Underground chamber rock mass crack propagation height measuring equipment

By designing a support box and detection unit in the rock mass of the underground chamber, using a vacuum pump and a rock film to form a sealed cavity, injecting fluorescent agent water to detect cracks, and moving the equipment through wire ropes and motors, the measurement difficulties in the existing technology are solved. problem, improving measurement efficiency and accuracy.

CN118816731AInactive Publication Date: 2024-10-22SHIJIAZHUANG TIEDAO UNIV +2
View PDF 0 Cites 2 Cited by

Patent Information

Application Number
CN202411022782.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-29
Publication Date
2024-10-22
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The existing technology cannot effectively measure the propagation height of rock mass cracks in underground chambers, especially when there is dripping water in the borehole, and it is difficult to distinguish between original cracks in the rock mass and cracks caused by the chamber.

Method used

A device including a support box, a detection unit and a support machine assembly is designed. The detection unit is installed through drilling, a vacuum pump and a rock film are used to form a sealed cavity, fluorescent agent water is injected to detect cracks, and the equipment is installed through a steel wire rope and a motor. Easy to move.

Benefits of technology

It can effectively measure the expansion height of rock mass cracks in the borehole, distinguish water-conducting fracture zones, save manpower, and improve measurement efficiency and accuracy.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118816731A_ABST
    Figure CN118816731A_ABST
Patent Text Reader

Abstract

The invention belongs to the technical field of chamber rock mass crack measurement, and particularly relates to underground chamber rock mass crack propagation height measuring equipment which comprises a supporting box, and foot stool plates are symmetrically and fixedly mounted at the bottom of the supporting box; the two metal circular plates are placed in a drill hole through the steel wire rope, the vacuum pump conducts internal pressure through the conversion valve, the conversion valve pressurizes the two metal circular plates, the air pressure extrudes the rock pasting films on the metal circular plates to expand, the rock pasting films are tightly attached to the wall of the rock body when expanding, and two completely-sealed pressure cavities are formed. A cavity is formed between the two groups of metal circular plates, a liquid storage tank injects water added with a fluorescent agent into the cavity through an air pressing pipe II, a conversion valve performs conversion pressurization, a vacuum pump performs pressurization on the interior of the cavity through the air pressing pipe II, and a transposition type camera penetrating into the chamber is rotated; and determining the height of the water flowing fractured zone through the up-and-down movement of the steel wire rope.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of chamber rock mass crack measurement, in particular to an underground chamber rock mass crack extension height measurement device. Background Art

[0002] After the excavation of underground chambers, cracks will appear in the surrounding rock mass, which are called water-conducting fracture zones in the mining industry. Measuring the height of water-conducting fracture zones is one of the difficult problems in the mining field.

[0003] At present, the measurement of the extension height of rock cracks in underground chambers is mainly carried out by using borehole camera technology, which obtains the influence of whether the rock has cracks by taking pictures inside the borehole, so as to judge the height of the fracture zone. However, this method has obvious defects: it cannot be used when there is water dripping in the borehole, and when the borehole reveals that there are cracks in the rock, it is often impossible to judge whether it is the original crack of the rock or the crack caused by the chamber.

[0004] To this end, the present invention provides a device for measuring the crack extension height of rock mass in an underground chamber. Summary of the invention

[0005] In order to make up for the deficiencies of the prior art, at least one technical problem raised in the background technology is solved.

[0006] The technical solution adopted by the present invention to solve the technical problem is as follows: the underground chamber rock crack extension height measuring device described in the present invention comprises a support box, the support box, the bottom of the support box is symmetrically fixedly installed with a tripod plate, the top of the support box is provided with a detection unit, the detection unit is used to detect the extension height of the chamber rock crack, and plays a role in measuring the crack extension height, the support box is provided with a support machine component inside, the support machine component is used to support the device after the detection unit completes the detection of the chamber rock, and move it to the next chamber rock for detection, so as to facilitate movement;

[0007] The biggest feature of the cracks caused by the chamber is that the crack zones are all connected to the chamber. This feature is used to develop the technical solution; first use a drilling device to drill a hole in the underground chamber rock mass that needs to be measured. After the drilling is completed, the detection unit on the top of the support box is placed in the drill hole, and then the support machine assembly in the support box is slowly lowered. When the tripod plate at the bottom of the support box is completely placed on the ground, the support box is completely placed on the ground, and the detection unit is completely placed in the drill hole. Then the detection unit measures the crack extension height of the underground chamber rock mass. The unique design of the detection unit can solve the above-mentioned problem that it cannot be used when there is dripping water in the borehole and when the borehole reveals that there are cracks in the rock, it is often impossible to determine whether it is an original crack in the rock mass or a crack caused by the chamber.

[0008] Preferably, the detection unit includes a pressure component and a detection component. The pressure component is used to form a cavity in the borehole to facilitate the detection component to detect the chamber rock mass and play a role in cooperating with the detection. The detection component is used to detect the chamber rock mass and plays a role in measurement. When the detection unit is placed in the borehole, the pressure component forms a cavity in the borehole, and then the detection component detects the chamber rock mass. When cracks are found in the chamber rock mass, the detection component measures the height of the crack extension. The two work in coordination with each other to measure the height of the crack extension.

[0009] Preferably, the pressure component includes metal circular plates, and there are two groups of metal circular plates, each of which has a group of columns fixedly installed inside, and metal tubes are symmetrically fixedly installed between the two groups of metal circular plates, and a compressed air pipe 1 is fixedly installed on the top of one group of metal circular plates, and the compressed air pipe 1 penetrates the inner wall of the support box, and a vacuum pump and a conversion valve are fixedly installed on the top of the support box, and a flow pipe is fixedly installed between the vacuum pump and the conversion valve, and one end of the compressed air pipe 1 is fixedly connected to the outer wall of the conversion valve, and rock-adhering membranes are fixedly installed on the outer walls of the two groups of metal circular plates. During measurement, the two groups of metal circular plates are placed in the borehole, and then the vacuum pump is controlled to pressurize the conversion valve through the flow pipe, and the conversion valve pressurizes the introduced pressure through the compressed air pipe 1 and enters one of the groups of metal circular plates. When the air pressure enters one of the groups of metal circular plates, the air pressure squeezes the rock-adhering membrane on the metal circular plate to expand, and the rock-adhering membrane is tightly pressed when it expands. The two sets of metal circular plates are pressed against the rock wall, and the air pressure flows into the other set of metal circular plates along the metal tube while pressurizing. Similarly, the rock-sticking membranes on the other set of metal circular plates are tightly pressed against the rock wall under the action of air pressure. When the two sets of metal circular plates are pressurized to a certain extent, the rock-sticking membranes on the two sets of metal circular plates are completely matched with the rock wall to form two completely sealed pressure chambers, and a cavity is formed between the two sets of metal circular plates. The rock-sticking membranes on the two sets of metal circular plates are completely matched with the rock wall to form two completely sealed pressure chambers. A cavity is formed between the two sets of metal circular plates, which is convenient for subsequent detection components to detect the rock wall and play a role in coordinated operations. A set of columns are arranged on the inner walls of the two sets of metal circular plates, and metal tubes are symmetrically installed between the two sets of metal circular plates. The columns and the metal tubes can limit and prop the two sets of metal circular plates apart to prevent the metal circular plates from tilting during pressurization and being out of level with the borehole, thereby enhancing the stability of the metal circular plates during pressurization.

[0010] Preferably, the detection component includes a liquid storage tank, which is fixedly installed on the top of the support box, and the outer wall of the conversion valve is fixedly installed with a compressed air pipe 2, and a liquid flow pipe is fixedly installed between the liquid storage tank and the compressed air pipe 2, one end of the compressed air pipe 2 passes through one group of metal circular plates, and one end of the compressed air pipe 2 is fixedly installed with a tube sticking film, and the tube sticking film is in contact with the inner wall of one group of metal circular plates, and metal rods are fixedly installed on the inner walls of the two groups of metal circular plates, and a transfer camera is fixedly installed on one end of the metal rod. When pressurized, under the action of pressure, one of the The tube film in the group of metal circular plates will be tightened on one end of the second compressed air pipe. When the two groups of metal circular plates are pressurized, the liquid storage tank will pass water with fluorescent agent into the second compressed air pipe through the liquid flow pipe. The water in the second compressed air pipe will finally be injected into the cavity formed between the two groups of metal circular plates. Then the liquid storage tank will stop injecting water, and the conversion valve will switch the pressurization. The vacuum pump will pressurize the cavity through the second compressed air pipe. When there are cracks in the rock mass, the water in the cavity will be continuously pressurized and will flow into the cracks in the rock mass, thereby determining that there are cracks in the rock mass here, which plays a role in detecting cracks.

[0011] Preferably, a metal rod is fixedly installed on the inner walls of the two groups of metal circular plates, a rope winding drum is fixedly installed on the top of the support box, a steel wire rope is wound on the rope winding drum, a pulley is fixedly installed on the top of the support box, the outer wall of the steel wire rope is slidably connected to the outer wall of the pulley, one end of the steel wire rope is fixedly connected to the top of the metal rod, a rotating cylinder is fixedly installed on the outer wall of the rope winding drum, the metal rod is arranged in the middle of the inner walls of the two groups of metal circular plates, when the two groups of metal circular plates are placed in the drilled hole, the rope winding drum is driven to rotate by the rotating cylinder, and when the rope winding drum rotates, the steel wire rope wound on the rope winding drum is loosened, and the steel wire rope and the metal The rod is fixedly connected. When the wire rope is loosened, the wire rope drives the two groups of metal circular plates to move downward in the borehole through the metal rod. When it moves to a certain position, the rotating cylinder stops rotating, and then the vacuum pump applies pressure between the two groups of metal circular plates. During pressurization, the pressure squeezes the rod-adhering membrane hoop tightly against the metal rod to prevent pressure leakage due to gaps during operation, which affects the operation effect. When the detection of a rock mass in the borehole is completed, the rotating cylinder drives the wire rope to wind and rewind, and drives the two groups of metal circular plates to move up and down through the wire rope, thereby testing whether there are water-conducting fracture zones at different heights in the borehole, and realizing the measurement of the height of the water-conducting fracture zone.

[0012] Preferably, the outer wall of the metal rod is symmetrically fixed with a rod-sticking film, and the two rod-sticking films are respectively fitted with the inner walls of the two groups of metal circular plates. During detection, the indexable camera is rotated deep into the chamber. If fluorescent liquid is found dripping into the chamber, it is determined that there is a water-conducting fissure, and then the height of the water-conducting fissure zone is determined by moving the wire rope up and down. It should be noted here that the indexable camera can be equipped with an ultraviolet lamp to cooperate with the operation, and the wires of the indexable camera and other wires are laid along the middle metal rod to the outside of the drill hole, and the metal rod is a hollow rod.

[0013] Preferably, a storage box is provided on the top of the support box. When working, the storage box can store some tools or spare parts required for detection. The setting of the storage box serves to facilitate the storage of tools or parts.

[0014] Preferably, a straightening ring is provided at the bottom of the support box. When the wire rope is released, the straightening ring is completely placed on the top of the drill hole, which can provide a certain limiting stability for the wire rope when it is released and play a reinforcement role.

[0015] Preferably, the support machine assembly has a motor, the output end of the motor is fixedly installed with a screw, the outer wall of the screw is threadedly connected with a torque rod, both ends of the torque rod are symmetrically installed with push rod blocks, the inner wall of the support box is symmetrically fixedly installed with limit baffles, the inner walls of the two limit baffles are hinged with support rods, and the outer walls of the two push rod blocks are respectively slidably connected to the tops of the two support rods. When the measurement is completed, the motor drives the screw to rotate, and the rotation of the screw drives the torque rod to move. When the torque rod moves, it drives the two push rod blocks to move. When moving, the two push rod blocks squeeze the two support rods and hinge and rotate to open in the limit baffle, and the support box will rise from the ground. When the two support rods are fully opened in the limit baffle, the four support rods completely support the support box, and the detection unit will rise from the drill hole. Subsequently, the device can be moved by pushing the support rod, which facilitates movement and saves manpower. The opposite is true when detecting and storing.

[0016] Preferably, a connecting plate is fixedly installed between the two struts, and a return spring is fixedly installed on the top of the connecting plate, and one end of the return spring is fixedly connected to the inner wall of the support box. When the push rod block squeezes the strut to be hinged open in the limit baffle, the two struts pull the return spring on the connecting plate between them to rotate. The return spring is set to provide a certain buffering force when the strut is rotated open, so that the strut is smoother when opening or storing, thereby playing a role in smoothing the movement of the strut.

[0017] The beneficial effects of the present invention are as follows:

[0018] 1. The present invention relates to an underground chamber rock crack extension height measuring device, which places two sets of metal circular plates in a borehole through a steel wire rope, and a vacuum pump passes pressure through a conversion valve. The conversion valve pressurizes the two sets of metal circular plates, and the air pressure squeezes the rock-adhering membranes on the metal circular plates to expand. When the rock-adhering membranes expand, they tightly adhere to the rock wall to form two completely sealed pressure chambers, and a cavity is formed between the two sets of metal circular plates. Subsequently, a liquid storage tank injects water with a fluorescent agent into the cavity through two pairs of compressed air pipes, and the conversion valve converts the pressure. The vacuum pump pressurizes the cavity through two pairs of compressed air pipes, and a rotating camera is used to penetrate into the chamber. If fluorescent liquid is found dripping into the chamber, it is determined that there is a water-conducting fracture, and the height of the water-conducting fracture zone is determined by the up and down movement of the steel wire rope.

[0019] 2. The underground chamber rock crack propagation height measuring device described in the present invention drives two push rod blocks to move by a motor. When moving, the two push rod blocks squeeze the two support rods to hinge and rotate open in the limit baffle, and the support box will rise from the ground. When the two support rods are fully opened in the limit baffle, the four support rods completely support the support box, and the detection unit will rise from the drill hole. Then, the device can be moved by pushing the support rods, which facilitates movement and saves manpower. When the push rod blocks squeeze the support rods to hinge open in the limit baffle, the two support rods pull the reset spring on the connecting plate between the two to rotate. The reset spring is set to provide a certain buffering force when the support rods rotate and open, so that the support rods are smoother when opening or storing. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] The present invention will be further described below in conjunction with the accompanying drawings.

[0021] Figure 1 It is the main figure of the present invention;

[0022] Figure 2 It is an overall diagram of the present invention;

[0023] Figure 3 It is a schematic diagram of the structure of the second part of the medium-pressure air pipe of the present invention;

[0024] Figure 4 It is a structural schematic diagram of the metal pipe in the present invention;

[0025] Figure 5 It is a structural schematic diagram of the screw in the present invention;

[0026] Figure 6 It is a structural schematic diagram of the reset spring in the present invention.

[0027] In the figure: 1. support box; 2. storage box; 3. rope drum; 4. rotary cylinder; 5. vacuum pump; 6. conversion valve; 7. flow pipe; 8. liquid storage tank; 9. correction ring; 10. tripod plate; 11. pulley; 12. compressed air pipe 1; 13. compressed air pipe 2; 14. liquid flow pipe; 15. wire rope; 16. rock film; 17. metal round plate; 18. metal rod; 19. rod film; 20. column; 21. metal pipe; 22. transfer camera; 23. support rod; 24. motor; 25. screw; 26. torque rod; 27. push rod block; 28. limit baffle; 29. ​​connecting plate; 30. reset spring; 31. tube film. DETAILED DESCRIPTION

[0028] In order to make the technical means, creative features, objectives and effects achieved by the present invention easy to understand, the present invention is further explained below in conjunction with specific implementation methods.

[0029] like Figures 1 to 6 As shown, an underground chamber rock crack extension height measuring device according to an embodiment of the present invention comprises a support box 1, the support box 1, a tripod plate 10 is symmetrically fixedly installed at the bottom of the support box 1, a detection unit is arranged on the top of the support box 1, the detection unit is used to detect the extension height of the chamber rock crack, and plays a role in measuring the crack extension height, and a support machine assembly is arranged inside the support box 1, and the support machine assembly is used to support the device after the detection unit completes the detection of the chamber rock, and move it to the next chamber rock for detection, so as to facilitate movement;

[0030] At present, the measurement of the extension height of rock cracks in underground chambers is mainly carried out by using borehole photography technology. The camera in the borehole is used to obtain the influence of whether the rock has cracks, so as to judge the height of the fracture zone. However, this method has obvious defects: it cannot be used when there is water dripping in the borehole, and when the drilling hole reveals that there are cracks in the rock, it is often impossible to judge whether it is the original crack of the rock or the crack caused by the chamber;

[0031] The biggest feature of the cracks caused by the chamber is that the crack zones are all connected to the chamber. This feature is used to develop the technical solution; first use a drilling device to drill a hole in the underground chamber rock mass that needs to be measured. After the drilling is completed, the detection unit on the top of the support box 1 is placed into the borehole, and then the support machine assembly in the support box 1 is slowly lowered. When the tripod plate 10 at the bottom of the support box 1 is completely placed on the ground, the support box 1 is completely placed on the ground, and the detection unit is completely placed in the borehole. Then the detection unit measures the crack extension height of the underground chamber rock mass. The unique design of the detection unit can solve the above-mentioned problem that it cannot be used when there is dripping water in the borehole and when the borehole reveals that there are cracks in the rock, it is often impossible to determine whether it is an original crack in the rock mass or a crack caused by the chamber.

[0032] like Figures 1 to 4 As shown, the detection unit includes a pressure component and a detection component. The pressure component is used to form a cavity in the borehole, which is convenient for the detection component to detect the rock mass in the chamber and plays a role in cooperating with the detection. The detection component is used to detect the rock mass in the chamber and plays a role in measurement.

[0033] When the detection unit is placed in the borehole, the pressure component forms a cavity in the borehole, and then the detection component detects the rock mass in the chamber. When cracks are found in the rock mass in the chamber, the detection component measures the height of the crack extension. The two work together to measure the height of the crack extension.

[0034] like Figure 3 to Figure 4 As shown, the pressure assembly includes metal circular plates 17, and there are two groups of metal circular plates 17. A group of columns 20 are fixedly installed inside the two groups of metal circular plates 17. Metal pipes 21 are symmetrically fixedly installed between the two groups of metal circular plates 17. A compressed air pipe 12 is fixedly installed on the top of one group of metal circular plates 17. The compressed air pipe 12 penetrates the inner wall of the support box 1. A vacuum pump 5 and a conversion valve 6 are fixedly installed on the top of the support box 1. A flow pipe 7 is fixedly installed between the vacuum pump 5 and the conversion valve 6. One end of the compressed air pipe 12 is fixedly connected to the outer wall of the conversion valve 6. The outer walls of the two groups of metal circular plates 17 are fixedly installed with rock-attaching films 16.

[0035] During measurement, two groups of metal circular plates 17 are placed in the borehole, and then the vacuum pump 5 is controlled to pass pressure through the flow pipe 7 to the conversion valve 6. The conversion valve 6 pressurizes the introduced pressure through the pressure pipe 12 and enters one group of metal circular plates 17. When the air pressure enters one group of metal circular plates 17, the air pressure squeezes the rock-adhering membrane 16 on the metal circular plate 17 to expand. When the rock-adhering membrane 16 expands, it tightly fits the rock wall. While pressurizing, the air pressure flows into the other group of metal circular plates 17 along the metal pipe 21. Similarly, the rock-adhering membrane 16 on the other group of metal circular plates 17 tightly fits the rock wall under the action of the air pressure. When the two groups of metal circular plates 17 are pressurized to a certain degree, the rock-adhering membrane 16 on the two groups of metal circular plates 17 and The rock wall is completely matched to form two completely sealed pressure chambers, and a cavity is formed between the two groups of metal circular plates 17. The rock-sticking membranes 16 on the two groups of metal circular plates 17 are completely matched with the rock wall to form two completely sealed pressure chambers. A cavity is formed between the two groups of metal circular plates 17, which is convenient for subsequent detection components to detect the rock wall and play a role in coordinated operations. A group of columns 20 are provided on the inner walls of the two groups of metal circular plates 17, and metal tubes 21 are symmetrically installed between the two groups of metal circular plates 17. The columns 20 and the metal tubes 21 can limit the two groups of metal circular plates 17 and prop them apart to prevent the metal circular plates 17 from tilting when pressurized and not being in a horizontal state with the drill hole, thereby enhancing the stability of the metal circular plates 17 when pressurized.

[0036] like Figure 3 to Figure 4 As shown, the detection assembly includes a liquid storage tank 8, which is fixedly installed on the top of the support box 1, a compressed air pipe 13 is fixedly installed on the outer wall of the conversion valve 6, a liquid flow pipe 14 is fixedly installed between the liquid storage tank 8 and the compressed air pipe 13, one end of the compressed air pipe 13 passes through one group of metal circular plates 17, one end of the compressed air pipe 13 is fixedly installed with a tube sticking film 31, the tube sticking film 31 is attached to the inner wall of one group of metal circular plates 17, the inner walls of the two groups of metal circular plates 17 are fixedly installed with metal rods 18, and one end of the metal rods 18 is fixedly installed with a transfer camera 22;

[0037] During pressurization, under the action of pressure, the tube film 31 in one set of metal discs 17 will be clamped tightly to one end of the second compressed air pipe 13. When the two sets of metal discs 17 are pressurized, the liquid storage tank 8 passes water with fluorescent agent into the second compressed air pipe 13 through the liquid flow pipe 14. The water in the second compressed air pipe 13 is finally injected into the cavity formed between the two sets of metal discs 17. Then the liquid storage tank 8 stops injecting water, the switching valve 6 switches to pressurization, and the vacuum pump 5 pressurizes the cavity through the second compressed air pipe 13. When there are cracks in the rock mass, , the water in the cavity is constantly pressurized, and the water in the cavity will flow into the cracks in the rock. At this time, the rotary camera 22 that rotates deep into the chamber, if fluorescent liquid drips in the chamber, it is determined that there are water-conducting fissures, thereby determining that there are cracks in the rock mass here, which plays a role in detecting cracks. It should be noted here that the rotary camera 22 can be equipped with an ultraviolet lamp to cooperate with the operation, and the rotary camera 22 and other wires are laid along the middle metal rod 18 to the outside of the drill hole, and the metal rod 18 is a hollow rod.

[0038] like Figure 3 to Figure 4 As shown, metal rods 18 are fixedly installed on the inner walls of the two groups of metal circular plates 17, a rope drum 3 is fixedly installed on the top of the support box 1, a steel wire rope 15 is wound on the rope drum 3, a pulley 11 is fixedly installed on the top of the support box 1, the outer wall of the steel wire rope 15 is slidably connected to the outer wall of the pulley 11, one end of the steel wire rope 15 is fixedly connected to the top of the metal rod 18, a rotating cylinder 4 is fixedly installed on the outer wall of the rope drum 3, and the metal rod 18 is arranged in the middle of the inner walls of the two groups of metal circular plates 17;

[0039] When the two groups of metal circular plates 17 are placed in the borehole, the rope drum 3 is driven to rotate by the rotating cylinder 4. When the rope drum 3 rotates, the wire rope 15 wound on the rope drum 3 is loosened. Due to the fixed connection between the wire rope 15 and the metal rod 18, when the wire rope 15 is loosened, the wire rope 15 drives the two groups of metal circular plates 17 to move downward in the borehole through the metal rod 18. When they move to a certain position, the rotation of the rotating cylinder 4 is stopped, and then the vacuum pump 5 pressurizes the space between the two groups of metal circular plates 17. When the rock mass detection in the borehole is completed, the rotating cylinder 4 drives the wire rope 15 to wind and rewind, and drives the two groups of metal circular plates 17 to move up and down through the wire rope 15, so as to test whether there are water-conducting fracture zones at different heights in the borehole, and realize the measurement of the height of the water-conducting fracture zone. It should be noted here that the detection sequence is to test step by step from top to bottom, so as to determine the height of the water-conducting fracture zone.

[0040] like Figure 3 to Figure 4 As shown, the outer wall of the metal rod 18 is symmetrically fixed with a rod-sticking film 19, and the two rod-sticking films 19 are respectively attached to the inner walls of the two sets of metal circular plates 17;

[0041] When pressurized, the pressure squeezes the rod-sticking film 19 to tightly fit the metal rod 18, thereby preventing pressure leakage due to gaps during operation, which affects the operation effect.

[0042] like Figure 1 to Figure 2 As shown, a storage box 2 is provided on the top of the support box 1;

[0043] During operation, the storage box 2 can store some tools or spare parts required for detection. The setting of the storage box 2 plays a role in facilitating the storage of tools or parts.

[0044] like Figure 1 to Figure 2 As shown, a correction ring 9 is provided at the bottom of the support box 1;

[0045] When the steel wire rope 15 is released, the position-correcting ring 9 is completely placed on the top of the drill hole, which can provide a certain position-limiting stability for the steel wire rope 15 during the release and play a role of reinforcement.

[0046] like Figures 5 and 6 As shown, the support machine assembly motor 24, the output end of the motor 24 is fixedly installed with a screw rod 25, the outer wall of the screw rod 25 is threadedly connected with a moment rod 26, and push rod blocks 27 are symmetrically installed at both ends of the moment rod 26. The inner wall of the support box 1 is symmetrically fixedly installed with a limit baffle 28, and the inner walls of the two limit baffles 28 are hinged with a support rod 23. The outer walls of the two push rod blocks 27 are respectively slidably connected to the tops of the two support rods 23;

[0047] When the measurement is completed, the motor 24 drives the screw rod 25 to rotate, and the rotation of the screw rod 25 drives the torque rod 26 to move. When the torque rod 26 moves, it drives the two push rod blocks 27 to move. When the two push rod blocks 27 move, they squeeze the two support rods 23 and hinge and rotate open in the limit baffle 28, and the support box 1 will rise from the ground. When the two support rods 23 are fully opened in the limit baffle 28, the four support rods 23 completely support the support box 1, and the detection unit will rise from the drill hole. Then, by pushing the support rod 23, the device can be moved, which is convenient for movement and can save manpower. When detecting and storing, on the contrary, it should be noted that the convex rod end of the push rod block 27 should be lower than the hinged end of the support rod 23.

[0048] like Figures 5 and 6 As shown, a connecting plate 29 is fixedly installed between the two support rods 23, a return spring 30 is fixedly installed on the top of the connecting plate 29, and one end of the return spring 30 is fixedly connected to the inner wall of the support box 1;

[0049] When the push rod block 27 squeezes the strut 23 to hinge open in the limit baffle 28, the two struts 23 pull the return spring 30 on the connecting plate 29 therebetween to rotate. The return spring 30 is set to provide a certain buffer force for the strut 23 when it rotates open, so that the strut 23 is smoother when opening or storing, thereby playing the role of smoothing the movement of the strut 23.

[0050] Working principle: The biggest feature of the cracks caused by the chamber is that the crack zones are all connected to the chamber. This technical solution is developed using this feature. First, use a drilling device to drill a hole in the underground chamber rock mass that needs to be measured. After the drilling is completed, put the detection unit on the top of the support box 1 into the borehole, and then slowly lower the support machine assembly in the support box 1. When the tripod plate 10 at the bottom of the support box 1 is completely placed on the ground, the support box 1 is completely placed on the ground, and the detection unit is completely placed in the borehole. Then the detection unit measures the crack extension height of the underground chamber rock mass. The unique design of the detection unit can solve the above-mentioned problem that it cannot be used when there is water dripping in the borehole, and when the borehole reveals that there are cracks in the rock, it is often impossible to determine whether it is a native crack in the rock mass or a crack caused by the chamber.

[0051] When the detection unit is placed in the borehole, the pressure component forms a cavity in the borehole, and then the detection component detects the rock mass in the chamber. When cracks are found in the rock mass in the chamber, the detection component measures the height of the crack extension. The two work together to measure the height of the crack extension.

[0052] During measurement, two groups of metal circular plates 17 are placed in the borehole, and then the vacuum pump 5 is controlled to pass pressure through the flow pipe 7 to the conversion valve 6. The conversion valve 6 pressurizes the introduced pressure through the pressure pipe 12 and enters one group of metal circular plates 17. When the air pressure enters one group of metal circular plates 17, the air pressure squeezes the rock-adhering membrane 16 on the metal circular plate 17 to expand. When the rock-adhering membrane 16 expands, it tightly fits the rock wall. While pressurizing, the air pressure flows into the other group of metal circular plates 17 along the metal pipe 21. Similarly, the rock-adhering membrane 16 on the other group of metal circular plates 17 tightly fits the rock wall under the action of the air pressure. When the two groups of metal circular plates 17 are pressurized to a certain degree, the rock-adhering membrane 16 on the two groups of metal circular plates 17 and The rock mass wall is completely matched to form two completely sealed pressure chambers, and a cavity is formed between the two sets of metal circular plates 17. The rock-attaching films 16 on the two sets of metal circular plates 17 are completely matched with the rock mass wall to form two completely sealed pressure chambers. A cavity is formed between the two sets of metal circular plates 17, which is convenient for subsequent detection components to detect the rock mass wall and play a role in coordinated operations. A set of columns 20 are arranged on the inner walls of the two sets of metal circular plates 17, and metal tubes 21 are symmetrically installed between the two sets of metal circular plates 17. The columns 20 and the metal tubes 21 can limit the two sets of metal circular plates 17 and open them to prevent the metal circular plates 17 from tilting when pressurized and not being in a horizontal state with the drill hole, thereby enhancing the stability of the metal circular plates 17 when pressurized;

[0053] During pressurization, under the action of pressure, the tube film 31 in one group of metal circular plates 17 will be clamped on one end of the second compressed air pipe 13. When the two groups of metal circular plates 17 are pressurized, the liquid storage tank 8 will pass water with fluorescent agent into the second compressed air pipe 13 through the liquid flow pipe 14. The water in the second compressed air pipe 13 will finally be injected into the cavity formed between the two groups of metal circular plates 17. Then the liquid storage tank 8 stops injecting water, and the switching valve 6 switches the pressurization. The vacuum pump 5 will pressurize the cavity through the second compressed air pipe 13. When there are cracks in the rock mass, the water in the cavity is continuously pressurized, and the water in the cavity will flow into the cracks in the rock mass. At this time, the rotating camera 22 deep into the chamber will determine the presence of water-conducting fissures if fluorescent liquid drips in the chamber, thereby determining that there are cracks in the rock mass here, which plays a role in detecting cracks.

[0054] When the two groups of metal circular plates 17 are placed in the borehole, the rope drum 3 is driven to rotate by the rotating cylinder 4. When the rope drum 3 rotates, the steel wire rope 15 wound on the rope drum 3 is loosened. Due to the fixed connection between the steel wire rope 15 and the metal rod 18, when the steel wire rope 15 is loosened, the steel wire rope 15 drives the two groups of metal circular plates 17 to move downward in the borehole through the metal rod 18. When they move to a certain position, the rotation of the rotating cylinder 4 is stopped, and then the vacuum pump 5 pressurizes the space between the two groups of metal circular plates 17. When the detection of a rock mass in the borehole is completed, the rotating cylinder 4 drives the steel wire rope 15 to be wound and rewound, and the two groups of metal circular plates 17 are driven up and down by the steel wire rope 15, so as to test whether there are water-conducting fracture zones at different heights in the borehole, and realize the measurement of the height of the water-conducting fracture zones;

[0055] When pressurized, the pressure squeezes the rod-sticking film 19 to tightly fit the metal rod 18, preventing pressure leakage due to gaps during operation, which affects the operation effect;

[0056] During operation, the storage box 2 can store some tools or spare parts required for testing. The setting of the storage box 2 serves to facilitate the storage of tools or parts.

[0057] When the wire rope 15 is released, the position correction ring 9 is completely placed on the top of the drill hole, which can provide a certain limit stability for the wire rope 15 when it is released, and play a role of reinforcement;

[0058] When the measurement is completed, the motor 24 drives the screw rod 25 to rotate, and the screw rod 25 drives the moment rod 26 to move while rotating. When the moment rod 26 moves, it drives the two push rod blocks 27 to move. When the two push rod blocks 27 move, they squeeze the two support rods 23 to hinge and rotate in the limit baffle 28 to open, and the support box 1 will rise from the ground. When the two support rods 23 are fully opened in the limit baffle 28, the four support rods 23 completely support the support box 1, and the detection unit will rise from the drill hole. Then, by pushing the support rods 23, the device can be moved, which is convenient for movement and can save manpower. When detecting and storing, the opposite is true;

[0059] When the push rod block 27 squeezes the strut 23 to hinge open in the limit baffle 28, the two struts 23 pull the return spring 30 on the connecting plate 29 therebetween to rotate. The return spring 30 is set to provide a certain buffer force for the strut 23 when it rotates open, so that the strut 23 is smoother when opening or storing, thereby playing the role of smoothing the movement of the strut 23.

[0060] The above shows and describes the basic principles, main features and advantages of the present invention. It should be understood by those skilled in the art that the present invention is not limited to the above embodiments. The above embodiments and descriptions are only for explaining the principles of the present invention. Without departing from the spirit and scope of the present invention, the present invention may have various changes and improvements, which fall within the scope of the present invention. The scope of protection of the present invention is defined by the attached claims and their equivalents.

Claims

1. An underground chamber rock crack extension height measuring device, characterized in that: The invention comprises a support box (1), wherein a tripod plate (10) is symmetrically fixedly mounted on the bottom of the support box (1), and a detection unit is arranged on the top of the support box (1). The detection unit is used to detect the expansion height of cracks in the rock mass of the chamber, thereby playing a role in measuring the expansion height of the cracks. A support machine assembly is arranged inside the support box (1). The support machine assembly is used to support the device after the detection unit completes the detection of the rock mass in the chamber, and move it to the next rock mass in the chamber for detection, thereby playing a role in facilitating movement.

2. The underground chamber rock crack extension height measuring device according to claim 1, characterized in that: The detection unit includes a pressure component and a detection component. The pressure component is used to form a cavity in the borehole to facilitate the detection component to detect the rock mass in the chamber and play a role in cooperating with the detection. The detection component is used to detect the rock mass in the chamber and plays a role in measurement.

3. The underground chamber rock crack extension height measuring device according to claim 1, characterized in that: The pressure assembly comprises a metal circular plate (17), wherein the metal circular plates (17) are in two groups, a group of columns (20) are fixedly installed inside the two groups of the metal circular plates (17), a metal tube (21) is symmetrically fixedly installed between the two groups of the metal circular plates (17), a compressed air pipe (12) is fixedly installed on the top of one group of the metal circular plates (17), the compressed air pipe (12) passes through the inner wall of the support box (1), a vacuum pump (5) and a conversion valve (6) are fixedly installed on the top of the support box (1), a flow pipe (7) is fixedly installed between the vacuum pump (5) and the conversion valve (6), one end of the compressed air pipe (12) is fixedly connected to the outer wall of the conversion valve (6), and a rock-attaching film (16) is fixedly installed on the outer wall of the two groups of the metal circular plates (17).

4. The underground chamber rock crack extension height measuring device according to claim 3, characterized in that: The detection component comprises a liquid storage tank (8), the liquid storage tank (8) is fixedly installed on the top of the support box (1), a compressed air pipe (13) is fixedly installed on the outer wall of the conversion valve (6), a liquid flow pipe (14) is fixedly installed between the liquid storage tank (8) and the compressed air pipe (13), one end of the compressed air pipe (13) passes through one group of metal circular plates (17), one end of the compressed air pipe (13) is fixedly installed with a tube film (31), the tube film (31) is in contact with the inner wall of one group of metal circular plates (17), the inner walls of the two groups of metal circular plates (17) are fixedly installed with metal rods (18), and one end of the metal rod (18) is fixedly installed with a transfer camera (22).

5. The underground chamber rock crack extension height measuring device according to claim 4, characterized in that: A rope drum (3) is fixedly mounted on the top of the support box (1), a steel wire rope (15) is wound around the rope drum (3), a pulley (11) is fixedly mounted on the top of the support box (1), the outer wall of the steel wire rope (15) is slidably connected to the outer wall of the pulley (11), one end of the steel wire rope (15) is fixedly connected to the top of a metal rod (18), a rotating cylinder (4) is fixedly mounted on the outer wall of the rope drum (3), and the metal rod (18) is arranged in the middle of the inner walls of two groups of metal circular plates (17).

6. The underground chamber rock crack extension height measuring device according to claim 5, characterized in that: The outer wall of the metal rod (18) is symmetrically fixedly mounted with a rod-sticking film (19), and the two rod-sticking films (19) are respectively attached to the inner walls of the two groups of metal circular plates (17).

7. The underground chamber rock crack extension height measuring device according to claim 3, characterized in that: A storage box (2) is provided on the top of the support box (1).

8. The underground chamber rock crack extension height measuring device according to claim 3, characterized in that: A positioning ring cylinder (9) is arranged at the bottom of the support box (1).

9. The underground chamber rock crack extension height measuring device according to claim 1, characterized in that: A support machine assembly motor (24), the output end of the motor (24) is fixedly mounted with a screw rod (25), the outer wall of the screw rod (25) is threadedly connected with a torque rod (26), push rod blocks (27) are symmetrically mounted at both ends of the torque rod (26), the inner wall of the support box (1) is symmetrically fixedly mounted with limit baffles (28), the inner walls of the two limit baffles (28) are hinged with support rods (23), and the outer walls of the two push rod blocks (27) are respectively slidably connected to the tops of the two support rods (23).

10. The underground chamber rock crack extension height measuring device according to claim 9, characterized in that: A connecting plate (29) is fixedly installed between the two support rods (23), a return spring (30) is fixedly installed on the top of the connecting plate (29), and one end of the return spring (30) is fixedly connected to the inner wall of the support box (1).

Citation Information

Cited By

  • Underground chamber rock mass crack propagation height measuring equipment

    CN120759637A

  • A device for measuring the height of rock mass crack propagation in an underground chamber

    CN120759637B