Staged permanent and temporary combined construction method for fire-fighting water supply system

By gradually replacing temporary firefighting pipes and water tanks with formal firefighting pipes and pump rooms at the construction site, the problem of high material and labor costs for temporary firefighting water supply systems during construction was solved, and more efficient construction management and fire safety management were achieved.

CN118855046APending Publication Date: 2024-10-29THE FOURTH CONSTR ENG COMPANY LTD OF CHINA CONSTR SECOND ENG BUREAU
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410930194.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-11
Publication Date
2024-10-29

AI Technical Summary

Technical Problem

The existing construction fire water supply system requires a large amount of material input for temporary fire protection pipes, high rental costs, high installation and removal labor costs, and the unreasonable capacity of temporary fire protection water tanks, which affects construction efficiency and fire safety.

Method used

The fire water supply system adopts a phased and permanent construction method. By setting up temporary fire water tanks and pump rooms, and gradually replacing them with formal fire pipes and pump rooms, the construction progress is dynamically managed, the cost of temporary pipeline materials and labor is reduced, the turnover rate is increased, and the temporary Cost of increased tank capacity.

Benefits of technology

It reduces temporary fire piping material and labor costs, shortens the installation period, improves construction efficiency, complies with fire safety management requirements, realizes interleaved construction of civil construction and installation operations, and improves the economy and efficiency of construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118855046A_ABST
    Figure CN118855046A_ABST
Patent Text Reader

Abstract

The invention relates to a stage permanent and temporary combined construction method for a fire-fighting water supply system. The method comprises the following steps: arranging a temporary fire-fighting water tank and a temporary fire-fighting pump room; laying a temporary fire-fighting pipeline on the ground; laying a temporary fire-fighting pipeline of the garage; cleaning the fire pool and injecting water; the temporary fire pump room is integrally transferred to the position above the underground garage; building formal fire-fighting pipelines are constructed, the building formal fire-fighting pipelines are connected into garage temporary fire-fighting pipelines, and temporary fire-fighting water tanks are dismantled; a formal fire pump room and a garage formal fire pipeline are constructed; a garage formal fire-fighting pipeline and a building formal fire-fighting pipeline are connected into a formal fire-fighting pump room, and a temporary fire-fighting pump room is dismantled; and the garage temporary fire-fighting pipeline and the overground temporary fire-fighting pipeline are successively dismantled. The transformation of the stage fire-fighting water supply system embodies a dynamic management process and is combined with the field, the construction is more efficient, and a novel construction mode of interspersed construction of civil engineering and installation operation is embodied.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of building construction fire protection systems, and in particular to a phased permanent and temporary combined construction method for a fire protection water supply system. Background Art

[0002] The construction fire water supply system is the focus of fire protection requirements in building construction. How to lay out the fire water supply system economically and effectively under the premise of meeting the specifications? At present, construction sites generally choose to use temporary fire pipes, set up temporary fire water tanks and temporary water pump rooms on site, and the temporary fire water tanks and temporary water pump rooms will last from the start of construction until the completion of project decoration. The scope of the temporary fire protection system includes outdoor circular fire pipes, basement fire pipes, and main structure construction fire pipes. A fire hydrant is set at intervals of no more than 120m for outdoor temporary fire pipes.

[0003] At present, during the main construction phase of most construction sites, temporary DN100 galvanized steel pipes are arranged vertically upstairs, and temporary fire hydrants are arranged on each floor, which are then removed after the interior decoration is completed. The existing construction method requires a large amount of temporary pipeline materials, high rental costs for temporary fire water tanks, and high labor costs for pipeline installation and removal. At the same time, after the temporary fire pipes are removed, the holes reserved in the floor slabs also need to be sealed in time. Summary of the invention

[0004] In order to improve the economic benefits of the construction fire protection system, the present invention provides a phased permanent and temporary construction method for a fire protection water supply system.

[0005] The present invention provides a phased permanent and temporary construction method for a fire water supply system, which adopts the following technical solution: A phased permanent and temporary construction method for a fire water supply system comprises the following steps: S1: According to the construction progress of the underground garage and single building, set up temporary fire water tanks and temporary fire pump room; S2: Lay temporary fire-fighting pipelines on the ground; S3: Lay out temporary fire-fighting pipes in the garage; S4: Clean the fire water pool in the underground garage and fill it with water, and put the fire water pool into use; S5: Transfer the temporary fire pump room as a whole to the top of the underground garage; S6: The formal fire-fighting pipelines of the building are constructed along with the floors. The formal fire-fighting pipelines of the building are connected to the temporary fire-fighting pipelines of the garage. The fire-fighting pool starts to supply water to the temporary fire-fighting pipelines of the garage, the formal fire-fighting pipelines of the building and the temporary fire-fighting pipelines on the ground. The temporary fire-fighting water tank is removed; S7: Construction of formal fire pump room and garage formal fire pipelines; S8: Connect the official fire-fighting pipelines of the garage and the building to the official fire-fighting pump room, and dismantle the temporary fire-fighting pump room; S9: According to the construction progress, the temporary fire-fighting pipes in the garage and the temporary fire-fighting pipes on the ground will be dismantled one by one.

[0006] By adopting the above technical scheme, the official fire-fighting pipes in the building replace the temporary fire-fighting pipes entering the single building in the existing technology, reducing the material consumption and installation labor costs of this part of the temporary fire-fighting pipes, and inserting the official fire-fighting pipes in the construction garage and the official fire-fighting pipes in the building in advance, shortening the construction period of the installation phase; the transformation of the phased fire-fighting water supply system reflects the dynamic management process, and combined with the site, the construction is more efficient, reflecting a new construction method in which civil engineering and installation operations are interspersed.

[0007] Optionally, the capacity of the temporary fire water tank only meets the needs of underground garages, non-standard floor construction and outdoor fire fighting.

[0008] By adopting the above technical solution, the capacity and usage time of the temporary fire water tank can be considered only according to the construction phase of the underground garage, temporary ground fire pipes and non-standard floors. While improving the turnover rate, it also reduces the cost increase caused by the increase in the capacity of the temporary fire water tank, and also meets the fire safety management requirements of the project.

[0009] Optionally, a sleeve may be embedded in the wall of the underground garage for use in laying temporary fire-fighting pipes in the garage.

[0010] By adopting the above technical solution, the installation and construction of temporary fire-fighting pipes in the garage is facilitated.

[0011] Optionally, the temporary fire pump room in step S5 is set above the fire water tank.

[0012] By adopting the above technical solution, short-distance water supply is facilitated, saving pipeline consumables and power consumption.

[0013] Optionally, the temporary fire water tank and temporary fire pump room in step S1 are set up inside the construction site enclosure and close to the water intake point.

[0014] By adopting the above technical solution, the timely supply of water in the temporary fire water tank is facilitated.

[0015] Optionally, in step S3, a temporary construction water pipe for the building is laid in the single building and connected to the temporary fire-fighting pipe in the garage; in step S6, water is supplied to the temporary construction water pipe for the building from the fire-fighting water tank; in step S7, a domestic water tank and a domestic water pump room are constructed simultaneously; in step S8, the temporary fire-fighting pipe in the garage, the temporary fire-fighting pipe on the ground and the temporary construction water pipe for the building are connected to the domestic water pump room; in step S9, the temporary construction water pipes for the building are gradually dismantled.

[0016] By adopting the above technical solution, the temporary construction water system of the building is involved in the fire protection system construction process, and the domestic water tank and the domestic water pump room are interspersed with the fire protection system construction. The domestic water tank plays the role of supplying water to the temporary construction of the building in the early stage, reducing the water supply burden of the fire protection pool.

[0017] In summary, the present invention includes at least one of the following beneficial technical effects: The formal fire-fighting pipelines in the building replaced the temporary fire-fighting pipelines entering the single building in the existing technology, reducing the material consumption and installation and removal labor costs of these temporary fire-fighting pipelines. The formal fire-fighting pipelines in the construction garage and the formal fire-fighting pipelines in the building were inserted in advance, shortening the construction period of the installation stage. The transformation of the phased fire-fighting water supply system reflects the dynamic management process. Combined with the site, the construction is more efficient, reflecting a new construction method of interlacing civil engineering and installation operations. The capacity and use time of temporary fire water tanks can be considered only according to the construction phase of underground garages, temporary fire pipes on the ground and non-standard floors. This improves the turnover rate and reduces the cost increase caused by the increase in the capacity of temporary fire water tanks. It also meets the fire safety management requirements of the project. The temporary construction water system of the building is involved in the construction process of the fire protection system. The domestic water tank and the domestic water pump room are interspersed with the construction of the fire protection system. In the early stage, the domestic water tank played the role of supplying water to the temporary construction of the building, reducing the water supply burden of the fire water pool. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] Figure 1 It is a flow chart of the phased permanent and temporary combined construction method of the fire water supply system according to an embodiment of the present invention.

[0019] Figure 2 It is a schematic diagram of the first-stage temporary fire pump room before transfer in an embodiment of the present invention.

[0020] Figure 3 It is a schematic diagram of the second-stage temporary fire pump room of an embodiment of the present invention being transferred as a whole to above the underground garage.

[0021] Figure 4 It is a schematic diagram of a formal fire pump room in the third stage of an embodiment of the present invention.

[0022] Explanation of the reference numerals in the accompanying drawings: 1. Underground garage; 10. Temporary fire-fighting pipe in garage; 11. Formal fire-fighting pipe in garage; 2. Single building; 20. Temporary construction water pipe in building; 21. Formal fire-fighting pipe in building; 3. Temporary fire-fighting water tank; 4. Temporary fire-fighting pump room; 5. Temporary fire-fighting pipe on the ground; 6. Fire-fighting pool; 7. Formal fire-fighting pump room; 8. Domestic water tank; 9. Domestic water pump room. DETAILED DESCRIPTION

[0023] The following is combined with Figure 1 -Attached Figure 4 The present invention is described in further detail.

[0024] The embodiment of the present invention discloses a phased permanent and temporary construction method for a fire water supply system, comprising the following steps: Reference Figure 1 and Figure 2 The first phase of the fire water supply system construction process includes: S1: According to the construction progress of the underground garage 1 and the single building 2, a temporary fire water tank 3 and a temporary fire pump room 4 are rationally planned to be set up near the water intake point within the construction site enclosure. The temporary fire water tank 3 only needs to meet the needs of the underground garage 1, non-standard floor construction and outdoor fire fighting.

[0025] S2: Lay out a temporary fire-fighting pipe 5 outdoors on the ground, which uses a DN150 pipe.

[0026] S3: Lay out the temporary fire-fighting pipe 10 in the garage. The temporary fire-fighting pipe 10 in the garage adopts a DN100 pipe and needs to be laid underground at the crossing. The outer wall of the underground garage 1 is pre-buried with a casing for the temporary fire-fighting pipe 10 in the garage. The temporary fire-fighting pipe 10 in the garage is introduced into the underground garage 1. The temporary fire-fighting pipe 10 in the garage is arranged under the roof of the underground garage 1. Then the temporary fire-fighting pipe 10 in the garage branches off and connects to each single building 2. After entering the single building 2, it is connected to the temporary construction water pipe 20 of the building. The temporary construction water pipe 20 of the building adopts a DN100 pipe. The temporary construction water pipe 20 of the building is used to provide water for construction personnel during the construction process, such as water for cleaning formwork and concrete maintenance.

[0027] Reference Figure 1 and Figure 3 The second phase construction process of the fire water supply system includes: S4: After the top plate of the underground garage 1 is demolded, the fire pool 6 located at the bottom of the underground garage 1 is cleaned first and waterproofed; the fire pool 6 is used to temporarily store water, and the water supply pipe of the fire pool 6 is constructed to introduce municipal water into the fire pool 6 for water supply.

[0028] S5: After the fire water tank 6 is filled with water, the temporary fire pump room 4 is transferred as a whole to the roof of the underground garage 1. The temporary fire pump room 4 is required to be located above the fire water tank 6 to facilitate short-distance water supply, save pipeline consumables and power consumption, and the waterproof and protective layer on the roof of the underground garage 1 where the temporary fire pump room 4 is located must be completed in advance.

[0029] S6: As the floor construction progresses, the formal fire-fighting pipe 21 of the building is gradually installed. The formal fire-fighting pipe 21 of the building adopts a DN100 pipe. The formal fire-fighting pipe 21 of the building is connected to the temporary fire-fighting pipe 10 in the garage. The fire-fighting water pool 6 starts to supply water to the temporary fire-fighting pipe 10 in the garage, the temporary construction water pipe 20 of the building, the formal fire-fighting pipe 21 of the building and the temporary fire-fighting pipe 5 on the ground. The temporary fire-fighting water tank 3 located outdoors is removed.

[0030] Reference Figure 1 and Figure 4 The third phase construction process of the fire water supply system includes: S7: Construction of formal fire pump room 7, formal fire pipe 11 in garage, domestic water tank 8 and domestic water pump room 9. The formal fire pipe 11 in garage adopts DN100 pipe.

[0031] S8: Connect the official fire-fighting pipe 11 of the garage and the official fire-fighting pipe 21 of the building to the official fire-fighting pump room 7, and dismantle the temporary fire-fighting pump room 4; connect the temporary fire-fighting pipe 10 of the garage, the temporary construction water pipe 20 of the building and the temporary fire-fighting pipe 5 on the ground to the domestic water pump room 9.

[0032] S9: According to the construction progress, the temporary fire-fighting pipes 10 in the garage, the temporary construction water pipes 20 in the building and the temporary fire-fighting pipes 5 on the ground are dismantled one after another.

[0033] The fire water pool 6 in the present invention can be put into use after the construction is completed. At the same time, the formal fire-fighting pipes 21 of the building are installed layer by layer in the single building 2. The capacity of the temporary fire-fighting water tank 3 can only meet the use needs of the temporary fire-fighting pipes 10 in the garage, the temporary construction water pipes 20 in the building and the temporary fire-fighting pipes 5 on the ground. It does not need to meet the use needs of the standard floors of the building. While improving the turnover rate, it also reduces the cost increase caused by the increase in the capacity of the temporary fire-fighting water tank 3, and also meets the fire safety management requirements of the project.

[0034] The formal fire-fighting pipeline 21 of the building replaces the temporary fire-fighting pipeline entering the single building 2 in the prior art, reducing the material consumption and installation labor cost of this part of the temporary fire-fighting pipeline, and inserting the formal fire-fighting pipeline 21 of the building and the formal fire-fighting pipeline 11 of the garage in advance, effectively shortening the construction period of the installation phase.

[0035] Through the above three-stage layout, the initial temporary fire water tank 3, temporary fire pump room 4, and temporary ground fire pipe 5 are gradually transformed into the fire water pool 6, the formal fire pump room 7, the garage formal fire pipe 11 and the building formal fire pipe 21 which are put into use.

[0036] During the construction of the fire protection system, the domestic water tank 8 and the domestic water pump room 9 are interspersed with the construction. The domestic water tank 8 is used to bear the water demand of the temporary construction water pipe 20 of the building and the temporary fire protection pipe 5 on the ground in the later stage of construction. After the construction is completed, the temporary fire protection pipe 10 in the garage, the temporary construction water pipe 20 of the building and the temporary fire protection pipe 5 on the ground are promptly dismantled without affecting the operation of the formal fire protection system; and the domestic water tank 8 is temporarily used as a water source, which effectively reduces the water supply pressure of the fire water pool 6.

[0037] The phased transformation of the fire water supply system reflects a dynamic management process. Combined with the site, the construction is more efficient and reflects a new construction method in which civil engineering and installation operations are interspersed.

[0038] The above are all preferred embodiments of the present invention, and are not intended to limit the protection scope of the present invention. Therefore, any equivalent changes made based on the structure, shape, and principle of the present invention should be included in the protection scope of the present invention.

Claims

1. A phased permanent and temporary construction method for a fire water supply system, characterized in that: The following steps are involved: S1: According to the construction progress of the underground garage (1) and the single building (2), a temporary fire water tank (3) and a temporary fire pump room (4) are set up; S2: Lay out temporary fire-fighting pipes on the ground (5); S3: Lay out temporary fire-fighting pipes in the garage (10); S4: cleaning the fire water pool (6) in the underground garage (1) and filling it with water, and the fire water pool (6) is put into use; S5: The temporary fire pump room (4) is transported as a whole to the top of the underground garage (1); S6: The formal fire-fighting pipeline (21) of the building is constructed along with the floors. The formal fire-fighting pipeline (21) of the building is connected to the temporary fire-fighting pipeline (10) of the garage. The fire-fighting pool (6) starts to supply water to the temporary fire-fighting pipeline (10) of the garage, the formal fire-fighting pipeline (21) of the building and the temporary fire-fighting pipeline (5) on the ground. The temporary fire-fighting water tank (3) is removed. S7: Construction of the formal fire pump room (7) and the formal fire pipes in the garage (11); S8: Connect the garage's official fire-fighting pipeline (11) and the building's official fire-fighting pipeline (21) to the official fire-fighting pump room (7), and dismantle the temporary fire-fighting pump room (4); S9: According to the construction progress, the temporary fire-fighting pipes in the garage (10) and the temporary fire-fighting pipes on the ground (5) are gradually removed.

2. The phased permanent and temporary construction method for fire water supply system according to claim 1 is characterized by: The capacity of the temporary fire water tank (3) can only meet the needs of the underground garage (1), non-standard floor construction and outdoor fire fighting.

3. The phased permanent and temporary construction method for fire water supply system according to claim 1 is characterized by: A sleeve is pre-buried in the wall of the underground garage (1) for use in laying a temporary fire-fighting pipeline (10) in the garage.

4. The phased permanent and temporary construction method for fire water supply system according to claim 1 is characterized by: The temporary fire pump room (4) in step S5 is arranged above the fire water pool (6).

5. The phased permanent and temporary construction method for fire water supply system according to claim 1 is characterized by: The temporary fire water tank (3) and the temporary fire pump room (4) in step S1 are arranged inside the construction site enclosure and close to the water intake point.

6. The phased permanent and temporary construction method for fire water supply system according to claim 1 is characterized by: In step S3, a temporary building construction water pipe (20) connected to the temporary garage fire pipe (10) is laid in the single building (2); in step S6, water is supplied from the fire water tank (6) to the temporary building construction water pipe (20); in step S7, a domestic water tank (8) and a domestic water pump room (9) are simultaneously constructed; in step S8, the temporary garage fire pipe (10), the temporary ground fire pipe (5) and the temporary building construction water pipe (20) are connected to the domestic water pump room (9); in step S9, the temporary building construction water pipe (20) is gradually removed.