Gas turbine power plant furnace bottom through-wall pipe expansion device

By designing a multi-layer insulating pillow and ceramic cloth furnace bottom wall-penetrating tube expansion device in a gas turbine power plant, and using hot melt technology to achieve sealing, the problems of poor sealing and over-temperature are solved, and the flue gas heat exchange efficiency and safety are improved. .

CN118793864APending Publication Date: 2024-10-18HUANENG CHONGQING LIANGJIANG GAS TURBINE POWER GENERATION CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411066586.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-05
Publication Date
2024-10-18

AI Technical Summary

Technical Problem

The poor sealing between the furnace floor and the pipes in the gas turbine power plant results in reduced flue gas heat exchange efficiency and serious overtemperature in the boiler area. The bellows is damaged due to the reduced flexibility of the expansion joint, and the flue gas leaks directly from the crack to the furnace bottom, posing safety risks.

Method used

A furnace bottom wall-through tube expansion device is designed, which uses a combination of multi-layer insulation pillows, ceramic cloth and other materials. The hot melt technology is used to seal the interface of each layer of material without leakage, and the sliding blockage of the flue gas solves the problem of hot and cold expansion and contraction. Improve thermal insulation effect and prevent overheating.

Benefits of technology

It effectively improves the flue gas heat exchange efficiency, avoids damage to the bellows, improves the safety of the furnace bottom temperature environment, and solves the over-temperature problem caused by poor sealing.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118793864A_ABST
    Figure CN118793864A_ABST
Patent Text Reader

Abstract

The invention belongs to the technical field of gas turbine power plants, particularly relates to a gas turbine power plant furnace bottom through-wall pipe expansion device, and provides the following scheme aiming at the problems of low flue gas heat exchange efficiency, poor sealing and serious boiler area overtemperature in the background technology: the gas turbine power plant furnace bottom through-wall pipe expansion device comprises a furnace wall plate, and an upper flange is welded on the outer wall of the bottom of the furnace wall plate; a lower flange is arranged at the bottom of the upper flange, and a first heat insulation pillow is arranged in the upper flange. The problems that under the condition of unit start-stop reciprocating motion and high-temperature flue gas scouring, the flexibility of the corrugated expansion joint reduces thin-wall tension fracture and damage, thermal insulation cotton in the box is lost, flue gas directly leaks to the furnace bottom from a crack, and the flue gas heat exchange efficiency is reduced are solved, the serious over-temperature phenomenon is avoided, accordingly, corrugated pipe damage is avoided, and the service life of the corrugated pipe is prolonged. And flue gas is prevented from directly washing towards the furnace bottom from a crack of the corrugated pipe, the temperature environment of the whole furnace bottom is improved, the safety coefficient is high, and the problem of serious overtemperature of a boiler area due to poor sealing is solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of gas turbine power plants, in particular to a furnace bottom wall penetrating pipe expansion device for gas turbine power plants. Background Art

[0002] Whether it is a gas turbine or an ordinary internal combustion engine, their working principles are basically the same. That is, the fuel is compressed, ignited, burned, and expanded in the cylinder to generate huge pressure gas to push the piston (internal combustion engine) or impeller (gas turbine). The piston can rotate the output shaft through the crank-connecting rod mechanism, and the impeller directly drives the rotor to rotate, thus realizing the conversion of combustion heat energy into mechanical energy.

[0003] After the gas turbine unit is started, the inlet header of the high-temperature reheater of the waste heat boiler is filled with steam and water, the metal temperature rises, and the inlet header of the high-temperature reheater will sink, causing the insulation covering the pipe to move down. The thermal insulation expansion performance of the pipe is poor. After moving down, a gap will appear in the insulation of the pipe, and all the insulation cotton between the furnace bottom plate and the pipe will be squeezed open to create gaps. In addition, the start and stop of the unit, the high temperature environment and flue gas and other factors cause the insulation cotton in the insulation box in the furnace to be missing, and the pipe insulation is incomplete, resulting in serious overheating. After a long time, the bellows is damaged, and the flue gas directly flushes to the furnace bottom from the crack of the bellows, making the temperature environment of the entire furnace bottom harsh, posing a great safety hazard.

[0004] Therefore, under the reciprocating motion of the gas turbine unit at start and stop and the scouring of high-temperature flue gas, the elasticity of the corrugated expansion joint is reduced and the thin wall is torn and damaged, which will lead to the loss of thermal insulation cotton in the box, and the flue gas will directly leak from the crack to the bottom of the furnace, resulting in a decrease in the flue gas heat exchange efficiency.

[0005] In addition, due to poor sealing, serious overheating problems may occur in the boiler area. Summary of the invention

[0006] In view of the deficiencies of the prior art, the present invention provides a furnace bottom through-wall pipe expansion device for a gas turbine power plant, which overcomes the deficiencies of the prior art and effectively solves the problems of reduced flue gas heat exchange efficiency, poor sealing, and serious overheating in the boiler area.

[0007] In order to achieve the above object, the present invention adopts the following technical solutions:

[0008] A furnace bottom through-wall pipe expansion device for a gas turbine power plant, comprising a furnace wall plate, an upper flange is welded to the outer wall of the bottom of the furnace wall plate, and a lower flange is arranged at the bottom of the upper flange, a first insulation pillow is arranged inside the upper flange, and L-shaped steel hooks are welded to the inner wall of the bottom of the upper flange and are equidistantly distributed, and U-shaped steel hooks are welded to the outer wall of the bottom of the L-shaped steel hook, a second insulation pillow is arranged at the bottom of the first insulation pillow, and a third insulation pillow is arranged on the outer wall of the second insulation pillow, and a non-metallic composite layer is arranged on the outer wall of the third insulation pillow, a stainless steel sheet is arranged between the second insulation pillow and the third insulation pillow, and a limiting connecting rod equidistantly distributed is welded between the upper flange and the lower flange, and a steel belt is arranged on the outer wall of the third insulation pillow, and a ceramic cloth is arranged on the outer wall of the steel belt;

[0009] The second thermal insulation pillow and the outer wall of the ceramic cloth are respectively provided with a symmetrically distributed first steel wire ring and a second steel wire ring, a skin is provided inside the non-metallic composite layer, and a polytetrafluoroethylene film is provided on the outer wall of the skin, a top clamp and a bottom clamp are respectively provided on the top and bottom of the outer wall of the skin, and the outer walls of the top clamp and the bottom clamp are fixedly connected with a first fastener.

[0010] Through the above scheme, the first insulation pillow, the second insulation pillow and the third insulation pillow are arranged in the device. On the premise of the first insulation pillow as the basic seal, the second insulation pillow and the third insulation pillow slide relative to each other to solve the problem of hot and cold expansion and contraction. During operation, the flue gas is blocked by sliding, so as to solve the problem that the bellows expansion joint has reduced elasticity, thin wall cracking and damage, insulation cotton in the box is missing, flue gas directly leaks from the crack to the bottom of the furnace, and the flue gas heat exchange efficiency is reduced under the reciprocating motion of the unit start and stop and the high-temperature flue gas scouring. The through-wall pipe expansion device adopts hot-melt technology to hot-melt the interface of each layer of materials into a whole to make the product sealed and leak-free, so as to prevent the lack of insulation cotton in the insulation box in the furnace due to high temperature environment and flue gas. The pipeline covering insulation effect is very comprehensive, so as to avoid serious overheating, thereby avoiding damage to the bellows and preventing flue gas from directly scouring from the bellows crack to the bottom of the furnace, improving the temperature environment of the entire furnace bottom, with a high safety factor, and solving the problem of serious overheating in the boiler area due to poor sealing.

[0011] Preferably, the third heat insulation pillow is closely attached to the inner wall of the U-shaped steel hook.

[0012] Preferably, the outer wall of the polytetrafluoroethylene membrane is provided with polytetrafluoroethylene cloth and alkali-free glass fiber cloth.

[0013] Preferably, glass fiber wool is arranged inside the ceramic cloth.

[0014] Preferably, a furnace body is arranged on the top outer wall of the furnace wall plate, and a through-wall pipe is arranged on the bottom outer wall of the furnace body.

[0015] Preferably, the inner walls of the first thermal insulation pillow and the second thermal insulation pillow are both tightly attached to the outer wall of the wall-penetrating tube.

[0016] Preferably, a flange clamp is welded to the outer wall of the top of the lower flange, and the flange clamp is tightly attached to the outer wall of the wall-penetrating pipe, and the second fastener is fixedly connected to the outer wall of the flange clamp.

[0017] Preferably, the outer wall of the third thermal insulation pillow is provided with vertical grooves distributed at equal distances, and the limiting connecting rods are arranged on the inner walls of the vertical grooves.

[0018] Preferably, the outer wall of the ceramic cloth is provided with symmetrically distributed first annular grooves, and the second wire ring is arranged on the inner wall of the first annular groove.

[0019] Preferably, the outer wall of the second thermal insulation pillow is provided with symmetrically distributed second annular grooves, and the first wire ring is arranged on the inner wall of the second annular groove.

[0020] The beneficial effects of the present invention are:

[0021] 1. The wall-penetrating pipe expansion device for the furnace bottom of a gas turbine power plant of the present invention is provided with a first insulation pillow, a second insulation pillow and a third insulation pillow. On the premise of the first insulation pillow as the basic seal, the second insulation pillow and the third insulation pillow are used to slide relative to each other to solve the problem of cold and hot expansion and contraction. During operation, the flue gas is blocked by sliding, so as to solve the problem that the bellows expansion joint has reduced elasticity, thin-wall tearing and damage, the insulation cotton in the box is missing, the flue gas directly leaks from the crack to the furnace bottom, and the flue gas heat exchange efficiency is reduced under the reciprocating motion of the unit start and stop and the scouring of high-temperature flue gas;

[0022] 2. The wall-penetrating pipe expansion device for the furnace bottom of a gas turbine power plant of the present invention adopts hot-melt technology to hot-melt the interfaces of each layer of materials into a whole so that the product is sealed and leak-free, thereby preventing the occurrence of high temperature environment and smoke and other factors that cause the loss of insulation cotton in the insulation box in the furnace. The pipe covering insulation effect is very comprehensive, avoiding serious overheating, thereby avoiding damage to the bellows, preventing smoke from directly flushing to the furnace bottom from the cracks in the bellows, improving the temperature environment of the entire furnace bottom, and having a high safety factor, solving the problem of serious overheating in the boiler area due to poor sealing. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] Figure 1 This is a front view of the overall structure of a furnace bottom through-wall pipe expansion device for a gas turbine power plant proposed by the present invention;

[0024] Figure 2 This is a schematic diagram of the overall structure of a furnace bottom through-wall pipe expansion device for a gas turbine power plant proposed by the present invention;

[0025] Figure 3 A schematic diagram of the internal structure of a ceramic cloth of a wall-penetrating pipe expansion device for a furnace bottom of a gas turbine power plant proposed by the present invention;

[0026] Figure 4This is a schematic diagram of the structure of a fuel-fired power plant furnace bottom through-wall pipe expansion device in a startup state proposed by the present invention;

[0027] Figure 5 The present invention is a schematic structural diagram of a shutdown state of a furnace bottom through-wall pipe expansion device for a gas turbine power plant.

[0028] In the figure: 1. furnace wall plate; 2. upper flange; 3. lower flange; 4. first insulation pillow; 5. L-shaped steel hook; 6. U-shaped steel hook; 7. second insulation pillow; 8. third insulation pillow; 9. non-metallic composite layer; 10. stainless steel sheet; 11. limit connecting rod; 12. steel belt; 13. first steel wire ring; 14. second steel wire ring; 15. ceramic cloth; 16. skin; 17. polytetrafluoroethylene film; 18. top clamp; 19. bottom clamp; 20. first fastener; 21. wall pipe; 22. flange clamp; 23. second fastener; 24. furnace body; 25. first annular groove; 26. second annular groove; 27. vertical groove. DETAILED DESCRIPTION

[0029] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments.

[0030] Embodiment 1, refer to Figures 1 to 5 A furnace bottom through-wall pipe expansion device for a gas turbine power plant comprises a furnace wall plate 1, an upper flange 2 is welded to the bottom outer wall of the furnace wall plate 1, and a lower flange 3 is arranged at the bottom of the upper flange 2, a first thermal insulation pillow 4 is arranged inside the upper flange 2, and L-shaped steel hooks 5 with equal distances are welded to the bottom inner wall of the upper flange 2, and U-shaped steel hooks 6 with equal distances are welded to the bottom outer wall of the L-shaped steel hook 5, a second thermal insulation pillow 7 is arranged at the bottom of the first thermal insulation pillow 4, and a third thermal insulation pillow 8 is arranged on the outer wall of the second thermal insulation pillow 7, a non-metallic composite layer 9 is arranged on the outer wall of the third thermal insulation pillow 8, a stainless steel sheet 10 is arranged between the second thermal insulation pillow 7 and the third thermal insulation pillow 8, and a limiting connecting rod 11 with equal distances is welded between the upper flange 2 and the lower flange 3, a steel belt 12 is arranged on the outer wall of the third thermal insulation pillow 8, and a ceramic cloth 15 is arranged on the outer wall of the steel belt 12.

[0031] In this embodiment, the device is provided with a first insulation pillow 4, a second insulation pillow 7 and a third insulation pillow 8. On the premise of the first insulation pillow 4 as the basic seal, the second insulation pillow 7 and the third insulation pillow 8 slide relative to each other to solve the problem of thermal expansion and contraction. During operation, the flue gas is blocked by sliding, so as to solve the problem that the elasticity of the corrugated expansion joint is reduced, the thin wall is torn and damaged, the insulation cotton in the box is missing, the flue gas directly leaks from the crack to the bottom of the furnace, and the flue gas heat exchange efficiency is reduced under the reciprocating motion of the start and stop of the unit and the scouring of high-temperature flue gas.

[0032] Example 3, refer to Figure 2 , a furnace bottom through-wall pipe expansion device for a gas turbine power plant, the outer walls of the second insulation pillow 7 and the ceramic cloth 15 are respectively provided with symmetrically distributed first steel wire rings 13 and second steel wire rings 14, a skin 16 is provided inside the non-metallic composite layer 9, and a polytetrafluoroethylene film 17 is provided on the outer wall of the skin 16, a top clamp 18 and a bottom clamp 19 are respectively provided on the top and bottom of the outer wall of the skin 16, and the outer walls of the top clamp 18 and the bottom clamp 19 are fixedly connected with a first fastener 20.

[0033] In this embodiment, the expansion device of the wall-penetrating pipe 21 adopts hot-melt technology to hot-melt the interface of each layer of material into a whole to make the product sealed and leak-free, thereby preventing the high temperature environment and smoke and other factors from causing the insulation cotton in the insulation box in the furnace to be missing. The pipeline coverage insulation effect is very comprehensive, avoiding serious overheating, thereby avoiding damage to the bellows, preventing smoke from directly flushing to the bottom of the furnace from the cracks in the bellows, improving the temperature environment of the entire furnace bottom, and having a high safety factor, solving the problem of serious overheating in the boiler area due to poor sealing.

[0034] Reference Figure 3 The third heat insulation pillow 8 is closely attached to the inner wall of the U-shaped steel hook 6 .

[0035] Reference Figure 2 The outer wall of the polytetrafluoroethylene film 17 is provided with polytetrafluoroethylene cloth and alkali-free glass fiber cloth. The polytetrafluoroethylene film 17 has the characteristics of acid and alkali resistance and resistance to various organic solvents, and is almost insoluble in all solvents. At the same time, polytetrafluoroethylene has the characteristics of high temperature resistance, its friction coefficient is extremely low, and its air tightness is strong. The polytetrafluoroethylene cloth is between low temperature -196℃ and high temperature 350℃, and has weather resistance, aging resistance, non-adhesiveness, chemical corrosion resistance, strong acid, strong alkali, aqua regia and various organic solvents. It has a low friction coefficient (0.05-0.1) and is the best choice for oil-free self-lubrication. The light transmittance reaches 6-13%. It has high insulation performance, good dimensional stability, high strength, drug resistance, and non-toxicity. Alkali-free glass fiber cloth is an inorganic non-metallic material with excellent performance, good insulation, strong heat resistance, good corrosion resistance, and high mechanical strength.

[0036] Reference Figure 2 The ceramic cloth 15 is provided with glass fiber wool inside. The continuous use temperature of the ceramic cloth 15 can reach 1000°C, and the short-term use temperature can reach 1260°C. It has good acid and alkali corrosion resistance and resistance to molten metal erosion such as aluminum and zinc, good high-temperature strength and thermal insulation performance, non-toxic, harmless, and odorless. Glass fiber wool is an amorphous material. It has no fixed melting point. It is generally believed that its softening point is 500-750°C. The biggest feature is high tensile strength and good heat resistance. When the temperature reaches 300°C, it has no effect on strength. It has excellent electrical insulation and is an advanced electrical insulation material. It is also used for thermal insulation materials and fire shielding materials.

[0037] Reference Figures 2 to 4 A furnace body 24 is provided on the top outer wall of the furnace wall panel 1, and a through-wall pipe 21 is provided on the bottom outer wall of the furnace body 24. The inner walls of the first thermal insulation pillow 4 and the second thermal insulation pillow 7 are both tightly attached to the outer wall of the through-wall pipe 21. The first thermal insulation pillow 4 and the second thermal insulation pillow 7 wrap the through-wall pipe 21 in turn for sealing.

[0038] Reference Figure 1 A flange clamp 22 is welded to the outer wall of the top of the lower flange 3, and the flange clamp 22 is tightly attached to the outer wall of the wall-penetrating pipe 21. The second fastener 23 is fixedly connected to the outer wall of the flange clamp 22. Fixing the second fastener 23 on the flange clamp 22 can increase the fastness between the lower flange 3 and the wall-penetrating pipe 21.

[0039] Reference Figures 2 to 3 The outer wall of the third thermal insulation pillow 8 is provided with vertical grooves 27 distributed at equal distances, and the limiting connecting rod 11 is arranged on the inner wall of the vertical groove 27.

[0040] Reference Figures 2 to 3 The outer wall of the ceramic cloth 15 is provided with a symmetrically distributed first annular groove 25, and the second steel wire ring 14 is arranged on the inner wall of the first annular groove 25; the outer wall of the second thermal insulation pillow 7 is provided with a symmetrically distributed second annular groove 26, and the first steel wire ring 13 is arranged on the inner wall of the second annular groove 26.

[0041] Working principle:

[0042] (I) Remove the aluminum skin and insulation of the furnace bottom wall pipe 21, steel drum and baffle

[0043] First, remove the aluminum skin and insulation of the furnace bottom through-wall pipe 21, cut the furnace bottom plate steel barrel and baffle of the through-wall pipe 21 with electric welding, and remove and clean the invalid insulation cotton inside;

[0044] Then, keep the construction site clean during dismantling, and sort the old insulation cotton to the designated location in time and place it neatly.

[0045] (II) Welding of new flange

[0046] First, the furnace wall plate 1 where the new flange is welded is polished and smoothed to meet the installation requirements of the new flange;

[0047] Then, strictly follow the design process requirements to check whether the flange size design is consistent with the actual size on site, whether there are defects such as welding leakage, pores, deformation, etc., and make timely corrections;

[0048] After that, after the flange is confirmed to be correct, the pre-made flange will be welded in sequence according to the design plan and the requirements of the construction drawing;

[0049] Finally, after welding, polish it to make it flat, smooth and burr-free to ensure that it meets the installation requirements of skin 16.

[0050] (III) Installation of insulation part

[0051] First, the heat insulation inside the skin 16 is carried out by using a heat insulation pillow. The prefabricated first heat insulation pillow 4 is installed in the upper flange 2 close to the furnace wall plate 1. The surrounding gaps are then filled with sheet-like heat insulation cotton and then fixed by welding an L-shaped steel hook 5.

[0052] Then, prepare to install the second insulation pillow 7, the insulation pillow wraps the aluminum silicate insulation cotton around the wall-penetrating pipe 21 according to the actual situation on site, and then wraps it with the first steel wire ring 13;

[0053] After that, after installing the second heat-insulating pillow 7, the U-shaped steel hook 6 is welded to the L-shaped steel hook 5 close to the second heat-insulating pillow 7;

[0054] Next, in order to ensure that the second insulation pillow 7 and the third insulation pillow 8 can fully slide when the unit is running to block the gap leakage of flue gas caused by the up and down movement of the pipe, we weld a stainless steel sheet 10 between the insulation pillows of the second insulation pillow 7 and the third insulation pillow 8;

[0055] Then, finally install the prepared third heat-insulating pillow 8 close to the U-shaped steel hook 6, and finally tighten it with a steel belt 12;

[0056] Finally, the outermost layer is wrapped with ceramic cloth 15 to insulate and isolate the skin 16 from the third insulation pillow 8.

[0057] (IV) Installation of skin 16

[0058] First, fix the skin 16 on the upper flange 2 and the lower flange 3 and make the joint of the skin 16. The joint of the skin 16 is firmly bonded using a special welding tool hot melt machine. Set the bonding time of the polytetrafluoroethylene film 17 and the alkali-free glass fiber cloth respectively. Press and delay for about three to five seconds before releasing. Each layer must have more than two bonding seams to ensure that the product is sealed without leakage.

[0059] Then, use the top clamp 18 and the bottom clamp 19 to neatly fix the skin 16 on the flange position, and when tightening the bolts on the first fastener 20 of the clamp, hit the clamp with appropriate force so that the pre-tightening force of the clamp acts evenly on the clamp to prevent the skin 16 from wrinkling and causing leakage points, and lock the clamp with appropriate pre-tightening force;

[0060] Finally, check the air tightness of the skin 16 joint and whether the pre-tightening force of the clamp is sufficient.

[0061] In the description of the present invention, it is necessary to understand that the orientations or positional relationships indicated by the terms, "up", "down", "front", "back", "left", "right", "top", "bottom", "inside", "outside", etc. are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.

[0062] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include one or more of the features. In the description of the present invention, the meaning of "plurality" is two or more, unless otherwise clearly and specifically defined.

[0063] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes according to the technical scheme and inventive concept of the present invention within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.

Claims

1. A furnace bottom through-wall pipe expansion device for a gas turbine power plant, comprising a furnace wall plate (1), characterized in that: The furnace wall plate (1) is welded with an upper flange (2) on the outer wall at the bottom, and a lower flange (3) is arranged at the bottom of the upper flange (2); a first heat-insulating pillow (4) is arranged inside the upper flange (2); L-shaped steel hooks (5) are welded to the inner wall at the bottom of the upper flange (2) at equal distances; U-shaped steel hooks (6) are welded to the outer wall at the bottom of the L-shaped steel hook (5) at equal distances; a second heat-insulating pillow (7) is arranged at the bottom of the first heat-insulating pillow (4); and the second heat-insulating pillow (7) is arranged at the bottom of the first heat-insulating pillow (4). (7) A third heat-insulating pillow (8) is provided on the outer wall, a non-metallic composite layer (9) is provided on the outer wall of the third heat-insulating pillow (8), a stainless steel sheet (10) is provided between the second heat-insulating pillow (7) and the third heat-insulating pillow (8), and equidistantly distributed limiting connecting rods (11) are welded between the upper flange (2) and the lower flange (3), a steel belt (12) is provided on the outer wall of the third heat-insulating pillow (8), and a ceramic cloth (15) is provided on the outer wall of the steel belt (12); The outer walls of the second thermal insulation pillow (7) and the ceramic cloth (15) are respectively provided with a first steel wire ring (13) and a second steel wire ring (14) which are symmetrically distributed; a skin (16) is provided inside the non-metallic composite layer (9); and a polytetrafluoroethylene film (17) is provided on the outer wall of the skin (16); a top clamp (18) and a bottom clamp (19) are respectively provided on the top and bottom of the outer wall of the skin (16); and the outer walls of the top clamp (18) and the bottom clamp (19) are both fixedly connected with a first fastener (20).

2. The expansion device for the bottom wall pipe of a gas turbine power plant according to claim 1 is characterized in that: The third heat-insulating pillow (8) is closely attached to the inner wall of the U-shaped steel hook (6).

3. The expansion device for the bottom wall pipe of a gas turbine power plant according to claim 1, characterized in that: The outer wall of the polytetrafluoroethylene membrane (17) is provided with polytetrafluoroethylene cloth and alkali-free glass fiber cloth.

4. The expansion device for the bottom wall pipe of a gas turbine power plant according to claim 1, characterized in that: Glass fiber wool is arranged inside the ceramic cloth (15).

5. The expansion device for the bottom wall pipe of a gas turbine power plant according to claim 1, characterized in that: A furnace body (24) is arranged on the top outer wall of the furnace wall plate (1), and a wall-penetrating pipe (21) is arranged on the bottom outer wall of the furnace body (24).

6. The expansion device for the bottom wall pipe of a gas turbine power plant according to claim 1, characterized in that: The inner walls of the first heat-insulating pillow (4) and the second heat-insulating pillow (7) are both tightly attached to the outer wall of the wall-penetrating tube (21).

7. The expansion device for the bottom wall pipe of a gas turbine power plant according to claim 1, characterized in that: A flange clamp (22) is welded to the outer wall of the top of the lower flange (3), and the flange clamp (22) is tightly attached to the outer wall of the wall-penetrating pipe (21), and a second fastener (23) is fixedly connected to the outer wall of the flange clamp (22).

8. The expansion device for the bottom wall pipe of a gas turbine power plant according to claim 1, characterized in that: The outer wall of the third heat-insulating pillow (8) is provided with vertical grooves (27) distributed at equal distances, and the limiting connecting rod (11) is arranged on the inner wall of the vertical groove (27).

9. The expansion device for the bottom wall pipe of a gas turbine power plant according to claim 1, characterized in that: The outer wall of the ceramic cloth (15) is provided with symmetrically distributed first annular grooves (25), and the second wire ring (14) is arranged on the inner wall of the first annular groove (25).

10. The expansion device for the bottom wall pipe of a gas turbine power plant according to claim 1, characterized in that: The outer wall of the second heat-insulating pillow (7) is provided with symmetrically distributed second annular grooves (26), and the first wire ring (13) is arranged on the inner wall of the second annular groove (26).