Rapid recovery method for high-ball-ratio schreyerite blast furnace after non-planned emergency damping down

By adjusting the blast furnace charging, blast, heat and slag-iron system, and optimizing the tuyere management, the problems of hearth heat loss and slag-iron separation after unplanned emergency shutdown of blast furnaces producing high-spherical-ratio vanadium-titanium magnetite were solved, enabling rapid recovery. This method is applicable to blast furnaces and high-titanium smelting blast furnaces.

CN118879960APending Publication Date: 2024-11-01PANGANG GRP XICHANG STEEL & VANADIUM CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410999122.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-24
Publication Date
2024-11-01

AI Technical Summary

Technical Problem

Under high sphericity ratio conditions, after an unplanned emergency shutdown of a vanadium-titanium magnetite blast furnace, the hearth loses heat severely, the blast capacity deteriorates, and the slag-iron separation effect is poor, making it difficult to restore the furnace condition. In some cases, the hearth may even freeze, and existing technologies cannot restore it quickly.

Method used

By adjusting the blast furnace charging system, blast system, heating system, slag forming system, and tapping system, and optimizing tuyer management and heat compensation measures, the furnace temperature recovery and slag-iron separation effects are ensured, process losses are reduced, and rapid recovery is achieved.

Benefits of technology

It enables rapid recovery of high vanadium-titanium magnetite blast furnaces after unplanned emergency shutdowns, reduces process losses, avoids repeated furnace condition fluctuations, and is applicable to blast furnaces and high-titanium smelting blast furnaces, with significant economic benefits.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118879960A_ABST
    Figure CN118879960A_ABST
Patent Text Reader

Abstract

The invention discloses a rapid recovery method for a high-ball-ratio schreyerite blast furnace after unplanned emergency damping down, and belongs to the technical field of vanadium titano-magnetite blast furnace smelting. By adjusting the cooling system, the charging system, the air supply system, the heating system, the slagging system and the stokehole tapping system of the blast furnace, the blast furnace can be recovered to be normal within 1-3 days; the technical problems that the duration of non-planned emergency damping-down of the high-ball-ratio vanadium titano-magnetite blast furnace is uncertain, heat loss of the hearth is large and the like are solved, process losses are reduced, repeated furnace condition recovery is avoided, and rapid recovery of non-planned emergency damping-down of the vanadium titano-magnetite blast furnace under the high ball ratio is achieved. The rapid recovery method can be popularized to other common smelting blast furnaces and high-titanium smelting blast furnaces, and is high in application value and high in economic benefit.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of vanadium-titanium magnetite blast furnace smelting, and in particular relates to a method for quickly recovering a high-spherical ratio vanadium-titanium blast furnace after an unplanned emergency shutdown. Background Art

[0002] There are two types of blast furnace shutdowns: planned shutdowns and unplanned emergency shutdowns. For planned shutdowns, the entire process from shutdown to resumption of operation is carried out under prepared conditions, and the furnace condition recovery process is relatively easy; for example, the patent with application number CN201810349797 provides a rapid resumption of operation method for vanadium-titanium magnetite blast furnace smelting, and the shutdown operation and the operation system involved in the recovery process are planned shutdown operations, and the shutdown process is controllable. However, for unplanned emergency shutdowns, the smelting process is often forced to be suddenly interrupted due to equipment and production accidents, and there are factors such as uncertain emergency shutdown duration and large heat loss in the furnace, which cause great obstacles to subsequent resumption of operation, especially long-term unplanned shutdowns, which bring huge challenges to the recovery of blast furnace conditions.

[0003] With the development of vanadium-titanium magnetite blast furnace smelting technology, high vanadium-titanium pellet ratio (hereinafter referred to as "high pellet ratio") technology has achieved great results. The high pellet ratio of some blast furnaces exceeds 50%, which is of great significance for cost reduction, efficiency improvement, energy conservation and carbon reduction. However, vanadium-titanium magnetite blast furnaces under high pellet ratio conditions may experience unplanned emergency wind downs for various reasons, just like ordinary ore blast furnaces, which may have an adverse impact on blast furnace production.

[0004] For blast furnaces smelting vanadium-titanium magnetite, due to the particularity of vanadium-titanium magnetite, its high-titanium blast furnace slag has the characteristics of viscosity, poor fluidity, poor stability, foamy slag, etc., and a more complete guarantee system and more sophisticated operation adjustment are needed during the smelting process. Once an unplanned emergency wind stop occurs, the furnace is interrupted when all the materials are heavy-loaded, the activity of the furnace will be greatly reduced, the wind receiving capacity will be poor, and the blast furnace may be in a long-term low-pressure slow wind operation state. In severe cases, the furnace will freeze. Therefore, several aspects should be paid attention to in the whole process: First, measures should be taken to prevent heat loss in the furnace during the wind stop process to prevent the furnace from freezing; second, the problem of appropriate furnace temperature [Ti] + [Si] during the furnace condition recovery process should be solved, and the air volume should be restored as soon as possible; third, the problem of TiO2 over-reduction of high-titanium slag at high furnace temperature should also be solved to ensure a good separation effect of slag and iron; fourth, the matching of the operation system during the recovery process should be done well to prevent the recovery cycle from being long due to repeated furnace conditions, and in severe cases, forced to shut down the furnace. Summary of the invention

[0005] In order to solve the bottleneck problem existing in the above-mentioned prior art, the present invention solves the problem of furnace condition recovery after unplanned emergency shutdown of the high-spherical ratio vanadium-titanium magnetite blast furnace by adjusting the blast furnace charging system, air supply system, heat system, slag making system and furnace front iron tapping system, reduces process losses, avoids repeated furnace condition recovery, and realizes the rapid recovery of the vanadium-titanium magnetite blast furnace after unplanned emergency shutdown under high spherical ratio.

[0006] In order to achieve the above-mentioned object of the invention, the present invention provides a method for quickly recovering a blast furnace with a high spherical ratio of vanadium and titanium after an unplanned emergency shutdown, the method comprising the following steps:

[0007] ① In case of unplanned emergency shutdown, the amount of cooling water in the cooling wall should be reduced according to the duration of the shutdown to reduce the heat loss in the furnace. At the same time, all air vents should be blocked with mud to slow down the oxidation-reduction process in the furnace and prevent a large amount of slag and iron from gathering and condensing in the furnace, causing the furnace to stick.

[0008] ② Adjust the material structure of the air supply into the furnace: The material structure of the furnace should follow the principle of less material varieties and appropriately reduce the (TiO2) content. The charge calculation is based on the use of only vanadium-titanium sintered ore, belt-type vanadium-titanium pellets and lump ore, slag (TiO2) ≤ 90% of the normal level, RO ≤ (normal value -0 ~ 0.05). By reducing pellets, increasing sintering and lump ore, the clinker rate is adjusted from 100% to 80% ~ 100%, ensuring that the slag has good fluidity. At the same time, the coal load should be stopped, the batch weight should be adjusted to 65% ~ 80% of the normal level, and the load should be adjusted to 60% ~ 90% of the normal level.

[0009] ③ Adjustment of air supply and charging system: After air supply, the charging system is adjusted based on the minimum ore angle of the normal air supply and charging system. When the emergency air stop time is 1 to 4 hours, the charging system may not be adjusted according to the situation; when the air stop time is 4 to 24 hours, the ore platform is ≤70% of the normal level, and the edge coke ratio is ≥40%; when the air stop time is longer than 24 hours, a single-ring distribution system is often adopted (the ore platform is 0°). At this time, it is necessary to decisively reduce the proportion of pellets to prevent the rolling of pellets from blocking the two airflows; the edge coke ratio is ≥50%. When the air stop time is 1 to 3 days, the proportion of pellets is 40% to 45%; when the air stop time is 4 to 5 days, the proportion of pellets is 30% to 40%; when the air stop time is 6 to 7 days, the proportion of pellets is ≤30%.

[0010] ④ Adjustment of air supply tuyere area: Considering the suddenness of emergency air stoppage, and the fact that the whole furnace is loaded with heavy-loaded materials, the air permeability of the material column is poor. It is necessary to ensure that there is enough blast kinetic energy in the lower part to activate the furnace, blow through the center, and eliminate the adverse effects of Ti (C, N) in the slag. Reduce the tuyere area to activate the furnace and create good slag-iron separation dynamic conditions. The air supply tuyere area is adjusted to 60% to 80% of the normal air supply area. If the blast kinetic energy of normal production is low, the lower limit of the air supply tuyere area is recommended, otherwise the upper limit is recommended. Depending on the raw materials, fuels and other internal and external conditions, if it is estimated that the recovery is difficult, it is recommended to block the tuyere to adjust the air inlet area.

[0011] ⑤ Heat compensation of blast furnace: Through heat balance calculation, according to the different durations of unplanned emergency wind stop, different amounts of net coke are added, and two methods of adding coke, centralized and decentralized, are adopted. When the unplanned emergency wind stop lasts for 1 to 4 hours, 0 to 30 tons of coke are added; when the unplanned emergency wind stop lasts for 4 to 24 hours, 30 to 60 tons of coke are added; when the unplanned emergency wind stop lasts for 1 to 2 days, 60 to 80 tons of coke are added; when the unplanned emergency wind stop lasts for 2 to 3 days, 100 to 120 tons of coke are added; when the unplanned emergency wind stop lasts for 4 to 5 days, 140 to 180 tons of net coke are added; when the unplanned emergency wind stop lasts for 6 to 7 days, 200 to 240 tons of coke are added. If the smooth operation is not good, serious collapse and sliding of materials and other situations occur, temporary additional coke can be added. The hot blast furnace should try to maintain high wind temperature air supply, enhance the heat supplement capacity, and enable the furnace temperature to quickly return to the level of [Si] + [Ti] ≥ 1.00%.

[0012] ⑥ The matching of the operation system of the re-airing process: before the net coke is issued, when Ti+Si≤0.20%, the air volume ≤75%; when Ti+Si>0.20%, the air volume ≤85%. After the net coke is issued, the air volume is lower than 60% of the normal level, the ore platform adopts 0~2°, and the marginal coke accounts for ≥50% (unplanned emergency wind break duration ≤4h, and the distribution system can be adjusted according to the situation); the air volume is restored to 65%~75% of the normal level, the furnace temperature Ti+Si≥0.60%, the ore platform adopts 2~4°, and the marginal coke accounts for ≥45%; the air volume is restored to 85%~95% of the normal level, the furnace temperature Ti+Si≥0.40%, the ore platform adopts 4~6°, and the marginal coke accounts for ≥40%; the air volume is restored to the normal level, the furnace temperature Ti+Si≥0.30%, the ore platform adopts 5~7°, and the marginal coke accounts for ≥35%.

[0013] ⑦ Furnace front guarantee during the re-airing process: the angle of the opening machine is reduced by 0-4°, which is conducive to the smooth removal of cold slag iron in the initial stage of air supply; temporary sand dam is used to tap iron to prevent low-temperature slag iron from blocking the slag iron ditch and slag shield, resulting in the inability of the furnace to operate normally. When the fluidity of slag iron improves, consider restoring sand pit tapping as appropriate. At the same time, a dry shell tank should be equipped to prevent the slag tank from burning through due to poor slag iron separation.

[0014] Compared with the prior art, the present invention has the following beneficial effects:

[0015] The present invention can restore the blast furnace to normal in 1 to 3 days by adjusting the cooling system, the blast furnace charging system, the air supply system, the heat system, the slag making system and the iron-tapping system in front of the furnace; it solves the technical problems of the uncertain duration of the unplanned emergency wind-down of the high-spherical ratio vanadium-titanium magnetite blast furnace and the large heat loss of the furnace, reduces the process loss, avoids the repetition of furnace condition recovery, and realizes the rapid recovery of the unplanned emergency wind-down of the vanadium-titanium magnetite blast furnace under high spherical ratio. The rapid recovery method can be extended to other common smelting blast furnaces and high-titanium smelting blast furnaces, with great application value and high economic benefits. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 The present invention is a process flow chart of a method for rapid recovery of a high spherical ratio vanadium-titanium ore blast furnace after an unplanned emergency shutdown. DETAILED DESCRIPTION

[0017] The present invention is further described below in conjunction with specific examples, but the present invention is not limited in any way. To avoid redundant description, the raw materials in the following examples are all commercially available products unless otherwise specified, and the methods used are all conventional methods unless otherwise specified.

[0018] A method for quickly recovering a blast furnace with a high spherical ratio of vanadium and titanium ore after an unplanned emergency shutdown, the method comprising the following steps:

[0019] ① Adjustment of cooling system: reduce the cooling water volume of cooling wall according to the wind-off time, and seal all air vents with mud;

[0020] ② Adjust the material structure of air supply into the furnace: the furnace charge is calculated based on the use of only vanadium-titanium sintered ore, belt-type vanadium-titanium pellets and lump ore, slag (TiO2) ≤ 90% of the normal level, RO ≤ (normal value -0 ~ 0.05); the clinker rate is adjusted from 100% to 80% ~ 100%, the coal load is stopped, the batch weight is adjusted to 65% ~ 80% of the normal level, and the load is adjusted to 60% ~ 90% of the normal level;

[0021] ③ Adjustment of air supply and charging system: when the air stop time is 4 to 24 hours, the ore platform is ≤70% of the normal level, and the marginal coke ratio is ≥40%; when the air stop time is longer than 24 hours, a single-ring feeding system is adopted, the ore platform is 0°, the proportion of pelletized ore is reduced, and the marginal coke ratio is ≥50%;

[0022] ④ Adjustment of air supply outlet area: adjust to 60% to 80% of the normal air supply area;

[0023] ⑤ Heat compensation for air supply furnace: through heat balance calculation, add different amounts of net coke according to the different durations of unplanned emergency wind stoppage;

[0024] ⑥ The matching of the operation system of the re-airing process: before the net coke is issued, when Ti+Si≤0.20%, the air volume ≤75%; when Ti+Si>0.20%, the air volume ≤85%; after the net coke is issued, the air volume is lower than 60% of the normal level, the ore platform adopts 0~2°, and the marginal coke accounts for ≥50%; the air volume recovers to 65%~75% of the normal level, the furnace temperature Ti+Si≥0.60%, the ore platform adopts 2~4°, and the marginal coke accounts for ≥45%; the air volume recovers to 85%~95% of the normal level, the furnace temperature Ti+Si≥0.40%, the ore platform adopts 4~6°, and the marginal coke accounts for ≥40%; the air volume recovers to the normal level, the furnace temperature Ti+Si≥0.30%, the ore platform adopts 5~7°, and the marginal coke accounts for ≥35%;

[0025] ⑦ Furnace front protection during the re-air process: the opening machine angle is reduced by 0 to 4°, and a temporary sand dam is used for iron production.

[0026] The matters not described in the following embodiments are the same as the description of the above specific implementation methods.

[0027] Example

[0028] In order to make the above characteristics and advantages of the method for rapid recovery of a high spherical ratio vanadium-titanium ore blast furnace after unplanned emergency wind down more clear and obvious, the following is combined with the attached Figure 1 A detailed implementation description is given. Taking a blast furnace for smelting high-titanium vanadium-titanium magnetite as an example, during normal production, the pellet ratio is 52% and the utilization coefficient is 2.656t / (m 3 ·d), fuel ratio 514kg / t, unplanned emergency wind stop for 52.05 hours (about 2.16 days) on January 29, 2024, using the above technology, the pellet ratio dropped to 42%, and it returned to normal after 22 hours of wind. Two days later, the utilization factor recovered to 2.793t / (m 3 ·d), fuel ratio 519kg / t, the specific implementation is as follows:

[0029] ① In case of unplanned emergency wind shutdown, stop one high-pressure cooling water supply pump and use the medium-pressure pump to supply cooling water. Block all air vents with mud and seal them. Before supplying air, poke open the blocked air vents and add circles to adjust the air vent area.

[0030] ② The accident blast furnace was supplied with air at 10:52 on January 31, 2024, with 4 air vents blocked and 8 rings added, with an air supply area of ​​0.1866m 2 (Before wind stop S = 0.2714m 2, accounting for 68.8% of the total air area), a total of 132.2t of coke was added during the air supply shift (of which 110t was added by air supply, and no coke was added later due to the forward movement, so 7.42*3=22.2t was added in 5 batches at intervals), batch weight and load were reduced to 26t and 3.5t / t, accounting for 61% and 77% of the normal values ​​respectively, single-ring distribution (ore platform 0°), edge coke accounted for 60%, and the air supply material structure was: 50% sintering + 42% pellets + 8% lump ore, of which pellets were reduced by 10%, sintering increased by 2%, and lump ore increased by 8%. After air supply, the main task is to ensure the air intake system and the single iron mouth in front of the furnace. The angle of the opening machine in front of the furnace was reduced by 2°. After the iron mouth was opened, the slag and iron could be discharged normally, and there was no freezing of the furnace cylinder. The air volume during the day shift was gradually increased to 2700m depending on the forward movement status. 3 / min, accounting for 67% of the total wind, 13:18 oxygen enrichment 2400m 3 / h, accounting for 24% of the total oxygen, coal injection at 14:33 to speed up the delivery of clean coke to the furnace.

[0031] ③ Before the delivery of net coke in the middle shift, the overall furnace temperature was low, with the average furnace temperature [Ti+Si] = 0.07%, the lowest to 0.03%, R2 = 0.99, close to the lower control limit, the main operation task is to ensure smooth operation, wait for the delivery of net coke and light load to improve the thermal potential of the furnace; after the delivery of net coke, the average furnace temperature [Ti+Si] = 0.96%, slag (TiO2) = 21%, accounting for 93% of the normal level, the main operation task is to pass the net coke, ensure smooth operation, attack the wind to improve the airflow, and ensure the discharge of sticky slag iron in front of the furnace. The air volume in the middle shift is increased to 3000m 3 / min (accounting for 75% of the total wind), the material is fed into the double ring, the ore platform is 2°, and the edge coke accounts for 50%; add to 3400m 3 / min (accounting for 85% of the total wind), the material is fed into the third ring, the ore platform is 4°, the edge coke accounts for 46%, and the highest oxygen enrichment in the middle shift is 3790m 3 / h, accounting for 37.9% of the total oxygen. 19:03 Use humidification, gradually expand the air intake area with wind speed > 270m / s as the standard, and gradually follow up with batches of heavy loads.

[0032] ④On February 1, the overall furnace temperature of the night shift was appropriate, with an average furnace temperature [Ti+Si] = 0.47%, slag (TiO2) = 20.41%, accounting for 90% of the normal level, R2 = 1.05, close to the control limit, and the main operation task was to attack the air, pass the light load charge, and gradually restore various operating parameters. During this period, the airflow distribution was reasonable, and the furnace top and throat temperatures tended to normal levels. In the late night shift, the air volume recovered to 3800m 3 / min (accounting for 95% of the total wind), oxygen-rich 4000m 3 / h, accounting for 40% of the total oxygen, the material is made into 4 rings, the ore platform is 6°, the edge coke accounts for 41.2%, and follows up with batch heavy load.

[0033] (5) The day shift quickly restores the air volume to 4000m3 based on the night shift. 3 / min or above, and gradually optimize the material structure entering the furnace, and the technical and economic indicators are close to normal levels.

[0034] For any technician familiar with the art, without departing from the scope of the technical solution of the present invention, the technical content disclosed above can be used to make many possible changes and modifications to the technical solution of the present invention, or modified into equivalent embodiments with equivalent changes. Therefore, any simple modification, equivalent change and modification made to the above embodiments according to the technical essence of the present invention without departing from the content of the technical solution of the present invention should still fall within the scope of protection of the technical solution of the present invention.

Claims

1. A method for rapid recovery of a high spherical ratio vanadium-titanium ore blast furnace after an unplanned emergency shutdown, characterized in that: The method comprises the following steps: ① Adjustment of cooling system: reduce the cooling water volume of cooling wall according to the duration of wind stoppage, and seal all air vents with mud; ② Adjust the material structure of the air supply to the furnace: the furnace charge is calculated based on the use of only vanadium-titanium sintered ore, belt-type vanadium-titanium pellets and lump ore, slag TiO2≤90% of the normal level, RO≤(normal value -0~0.05); the clinker rate is adjusted from 100% to 80%~100%, the coal load is stopped, the batch weight is adjusted to 65%~80% of the normal level, and the load is adjusted to 60%~90% of the normal level; ③ Adjustment of air supply and charging system: when the air stop time is 4 to 24 hours, the ore platform is ≤70% of the normal level, and the marginal coke ratio is ≥40%; when the air stop time is longer than 24 hours, a single-ring feeding system is adopted, the ore platform is 0°, the proportion of pelletized ore is reduced, and the marginal coke ratio is ≥50%; ④ Adjustment of air supply outlet area: adjust to 60% to 80% of the normal air supply area; ⑤ Heat compensation for blast furnace: through heat balance calculation, add different amounts of net coke according to the different durations of unplanned emergency wind stoppage; ⑥ The matching of the operation system of the re-airing process: before the net coke is issued, when Ti+Si≤0.20%, the air volume ≤75%; when Ti+Si>0.20%, the air volume ≤85%; after the net coke is issued, the air volume is lower than 60% of the normal level, the ore platform adopts 0~2°, and the marginal coke accounts for ≥50%; the air volume is restored to 65%~75% of the normal level, the furnace temperature Ti+Si≥0.60%, the ore platform adopts 2~4°, and the marginal coke accounts for ≥45%; The air volume is restored to 85% to 95% of the normal level, the furnace temperature Ti+Si ≥ 0.40%, the ore platform is 4 to 6°, and the edge coke ratio is ≥ 40%; the air volume is restored to the normal level, the furnace temperature Ti+Si ≥ 0.30%, the ore platform is 5 to 7°, and the edge coke ratio is ≥ 35%; ⑦ Furnace front guarantee for the re-air process: the opening machine angle is reduced by 0 to 4°, and a temporary sand dam is used for iron production.

2. The method according to claim 1, characterized in that In step ③, the wind-down period is 1 to 3 days, and the proportion of pellets is 40% to 45%; the wind-down period is 4 to 5 days, and the proportion of pellets is 30% to 40%; the wind-down period is 6 to 7 days, and the proportion of pellets is ≤30%.

3. The method according to claim 1, characterized in that The specific amount of net coke added in step ⑤ is: when the unplanned emergency wind break lasts 1 to 4 hours, 0 to 30 tons of coke are added; when the unplanned emergency wind break lasts 4 to 24 hours, 30 to 60 tons of coke are added; when the unplanned emergency wind break lasts 1 to 2 days, 60 to 80 tons of coke are added; when the unplanned emergency wind break lasts 2 to 3 days, 100 to 120 tons of coke are added; when the unplanned emergency wind break lasts 4 to 5 days, 140 to 180 tons of net coke are added; when the unplanned emergency wind break lasts 6 to 7 days, 200 to 240 tons of coke are added.