Generator water cut-off protection method based on multi-signal redundancy and application
By adopting multi-signal redundant protection logic and dynamic signal processing in the generator water-cut protection system, the problems of low monitoring accuracy and poor fault detection capability in the existing technology are solved, achieving higher system reliability and flexibility, and ensuring Safe operation of generators.
Patent Information
- Application Number
- CN202411105555.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-13
- Publication Date
- 2024-10-18
AI Technical Summary
The existing generator water cutoff protection system relies on differential pressure switches to monitor cooling water flow. It has problems such as low monitoring accuracy, poor fault detection capabilities, inflexible signal processing and a single delay protection mechanism, which affects the safe operation of the generator.
Using multi-signal redundant protection logic design, the cooling water flow is measured in real time by installing three sets of orifice flowmeters on the fixed cooling jellyfish pipe, combined with high and low comparators, AND gates, OR gates, limited OR gates, switching blocks and delays. The dynamic signal processing module of the block realizes multi-signal redundancy protection and flexible adjustment of signals to ensure the effective operation of the system under different working conditions.
It improves the monitoring accuracy and response speed, reduces the risk of protection system failure caused by a single equipment failure, simplifies maintenance work, enhances the flexibility and adaptability of the system, and ensures the safe operation and high reliability of the generator.
Smart Images

Figure SMS_4 
Figure SMS_9 
Figure SMS_11
Abstract
Description
Technical Field
[0001] The present invention relates to the field of power generation equipment protection, and in particular to a generator water cut-off protection method and application based on multi-signal redundancy. Background Art
[0002] The existing generator water cut-off protection system relies on a differential pressure switch to monitor the cooling water flow. Since the differential pressure switch cannot monitor the cooling water flow in real time and cannot detect the switch failure in time, there is a risk of protection failure, which affects the safe operation of the generator. Therefore, a more reliable and flexible water cut-off protection method is needed. The existing WK63 / 71 single-bar, double-divided, bottom-exhaust condensing steam turbine still has the following defects: 1. Multi-signal redundant protection logic design In the traditional generator water cut-off protection system, the cooling water flow is monitored by a differential pressure switch. The differential pressure switch is installed on the cooling water outlet main pipe and the return pipe, and the cooling water flow is determined by detecting the pressure difference between these two points. This method has multiple limitations and risks. First, the monitoring accuracy and real-time performance of the differential pressure switch are poor. Since the differential pressure switch can only detect the pressure difference and cannot directly measure the flow, when the cooling water flow changes, the differential pressure switch responds slowly and the accuracy is not high. The setting value of the differential pressure switch is fixed. When the cooling water flow is close to the set value, it is easy to make a misjudgment, which may lead to the false operation or refusal of the protection system.
[0003] The fault detection capability of the differential pressure switch is limited. The differential pressure switch may fail during long-term operation due to mechanical wear, environmental pollution, or electrical failure. However, the traditional generator water outage protection system cannot monitor the working status of the differential pressure switch in real time. When the differential pressure switch fails, it is difficult for the operator to detect and handle it in time. In this case, the protection system may lose its monitoring capability, thereby increasing the risk of water outage of the generator and seriously affecting the safe operation of the generator. The installation and maintenance costs of the differential pressure switch are high. The differential pressure switch needs to be installed at a specific location on the cooling water pipeline. The installation process is complicated and requires regular calibration and maintenance to ensure that it works properly. This high-frequency maintenance work not only increases the operating cost, but also increases the workload of maintenance personnel.
[0004] 2. Dynamic signal processing In traditional signal processing technology, a simple logic circuit is used to determine the state of the cooling water flow signal. Although this signal processing method is simple to implement, it has multiple limitations. First, the traditional logic circuit design is relatively simple and lacks flexibility. The traditional signal processing circuit uses fixed logic gates to make signal judgments, which is difficult to adapt to complex working conditions. When the cooling water flow signal fluctuates or interferes, the traditional logic circuit is prone to misjudgment, resulting in false operation or refusal to operate the protection system. Traditional signal processing circuits cannot achieve multi-signal redundant protection. In traditional designs, only a single signal source is used for protection judgment, lacking redundant design. When a single signal source fails, the protection system will lose its judgment basis, increasing the risk of water outages in the generator.
[0005] Traditional signal processing circuits lack dynamic adjustment capabilities. In the actual monitoring process of cooling water flow, the flow signal is often affected by factors such as environmental changes and equipment aging, resulting in fluctuations or drift. However, traditional signal processing circuits cannot be dynamically adjusted according to actual conditions and are difficult to adapt to complex working conditions. In this case, the stability and reliability of the protection system will be greatly reduced. In addition, traditional signal processing circuits lack self-test and fault handling capabilities. When the signal processing circuit itself fails, it is difficult for operators to detect and handle it in time, thereby increasing the risk of the protection system.
[0006] 3. Delay protection mechanism The traditional generator water outage protection system adopts a fixed time-delay protection mechanism, that is, when an abnormal cooling water flow is detected, the protection action is triggered after a fixed delay. Although this protection mechanism is simple to implement, it has several limitations. First, the traditional time-delay protection mechanism cannot adapt to the needs of different working conditions. In actual operation, the changes in cooling water flow are complex and diverse, and the protection delay requirements under different working conditions may be different. However, the traditional time-delay protection mechanism cannot be adjusted according to the actual situation, resulting in the protection system being triggered too early or too late in some cases, thus affecting the protection effect.
[0007] The traditional time-delay protection mechanism cannot achieve multi-stage protection. In actual operation, the cooling water flow abnormality may be gradual, that is, the cooling water flow gradually decreases until the water is cut off. However, the traditional time-delay protection mechanism only sets a fixed delay time and cannot perform multi-stage protection for abnormal conditions at different stages. In this case, when the cooling water flow gradually decreases, the protection system may not be triggered in time, increasing the risk of water cutoff of the generator. In addition, the traditional time-delay protection mechanism lacks adaptive capabilities. In actual operation, the cooling water flow signal may be disturbed or fluctuated, resulting in a short-term abnormality of the signal. The traditional time-delay protection mechanism cannot be adaptively adjusted according to the actual situation and is easily affected by interference signals, resulting in false operation or refusal of the protection system. In general, the traditional generator water cutoff protection system has many disadvantages such as low monitoring accuracy, poor fault detection capability, inflexible signal processing, and a single time-delay protection mechanism, which makes it difficult to meet the requirements of modern power generation equipment for high reliability and high stability of the protection system. Summary of the invention
[0008] A generator water cut-off protection method and application based on multi-signal redundancy, the specific steps are as follows: signal acquisition and comparison, high and low comparator judgment, signal validity judgment, logic and operation, logic or operation, signal summation processing, redundant protection switching, delayed protection mechanism, and protection action triggering.
[0009] Step S1: signal acquisition and comparison.
[0010] Step S2: High-low comparator judgment.
[0011] Step S3: Signal validity determination.
[0012] Step S4: logical AND operation.
[0013] Step S5: logical OR operation.
[0014] Step S6: Signal summing processing.
[0015] Step S7: Redundancy protection switching.
[0016] Step S8: Delay protection mechanism.
[0017] Step S9: protection action triggering.
[0018] Furthermore, in step S1 , three stator cooling water flow meters ( D0001 , D0002 , D0003 ) collect cooling water flow signals.
[0019] Furthermore, in step S2, the signal of each flow meter is compared with the set value (50 t / h) through a high-low comparator (H / L) to determine whether it is lower than the set value.
[0020] Furthermore, in step S3, the quality judgment module (TSTO and NOT) detects the validity of the signal.
[0021] Furthermore, in step S4, the three flow meter signals are logically ANDed through an AND gate (AND), and a high level is output when all the signals meet the conditions.
[0022] Furthermore, in step S5, the signal output by the AND gate is subjected to a logic OR operation through an OR gate, and a high level is output as long as one signal meets the condition.
[0023] Furthermore, in step S6, the gain summation module (DSUM) sums the three flow meter signals and determines whether the comprehensive signal meets the set conditions through the high-low comparator (H / L).
[0024] Further, in step S7, the signal comprehensive judgment is processed through a qualified OR gate (QOR), and switching is performed between different signal sources through a switching block (T), and switching to the backup protection logic in case of signal failure.
[0025] Furthermore, in step S8, the delay block (TD-DIG) ensures that the signal is output after a delay of 15 seconds after the signal meets the protection condition.
[0026] Furthermore, in step S9, after a delay of 15 seconds, a generator water cut protection action signal is output, and after the electrical side receives the signal, the generator is de-energized after a delay of another 15 seconds, so that the generator can be shut down smoothly.
[0027] Compared with the prior art, the present invention has the following advantages: 1. Multi-signal redundant protection logic design In the generator water cut protection system, the introduction of multi-signal redundant protection logic design has significant advantages. This design greatly improves the reliability of the system. By installing three sets of orifice flowmeters on the stator cooling water main pipe, the stator cooling water flow can be measured in real time, rather than relying solely on a single differential pressure switch. Under normal circumstances, the system uses the three signals of the flowmeter for judgment. When two of the signals are lower than the set value and the signals are normal, the water cut protection action signal is triggered after a delay of 15 seconds. When one flowmeter signal fails, the system can still rely on the remaining two signals for judgment. When two flowmeter signals fail, the last signal is used for judgment. If all flowmeter signals fail, the system automatically switches to the original differential pressure switch protection logic. This multi-signal redundant protection logic design ensures that the protection system can work effectively in a variety of situations, reducing the risk of protection system failure due to a single device failure.
[0028] The multi-signal redundant protection logic design improves the monitoring accuracy and response speed of the protection system. Compared with the traditional differential pressure switch, the orifice flowmeter can measure the actual flow of cooling water more accurately and respond faster. The traditional differential pressure switch can only indirectly judge the flow rate through the pressure difference, with low accuracy, while the flowmeter can directly measure the flow rate and provide more accurate data. In addition, the signal processing process of the flowmeter is faster and can reflect the changes in the cooling water flow in real time. This high-precision and fast-response monitoring capability enables the protection system to detect abnormalities in the cooling water flow in a timely manner and respond quickly, thereby better protecting the safe operation of the generator.
[0029] The multi-signal redundant protection logic design simplifies maintenance and reduces operating costs. Traditional differential pressure switches require regular calibration and maintenance to ensure they work properly. The maintenance requirements of flow meters are relatively low, and their working status can be monitored in real time by the system. Operators can detect and handle faults in a timely manner, avoiding long-term operation of equipment with faults. In addition, the multi-signal redundant design can automatically switch to the backup protection logic, reducing system downtime and maintenance workload.
[0030] 2. Dynamic signal processing The application of dynamic signal processing in the generator water cut-off protection system solves many limitations of traditional signal processing methods. Dynamic signal processing improves the flexibility and adaptability of the system. By designing a logic processing module including high and low comparators, AND gates, OR gates, limited OR gates, switching blocks and delay blocks, the system can better cope with complex and changeable working conditions. When the cooling water flow signal fluctuates or interferes, the dynamic signal processing system can be adjusted according to the actual situation to ensure the accuracy of signal judgment. The traditional signal processing circuit design is relatively simple, lacks flexibility, and is difficult to adapt to changes in actual working conditions. Dynamic signal processing can adapt to various complex working conditions through flexible logical combinations and reduce the risk of misjudgment and misoperation.
[0031] Dynamic signal processing can achieve multi-signal redundant protection and improve system reliability. In traditional designs, only a single signal source is usually used for protection judgment, lacking redundant design. When a single signal source fails, the protection system will lose its basis for judgment, increasing the risk of water shortage in the generator. The dynamic signal processing system can make redundant judgments through multiple signal sources. When a signal source fails, the system can automatically switch to other signal sources to continue working, ensuring that the protection function is not affected. Dynamic signal processing also has self-test and fault handling capabilities. When the signal processing circuit itself fails, the system can detect and take corresponding measures in time to avoid failure of the protection system.
[0032] Dynamic signal processing improves the stability and reliability of the protection system. Through logic processing modules such as high and low comparators, AND gates, and OR gates, the system can accurately judge the flow signal and reduce the possibility of false operation. The application of limited OR gates and switching blocks ensures that OR operations and signal source switching are performed under specific conditions, further improving the stability of the system. In addition, the use of delay blocks ensures that the signal is output after a certain delay after meeting the protection conditions, avoiding false operation caused by instantaneous interference signals.
[0033] 3. Delay protection mechanism The introduction of the time-delay protection mechanism improves the performance and reliability of the generator water cut-off protection system. First of all, the time-delay protection mechanism can adapt to the needs of different working conditions and provide a more flexible protection method. In the actual operation process, the changes in cooling water flow are complex and diverse, and the protection delay requirements under different working conditions are also different. The traditional time-delay protection mechanism usually adopts a fixed delay time, which is difficult to adjust according to the actual situation, resulting in the protection system being triggered too early or too late in some cases, affecting the protection effect. The modern time-delay protection mechanism can output a signal after a delay of 15 seconds when the protection logic determines that the water cut-off protection action signal needs to be triggered through the delay block (TD-DIG). This can avoid false operation caused by instantaneous interference signals, while ensuring that the protection action is triggered within a reasonable time, improving the adaptability of the system.
[0034] The time-delay protection mechanism can achieve multi-stage protection and enhance the protection capability of the system. In actual operation, the cooling water flow abnormality may be gradual, that is, the cooling water flow gradually decreases until the water is cut off. The traditional time-delay protection mechanism usually only sets a fixed delay time, and cannot perform multi-stage protection for abnormal conditions at different stages, which can easily miss the best protection opportunity. The modern time-delay protection mechanism can set multiple delay periods according to the changing trend of the cooling water flow, and use different delay strategies to deal with flow abnormalities at different stages. When the flow gradually decreases, the protection system can trigger protection actions at different stages to ensure that the generator is protected in a timely and effective manner when the cooling water flow is abnormal.
[0035] The delay protection mechanism has adaptive capabilities and can be dynamically adjusted according to actual conditions to improve the reliability of the system. During the cooling water flow monitoring process, the flow signal will be affected by factors such as environmental changes and equipment aging, resulting in fluctuations or interference. The traditional delay protection mechanism cannot be adaptively adjusted according to actual conditions and is easily affected by interference signals, causing the protection system to malfunction or refuse to operate. The modern delay protection mechanism can dynamically adjust according to the actual flow signal through the delay block, filter out short-term interference signals, and ensure the stability and reliability of the protection system. DETAILED DESCRIPTION
[0036] The subject matter described herein will now be discussed with reference to example embodiments. It should be understood that the discussion of these embodiments is only to enable those skilled in the art to better understand and implement the subject matter described herein, and is not a limitation of the scope of protection, applicability or examples set forth in the claims. The functions and arrangements of the elements discussed can be changed without departing from the scope of protection of the contents of this specification. Various examples can omit, replace or add various processes or components as needed. For example, the described method can be performed in an order different from the described order, and various steps can be added, omitted or combined. In addition, the features described relative to some examples can also be combined in other examples.
[0037] As used herein, the term "including" and its variations represent open terms, meaning "including but not limited to". The term "based on" means "based at least in part on". The terms "one embodiment" and "an embodiment" mean "at least one embodiment". The term "another embodiment" means "at least one other embodiment". The terms "first", "second", etc. may refer to different or the same objects. Other definitions may be included below, whether explicit or implicit. Unless the context clearly indicates otherwise, the definition of a term is consistent throughout the specification.
[0038] Example A generator water cut-off protection method and application based on multi-signal redundancy, the specific steps are as follows: signal acquisition and comparison, high and low comparator judgment, signal validity judgment, logic and operation, logic or operation, signal summation processing, redundant protection switching, delayed protection mechanism, and protection action triggering.
[0039] Step S1: signal acquisition and comparison.
[0040] Step S2: High-low comparator judgment.
[0041] Step S3: Signal validity determination.
[0042] Step S4: logical AND operation.
[0043] Step S5: logical OR operation.
[0044] Step S6: Signal summing processing.
[0045] Step S7: Redundancy protection switching.
[0046] Step S8: Delay protection mechanism.
[0047] Step S9: protection action triggering.
[0048] The following are specific embodiments of the features of the present invention: Step S1: Signal acquisition and comparison In this step, stator cooling water flow meters (D0001, D0002, D0003) are installed on the stator cooling water mother pipe to collect cooling water flow signals in real time. These flow meters convert cooling water flow information into electrical signals and transmit them to subsequent processing modules. By collecting real-time flow signals, the flow of cooling water can be accurately monitored, ensuring the accuracy and timeliness of flow data, and providing a reliable basis for subsequent logical judgment.
[0049] Step S2: High and low comparator judgment After signal acquisition, the signal of each flow meter is sent to the high-low comparator (H / L). The high-low comparator compares the flow signal with the pre-set threshold (50 t / h) to determine whether the flow is lower than the set value. When the flow is lower than the threshold, the high-low comparator outputs a low-level signal (L), otherwise it outputs a high-level signal (H). In this way, the high-low comparator can quickly and accurately identify whether the flow is within the safe range.
[0050] Step S3: Signal validity determination To ensure the reliability of the input signal, the quality judgment module (TSTO and NOT) is used to detect the validity of the flow signal. The TSTO module determines whether the signal is working properly. If the signal is invalid, it outputs a low-level signal. The NOT module acts as a logic NOT gate to convert the invalid signal into a high-level signal. Only signals that pass the quality judgment will continue to be passed to the next step of processing, thereby ensuring that the system only processes valid flow signals and avoids misjudgment caused by invalid signals.
[0051] Step S4: Logical AND operation In this step, the valid signals from the three flow meters are logically ANDed through an AND gate. The output of the AND gate is high only when all input signals are high. This means that the system considers the cooling water flow rate to be normal only when all flow meter signals indicate that the flow rate is normal. In this way, the accuracy of judgment can be improved and the risk of false operation caused by a single signal failure can be reduced.
[0052] Step S5: Logical OR operation The signal after the logic AND operation is passed to the OR gate (OR) for logic OR operation. The output of the OR gate is high as long as one of the input signals is high. This step is used in some cases, when some signals are normal and other signals are faulty, protection judgment can still be made through normal signals, providing a flexible protection method.
[0053] Step S6: Signal summing processing In the signal summing process, the gain summing module (DSUM) sums the three flow meter signals to generate a composite signal. The composite signal is judged by the high and low comparator (H / L) to see whether it meets the set protection conditions. By summing multiple signals, the flow of cooling water can be more comprehensively reflected, the judgment ability of the system can be enhanced, and the reliability of protection can be further improved.
[0054] Step S7: Redundancy protection switching When a signal source fails, the redundant protection switching mechanism starts to work. The signal comprehensive judgment is processed through the qualified OR gate (QOR) to ensure that the OR operation is performed under specific conditions. The switching block (T) is used to switch between different signal sources. When a signal source fails, the system automatically switches to the backup protection logic and uses other normally working signal sources to continue protection judgment to ensure the continuity and reliability of the system.
[0055] Step S8: Delay protection mechanism In this step, the delay block (TD-DIG) ensures that the signal is output after a delay of 15 seconds after the signal meets the protection conditions. The delay protection mechanism is designed to avoid false operation caused by instantaneous interference signals. After the protection signal is triggered, the system will wait for the set delay time to confirm the persistence of the abnormal cooling water flow. The actual protection action will only be triggered after the abnormal situation lasts for more than the delay time, ensuring the accuracy and reliability of the protection action.
[0056] Step S9: Protection action triggering After the delayed protection mechanism confirms that the protection conditions are met, the system outputs the generator water cut protection action signal. After the electrical side receives the protection action signal, it delays for another 15 seconds to trigger the generator to disconnect. The purpose of this delay design is to ensure that the generator can shut down smoothly and avoid equipment damage caused by sudden operations. Through this dual delayed protection mechanism, the system can perform protection operations more reliably and ensure that the generator is protected in a timely and effective manner when the cooling water is cut off.
[0057] The following is a specific technical logic implementation of the innovative points of the present invention: 1. Signal acquisition and comparison: 1.1 Install 3 sets of high-precision orifice flowmeters on the cooling water main pipe to collect the flow signals of cooling water and convert them into electrical signals. .
[0058] 1.2 These signals are processed by high and low comparators, and the signal of each flow meter With the preset threshold For comparison:
[0059] in, It is the output signal of the high and low comparator.
[0060] 2. Signal validity judgment: 2.1 Through the quality judgment module Perform validity check on each signal. If the signal is normal, ; If the signal is invalid, then .
[0061] 2.2 The NOT module is used to convert an invalid signal into a high-level signal to ensure that subsequent logic processing uses only valid signals.
[0062] 3. Logic and operation: 3.1 The three flow meter signals are logically ANDed through the AND gate:
[0063] Only when all input signals are high, the output .
[0064] 4. Logical or operation: 4.1 The signal output by the AND gate is logically ORed through the OR gate:
[0065] As long as one of the input signals is high, the output =1.
[0066] 5. Signal summing processing: 5.1 The gain summation module sums the three flow signals to generate a comprehensive signal:
[0067] 5.2 The comprehensive signal is judged by the high and low comparator:
[0068] in, It is the high and low comparison result of the comprehensive signal.
[0069] 6. Redundant protection switching: 6.1 Signal comprehensive judgment is processed through limited OR gate:
[0070] 6.2 The switch block is used to switch between different signal sources. When a signal source fails, it automatically switches to the backup protection logic.
[0071] 7. Delay protection mechanism: 7.1 After confirming that the flow signal is abnormal and meets the protection conditions, the delay block starts timing. Seconds output signal:
[0072] 7.2 This delay mechanism ensures the stability of the signal and avoids malfunction caused by instantaneous interference signals.
[0073] 8. Protection action trigger: 8.1 Delay After seconds, the system outputs the generator water cut protection action signal:
[0074] 8.2 After the electrical side receives the protection action signal, it will delay Seconds trigger generator disconnection:
[0075] In summary, through the above logic, the system can reliably monitor the cooling water flow, and when an abnormal situation is detected, it can trigger the protection action in a timely and effective manner through redundant protection logic, dynamic signal processing and delayed protection mechanism to ensure the safe operation of the generator.
[0076] Those skilled in the art should understand that the various embodiments disclosed above can be changed and modified in various ways without departing from the essence of the invention. Therefore, the protection scope of the present invention should be defined by the appended claims.
[0077] It should be noted that not all steps and units in the above processes are necessary, and some steps or units can be ignored according to actual needs. The execution order of each step is not fixed and can be determined as needed. The device structure described in the above embodiments can be a physical structure or a logical structure. Some units may be implemented by the same physical entity, or some units may be implemented by multiple physical entities, or some components in multiple independent devices may be implemented together.
[0078] The specific embodiments set forth above describe exemplary embodiments, but do not represent all embodiments that may be implemented or fall within the scope of protection of the claims. The term "exemplary" used throughout this specification means "used as an example, instance, or illustration" and does not mean "preferred" or "having advantages" over other embodiments. For the purpose of providing an understanding of the described techniques, the specific embodiments include specific details. However, these techniques may be implemented without these specific details. In some instances, in order to avoid obscuring the concepts of the described embodiments, well-known structures and devices are shown in block diagram form.
[0079] The above description of the present disclosure is provided to enable any person of ordinary skill in the art to implement or use the present disclosure. Various modifications to the present disclosure will be apparent to those of ordinary skill in the art, and the general principles defined herein may be applied to other variations without departing from the scope of protection of the present disclosure. Therefore, the present disclosure is not limited to the examples and designs described herein, but is consistent with the widest range of principles and novel features disclosed herein.
Claims
1. A generator water cut protection method and application based on multi-signal redundancy, characterized by: Signal acquisition and comparison, high and low comparator judgment, signal validity judgment, logic and operation, logic or operation, signal summation processing, redundant protection switching, delayed protection mechanism, protection action triggering; Step S1: signal acquisition and comparison; Step S2: high and low comparator judgment; Step S3: Signal validity determination; Step S4: logical AND operation; Step S5: logical OR operation; Step S6: signal summing processing; Step S7: redundant protection switching; Step S8: Delay protection mechanism; Step S9: protection action triggering.
2. According to the method and application of a generator water cut-off protection method based on multi-signal redundancy according to claim 1, it is characterized in that: In step S1 , three stator cooling water flow meters ( D0001 , D0002 , and D0003 ) collect cooling water flow signals.
3. The method and application of generator water cut-off protection based on multi-signal redundancy according to claim 1 is characterized in that: In step S2, the signal of each flow meter is compared with the set value (50t / h) through a high-low comparator (H / L) to determine whether it is lower than the set value.
4. The method and application of generator water cut-off protection based on multi-signal redundancy according to claim 1 is characterized in that: In step S3, the quality judgment modules (TSTO and NOT) detect the validity of the signal.
5. The method and application of generator water cut-off protection based on multi-signal redundancy according to claim 1 is characterized in that: In step S4, the three flow meter signals are logically ANDed through an AND gate (AND), and a high level is output when all signals meet the conditions.
6. The method and application of generator water cut-off protection based on multi-signal redundancy according to claim 1 is characterized in that: In step S5, the signal output by the AND gate is subjected to a logic OR operation through an OR gate, and a high level is output as long as one signal meets the condition.
7. The method and application of generator water cut-off protection based on multi-signal redundancy according to claim 1 is characterized in that: In step S6, the gain summation module (DSUM) sums the three flow meter signals and determines whether the comprehensive signal meets the set conditions through the high-low comparator (H / L).
8. The method and application of generator water cut-off protection based on multi-signal redundancy according to claim 1 is characterized in that: In step S7, the signal comprehensive judgment is processed through the qualified OR gate (QOR), and the switching block (T) is used to switch between different signal sources, and switch to the backup protection logic when the signal fails.
9. The method and application of generator water cut-off protection based on multi-signal redundancy according to claim 1 is characterized in that: In step S8, the delay block (TD-DIG) ensures that the signal meets the protection conditions and is output after a delay of 15 seconds.
10. The method and application of generator water cut-off protection based on multi-signal redundancy according to claim 1, characterized in that: In step S9, after a delay of 15 seconds, the generator water cut protection action signal is output. After the electrical side receives the signal, the generator is de-energized after a delay of another 15 seconds, and the generator can be shut down smoothly.