Soft coal tunneling key layer hydraulic slotting-fracturing pressure relief three-dimensional outburst prevention process
By hydraulically cutting and fracturing the sub-critical strata overlying the coal seam, a continuous weak surface is formed, which solves the problems of difficulty in coal seam gas extraction and high risk of tunneling operations, and achieves efficient coal seam gas drainage and safe operation.
Patent Information
- Application Number
- CN202410893568.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-04
- Publication Date
- 2024-10-22
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
Coal and gas outbursts lead to difficulties in coal seam gas extraction, low extraction efficiency, high risks in excavation operations, and frequent gas overruns, which are difficult to effectively solve with existing technology.
The three-dimensional outburst prevention technology of hydraulic cutting and fracturing for pressure relief in key layers of soft coal excavation is used to perform hydraulic cutting and fracturing on the overlying sub-key layers of the coal seam to form a continuous weak surface, weaken the roof stress transmission, and relieve the pressure of the coal body. , improve the gas permeability of coal seams, and achieve efficient gas drainage through hole sealing and grid-connected pre-drainage.
It significantly improves the coal seam permeability and gas drainage efficiency, reduces the risk of excavation operations, avoids gas over-limit phenomena, and achieves safe coal seam gas drainage.
Smart Images

Figure CN118815436A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of gas outburst prevention, in particular to a three-dimensional outburst prevention process for hydraulic slitting and fracturing pressure relief in a key layer of soft coal excavation. Background Art
[0002] Coal and gas outburst is a complex geological dynamic disaster that occurs during deep underground mining and production. The number of coal and gas outburst disasters in my country accounts for about one-third of the world's total. Although the overall safety situation of coal mines has improved with the improvement of scientific and technological cultural levels and management standards, serious and extremely large accidents in coal mines still occur frequently, especially gas-related fatalities account for a large proportion. Gas disasters pose a major threat to the safety of the coal industry, so solving the problem of coal and gas outburst disasters has become an urgent task that the coal industry must address.
[0003] Coal and gas outbursts are the result of the combined effects of the coal seam's own characteristics, ground stress, and gas. Under the action of complex ground stress, the original coal seam in the mine is gradually destroyed after being squeezed and sheared by the surrounding rock strata. The coal seam structure undergoes a large amount of deformation and rheological migration, and is broken and crumpled under the action of ground stress. The destruction of the original structure of the coal leads to a decrease in mechanical strength, and it becomes unstable, severely damaged, and even pulverized in a short period of time. The mechanical strength of the rock in this coal seam that is deformed due to ground stress is extremely low, and the gas pressure and content are higher. In addition, the cleat fracture system often becomes irregular, disconnected, and compacted and closed due to the strong deformation of the coal seam, resulting in extremely low permeability and low porosity of the coal seam under the original ground stress conditions.
[0004] Based on the above problems, a three-dimensional outburst prevention technology of hydraulic slitting and fracturing pressure relief in key strata of soft coal excavation is proposed. Summary of the invention
[0005] The purpose of the present invention is to provide a three-dimensional anti-blowout process for key layers of soft coal excavation by hydraulic slitting and fracturing to relieve pressure. Starting from the direction of reducing ground stress, the original cracks in the rock mass are connected by slitting and fracturing, and continuous weak surfaces are formed in the hard roof, so as to achieve the purpose of weakening the stress transmission of the roof, relieve the pressure of the coal body, and greatly improve the permeability of the coal seam, fundamentally solving the problems of great difficulty in coal seam gas extraction, low extraction efficiency, high risk of excavation operations, and frequent occurrence of gas exceeding the limit, thereby achieving the purpose of eliminating blowouts.
[0006] To achieve the above object, the present invention provides a three-dimensional outburst prevention process for hydraulic slitting and fracturing pressure relief in a key layer of soft coal excavation, comprising the following steps:
[0007] S1. Drilling construction: According to the distribution of rock formations, determine the positions of the main key layers and sub-key layers, and construct a group of low-position directional long drill holes and high-position directional long drill holes in the excavated tunnel;
[0008] S2, Slotting: hydraulic slotting of sub-critical layers in low-position directional long boreholes;
[0009] S3, fracturing: after the slitting is completed, fracturing is performed in the main key layer and sub-key layer through high-position directional long drilling and low-position directional long drilling respectively;
[0010] S4. Sealing and grid-connected pre-extraction: low-position directional long borehole sealing and connecting to the mine extraction system for grid-connected pre-extraction.
[0011] Preferably, in S1, preliminary data exploration is first carried out to study the gas occurrence and geological structure, determine the rock composition and distribution of the overlying rock layer of the constructed coal seam, obtain the physical properties of the rock samples, determine the key layer positions and the fracture pressure of the rock layer, and the key layer positions include the main key layer and sub-key layer.
[0012] Preferably, in S1, low-position directional long drill holes penetrate the layers inside the tunnel to the sub-key layers and are arranged on both sides of the tunnel, and the final hole vertical height is controlled at the coal seam roof; high-position directional long drill holes penetrate the overlying rock layers of the coal seam to the main key layers and are arranged on both sides of the tunnel.
[0013] Preferably, in S2, hydraulic cutting measures are first carried out on the low-position directional long borehole, multiple cutting points are arranged, and a cutting point is arranged at a certain distance, and hydraulic cutting integrated equipment is used to perform segmented hydraulic cutting on the sub-critical layer to pre-set the seam groove.
[0014] Preferably, in S3, segmented hydraulic fracturing is performed in the high-position directional long borehole and the low-position directional long borehole respectively, and multiple fracturing points are arranged, with one fracturing point arranged at a certain distance. After the arrangement is completed, the sealer is sent to the fracturing point to start water injection and fracturing; the change of pump pressure is monitored at any time during the fracturing process.
[0015] Preferably, in S3, before determining the fracturing position, an electronic borehole peep instrument is used to observe the rock formation, select a complete rock formation, and try to avoid the layer containing larger cracks.
[0016] Preferably, in S4, a "two blocking and one injection" sealing process is adopted to seal the hole, and a bundled PVC pipe with an expansion belt and a grouting pipe is used to seal the hole. After the sealing is completed, the grid is connected to start gas extraction, and the changes in gas content are monitored at any time.
[0017] Therefore, the three-dimensional anti-burst process of hydraulic slitting-fracturing pressure relief in the key layer of soft coal excavation of the present invention, in the process of coal roadway excavation in high ground stress, high gas pressure and low permeability outburst coal seam, firstly, hydraulic slitting is carried out in the sub-key layer overlying the coal seam by using directional long drilling, and the slits are pre-set to provide a crack propagation path for the later fracturing. The hydraulic slitting in the sub-key layer can also guide the expansion of hydraulic fracturing cracks, and conduct the original cracks in the rock body to increase the influence range of hydraulic fracturing cracks; then, hydraulic fracturing is carried out in the main and sub-key layers to form a continuous weak surface in the hard roof, so as to achieve the purpose of weakening the stress transmission of the roof. The coal body is decompressed and the cracks are further expanded until they penetrate the coal seam, eliminating the sealing effect of the roof rock layer on the coal seam gas and reducing the coal seam gas pressure. Finally, after the slitting and fracturing is completed, the low-position directional long borehole is sealed and connected to the mine extraction system for grid-connected pre-extraction, achieving the effect of one hole for multiple uses and reducing the extraction cost. The cracks produced by slitting and fracturing provide a migration channel for the decompressed gas, and the extraction efficiency is greatly improved, fundamentally solving the problems of difficult and low extraction efficiency of coal seam gas, high risk of excavation operations, and frequent gas over-limit, thereby achieving the purpose of eliminating protrusions.
[0018] This process has a simple operation process, low cost and good permeability-enhancing effect. After unloading the overlying rock strata of the coal seam, it can improve the permeability and air permeability of the coal seam and improve the gas extraction efficiency. It can eliminate the concentration of ground stress and gas pressure in the coal seam, making the distribution of ground stress, gas pressure and gas content uniform. It can also delineate safe working areas to fundamentally prevent abnormal gas outbursts and gas dynamic disasters during coal seam excavation.
[0019] The technical solution of the present invention is further described in detail below through the accompanying drawings and embodiments. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] Figure 1 is a process flow chart of an embodiment of the present invention;
[0021] Figure 2 A schematic diagram of the internal structure of a coal seam according to an embodiment of the present invention;
[0022] Reference numerals:
[0023] 1. Ground; 2. Surface rock and soil layer; 3. Main key layer; 4. Intermediate rock layer; 5. Sub-key layer; 6. Coal seam; 7. Low-position directional long drilling hole; 8. High-position directional long drilling hole; 9. Cutting point; 10. Fracturing point; 11. Fracturing equipment. DETAILED DESCRIPTION
[0024] The technical solution of the present invention is further described below through the accompanying drawings and embodiments.
[0025] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments.
[0026] Example
[0027] like Figure 1 As shown, this embodiment specifically includes the following steps:
[0028] S1. Based on the data obtained in the previous exploration, the gas occurrence, geological structure and other conditions are studied to determine the composition and distribution of the rock strata overlying the coal seam to be constructed; the rock stratum breaking distance and breaking angle are calculated, and then the "three-zone" height is obtained. After analyzing the above data, the key layer positions are finally determined, such as Figure 2 As shown, from top to bottom, they are ground 1, surface rock and soil layer 2, main key layer 3, intermediate rock layer 4, sub-key layer 5 and coal seam 6.
[0029] The fracturing boreholes and observation holes are arranged on the side of the roadway, and the key layers overlying the coal seam are hydraulically fractured to finally obtain the fracture initiation pressure of the key layers.
[0030] Then, a group of high-position directional long drill holes 7 and low-position directional long drill holes 8 are arranged on both sides of the tunnel of the excavation working face; among them, the low-position directional long drill holes 7 penetrate the layer from the tunnel to the sub-key layer 5, are arranged on both sides of the tunnel, and the final hole vertical height is controlled at the coal seam roof; the high-position directional long drill holes 8 penetrate the overlying rock layer of the coal seam to the main key layer 3, and are arranged on both sides of the tunnel;
[0031] S2, firstly carry out hydraulic cutting measures for the low-position directional long borehole 7, arrange a cutting point 9 at a certain distance, and use hydraulic cutting integrated equipment to perform segmented hydraulic cutting and pre-set seam grooves on the sub-critical layer 5;
[0032] S3, then carry out segmented hydraulic fracturing measures in the high-position directional long borehole 8 and the low-position directional long borehole 7, arrange a fracturing point 10 at a certain distance, and the fracturing point 10 and the cutting point 9 in the low-position directional long borehole 7 are located at the same position; before determining the fracturing position, use an electronic borehole peep instrument to observe the rock formation, select a complete rock formation, and try to avoid the layer with large cracks; after the borehole arrangement is completed, the pre-assembled sealer is connected to the drill pipe and sent to the fracturing point 10, and the fracturing equipment 11 is used for fracturing, and water injection is started. The manual operation is carried out on site, and the water injection pressure and fracturing time are monitored in real time. This step is carried out on the fracturing point 10 of the main key layer 3 and the sub-key layer 5 in turn;
[0033] S4. After the slitting and fracturing are completed, the low-position directional long borehole 7 is sealed by the "two blocking and one injection" sealing process, and the bundled PVC pipe with expansion belt and grouting pipe is used to seal the hole. After the sealing is completed, the grid is connected to start gas extraction, and the changes in gas content are monitored at any time.
[0034] Therefore, the three-dimensional anti-blowout technology of hydraulic slitting and fracturing pressure relief in the key layer of soft coal excavation of the present invention, starting from the direction of reducing ground stress, conducts the original cracks in the rock mass through slitting and fracturing, forms a continuous weak surface in the hard roof, and achieves the purpose of weakening the stress transmission of the roof, relieves the pressure of the coal body, and greatly improves the permeability of the coal seam, fundamentally solving the problems of great difficulty in coal seam gas extraction, low extraction efficiency, high risk of excavation operations, and frequent occurrence of gas exceeding the limit, thereby achieving the purpose of eliminating blowouts.
[0035] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that they can still modify or replace the technical solution of the present invention with equivalents, and these modifications or equivalent replacements cannot cause the modified technical solution to deviate from the spirit and scope of the technical solution of the present invention.
Claims
1. Hydraulic slitting and fracturing pressure relief three-dimensional outburst prevention technology for key layers of soft coal excavation, characterized in that: The following steps are involved: S1. Drilling construction: According to the distribution of rock formations, determine the positions of the main key layers and sub-key layers, and construct a group of low-position directional long drill holes and high-position directional long drill holes in the excavated tunnel; S2, Slitting: hydraulically slitting the sub-critical layer in the low-position directional long borehole; S3, Fracturing: After the slitting is completed, fracturing is carried out in the main key layer and sub-key layer through high-position directional long drilling and low-position directional long drilling respectively; S4. Sealing and pre-extraction in grid connection: seal the low-position directional long borehole and then connect it to the mine extraction system for pre-extraction in grid connection.
2. The three-dimensional anti-outburst process of hydraulic slitting and fracturing pressure relief in the key layer of soft coal excavation according to claim 1 is characterized by: In S1, preliminary data exploration is first carried out to study gas occurrence and geological structure, determine the composition and distribution of the rock strata overlying the coal seam to be constructed, obtain the physical properties of the rock samples, and determine the key layer positions and the fracture pressure of the rock strata.
3. The three-dimensional anti-outburst process of hydraulic slitting and fracturing pressure relief in the key layer of soft coal excavation according to claim 2 is characterized by: In S1, the low-position directional long drill hole penetrates into the sub-key layer; the high-position directional long drill hole penetrates into the main key layer.
4. The three-dimensional anti-outburst process of hydraulic slitting and fracturing pressure relief in the key layer of soft coal excavation according to claim 1 is characterized by: In S2, hydraulic cutting measures are first carried out on the low-position directional long borehole, multiple cutting points are arranged, and hydraulic cutting integrated equipment is used to perform segmented hydraulic cutting to pre-set seam grooves.
5. The three-dimensional anti-outburst process of hydraulic slitting and fracturing pressure relief in the key layer of soft coal excavation according to claim 1 is characterized by: In S3, staged hydraulic fracturing is performed in the high-position directional long borehole and the low-position directional long borehole respectively, and multiple fracturing points are arranged. After the arrangement is completed, the sealer is sent to the fracturing point to start water injection and fracturing.
6. The three-dimensional anti-outburst process of hydraulic slitting and fracturing pressure relief in the key layer of soft coal excavation according to claim 5 is characterized by: In S3, before determining the fracturing position, an electronic borehole peep instrument is used to observe the rock formation and select a complete rock formation.
7. The three-dimensional outburst prevention process for hydraulic slitting and fracturing pressure relief in the key layer of soft coal excavation according to claim 1 is characterized by: In S4, the "two blocking and one injection" sealing process is adopted to seal the hole. After the sealing is completed, the grid is connected to start gas extraction, and the changes in gas content are monitored at any time.
Citation Information
Patent Citations
Method for weakening high hard roof having distance of 100-350m to coal seam, and apparatus thereof
CN104790951A
Working face coal pillar reserving method
CN112983419A
Impact-prevention pressure-relief tunneling method for rock burst coal seam roadway
CN114856564A
Method for reducing reserved width of mining stopping line coal pillar of working face with extra-large mining height
CN114934773A
Soft coal seam gas treatment process based on key layer segmented hydraulic fracturing and coal seam hydraulic caving and application
CN115288682A
Cited By
Rock burst source three-dimensional collaborative targeted prevention and control method and system
CN121932235A