Welding material supply management method
By establishing a shipbuilding carrying network tree and schedule tree, classifying welds and counting welding material quantities, the problems of accumulation and functional impairment in welding material management are solved, and the efficient utilization of the welding material warehouse and real-time demand satisfaction are achieved.
Patent Information
- Application Number
- CN202410921300.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-10
- Publication Date
- 2024-10-15
AI Technical Summary
The traditional management method of welding materials causes the welding materials to accumulate in the warehouse, wasting storage capacity, and causing damage to the function of the welding materials due to long-term storage, and cannot effectively meet the real-time demand for welding materials during the shipbuilding process.
By establishing a shipbuilding network tree and a schedule tree, we can classify welds and count the quantity of welding materials. We can establish welding material procurement and storage rules based on demand time nodes and quantities to ensure that there is sufficient reserve of welding materials in the warehouse and avoid early purchase and storage. All welding consumables.
It improves the storage capacity of the welding material warehouse, reduces the welding material accumulation time and inventory, ensures that the function of the welding material is not damaged, and meets the real-time welding material demand during the ship building process.
Smart Images

Figure CN118780723A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of welding material supply, and in particular to a welding material supply management method. Background Art
[0002] During the shipbuilding process, the amount of welding materials is very large. The types of welding materials required vary according to the thickness, material, welding method, welding posture, etc. of the welded components. And according to the requirements of the entire shipbuilding cycle, the demand for welding materials varies greatly in different periods. Traditional welding material management does not prepare welding materials according to the real-time needs of shipbuilding, but adopts a large number of stacking methods, which seriously wastes the storage capacity of the warehouse, and the welding materials will be damaged if they are placed for a long time. Summary of the invention
[0003] In view of the above-mentioned shortcomings of the prior art, an object of the present invention is to provide a welding material supply management method for solving the problem that the welding material supply in the prior art adopts a large number of warehouses, thereby wasting the storage capacity of the warehouse and causing the welding material to be damaged due to long storage time.
[0004] To achieve the above objectives and other related objectives, the present invention provides a welding material supply management method, comprising:
[0005] Establishing a ship construction and embarkation network tree, wherein the ship construction and embarkation network tree includes each construction node in the ship construction process and a number corresponding to each construction node;
[0006] Classifying the welds, and classifying each weld on the ship to each of the construction nodes;
[0007] Performing welding material quantity statistics on the welds corresponding to each of the construction nodes;
[0008] Establishing a ship construction schedule tree, wherein the ship construction schedule tree includes a date when each construction node starts construction;
[0009] According to the ship construction schedule tree and the welding material quantity corresponding to the construction node, obtaining the welding material demand time node and the welding material demand quantity;
[0010] Supply rules for welding material procurement and storage are established based on the demand time node and the demand quantity to form the welding material supply management method.
[0011] Optionally, the step of establishing a ship construction and embarkation network tree comprises:
[0012] According to the actual construction plan of the ship, the ship is divided into various construction nodes;
[0013] Numbering each of the construction nodes;
[0014] Generate a network tree for building the ship.
[0015] Optionally, the step of classifying the welds includes:
[0016] Acquire weld information of the weld, wherein the weld information includes names of the two components generating the weld;
[0017] The construction node to which the weld is classified is determined according to the minimum construction node to which the set of minimum construction nodes corresponding to the names of the two components belongs, and the weld is named.
[0018] Optionally, the construction node includes segments, the welds include intra-segment welds and inter-segment welds, and the intra-segment welds and inter-segment welds are named in different ways.
[0019] Optionally, the step of performing welding material quantity statistics on the welds corresponding to each of the construction nodes includes:
[0020] Acquire weld information of the weld, wherein the weld information includes the type and length of welding material of the weld;
[0021] The welding material type and the welding material length of the weld corresponding to each construction node are summarized.
[0022] Optionally, the weld information also includes a welding method, and the welding material types are differentiated according to the material of the welding material and the welding method.
[0023] Optionally, the step of obtaining the weld information of the weld includes:
[0024] Obtain a three-dimensional model of the ship;
[0025] Based on the collision check of the three-dimensional model, a butt joint and fillet weld information table of the ship is obtained;
[0026] The weld information is obtained from the information table.
[0027] Optionally, the construction nodes are, from small to large, a segment, a total assembly segment, a total segment and a mounting segment.
[0028] Optionally, the welding material supply management method further includes reserving a spare amount when purchasing welding materials.
[0029] Optionally, according to the actual construction situation of the ship, when the reserve quantity is insufficient, the reserve quantity is supplemented.
[0030] In a welding material supply management method of the present invention, the welding seams are classified into corresponding construction nodes to obtain the welding material quantity required for the corresponding construction node. And according to the ship construction schedule tree, the start time of the corresponding construction node is obtained. Before the construction node is started, it is sufficient to ensure that the warehouse has a corresponding amount of welding materials. There is no need to purchase and store all the welding materials required for ship construction in advance, which greatly improves the storage capacity of the welding material warehouse, while reducing the accumulation time and accumulation inventory of welding materials, ensuring that the function of the welding materials is not damaged. BRIEF DESCRIPTION OF THE DRAWINGS
[0031] Figure 1 It is a simplified schematic diagram of ship composition in sections according to one embodiment of the present invention;
[0032] Figure 2 It is a simplified schematic diagram of ship composition in units of overall sections according to one embodiment of the present invention;
[0033] Figure 3 It is a simplified schematic diagram of ship composition in units of sections according to one embodiment of the present invention;
[0034] Figure 4 This is a simplified schematic diagram of ship composition based on carrying capacity in one embodiment of the present invention;
[0035] Figure 5 It is a shipbuilding carrying network tree of one embodiment of the present invention;
[0036] Figure 6 This is a ship construction schedule tree according to an embodiment of the present invention. DETAILED DESCRIPTION
[0037] Refer to the following Figures 1 to 6 To describe a welding material supply management method of the present invention. In the description of this embodiment, it should be understood that the terms "first" and "second" are only used for descriptive purposes, and cannot be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features, that is, include one or more of the features. In the description of the present invention, the meaning of "multiple" is at least two, such as two, three, etc., unless otherwise clearly and specifically defined. When a feature "includes or contains" one or some of the features it covers, unless otherwise specifically described, this indicates that other features are not excluded and may further include other features.
[0038] Unless otherwise clearly defined and limited, the terms "set", "install", "connect", "connect", "fix", "couple" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral one; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements, unless otherwise clearly defined. A person skilled in the art should be able to understand the specific meanings of the above terms in the present invention according to the specific circumstances.
[0039] In addition, in the description of this embodiment, the first feature being "above" or "below" the second feature may include the first and second features being in direct contact, or may include the first and second features not being in direct contact but being in contact through another feature between them. That is, in the description of this embodiment, the first feature being "above", "above", and "above" the second feature includes the first feature being directly above and obliquely above the second feature, or simply indicates that the first feature is higher in level than the second feature. The first feature being "below", "below", or "below" the second feature may mean that the first feature is directly below or obliquely below the second feature, or simply indicates that the first feature is lower in level than the second feature.
[0040] In the description of the present embodiment, the description with reference to the terms "one embodiment", "some embodiments", "illustrative embodiments", "examples", "specific examples", or "some examples" means that the specific features, structures, materials, or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials, or characteristics described may be combined in any one or more embodiments or examples in a suitable manner.
[0041] like Figure 1-Figure 5 As shown, an embodiment of the present invention provides a welding material supply management method, comprising:
[0042] Establish a ship construction and loading network tree. The ship construction and loading network tree includes each construction node in the ship construction process and the corresponding number of each construction node. Each construction node is divided according to the actual construction plan of the ship, so that the establishment of the ship construction and loading network tree is more practical. The various construction nodes are divided from small to large into sections, total assembly sections, total sections and loading sections. After the division of each construction node is completed, each construction node can be numbered. Generally, the section is named B, the total assembly section is named P, the total section is named Z, and the loading section is named E. According to each construction node and the corresponding number, the ship construction and loading network tree can be directly generated.
[0043] Optionally, refer to Figure 1-Figure 4, the whole ship is divided into 12 sections B1~B12. According to the actual construction plan of the ship, B1 and B2 are assembled to form the assembly section P1, B3 and B4 are assembled to form the assembly section P2, and so on, forming a total of 6 assembly sections P1~P6. Similarly, P1 and P2 are docked to form the assembly section Z1, Z1 and P3 are docked to form the assembly section Z2, P4 and P5 are docked to form the assembly section Z3, and Z3 and P6 are docked to form the assembly section Z4. Z2 and Z4 are loaded to form the loading section E1, and E1 is the current ship. According to the numbers corresponding to the above-mentioned construction nodes, the generated ship construction loading network tree is as follows Figure 5 shown.
[0044] The welds are classified, and each weld on the ship is classified into each construction node. The step of classifying the welds includes obtaining weld information of the welds, and the weld information includes the names of two components that generate the welds. The construction node for classifying the welds is determined according to the minimum construction node to which the set of minimum construction nodes corresponding to the names of the two components belongs, and the welds are named.
[0045] Specifically, welds include intra-segment welds and inter-segment welds. According to the segment numbers corresponding to the names of the two components that produce the welds, the intra-segment welds can be named B x -B x , name the inter-segment weld B y -B z For the inter-segment welds, the welds can be classified to the minimum construction node of the set of minimum construction nodes corresponding to the names of the two components. The construction node to which the welds are classified is determined by the minimum construction node, that is, B y and B z For example, the names of the two components that produce the weld correspond to the segment numbers B3-B5. According to the ship construction network tree, the smallest construction node to which the combination of B3 and B5 belongs is Z2, so the weld is classified under Z2. For welds within a segment, the weld can be classified under B x At this time, the names of the two components that produce the weld are both numbered B. x , which can also be seen as two B x The minimum construction node to which the collection belongs.
[0046] The welding material quantity of the corresponding welds under each construction node is counted. The step of counting the welding material quantity of the corresponding welds under each construction node includes obtaining the weld information of the weld, and the weld information includes the welding material type and welding material length of the weld. The welding material type and welding material length of the corresponding welds under each construction node are summarized.
[0047] Furthermore, the weld information also includes the welding method. The types of welding materials can be distinguished according to the material of the welding material and the welding method. Specifically, the types of welding materials can be divided into nickel steel, carbon steel, low temperature steel and special steel according to their different materials. According to different welding methods, they can be divided into solid and hollow. And the diameter of the welding material can also be divided into 1.2mm, 3.2mm, 4.0mm, 5.0mm, etc.
[0048] Furthermore, the step of obtaining the weld information of the weld includes obtaining a three-dimensional model of the ship, performing a collision check based on the three-dimensional model, and obtaining a butt joint and fillet weld information table of the ship. The weld information can be obtained from the information table.
[0049] refer to Figure 6 , establish a ship construction schedule tree, which includes the start date of construction of each construction node. The ship construction schedule tree is established based on the planned construction cycle of the ship.
[0050] According to the ship construction schedule tree and the welding material quantity under the corresponding construction node, the required time node and required material quantity of welding materials are obtained. That is, according to the ship construction schedule tree and the welding material quantity under the corresponding construction node, the material quantity of welding materials required at different time nodes in the ship construction process can be obtained.
[0051] According to the demand time node and the demand quantity, the supply rules for welding material procurement and storage are established to form a welding material supply management method. That is, the quantity of different welding materials required to be purchased is determined before the demand time node, and the demand time node is the start time of the construction node.
[0052] Furthermore, in order to cope with statistical deviations and temporary emergencies, a reserve quantity W needs to be reserved when purchasing. According to the actual construction of the ship, when the reserve quantity is lower than the value of W, it needs to be supplemented.
[0053] In summary, by classifying welds into corresponding construction nodes, the amount of welding materials required for the corresponding construction nodes can be obtained. And according to the ship construction schedule tree, the start time of the corresponding construction node can be obtained. Before the construction node starts, it is sufficient to ensure that the warehouse has the corresponding amount of welding materials. There is no need to purchase and store all the welding materials required for ship construction in advance, which greatly improves the storage capacity of the welding material warehouse, reduces the accumulation time and inventory of welding materials, and ensures that the function of the welding materials is not damaged.
[0054] The above embodiments are merely illustrative of the principles and effects of the present invention, and are not intended to limit the present invention. Anyone familiar with the art may modify or alter the above embodiments without departing from the spirit and scope of the present invention. Therefore, all equivalent modifications or alterations made by a person of ordinary skill in the art without departing from the spirit and technical concept disclosed by the present invention shall still be covered by the claims of the present invention.
Claims
1. A welding material supply management method, characterized in that: include: Establishing a ship construction and embarkation network tree, wherein the ship construction and embarkation network tree includes each construction node in the ship construction process and a number corresponding to each construction node; Classifying the welds, and classifying each weld on the ship to each of the construction nodes; Performing welding material quantity statistics on the welds corresponding to each of the construction nodes; Establishing a ship construction schedule tree, wherein the ship construction schedule tree includes a date when each construction node starts construction; According to the ship construction schedule tree and the welding material quantity corresponding to the construction node, obtaining the welding material demand time node and the welding material demand quantity; Supply rules for welding material procurement and storage are established based on the demand time node and the demand quantity to form the welding material supply management method.
2. The welding material supply management method according to claim 1, characterized in that: The steps of establishing a ship construction and embarkation network tree include: According to the actual construction plan of the ship, the ship is divided into various construction nodes; Numbering each of the construction nodes; Generate a network tree for building the ship.
3. The welding material supply management method according to claim 1, characterized in that: The step of classifying the welds comprises: Acquire weld information of the weld, wherein the weld information includes names of the two components generating the weld; The construction node to which the weld is classified is determined according to the minimum construction node to which the set of minimum construction nodes corresponding to the names of the two components belongs, and the weld is named.
4. The welding material supply management method according to claim 3, characterized in that: The construction node includes segments, and the welds include welds within the segments and welds between the segments. The welds within the segments and welds between the segments are named in different ways.
5. The welding material supply management method according to claim 1, characterized in that: The step of counting the welding material quantity of the weld corresponding to each of the construction nodes comprises: Acquire weld information of the weld, wherein the weld information includes the type and length of welding material of the weld; The welding material type and the welding material length of the weld corresponding to each construction node are summarized.
6. The welding material supply management method according to claim 5, characterized in that: The weld information also includes a welding method, and the welding material types are differentiated according to the material of the welding material and the welding method.
7. The welding material supply management method according to any one of claims 3 to 6, characterized in that: The step of obtaining the weld information of the weld includes: Obtain a three-dimensional model of the ship; Based on the collision check of the three-dimensional model, a butt joint and fillet weld information table of the ship is obtained; The weld information is obtained from the information table.
8. The welding material supply management method according to claim 1, characterized in that: The various construction nodes are, from small to large, a segment, a total assembly segment, a total segment and a mounting segment.
9. The welding material supply management method according to claim 1, characterized in that: It also includes reserving spare quantities when purchasing welding materials.
10. The welding material supply management method according to claim 9, characterized in that: According to the actual construction situation of the ship, when the reserve quantity is insufficient, the reserve quantity is supplemented.