Steel lifting chain automatic control method and system

By acquiring signals from the traversing conveyor chain, collection rollers and lifting chains, the speed and direction of the lifting chains are automatically controlled, which solves the problem of manual operation errors, realizes the automation of steel transportation, and improves production efficiency and continuity.

CN118790702APending Publication Date: 2024-10-18YANGCHUN NEW STEEL CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410973720.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-19
Publication Date
2024-10-18

AI Technical Summary

Technical Problem

In the existing technology, the operator of the lifting chain needs to manually control the steel transportation, which can easily lead to errors and production shutdowns, and cannot meet the demand for rapid production.

Method used

By acquiring signals from the traversing conveyor chain, collection rollers and lifting chains, the speed and direction of the lifting chains are automatically controlled to achieve full automation and avoid manual intervention.

Benefits of technology

It realizes fully automatic control of the lifting chain equipment, reduces the operator's workload, improves the production rhythm, and ensures the continuity of the entire production line.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118790702A_ABST
    Figure CN118790702A_ABST
Patent Text Reader

Abstract

The invention discloses an automatic control method for a lifting chain of steel, relates to the technical field of steel rolling production, and solves the technical problem that errors are easily caused when the lifting chain is manually operated in the prior art. The method comprises the following steps of: 1, acquiring steel signals of three sections of a transverse moving conveying chain, judging whether the steel signals of the three sections of the transverse moving conveying chain are true values or not, controlling a lifting chain positioned at a steel receiving position to descend to a waiting position along a set first speed when the steel signals of the three sections of the transverse moving conveying chain are true values, and controlling the lifting chain positioned at a steel receiving position to descend to the waiting position along a set second speed when the steel signals of the three sections of the transverse moving conveying chain are false values; if yes, controlling the lifting chain not to act. The invention further discloses a steel lifting chain automatic control system. Human errors of operators are avoided, meanwhile, the workload of the operators is reduced, the production rhythm of the lifting chain link is improved, and the production rhythm of the whole line is guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of steel rolling production, and more specifically, to an automatic control method and system for a lifting chain of steel. Background Art

[0002] The bundle shape of steel and the scratches on the surface of steel are important indicators of steel sales. The original equipment that uses the transverse conveyor chain to drop steel to the collecting roller is not very good at controlling the bundle shape of steel and the scratches on the surface of steel. In order to improve the bundle shape and scratches of steel, the original equipment that uses the transverse conveyor chain to drop steel to the collecting roller is modified, and the lifting chain equipment is used to replace the original equipment to transport the transverse conveyor chain steel to the collecting roller. After the transformation, the lifting chain can only wait for the transverse conveyor chain to drop a bundle of steel to the lifting chain support arm, and then the operator will observe whether there is steel on the collecting roller. If there is steel, the lifting chain cannot be started. The steel on the collecting roller must be sent to the bundling roller first, and then the collecting roller is free of steel and then the lifting chain start button is manually pressed. The lifting chain starts to descend, and the lifting chain drops the steel to the collecting roller. It continues to run until the lifting chain detects the lifting link steel position signal. The lifting chain triggers a stop signal, and the lifting chain stops at the steel receiving position. The lifting chain completes an action cycle. However, since the operators at the lifting chain operating positions require many operating equipment, they may not be able to drop the steel from the lifting chain to the collecting roller in time, and mistakes are prone to occur, causing the lifting chain to press the steel and cause production to stop. Therefore, manual control cannot meet the fast-paced production on site. Summary of the invention

[0003] The technical problem to be solved by the present invention is to provide a steel lifting chain automatic control method and system in view of the deficiencies in the prior art, thereby solving the technical problem that the prior manual operation of the lifting chain is prone to errors.

[0004] The present invention provides a method for automatically controlling a lifting chain of steel, the method comprising:

[0005] Step 1: Obtain the signal that there is steel in the three sections of the transverse conveyor chain, and determine whether the signal that there is steel in the three sections of the transverse conveyor chain is true. When the signal that there is steel in the three sections of the transverse conveyor chain is true, control the lifting chain at the steel receiving position to descend to the waiting position along the set first speed. When the signal that there is steel in the three sections of the transverse conveyor chain is false, control the lifting chain not to move.

[0006] Step 2: obtaining a steel signal from the collecting roller, and determining whether the steel signal from the collecting roller is true. When the steel signal from the collecting roller is true, the lifting chain at the waiting position does not work; when the steel signal from the collecting roller is false, the lifting chain at the waiting position descends along the set second speed.

[0007] Step three: obtain the lifting link steel position signal, and determine whether the lifting link steel position signal is a true value. When the lifting link steel position signal is a true value, the lifting chain stops at the steel receiving position; when the lifting link steel position signal is a false value, the lifting chain continues to descend along the set second speed.

[0008] As a further improvement, in step 1, the method for controlling the lifting chain at the steel receiving position to descend to the waiting position along the set first speed is to obtain the steel receiving position and the waiting position, make a difference between the steel receiving position and the waiting position, obtain the first movement distance of the lifting chain, and evenly divide the first movement distance into n first distance intervals;

[0009] The speed of the lifting chain at the steel receiving position is set to the first speed v1, and the speed of the lifting chain is successively reduced at each next first distance interval. When approaching the waiting position, the speed of the lifting chain is set to zero.

[0010] Furthermore, the set speed expression of the kth first distance interval is:

[0011] v k =v1-[(v1-v0) / n×(nk)];

[0012] Among them, v k is the set speed of the kth first distance interval, v1 is the first speed, v0 is the speed at which the lifting chain reaches the waiting position, and n is the total number of first distance intervals.

[0013] Furthermore, in step 2 and step 3, the method for controlling the lifting chain of the waiting position to descend to the steel receiving position along the set second speed is to obtain the steel receiving position and the waiting position, make a difference between the steel receiving position and the waiting position, obtain the second movement distance of the lifting chain, and evenly divide the second movement distance into p second distance intervals;

[0014] The speed of the lifting chain at the waiting position is set to the second speed v2, and the speed of the lifting chain is reduced successively at each next second distance interval. When approaching the steel connecting position, the speed of the lifting chain is set to zero.

[0015] Furthermore, the set speed expression of the qth second distance interval is:

[0016] v q =v2-[(v2-v3)) / p×(pq)];

[0017] Among them, v q is the set speed of the qth second distance interval, v2 is the second speed, v3 is the speed at which the lifting chain reaches the steel receiving position, and p is the total number of second distance intervals.

[0018] Furthermore, the lifting chain start delay time and the lifting chain speed are set on the HMI screen.

[0019] Furthermore, the magnitude relationship between the first speed and the second speed is: first speed<second speed.

[0020] An automatic control system for lifting chains of steel materials, comprising:

[0021] The pressure rod is installed at the end of the third section of the transverse conveyor chain and is used to trigger the proximity switch when there are running steel bars on the third section of the transverse conveyor chain;

[0022] The proximity switch is installed on the rotation path of the pressure rod and is used to collect the steel signal of the three sections of the transverse conveyor chain;

[0023] The transmitting end and receiving end of the beam grating are respectively installed on both sides of the collecting roller to collect the steel signal of the collecting roller;

[0024] The controller uses the control method as described above to control the movement of the lifting chain according to the steel presence signal of the three sections of the transverse conveyor chain, the steel presence signal of the collecting roller and the steel position signal of the lifting link.

[0025] Furthermore, the controller is a PLC.

[0026] Beneficial Effects

[0027] The advantages of the present invention are:

[0028] The present invention operates the speed and direction of the lifting chain by obtaining the steel presence signals of the three sections of the transverse conveyor chain, the steel presence signal of the collecting roller and the steel position signal of the lifting link. The lifting chain equipment is fully automatically controlled throughout the process without manual intervention, thus avoiding operator errors and reducing the operator's workload, improving the production rhythm of the lifting chain link and ensuring the production rhythm of the entire line. BRIEF DESCRIPTION OF THE DRAWINGS

[0029] Figure 1 The figure is a flow chart of the automatic control method of the lifting chain of the present invention. DETAILED DESCRIPTION

[0030] The present invention will be further described below in conjunction with the embodiments, but it does not constitute any limitation to the present invention. Any limited number of modifications made by anyone within the scope of the claims of the present invention are still within the scope of the claims of the present invention.

[0031] See also Figure 1 The present invention provides a steel lifting chain automatic control method, the method comprising:

[0032] Step 1: Get the signal that there is steel in the three sections of the transverse conveyor chain, and determine whether the signal that there is steel in the three sections of the transverse conveyor chain is true. When the signal that there is steel in the three sections of the transverse conveyor chain is true, the lifting chain at the steel receiving position is controlled to descend to the waiting position along the set first speed. When the signal that there is steel in the three sections of the transverse conveyor chain is false, the lifting chain is controlled not to move.

[0033] The method for controlling the lifting chain at the steel receiving position to descend to the waiting position along the set first speed is to obtain the steel receiving position and the waiting position, make a difference between the steel receiving position and the waiting position, obtain the first movement distance of the lifting chain, and evenly divide the first movement distance into n first distance intervals;

[0034] The speed of the lifting chain at the steel receiving position is set to the first speed v1, and the speed of the lifting chain is reduced successively at each next first distance interval. When approaching the waiting position, the speed of the lifting chain is set to zero.

[0035] v k =v1-[(v1-v0) / n×(nk)];

[0036] Among them, v k is the set speed of the kth first distance interval, v1 is the first speed, v0 is the speed at which the lifting chain reaches the waiting position, and n is the total number of first distance intervals.

[0037] Step 2: Get the steel signal from the collecting roller, and determine whether the steel signal from the collecting roller is true. When the steel signal from the collecting roller is true, the lifting chain in the waiting position does not work; when the steel signal from the collecting roller is false, the lifting chain in the waiting position descends along the set second speed.

[0038] Step 3: Get the lifting link steel position signal, and determine whether the lifting link steel position signal is true. When the lifting link steel position signal is true, the lifting chain stops at the steel receiving position; when the lifting link steel position signal is false, the lifting chain continues to descend along the set second speed.

[0039] The method for controlling the lifting chain at the waiting position to descend to the steel receiving position along the set second speed is to obtain the steel receiving position and the waiting position, make a difference between the steel receiving position and the waiting position, obtain the second movement distance of the lifting chain, and evenly divide the second movement distance into p second distance intervals;

[0040] The speed of the lifting chain at the waiting position is set to the second speed v2, and the speed of the lifting chain is reduced successively at each next second distance interval. When approaching the steel receiving position, the speed of the lifting chain is set to zero.

[0041] v q =v2-[(v2-v3) / p×(pq)];

[0042] Among them, v qis the set speed of the qth second distance interval, v2 is the second speed, v3 is the speed at which the lifting chain reaches the steel receiving position, and p is the total number of second distance intervals.

[0043] The magnitude relationship between the first speed and the second speed is: first speed < second speed.

[0044] Set the lifting chain start delay time and lifting chain speed on the HMI screen.

[0045] An automatic control system for lifting chains of steel materials, comprising:

[0046] The pressure rod is installed at the end of the third section of the transverse conveyor chain, and is used to trigger the proximity switch when there are running steel bars on the third section of the transverse conveyor chain. When the third section of the transverse conveyor chain is running in the forward direction and the steel bars on the chain press the pressure rod of the detection device, the pressure rod rises to the detection position of the proximity switch probe, thereby triggering the signal that there is steel on the third section of the transverse conveyor chain.

[0047] The proximity switch is installed on the rotation path of the pressure rod and is used to collect the steel signal of the three sections of the transverse conveyor chain. When there is a metal object in the effective detection distance of the proximity switch, the proximity switch will output a high-level signal to the PLC. The proximity switch can be connected to the PLC as feedback of the steel signal.

[0048] The transmitting end and receiving end of the beam grating are respectively installed on both sides of the collecting roller, and are used to collect the steel signal of the collecting roller. When the transmitting end and the receiving end of the beam grating are blocked by an object, the signal line can trigger a high-level signal, which is connected to the PLC system for steel signal feedback.

[0049] The controller is a PLC, which uses the above control method to control the movement of the lifting chain according to the steel-presence signal of the three sections of the transverse conveyor chain, the steel-presence signal of the collecting roller and the steel position signal of the lifting link.

[0050] When the lifting chain is at the steel receiving position, the three sections of the transverse conveyor chain have steel signals to trigger the lifting chain to automatically descend at a low speed for the first time. When the lifting chain descends to the waiting position, the lifting chain stops for the first time. At this time, if there is steel on the collecting roller, the lifting chain waits at the waiting position. When there is no steel on the collecting roller, the lifting chain descends along the set second speed. If there is no steel on the collecting roller, the lifting chain immediately descends along the set second speed until the lifting steel receiving position signal is detected. The lifting chain stops at the steel receiving position and finally completes an action cycle.

[0051] The above is only a preferred embodiment of the present invention. It should be pointed out that for those skilled in the art, several modifications and improvements can be made without departing from the structure of the present invention, which will not affect the effect of the implementation of the present invention and the practicality of the patent.

Claims

1. A method for automatically controlling a lifting chain of steel, characterized in that: The method is, Step 1: Obtain the signal that there is steel in the three sections of the transverse conveyor chain, and determine whether the signal that there is steel in the three sections of the transverse conveyor chain is true. When the signal that there is steel in the three sections of the transverse conveyor chain is true, control the lifting chain at the steel receiving position to descend to the waiting position along the set first speed. When the signal that there is steel in the three sections of the transverse conveyor chain is false, control the lifting chain not to move. Step 2: obtaining a steel signal from the collecting roller, and determining whether the steel signal from the collecting roller is true. When the steel signal from the collecting roller is true, the lifting chain at the waiting position does not work; when the steel signal from the collecting roller is false, the lifting chain at the waiting position descends along the set second speed. Step three: obtain the lifting link steel position signal, and determine whether the lifting link steel position signal is a true value. When the lifting link steel position signal is a true value, the lifting chain stops at the steel receiving position; when the lifting link steel position signal is a false value, the lifting chain continues to descend along the set second speed.

2. The automatic control method for lifting chain of steel according to claim 1, characterized in that: In step 1, the method of controlling the lifting chain at the steel receiving position to descend to the waiting position along the set first speed is to obtain the steel receiving position and the waiting position, make a difference between the steel receiving position and the waiting position, obtain the first movement distance of the lifting chain, and evenly divide the first movement distance into n first distance intervals; The speed of the lifting chain at the steel receiving position is set to the first speed v1, and the speed of the lifting chain is successively reduced at each next first distance interval. When approaching the waiting position, the speed of the lifting chain is set to zero.

3. The automatic control method for lifting chain of steel according to claim 2, characterized in that: The set speed expression of the kth first distance interval is: v k =v1-[(v1-v0) / n×(nk)]; Among them, v k is the set speed of the kth first distance interval, v1 is the first speed, v0 is the speed at which the lifting chain reaches the waiting position, and n is the total number of first distance intervals.

4. The automatic control method for lifting chain of steel according to claim 1, characterized in that: In step 2 and step 3, the method of controlling the lifting chain of the waiting position to descend to the steel receiving position along the set second speed is to obtain the steel receiving position and the waiting position, make a difference between the steel receiving position and the waiting position, obtain the second movement distance of the lifting chain, and evenly divide the second movement distance into p second distance intervals; The speed of the lifting chain at the waiting position is set to the second speed v2, and the speed of the lifting chain is reduced successively at each next second distance interval. When approaching the steel connecting position, the speed of the lifting chain is set to zero.

5. The automatic control method for lifting chain of steel material according to claim 4, characterized in that: The set speed expression of the qth second distance interval is: v3 = v2 - [(v2 - v3) / p × (pq)]; Among them, v q is the set speed of the qth second distance interval, v2 is the second speed, v3 is the speed at which the lifting chain reaches the steel receiving position, and p is the total number of second distance intervals.

6. The automatic control method for lifting chain of steel material according to claim 1, characterized in that: The lifting chain start delay time and the lifting chain speed are set on the HMI screen.

7. The automatic control method for lifting chain of steel material according to claim 1, characterized in that: The magnitude relationship between the first speed and the second speed is: first speed<second speed.

8. An automatic control system for lifting chains of steel, characterized in that: It includes, The pressure rod is installed at the end of the third section of the transverse conveyor chain and is used to trigger the proximity switch when there are running steel bars on the third section of the transverse conveyor chain; The proximity switch is installed on the rotation path of the pressure rod and is used to collect the steel signal of the three sections of the transverse conveyor chain; The transmitting end and receiving end of the beam grating are respectively installed on both sides of the collecting roller to collect the steel signal of the collecting roller; The controller uses the control method as described in claims 1-7 to control the movement of the lifting chain according to the steel presence signal of the three sections of the transverse conveyor chain, the steel presence signal of the collecting roller and the steel position signal of the lifting link.

9. The automatic control system for lifting chain of steel materials according to claim 8, characterized in that: The controller is a PLC.