Cooling tower integrated circulating cooling water treatment control method
By monitoring temperature changes in real time, dynamically adjusting the number of fans and starting and stopping, combined with electro-adsorption and desalting treatment, the problems of electricity energy consumption and water quality in the cooling tower circulation cooling water treatment system are solved, and electricity saving and water quality improvement are achieved, and the fan life is extended.
Patent Information
- Application Number
- CN202411103132.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-13
- Publication Date
- 2024-11-01
AI Technical Summary
The existing cooling tower circulating cooling water treatment system lacks effective power consumption treatment methods, which leads to the inability to automatically control the opening and closing of the fan when the temperature changes, resulting in excessive consumption of electricity.
The temperature sensor collects return water and water supply temperature data in real time, calculates the temperature difference and temperature difference change, dynamically adjusts the start and stop and quantity of fans according to preset thresholds and adjustment strategies, and prioritizes fans with short running time to extend their service life, and combines the The electro-adsorption and salt removal device treats water quality.
The fan load balancing is achieved, the fan service life is extended, the fan is reduced, the power consumption and operating costs are reduced, the cooling efficiency and water quality stability are improved, and the cooling water is operated in the best condition.
Smart Images

Figure CN118877971A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of circulating cooling water treatment, and in particular to a cooling tower integrated circulating cooling water treatment control method. Background Art
[0002] The integrated circulating cooling water treatment of cooling towers mainly involves the removal of dirt, corrosion products, microorganisms and their derivatives in the cooling water system to improve the working efficiency of the system. This process includes cooling the recycled cooling water and treating the water quality, and maintaining the good operation of the system by controlling scale, corrosion and scale. In industrial production, cooling towers are important heat exchange equipment, and their operating efficiency directly affects the energy consumption and stability of the entire system. In practical applications, a comprehensive method is often used to treat the circulating water, perform qualified treatment on the supplementary water of the circulating system, perform bypass filtration on the circulating water, and use compound stabilizers inside the circulating system to comprehensively control the problems of scale, mud, fouling and electrochemical corrosion in the system.
[0003] In addition, the application of environmentally friendly and water-saving water treatment technology is also a major trend, aiming to save water and protect the environment. For example, the application of materials such as LHE polymers can work effectively under high alkalinity and high hardness water conditions, inhibit the growth of bacteria and algae, and do not require the use of bactericides, thereby reducing the negative impact on the environment. However, among the various control methods applied to circulating cooling water treatment mentioned above, most of them save energy from the aspect of water saving, and the operation of the cooling tower also includes the consumption and saving of electrical energy for water cooling treatment. The traditional cooling tower circulating water system usually turns on all the cooling fans in the equipment when circulating the water source. This cooling method will lead to excessive consumption of electricity when the temperature is low. Even if there are a few fans that can be manually controlled to turn on and off, it is impossible to automatically control the opening and closing of the fans as the water temperature changes. Summary of the invention
[0004] 1. Technical issues to be solved
[0005] In view of the deficiencies in the prior art, the present invention provides an integrated circulating cooling water treatment control method for a cooling tower, which solves the problem that the circulating cooling water treatment control system for a cooling tower in the prior art lacks a method for processing electric energy consumption.
[0006] (II) Technical solution
[0007] To achieve the above objectives, the present invention is implemented through the following technical solutions: A cooling tower integrated circulating cooling water treatment control method, applied to a circulating cooling water system, comprising:
[0008] Step 1: Data collection: the temperature sensor collects the return water temperature and supply water temperature data in real time and transmits them to the control system;
[0009] Step 2, data processing, the control system calculates the current temperature difference and the temperature difference change through the processing module, determines the start and stop and the number of fans according to the preset threshold and adjustment strategy, and dynamically adjusts the number of running fans;
[0010] Step 3: Execution control: the control system controls the start and stop of different numbers of fans through the execution module according to the judgment result.
[0011] Preferably, the process of controlling the start and stop of the fans and the number of fans is as follows:
[0012] According to the preset temperature difference threshold ΔT_threshold, when ΔT≥ΔT_threshold, start the fan;
[0013] When ΔT<ΔT_threshold, turn off the fan;
[0014] If ΔT is equal to ΔT_threshold, the minimum number of fans is started to maintain the basic cooling effect.
[0015] Preferably, the steps for dynamically adjusting the number of fans are as follows:
[0016] According to the change in temperature difference ΔΔT, one fan is added for every increase of 1.5 to 3°C. The specific value is adjusted according to the actual situation, such as cooling tower model, ambient temperature, etc.
[0017] Preferably, the number of fan openings is calculated using the following formula:
[0018] Cf = (ΔT1-ΔT2) / x;
[0019] Where: Cf is the number of fan openings;
[0020] ΔT1 is the current temperature difference threshold;
[0021] ΔT2 is the last temperature difference threshold;
[0022] The value range of x is (1.5~3);
[0023] The specific value of x depends on the actual situation;
[0024] △T is the temperature difference threshold, where the number of fans turned on is based on the currently started fans, and the fans that are not turned on are started.
[0025] Preferably, in step three, when controlling the operation of different numbers of fans through the execution module, fans with relatively short operation time are preferentially selected to operate, so that fans with shorter shutdown time can be effectively restored, thereby increasing the service life of the fans.
[0026] Preferably, the step of preferentially selecting fans with relatively short operating time is as follows:
[0027] a. Record the running and stopping time of each fan through sensors;
[0028] b. Record various fan data through the data acquisition module;
[0029] c. After the processing module calculates the fan with the longest relative stop time, it controls the fan to start through the execution module.
[0030] Preferably, the temperature difference variation in step 2 is calculated using the following formula:
[0031] ΔΔT = t1 - t2;
[0032] Where: ΔΔT is the change in temperature difference;
[0033] t1 is the current temperature value;
[0034] t2 is the previous detected temperature value.
[0035] Preferably, the circulating water cooling system includes a cooling tower body, a plurality of temperature sensors, a plurality of fan sensors and an electric adsorption desalination mechanism.
[0036] Preferably, the cooling tower body also includes components and mechanisms required for the operation of a conventional cooling tower, which are used to spray and cool the water source;
[0037] Several temperature sensors are installed on the return water pipe and the supply water pipe respectively to monitor the return water temperature and the supply water temperature in real time;
[0038] The electro-adsorption desalination mechanism is integrated into the cooling water system to remove salt and impurities from the water;
[0039] Several of the fan sensors are installed on each fan respectively to record the operation and start and stop time of the fan.
[0040] Preferably, the circulating water cooling system also includes a control system, which is composed of a data acquisition module, a processing module and an execution module, which are respectively used to receive temperature data, calculate temperature difference, and control the start and stop and number of fans.
[0041] (III) Beneficial effects
[0042] The present invention provides a cooling tower integrated circulating cooling water treatment control method. It has the following beneficial effects:
[0043] 1. When controlling the operation of different numbers of fans through the execution module, fans with relatively short operating time are given priority to work, so that fans with shorter downtime can be effectively restored to balance the fan load and effectively ensure the service life of the cooling equipment.
[0044] 2. Treat drainage water through the electro-adsorption desalination device to reduce the amount of external drainage and maximize the utilization of water resources. At the same time, the water quality is improved, the salt and impurities in the circulating water are effectively removed, scaling, corrosion and microbial growth are reduced, the operating efficiency of the system is improved, and the operating cost is reduced. The electro-adsorption desalination has low energy consumption and simple equipment maintenance, which effectively reduces the operating cost.
[0045] 3. Automatically adjust the treatment process through intelligent control algorithms to ensure that the cooling water operates in the best condition and improve cooling efficiency. By optimizing the treatment process and the amount of reagents added, unnecessary energy consumption and reagent waste can be reduced. The water quality parameters are monitored in real time, and the treatment process and the amount of reagents added can be automatically adjusted to ensure that the water quality is stable and meets the standards. BRIEF DESCRIPTION OF THE DRAWINGS
[0046] Figure 1 A flow chart of the steps of a cooling tower integrated circulating cooling water treatment control method proposed by the present invention;
[0047] Figure 2 A flow chart of the electrosorption operation steps of a cooling tower integrated circulating cooling water treatment control method proposed by the present invention;
[0048] Figure 3 This is a flow chart of the intelligent algorithm implementation of the cooling tower integrated circulating cooling water treatment control method proposed by the present invention. DETAILED DESCRIPTION
[0049] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0050] Embodiment 1:
[0051] like Figure 1 As shown, an embodiment of the present invention provides a cooling tower integrated circulating cooling water treatment control method, which is applied to a circulating cooling water system, comprising:
[0052] Step 1: Data collection: the temperature sensor collects the return water temperature and supply water temperature data in real time and transmits them to the control system;
[0053] Step 2, data processing, the control system calculates the current temperature difference and the temperature difference change through the processing module, determines the start and stop and the number of fans according to the preset threshold and adjustment strategy, and dynamically adjusts the number of running fans;
[0054] Step 3: Execution control: the control system controls the start and stop of different numbers of fans through the execution module according to the judgment result.
[0055] The control process of fan start and stop and quantity is as follows:
[0056] According to the preset temperature difference threshold ΔT_threshold, when ΔT≥ΔT_threshold, start the fan;
[0057] When ΔT<ΔT_threshold, turn off the fan;
[0058] If ΔT is equal to ΔT_threshold, the minimum number of fans is started to maintain the basic cooling effect.
[0059] The steps for dynamic adjustment and control of the number of fans are as follows:
[0060] According to the change in temperature difference ΔΔT, one fan is added for every increase of 1.5 to 3°C. The specific value is adjusted according to the actual situation, such as cooling tower model, ambient temperature, etc.
[0061] The number of fans turned on is calculated using the following formula:
[0062] Cf = (ΔT1-ΔT2) / x;
[0063] Where: Cf is the number of fan openings;
[0064] ΔT1 is the current temperature difference threshold;
[0065] ΔT2 is the last temperature difference threshold;
[0066] The value range of x is (1.5~3);
[0067] The specific value of x depends on the actual situation;
[0068] △T is the temperature difference threshold, where the number of fans turned on is based on the currently started fans, and the fans that are not turned on are started.
[0069] In the step three, when the execution module is used to control the operation of different numbers of fans, fans with relatively short operation time are preferentially selected to operate, so that fans with shorter shutdown time can be effectively restored, thereby increasing the service life of the fans.
[0070] The steps of preferentially selecting fans with relatively short operating time are as follows:
[0071] a. Record the running and stopping time of each fan through sensors;
[0072] b. Record various fan data through the data acquisition module;
[0073] c. After the processing module calculates the fan with the longest relative stop time, it controls the fan to start through the execution module.
[0074] The temperature difference variation in step 2 is calculated using the following formula:
[0075] ΔΔT = t1 - t2;
[0076] Where: ΔΔT is the change in temperature difference;
[0077] t1 is the current temperature value;
[0078] t2 is the previous detected temperature value.
[0079] The circulating water cooling system includes a cooling tower body, a plurality of temperature sensors, and a plurality of fan sensors.
[0080] The cooling tower body also includes components and mechanisms required for the operation of conventional cooling towers, which are used to spray and cool water sources;
[0081] Several temperature sensors are installed on the return water pipe and the supply water pipe respectively to monitor the return water temperature and the supply water temperature in real time;
[0082] Several of the fan sensors are installed on each fan respectively to record the operation and start and stop time of the fan.
[0083] The circulating water cooling system also includes a control system, which is composed of a data acquisition module, a processing module and an execution module, which are respectively used to receive temperature data, calculate temperature differences, and control the start and stop and number of fans.
[0084] Comparative Example 1:
[0085] A cooling tower integrated circulating cooling water treatment control method, applied to a circulating cooling water system, comprising:
[0086] Step 1: Data collection: the temperature sensor collects the return water temperature and supply water temperature data in real time and transmits them to the control system;
[0087] Step 2: Data processing: the control system calculates the current temperature difference and the temperature difference change through the processing module, and determines whether to start or stop the fan according to the preset threshold and adjustment strategy;
[0088] Step 3: Execution control: the control system controls the start and stop of the fan through the execution module according to the judgment result.
[0089] The control process of fan start and stop is as follows:
[0090] According to the preset temperature difference threshold ΔT_threshold, when ΔT≥ΔT_threshold, start the fan;
[0091] According to the preset temperature value X, when X1≥X, start the fan;
[0092] When X1≤X, turn off the fan;
[0093] Among them: X1 is the current temperature value.
[0094] The circulating water cooling system comprises a cooling tower body, a plurality of temperature sensors, a plurality of fan sensors and an electric adsorption desalination mechanism.
[0095] The cooling tower body also includes components and mechanisms required for the operation of conventional cooling towers, which are used to spray and cool water sources;
[0096] Several temperature sensors are installed on the return water pipe and the supply water pipe respectively to monitor the return water temperature and the supply water temperature in real time;
[0097] The electro-adsorption desalination mechanism is integrated into the cooling water system to remove salt and impurities from the water;
[0098] Several of the fan sensors are installed on each fan respectively to record the operation and start and stop time of the fan.
[0099] The circulating water cooling system also includes a control system, which is composed of a data acquisition module, a processing module and an execution module, which are respectively used to receive temperature data, calculate temperature difference, and control the start and stop of the fan.
[0100] Comparison table of energy consumption of conventional cooling tower fans and cooling tower fans in this application at different temperatures:
[0101]
[0102] It can be seen from the above table that only when all cooling fans are started, the cooling fan power consumption of the cooling tower of the present application is equal to that of a conventional cooling tower. Except in the shutdown state, it is lower than the fan power consumption of a conventional cooling tower under other circumstances. Therefore, it can be seen that the cooling tower fan control method in the present application, which can automatically control the number of fan starts according to temperature requirements, can effectively reduce the power consumption of the cooling tower fan, thereby reducing the operating power consumption of the cooling tower itself.
[0103] Embodiment 2:
[0104] Please refer to Figure 2 Based on the cooling tower integrated circulating cooling water treatment control method provided by the first embodiment of the present application, the second embodiment of the present application proposes another cooling tower integrated circulating cooling water treatment control method. The second embodiment is only a preferred method of the first embodiment, and the implementation of the second embodiment will not affect the independent implementation of the first embodiment.
[0105] Specifically, the cooling tower integrated circulating cooling water treatment control method provided in the second embodiment of the present application is applied to a circulating cooling water system, including:
[0106] Step 1: Data collection: the temperature sensor collects the return water temperature and supply water temperature data in real time and transmits them to the control system;
[0107] Step 2, data processing, the control system calculates the current temperature difference and the temperature difference change through the processing module, determines the start and stop and the number of fans according to the preset threshold and adjustment strategy, and dynamically adjusts the number of running fans;
[0108] Step 3: Execution control: the control system controls the start and stop of different numbers of fans through the execution module according to the judgment result.
[0109] When the execution module is used to control the operation of different numbers of fans in step three, fans with relatively short operation time are preferentially selected to operate so that fans with shorter shutdown time can be effectively restored.
[0110] The steps of preferentially selecting fans with relatively short operating time are as follows:
[0111] a. Record the running and stopping time of each fan through sensors;
[0112] b. Record various fan data through the data acquisition module;
[0113] c. After the processing module calculates the fan with the longest relative stop time, it controls the fan to start through the execution module.
[0114] The circulating water cooling system includes a cooling tower body, a number of temperature sensors, a number of fan sensors and an electric adsorption desalination mechanism. The cooling tower body also includes the components required for the operation of a conventional cooling tower, which are used to spray and cool the water source;
[0115] Several temperature sensors are installed on the return water pipe and the supply water pipe respectively to monitor the return water temperature and the supply water temperature in real time;
[0116] The electro-adsorption desalination mechanism is integrated into the cooling water system to remove salt and impurities from the water;
[0117] Several of the fan sensors are installed on each fan respectively to record the operation and start and stop time of the fan.
[0118] The circulating water cooling system also includes a control system, which is composed of a data acquisition module, a processing module and an execution module, which are respectively used to receive temperature data, calculate temperature differences, and control the start and stop and number of fans.
[0119] The electric adsorption desalination device is integrated into the system, and includes a diaphragm, a carbon nanotube composite electrode, and a power supply system for removing salt and impurities in circulating water.
[0120] The electrosorption operation steps are as follows:
[0121] 1. Real-time monitoring: The conductivity, pH value, turbidity and other water quality indicators of circulating water are monitored in real time through detection instruments.
[0122] 2. Intelligent control: Automatically adjust the operating parameters (such as voltage, current, etc.) of the electric adsorption desalination device according to water quality indicators to achieve the best desalination effect.
[0123] 3. Drainage treatment: When the circulating water concentration is too high and needs to be drained, the drainage will be introduced into the electro-adsorption desalination device for treatment. After removing the ions that are not easy to precipitate, the produced fresh water will be reused in the system, and the remaining concentrated water will be discharged.
[0124] The intelligent control method is as follows:
[0125] Parameter setting and initialization: When the system starts, set the initial voltage, current, processing time and other parameters of each electrosorption desalination module according to the initial water quality data;
[0126] Real-time monitoring and data collection: Water quality monitoring sensors continuously monitor the quality of circulating water and transmit data to the intelligent control unit;
[0127] Data analysis and parameter optimization: The intelligent control unit uses machine learning or preset models to analyze water quality data, compare the desalination effects under different parameter combinations, and select the best parameter combination through algorithm optimization;
[0128] Automatic adjustment and feedback: According to the analysis results, the intelligent control unit automatically adjusts the working parameters of the electrosorption desalination module to achieve dynamic optimization of the desalination effect. At the same time, the water quality data before and after each adjustment is recorded and stored for subsequent algorithm optimization and fault diagnosis.
[0129] In order to verify the effect of the present invention, several groups of comparative experiments were conducted. The following are some examples of experimental data:
[0130] Experiment number Voltage (V) Current (A) Processing time (h) Salt removal rate (%) 1 10 1 2 75 2 15 1.5 2 82 3 15 1 3 85 4 20 1.5 3 88 5 20 2 2.5 90
[0131] It can be seen from the above experimental data that with the increase of voltage and current and the extension of treatment time, the desalination rate shows an upward trend, but considering the energy consumption and efficiency comprehensively, the parameter combination of experiment number 5 (voltage 20V, current 2A, treatment time 2.5h) shows the best desalination effect and cost performance.
[0132] By treating drainage with an electro-adsorption desalination device, the amount of external drainage is reduced, and the maximum utilization of water resources is achieved. At the same time, the water quality is improved, the salt and impurities in the circulating water are effectively removed, scaling, corrosion and microbial growth are reduced, the operating efficiency of the system is improved, and the operating cost is reduced. The electro-adsorption desalination has low energy consumption and simple equipment maintenance, which effectively reduces the operating cost. At the same time, by integrating multiple electro-adsorption desalination modules and intelligent control systems, the automation and intelligence of the cooling tower circulating cooling water treatment is realized, which significantly improves the desalination efficiency and water quality stability, and provides a strong guarantee for the long-term stable operation of the industrial cooling system.
[0133] Embodiment 3:
[0134] Please refer to Figure 3 Based on the cooling tower integrated circulating cooling water treatment control method provided by the first embodiment of the present application, the third embodiment of the present application proposes another cooling tower integrated circulating cooling water treatment control method. The third embodiment is only a preferred method of the first embodiment, and the implementation of the third embodiment will not affect the independent implementation of the first embodiment.
[0135] Specifically, the cooling tower integrated circulating cooling water treatment control method provided in the third embodiment of the present application is applied to a circulating cooling water system, including:
[0136] Step 1: Data collection: the temperature sensor collects the return water temperature and supply water temperature data in real time and transmits them to the control system;
[0137] Step 2, data processing, the control system calculates the current temperature difference and the temperature difference change through the processing module, determines the start and stop and the number of fans according to the preset threshold and adjustment strategy, and dynamically adjusts the number of running fans;
[0138] Step 3: Execution control: the control system controls the start and stop of different numbers of fans through the execution module according to the judgment result.
[0139] When the execution module is used to control the operation of different numbers of fans in step three, fans with relatively short operation time are preferentially selected to operate so that fans with shorter shutdown time can be effectively restored.
[0140] The steps of preferentially selecting fans with relatively short operating time are as follows:
[0141] a. Record the running and stopping time of each fan through sensors;
[0142] b. Record various fan data through the data acquisition module;
[0143] c. After the processing module calculates the fan with the longest relative stop time, it controls the fan to start through the execution module.
[0144] The circulating water cooling system comprises a cooling tower body, several types of sensors, an actuator and an electric adsorption desalination mechanism.
[0145] The cooling tower body also includes components and mechanisms required for the operation of conventional cooling towers, which are used to spray and cool water sources;
[0146] Some of the aforementioned types of sensors include, but are not limited to: temperature sensors, turbidity meters, flow meters and pH meters, etc., which are used to monitor various parameters (such as temperature, turbidity, flow rate, pH value, etc.) of circulating cooling water in the cooling tower in real time;
[0147] The electro-adsorption desalination mechanism is integrated into the cooling water system to remove salt and impurities from the water;
[0148] The actuators include but are not limited to circulation pumps, dosing pumps, valves, etc.
[0149] The circulating water cooling system also includes an intelligent control algorithm module and an execution module, wherein:
[0150] Intelligent control algorithm module: Based on real-time monitoring data, intelligent control algorithms (such as neural networks, support vector machines, model predictive control, etc.) are used to automatically calculate and adjust the treatment process and reagent dosage;
[0151] Execution module: According to the calculation results of the intelligent control algorithm module, it controls the corresponding actuators to achieve automatic adjustment of the processing technology.
[0152] The intelligent control model training method comprises the following steps:
[0153] 1. Data preprocessing: Filter, denoise and calibrate the raw data collected by the sensor to ensure the accuracy and reliability of the data;
[0154] 2. Feature extraction: Extract key features, such as temperature change trend, turbidity peak, etc., from the preprocessed data as input for the intelligent control algorithm;
[0155] 3. Selection of intelligent control algorithm: Select the appropriate intelligent control algorithm according to the system characteristics and control objectives. For nonlinear and time-varying systems, use the neural network algorithm; for systems that require fast response, use the model predictive control algorithm;
[0156] 4. Model training and optimization: Use historical data and simulation data to train and optimize intelligent control algorithms to improve their control accuracy;
[0157] 5. Real-time control: Apply the trained intelligent control algorithm to the actual system to automatically adjust the treatment process and dosage of the reagent according to the real-time parameters.
[0158] The intelligent algorithm implementation process is as follows:
[0159] Data collection: various parameters of circulating cooling water in the cooling tower are collected in real time through sensors;
[0160] Data preprocessing: filtering, denoising and calibrating the collected data;
[0161] Feature extraction: extract key features from preprocessed data;
[0162] Intelligent control calculation: Calculate the adjustment value of the treatment process and the dosage of the reagent according to the extracted features and intelligent control algorithm;
[0163] Execute control instructions: send control instructions to the actuator to adjust the treatment process and dosage of reagents.
[0164] The treatment process is automatically adjusted through intelligent control algorithms to ensure that the cooling water operates in the best condition and improve cooling efficiency. By optimizing the treatment process and the amount of reagents added, unnecessary energy consumption and reagent waste are reduced. Water quality parameters are monitored in real time, and the treatment process and the amount of reagents added are automatically adjusted to ensure that the water quality is stable and meets the standards.
[0165] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A cooling tower integrated circulating cooling water treatment control method, applied to a circulating cooling water system, It is characterized in that include: Step 1: Data collection: the temperature sensor collects the return water temperature and supply water temperature data in real time and transmits them to the control system; Step 2, data processing, the control system calculates the current temperature difference and the temperature difference change through the processing module, determines the start and stop and the number of fans according to the preset threshold and adjustment strategy, and dynamically adjusts the number of running fans; Step 3: Execution control: the control system controls the start and stop of different numbers of fans through the execution module according to the judgment result.
2. A cooling tower integrated circulating cooling water treatment control method according to claim 1, Features: The control process of fan start and stop and quantity is as follows: According to the preset temperature difference threshold ΔT_threshold, when ΔT≥ΔT_threshold, the fan is started; When ΔT<ΔT_threshold, turn off the fan; If ΔT is equal to ΔT_threshold, a minimum number of fans are started to maintain the basic cooling effect.
3. A cooling tower integrated circulating cooling water treatment control method according to claim 1, Features: The steps for dynamic adjustment and control of the number of fans are as follows: According to the change in temperature difference ΔΔT, one fan is added for every increase of 1.5 to 3°C. The specific value is adjusted according to the actual situation, such as cooling tower model, ambient temperature, etc.
4. A cooling tower integrated circulating cooling water treatment control method according to claim 1, Features: The number of fans turned on is calculated using the following formula: Cf=(ΔT 1 -ΔT 2 ) / x; Where: Cf is the number of fan openings; ΔT 1 is the current temperature difference threshold; ΔT 2 is the last temperature difference threshold; The value range of x is (1.5~3); The specific value of x depends on the actual situation; △T is the temperature difference threshold.
5. A cooling tower integrated circulating cooling water treatment control method according to claim 1, Features: When the execution module is used to control the operation of different numbers of fans in step three, fans with relatively short operation time are preferentially selected to operate so that fans with shorter shutdown time can be effectively restored.
6. A cooling tower integrated circulating cooling water treatment control method according to claim 5, Features: The steps of preferentially selecting fans with relatively short operating time are as follows: a. Record the running and stopping time of each fan through sensors; b. Record various fan data through the data acquisition module; c. After the processing module calculates the fan with the longest relative stop time, it controls the fan to start through the execution module.
7. A cooling tower integrated circulating cooling water treatment control method according to claim 1, Features: The temperature difference variation in step 2 is calculated using the following formula: ΔΔT=t 1 -t 2 ; Where: ΔΔT is the change in temperature difference; t 1 is the current temperature value; t 2 This is the temperature value of the previous detection.
8. A cooling tower integrated circulating cooling water treatment control method according to claim 1, Features: The circulating water cooling system comprises a cooling tower body, a plurality of temperature sensors, a plurality of fan sensors and an electric adsorption desalination mechanism.
9. A cooling tower integrated circulating cooling water treatment control method according to claim 8, Features: The cooling tower body also includes components and mechanisms required for the operation of conventional cooling towers, which are used to spray and cool water sources; Several temperature sensors are installed on the return water pipe and the supply water pipe respectively to monitor the return water temperature and the supply water temperature in real time; The electro-adsorption desalination mechanism is integrated into the cooling water system to remove salt and impurities from the water; Several of the fan sensors are installed on each fan respectively to record the operation and start and stop time of the fan.
10. The integrated circulating cooling water treatment control method according to claim 1, Features: The circulating water cooling system also includes a control system, which is composed of a data acquisition module, a processing module and an execution module, which are respectively used to receive temperature data, calculate temperature differences, and control the start and stop and number of fans.
Citation Information
Patent Citations
Method for controlling cooling tower and cooling tower therewith
CN101029810A
Optimal water supply temperature control method for circulating cooling water system
CN107065543A
Control method for most energy-saving cooling tower fan under different temperature and humidity based on big data and cooling tower
CN114857064A
Intelligent control system and control method for cooling tower
CN115823928A
Control method of cooling tower fan
CN117516255A
Cited By
Sewage treatment system and method for buried water plant
CN119873911A
Method and system for automatically switching air-cooling operation mode of main transformer based on ambient temperature
WO2026218540A1