows should be placed according to the identification numbers on the general drawing, and pay attention to their front and back sides, up and down, left and right directions. Check the drawings to confirm whether the positions of each door hole are correct to prevent incorrect placement of the pipe rows.
[0108] 4.5 After the diagonal inspection of the pipe row is correct, limit blocks are welded on the combination frame along the length direction to prevent the pipe row from shifting and deforming during the docking process.
[0109] 4.6 Before the connection, the interior of the header should be cleaned and the vertical and horizontal center lines should be marked. Before the connection, it should be reinforced and the reinforcement should be firm and reliable.
[0110] 4.7 Installation of furnace wall accessories (door holes): Before assembly, all parts should be counted and the appearance quality should be checked against the drawings. Alloy parts should be spectrally confirmed and stored in categories. Alloy parts should be installed in the correct position during installation and should not be installed incorrectly. During installation, attention should be paid to the seal between the heated surface and the installation position and direction should be correct and meet the requirements of the drawings. When installing the soot blower box, the casing should be ensured to be vertical to the pipe row; the door holes are all castings and should be prevented from collision damage during installation.
[0111] 4.8 Temporary facilities for hoisting wall components
[0112] Except for the upper part of the front wall and the upper part of the middle partition wall, all other components must be welded with lifting lugs on the upper and lower parts. Each component is supported by 4 lifting lugs, which are 800mm away from the pipe mouth. The lifting lugs are made of δ20mm steel plates.
[0113] 4.9 Review and marking of wall installation dimensions
[0114] Taking the 1000mm elevation line of the boiler steel frame as the benchmark, mark the elevation line of the header on the middle partition wall on the steel frame column. Marking of vertical and horizontal positioning dimensions: Mark the center line of the furnace, check whether the position of each suspender beam is consistent with the drawing size according to the symmetric center line of the boiler and the center line of the furnace, and mark the installation center line to ensure that the error is within the range required by the specification; mark the wall installation dimension line with the symmetric center line of the boiler and the center line of the furnace, and ensure that the error is within the range required by the specification.
[0115] 4.10 Wall installation and alignment
[0116] First, align the right side wall and the middle partition wall. After aligning and reinforcing the vertical and horizontal positioning dimensions of the upper header and aligning the pipe row joints, use 16# channel steel to reinforce the entire assembly.
[0117] After completing the alignment of the middle partition wall, the top wall is divided into two pieces for secondary hoisting into position, alignment, and welding. After the hanging device is installed and adjusted into place, the front and rear walls are reset for the second time, aligned, welded, and reinforced. The left wall is aligned after it has been lowered and hoisted again.
[0118] 4.10.1 Hoisting of left wall assembly
[0119] The weight of the left wall assembly is 44516kg, and it is hoisted by an 80t tower crane and a 280t crawler crane. After erection, the left wall assembly is hoisted separately by an 80t tower crane, dropped from the gap between MB-4 and MB-5 into the rear furnace, and temporarily suspended under the MB-5 plate beam. The suspension rope is φ42, L = 30m steel wire rope 2, four strands of force.
[0120] When lifting, the 80t tower crane has an operating radius of 28m, a rated load of 75.1t, an actual load of 25t, and a load factor of 33% (including the weight of 3t slings); the 280t crawler crane has an operating radius of 20m, a rated load of 49.6t, an actual load of 23t, and a load factor of 46% (including the weight of 1t slings). When in position, the 80t tower crane has an operating radius of 28m, a rated load of 75.1t, an actual load of 47.5t, and a load factor of 63% (including the weight of 3t slings). For details, see the attached Figure 1 Schematic diagram of left wall hoisting, there are multiple rigid beams 2 under the upper header 1, and below that is the lower header 3. A φ42 steel wire rope 8 is connected below the 80t tower crane hook 4, and a φ38 steel wire rope 6 and a single pulley 7 are connected below the 280t crawler crane hook 5.
[0121] 4.10.2 Hoisting of front wall
[0122] The weight of the upper component of the front wall is 20247kg, and the weight of the lower component of the front wall is 43610kg. The lower component is hoisted first, and then the upper component. The hoisting is carried out by using an 80t tower crane and a 20t crawler crane to lift it upright. After erection, the components on the front wall are hoisted separately by using an 80t tower crane, and airdropped from the gap between MB-4 and MB-5 into the rear furnace, and temporarily suspended under the MB-4 plate beam. The upper component suspension rope uses two φ28, L=30m steel wire ropes, and four strands are stressed. The lower component suspension rope uses two φ41, L=30m steel wire ropes, and four strands are stressed.
[0123] When lifting the components, the 80t tower crane has an operating radius of 35m, a rated load of 58t, an actual load of 13t, and a load factor of 23% (including the weight of 3t slings); the 280t crawler crane has an operating radius of 30m, a rated load of 25.3t, an actual load of 11t, and a load factor of 44% (including the weight of 1t slings). When in place, the 80t tower crane has an operating radius of 35m, a rated load of 58t, an actual load of 23t, and a load factor of 40% (including the weight of 3t slings).
[0124] 4.10.3 Lifting of ceiling wall
[0125] After the top wall assembly is completed, it is lifted separately by an 80t tower crane. After all the wall superheaters are hoisted, the secondary plate beam and the corresponding hanger beam between MB-4 and MB-5 are restored. Then, the rear wall assembly is formally put in place, the middle partition wall assembly is formally put in place, the front wall assembly is formally put in place, the left wall is temporarily suspended, and after the lower and lower pipe rows are hoisted, the left wall is formally put in place.
[0126] The hoisting of the right wall, rear wall and middle partition wall components shall be carried out according to the above method. Please refer to the attached hoisting diagram. Figure 2 Similarly, the front wall assembly 9 is also lifted by the 80t tower crane hook 4 and the 280t crawler crane hook 5.
[0127] 4.11 Rigid beam installation
[0128] 4.11.1 Inventory of Rigid Beam Equipment and Accessories
[0129] Rigid beams should be counted and numbered before installation. If there are front and back sides, they should be separated according to the drawings. The top and bottom sides of each rigid beam should be determined, and it should be checked whether the actual rigid beam is consistent with the design on the drawings and whether the layout of the vertical reinforcement is correct.
[0130] 4.11.2 Rigid beam-ground combination
[0131] For the convenience of transportation, the rigid beams are supplied in single pieces and need to be assembled on site. According to the working conditions of the crane, the rigid beams for the wall are assembled on the ground. The rigid beams are assembled strictly according to the technical requirements of the drawings. If there are any changes, they must be communicated with the technicians first. After confirmation by the technicians, partial changes can be made. The tension plates and connectors of the rigid beams can be pre-installed on the attached wall when assembled on the ground.
[0132] 4.11.3 Paying off
[0133] According to the elevation of the rigid beam, convert it into the relative distance between the rigid beams and the rigid beams and the tube row, and then draw lines on the tube row. When drawing lines, pay attention to the unity of the reference line, and at the same time draw the expansion zero point of the wall (i.e. the longitudinal center of the furnace).
[0134] 4.11.4 Horizontal rigid beam installation
[0135] The rigid beam is fixed by inserting the ear plate welded on the tube bank into the rigid beam connector. There is a 6mm gap between the angle steel of the rigid beam connector and the ear plate on the rigid beam. Install the tension plate or collection plate before installing the rigid beam connector.
[0136] 4.11.5 Installation of vertical rigid beams
[0137] There is a vertical rigid beam in the upper area of the two side walls respectively. The upper part of the vertical rigid beam is connected to the top wall balance device through a connecting piece at 59591mm, and the lower part is connected to the mounting part with bolts at 51280.
[0138] 4.11.6 Installation of corner devices
[0139] The corner connections between the rigid beams are fixed with pins, and the corner installation is carried out after the wall alignment is completed.
[0140] 4.11.7 Installation of guide device
[0141] The installation of the guide device must be carried out after the wall alignment and acceptance is completed. One part of the guide device is welded and fixed to the rigid beam, and the other part is welded and fixed to the steel beam.
[0142] 4.11.8 After the rigid beams are installed, the wall alignment is completed, and the overall acceptance by the supervisor is completed, the temporary lifting ears shall be cut off and polished, and the temporary hanging facilities shall be removed in time.
[0143] 4.12 Wall area sealing device
[0144] 4.12.1 The sealing of the wall area includes: the sealing device at the bottom of the wall, the through-wall seal of the wall superheater, the through-wall seal of the low-temperature reheater, and the top seal of the wall.
[0145] 4.12.2 The sealing of the wall area is made of comb plate δ4 and steel plate δ4 welded together.
[0146] 4.12.3 The sealed box should be filled with insulation or refractory materials
[0147] 4.12.4 When installing the seal, pay attention to the installation sequence of the seal and other equipment
[0148] (1) Before assembly, place all the tube rows on each side wall on the assembly rack with the fire side facing downwards. Spot weld the fins between the tube rows firmly. Check the opening and diagonal angles. Cut the corresponding joints when formally assembling.
[0149] (2) All pipe rows should be placed according to the identification numbers on the general drawing, and pay attention to their front and back, up and down, left and right directions. Check the drawings to confirm whether the positions of each door hole are correct to prevent incorrect placement of the pipe rows.
[0150] (3) After the pipe row is checked diagonally and found to be correct, limit blocks are welded on the assembly frame along the length direction to prevent the pipe row from shifting and deforming during the docking process.
[0151] (4) The interior of the header should be cleaned and the vertical and horizontal center lines should be marked before connection. It should be reinforced before connection, and the reinforcement should be firm and reliable.
[0152] (5) After the pipe row is assembled, the tension plate and the connecting device need to be installed. When installing the tension plate, pay attention to its welding height and welding length.
[0153] (6) When ground assembly is performed, a temporary bracket is installed at the lower part of the upper header of the wall-wrapped superheater and at the position where the pipe row is connected.
[0154] (7) Before assembling the furnace wall accessories (door holes), all parts should be counted and the appearance quality should be checked against the drawings. Alloy parts should be spectrally confirmed and stored in categories. Alloy parts should be installed in the correct position during installation and should not be installed incorrectly. During installation, attention should be paid to the seal between the heated surface and the installation position and direction should be correct and meet the requirements of the drawings. When installing the sealing box, it should be ensured that the vertical door holes of the casing and the pipe row are castings, and collision damage should be prevented during installation.
[0155] (8) After the wall-clad superheater is assembled, mark the tube screen of the wall-clad superheater according to the lifting sequence, and mark the upper and lower sections with a marker.
[0156] 5 Low temperature superheater installation
[0157] 5.1 The lower outlet header can be temporarily suspended on the steel frame at 64600mm behind the furnace, and the lower outlet header can be temporarily suspended on the steel frame at 74700mm behind the furnace.
[0158] 5.2 Tube row combination
[0159] First, weld the positioning angle steel on the assembly frame according to the drawings, with no less than 4 angles on each side to ensure the assembly size. Ensure that the first and second tube groups of the vertical section of the low-temperature superheater are assembled, and every 2 tube groups are assembled into one assembly, of which the first and second tube groups of the low-temperature superheater are assembled into 73 assemblies. Before the tube rows are aligned, confirm that the assembly is consistent with the requirements of the drawings according to the drawing numbers, and install the superheater anti-wear device on the ground. After the tube rows are assembled, they are uniformly numbered and then placed in the order of hoisting to prevent misplacement or random placement.
[0160] 5.3 Low temperature superheater hoisting
[0161] Before installing the low-pass, the left wall must be reserved. The two upper and lower pipe rows of the low-pass are assembled and hoisted. The weight of the assembly is about 4614kg. When assembling and hoisting the pipe rows, the factory-supplied pipe panel lifting tools are used. The 80t tower crane and 280t crawler crane are used to lift it upright. After erection, the low-temperature superheater assembly is lifted separately using an 80t tower crane, and airdropped from the gap between MB-4 and MB-5 and the reserved opening for slow installation on the left wall into the rear furnace. Then, the electric hoist hook arranged under the ceiling is used to officially put the low-pass in place. See the attached for details. Figure 3 The low temperature superheater 13 is airdropped through the 2t fall chain 12. Before airdropping, it is erected by the 80t tower crane hook 4 and the 280t crawler crane hook 5 with the help of φ19 steel wire rope 10 and φ15 steel wire rope 11.
[0162] 6. Medium temperature superheater installation
[0163] 6.1 Tube row combination
[0164] The medium-temperature superheater inlet and outlet distribution headers and tube screens are assembled on the ground. There are 64 medium-temperature superheaters in total with a total weight of 115,034 kg.
[0165] The installation of the sealing plugs between the tube panels must be completed before the tube panels are aligned. After each single tube panel is assembled, the sealing device must be installed before the header can be aligned. When installing the sealing device, the direction must be distinguished. After the tube panels are aligned, the pins in the pin area must be welded according to the requirements of the drawings.
[0166] 6.2 Lifting of medium temperature superheater.
[0167] The medium-temperature superheaters consist of 8 groups, each weighing 14,315 kg, and are airdropped into place from the furnace top.
[0168] 6.3 Temporary hanging of header: The lower header of the medium-temperature superheater needs to be temporarily hung outside the front wall of the water-cooled wall in advance, and then the connection can be carried out after the screen tube row passes through the front water.
[0169] 6.4 Alignment of the header Use a glass tube level to measure whether both ends of the header are horizontal, and use the plumb bob to check whether the header is placed correctly. Use a glass tube level to measure the center elevation of the header and the elevation of the support surface of the assembly frame. The center elevation of the header is higher than the elevation of the support surface of the assembly frame, and the value should be equal to the radius of the pipe. After alignment, use electric welding and angle steel to reinforce the header (electric welding cannot be used directly on the header) to prevent the header from rolling. Use an angle grinder and a grinding head to grind the welding grooves of the connecting pipes and the pipe row pipes on the header; clean the oil and rust on the welds until the metallic luster is revealed. Use a ruler to check the large and small diagonal dimensions of the header and the pipe row to make the pipe row perpendicular to the header. Before matching, confirm the numbering, positive and reverse directions of the pipe row again according to the drawing. According to the positions of the outermost pipe seats on both sides of the header, draw the position lines of the two pipes on the assembly frame. After the pipe row is checked diagonally at the opening and confirmed to be correct, weld limit blocks on the assembly frame along the length direction to prevent the pipe row from shifting and deforming during the docking process. After the tube panel is assembled, the pin area specified on the drawing must be welded with pins.
[0170] 6.5 Installation of medium temperature superheater tube row: The assembled tube row of the medium temperature superheater is hoisted by a 80t tower crane using the header lifting lug (or directly tying the small header). The medium temperature superheater is composed of 8 groups, each weighing 14315kg, and is airdropped from the furnace top to place. After the tube panel passes through the front wall, it is matched with the previously temporarily hung lower header, and the matching process is monitored. The matching fall chain can be loosened only after the weld heat treatment is completed.
[0171] 6.6 Overall dimension alignment: adjust the dimensions between the tube rows of each heating surface to be consistent with the design dimensions, and adjust the distance between the front tube row and the front wall of the furnace to 760mm. After the dimensions of each level of heating surface are adjusted in place, reinforcement should be carried out.
[0172] 7. High temperature superheater installation
[0173] The installation position and design form of the high-temperature superheater are basically the same as those of the medium-temperature superheater. It consists of 10 groups, each weighing 14,632 kg. It is airdropped from the top of the furnace into place. The installation method refers to the medium-temperature superheater.
[0174] 8. Installation and adjustment of superheater tube banks
[0175] After the alignment of the superheater tube bank and header is completed, the welding of the superheater tube group and header can be carried out. After the welding is completed, the gaps between the low-temperature superheater and the wall-wrapped superheater, the medium-temperature superheater and the water-cooled wall, the high-temperature superheater and the water-cooled wall, and the tube banks are inspected to meet the requirements of the drawings.
[0176] 9Superheater sealing, anti-wear and device installation
[0177] The sealing and anti-wear accessories of the superheater can be partially installed without affecting the lifting, welding and inspection of the superheater. If it affects the welding of the pipe row, it should be installed in time after the welding inspection is completed.
[0178] 10 Overall acceptance
[0179] After the superheater weld is completed, the gaps between the tube rows, between the tube rows and the wall, and between the water-cooled wall are adjusted. Then the acceptance work is carried out.
[0180] 11Installation of return device
[0181] Installation of the valve body of the return device. Three "U" valve return devices are designed in this phase, which are arranged under three cyclone separators and supported on the 27.7m layer of the boiler steel frame. After the positioning line of the return device is drawn, some steel beams at this position are slowly installed. After the return device is installed in place, it is installed. The installation adopts loose parts hoisting and combined installation at the installation position. The valve body of the return device is pre-stored with an 80t tower crane. After the combination is aligned, the riser and compensator of the return device are pre-stored and temporarily fixed. After the cyclone separator is installed, the sealing welding is carried out. The return pipe of the return device is pre-stored and aligned for welding. The installation of the return pipe is pre-stored from bottom to top.
[0182] 12 Cyclone separator assembly installation
[0183] 12.1 Pipeline ball
[0184] The cyclone separator tube screen is passed through and the header is cleaned. Since the bending radius of the conical tube row is not available in the design drawings, the ball diameter cannot be calculated for the time being. After the designer determines the bending radius of the pipe fittings, select the appropriate steel ball diameter for the ball test. The ball passers must have a clear division of labor, mark the pipes that the ball cannot pass through, check the reasons why the ball cannot pass through so as to deal with it. After the ball pass is completed, timely count and collect the steel balls, seal them, and make a visa.
[0185] 12.2 Installation of straight section and cone section tube screen combination of cyclone separator
[0186] The cyclone separator tube screen is composed of an inlet straight tube screen, a straight tube screen and a cone tube screen. There are 3 sets of inlet straight tube screens, weighing 27195kg, 27180kg and 27240kg respectively; there are 3 sets of straight tube screens, weighing 26475kg, 26582kg and 26475kg respectively; the cone tube screen is divided into an upper cone tube screen and a lower cone tube screen. The upper cone tube screen is divided into 3 sets, each weighing 24156kg, and the lower cone tube screen is divided into 3 sets, each weighing 13743kg.
[0187] The cyclone separator tube screen assembly method is ground assembly according to the inlet straight tube screen, straight tube screen, upper cone tube screen and lower cone tube screen. The assembly method is consistent with the wall-wrapped superheater assembly method, but because it is a membrane screen with an arc, in order to ensure that the assembled components meet the requirements of the drawings and specifications, additional temporary measures such as supports and brackets are required during assembly.
[0188] After the assembly is completed, use an 80t tower crane to lift it, and a 280t crawler crane to help lift it. After lifting it into place, close the seams and seal it according to the dimensions on the drawing. When closing the upper header of the cyclone separator, ensure the parallelism and concentric verticality of the header to avoid overall distortion of the tube screen. After welding and installing it with the upper header, weld it with the lower header of the cyclone separator. The lifting form refers to the wall-wrapped superheater.
[0189] 12.3 Pre-installation of cyclone separator inlet and outlet flues and steam cooling flues
[0190] 12.3.1 The inlet flue of the cyclone separator is pre-stored. There are 3 inlet flues in this unit, each weighing 15177kg. They are supplied as a whole. They are pre-stored with an 80t tower crane and temporarily suspended under a 64.6m steel beam. The hanging wire rope is protected with asbestos cloth, and the flue is protected with Φ16 round steel for secondary protection. Before the inlet flue of the cyclone separator is pre-stored, since the upper and lower headers of the inlet flue of the cyclone separator have been butt-welded before leaving the factory, it is impossible to conduct a ball inspection on the pipe row. Only the upper and lower headers of the cyclone separator can be inspected. The inside of the header is inspected with an endoscope and purged with compressed air. After confirming that the inside is clean, the pre-stored hoisting can be carried out.
[0191] 12.3.2 Cyclone separator outlet flue, this unit is designed with 3 pieces, each piece weighs 2653kg, arranged on the upper part of the central tube, and before installation, together with the central tube, it is pre-stored on the 64.6m steel beam by an 80t tower crane, and temporarily reinforced by spot welding with channel steel [10. After the central tube is installed in place, it can be installed in place.
[0192] 12.3.3 Three sets of steam-cooled flue units are designed, with single set weights of 44188kg, 38805kg and 44213kg respectively. As the weight of a single set of components is too heavy, and comprehensive consideration is given to the hoisting performance of various hoisting machinery on site, loose parts and rigid beams are used for hoisting during installation, and then the whole is assembled after they are in place.
[0193] 12.4 Pre-storage of the cyclone separator center tube
[0194] The cyclone separator center cylinder is pre-stored. There are 3 units in total. The cylinder diameter is 3849mm, the thickness is 12mm, the material is SA-240S30815, and the weight of a single unit is 5714kg. Before installation, the alloy parts need to be spectrally tested to confirm the material. When pre-stored, use an 80t tower crane to pre-store and temporarily store it on a 64.6m steel beam. Use channel steel [10 spot welding for temporary reinforcement. After the cyclone separator straight section and cone section assembly are pre-stored, the cyclone separator center cylinder is officially installed.
[0195] 12.5 Installation of hanging device
[0196] The hanging device is installed, and the hanging device is officially hung after the secondary plate beam and the hanger beam are installed. The hanger height is installed according to the actual elevation.
[0197] 12.6 Sealing device installation and overall alignment acceptance
[0198] 12.6.1 For sealing devices, perform sealing welding according to the requirements of the drawings, and perform oil penetration test after welding to check for leaks. If there are leaks, perform repair welding. After acceptance, perform concealed visa.
[0199] 12.6.2 Align the entire structure and conduct self-inspection according to the dimensions on the drawing. After the site inspection is qualified, notify Party A and the supervisor to conduct acceptance.
[0200] 13 Lifting equipment installation
[0201] 13.1 The hoisting of wall-wrapped superheater, low-temperature superheater, medium-temperature superheater, high-temperature superheater, cyclone separator, etc. is carried out by 80t tower crane
[0202] 13.2 The low-temperature superheater is hoisted into place by an 80t tower crane from the opening of the left wall of the furnace and hooked by an electric hoist arranged under the ceiling.
[0203] 13.3 Secondary slab beams BK-E-7 and 14 are slow to install; HBK-D-2, HBK-D-3, HBK-D-6 are slow to install; HBK-E-1, 4, 5, 6 are slow to install, as the entrance for electric hoist and later low over- and low re-lifting, the left side wall of the furnace is temporarily suspended on the top plate and not put into place.
[0204] 13.4 Lifting equipment Use I32a as a monorail beam, which is placed under the ceiling wall superheater. One is arranged in each superheater compartment and reheater compartment on both sides of the middle partition wall, which are arranged parallel to the middle partition wall. The ceiling superheater reserves a hole for the monorail beam lifting ear. The lifting ear passes through the ceiling superheater and is welded to the ceiling tube fin. Hang 7 10t chain hoists and 10t unloading cards from the front and rear secondary plate beams between the large plate beams D and F to lift the monorail beam. The two ends of the track are welded with steel plates for upper limit. If there is a joint in the middle, a web needs to be added at the joint; after installation, reinforce the two ends of the monorail with channel steel to prevent shaking during lifting. After the monorail is installed in place, the 16t electric hoist shall be tested and accepted in accordance with the specifications before use.
[0205] 14 Hoisting calculations for overheating system components
[0206] The wall-wrapped superheater and cyclone separator were assembled as required. All components were hoisted by a 80t tower crane and a 280t crawler crane. After the components were erected, the 80t tower crane was used to place the components in place or temporarily hang them.
[0207] The low-temperature superheater tube array is completed by using an 80t tower crane and a 280t crawler crane in conjunction with an electric hoist arranged under the ceiling.
[0208] The high-temperature superheater and medium-temperature superheater are hoisted by a 80t tower crane and a 280t crawler crane. The 80t tower crane then moves the components into place.
[0209] 14.1 Lifting performance of 80t tower crane
[0210] 14.2 Calculation of wire rope selection
[0211] The steel wire rope used for hoisting the overheating system is planned to be 6×37+ fiber core steel wire rope with an 8-fold safety factor. The diameter is calculated according to formula 6.2.6 in "Important Purpose Steel Wire Rope GB8918-2006".
[0212] 14.3 Statistics of hoisting of main components of superheating system
[0213] According to Articles 14.1 and 14.2 of this plan, the load rate of the overheating system component hoisting and the selection of wire ropes are calculated and statistically analyzed.
[0214] The above is only a preferred implementation of the present application. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the principles of the present application. These improvements and modifications should also be regarded as the scope of protection of the present application.
Claims
1. A combined installation construction method for a boiler unit superheating system, characterized in that: include: Step 1: Superheater assembly, installation and construction procedures; Step 2: Assembly and installation of cyclone separator and return device; The step one specifically includes: equipment inspection, ball passing, ground assembly, hanging device installation, wall-wrapped superheater installation, low-temperature superheater installation, medium-temperature superheater installation, high-temperature superheater installation, superheater tube row installation, adjustment, superheater sealing, and anti-wear device installation.
2. The combined installation construction method of the boiler unit superheating system according to claim 1 is characterized in that: The hanging device installation specifically includes: After the installation and alignment of the furnace roof steel structure is completed, the overheating system hanging device can be installed with the roof beam, hanger beam, or separately by using a lifting machine. Before hanging the hanger, number the hanger on the ground, and try to match the nut with the hanger thread and thread. When hanging the hanger, apply black lead powder or spray molybdenum disulfide on the threaded part of the hanger. If the thread of the hanger is damaged during the hanging process, repair it in time to ensure a smooth connection with the nut. After the hanger is hoisted into place, add a locking nut or tie it with wire to prevent free rotation and falling off. After the installation and adjustment of the superheater hanger, spot weld one place at the nut. When installing the hanger, the welding of the pin shaft should ensure that there is a certain gap between the ear plate and the lap plate, and the gap on both sides of each hanger must be guaranteed according to the drawing.
3. The combined installation construction method of the boiler unit superheating system according to claim 1 is characterized in that: The wall-wrapped superheater installation specifically includes: Ground combination: According to the on-site hoisting capacity and construction conditions, the wall components are divided into: the front wall and the rear wall are divided into two components according to the manufacturer's supply section, and the lower section component is combined with the lower header; the middle partition wall is divided into two components, and the upper and lower components each have a header; the top wall is combined into the front and rear components; the right wall is divided into two components, and the upper and lower components each have a header; the left wall is composed of upper and lower headers and pipe screens combined into a whole for hoisting; The assembly order is rear wall, right wall, middle partition wall, top wall, front wall, and left wall; Before assembly, place all the pipe rows on each side wall on the assembly rack with the fire side facing downwards, spot weld the fins between the pipe rows firmly, check the opening and diagonal angles, and cut the joints at the corresponding joint positions when formally assembled; All pipe rows should be placed according to the identification numbers on the general drawing, and pay attention to their front and back, up and down, left and right directions. Check the drawings to confirm whether the positions of each door hole are correct to prevent incorrect placement of pipe rows; After the pipe row is checked diagonally and found to be correct, the limit blocks are welded on the assembly frame along the length direction to fix it; Before the header is connected, the inside should be cleaned and the vertical and horizontal center lines should be marked. Before the header is connected, it should be reinforced and the reinforcement should be firm and reliable. Installation of furnace wall accessories: Before assembly, all parts should be counted and their appearance quality checked against the drawings. Alloy parts should be spectrally confirmed for material and stored in categories. Alloy parts should be installed in the correct position during installation and should not be installed incorrectly. During installation, attention should be paid to the seal between the heated surface and the correct installation position and direction. When installing the sootblower box, the casing should be vertical to the pipe row. The door holes are all castings and should be prevented from collision damage during installation. Temporary facilities for hoisting wall components: Except for the upper part of the front wall and the upper part of the middle partition wall, all other components must be welded with lifting lugs on the upper and lower parts. Each component is supported by 4 lifting lugs. Wall installation dimension review and marking: Take the elevation line of the boiler steel frame as the benchmark, and mark the elevation line of the header on the middle partition wall on the steel frame column; mark the center line of the furnace according to the vertical and horizontal positioning dimensions, and check whether the position of each suspender beam is consistent with the drawing dimensions according to the symmetric center line of the boiler and the center line of the furnace, and mark the installation center line to ensure that the error is within the range required by the specification; mark the wall installation dimension line according to the symmetric center line of the boiler and the center line of the furnace, and ensure that the error is within the range required by the specification; Wall installation and alignment: First, align the right side wall and the middle partition wall. After aligning and reinforcing the vertical and horizontal positioning dimensions of the upper header and aligning the pipe row joints, use channel steel to reinforce the entire assembly. After the alignment of the middle partition wall is completed, the top wall is divided into two pieces for secondary hoisting, alignment, and welding. After the hanging device is installed and adjusted in place, the front and rear wall are reset for the second time, alignment, welding, and reinforcement work is carried out; the left wall is aligned after the low pass and low re-hoisting is completed; Hoisting of left wall assembly: The tower crane and crawler crane are used to lift it up. After it is erected, the left wall assembly is lifted up by the tower crane alone, airdropped into the rear furnace, and temporarily suspended under the plate beam. Two steel wire ropes are used as the hanging rope, and four strands are stressed. Front wall hoisting: Prepare the components on the front wall and the components under the front wall, first hoist the lower components and then the upper components; use tower crane and crawler crane to lift and erect them, and then use the tower crane to lift the components on the front wall separately, drop them into the rear furnace, and temporarily hang them under the plate beam. The upper component hanging rope uses two φ28, L=30m steel wire ropes, four strands of force, and the lower component hanging rope uses two φ41, L=30m steel wire ropes, four strands of force; Ceiling wall hoisting: After the top wall assembly is completed, it is hoisted separately by a tower crane. After all the wall superheaters are hoisted, the secondary plate beam and the corresponding hanger beam are restored. Then, the rear wall assembly is formally put in place, the middle partition wall assembly is formally put in place, the front wall assembly is formally put in place, and the left wall is temporarily suspended; Rigid beam installation: Inventory of rigid beam equipment and accessories: The rigid beams should be counted and numbered before installation. If there is a distinction between the front and back, the front and back parts should be distinguished according to the drawings. The upper and lower sides of each rigid beam should be determined. Check whether the rigid beam is consistent with the design on the drawings and whether the layout of the vertical reinforcement is correct. Rigid beam ground combination: The rigid beams for the wall are assembled on the ground, and the rigid beams are assembled strictly according to the technical requirements of the drawings. The tension plates and connectors of the rigid beams can be pre-installed on the attached wall when assembled on the ground; According to the elevation of the rigid beam, convert it into the relative distance between the rigid beams and the rigid beams and the pipe row, and then draw lines on the pipe row. When drawing lines, pay attention to the unity of the reference line and draw the expansion zero point of the wall at the same time; Horizontal rigid beam installation: The rigid beam is fixed by inserting the ear plate welded on the tube bank into the rigid beam connector. There is a gap between the angle steel of the rigid beam connector and the ear plate on the rigid beam. The tension plate or the collecting plate is installed before installing the rigid beam connector. Installation of vertical rigid beams: There is a vertical rigid beam in the upper area of the two side walls respectively. The upper part of the vertical rigid beam is connected to the top wall balancing device through a connecting piece, and the lower part is connected to the mounting piece with a bolt piece; Installation of corner fixtures: The corner connection of the rigid beams is fixed by pins, and the installation of the corners is carried out after the wall is aligned; Guide installation: The installation of the guide device must be carried out after the wall alignment is completed. One end of the guide device is welded and fixed to the rigid beam, and the other end is welded and fixed to the steel beam; After the rigid beam is installed, the wall is aligned, and the overall inspection and acceptance by the supervisor is completed, the temporary hanging ears are cut off and polished, and the temporary hanging facilities are removed in time; Wall area sealing device: The sealing of the wall area includes: the sealing device at the bottom of the wall, the through-wall seal of the wall superheater, the through-wall seal of the low-temperature reheater, and the top seal of the wall; the sealing of the wall area is composed of comb plates and steel plates welded together; the sealing box should be filled with insulation or refractory materials.
4. The combined installation construction method of the boiler unit superheating system according to claim 1 is characterized in that: The low temperature superheater installation specifically includes: Pipe row combination: First, weld the positioning angle steel on the assembly frame according to the drawings, with no less than 4 angle steels on each side to ensure the assembly size; ensure that the first and second tube groups of the vertical section of the low-temperature superheater are assembled, and every 2 tube groups are assembled into one assembly, among which the first and second tube groups of the low-temperature superheater are assembled into 73 assemblies. Before the tube rows are aligned, confirm that the assembly is consistent with the requirements of the drawings according to the drawing numbers, and install the superheater anti-wear device on the ground. After the tube rows are assembled, they are uniformly numbered and then placed in the order of hoisting to prevent misplacement or random placement; Low temperature superheater hoisting: Before installing the low-pass, the left wall must be reserved. The two upper and lower tube rows of the low-pass must be assembled and then hoisted. When assembling and hoisting the tube rows, use the factory-supplied pipe panel lifting tools. Use tower cranes and crawler cranes to lift them upright. After erecting them, use the tower crane to lift the low-temperature superheater assembly alone, drop it into the rear furnace, and then use the electric hoist hook arranged under the ceiling to officially put the low-pass in place.
5. The combined installation construction method of the boiler unit superheating system according to claim 1 is characterized in that: The installation of the medium temperature superheater specifically includes: Tube row combination Assemble the inlet and outlet distribution headers and tube panels of the medium-temperature superheater on the ground; The installation of the sealing plugs between the tube panels must be completed before the tube panels are aligned. After each single tube panel is assembled, the sealing device must be installed before the header can be aligned. When installing the sealing device, the direction must be distinguished. After the tube panels are aligned, the pins in the pin area must be welded according to the drawing requirements; Medium temperature superheater hoisting: The medium-temperature superheaters consist of 8 groups, which are airdropped into place from the furnace top; Temporary hanging of header: The lower header of the medium-temperature superheater needs to be temporarily hung outside the front wall of the water-cooled wall in advance, and the interface can be made after the screen tube row passes through the front water; Use a glass tube level to measure whether both ends of the header are level, and use a plumb bob to check whether the header is aligned; use a glass tube level to measure the center elevation of the header and the elevation of the support surface of the assembly frame. The center elevation of the header is higher than the elevation of the support surface of the assembly frame, and the value should be equal to the radius of the pipe; after alignment, use electric welding and angle steel to reinforce the header; use an angle grinder and a grinding head to grind the welding grooves of the connecting pipes and pipe rows on the header; clean the oil and rust on the welds until the metallic luster is revealed; use a ruler to align the header. Check the size of the large and small diagonal dimensions of the box and the tube row to make the tube row perpendicular to the header; confirm the number, positive and negative directions of the tube row according to the drawing before docking; draw the position lines of the two pipes on the assembly frame according to the positions of the outermost tube seats on both sides of the header. After the diagonal check of the tube row is correct, weld the limit blocks on the assembly frame along the length direction to prevent the tube row from shifting and deforming during the docking process. After the tube panel is assembled, the pin area specified on the drawing must be welded with pins; Installation of medium-temperature superheater tube row: The assembled tube row of the medium-temperature superheater is hoisted by a single tower crane using the header lifting ears or directly bundling with a small header. The medium-temperature superheater is composed of 8 groups in total, which are dropped into place from the furnace top. After the tube panel passes through the front wall, it is aligned with the previously temporarily hung lower header, and attention should be paid to monitoring the alignment process. The alignment fall chain can be loosened only after the heat treatment of the weld is completed.
6. The combined installation construction method of the boiler unit superheating system according to claim 1, characterized in that: The superheater pipe installation specifically includes: After the alignment of the superheater tube row and the header is completed, the welding work of the superheater tube group and the header can be carried out. After the welding is completed, the gaps between the low-temperature superheater and the wall-clad superheater, the medium-temperature superheater and the water-cooled wall, the high-temperature superheater and the water-cooled wall, and the tube rows are inspected to meet the requirements of the drawings.
7. The combined installation construction method of the boiler unit superheating system according to claim 1 is characterized in that: In the step 2, the installation of the material return device specifically includes: The valve body of the return device is installed. The three return devices are arranged under the three cyclone separators respectively and supported on the boiler steel frame. After the positioning line of the return device is drawn, some steel beams at this position are slowly installed. After the return device is installed in place, it is installed. The installation adopts loose parts lifting and combined installation is carried out at the installation position. The valve body of the return device is pre-stored with a tower crane. After the combination is aligned, the riser and compensator of the return device are pre-stored and temporarily fixed. After the cyclone separator is installed, sealing welding is carried out. The return pipe of the return device is pre-stored and aligned for welding. The return pipe is pre-stored from bottom to top.
8. The combined installation construction method of the boiler unit superheating system according to claim 1 is characterized in that: In the step 2, the installation of the cyclone separator specifically includes: Pipeline ball: Pass the balls through the cyclone separator tube screen and clean the header; Choose the appropriate diameter of the steel ball for the ball-passing test. After the ball-passing test is completed, count and collect the steel balls in time, seal them and make a visa. Combination installation of straight section and cone section tube screen of cyclone separator: The cyclone separator tube screen is composed of an inlet straight tube screen, a straight tube screen and a cone tube screen; there are 3 sets of inlet straight tube screens; there are 3 sets of straight tube screens; the cone tube screen is divided into an upper cone tube screen and a lower cone tube screen, the upper cone tube screen is divided into 3 sets, and the lower cone tube screen is divided into 3 sets; The cyclone separator tube screen assembly method is ground assembly according to the inlet straight tube screen, straight tube screen, upper cone tube screen and lower cone tube screen. Its assembly method is consistent with that of the wall-wrapped superheater. However, because it is a membrane screen with an arc, in order to ensure that the assembly components meet the requirements of the drawings and specifications, additional support, brackets and other temporary measures are required during assembly. After the assembly is completed, use a tower crane to hoist it, and crawler crane to lift it together; after hoisting it into place, close the seams and seal it according to the dimensions on the drawing; when closing the upper header of the cyclone separator, ensure the parallelism and concentric verticality of the header to avoid the overall distortion of the tube screen; after welding and installing it with the upper header, weld it with the lower header of the cyclone separator. The hoisting method refers to the wall-wrapped superheater; Pre-installation of the inlet and outlet flues of the cyclone separator and the steam cooling flue; The inlet flue of the cyclone separator is pre-stored. There are a total of 3 inlet flues in this unit. They are pre-stored with a tower crane and temporarily suspended under the steel beam. The hanging wire rope is protected with asbestos cloth, and the flue is protected again with round steel. Before the inlet flue of the cyclone separator is pre-stored, the upper and lower headers of the cyclone separator have been welded before leaving the factory, so it is impossible to conduct a ball inspection on the pipe row. Only the upper and lower headers of the cyclone separator can be inspected. The inside of the header is inspected with an endoscope and purged with compressed air. After confirming that the inside is clean, the pre-storage hoisting can be carried out. The cyclone separator outlet flue is designed with 3 parts in total and is arranged on the upper part of the central tube. Before installation, it is pre-stored on the steel beam together with the central tube by a tower crane and temporarily reinforced by spot welding with channel steel. It will be installed in place after the central tube is installed in place. A total of 3 sets of steam-cooled flue units are designed. During installation, loose parts and rigid beams are used for hoisting, and then the whole assembly is carried out after they are in place; Cyclone separator center tube pre-storage: The center tube of the cyclone separator is pre-stored. There are a total of 3 pieces in this unit. Before installation, the alloy parts need to be spectrally tested to confirm the material. A tower crane is used for pre-storage and it is temporarily stored on a steel beam and temporarily reinforced with channel steel spot welding. After the pre-storage of the straight section and cone section assembly of the cyclone separator is completed, the center tube of the cyclone separator will be officially installed.