Comprehensive construction method for supporting high-water-level ultra-deep foundation pit with weak permeable soil texture
Through the combined use of water-stop curtain piles, reinforced concrete supporting piles, jet grouting piles, dewatering wells and anchor cables, the problems of stability and drainage difficulty in the construction of ultra-deep foundation pits with high water levels in weakly permeable soil have been solved, and the foundation has been achieved. The safe, reliable construction and long-term stability of the pit have improved construction efficiency and precipitation effects.
Patent Information
- Application Number
- CN202411256342.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-09
- Publication Date
- 2024-10-18
AI Technical Summary
Under the conditions of weakly permeable soil and high water level, traditional foundation pit support methods cannot effectively drain water and resist water pressure, making it difficult to ensure the stability of foundation pits and construction safety. Especially in the construction of ultra-deep foundation pits, existing technologies are difficult to Ensure long-term foundation pit slope safety.
Use a combination of construction methods such as water-stop curtain piles, reinforced concrete supporting piles, jet grouting piles, dewatering wells, anchor cables and internal supports, combined with layered earth excavation and backfilling, to monitor deformation and internal forces to ensure the safety of the supporting structure. and stability.
A comprehensive construction plan for ultra-deep foundation pits in weakly permeable soil with high water levels, safe and reliable structure, small deformation, fast construction, and good dewatering effect has been achieved, ensuring the long-term stability of the foundation pit and the construction safety progress, and has economic and social benefits.
Smart Images

Figure CN118793070A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of foundation pit support, and more specifically to a comprehensive construction method for supporting an ultra-deep foundation pit in weakly permeable soil with a high water level. Background Art
[0002] Weakly permeable soil usually refers to soil types with poor permeability and poor drainage capacity. When excavating foundation pits in such soils, due to the poor permeability of the soil, water may accumulate in the foundation pit, which in turn affects the construction progress and stability of the foundation pit. If the groundwater level is high, the water pressure on the soil increases, increasing the risk of foundation pit collapse. At the same time, high water levels may also cause water seepage on the side walls of the foundation pit, further affecting the stability of the foundation pit. At this time, as the depth of the foundation pit increases, the horizontal soil pressure and water pressure on the side walls of the foundation pit also increase, which puts higher requirements on the support structure of the foundation pit.
[0003] Traditional foundation pit support methods may not be effective in conditions of weak permeability soil and high water levels, and may not be able to effectively drain water and resist water pressure. For ultra-deep foundation pits, traditional support methods may require a large amount of materials and time to construct, and the stability of the support structure is difficult to guarantee.
[0004] The invention patent with publication number CN103114602A discloses a foundation pit water-stop curtain with secondary melting and filling of a permeable impregnated polymer adhesive and a construction method. This scheme forms a permeable impregnated polymer adhesive while supplementing secondary curtain piles at the bifurcation of the traditionally constructed water-stop curtain, thereby achieving an effective water-stopping function. However, this scheme does not record a construction scheme for weakly permeable soil scenes. Therefore, the construction effect is poor in soils with poor permeability and poor drainage capacity. The invention patent with publication number CN104631470B discloses a combined support construction method for deep foundation pits in high-water-level large-grained gravel geology. This construction method utilizes a variety of The combined construction of support forms and their interaction solve the problems of support and treatment of geological foundation pits with large grain size gravel at high water level. However, this solution is aimed at the geological conditions of large grain size gravel at high water level, which is different from the construction scenario of weak permeability soil. It cannot solve the support problems of foundation pits in soils with poor permeability and weak drainage. The invention patent with publication number CN117144931A discloses a support structure for ultra-deep foundation pit excavation construction and its deformation control method. This method has high safety and construction efficiency, little impact on the surrounding environment, and low cost, but this solution cannot guarantee the long-term stability and safety of high water level foundation pit support in weak permeability soil.
[0005] Existing technical measures can only meet the stability of foundation pit slopes in a short period of time, and cannot ensure the long-term safety of foundation pit slopes. Based on the above background, in order to meet the needs of foundation pit construction under complex geological conditions, it is urgent to develop a construction technology for ultra-deep foundation pit support in weakly permeable soil with high water level. Summary of the invention
[0006] In order to overcome the deficiencies in the above-mentioned prior art, the present invention provides a comprehensive construction method for supporting ultra-deep foundation pits in weakly permeable soil with high water level. The comprehensive construction method for supporting has the advantages of safe and reliable structure, small deformation, fast construction, good precipitation effect, etc.
[0007] In order to solve the above technical problems, the technical solution adopted by the present invention is: A comprehensive construction method for supporting ultra-deep foundation pits in weakly permeable soil with high water level, comprising the following steps: S1. Water-stop curtain pile construction; S2, construction of reinforced concrete support piles; S3, adopt the double-pipe method of jet grouting to carry out high-pressure jet grouting pile construction; S4. Construction of precipitation wells; S5. Earth excavation, slope surface mesh spraying and crown beam construction; S6, layered earth excavation; S7, construction of layered anchor cables, waist beams, soil mesh spraying between piles and internal support; S8, earth backfill; S9. Deformation monitoring.
[0008] In step S1, the water-stop curtain pile construction process includes: S11, site cleaning, surveying and trenching; S12, the pile driver is in place, the embedded hole is drilled, and the additional drill rod is inserted; S13, the pile driver is in place and the three-axis mixing pile hole is positioned; S14, stirring and sinking to the first group depth; performing grouting injection; S15, whether the designed pile is reached; S151, if reached, re-stir the pile bottom, reverse and lift, remove the drill rod, and put it back into the pre-buried hole; S152. If the pile is not reached, remove the drill rod joint and move the pile driver; connect the pre-buried drill rod and pull out the drill rod; move the pile driver to the construction pile position and connect the drill rod; stir and sink the pre-buried drill rod, which can be repeated several times until the designed pile is reached; S16: After the single pile construction is completed, the pile driver is moved to the construction pile position; S17. The residue is transported out and the construction is completed.
[0009] In step S2, the construction process of reinforced concrete support piles includes measurement and layout → drilling rig in place to open holes → setting casing and injecting mud → drilling → hole cleaning → placing steel cage and grouting pipe → placing guide tube → secondary hole cleaning → concrete pouring → pulling out guide tube → pulling out casing → drilling rig shifting → empty hole backfilling.
[0010] In step S3, the high-pressure rotary jet grouting pile construction process includes: measuring and setting out → drilling rig in place → stabilizing and calibrating the drilling rig → preparing cement slurry → penetrating the jet pipe with high-pressure mud rotary jetting to force soil cutting and drilling → rechecking the verticality of the drilling rig → continuing drilling → designing the pile bottom elevation value → rotary jetting of the drilling rig to lift the drill to the top of the pile → moving the drilling rig to the new pile position.
[0011] In step S4, the construction process of the dewatering well includes: determining the axis line, placing the well point → positioning the drilling rig, drilling the hole → changing the slurry, lowering the filter pipe, filling the gravel → washing the well → making the ground joint pipe or drainage ditch → lowering the pump to pump water → observing and maintaining the dewatering.
[0012] In step S7, the anchor cable construction process includes: digging to the designed elevation → measuring and laying out, anchor cable production → drilling rig in place to open the cast-in-place pile hole → drilling with self-contained anchor cable → drilling to the designed length → drilling with drill rod into anchor → maintenance → tensioning and locking → cutting off excess steel strands to protect the anchor head.
[0013] In step S7, the installation and removal construction process of the inner support includes: S71, after the foundation slab and exterior wall are constructed to the second support of 500, and the exterior wall waterproofing is completed, pour C15 concrete between the exterior wall and the supporting piles; S72. After the concrete between the outer wall and the outer wall and the supporting piles reaches the designed strength, the second support is removed; S73, after the first support of the exterior wall is 500 meters, and the exterior wall waterproofing is completed, pour C15 concrete between the exterior wall and the supporting piles; S74. After the concrete of the exterior wall and between the exterior wall and the supporting piles reaches the designed strength, additional support is added to the inner side of the exterior wall and the first support is removed; S75. After the exterior wall is constructed to more than 300 meters above the bottom roof slab and the bottom roof slab is constructed, and the exterior wall waterproofing is completed, pour C15 concrete between the exterior wall and the supporting piles; after the concrete between the exterior wall and the supporting piles reaches the designed strength, remove the inner support of the exterior wall.
[0014] In step S8, the narrow and difficult to compact parts are filled with foam concrete, and the other parts are backfilled and compacted in layers with graded crushed stones.
[0015] In step S8, the monitoring items include horizontal and vertical displacement of the pit top; deep horizontal displacement; groundwater level change monitoring; anchor cable internal force, support internal force, pit bottom uplift monitoring; and road settlement and crack monitoring around the foundation pit.
[0016] Compared with the prior art, the present invention has the following beneficial effects: This construction method is suitable for the construction of ultra-deep foundation pit support with weak permeability soil and high water level. It provides a practical solution for the deep foundation pit with high groundwater level, small soil permeability coefficient, poor groundwater fluidity, and great difficulty in precipitation. The water-stop curtain pile is deep, the underground soil is poor, and the support pile hole is easy to collapse. The design of the foundation pit support structure is complex, and the vertical spacing between adjacent internal supports is small, making it difficult to excavate the earth between supports. It ultimately achieves the purpose of ensuring the safe progress of construction, with considerable economic and social benefits, and accumulates rich experience for similar projects. It has the advantages of safe and reliable support structure, small deformation, fast construction, and good precipitation effect. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1 It is a schematic diagram of the construction process of the present invention; Figure 2 It is a schematic diagram of the construction process of the water-stop curtain pile of the present invention. DETAILED DESCRIPTION
[0018] In order to more clearly understand the above-mentioned purpose, features and advantages of the present invention, the present invention is further described in detail below in conjunction with the accompanying drawings and specific embodiments. It should be noted that the embodiments of the present application and the features in the embodiments can be combined with each other without conflict.
[0019] In the following description, many specific details are set forth to facilitate a full understanding of the present invention. However, the present invention may also be implemented in other ways different from the description. Therefore, the protection scope of the present invention is not limited to the specific embodiments disclosed below.
[0020] like Figure 1 to Figure 2 As shown, a comprehensive construction method for supporting ultra-deep foundation pits with low permeability and high water level comprises the following steps: S1. Water-stop curtain pile construction; S2, construction of reinforced concrete support piles; S3, adopt the double-pipe method of jet grouting to carry out high-pressure jet grouting pile construction; S4. Construction of precipitation wells; S5. Earth excavation, slope surface mesh spraying and crown beam construction; S6, layered earth excavation; S7, construction of layered anchor cables, waist beams, soil mesh spraying between piles and internal support; S8, earth backfill; S9. Deformation monitoring.
[0021] BIM was used for planning and arrangement of various structures before construction.
[0022] In step S1, the water-stop curtain pile construction process includes: S11, site cleaning, surveying and trenching; S12, the pile driver is in place, the embedded hole is drilled, and the additional drill rod is inserted; S13, the pile driver is in place and the three-axis mixing pile hole is positioned; S14, stirring and sinking to the first group depth; performing grouting injection; S15, whether the designed pile is reached; S151, if reached, re-stir the pile bottom, reverse and lift, remove the drill rod, and put it back into the pre-buried hole; S152. If the pile is not reached, remove the drill rod joint and move the pile driver; connect the pre-buried drill rod and pull out the drill rod; move the pile driver to the construction pile position and connect the drill rod; stir and sink the pre-buried drill rod, which can be repeated several times until the designed pile is reached; S16: After the single pile construction is completed, the pile driver is moved to the construction pile position; S17. The residue is transported out and the construction is completed.
[0023] Strengthen the cold joint treatment of curtain piles during construction.
[0024] In step S2, the construction process of reinforced concrete support piles includes measurement and layout → drilling rig in place to open holes → setting casing and injecting mud → drilling → hole cleaning → placing steel cage and grouting pipe → placing guide tube → secondary hole cleaning → concrete pouring → pulling out guide tube → pulling out casing → drilling rig shifting → empty hole backfilling.
[0025] The holes are drilled using the reverse circulation drilling process with a submersible drilling rig, commercial concrete is used for concrete, the steel cage is welded in two or three sections and partially tied into shape, and hoisted as a whole, and the underwater concrete pouring process is used in the duct.
[0026] In step S3, the high-pressure rotary jet grouting pile construction process includes: measuring and setting out → drilling rig in place → stabilizing and calibrating the drilling rig → preparing cement slurry → penetrating the jet pipe with high-pressure mud rotary jetting to force soil cutting and drilling → rechecking the verticality of the drilling rig → continuing drilling → designing the pile bottom elevation value → rotary jetting of the drilling rig to lift the drill to the top of the pile → moving the drilling rig to the new pile position.
[0027] In step S4, the construction process of the dewatering well includes: determining the axis line, placing the well point → positioning the drilling rig, drilling the hole → changing the slurry, lowering the filter pipe, filling the gravel → washing the well → making the ground joint pipe or drainage ditch → lowering the pump to pump water → observing and maintaining the dewatering.
[0028] The dewatering well is constructed by using the mud wall protection method with a submersible drilling rig. When the foundation pit is excavated, the area around the dewatering well is excavated manually, and the well mouth must be protected and covered to prevent anything from falling into the well.
[0029] In step S7, the anchor cable construction process includes: digging to the designed elevation → measuring and laying out, anchor cable production → drilling rig in place to open the cast-in-place pile hole → drilling with self-contained anchor cable → drilling to the designed length → drilling with drill rod into anchor → maintenance → tensioning and locking → cutting off excess steel strands to protect the anchor head.
[0030] The anchor cable can be tensioned only after the concrete strength of the waist beam reaches 80% and the strength of the grouting body reaches the design requirements. The tensioning equipment needs to be calibrated before tensioning the anchor cable.
[0031] In step S7, the installation and removal construction process of the inner support includes: S71, after the foundation slab and exterior wall are constructed to the second support of 500, and the exterior wall waterproofing is completed, pour C15 concrete between the exterior wall and the supporting piles; S72. After the concrete between the outer wall and the outer wall and the supporting piles reaches the designed strength, the second support is removed; S73, after the first support of the exterior wall is 500 meters, and the exterior wall waterproofing is completed, pour C15 concrete between the exterior wall and the supporting piles; S74. After the concrete of the exterior wall and between the exterior wall and the supporting piles reaches the designed strength, additional support is added to the inner side of the exterior wall and the first support is removed; S75. After the exterior wall is constructed to more than 300 meters above the bottom roof slab and the bottom roof slab is constructed, and the exterior wall waterproofing is completed, pour C15 concrete between the exterior wall and the supporting piles; after the concrete between the exterior wall and the supporting piles reaches the designed strength, remove the inner support of the exterior wall.
[0032] In step S8, the narrow and difficult to compact parts are filled with foam concrete, and the other parts are backfilled and compacted in layers with graded crushed stones.
[0033] In step S8, the monitoring items include horizontal and vertical displacement of the pit top; deep horizontal displacement; groundwater level change monitoring; anchor cable internal force, support internal force, pit bottom uplift monitoring; and road settlement and crack monitoring around the foundation pit.
[0034] After construction and monitoring are completed, support safety verification is carried out.
[0035] Only the preferred embodiments of the present invention are described in detail above, but the present invention is not limited to the above embodiments. Various changes can be made within the knowledge scope of ordinary technicians in this field without departing from the purpose of the present invention, and various changes should be included in the protection scope of the present invention.
Claims
1. A comprehensive construction method for supporting ultra-deep foundation pits in weakly permeable soil with high water level, characterized in that: The following steps are involved: S1. Water-stop curtain pile construction; S2, construction of reinforced concrete support piles; S3, adopt the double-pipe method of jet grouting to carry out high-pressure jet grouting pile construction; S4. Construction of precipitation wells; S5. Earth excavation, slope surface mesh spraying and crown beam construction; S6, layered earth excavation; S7, construction of layered anchor cables, waist beams, soil mesh spraying between piles and internal support; S8, earth backfill; S9. Deformation monitoring.
2. The comprehensive construction method for supporting ultra-deep foundation pits in weakly permeable soil with high water level according to claim 1 is characterized by: In step S1, the water-stop curtain pile construction process includes: S11, site cleaning, surveying and trenching; S12, the pile driver is in place, the embedded hole is drilled, and the additional drill rod is inserted; S13, the pile driver is in place and the three-axis mixing pile hole is positioned; S14, stirring and sinking to the first group depth; performing grouting injection; S15, whether the designed pile is reached; S151, if reached, re-stir the pile bottom, reverse and lift, remove the drill rod, and put it back into the pre-buried hole; S152. If the pile is not reached, remove the drill rod joint and move the pile driver; connect the pre-buried drill rod and pull out the drill rod; move the pile driver to the construction pile position and connect the drill rod; stir and sink the pre-buried drill rod, which can be repeated several times until the designed pile is reached; S16: After the single pile construction is completed, the pile driver is moved to the construction pile position; S17. The residue is transported out and the construction is completed.
3. The comprehensive construction method for supporting ultra-deep foundation pits in weakly permeable soil with high water level according to claim 1 is characterized by: In step S2, the construction process of reinforced concrete support piles includes measurement and layout → drilling rig in place to open holes → setting casing and injecting mud → drilling → hole cleaning → placing steel cage and grouting pipe → placing guide tube → secondary hole cleaning → concrete pouring → pulling out guide tube → pulling out casing → drilling rig shifting → empty hole backfilling.
4. The comprehensive construction method for supporting ultra-deep foundation pits in weakly permeable soil with high water level according to claim 1 is characterized by: In step S3, the high-pressure rotary jet grouting pile construction process includes: measuring and setting out → drilling rig in place → stabilizing and calibrating the drilling rig → preparing cement slurry → penetrating the jet pipe with high-pressure mud rotary jetting to force soil cutting and drilling → rechecking the verticality of the drilling rig → continuing drilling → designing the pile bottom elevation value → rotary jetting of the drilling rig to lift the drill to the top of the pile → moving the drilling rig to the new pile position.
5. The comprehensive construction method for supporting ultra-deep foundation pits in weakly permeable soil with high water level according to claim 1 is characterized by: In step S4, the construction process of the dewatering well includes: determining the axis line, placing the well point → positioning the drilling rig, drilling the hole → changing the slurry, lowering the filter pipe, filling the gravel → washing the well → making the ground joint pipe or drainage ditch → lowering the pump to pump water → observing and maintaining the dewatering.
6. The comprehensive construction method for supporting ultra-deep foundation pits in weakly permeable soil with high water level according to claim 1 is characterized by: In step S7, the anchor cable construction process includes: digging to the designed elevation → measuring and laying out, anchor cable production → drilling rig in place to open the cast-in-place pile hole → drilling with self-contained anchor cable → drilling to the designed length → drilling with drill rod into anchor → maintenance → tensioning and locking → cutting off excess steel strands to protect the anchor head.
7. The comprehensive construction method for supporting ultra-deep foundation pits in weakly permeable soil with high water level according to claim 1 is characterized by: In step S7, the installation and removal construction process of the inner support includes: S71, after the foundation slab and exterior wall are constructed to the second support of 500, and the exterior wall waterproofing is completed, pour C15 concrete between the exterior wall and the supporting piles; S72. After the concrete between the outer wall and the outer wall and the supporting piles reaches the designed strength, the second support is removed; S73, after the first support of the exterior wall is 500 meters, and the exterior wall waterproofing is completed, pour C15 concrete between the exterior wall and the supporting piles; S74. After the concrete of the exterior wall and between the exterior wall and the supporting piles reaches the designed strength, additional support is added to the inner side of the exterior wall and the first support is removed; S75. After the exterior wall is constructed to more than 300 meters above the bottom roof slab and the bottom roof slab is constructed, and the exterior wall waterproofing is completed, pour C15 concrete between the exterior wall and the supporting piles; after the concrete between the exterior wall and the supporting piles reaches the designed strength, remove the inner support of the exterior wall.
8. The comprehensive construction method for supporting ultra-deep foundation pits in weakly permeable soil with high water level according to claim 1 is characterized by: In step S8, the narrow and difficult to compact parts are filled with foam concrete, and the other parts are backfilled and compacted in layers with graded crushed stones.
9. The comprehensive construction method for supporting ultra-deep foundation pits in weakly permeable soil with high water level according to claim 1 is characterized by: In step S8, the monitoring items include horizontal and vertical displacement of the pit top; deep horizontal displacement; groundwater level change monitoring; anchor cable internal force, support internal force, pit bottom uplift monitoring; and road settlement and crack monitoring around the foundation pit.