Construction method for shield tunnel to underpass existing subway tunnel in micro-distance mode
Through environmental investigation, test section setting and real-time monitoring system, the problem of excavation parameter adjustment when the shield tunnel passes through the existing subway tunnel has been solved, real-time monitoring and control of the ground and tunnels of the shield tunnel have been achieved, and construction risks have been reduced. and cost, improving construction efficiency and quality.
Patent Information
- Application Number
- CN202411048259.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-01
- Publication Date
- 2024-10-25
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
When a shield tunnel passes through an existing subway tunnel, it is difficult to grasp the disturbance to the stratum in a timely manner. As a result, parameters cannot be adjusted in a timely manner during the construction process, and serious problems such as disturbance expansion, settlement monitoring alarms, and over-limits are prone to occur.
Through pre-construction environmental surveys and finite element safety assessments, test sections are set up to determine the excavation mode and parameters, and soil disturbance and tunnel deformation are monitored in real time. In combination with grouting reinforcement and automated monitoring systems, excavation parameters are adjusted, and slag output and grouting are controlled. , to achieve micro-distance penetration construction of shield tunnels.
Effectively monitor and control the disturbance and settlement of the stratum and tunnel caused by shield tunneling, reduce construction risks, ensure construction safety, improve construction efficiency and quality, and reduce project volume and construction period.
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of shield tunnel construction, and in particular to a construction method for a shield tunnel to pass under an existing subway tunnel at a micro-distance. Background Art
[0002] With the continuous development of cities, shield tunneling is increasingly used to pass through important structures, and settlement requirements are becoming increasingly stringent. It is crucial to timely grasp the disturbance of the ground during shield tunneling. When passing through important structures such as existing lines and subway tunnels, if the disturbance of the ground caused by tunneling cannot be grasped in time, it will be impossible to timely feedback the information to the technical staff to guide the adjustment of shield tunneling parameters during the construction process, which will easily lead to serious problems such as disturbance expansion, settlement monitoring alarm, and over-limit. Summary of the invention
[0003] In order to solve the above technical problems, the present invention provides a method for constructing a shield tunnel under an existing subway tunnel at a micro-distance. The method can monitor the disturbance of the soil in real time and comprehensively, and promptly feedback the information to technical personnel to guide the adjustment of shield tunneling parameters, avoid the expansion of disturbance, and avoid accidents.
[0004] In order to achieve the above-mentioned purpose, the technical solution adopted by the present invention is: to provide a construction method of a shield tunnel passing through an existing subway tunnel at a micro-distance, comprising the following steps:
[0005] 1) Pre-construction environmental investigation and safety assessment: Before construction, investigate the surrounding construction environment of the site, as well as the spatial position relationship between the shield tunnel and the existing subway tunnel, establish a three-dimensional numerical calculation model, conduct a finite element safety assessment, and obtain the deformation impact range and impact value of the shield tunnel excavation on the existing subway tunnel and surrounding strata;
[0006] 2) Ground reinforcement and tunnel support: Determine the reinforcement scope according to the deformation influence scope of step 1), and reinforce the ground and existing subway tunnel within the reinforcement scope. The ground reinforcement adopts the grouting reinforcement method combining inside and outside the tunnel, and the existing subway tunnel reinforcement adopts the internal support reinforcement method;
[0007] 3) Setting up a test section to determine the excavation mode and parameters: Before the shield machine goes through, set up a test section of at least 50 meters. The geological conditions of the test section are the same as those when the shield machine officially goes through the existing subway tunnel. The shield machine excavates in the test section to obtain test data. Based on the test data, the excavation mode and parameters when the shield machine officially goes through the existing subway tunnel are determined;
[0008] 4) Soil disturbance monitoring and deformation monitoring of existing tunnels: A dual-source geological observation system is installed on the shield machine, a geological ultrasonic detector is installed at the intersection of the shield tunnel and the existing subway tunnel or on the ground, an inclinometer is installed in the stratum between the shield tunnel and the existing subway tunnel, and an automatic deformation monitoring system is installed in the existing subway tunnel. The surrounding soil disturbance monitoring and existing tunnel deformation monitoring are carried out through the above settings;
[0009] 5) Shield tunneling parameter control for tunneling under an existing subway tunnel: The shield starts tunneling. During the tunneling process, tunneling construction is carried out according to the tunneling mode and tunneling parameters determined in step 3), and the tunneling parameters are adjusted in combination with the soil disturbance monitoring and automated monitoring data in step 4). At the same time, grouting is used to strengthen the improvement of the tunneling slag in the underpass section;
[0010] 6) Control of slag discharge when the shield machine passes through an existing subway tunnel: Use a continuous belt conveyor to transport slag and control the slag discharge to avoid over-excavation and over-discharge, and reduce disturbance to the surrounding strata and the existing subway tunnel;
[0011] 7) Annular gap synchronous grouting and secondary supplementary grouting: Annular gap synchronous grouting and secondary supplementary grouting are carried out during shield excavation to fill the gap between the shield tunnel segments and the disturbed soil.
[0012] As a further improvement of the present invention, in step 1), Midas / GTS software is used to perform finite element safety assessment of the formation.
[0013] As a further improvement of the present invention, in step 2), the internal support of the existing subway tunnel adopts portal steel support or annular support.
[0014] As a further improvement of the present invention, in step 3), the shield tunneling mode adopts a full earth pressure balance mode and a gas pressure assisted mode.
[0015] As a further improvement of the present invention, in step 3), it is also necessary to conduct a comprehensive inspection and maintenance of the shield equipment, and replace the cutterhead tools.
[0016] As a further improvement of the present invention, in step 5), the method for improving the slag is to continuously inject fermented sodium-based bentonite liquid into the stratum through the radial holes of the shield.
[0017] As a further improvement of the present invention, in step 6), the method for controlling the slag discharge amount is: installing a slag weighing system and a slag three-dimensional scanning system on the belt conveyor to perform real-time dual control of the weight and volume of the slag discharge of each ring.
[0018] As a further improvement of the present invention, in step 7), the synchronous grouting of the annular gap adopts grouting through the shield tail grouting pipe, and the grouting parameters are adjusted according to the monitoring data of step 4); the secondary supplementary grouting adopts grouting behind the segment wall, and the grouting parameters are adjusted according to the monitoring data of step 4), and at the same time, multiple, low-pressure grouting processes are adopted for the areas with voids behind the segment wall in the underpass area.
[0019] As a further improvement of the present invention, in step 7), after each excavation of a certain distance, double liquid slurry is injected behind the annular wall of the segment to form a water-stop ring to prevent the flow of groundwater.
[0020] As a further improvement of the present invention, in step 7), after the shield tunneling reaches the point where the shield tail is 50m away from the crossing area, grouting is performed on the surface settlement area based on ground monitoring information, and the tunnel body is scanned by geological radar, and secondary grouting is performed on the area with voids behind the wall.
[0021] The beneficial effects of the present invention are as follows: the method effectively solves the construction difficulties of shield tunneling with a micro-distance underpass of an existing subway tunnel, and provides an effective reference for the tunneling mode and tunneling parameter selection of the shield tunneling through the tunnel through finite element safety assessment analysis and the setting of a test section before construction. At the same time, through ultrasonic waves, dual-source geology, inclinometers and automated deformation monitoring systems, the three-in-one real-time monitoring of the shield tunnel, the surrounding soil and the existing subway tunnel is achieved, and the shield tunneling parameters are adjusted in real time according to the monitoring data, thereby effectively controlling the disturbance and settlement deformation of the existing subway tunnel and the surrounding soil caused by the shield tunneling, reducing the risk of underpass construction, and ensuring the safety of shield construction. DETAILED DESCRIPTION
[0022] The present invention will be further described below in conjunction with specific embodiments.
[0023] A construction method for a shield tunnel to pass through an existing subway tunnel at a micro-distance, characterized by comprising the following steps:
[0024] 1) Pre-construction environmental investigation and safety assessment: Before construction, investigate the surrounding construction environment of the site, as well as the spatial position relationship between the shield tunnel and the existing subway tunnel. Establish a three-dimensional numerical calculation model, use Midas / GTS software to conduct finite element safety assessment of the formation, and obtain the deformation impact range and impact value of shield tunneling on the existing subway tunnel and surrounding formations.
[0025] 2) Stratum reinforcement and tunnel support: Determine the reinforcement scope according to the deformation influence scope of step 1), and reinforce the stratum and existing subway tunnel within the reinforcement scope. The stratum reinforcement adopts the grouting reinforcement method combining inside and outside the tunnel, and the existing subway tunnel reinforcement adopts the internal support reinforcement method, and the internal support adopts portal steel support or ring support.
[0026] 3) Set up a test section to determine the excavation mode and parameters: Before the shield machine goes under, set up a test section of at least 50 meters. The geological conditions of the test section are the same as those when the shield machine officially goes under the existing subway tunnel. The shield machine excavates in the test section to obtain test data such as excavation parameters and ground settlement. The excavation mode and parameters when the shield machine officially goes under the existing subway tunnel are determined based on the test data. According to the different geological conditions, the shield machine excavation mode can adopt the full earth pressure balance mode and the air pressure auxiliary mode. In addition, before going under, it is necessary to conduct a comprehensive inspection and maintenance of the shield equipment, and replace the cutterhead tool to ensure the continuous and rapid passage of the shield machine.
[0027] 4) Soil disturbance monitoring and deformation monitoring of existing tunnels: Before the shield machine officially passes through the existing subway tunnel, a three-in-one monitoring method of "new shield tunnel-surrounding soil-existing subway tunnel" is adopted to monitor the surrounding soil disturbance and deformation of the existing tunnel. By setting soil disturbance and existing tunnel monitoring points and monitoring sections, the horizontal and vertical deformation data and the impact range of the soil and the existing tunnel are obtained. Specifically, a dual-source geological observation system is installed on the shield machine, a geological ultrasonic detector is installed at the intersection of the shield tunnel and the existing subway tunnel or on the ground, an inclinometer is installed in the stratum between the shield tunnel and the existing subway tunnel, and an automated deformation monitoring system is installed in the existing subway tunnel. Through the mutual verification of the soil disturbance monitoring results of ultrasonic, dual-source geology, and inclinometer tubes and the automated deformation monitoring results, a more accurate deformation law of the existing subway tunnel is obtained.
[0028] 5) Parameter control of shield tunneling under existing subway tunnels: The shield starts tunneling. During the tunneling process, the tunneling construction is carried out according to the tunneling mode and tunneling parameters determined in step 3), and the tunneling parameters are adjusted in combination with the soil disturbance monitoring and automated monitoring data in step 4). At the same time, grouting is used to strengthen the improvement of the excavation slag in the underpass section. The method of improving the slag is to continuously inject fermented sodium-based bentonite liquid into the stratum through the radial holes of the shield, and a combination of high molecular polymer and foam is used to strengthen the improvement of the excavation slag in the underpass section, reduce the disturbance to the upper stratum, and control the settlement within the minimum range.
[0029] 6) Control of the amount of slag discharged when the shield machine passes through the existing subway tunnel: Use a continuous belt conveyor to transport slag and control the amount of slag discharged, so as to achieve precise control of the amount of slag discharged during the shield machine passing through, avoid over-excavation and over-discharge, and reduce the disturbance of the surrounding strata and the existing subway tunnel. The method for controlling the amount of slag discharged is to install a slag weighing system and a slag three-dimensional scanning system on the belt conveyor, and use the above system to control the weight and volume of the slag discharged in each ring in real time.
[0030] 7) Annular gap synchronous grouting and secondary supplementary grouting: During the shield excavation process, the annular gap synchronous grouting and secondary supplementary grouting are carried out to fill the gap between the shield tunnel segment and the disturbed soil. The annular gap synchronous grouting adopts the shield tail grouting pipe grouting, and the grouting parameters are adjusted according to the monitoring data of step 4). The secondary supplementary grouting adopts the grouting behind the segment wall, and the grouting parameters are adjusted according to the monitoring data of step 4). Multiple, low-pressure grouting processes are used for the areas with voids behind the segment wall in the underpass area. At the same time, after each excavation distance, double liquid slurry is injected behind the segment annular wall to form a water-stop ring hoop to prevent groundwater from colluding. When the shield excavates to 50m after the shield tail is separated from the crossing area, according to the ground monitoring information, the surface settlement area is supplemented with grouting, and the crossing tunnel body is scanned by geological radar, and the area with voids behind the wall is supplemented with grouting.
[0031] The above solution has the following advantages:
[0032] 1. Strong practicability. This method can monitor the soil disturbance during the construction process through the soil disturbance monitoring system, and feedback the information to the technical personnel, so as to timely guide the adjustment of the shield excavation parameters to avoid the expansion of the disturbance and the occurrence of accidents. In addition, this method is suitable for the earth pressure balance shield machine to pass through the existing subway tunnel with a small spacing, and can also be used for other shield methods to pass through important buildings.
[0033] 2. Efficient and convenient. This method sets up soil disturbance monitoring, automatic monitoring system, continuous belt conveyor slag transport system, and slag discharge control system, realizing visual shield tunneling control, which can effectively ensure the shield to pass continuously at a uniform speed, and plays an important role in improving the construction efficiency of shield tunneling under existing subway tunnels.
[0034] 3. Ensure construction quality. This method makes full use of ultrasonic geophysical exploration, information technology and other technologies to improve the quality of shield construction control, avoid conservative and blind operations due to the lack of comprehensive understanding of the on-site conditions during construction, effectively control the settlement and deformation of existing subway tunnels, reduce the risk of shield underpass construction, and ensure the safety of shield construction.
[0035] 4. High economic efficiency. This method has the characteristics of simple construction process, convenient operation and strong practicality. It can avoid the use of grouting reinforcement and other measures on the ground to the greatest extent, avoid complicated construction procedures, greatly reduce the amount of work, shorten the construction period, and achieve the ideal process effect, saving labor costs and construction period costs, and establishing an image for the project.
[0036] The above embodiments are only used to illustrate the present invention and are not intended to limit the present invention in any form. Any person with ordinary knowledge in the technical field may make partial changes or modifications to the technical contents disclosed in the present invention without departing from the scope of the technical features of the present invention, and the equivalent embodiments without departing from the technical features of the present invention are still within the scope of the technical features of the present invention.
Claims
1. A construction method for a shield tunnel to pass through an existing subway tunnel at a micro-distance, characterized in that The following steps are involved: 1) Pre-construction environmental investigation and safety assessment: Before construction, investigate the surrounding construction environment of the site, as well as the spatial position relationship between the shield tunnel and the existing subway tunnel, establish a three-dimensional numerical calculation model, conduct a finite element safety assessment, and obtain the deformation impact range and impact value of the shield tunnel excavation on the existing subway tunnel and surrounding strata; 2) Ground reinforcement and tunnel support: Determine the reinforcement scope according to the deformation influence scope of step 1), and reinforce the ground and existing subway tunnel within the reinforcement scope. The ground reinforcement adopts the grouting reinforcement method combining inside and outside the tunnel, and the existing subway tunnel reinforcement adopts the internal support reinforcement method; 3) Setting up a test section to determine the excavation mode and parameters: Before the shield machine goes through, set up a test section of at least 50 meters. The geological conditions of the test section are the same as those when the shield machine officially goes through the existing subway tunnel. The shield machine excavates in the test section to obtain test data. Based on the test data, the excavation mode and parameters when the shield machine officially goes through the existing subway tunnel are determined; 4) Soil disturbance monitoring and deformation monitoring of existing tunnels: A dual-source geological observation system is installed on the shield machine, a geological ultrasonic detector is installed at the intersection of the shield tunnel and the existing subway tunnel or on the ground, an inclinometer is installed in the stratum between the shield tunnel and the existing subway tunnel, and an automatic deformation monitoring system is installed in the existing subway tunnel. The surrounding soil disturbance monitoring and existing tunnel deformation monitoring are carried out through the above settings; 5) Shield tunneling parameter control for tunneling under an existing subway tunnel: The shield starts tunneling. During the tunneling process, tunneling construction is carried out according to the tunneling mode and tunneling parameters determined in step 3), and the tunneling parameters are adjusted in combination with the soil disturbance monitoring and automated monitoring data in step 4). At the same time, grouting is used to strengthen the improvement of the tunneling slag in the underpass section; 6) Control of slag discharge when the shield machine passes through an existing subway tunnel: Use a continuous belt conveyor to transport slag and control the slag discharge to avoid over-excavation and over-discharge, and reduce disturbance to the surrounding strata and the existing subway tunnel; 7) Annular gap synchronous grouting and secondary supplementary grouting: Annular gap synchronous grouting and secondary supplementary grouting are carried out during shield excavation to fill the gap between the shield tunnel segments and the disturbed soil.
2. The method for constructing a shield tunnel with a micro-distance underpass through an existing subway tunnel according to claim 1, characterized in that: In step 1), Midas / GTS software is used to perform finite element safety assessment of the formation.
3. The method for constructing a shield tunnel with a micro-distance underpass through an existing subway tunnel according to claim 1, characterized in that: In step 2), the internal support of the existing subway tunnel adopts portal steel support or ring support.
4. The method for constructing a shield tunnel with a micro-distance underpass through an existing subway tunnel according to claim 1, characterized in that: In step 3), the shield tunneling mode adopts the full earth pressure balance mode and the air pressure assisted mode.
5. The method for constructing a shield tunnel with a micro-distance underpass through an existing subway tunnel according to claim 1, characterized in that: In step 3), the shield equipment also needs to be fully inspected and maintained, and the cutterhead tools need to be replaced.
6. The method for constructing a shield tunnel with a micro-distance underpass through an existing subway tunnel according to claim 1, characterized in that: In step 5), the method for improving the slag is to continuously inject fermented sodium-based bentonite liquid into the stratum through the radial holes of the shield.
7. The method for constructing a shield tunnel with a micro-distance underpass through an existing subway tunnel according to claim 1, characterized in that: In step 6), the method for controlling the slag discharge amount is: installing a slag weighing system and a slag three-dimensional scanning system on the belt conveyor to perform real-time dual control of the weight and volume of the slag discharge of each ring.
8. The method for constructing a shield tunnel with a micro-distance underpass through an existing subway tunnel according to claim 1, characterized in that: In step 7), the synchronous grouting of the annular gap adopts grouting through the shield tail grouting pipe, and the grouting parameters are adjusted according to the monitoring data of step 4); the secondary supplementary grouting adopts grouting behind the segment wall, and the grouting parameters are adjusted according to the monitoring data of step 4). At the same time, multiple, low-pressure grouting processes are used for the areas with voids behind the segment wall in the underpass area.
9. The method for constructing a shield tunnel with a micro-distance underpass through an existing subway tunnel according to claim 1, characterized in that: In step 7), after each excavation for a certain distance, double liquid slurry is injected behind the annular wall of the segment to form a water-stop ring to prevent groundwater from flowing through.
10. The method for constructing a shield tunnel with a micro-distance underpass through an existing subway tunnel according to claim 1, characterized in that: In step 7), when the shield tunneling reaches the point where the shield tail is 50m away from the crossing area, grouting is performed on the surface settlement area according to the ground monitoring information, and the tunnel body is scanned by geological radar, and secondary grouting is performed on the area with voids behind the wall.
Citation Information
Patent Citations
Large diameter tunneling close range down-traversing small diameter subway tunnel distortion control method
CN101215969A
Active protection structurefor water-rich soft soil area shield closely passing throughoperation tunnel and construction method
CN110230499A
Construction method for directly grinding group piles when subway shield penetrates through existing station in close range
CN117514214A
Pre-reinforcement construction method for shield tunnel underneath pass and side pass subsurface tunnel
CN117703391A
Construction method for making water-rich sand layer shield over cross existing line and underneath cross sewage push pipe at close range
US20210301660A1
Cited By
Construction method and device for shield tunneling to pass through existing structure
CN119249582A
Construction method for shield tunneling machine to pass through expressway under narrow space condition
CN119825378A