By designing a three-axis comprehensive simulation test system for displacing coal bed methane, the problem that the existing system cannot accurately simulate deep coal seam conditions has been solved, efficient coal bed methane mining and CO2 storage have been achieved, mining parameters have been optimized, and environmental pollution has been reduced.
Patent Information
- Application Number
- CN202410869410.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-01
- Publication Date
- 2024-10-29
AI Technical Summary
The existing simulated coalbed methane mining test system cannot accurately simulate the complex geological conditions of deep coal seams, and lacks stability and accuracy, making it difficult to verify and optimize the feasibility of gas displacement coalbed methane technology.
A three-axis comprehensive simulation test system for displacing coal bed methane is designed, including a gas source module, a pressurization module, a geochemical reaction module, an adsorption and desorption module and a three-axis displacement module, which can simulate the coal bed methane mining process under real formation conditions. , optimize mining parameters by monitoring and recording parameter changes in real time.
It has improved the accuracy and stability of coalbed methane mining, verified the feasibility of CO2 displacement coalbed methane technology, optimized mining parameters, improved mining efficiency, achieved underground storage of CO2, and reduced environmental pollution.
Smart Images

Figure CN118855432A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of coalbed methane mining and relates to a three-axis comprehensive simulation test system for displacing coalbed methane. Background Art
[0002] Coalbed methane is an important clean energy source, which is mainly stored in the pores and cracks of coal seams. With the increase of global demand for energy and the improvement of environmental awareness, the development and utilization of coalbed methane as a clean and efficient energy resource has received more and more attention.
[0003] However, the extraction of coalbed methane faces many challenges. First, the permeability of coal seams is usually low, which makes it difficult for coalbed methane to be released naturally. Second, the geological conditions of deep coal seams are complex, such as high ground stress and high ground temperature, which increase the difficulty of extraction. In addition, the extraction of coalbed methane may also cause environmental problems such as ground subsidence and groundwater pollution.
[0004] In order to overcome these challenges, researchers have proposed a technology to use gas to displace coalbed methane. The core idea of this technology is to inject gas into the coal seam and replace CH4 (the main component of coalbed methane) in the coal seam through the effect of pressure difference and concentration difference. For example, CO2 displaces coalbed methane. This method can not only improve the efficiency of coalbed methane extraction, but also realize the underground storage of CO2, which helps to mitigate global climate change.
[0005] In order to verify the feasibility of gas displacement of coalbed methane technology and optimize mining parameters, it is necessary to establish a test system that can simulate the coalbed methane mining process under real formation conditions. Although there are some test systems that simulate coalbed methane mining, they can often only simulate a single or a few conditions, and often lack sufficient accuracy and stability. Therefore, designing a three-axis comprehensive simulation test system for deep coal seam gas injection to displace coalbed methane, simulating the deep coal seam environment in the laboratory, not only helps to promote the innovative development of coalbed methane mining technology, but also provides strong technical support for achieving the dual goals of energy and environment. This design not only has far-reaching theoretical significance, but also shows broad prospects in practical applications. Summary of the invention
[0006] The present invention proposes a three-axis comprehensive simulation test system for displacing coalbed methane, which can simulate the coalbed methane mining process under real formation conditions, has high accuracy and stability, is easy to control, simple to operate, safe and reliable.
[0007] The technical solution of the present invention is achieved in this way:
[0008] Technical Theme 1
[0009] A three-axis comprehensive simulation test system for displacing coalbed methane, comprising:
[0010] The gas source module is connected to the booster module and is used to provide gas for the entire system;
[0011] The booster module is connected to the geochemical reaction module, the adsorption and desorption module and the three-axis displacement module, and is used to provide high-pressure test gas;
[0012] Geochemical reaction module, used to conduct geochemical reaction experiments during the process of gas injection to displace coalbed methane in deep coal seams;
[0013] Adsorption and desorption module, used for gas adsorption and desorption test during gas injection to displace coalbed methane in deep coal seams;
[0014] The three-axis displacement module comprises a three-axis displacement device, a gas supply device, a liquid supply device, a vacuum device and a gas-liquid collecting device; one end of the three-axis displacement device is respectively connected to the gas supply device, the liquid supply device and the vacuum device, and the other end is connected to the gas-liquid collecting device;
[0015] The three-axis displacement device includes a twenty-third valve, a second pressure tracking pump, a sample chamber, a hydraulic layer, a third pressure tracking pump, and a resistance strain gauge; the second pressure tracking pump and the third pressure tracking pump are connected to the three-axis instrument device through pipelines, and the three-axis instrument device is provided with a seventh pressure sensor and a fifth temperature sensor; the twenty-third valve is connected to the first pressure reducing valve of the gas supply device, the twenty-first valve, the twenty-second valve of the liquid supply device, and the twenty-ninth valve of the vacuum pumping device, and the outlet of the sample chamber is connected to the third pressure reducing valve of the gas-liquid collecting device through a pipeline; the sixth pressure sensor is arranged on the connecting pipeline between the twenty-third valve and the gas supply device and the liquid supply device; a plurality of strain gauges are arranged on the sample, and the strain gauge leads are connected to the electrical signals of the resistance strain gauge;
[0016] A gas supply device, comprising a first high-pressure gas buffer tank and a second high-pressure gas buffer tank; the first high-pressure gas buffer tank is connected to a sixteenth valve and a first pressure reducing valve in sequence, and the second high-pressure gas buffer tank is connected to a seventeenth valve, a second pressure reducing valve, a fifth one-way valve, and a twenty-first valve in sequence, wherein the seventeenth valve and the second pressure reducing valve are connected in parallel to a branch valve eighteenth valve, a nineteenth valve, a liquid cylinder, and a twentieth valve; a fourteenth valve is arranged on a pipeline between the first high-pressure gas buffer tank and a boosting module, and a fifteenth valve is arranged on a pipeline between the second high-pressure gas buffer tank and the boosting module; a third temperature sensor and a fourth pressure sensor are arranged in the first high-pressure gas buffer tank, and a fifth pressure sensor and a fourth temperature sensor are arranged in the second high-pressure gas buffer tank;
[0017] The liquid supply device includes a first pressure tracking pump, a sixth one-way valve, a hydraulic tank, a seventh one-way valve and a twenty-second valve connected in sequence;
[0018] A vacuum device, used to exhaust the gas in the three-axis displacement device;
[0019] Gas-liquid collection device, used to collect liquid and gas during and after the test;
[0020] The information control module is used to control the test process, display and store data.
[0021] Preferably, the gas source module includes methane, nitrogen, carbon dioxide and argon gas cylinders connected in parallel; wherein the methane gas cylinder is connected in series with the first pressure regulating valve and the first one-way valve, the nitrogen gas cylinder is connected in series with the second pressure regulating valve and the second one-way valve, the carbon dioxide gas cylinder is connected in series with the third pressure regulating valve and the third one-way valve, and the argon gas cylinder is connected in series with the fourth pressure regulating valve and the fourth one-way valve; the first one-way valve, the second one-way valve, the third one-way valve and the fourth one-way valve are connected in parallel with the gas booster pump of the booster module.
[0022] Preferably, the boosting module comprises an air compressor, a first valve and a gas boosting pump which are connected in sequence, and the gas boosting pump is respectively connected to the fourteenth valve and the fifteenth valve of the three-axis displacement module.
[0023] Preferably, the vacuum pumping device comprises a third vacuum pump and a twenty-ninth valve connected in sequence.
[0024] Preferably, the gas-liquid collecting device includes a third pressure reducing valve, a twenty-fourth valve, a gas flow meter, a twenty-fifth valve, a gas collecting tank, a twenty-seventh valve, a gas sampling bottle, a twenty-eighth valve, a twenty-ninth valve, and a gas chromatograph which are connected in sequence; a gas-liquid separator is arranged on the pipeline between the twenty-fourth valve and the gas flow meter, a twenty-sixth valve is arranged at the lower part of the gas collecting tank, and the twenty-sixth valve is connected to the drainage trough.
[0025] Preferably, the geochemical reaction module comprises: a high-temperature and high-pressure reactor, a fourth valve, a liquid collecting tank and a fifth valve connected in sequence; a second valve is arranged on the pipeline between the high-temperature and high-pressure reactor and the boosting module; a second valve is arranged on the pipeline between the high-temperature and high-pressure reactor and the gas boosting pump; a third valve is arranged on the pipeline between the high-temperature and high-pressure reactor and the first vacuum pump; wherein the high-temperature and high-pressure reactor is provided with a first pressure sensor and a first temperature sensor; a heating device is arranged inside the high-temperature and high-pressure reactor, and an insulation layer is also arranged on the outer layer of the heating device.
[0026] Preferably, the adsorption and desorption module includes a reference cylinder, a sample cylinder, an eighth valve, a ninth valve, an eleventh valve, a gas collecting pipe, and a thirteenth valve connected in sequence; a sixth valve is arranged on the pipeline between the reference cylinder and the boosting module, and a sixth valve is arranged on the pipeline between the reference cylinder and the gas boosting pump; a tenth valve is arranged on the pipeline between the eighth valve and the ninth valve, and the tenth valve controls the connection with the atmosphere; a twelfth valve is arranged on the pipeline between the ninth valve and the eleventh valve, and the twelfth valve is connected to a second vacuum pump; a second pressure sensor and a third pressure sensor are respectively arranged on the reference cylinder and the sample cylinder, which are respectively used to detect the pressure of the reference cylinder and the sample cylinder; the reference cylinder and the sample cylinder are placed in a constant temperature water bath, and a second temperature sensor is arranged on the constant temperature water bath; the seventh valve connects the reference cylinder and the sample cylinder, and controls whether the gas between the reference cylinder and the sample cylinder circulates with each other.
[0027] Technical Theme 2
[0028] The geochemical reaction test based on the above-mentioned triaxial comprehensive simulation test system for displacing coalbed methane includes the following specific steps:
[0029] Step 1: Sample filling
[0030] The particle samples and powder samples were wrapped with gauze and placed in a high-temperature and high-pressure reactor, where some powder samples were dispersed in the high-temperature and high-pressure reactor. The reaction time for samples with a diameter of less than 10 mm was 15 days, and the reaction time for column samples with a diameter of no more than 50 mm and a length of no more than 100 mm was extended to 60 days;
[0031] Step 2: Air tightness check
[0032] Close the fifth valve, the sixth valve, and the fourteenth valve, and open the second valve, the fourth pressure regulating valve, the fourth check valve, and the first valve, so that the argon gas cylinder is compressed and pressurized to the geochemical reaction module through the air compressor and the gas booster pump. If the reading of the first pressure sensor is stable and maintained for a period of time, it means that the geochemical reaction module is airtight;
[0033] Step 3: Conduct geochemical reaction simulation
[0034] Deionized water and coal rock samples were placed in a high-temperature and high-pressure reactor, and the pressure in the high-temperature and high-pressure reactor was reduced to -0.1 MPa using the first vacuum pump. Then, the third pressure regulating valve and the third one-way valve were opened, and pure CO2 was injected into the high-temperature and high-pressure reactor using an air compressor and a gas booster pump. At the same time, a heating device was used to heat the reactor to reach the required temperature. The temperature and pressure were monitored and adjusted every 8 hours to ensure that the system was within ±0.5 MPa and ±0.5°C. On the 1st, 4th, 7th, 10th and 15th day of the experiment, the fourth valve and the fifth valve were opened, and the mixed solution of the powder sample and the extract was taken out from the leaching liquid outlet. On the 15th day, the particle sample was retrieved. The leaching liquid of the powder sample and the particle sample was washed with deionized water several times to prevent mineral recrystallization, and then kept in a vacuum dryer at 50°C for 24 hours.
[0035] Step 4: Clean up the test equipment
[0036] After the test, close the third pressure regulating valve and the third one-way valve, open the fourth valve and the fifth valve to release the gas in the device, disconnect the pipelines and lines, and cool down; take out the rock samples in the high-temperature and high-pressure reactor, and classify and put away the components of the device.
[0037] Technical Theme 3
[0038] The gas adsorption and desorption test based on the above-mentioned triaxial comprehensive simulation test system for displacing coalbed methane includes the following specific steps:
[0039] Step 1: Sample preparation
[0040] Prepare coal samples with a particle size of 0.25 mm to 0.18 mm according to GB / T474, and perform industrial analysis according to GB / T212. Perform equilibrium moisture test on coal samples according to formula (1), accurately weigh the coal samples that have reached equilibrium moisture, and put them into the sample cylinder;
[0041]
[0042] Where: M e is the equilibrium moisture content of the sample, in %;
[0043] G1: air-dried sample mass before equilibrium, in g;
[0044] G2 is the mass of the sample after equilibrium, in g;
[0045] M ad Air-free coal-based moisture content of the sample, in %;
[0046] Step 2: Air tightness test
[0047] Open the thermostatic water bathtub to adjust the temperature so that the temperature of the sample tank and the reference cylinder is stable at the set target reservoir temperature. Close the second valve, the fourteenth valve, the tenth valve, and the thirteenth valve. Open the fourth pressure regulating valve, the fourth check valve, the first valve, and the sixth valve. Compress the argon gas cylinder through the air compressor and the gas booster pump to increase the pressure to the system. The pressure is 1MPa higher than the maximum pressure of the isothermal adsorption experiment. The system collects the pressure data of the second pressure sensor and the third pressure sensor of the reference cylinder and the sample cylinder. If the pressure remains unchanged within 6 hours, the system is considered to be airtight.
[0048] Step 3: Free space volume determination
[0049] Open the second vacuum pump and evacuate the test system for 24 hours; open the fourth pressure regulating valve and the fourth check valve, inject argon into the system, adjust the pressure of the reference cylinder so that the pressure value of the third pressure sensor reaches 2MPa-3MPa, and close the second valve; open the seventh valve, collect a set of data after the pressure is balanced; repeat the above steps twice; repeat the free space volume three times, and the difference between the two values is no more than 1cm 3 ; Calculate the volume of the coal sample according to formula (2), and calculate the volume of the free space in the sample tank according to formula (3);
[0050]
[0051] Where: Vs is the volume of the coal sample, in cubic centimeters;
[0052] p1 equilibrium pressure, in MPa;
[0053] p2 initial pressure of the reference cylinder, in MPa;
[0054] p3 initial pressure of the sample cylinder, in MPa;
[0055] T1 equilibrium temperature, unit is K;
[0056] T2 initial temperature of the reference cylinder, in K;
[0057] T3 initial temperature of sample cylinder, unit is K;
[0058] V1 total system volume in cubic centimeters;
[0059] V2 reference cylinder volume, in cubic centimeters;
[0060] V3 sample cylinder volume, in cubic centimeters;
[0061] The compressibility factor of the gas under Z1 equilibrium conditions;
[0062] Z2 compressibility factor of the initial gas in the reference cylinder;
[0063] Z3: compressibility factor of the initial gas in the sample cylinder;
[0064] V f =V0-V s Formula (3);
[0065] Where: V f The volume of free space is measured in cubic centimeters;
[0066] V0 total volume of the sample cylinder, in cubic centimeters;
[0067] V s The volume of the coal sample in cubic centimeters;
[0068] Step 4: Adsorption and desorption test
[0069] Open the second vacuum pump, evacuate the system, set the highest test pressure to 1.1 times the reservoir pressure, and the highest test balance pressure shall not be less than 8MPa. When the highest test balance pressure is 8MPa, the test pressure points shall be no less than 6; close the twelfth valve and the second vacuum pump, open the first pressure regulating valve and the first check valve, fill the reference cylinder with methane gas, observe that the pressure value of the third pressure sensor is the target pressure, and after the second temperature sensor is stable, start the isothermal adsorption test program to automatically collect the time, pressure, and temperature data in the sample cylinder and the reference cylinder. The adsorption balance time shall not be less than 12h. Repeat the above steps to test each pressure point from low to high until the last pressure point test is completed. Open the third pressure regulating valve and the third check valve, and continuously inject supercritical CO2 into the coal body at a pressure of 10MPa for 12h. Observe that the pressure of the third pressure sensor reaches the target pressure, collect data, open the eighth valve and the ninth valve to collect gas, and calculate the gas adsorption amount as follows (4).
[0070] pV=nZRT Formula (4);
[0071] Where: p is the gas pressure, in MPa;
[0072] V is the volume of the gas in cubic centimeters;
[0073] n is the number of moles of gas, in mol;
[0074] The compressibility factor of the Z gas;
[0075] R is the molar gas constant, in J·mol -l ·K -1 ;
[0076] T is the equilibrium temperature in K;
[0077] Calculate the number of moles of gas in the sample cylinder before equilibrium at each pressure point n1 and the number of moles of gas in the sample cylinder after equilibrium n2, then the number of moles of gas adsorbed by the coal sample n i for:
[0078] n i =n1-n2 Formula (5);
[0079] Where: n i is the number of moles of gas, in mol;
[0080] n1 is the number of moles of gas in the sample cylinder before equilibrium, in mol;
[0081] n2 is the number of moles of gas in the sample cylinder after equilibrium, in mol;
[0082] The total volume V of adsorbed gas at each pressure point i See formula (6):
[0083] V i =n i ×22.4×1000 Formula (6);
[0084] Adsorption volume V at each pressure point 吸附量 See formula (7):
[0085] V 吸附量 =V i / G c Formula (7);
[0086] Where: V 吸附量 is the adsorption amount, in cm 3 ·g -1 ;
[0087] V i is the total volume of adsorbed gas in cubic centimeters;
[0088] G c is the mass of coal sample, in g;
[0089] Step 5: Clean up the test equipment
[0090] After the test, close the third pressure regulating valve and the third one-way valve, open the tenth valve to recycle the gas in the device, disconnect the pipelines and lines, and cool down; take out the coal and rock samples in the sample cylinder, and put the air compressor and gas booster pump of the device in order.
[0091] Technical Theme 4
[0092] The gas adsorption and expansion strain test based on the above-mentioned triaxial comprehensive simulation test system for displacing coalbed methane includes the following specific steps:
[0093] Step 1: Sample preparation
[0094] According to GB / T18668-2002, a cubic sample (3×3×3cm) was prepared. The coal sample was placed in a drying oven and dried at 60°C for 12h. The coal sample was polished with 240-mesh, 600-mesh and 1200-mesh sandpapers, and then polished at both ends with a polishing machine. If there were gaps, coal powder could be used to fill them to ensure a smooth surface of the sample.
[0095] Step 2: Sample installation
[0096] 1) Installation of resistance strain gauge:
[0097] ① Select the location and direction of strain gauge pasting: For cubic samples, three strain gauges are pasted along the parallel surface cleats, parallel end cleats, and perpendicular to the bedding directions respectively;
[0098] ② Pasting of strain gauge: Apply 502 glue evenly on the selected strain gauge pasting position and the back of the strain gauge, fix the strain gauge to the surface of the coal sample with tweezers, press for 5 minutes to ensure that the strain gauge and the coal sample are completely fitted;
[0099] ③ Wire welding: Paste the terminal blocks to both ends of the strain gauge, and use a soldering iron to weld the strain gauge connecting wire and the external guide wire to the terminal blocks. During this process, the solder should be kept flat to prevent the rubber sleeve from being punctured after the confining pressure is loaded;
[0100] ④ Conductivity test: Use a multimeter to test the strain gauge circuit. If the result displayed by the multimeter is consistent with the actual result of the strain gauge, the conductivity is good;
[0101] ⑤ Wire reinforcement: Apply silicone rubber on the wire and install the sample after the silicone rubber solidifies;
[0102] 2) Turn on the triaxial test instrument, place the cubic sample on the right end of the pad, lead the strain gauge wire through the lead slot, and lay a layer of rubber sleeve on both ends of the sample according to the size of the sample to ensure the sealing of the sample during the experiment;
[0103] Step 3: Air tightness check
[0104] According to the Chinese industry standard (NB / T4701-2012), the system is tested for air tightness. The 29th valve is opened, the 2nd valve, the 6th valve, the 18th valve, the 20th valve, and the 22nd valve are closed. The entire gas pipeline and the instrument are evacuated to -0.1MPa using the third vacuum pump and maintained for 30 minutes. If the data of the sixth pressure sensor remains unchanged, the air tightness of the device is good.
[0105] Step 4: CO2 adsorption and expansion strain experiment
[0106] After the air tightness of the device is tested to be good, the device is heated by a large thermostatic box to stabilize the temperature at the preset value of 35°C. The third pressure regulating valve, the third one-way valve and the first valve are opened, and CO2 gas is injected into the system through the air compressor and the gas booster pump until the pressure reaches the preset value. Then, the hydraulic layer is pressurized by the second pressure tracking pump and the third pressure tracking pump to make the confining pressure 12MPa. Then, the valve of the three-axis instrument is closed to ensure the constancy of the gas in the instrument. The micro-strain value is recorded in real time by the resistance strain gauge. The recording frequency is once every 10s. The test is carried out for 12h. After the strain reaches stability, the strain size is calculated using formula (8). After the test is completed, different gas injection pressures or different coal samples are set to repeat the above steps. The sample strain is monitored and recorded using the DH3821 resistance strain gauge. The relationship between the resistance and strain of the strain gauge is shown in formula (8).
[0107]
[0108] Where: ε is strain;
[0109] K is the coefficient;
[0110] ΔR is the resistance difference, unit is Ω;
[0111] R ε is the strain ε is the resistance of the specimen, in Ω;
[0112] R0 is the resistance of the specimen when there is no strain, in Ω.
[0113] Step 5: Clean up the test equipment
[0114] After the test, open the vent valve of the adsorption tank to discharge the gas in the adsorption tank, turn off all power lines, take out the coal samples, and then classify and store them according to regulations;
[0115] Preferably, a spacer block is provided in the sample chamber.
[0116] Preferably, the measurement accuracy of all pressure sensors used in the system is 0.01MPa; the temperature control accuracy of the constant temperature water bath is ±0.1°C; the flow accuracy of the pressure tracking pump is 0.001MPa; the measurement accuracy of the resistance strain gauge is 0.05%±0.1με; and the measurement accuracy of the temperature sensor is 0.1°C.
[0117] Preferably, the detection accuracy of the gas chromatograph can reach 0.1%.
[0118] The working principle and beneficial effects of the present invention are:
[0119] The system provided by the present invention can simulate the coalbed methane mining process under real formation conditions, thereby verifying the feasibility of CO2 displacement coalbed methane technology and providing a scientific basis for practical engineering applications. By real-time monitoring and recording the changes in various parameters during the test, the influence of different parameters on the mining effect can be analyzed, thereby optimizing the mining parameters and improving the mining efficiency and economic benefits of coalbed methane. The use of CO2 displacement coalbed methane technology can achieve underground storage of CO2, thereby reducing greenhouse gas emissions and helping to mitigate global climate change. By optimizing mining parameters and reducing unnecessary mining activities, damage and pollution to the environment can be reduced and the ecological environment can be protected. Among them, the test system can be injected with pure high-pressure gas, high-pressure mixed gas, high-pressure gas and liquid, high-pressure gas and high-pressure humid gas respectively. It can better simulate the actual environment in the formation. There is also a gas collection device at the end of the test instrument, which can collect and analyze the reacted gas. BRIEF DESCRIPTION OF THE DRAWINGS
[0120] The present invention will be further described in detail below in conjunction with the accompanying drawings and specific embodiments.
[0121] Figure 1 This is a schematic diagram of the structure of the triaxial comprehensive simulation test system for displacing coalbed methane according to the present invention.
[0122] Figure 2 It is a schematic diagram of the structure of the geochemical reaction module, adsorption and desorption module, and three-axis displacement module of the present invention.
[0123] In the figure: 1 air source module, 1.1 first pressure regulating valve, 1.2 second pressure regulating valve, 1.3 third pressure regulating valve, 1.4 fourth pressure regulating valve, 1.5 first check valve, 1.6 second check valve, 1.7 third check valve, 1.8 fourth check valve,
[0124] 2 booster module, 2.1 first valve, 2.2 air compressor, 2.3 gas booster pump,
[0125] 3 geochemical reaction module, 3.1 second valve, 3.2 third valve, 3.3 first temperature sensor, 3.4 first pressure sensor, 3.5 deionized water, 3.6 coal rock sample, 3.7 insulation layer, 3.8 heating device, 3.9 fourth valve, 3.10 liquid collecting tank, 3.11 fifth valve, 3.12 first vacuum pump, 3.13 high temperature and high pressure reactor,
[0126] 4 adsorption and desorption module, 4.1 the sixth valve, 4.2 the seventh valve, 4.3 the eighth valve, 4.4 the ninth valve, 4.5 the tenth valve, 4.6 the eleventh valve, 4.7 the twelfth valve, 4.8 the second vacuum pump, 4.9 the thirteenth valve, 4.10 the second temperature sensor, 4.11 the second pressure sensor, 4.12 the third pressure sensor, 4.13 the gas collecting pipe,
[0127] 5 Three-axis displacement module, 5.1 Fourteenth valve, 5.2 Fifteenth valve, 5.3 Third temperature sensor, 5.4 Fourth pressure sensor, 5.5 First high-pressure gas buffer tank, 5.6 Fifth pressure sensor, 5.7 Fourth temperature sensor, 5.8 Second high-pressure gas buffer tank, 5.9 Sixteenth valve, 5.10 Seventeenth valve, 5.11 Eighteenth valve, 5.12 Nineteenth valve, 5.13 Liquid cylinder, 5.14 Twentieth valve, 5.15 First pressure reducing valve, 5.16 Second pressure reducing valve, 5.17 Fifth check valve, 5.18 Twenty-first valve, 5.19 First pressure tracking pump, 5.20 Sixth check valve, 5.21 Hydraulic tank, 5.22 Seventh check valve, 5.23 Second The twelfth valve, 5.24 the twenty-third valve, 5.25 the sixth pressure sensor, 5.26 the third vacuum pump, 5.27 the second pressure tracking pump, 5.28 the seventh pressure sensor, 5.29 the fifth temperature sensor, 5.30 the gasket, 5.31 the rubber sleeve, 5.32 the hydraulic layer, 5.33 the resistance strain gauge, 5.34 the third pressure tracking pump, 5.35 the third pressure reducing valve, 5.36 the twenty-fourth valve, 5.37 the gas-liquid separator, 5.38 the gas flow meter, 5.39 the twenty-fifth valve, 5.40 the gas collecting tank, 5.41 the twenty-sixth valve, 5.42 the drain tank, 5.43 the twenty-seventh valve, 5.44 the gas sampling bottle, 5.45 the twenty-eighth valve, 5.46 the twenty-ninth valve. DETAILED DESCRIPTION
[0128] The following will be combined with the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0129] like Figure 1 As shown, a triaxial comprehensive simulation test system for displacing coalbed methane comprises:
[0130] Gas source module, boosting module, geochemical reaction module, adsorption and desorption module, three-axis displacement module and information control module.
[0131] The gas source module is connected to the boosting module to provide gas for the overall system; the gas source module includes parallel methane, nitrogen, carbon dioxide and argon gas cylinders; the methane gas cylinder is connected in series with the first pressure regulating valve 1.1 and the first one-way valve 1.5, the nitrogen gas cylinder is connected in series with the second pressure regulating valve 1.2 and the second one-way valve 1.6, the carbon dioxide gas cylinder is connected in series with the third pressure regulating valve 1.3 and the third one-way valve 1.7, and the argon gas cylinder is connected in series with the fourth pressure regulating valve 1.4 and the fourth one-way valve 1.8; the first one-way valve 1.5, the second one-way valve 1.6, the third one-way valve 1.7 and the fourth one-way valve 1.8 are connected in series to the gas booster pump 2.3.
[0132] The booster module is connected to the geochemical reaction module, the adsorption and desorption module and the triaxial displacement module respectively, and is used to provide high-pressure test gas to the geochemical reaction module, the adsorption and desorption module and the triaxial displacement module; the booster module includes an air compressor 2.2, a first valve 2.1 and a gas booster pump 2.3 which are connected in sequence; the gas booster pump 2.3 is connected to the geochemical reaction module, the adsorption and desorption module and the triaxial displacement module respectively, specifically, the gas booster pump 2.3 is connected to the second valve 3.1 of the geochemical reaction module, the sixth valve 4.1 of the adsorption and desorption module, the fourteenth valve 5.1 and the fifteenth valve 5.2 of the triaxial displacement module.
[0133] The geochemical reaction module is used for conducting geochemical reaction experiments during the process of deep coal seam gas injection to displace coal seam gas; the geochemical reaction module includes: a high-temperature and high-pressure reactor 3.13, a fourth valve 3.9, a liquid collecting tank 3.10 and a fifth valve 3.11 connected in sequence, a second valve 3.1 is arranged on the pipeline between the high-temperature and high-pressure reactor 3.13 and the booster module; a second valve 3.1 is arranged on the pipeline between the high-temperature and high-pressure reactor 3.13 and the gas booster pump 2.3; a third valve 3.2 is arranged on the pipeline between the high-temperature and high-pressure reactor 3.13 and the first vacuum pump 3.12; the third valve 3.2 controls the vacuum The flow rate and direction of the pumped air are prevented from backflowing, ensuring that the gas in the vacuum pump cannot flow out through the valve, thereby achieving effective exhaust; the first vacuum pump 3.12 evacuates the air in the entire test device, so that the test device reaches a vacuum state, ensuring the accuracy and reliability of the test data; the high-temperature and high-pressure reactor 3.13 is provided with a first pressure sensor 3.4 and a first temperature sensor 3.3, which are respectively used to detect the pressure and temperature inside the high-temperature and high-pressure reactor 3.13; the high-temperature and high-pressure reactor 3.13 is provided with a heating device 3.8, and the outer layer of the heating device 3.8 is also provided with a thermal insulation layer 3.7.
[0134] The adsorption and desorption module is used for conducting gas adsorption and desorption tests during the process of deep coal seam gas injection to displace coal seam gas; the adsorption and desorption module comprises a reference cylinder, a sample cylinder, an eighth valve 4.3, a ninth valve 4.4, an eleventh valve 4.6, a gas collecting pipe 4.13, and a thirteenth valve 4.9 connected in sequence; the gas collecting pipe 4.13 is mainly used to collect and measure the gas generated during the test, and the thirteenth valve 4.9 maintains the pressure in the gas collecting pipe 4.13 to maintain the stability of the test conditions; the sixth valve 4.1 is arranged on the pipeline between the reference cylinder and the booster module, and the pipeline between the reference cylinder and the gas booster pump 2.3 is provided with a valve 4.6. A sixth valve 4.1 is arranged on the pipeline between the eighth valve 4.3 and the ninth valve 4.4; a tenth valve 4.5 is arranged on the pipeline between the eighth valve 4.3 and the ninth valve 4.4, and the tenth valve 4.5 controls the connection with the atmosphere, and when necessary, is used for the rapid discharge of the gas in the entire test device to deal with possible dangers; a twelfth valve 4.7 is arranged on the pipeline between the ninth valve 4.4 and the eleventh valve 4.6, and the twelfth valve 4.7 is connected to the second vacuum pump 4.8, and the twelfth valve 4.7 controls the flow rate and direction of the exhaust air of the vacuum pump to prevent the gas from flowing back, and ensure that the gas in the vacuum pump cannot flow out through the valve, so as to achieve effective exhaust. The second vacuum pump 4.8 evacuates the air in the entire test device, so that the test device can reach a vacuum state as much as possible, ensuring the accuracy and reliability of the test data; the reference cylinder and the sample cylinder are respectively provided with a second pressure sensor 4.11 and a third pressure sensor 4.12, which are used to detect the pressure of the reference cylinder and the sample cylinder respectively; the reference cylinder and the sample cylinder are placed in a constant temperature water bath, and a second temperature sensor 4.10 is provided on the constant temperature water bath to detect the temperature of the constant temperature water bath. The constant temperature water bath ensures that the experiment is carried out under constant temperature conditions through its precise temperature control function, which helps to ensure the reliability and repeatability of the experimental results, thereby improving the accuracy and efficiency of the experiment. The reference cylinder is used to calibrate the volume of the sample cylinder to obtain accurate test data; a high-pressure stainless steel tank is used as the reference cylinder to ensure that the cylinder body still has good sealing under the large temperature difference range and ultra-high pressure conditions required by the test; the seventh valve 4.2 connects the reference cylinder and the sample cylinder, and controls whether the gas between the reference cylinder and the sample cylinder flows with each other.
[0135] The triaxial displacement module is used for gas adsorption and expansion strain test or coal permeability test and gas component analysis in the process of gas injection to displace coalbed methane in deep coal seams; the triaxial displacement module includes a triaxial displacement device, a gas supply device, a liquid supply device, a vacuum device and a gas-liquid collection device; one end of the triaxial displacement device is respectively connected to the gas supply device, the liquid supply device and the vacuum device, and the other end is connected to the gas-liquid collection device. The triaxial displacement device, the gas supply device, the liquid supply device and the gas-liquid collection device (except the gas chromatograph, the third vacuum pump 5.26, the second pressure tracking pump 5.27 and the third pressure tracking pump 5.34) are all placed in a large constant temperature box, which can maintain the temperature stability during the test, thereby ensuring the accuracy and reliability of the test results;
[0136] Among them, the three-axis displacement device is used to simulate the high temperature, high pressure and sealed environment of the formation; the three-axis displacement device includes a twenty-third valve 5.24, a second pressure tracking pump 5.27, a sample chamber, a hydraulic layer 5.32, a third pressure tracking pump 5.34, and a resistance strain gauge 5.33; the second pressure tracking pump 5.27 and the third pressure tracking pump 5.34 are connected to the three-axis instrument device through pipelines, and the three-axis instrument device is provided with a seventh pressure sensor 5.28 and a fifth temperature sensor 5.29; a cushion block 5.30 is arranged in the sample chamber, and a plurality of strain gauges are arranged on the sample, and the strain gauge leads are connected to the resistance strain gauge 5.33 electrical signal, and the second pressure tracking pump 5.27 and the third pressure tracking pump 5.34 respectively and independently control the pressure in the axial direction and the confining pressure direction , so as to more accurately simulate the complex stress state of the real underground environment; the seventh pressure sensor 5.28 and the fifth temperature sensor 5.29 detect the pressure and temperature of the sample chamber in real time; the twenty-third valve 5.24 is connected to the first pressure reducing valve 5.15 of the gas supply device, the twenty-first valve 5.18, the twenty-second valve 5.23 of the liquid supply device and the twenty-ninth valve 5.46 of the vacuum device, and the outlet of the sample chamber is connected to the third pressure reducing valve 5.35 of the gas-liquid collection device through a pipeline; the twenty-third valve 5.24 is the main valve for controlling the gas entering the three-axis displacement device, and the sixth pressure sensor 5.25 is set on the connecting pipeline between the twenty-third valve 5.24 and the gas supply device and the liquid supply device to detect the pressure of the gas entering the three-axis displacement device. The sample load and fluid pressure in the device are controlled by different high-precision pressure tracking pumps, which can provide a maximum load of 20MPa in three directions of the sample (small clamps may achieve higher loads), and the maximum displacement liquid pressure and maximum displacement gas pressure can reach 15MPa. The static resistance strain gauge used to detect the strain during the displacement of the sample has 8 optional parameter channels and a measurement accuracy of 0.05% ± 0.1με. The experimental system is equipped with a high-precision pressure sensor and a temperature control system. The pressure sensor has an accuracy range of 0.01MPa. The large gripper has its own integrated temperature control function, and the temperature of the small gripper system is provided by a constant temperature box with an accuracy of up to 0.1℃.
[0137] The gas supply device is used to inject test gas into the three-axis displacement device and can adjust the pressure in the three-axis displacement device; the gas supply device includes a first high-pressure gas buffer tank 5.5 and a second high-pressure gas buffer tank 5.8; the first high-pressure gas buffer tank 5.5 is connected to the sixteenth valve 5.9 and the first pressure reducing valve 5.15 in sequence, and the second high-pressure gas buffer tank 5.8 is connected to the seventeenth valve 5.10, the second pressure reducing valve 5.16, the fifth check valve 5.17, and the twenty-first valve 5.18 in sequence, wherein the seventeenth valve 5.10 and the second pressure reducing valve 5.16 are connected in parallel to the branch eighteenth valve 5 .11, the nineteenth valve 5.12, the liquid cylinder 5.13 and the twentieth valve 5.14, the liquid cylinder 5.13 is used to provide humidified gas to the three-axis displacement device; the fourteenth valve 5.1 is arranged on the pipeline between the first high-pressure gas buffer tank 5.5 and the boosting module, and the fifteenth valve 5.2 is arranged on the pipeline between the second high-pressure gas buffer tank 5.8 and the boosting module. The fourteenth valve 5.1 and the fifteenth valve 5.2 control the gas flow between the three-axis displacement module and the boosting module, and the fourteenth valve 5.1 and the fifteenth valve 5.2 can control the injection of different required gases into the three-axis displacement device. The fourteenth valve 5.1 and the fifteenth valve 5.2 are connected to the first high-pressure gas buffer tank 5.5 and the second high-pressure gas buffer tank 5.8 respectively. Their function is to store gas and adjust pressure to smoothly release compressed air during the transmission of the high-pressure gas pipeline, thereby suppressing the pressure fluctuation of the gas. This helps to protect the equipment carried by the pipeline from the impact force caused by the change of gas pressure and ensure the safe operation of the equipment. The first high-pressure gas buffer tank 5.5 is provided with a third temperature sensor 5.3 and a fourth pressure sensor 5.4, and the second high-pressure gas buffer tank 5.8 is provided with a fifth pressure sensor 5.6 and a fourth temperature sensor 5.7 to detect the temperature and pressure in the tank.
[0138] The liquid supply device is used to inject the test liquid into the three-axis displacement device and can adjust the pressure in the three-axis displacement device; the liquid supply device includes a first pressure tracking pump 5.19, a sixth one-way valve 5.20, a hydraulic tank 5.21, a seventh one-way valve 5.22 and a twenty-second valve 5.23 connected in sequence to provide liquid to the test system.
[0139] The vacuum pumping device is used to exhaust the gas in the three-axis displacement device; the vacuum pumping device includes a third vacuum pump 5.26 and a twenty-ninth valve 5.46 connected in sequence. The third vacuum pump 5.26 and the twenty-ninth valve 5.46 are used to remove the gas in the test air pipe to prevent external gas from interfering with the experimental results.
[0140] The gas-liquid collecting device is used to collect liquid and gas during and after the test. The gas-liquid collecting device includes a third pressure reducing valve 5.35, a twenty-fourth valve 5.36, a gas flow meter 5.38, a twenty-fifth valve 5.39, a gas collecting tank 5.40, a twenty-seventh valve 5.43, a gas sampling bottle 5.44, a twenty-eighth valve 5.45, and a gas chromatograph, which are connected in sequence; a gas-liquid separator 5.37 is arranged on the pipeline between the twenty-fourth valve 5.36 and the gas flow meter 5.38, and the gas-liquid separator 5.37 performs gas-liquid separation, and the separated gas enters the gas chromatograph for gas component detection. During this process, the gas flow meter 5.38 monitors the flow rate of the gas in the pipeline, and the obtained data is used for later data processing to obtain the test results of the relevant test. A twenty-sixth valve 5.41 is provided at the lower part of the gas collecting tank 5.40, through which the liquid is discharged into the liquid draining tank 5.42, and the liquid draining tank 5.42 collects the discharged liquid; a gas sampling bottle 5.44 is used to collect the gas after the experiment, and can be used to detect the gas composition; a twenty-eighth valve 5.45 is a switch for controlling the gas to be detected to enter the gas chromatograph. The gas chromatograph used to detect the gas components in the displacement process can detect gas types including CH4, N2 and CO2, and the detection accuracy can reach 0.1%.
[0141] like Figure 2 As shown, the structures of the geochemical reaction module, adsorption and desorption module, and three-axis displacement module can be seen.
[0142] The information control module is used to control the test process, display and store data, wherein the information control module is electrically connected to each electrical component and sensor.
[0143] The entire operation control system is in a separate room. The sample room, reference cylinder and air compressor can be observed in the control room through a camera and can be isolated from the test area to ensure that personnel are operating in a safe area. The present invention adopts an operation procedure of heating first and then pressurizing. The required pressure value is set in the control system. When the pressure value reaches the target value, the pressurization system automatically stops, so that the pressurization process can be controlled to ensure the safety of the test. Specific embodiments
[0145] 1. ScCO2-H2O-coal / rock geochemical reaction experiment
[0146] 1. Sample canning: Considering the mass loss of the sample during the test, the volume limitation of the reactor and the error caused by sampling, 100g of granular sample and 100g of powder sample are used for geochemical reaction test, and the granular sample and 80g of powder sample are wrapped with gauze and placed in the high temperature and high pressure reactor 3.13, and 20g of powder sample is dispersed in the high temperature and high pressure reactor 3.13. The ScCO2-H2O reaction time of samples with a diameter less than 10mm is shorter, which is 15 days. If the sample is cylindrical with a diameter not exceeding 50mm and a length not exceeding 100mm, the reaction time of larger column samples is extended to 60 days or as long as possible under laboratory conditions.
[0147] 2. Air tightness check: close the fifth valve 3.11, the sixth valve 4.1, and the fourteenth valve 5.1, and open the second valve 3.1, the fourth pressure regulating valve 1.4, the fourth non-return valve 1.8, and the first valve 2.1, so that the argon gas cylinder is compressed and pressurized to the geochemical reaction module through the air compressor 2.2 and the gas booster pump 2.3. If the reading of the first pressure sensor 3.4 is stable and maintained for a period of time, it means that the geochemical reaction module is in good air tightness.
[0148] 3. Perform geochemical reaction simulation: Deionized water 3.5 (to avoid the influence of unnecessary chemicals, scale and other substances in the water on the experimental results, the use of deionized water can make the parameter results closer to the ideal data) and coal rock sample 3.6 are placed in the high temperature and high pressure reactor 3.13. The pressure in the high temperature and high pressure reactor 3.13 is reduced to -0.1MPa using the first vacuum pump 3.12 to prevent air interference. Then open the third pressure regulating valve 1.3 and the third check valve 1.7, and use the air compressor 2.2 and the gas booster pump 2.3 to inject pure CO2 (99.999%) into the high temperature and high pressure reactor 3.13. At the same time, use the heating device 3.8 to heat to reach the required temperature. The insulation layer 3.7 effectively reduces the heat loss during the experiment and ensures that the inside of the experimental container is maintained at a constant temperature. Monitor and adjust the temperature and pressure every 8 hours to ensure that the system is within ±0.5MPa and ±0.5℃. On the 1st, 4th, 7th, 10th and 15th days of the experiment, the fourth valve 3.9 and the fifth valve 3.11 were opened, and 10 ml of the mixed solution of the powder sample and the leachate was taken out from the leaching liquid outlet, and the particle sample was taken back on the 15th day. The leaching liquid of the powder sample and the particle sample was washed with deionized water several times to prevent mineral recrystallization, and then kept in a vacuum dryer at 50°C for 24 hours.
[0149] 4. Cleaning of the test device: After the test, close the third pressure regulating valve 1.3 and the third non-return valve 1.7, open the fourth valve 3.9 and the fifth valve 3.11 to release the gas in the device, disconnect the pipelines and lines, and cool down; take out the rock sample in the high-temperature and high-pressure reactor 3.13, and classify and put away the components of the device.
[0150] 2. CO2 adsorption and desorption experiment
[0151] 1. Sample preparation: Prepare 200g of coal sample with a particle size of 0.25mm-0.18mm (60 mesh-80 mesh) according to GB / T 474, and perform industrial analysis according to GB / T 212. Perform equilibrium moisture test on the coal sample as shown in formula (1);
[0152]
[0153] Where: M e is the equilibrium moisture content of the sample, %;
[0154] G1 is the mass of the sample on an air-dried basis before equilibrium, in grams (g);
[0155] G2 is the mass of the sample after equilibrium, in grams (g);
[0156] M ad Air-free coal-based moisture content of the sample, %.
[0157] Accurately weigh the coal sample that has reached equilibrium moisture content and quickly place it into the sample cylinder.
[0158] 2. Air tightness test: Open the thermostatic water bathtub to adjust the temperature so that the temperature of the sample tank and the reference cylinder is stable at the set target reservoir temperature, close the second valve 3.1, the fourteenth valve 5.1, the tenth valve 4.5, and the thirteenth valve 4.9, open the fourth pressure regulating valve 1.4, the fourth non-return valve 1.8, the first valve 2.1, and the sixth valve 4.1, so that the argon gas cylinder is compressed and pressurized to the system through the air compressor 2.2 and the gas booster pump 2.3. The pressure is higher than the maximum pressure of the isothermal adsorption experiment by 1MPa. The system collects the pressure data of the second pressure sensor 4.11 and the third pressure sensor 4.12 of the reference cylinder and the sample cylinder. If the pressure remains unchanged within 6 hours, the system is considered to be airtight.
[0159] 3. Free space volume measurement: Open the second vacuum pump 4.8 and evacuate the test system for 24 hours; open the fourth pressure regulating valve 1.4 and the fourth non-return valve 1.8, inject argon into the system, adjust the pressure of the reference cylinder so that the pressure value of the third pressure sensor 4.12 reaches 2MPa-3MPa, close the second valve 3.1; open the seventh valve 4.2, collect a set of data after the pressure is balanced; repeat the above steps twice; repeat the free space volume measurement three times, and the difference between the two values is no more than 1cm 3 ; Calculate the volume of the coal sample according to formula (2), and calculate the volume of the free space in the sample tank according to formula (3);
[0160]
[0161] Where: Vs is the volume of the coal sample, in cubic centimeters (cm 3 );
[0162] p1 is the pressure after equilibrium, in MPa;
[0163] p2 refers to the initial pressure of the reference cylinder, in megapascals (MPa);
[0164] p3 Initial pressure of the sample cylinder, in megapascals (MPa);
[0165] T1 is the temperature after equilibrium, in K;
[0166] T2 is the initial temperature of the reference cylinder, in Kelvin;
[0167] T3: Initial temperature of sample cylinder, in Kelvin;
[0168] V1 Total volume of the system, in cubic centimeters (cm 3 );
[0169] V2 reference cylinder volume, in cubic centimeters (cm 3 );
[0170] V3 Sample cylinder volume, in cubic centimeters (cm 3 );
[0171] The compressibility factor of the gas under Z1 equilibrium conditions;
[0172] Z2 compressibility factor of the initial gas in the reference cylinder;
[0173] Z3: The compressibility factor of the initial gas in the sample cylinder.
[0174] Vf=V0-V s Formula (3);
[0175] Where: V f The volume of free space is in cubic centimeters (cm3 );
[0176] V0 Total volume of the sample cylinder, in cubic centimeters (cm 3 );
[0177] V s The volume of the coal sample is in cubic centimeters (cm 3 ).
[0178] 4. Adsorption and desorption test: Open the second vacuum pump 4.8 and evacuate the system. The highest test pressure is usually set to 1.1 times the reservoir pressure, and the highest test balance pressure shall not be less than 8MPa. When the highest test balance pressure is 8MPa, there are no less than 6 test pressure points; the test pressure is set to 2MPa~10MPa in this test, increasing by 1MPa each time, for a total of 9 test pressure points. Close the twelfth valve 4.7 and the second vacuum pump 4.8, open the first pressure regulating valve 1.1 and the first check valve 1.5, fill the reference cylinder with methane gas, observe that the pressure value of the third pressure sensor 4.12 is the target pressure, and after the second temperature sensor 4.10 is stable, start the isothermal adsorption test program to automatically collect the time, pressure, temperature and other related data in the sample cylinder and the reference cylinder. Determine the adsorption balance time according to the actual conditions such as the degree of metamorphism of the coal sample and the sample quality, but it shall not be less than 12h. Repeat the above steps to test each pressure point from low to high until the last pressure point test is completed. Open the third pressure regulating valve 1.3 and the third one-way valve 1.7, and continuously inject supercritical CO2 into the coal body at a pressure of 10 MPa for 12 hours. Observe that the pressure of the third pressure sensor 4.12 reaches the target pressure and collect data. Open the eighth valve 4.3 and the ninth valve 4.4 to collect gas. The gas adsorption amount is calculated as follows (4);
[0179] p V =n ZRT Formula (4);
[0180] Where: p is the gas pressure, the unit is megapascal (MPa);
[0181] V is the volume of the gas in cubic centimeters (cm 3 );
[0182] n is the number of moles of gas, in mol;
[0183] The compressibility factor of the Z gas;
[0184] R is the molar gas constant, in joules per mole (J·mol -l ·K -1 );
[0185] T is the equilibrium temperature, in Kelvin.
[0186] Calculate the number of moles of gas in the sample cylinder before equilibrium at each pressure point n1 and the number of moles of gas in the sample cylinder after equilibrium n2, then the number of moles of gas adsorbed by the coal sample n i for:
[0187] n i =n1-n2 Formula (5);
[0188] Where: n i is the number of moles of gas, in mol;
[0189] n1 is the number of moles of gas in the sample cylinder before equilibrium, in mol;
[0190] n2 is the number of moles of gas in the sample cylinder after equilibrium, in mol.
[0191] The total volume V of adsorbed gas at each pressure point i See formula (6):
[0192] V i =n i ×22.4×1000 Formula (6);
[0193] Adsorption volume V at each pressure point 吸附量 See formula (7):
[0194] V 吸附量 =V i / G c Formula (7);
[0195] Where: V 吸附量 is the adsorption capacity, in cubic centimeters per gram (cm 3 ·g -1 );
[0196] V i is the total volume of adsorbed gas in cubic centimeters (cm 3 );
[0197] G c is the mass of coal sample in grams (g).
[0198] 5. Cleaning of the test device: After the test, close the third pressure regulating valve 1.3 and the third non-return valve 1.7, open the tenth valve 4.5 to recover the gas in the device, disconnect the pipelines and lines, and cool down; take out the rock sample in the sample cylinder, and put away the air compressor 2.2 and gas booster pump 2.3 of the device.
[0199] 3. CO2 adsorption and expansion strain experiment
[0200] 1. Sample preparation: According to GB / T18668-2002, a cubic sample of a certain size (3×3×3cm) was prepared. The coal sample was placed in a drying oven and dried at 60°C for 12 hours to avoid the influence of moisture on the experimental results. After the preparation of the coal sample, due to the heterogeneity of the coal rock, its surface may be rough or have gaps. The installation of the resistance strain gauge has strict requirements on the sample surface. If it is not treated, it is very easy to cause the breakage of the lead, the fall-off of the strain gauge or the crushing of the rubber sleeve after the confining pressure is loaded. For this reason, the sample was polished with 240 mesh, 600 mesh and 1200 mesh sandpaper before the experiment, and then polished with a polishing machine. If there is a gap, it can be filled with coal powder to ensure that the sample surface is smooth to meet the experimental requirements.
[0201] 2. Sample installation:
[0202] 1) Installation of resistance strain gauge:
[0203] ① Select the location and direction of strain gauge pasting. The pasting direction of strain gauge is based on the experimental requirements. For cubic samples, three strain gauges are pasted along the parallel face cleat, parallel end cleat and perpendicular bedding directions respectively.
[0204] ② Pasting of strain gauges. Apply 502 glue evenly on the selected strain gauge pasting position and the back of the strain gauge, fix the strain gauge to the surface of the coal sample with tweezers, and press evenly for 5 minutes to ensure that the strain gauge and the coal sample are completely fitted.
[0205] ③ Welding of wires. Paste the terminal blocks to both ends of the strain gauge, and use a soldering iron to weld the strain gauge connecting wires and external guide wires to the terminal blocks. During this process, the solder should be kept smooth to prevent the rubber sleeve from being punctured after the confining pressure is loaded.
[0206] ④ Conductivity test: Use a multimeter to test the strain gauge circuit. The strain gauge used in this experiment is a 120 ohm resistance strain gauge. If the multimeter shows 120 ohms, the conductivity is good.
[0207] ⑤ Reinforcement of the wire. Since the coal sample is very likely to squeeze the wire during installation, resulting in test failure, the wire must be reinforced. Apply silicone rubber on the wire and install the sample after the silicone rubber solidifies.
[0208] 2) Open the triaxial test instrument, place the cubic sample on the right end of the pad 5.30, and lead the strain gauge wire through the lead slot. The pad 5.30 can provide stable support for the sample or equipment in the experiment to prevent movement or tilt during adsorption and expansion, thereby ensuring the reliability of the experimental results. According to the size of the sample, a layer of rubber sleeve 5.31 is laid on both ends of the outer periphery of the sample to ensure the sealing of the sample during the experiment. When CO2 gas contacts the coal sample, the rubber sleeve 5.31 can effectively prevent gas leakage and ensure the accuracy and repeatability of the experiment. The existence of the rubber sleeve 5.31 can protect the sample from the extreme conditions of high pressure or high temperature environment that may be involved in the CO2 adsorption and expansion strain experiment.
[0209] 3. Air tightness check: Perform air tightness test on the system according to the Chinese industry standard (NB / T 47013.8-2012). Open the 29th valve 5.46, close the 2nd valve 3.1, the 6th valve 4.1, the 18th valve 5.11, the 20th valve 5.14, and the 22nd valve 5.23, and use the 3rd vacuum pump 5.26 to evacuate the entire gas pipeline and the instrument to -0.1MPa, and maintain it for 30 minutes. If the data of the 6th pressure sensor 5.25 remains unchanged for a long time, the air tightness of the device is good.
[0210] 4. CO2 adsorption and expansion strain experiment: After the air tightness of the device is tested to be good, the device is heated by a large thermostat to stabilize the temperature at the preset value of 35°C, the third pressure regulating valve 1.3, the third one-way valve 1.7, and the first valve 2.1 are opened, and CO2 gas is injected into the system through the air compressor 2.2 and the gas booster pump 2.3 until the pressure reaches the preset value (1, 2, 3, 4, 5, 6, 7, 8, 9, 10MPa), and then the hydraulic layer 5.32 is pressurized by the second pressure tracking pump 5.27 and the third pressure tracking pump 5.34 to make the confining pressure 12MPa. Then, the constant gas in the instrument is ensured, and the micro-strain value is recorded in real time by the resistance strain gauge 5.33, with a recording frequency of once every 10s, and the test is carried out for 12h. After the strain reaches stability, the strain size is calculated using formula (8). After the test is completed, set different gas injection pressures or different coal samples and repeat the above steps.
[0211] The DH3821 resistance strain gauge is used to monitor and record the sample strain. The principle of using strain gauges to measure coal deformation is the resistance strain effect of metals. The relationship between the resistance and strain of the strain gauge is shown in formula (8):
[0212]
[0213] Where: ε is strain;
[0214] K is the coefficient;
[0215] ΔR is the resistance difference, Ω;
[0216] R ε is the strain ε is the resistance of the specimen, Ω;
[0217] R0 is the resistance of the specimen when there is no strain, Ω.
[0218] 5. Cleaning of the test device: After the test, open the vent valve of the adsorption tank and slowly discharge the gas in the adsorption tank. Turn off all power lines, take out the coal samples, and then classify and store them according to regulations.
[0219] The above are only preferred embodiments of the present invention and are not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A triaxial comprehensive simulation test system for displacing coalbed methane, characterized in that: include: A gas source module (1) is connected to the booster module (2) and is used to provide gas for the entire system; The booster module (2) is respectively connected to the geochemical reaction module (3), the adsorption and desorption module (4) and the three-axis displacement module (5) to provide high-pressure test gas; A geochemical reaction module (3) is used to conduct geochemical reaction experiments during the process of displacing coalbed methane by gas injection in deep coal seams; An adsorption and desorption module (4) is used to conduct a gas adsorption and desorption test in the process of displacing coalbed methane by gas injection in deep coal seams; A three-axis displacement module (5) comprises a three-axis displacement device, a gas supply device, a liquid supply device, a vacuum device and a gas-liquid collecting device; one end of the three-axis displacement device is respectively connected to the gas supply device, the liquid supply device and the vacuum device, and the other end is connected to the gas-liquid collecting device; The triaxial displacement device comprises a twenty-third valve (5.24), a second pressure tracking pump (5.27), a sample chamber, a hydraulic layer (5.32), a third pressure tracking pump (5.34), and a resistance strain gauge (5.33); the second pressure tracking pump (5.27) and the third pressure tracking pump (5.34) are connected to the triaxial instrument device through pipelines, and the triaxial instrument device is provided with a seventh pressure sensor (5.28) and a fifth temperature sensor (5.29); the twenty-third valve (5.24) is connected to the seventh pressure sensor (5.28) and the fifth temperature sensor (5.29) of the gas supply device. A pressure reducing valve (5.15), a twenty-first valve (5.18), a twenty-second valve (5.23) of the liquid supply device and a twenty-ninth valve (5.46) of the vacuum pumping device are connected, and the outlet of the sample chamber is connected to a third pressure reducing valve (5.35) of the gas-liquid collecting device through a pipeline; a sixth pressure sensor (5.25) is arranged on the connecting pipeline between the twenty-third valve (5.24) and the gas supply device and the liquid supply device; a plurality of strain gauges are arranged on the sample, and the strain gauge leads are connected to the electrical signals of the resistance strain gauge (5.33); The gas supply device comprises a first high-pressure gas buffer tank (5.5) and a second high-pressure gas buffer tank (5.8); the first high-pressure gas buffer tank (5.5) is connected to a sixteenth valve (5.9) and a first pressure reducing valve (5.15) in sequence, and the second high-pressure gas buffer tank (5.8) is connected to a seventeenth valve (5.10), a second pressure reducing valve (5.16), a fifth check valve (5.17), and a twenty-first valve (5.18) in sequence, wherein the seventeenth valve (5.10) and the second pressure reducing valve (5.16) are connected in parallel to a branch line of an eighteenth valve (5.11), a nineteenth valve (5.12), and a second check valve (5.13). 5.12), liquid cylinder (5.13), twentieth valve (5.14); a fourteenth valve (5.1) is arranged on the pipeline between the first high-pressure gas buffer tank (5.5) and the boosting module (2), and a fifteenth valve (5.2) is arranged on the pipeline between the second high-pressure gas buffer tank (5.8) and the boosting module (2); a third temperature sensor (5.3) and a fourth pressure sensor (5.4) are arranged in the first high-pressure gas buffer tank (5.5), and a fifth pressure sensor (5.6) and a fourth temperature sensor (5.7) are arranged in the second high-pressure gas buffer tank (5.8); A liquid supply device, comprising a first pressure tracking pump (5.19), a sixth one-way valve (5.20), a hydraulic tank (5.21), a seventh one-way valve (5.22) and a twenty-second valve (5.23) connected in sequence; A vacuum device, used to exhaust the gas in the three-axis displacement device; Gas-liquid collection device, used to collect liquid and gas during and after the test; The information control module is used to control the test process, display and store data.
2. A triaxial comprehensive simulation test system for displacing coalbed methane according to claim 1, characterized in that: The gas source module (1) comprises methane, nitrogen, carbon dioxide and argon gas cylinders connected in parallel; wherein the methane gas cylinder is connected in series with a first pressure regulating valve (1.1) and a first one-way valve (1.5); the nitrogen gas cylinder is connected in series with a second pressure regulating valve (1.2) and a second one-way valve (1.6); the carbon dioxide gas cylinder is connected in series with a third pressure regulating valve (1.3) and a third one-way valve (1.7); and the argon gas cylinder is connected in series with a fourth pressure regulating valve (1.4) and a fourth one-way valve (1.8); and the first one-way valve (1.5), the second one-way valve (1.6), the third one-way valve (1.7) and the fourth one-way valve (1.8) are connected in parallel with the gas booster pump (2.3) of the booster module (2).
3. A triaxial comprehensive simulation test system for displacing coalbed methane according to claim 1, characterized in that: The booster module (2) comprises an air compressor (2.2), a first valve (2.1) and a gas booster pump (2.3) which are connected in sequence, and the gas booster pump (2.3) is respectively connected to the fourteenth valve (5.1) and the fifteenth valve (5.2) of the three-axis displacement module (5).
4. A triaxial comprehensive simulation test system for displacing coalbed methane according to claim 1, characterized in that: The vacuum pumping device comprises a third vacuum pump (5.26) and a twenty-ninth valve (5.46) which are connected in sequence.
5. The triaxial comprehensive simulation test system for displacing coalbed methane according to claim 1 is characterized in that: The gas-liquid collecting device comprises a third pressure reducing valve (5.35), a twenty-fourth valve (5.36), a gas flow meter (5.38), a twenty-fifth valve (5.39), a gas collecting tank (5.40), a twenty-seventh valve (5.43), a gas sampling bottle (5.44), a twenty-eighth valve (5.45), and a gas chromatograph which are connected in sequence; a gas-liquid separator (5.37) is arranged on the pipeline between the twenty-fourth valve (5.36) and the gas flow meter (5.38); a twenty-sixth valve (5.41) is arranged at the lower part of the gas collecting tank (5.40), and the twenty-sixth valve (5.41) is connected to a liquid drain trough (5.42).
6. A triaxial comprehensive simulation test system for displacing coalbed methane according to claim 1, characterized in that: The geochemical reaction module (3) comprises: a high-temperature and high-pressure reactor (3.13), a fourth valve (3.9), a liquid collecting tank (3.10) and a fifth valve (3.11) connected in sequence; a second valve (3.1) is arranged on the pipeline between the high-temperature and high-pressure reactor (3.13) and the booster module (2); a second valve (3.1) is arranged on the pipeline between the high-temperature and high-pressure reactor (3.13) and the gas booster pump (2.3); a third valve (3.2) is arranged on the pipeline between the high-temperature and high-pressure reactor (3.13) and the first vacuum pump (3.12); wherein the high-temperature and high-pressure reactor (3.13) is provided with a first pressure sensor (3.4) and a first temperature sensor (3.3); a heating device (3.8) is arranged inside the high-temperature and high-pressure reactor ((3.13)), and an outer layer of the heating device (3.8) is also provided with a heat-insulating layer (3.7).
7. The triaxial comprehensive simulation test system for displacing coalbed methane according to claim 1 is characterized in that: The adsorption and desorption module (4) comprises a reference cylinder, a sample cylinder, an eighth valve (4.3), a ninth valve (4.4), an eleventh valve (4.6), a gas collecting pipe (4.13), and a thirteenth valve (4.9) which are connected in sequence; a sixth valve (4.1) is arranged on the pipeline between the reference cylinder and the boosting module (2), and a sixth valve (4.1) is arranged on the pipeline between the reference cylinder and the gas boosting pump (2.3); a tenth valve (4.5) is arranged on the pipeline between the eighth valve (4.3) and the ninth valve (4.4), and the tenth valve (4.5) controls the connection with the atmosphere; the ninth valve A twelfth valve (4.7) is arranged on the pipeline between the door (4.4) and the eleventh valve (4.6), and the twelfth valve (4.7) is connected to a second vacuum pump (4.8); a second pressure sensor (4.11) and a third pressure sensor (4.12) are arranged on the reference cylinder and the sample cylinder, respectively, for detecting the pressure of the reference cylinder and the sample cylinder, respectively; the reference cylinder and the sample cylinder are placed in a constant temperature water bath, and a second temperature sensor (4.10) is arranged on the constant temperature water bath; a seventh valve (4.2) connects the reference cylinder and the sample cylinder, and controls whether the gas between the reference cylinder and the sample cylinder flows mutually.
8. A geochemical reaction test based on the triaxial comprehensive simulation test system for displacing coalbed methane according to any one of claims 1 to 7, characterized in that: The specific steps include: Step 1: Sample filling Wrap the granular sample and the powder sample with gauze and place them in a high-temperature and high-pressure reactor (3.13), wherein part of the powder sample is dispersed in the high-temperature and high-pressure reactor (3.13), the reaction time of the sample with a diameter less than 10 mm is 15 days, and the reaction time of the column sample with a diameter not exceeding 50 mm and a length not exceeding 100 mm is extended to 60 days; Step 2: Air tightness check Close the fifth valve (3.11), the sixth valve (4.1), and the fourteenth valve (5.1), and open the second valve (3.1), the fourth pressure regulating valve (1.4), the fourth non-return valve (1.8), and the first valve (2.1), so that the argon gas cylinder is compressed and pressurized to the geochemical reaction module through the air compressor (2.2) and the gas booster pump (2.3). If the reading of the first pressure sensor (3.4) is stable and maintained for a period of time, it means that the air tightness of the geochemical reaction module is good; Step 3: Conduct geochemical reaction simulation Deionized water (3.5) and coal rock sample (3.6) are placed in a high temperature and high pressure reactor (3.13). The pressure in the high temperature and high pressure reactor (3.13) is reduced to -0.1 MPa using the first vacuum pump (3.12). Then, the third pressure regulating valve (1.3) and the third check valve (1.7) are opened. Pure CO2 is injected into the high temperature and high pressure reactor (3.13) using the air compressor (2.2) and the gas booster pump (2.3). At the same time, the heating device (3.8) is used to heat the reactor to the desired temperature. The temperature and pressure were monitored and adjusted every 8 hours to ensure that the system was within ±0.5 MPa and ±0.5 °C. On the 1st, 4th, 7th, 10th and 15th days of the experiment, the fourth valve (3.9) and the fifth valve (3.11) were opened to take out the mixed solution of the powder sample and the leached substance from the leaching liquid outlet. On the 15th day, the particle sample was taken back. The leaching liquid of the powder sample and the particle sample was washed with deionized water for several times to prevent mineral recrystallization, and then kept in a vacuum dryer at 50 °C for 24 hours. Step 4: Clean up the test equipment After the test, close the third pressure regulating valve (1.3) and the third non-return valve (1.7), open the fourth valve (3.9) and the fifth valve (3.11) to release the gas in the device, disconnect the pipelines and lines, and cool down; take out the rock sample in the high-temperature and high-pressure reactor (3.13), and put the components of the device in order.
9. A gas adsorption and desorption test based on the triaxial comprehensive simulation test system for displacing coalbed methane according to any one of claims 1 to 7, characterized in that: The specific steps include: Step 1: Sample preparation Prepare coal samples with a particle size of 0.25 mm to 0.18 mm according to GB / T 474, and perform industrial analysis according to GB / T 212. Perform equilibrium moisture test on coal samples according to formula (1), accurately weigh the coal samples that have reached equilibrium moisture, and put them into the sample cylinder; Where: M e is the equilibrium moisture content of the sample, in %; G1: air-dried sample mass before equilibrium, in g; G2 is the mass of the sample after equilibrium, in g; M ad Air-free coal-based moisture content of the sample, in %; Step 2: Air tightness test Open the thermostatic water bathtub to adjust the temperature so that the temperature of the sample tank and the reference cylinder is stable at the set target reservoir temperature. Close the second valve (3.1), the fourteenth valve (5.1), the tenth valve (4.5), and the thirteenth valve (4.9). Open the fourth pressure regulating valve (1.4), the fourth check valve (1.8), the first valve (2.1), and the sixth valve (4.1). The argon gas cylinder is compressed and pressurized to the system through the air compressor (2.2) and the gas booster pump (2.3). The pressure is 1MPa higher than the maximum pressure of the isothermal adsorption experiment. The system collects the pressure data of the second pressure sensor (4.11) and the third pressure sensor (4.12) of the reference cylinder and the sample cylinder. If the pressure remains unchanged within 6 hours, the system is considered to be airtight. Step 3: Free space volume determination Open the second vacuum pump (4.8) and evacuate the test system for 24 hours; open the fourth pressure regulating valve (1.4) and the fourth non-return valve (1.8), inject argon into the system, adjust the pressure of the reference cylinder so that the pressure value of the third pressure sensor (4.12) reaches 2MPa-3MPa, and close the second valve (3.1); open the seventh valve (4.2), collect a set of data after the pressure is balanced; repeat the above steps twice; repeat the free space volume measurement three times, and the difference between the two values is no more than 1cm 3 ; Calculate the volume of the coal sample according to formula (2), and calculate the volume of the free space in the sample tank according to formula (3); Where: Vs is the volume of the coal sample, in cubic centimeters; p1 equilibrium pressure, in MPa; p2 initial pressure of the reference cylinder, in MPa; p3 initial pressure of the sample cylinder, in MPa; T1 equilibrium temperature, unit is K; T2 initial temperature of the reference cylinder, in K; T3 initial temperature of sample cylinder, unit is K; V1 total system volume in cubic centimeters; V2 reference cylinder volume, in cubic centimeters; V3 sample cylinder volume, in cubic centimeters; The compressibility factor of the gas under Z1 equilibrium conditions; Z2 compressibility factor of the initial gas in the reference cylinder; Z3: compressibility factor of the initial gas in the sample cylinder; V f = V0 - V s Equation (3); Where: V f The volume of free space is measured in cubic centimeters; V0 total volume of the sample cylinder, in cubic centimeters; V s The volume of the coal sample in cubic centimeters; Step 4: Adsorption and desorption test Open the second vacuum pump (4.8) to evacuate the system, set the maximum test pressure to 1.1 times the reservoir pressure, and the maximum test balance pressure shall not be less than 8MPa. When the maximum test balance pressure is 8MPa, the number of test pressure points shall be no less than 6. Close the twelfth valve (4.7) and the second vacuum pump (4.8), open the first pressure regulating valve (1.1) and the first check valve (1.5), fill the reference cylinder with methane gas, observe that the pressure value of the third pressure sensor (4.12) is the target pressure, and start the isothermal adsorption test program after the second temperature sensor (4.10) is stable. Automatically collect the time, pressure and temperature data in the sample cylinder and the reference cylinder. The adsorption equilibrium time shall not be less than 12 hours. Repeat the above steps to test each pressure point from low to high until the test of the last pressure point is completed. Open the third pressure regulating valve (1.3) and the third check valve (1.7), and continuously inject supercritical CO2 into the coal body at a pressure of 10MPa for 12 hours. Observe that the pressure of the third pressure sensor (4.12) reaches the target pressure, collect data, open the eighth valve (4.3) and the ninth valve (4.4) to collect gas, and calculate the gas adsorption amount as follows (4). pV=nZRT Formula (4); Where: p is the gas pressure, in MPa; V is the volume of the gas in cubic centimeters; n is the number of moles of gas, in mol; The compressibility factor of the Z gas; R is the molar gas constant, in J·mol -l ·K -1 ; T is the equilibrium temperature, in K; Calculate the number of moles of gas in the sample cylinder before equilibrium at each pressure point n1 and the number of moles of gas in the sample cylinder after equilibrium n2, then the number of moles of gas adsorbed by the coal sample n i for: n i =n1-n2 Formula (5); Where: n i is the number of moles of gas, in mol; n1 is the number of moles of gas in the sample cylinder before equilibrium, in mol; n2 is the number of moles of gas in the sample cylinder after equilibrium, in mol; The total volume V of adsorbed gas at each pressure point i See formula (6): V i =n i ×22.4×1000 Formula (6); Adsorption volume V at each pressure point 吸附量 See formula (7): V 吸附量 =V i / G c Formula (7); Where: V 吸附量 is the adsorption amount, in cm 3 ·g -1 ; V i is the total volume of adsorbed gas in cubic centimeters; G c is the mass of coal sample, in g; Step 5: Clean up the test equipment After the test, close the third pressure regulating valve (1.3) and the third non-return valve (1.7), open the tenth valve (4.5) to recover the gas in the device, disconnect the pipelines and lines, and cool down; take out the coal and rock samples in the sample cylinder, and put the device air compressor (2.2) and gas booster pump (2.3) in order.
10. A gas adsorption and expansion strain test based on the triaxial comprehensive simulation test system for displacing coalbed methane according to any one of claims 1 to 7, characterized in that: The specific steps include: Step 1: Sample preparation According to GB / T18668-2002, a cubic sample was prepared and the coal sample was dried; the coal sample was polished with 240 mesh, 600 mesh and 1200 mesh sandpaper respectively, and then polished with a polishing machine at both ends. If there was a gap, it could be filled with coal powder to ensure a smooth surface of the sample; Step 2: Sample installation 1) Installation of resistance strain gauge: ① Select the location and direction of strain gauge pasting: For cubic samples, three strain gauges are pasted along the parallel surface cleats, parallel end cleats, and perpendicular to the bedding directions respectively; ② Pasting of strain gauge: Apply glue evenly on the selected strain gauge pasting position and the back of the strain gauge, fix the strain gauge to the surface of the coal sample with tweezers, press for 5 minutes to ensure that the strain gauge and the coal sample are completely fitted; ③ Wire welding: Paste the terminal blocks to both ends of the strain gauge, and use a soldering iron to weld the strain gauge connecting wire and the external guide wire to the terminal blocks. During this process, the solder should be kept flat to prevent the rubber sleeve from being punctured after the confining pressure is loaded; ④ Conductivity test: Use a multimeter to test the strain gauge circuit. If the result displayed by the multimeter is consistent with the actual result of the strain gauge, the conductivity is good; ⑤ Wire reinforcement: Apply silicone rubber on the wire and install the sample after the silicone rubber solidifies; 2) Open the triaxial test instrument, place the cubic sample on the right end of the pad (5.30), lead the strain gauge wire through the lead slot, and lay a layer of rubber sleeve (5.31) on both ends of the sample according to the size of the sample to ensure the sealing of the sample during the experiment; Step 3: Air tightness check According to the Chinese industry standard (NB / T 47013.8-2012), the system is tested for air tightness. The twenty-ninth valve (5.46) is opened, the second valve (3.1), the sixth valve (4.1), the eighteenth valve (5.11), the twentieth valve (5.14), and the twenty-second valve (5.23) are closed, and the entire gas pipeline and the instrument are evacuated to -0.1 MPa using the third vacuum pump (5.26) and maintained for 30 minutes. If the data of the sixth pressure sensor (5.25) remains unchanged, the air tightness of the device is good; Step 4: CO2 adsorption and expansion strain experiment After the air tightness of the device is tested to be good, the device is heated by a large thermostatic box to stabilize the temperature at a preset value of 35°C. The third pressure regulating valve (1.3), the third one-way valve (1.7), and the first valve (2.1) are opened, and CO2 gas is injected into the system through the air compressor (2.2) and the gas booster pump (2.3) until the pressure reaches the preset value. Then, the hydraulic layer (5.32) is pressurized by the second pressure tracking pump (5.27) and the third pressure tracking pump (5.34) to make the confining pressure 12MPa. Then, the constant gas in the instrument is ensured, and the microstrain value is recorded in real time by the resistance strain gauge (5.33). The recording frequency is once every 10s. The test is 12h. After the strain reaches stability, the strain size is calculated using formula (8). After the test is completed, different gas injection pressures or different coal samples are set to repeat the above steps; the sample strain is monitored and recorded using the DH3821 resistance strain gauge. The relationship between the resistance and strain of the strain gauge is as shown in formula (8): Where: ε is strain; K is the coefficient; ΔR is the resistance difference, unit is Ω; R ε is the strain ε is the resistance of the specimen, in Ω; R0 is the resistance of the specimen when there is no strain, in Ω; Step 5: Clean up the test equipment After the test, open the vent valve of the adsorption tank to discharge the gas in the adsorption tank, close all power lines, take out the coal samples, and then classify and store them according to regulations.