Lifting rod simulated wind load testing device
Through the cooperation of the data acquisition module and the synchronous lifting module, laser ranging, inertial measurement and torsion sensors are used to collect data in real time, and the servo motor and electric winch are combined to apply tension to the lifting rod, which solves the problem that traditional testing devices cannot detect the height of the lifting rod in real time. , improving measurement accuracy.
Patent Information
- Application Number
- CN202410893515.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-04
- Publication Date
- 2024-10-15
AI Technical Summary
The traditional lift pole simulated wind load test device cannot detect the actual height of the top of the lift pole in real time, resulting in inaccurate measurement data.
Using the data acquisition module, control module, synchronous lifting module and force application module, the height, displacement and torsion force data of the top of the lifting rod are collected in real time through the laser ranging sensor, inertial measurement unit and torque sensor, and combined with the servo motor and electric winch to perform the lifting operation. The force module is adjusted to achieve accurate application of tension and measurement of the lifting rod.
It achieves real-time detection of the actual height of the lifting rod when it is bent, improves the accuracy of measurement data, and avoids the inaccuracy of traditional camera methods.
Smart Images

Figure CN118776945A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of lifting rod detection, and in particular to a lifting rod simulated wind load testing device. Background Art
[0002] The simulated wind load test of the lifting rod refers to applying a uniform wind load to the lifting rod under experimental simulated wind load conditions to evaluate the deformation of the equipment in the test and the overall connection and fixation. It is generally divided into two methods: static wind load test and dynamic wind load test.
[0003] As attached Figure 1 As shown, the traditional lifting rod simulation wind load test device mostly uses the ground to drive the drum to rotate through the motor to generate torque, and transmits the force to the air through the pulley set and wire rope, applies tension to the top of the lifting rod, records the tension through the sensor, and records the displacement of the top of the lifting rod through the camera;
[0004] The above-mentioned test device has the problem that after the top is subjected to tension, the lifting rod bends, thereby causing the height of the top of the lifting rod to decrease, and the test device cannot obtain the actual height after the change. Summary of the invention
[0005] In view of the deficiencies in the prior art, the present invention provides a lifting rod simulated wind load testing device, which solves the problems in the prior art.
[0006] According to an embodiment of the present invention, a lifting rod simulated wind load test device comprises:
[0007] Data acquisition module, control module, synchronous lifting module, collector and multiple force application modules;
[0008] A synchronous lifting module is provided with a force-applying module for driving the movement of multiple force-applying modules and adjusting the positions of the force-applying modules; wherein the force-applying module is used to apply a pulling force to the lifting rod to simulate the influence of wind load on the lifting rod;
[0009] The force-applying module is arranged on the synchronous lifting module, a plurality of force-applying modules are stacked, and the collector is arranged on the top of the lifting rod;
[0010] The data acquisition module is used to obtain test data, collect height data of the top of the lifting rod through a collector, and collect test result data during the test of the lifting rod;
[0011] The control module is used to control the synchronous lifting module to adjust the positions of multiple force-applying modules according to the height data, and to control the force-applying modules and the lifting rods to complete the test according to the test data.
[0012] As an embodiment of the present invention, the collector includes:
[0013] Laser distance measuring sensor, the force application module and the top of the lifting rod are both provided with laser distance measuring sensors, and the laser distance measuring sensor is electrically connected to the data acquisition module;
[0014] An inertial measurement unit is arranged at the top of the lifting rod, and the inertial measurement unit is electrically connected to the data acquisition module;
[0015] The torque sensor is arranged at the top of the lifting rod, and the torque sensor is electrically connected to the data acquisition module.
[0016] As an embodiment of the present invention, the data acquisition module performs the following operations:
[0017] Obtain management input on testing requirements;
[0018] Different laser distance measuring sensors are used to respectively collect the height information of the top of the lifting rod and multiple force application modules in real time to obtain height data and multiple adjustment height data;
[0019] The horizontal displacement of the top of the lifting rod during the test is collected by the inertial measurement unit to obtain displacement data;
[0020] The torque sensor collects the torsional force on the top of the lifting rod during the test to obtain torque data;
[0021] The test result data of the top end of the lifting rod is determined based on the height data, displacement data and torque data.
[0022] As an embodiment of the present invention, the synchronous lifting module includes:
[0023] Iron towers, two adjacent iron towers are arranged in parallel, the tops of the two adjacent iron towers are connected by a corridor, and two adjacent iron towers are provided with two parallel guide rails, and the guide rails on the two adjacent iron towers are arranged oppositely;
[0024] Pulling components, multiple pulling components are arranged at the top of the corridor, the pulling components are connected to the force application module, and the pulling components include:
[0025] The servo motor is arranged at the top of the corridor. The servo motor is connected to the input end of the reducer through transmission. The output end of the reducer is connected to the steel rope drum. The steel rope of the steel rope drum passes around the roller and passes through the corridor to be connected to the force module. The servo motor is electrically connected to the control module.
[0026] As an embodiment of the present invention, the force application module includes:
[0027] An intermediate lifting platform, wherein the intermediate lifting platform is slidably connected between two adjacent guide rails, and the top of the intermediate lifting platform is connected to the steel rope of the steel rope drum;
[0028] An electric winch is arranged on the middle lifting platform, a pull rope is wound around the electric winch, a hook is arranged on the pull rope, and the electric winch is electrically connected to the control module;
[0029] A force applying tooling is arranged at the top of the lifting rod, and a plurality of test connection holes are arranged on the force applying tooling, and the test connection holes are adapted to the hooks;
[0030] A safety locking mechanism is arranged at both ends of the intermediate lifting platform, and the safety locking mechanism is electrically connected to the control module.
[0031] As an embodiment of the present invention, the test data includes: a plurality of groups of test sub-data, the test sub-data including: test height data and tension data;
[0032] The control module performs the following operations:
[0033] Adjust the length of the lifting rod according to the test height data;
[0034] Control the servo motor of the synchronous lifting module to start and adjust the height of the force application module;
[0035] According to the tension data, the motor of the electric winch is controlled to start, and tension is applied to the top of the lifting rod to complete a set of test sub-data tests;
[0036] Repeat the above steps to complete the testing of all test sub-data.
[0037] As an embodiment of the present invention, controlling the servo motor of the synchronous lifting module to start and adjusting the height of the force application module includes:
[0038] Obtain the height data of the top of the lifting rod adjusted to the test height data, input the height data into the force-applying module height model, obtain the target height data of multiple force-applying modules, control the servo motor of the synchronous lifting module to start according to the target height data, adjust the adjustment height data of the force-applying module to be consistent with the target height data, and complete the height adjustment of the force-applying module.
[0039] As an embodiment of the present invention, it also includes:
[0040] The test report generating module is electrically connected to the data acquisition module and the control module respectively, and is used to generate a test result report according to the test result data and the test data.
[0041] Compared with the prior art, the present invention has the following beneficial effects: the height data of the top of the lifting rod during the test is collected in real time by a collector arranged at the top of the lifting rod. When the top of the lifting rod is subjected to tension and the lifting rod bends, resulting in a decrease in the height of the top of the lifting rod, the actual height of the top of the lifting rod can still be detected in real time. At the same time, during the test, after the lifting rod receives tension, the traditional camera method is avoided to detect the displacement of the top of the lifting rod, thereby improving the accuracy of the data. BRIEF DESCRIPTION OF THE DRAWINGS
[0042] Figure 1 Schematic diagram of a conventional lifting rod simulating wind load test device in the background technology of the present invention
[0043] Figure 2 It is a structural schematic diagram of an embodiment of the present invention;
[0044] Figure 3 It is a structural schematic diagram of a force application module according to an embodiment of the present invention;
[0045] Figure 4 It is a structural schematic diagram of a synchronous lifting module according to an embodiment of the present invention;
[0046] Figure 5 It is a structural schematic diagram of a force applying tooling according to an embodiment of the present invention;
[0047] Figure 6 It is a module schematic diagram of an embodiment of the present invention. DETAILED DESCRIPTION
[0048] The technical solution of the present invention is further described below in conjunction with the accompanying drawings and embodiments.
[0049] like Figure 2-Figure 6 As shown, an embodiment of the present invention provides a lifting rod simulated wind load test device, comprising:
[0050] Data acquisition module, control module, synchronous lifting module, collector and multiple force application modules;
[0051] A synchronous lifting module is provided with a force-applying module for driving the movement of multiple force-applying modules and adjusting the positions of the force-applying modules; wherein the force-applying module is used to apply a pulling force to the lifting rod to simulate the influence of wind load on the lifting rod;
[0052] The force-applying module is arranged on the synchronous lifting module, a plurality of force-applying modules are stacked, and the collector is arranged on the top of the lifting rod;
[0053] The data acquisition module is used to obtain test data, collect height data of the top of the lifting rod through a collector, and collect test result data during the test of the lifting rod;
[0054] A control module, used to control the synchronous lifting module to adjust the positions of multiple force-applying modules according to the height data, and to control the force-applying modules and the lifting rods to complete the test according to the test data;
[0055] The working principle of the above technical solution is as follows: in actual use, the test data uploaded by the management personnel is obtained, and the height data of the top of the lifting rod is collected in real time through the collector; then the control module controls the synchronous lifting module to drive the force-applying module to correspond to the position of the top of the lifting rod according to the height data, and then controls the force-applying module and the lifting rod to complete the test according to the test data; wherein, during the process of the force-applying module applying force to the lifting rod, the force-applying module applies tension to multiple positions of the lifting rod to achieve the effect of simulating the surface force applied by the wind load; and during the process of adjusting the position of the force-applying module, there will always be a force-applying module applying tension to the top of the lifting rod for testing;
[0056] After the test is completed, the test result data obtained by the test data input by the management personnel will be sorted out and a test report will be generated for display;
[0057] The beneficial effects of the above technical solution: through the above technical solution, the height data of the top of the lifting rod during the test is collected in real time by the collector arranged at the top of the lifting rod. When the top of the lifting rod is bent by the tension and the height of the top of the lifting rod is reduced, the actual height of the top of the lifting rod can still be detected in real time. At the same time, during the test, after the lifting rod receives the tension, the traditional camera method is avoided to detect the displacement of the top of the lifting rod, thereby improving the accuracy of the data.
[0058] In one embodiment, the collector includes:
[0059] Laser distance measuring sensor, the force application module and the top of the lifting rod are both provided with laser distance measuring sensors, and the laser distance measuring sensor is electrically connected to the data acquisition module;
[0060] An inertial measurement unit is arranged at the top of the lifting rod, and the inertial measurement unit is electrically connected to the data acquisition module;
[0061] The torque sensor is arranged at the top of the lifting rod, and the torque sensor is electrically connected to the data acquisition module;
[0062] The data acquisition module performs the following operations:
[0063] Obtain management input on testing requirements;
[0064] Different laser distance measuring sensors are used to respectively collect the height information of the top of the lifting rod and the force application module in real time to obtain height data and adjust the height data;
[0065] The horizontal displacement of the top of the lifting rod during the test is collected by the inertial measurement unit to obtain displacement data;
[0066] The torque sensor collects the torsional force on the top of the lifting rod during the test to obtain torque data;
[0067] Determine the test result data of the top end of the lifting rod according to the height data, displacement data and torque data;
[0068] The working principle of the above technical solution is as follows: in actual use, when the lifting rod is tested according to the test strategy, the height of the top of the lifting rod is measured by a laser ranging sensor, which is installed on the plumb bob mechanism at the top of the lifting rod so that its laser beam direction is always vertically downward, so that the height information of the lifting rod can be measured to obtain the height data; at the same time, the height information of the force module is measured by another laser ranging sensor to obtain the adjustment height data, and the horizontal displacement of the top of the lifting rod is measured by the inertial measurement unit, wherein the inertial measurement unit uses the inertial measurement unit widely used in aerospace, has a high degree of integration, and has a built-in three-axis gyroscope and a three-axis accelerometer; it can measure the speed, position, attitude of the top of the lifting rod, and output the compensated angular velocity, acceleration, temperature and other information;
[0069] A high-precision MEMS inertial measurement unit is installed at the top of the lifting rod. The inertial measurement unit consists of an accelerometer and a gyroscope. The accelerometer can detect the acceleration during the simulated wind load test in real time. By performing integral calculations, the horizontal displacement can be obtained with a measurement accuracy of 0.5mm, and the measured value can be displayed in real time. The gyroscope can also measure the real-time value of the top inclination during the inclination test with a measurement accuracy of 0.5' and a measurement range of 0-360°. The coordinate value of the top of the rod can be calculated through the distance between the top of the rod and the ground in the vertical direction, thereby fitting a motion trajectory of the top of the lifting rod.
[0070] The high-precision MEMS inertial measurement unit communicates with the host computer via RS485. RS485 has the advantage of long-distance communication and can meet the needs of long-distance data transmission. The high-precision MEMS inertial measurement unit and the data acquisition module send and respond to commands through the communication protocol.
[0071] The BW-MINS500 high-reliability MEMS accelerometer and gyroscope from North Micro Sensor is used. The attitude information data deviation is estimated accordingly through a 6-state Kalman filter with appropriate gain, and the measurement accuracy is guaranteed by the algorithm. The attitude motion parameters are compensated by nonlinear compensation, orthogonal compensation, temperature compensation, drift compensation, etc., which can greatly eliminate errors and improve the product accuracy level.
[0072] By providing a torque sensor, when the lifting rod is subjected to a cumulative backlash test between pipes, the torque sensor collects the torsional force at the top of the lifting rod during the test to obtain torque data;
[0073] The beneficial effects of the above technical solution are as follows: by installing a laser ranging sensor on the top of the lifting rod to measure the height of the top of the lifting rod, when the top of the lifting rod is subjected to tension and the lifting rod bends, thereby causing the height of the top of the lifting rod to decrease, the actual height of the top of the lifting rod can still be detected in real time; through the inertial measurement unit, the displacement of the top of the lifting rod can be accurately detected after the lifting rod receives horizontal tension, thereby improving the accuracy of the data.
[0074] In one embodiment, the synchronous lifting module 2 includes:
[0075] Iron towers, two adjacent iron towers are arranged in parallel, the tops of the two adjacent iron towers are connected by a corridor 1, two adjacent iron towers are provided with two parallel guide rails 3, and the guide rails 3 on the two adjacent iron towers are arranged oppositely;
[0076] The servo motor 10 is arranged at the top of the corridor 1. The servo motor 10 is connected to the input end of the reducer 11 by transmission. The output end of the reducer 11 is connected to the rope drum 9. The rope of the rope drum 9 passes through the roller 12 and passes through the corridor to connect to the force module 1. The servo motor 10 is electrically connected to the control module.
[0077] The working principle and beneficial effects of the above technical solution: in actual use, the tops of two adjacent towers are connected by a corridor 1, and two guide rails 3 extend from the bottom to the top, and are connected to the towers at intervals to ensure the strength of the guide rails 3; and three power systems are arranged at the top of the corridor 1, and the power system is distributed with a servo motor 10, a reducer 11, and a steel rope drum 9. The servo motor 10, the reducer 11, and the steel rope drum 9 are combined into a whole and placed above the tower corridor 1, which is convenient for maintenance and can also be protected from rain and sun by the tower roof; the three servo motors 10 are arranged in three layers and fixed by a bracket, and the steel rope is connected to the lower force module 4 through a guide wheel for adjusting the position of the force module 4.
[0078] In one embodiment, the force application module 4 includes:
[0079] An intermediate lifting platform 5, wherein the intermediate lifting platform 5 is slidably connected between two adjacent guide rails 3, and the top of the intermediate lifting platform 5 is connected to the steel rope of the steel rope drum 9;
[0080] An electric winch 8, which is arranged on the intermediate lifting platform 5, a pull rope is wound around the electric winch 8, a hook is arranged on the pull rope, and the electric winch 8 is electrically connected to the control module;
[0081] A force applying tool 13, which is arranged at the top of the lifting rod, and is provided with a plurality of test connection holes 15, which are adapted to the hooks; the force applying tool 13 is installed at the top of the lifting rod through a plurality of installation holes 14;
[0082] The working principle and beneficial effects of the above technical solution are as follows: the shape of the intermediate lifting platform 5 is rectangular, and four composite bearings are installed on the intermediate lifting platform 5. The composite bearings are distributed in the four corners of the intermediate lifting platform 5. The composite bearings are slidably connected to the guide rail 3. Two safety locking mechanisms are arranged between the two composite bearings. When the intermediate lifting platform 5 rises to a certain height, the safety locking mechanism fixes the entire platform at this position to prevent sliding up and down. The lifting rope is connected to the top of the intermediate lifting platform 5, and the electric winch 8 is installed in the middle of the intermediate lifting platform 5; during the test, the hook is hung in the test connection hole 15 set on the force-applying tooling 13, and the test connection hole 15 is divided into a test hole for cumulative backlash between pipes and a test hole for simulated wind load; wherein, the lifting rod is provided with a plurality of hook rings for connecting with the hook, so that the hook of the force-applying module is hung in the hook ring for testing; and a dynamometer is provided between the hook and the steel rope of the force-applying module, which is used to detect the tension applied by the force-applying module to the lifting rod, and transmit the tension data to the control module through the data acquisition module; the dynamometer is provided with a wireless network communication module, which is used to complete the data transmission between the dynamometer and the data acquisition module.
[0083] In one embodiment, the test data includes: a plurality of groups of test sub-data, the test sub-data including: test height data and tension data;
[0084] The control module performs the following operations:
[0085] Adjust the length of the lifting rod according to the test height data;
[0086] Control the servo motor of the synchronous lifting module to start, adjust the height of the force module, and keep the height of the force module level with the top of the lifting rod;
[0087] According to the tension data, the motor of the electric winch is controlled to start, and tension is applied to the top of the lifting rod to complete a set of test sub-data tests;
[0088] Repeat the above steps to complete the testing of all test sub-data;
[0089] The working principle and beneficial effects of the above technical solution: During the actual test process, the control module adjusts the length of the lifting rod according to the test height data, so that when the height of the top of the lifting rod reaches the test height data, the servo motor is controlled to drive the force module to move, so that the force module and the top of the lifting rod are kept at the same height; then the motor of the electric winch in the force module is controlled to start according to the test tension data, and the tension specified in the test strategy is applied to the top of the lifting rod, thereby completing the test.
[0090] In one embodiment, controlling the servo motor of the synchronous lifting module to start and adjusting the height of the force applying module includes:
[0091] Obtain the height data of the top of the lifting rod adjusted to the test height data, input the height data into the force-applying module height model, obtain the target height data of multiple force-applying modules, control the servo motor of the synchronous lifting module to start according to the target height data, adjust the adjustment height data of the force-applying module to be consistent with the target height data, and complete the height adjustment of the force-applying module.
[0092] The working principle and beneficial effects of the above technical solution: During the actual test process, a pulling force is applied to the lifting rod through a force-applying module to simulate the influence of wind load on the lifting rod, and the influence of wind load on the lifting rod is a surface influence, so generally a plurality of force-applying modules are used to apply force together; therefore, before conducting the test, it is necessary to adjust the position heights of a plurality of force-applying modules, and obtain the height data of the top end of the lifting rod adjusted to the test height data, input the height data into the height model of the force-applying module, obtain the target height data of a plurality of force-applying modules, arrange the obtained multiple height data from large to small, and thereby obtain the target height data of each force-applying module from high to low, according to The target height data controls the start-up of the servo motor of the synchronous lifting module, and adjusts the adjustment height data of the force-applying module to be consistent with the target height data, thereby completing the height adjustment of the force-applying module; wherein, the training process of the height model of the force-applying module is as follows: a number of sample data are obtained, and the sample data include multiple groups of training data, and a group of training data includes height data and multiple target height data; the height data in the sample data is used as input, and the multiple target height data are used as expected outputs, and are input into the basic neural network model for training until the model converges to obtain the height model of the force-applying module; wherein, the sample data is set based on historical data or expert opinions.
[0093] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that the technical solution of the present invention can be modified or replaced by equivalents without departing from the purpose and scope of the technical solution of the present invention, which should be included in the scope of the claims of the present invention.
Claims
1. A lifting rod simulated wind load test device, characterized in that: include: Data acquisition module, control module, synchronous lifting module, collector and multiple force application modules; A synchronous lifting module is provided with a force-applying module for driving the movement of multiple force-applying modules and adjusting the positions of the force-applying modules; wherein the force-applying module is used to apply a pulling force to the lifting rod to simulate the influence of wind load on the lifting rod; The force-applying module is arranged on the synchronous lifting module, a plurality of force-applying modules are stacked, and the collector is arranged on the top of the lifting rod; The data acquisition module is used to obtain test data, collect height data of the top of the lifting rod through a collector, and collect test result data during the test of the lifting rod; The control module is used to control the synchronous lifting module to adjust the positions of multiple force-applying modules according to the height data, and to control the force-applying modules and the lifting rods to complete the test according to the test data.
2. A lifting rod simulated wind load test device as claimed in claim 1, characterized in that: The collector comprises: Laser distance measuring sensor, the force application module and the top of the lifting rod are both provided with laser distance measuring sensors, and the laser distance measuring sensor is electrically connected to the data acquisition module; An inertial measurement unit is arranged at the top of the lifting rod, and the inertial measurement unit is electrically connected to the data acquisition module; The torque sensor is arranged at the top of the lifting rod, and the torque sensor is electrically connected to the data acquisition module.
3. A lifting rod simulated wind load test device as claimed in claim 2, characterized in that: The data acquisition module performs the following operations: Obtain management input on testing requirements; Different laser distance measuring sensors are used to respectively collect the height information of the top of the lifting rod and multiple force application modules in real time to obtain height data and multiple adjustment height data; The horizontal displacement of the top of the lifting rod during the test is collected by the inertial measurement unit to obtain displacement data; The torque sensor collects the torsional force on the top of the lifting rod during the test to obtain torque data; The test result data of the top end of the lifting rod is determined based on the height data, displacement data and torque data.
4. A lifting rod simulated wind load test device as claimed in claim 1, characterized in that: The synchronous lifting module comprises: Iron towers, two adjacent iron towers are arranged in parallel, the tops of the two adjacent iron towers are connected by a corridor, and two adjacent iron towers are provided with two parallel guide rails, and the guide rails on the two adjacent iron towers are arranged oppositely; Pulling components, multiple pulling components are arranged at the top of the corridor, the pulling components are connected to the force application module, and the pulling components include: The servo motor is arranged at the top of the corridor. The servo motor is connected to the input end of the reducer by transmission. The output end of the reducer is connected to the steel rope drum. The steel rope of the steel rope drum passes around the roller and passes through the corridor to be connected to the force module. The servo motor is electrically connected to the control module.
5. A lifting rod simulated wind load test device as claimed in claim 4, characterized in that: The force application module comprises: An intermediate lifting platform, wherein the intermediate lifting platform is slidably connected between two adjacent guide rails, and the top of the intermediate lifting platform is connected to the steel rope of the steel rope drum; An electric winch is arranged on the middle lifting platform, a pull rope is wound around the electric winch, a hook is arranged on the pull rope, and the electric winch is electrically connected to the control module; A force applying tooling is arranged at the top of the lifting rod, and a plurality of test connection holes are arranged on the force applying tooling, and the test connection holes are adapted to the hooks; A safety locking mechanism is arranged at both ends of the intermediate lifting platform, and the safety locking mechanism is electrically connected to the control module.
6. A lifting rod simulated wind load test device as claimed in claim 5, characterized in that: The test data includes: several groups of test sub-data, the test sub-data includes: test height data and tension data; The control module performs the following operations: Adjust the length of the lifting rod according to the test height data; Control the servo motor of the synchronous lifting module to start and adjust the height of the force application module; According to the tension data, the motor of the electric winch is controlled to start, and tension is applied to the top of the lifting rod to complete a set of test sub-data tests; Repeat the above steps to complete the testing of all test sub-data.
7. A lifting rod simulated wind load test device as claimed in claim 6, characterized in that Control the servo motor of the synchronous lifting module to start and adjust the height of the force module, including: Obtain the height data of the top of the lifting rod adjusted to the test height data, input the height data into the force-applying module height model, obtain the target height data of multiple force-applying modules, control the servo motor of the synchronous lifting module to start according to the target height data, adjust the adjustment height data of the force-applying module to be consistent with the target height data, and complete the height adjustment of the force-applying module.
8. The lifting rod simulated wind load test device according to claim 1, characterized in that: Also includes: The test report generating module is electrically connected to the data acquisition module and the control module respectively, and is used to generate a test result report according to the test result data and the test data.