Construction method of cable-stayed bridge tower capable of improving crack resistance of lower cross beam
By setting up vertical cross joints and segmented casting under beams in Taichung, combined with prestressed pipelines and ultra-high performance concrete, the cracking risk and prestressed beam durability of cross beams under cable-stayed cable-stayed bridge towers on large span ballless tracks are solved. The problem has achieved the effect of improving crack resistance and reducing engineering cost.
Patent Information
- Application Number
- CN202410979065.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-22
- Publication Date
- 2024-11-01
- Estimated Expiration
- 2044-07-22
AI Technical Summary
During the construction process, the beams under the cable-stayed bridge tower with large span ballless tracks have micro cracks, large shrinkage deformation, high temperature stress, and difficult to guarantee the durability of the prestressed beam of the bearing.
The construction method of setting up vertical cross joints and sectional casting under beams in Taichung is adopted. By pre-embedding of multi-layer transverse prestressed pipelines and sectional tensioning prestressed bundles, combined with ultra-high performance concrete or fiber concrete, the temperature self-stress is reduced. and horizontal component force to improve the crack resistance of the lower beam.
It effectively reduces the cracking risk of lower beams, improves crack resistance, saves engineering cost, and ensures the durability of prestressed bundles, reduces the amount of concrete pouring, and simplifies formwork processing and stress mode.
Smart Images

Figure CN118880740A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of bridge engineering, and in particular relates to a construction method of a cable-stayed bridge tower for improving the crack resistance of a lower cross beam. Background Art
[0002] High-speed trains have relatively stringent requirements on the smoothness (deformation) control of the track. High-speed railway ballastless tracks are usually laid continuously on top of bridge structures, which requires the bridge structure to provide sufficient supporting stiffness for the track.
[0003] For long-span ballastless track cable-stayed bridges, a steel truss beam of road and rail construction is usually used to increase the vertical stiffness of the main beam, and a concrete lower crossbeam with a larger cross section is used at the cable tower to provide sufficient vertical support stiffness for the main beam. For landscape and economic considerations, long-span cable-stayed bridges usually use high-pile caps, with the top surface of the cap placed near the horizontal plane (ground). The cap also serves as the foundation for the lower crossbeam bracket. For economic considerations, in addition to the necessary navigation clearance for cross-river bridges, the bridge deck is as close to the horizontal plane as possible to reduce the bridge height and reduce investment. The low bridge deck height will result in a lower height of the lower tower column between the lower crossbeam and the cap.
[0004] Conventional large-span cross-river ballastless track cable-stayed bridge towers have a high risk of cracking under the beams. The main reasons are: (1) There are microcracks inside the concrete beams during the construction process, which are prone to cracking under the huge dead load and live load transmitted by the bearings; (2) Considering the shrinkage of concrete, the age of the pedestal is longer than that of the beams. Before the construction of the beams is completed, the shrinkage of the pedestal concrete has been basically completed. After the structural system is formed, the beams with the shortest age will produce the most shrinkage effect. Under the strong constraints of the short tower columns and pedestals, the beams are at great risk of shrinkage and cracking; (3) Since the pedestals are usually located horizontally, the pedestals are usually located horizontally. Below the surface, the temperature changes slightly, but the lower beam is exposed to solar radiation and ambient temperature, and the temperature of the structure changes greatly. In the extremely rigid frame system composed of the pedestal, the lower tower columns on both sides, and the lower beam, a large system temperature self-stress will be generated. In particular, when the ambient temperature drops, the temperature tensile stress borne by the lower tower column may cause structural cracking. (4) Among the common cable tower forms, the A-shaped tower and the inverted Y-shaped tower have a large horizontal component at the bottom of the tower column. Prestressing needs to be set in the transverse direction of the pedestal to balance the horizontal component of the tower column. However, the pedestal is located in a dry-wet alternating zone, and the durability of the prestressed beam is difficult to guarantee.
[0005] In summary, the lower cross beams of cable-stayed bridge towers, especially the lower cross beams of cable-stayed bridge towers with large spans and ballastless tracks, have the risk of cracking due to micro cracks, large shrinkage deformation, and high temperature stress during construction, and the durability of the prestressed beams of the cap is difficult to ensure. In view of this, it is necessary to propose a construction method for cable-stayed bridge towers that improves the crack resistance of the lower cross beams to solve or at least alleviate the above defects. Summary of the invention
[0006] The purpose of the present invention is to overcome the shortcomings of the prior art and provide a construction method for a cable-stayed bridge tower that improves the crack resistance of the lower beam, so as to solve the technical problem that the lower beam of the cable-stayed bridge tower in the prior art, especially the lower beam of the cable-stayed bridge tower with a large span ballastless track, has a greater risk of cracking.
[0007] In order to achieve the above object, the present invention provides the following technical solutions: A construction method for a cable-stayed bridge tower for improving the crack resistance of a lower cross beam comprises the following steps: S1: Construction of bridge pile foundation and cap steel box cofferdam; S2: tying the cap steel mesh, pre-embedding multiple layers of transverse prestressed pipes arranged at intervals along the vertical direction in the cap steel mesh, each layer of the transverse prestressed pipe layer comprising multiple transverse prestressed pipes arranged at intervals along the longitudinal direction; fixing a plurality of filling bodies for forming vertical through seams at the center line of the wide side of the cap; pouring the cap concrete, and tensioning and anchoring the first temporary prestressed tendons to some of the transverse prestressed pipes; S3: Tie the tower column steel mesh to the height of the bottom edge of the lower beam and pour concrete; cast the lower beam in sections to obtain several lower beam precast sections, each of which has several long prestressed pipes, and the long prestressed pipes of two adjacent lower beam precast sections are connected in the transverse direction, and these long prestressed pipes form a first full-length prestressed pipe; S4: Continue to construct the tower column in sections, and pre-embed a second full-length prestressed pipe corresponding to and connected to the first full-length prestressed pipe in the tower column steel mesh; the outer end of the second full-length prestressed pipe extends outward to the outside of the middle tower column; Continue to construct the tower column, middle beam and horizontal cross brace; when constructing the horizontal cross brace, tension and anchor the second temporary prestressed tendon into the remaining transverse prestressed pipe in the cap to resist the horizontal component of the lower tower column; S5: pouring the joint concrete between the first pouring segments of the lower cross beam in sequence, and tensioning the full-length prestressed beam, wherein the full-length prestressed beam runs through the first full-length prestressed pipe and the second full-length prestressed pipe, and the two ends of the full-length prestressed beam are respectively anchored on the outside of the middle tower column, and after all the full-length prestressed beams are tensioned, grouting is promptly performed to seal the first full-length prestressed pipe, the second full-length prestressed pipe and the corresponding anchor heads; While the full-length prestressed tendons are being tensioned, the first temporary prestressed tendons and the second temporary prestressed tendons are released in equal proportion and removed, and the transverse prestressed pipes are sealed by grouting; S6: Remove the steel casing cofferdam of the foundation and continue to construct the remaining cable tower structure to complete the cable tower construction.
[0008] Furthermore, the specific steps of constructing the first cast section of the lower beam in step S3 include: S31: erecting a lower crossbeam support on the top of the cap, and performing overload preloading on the lower crossbeam support; S32: erecting inner and outer side templates of the lower cross beam in sections along the transverse direction of the bridge, tying the steel mesh of the lower cross beam of each section, and pre-embedding the long prestressed pipe and the short prestressed pipe of each section, and then pouring concrete to obtain a plurality of lower cross beam precast sections arranged at intervals along the transverse direction of the bridge; According to the overall stress state of the lower cross beam, the first cast section of the lower cross beam is divided into a first cast section of the lower cross beam in the positive bending moment area and a first cast section of the lower cross beam in the negative bending moment area; the long prestressed pipe is configured according to the overall stress state of the lower cross beam; the short prestressed pipe of the first cast section of the lower cross beam in the positive bending moment area is arranged in the bottom plate, and the lower section prestressed tendons are tensioned therein when the first cast section of the lower cross beam is prefabricated; the short prestressed pipe of the first cast section of the lower cross beam in the negative bending moment area is arranged in the top plate, and the upper section prestressed tendons are tensioned therein when the first cast section of the lower cross beam is prefabricated.
[0009] Furthermore, the number of the first cast sections of the lower beam is an odd number, and a medium-length prestressed pipe is also pre-buried in the first cast sections of the lower beam; in step S5, when pouring the joint concrete between the first cast sections of the lower beam, the following steps are also included: S51: first pouring joint concrete between three lower beam precast segments located in the middle span area of the lower beam to form a first segment combination; after the joint concrete of the first segment combination reaches a certain strength, tensioning and anchoring a first permanent prestressed tendon in the middle-length prestressed pipe of the first segment combination; the first permanent prestressed tendon runs through the entire first segment combination; S52: Continue pouring the joint concrete between the first segment combination and the adjacent first-cast segment of the lower crossbeam to form a second segment combination; adjust the second segment combination at this time to the corresponding first segment combination; tension and anchor the first permanent prestressed beam in the middle-length prestressed pipe of the first segment combination; the first permanent prestressed beam runs through the entire first segment combination; S53: Repeat step S52 until the joint concrete between all the first-cast segments of the lower beams is poured, and the second permanent prestressed tendons that pass through all the first-cast segments of the lower beams are tensioned and anchored to obtain the maximum segment combination.
[0010] Furthermore, the first permanent prestressed bundle and the second permanent prestressed bundle are arranged at the upper edge, the lower edge, or both the upper and lower edges of the lower cross beam segment combination; the first segment combination can be less or not equipped with the first permanent prestressed bundle at the upper edge, and the maximum segment combination can be less or not equipped with the second permanent prestressed bundle at the lower edge.
[0011] Furthermore, the step S53 further includes the following steps: Cast the beam-column joint between the lower cross beam and the tower column; ultra-high performance concrete or fiber concrete is used to cast the upper edge of the beam-column joint within a thickness range of 10 to 20 cm.
[0012] Further, in step S5, the step of extending the first temporary prestressed tendons and the second temporary prestressed tendons in equal proportion is: The full-length prestressed beams are tensioned in batches, and the first temporary prestressed beams and / or the second temporary prestressed beams are tensioned in equal proportions at the same time; wherein, when tensioning the full-length prestressed beams of the i-th batch, the first temporary prestressed beams and / or the second temporary prestressed beams of the i-th batch corresponding number are tensioned, and the full-length prestressed beams tensioned in the i-th batch account for 15% to 35% of all the full-length prestressed beams; the proportion of the first temporary prestressed beams and / or the second temporary prestressed beams tensioned in the i-th batch to all the temporary prestressed beams is denoted as the first proportion, and the proportion of the full-length prestressed beams tensioned in the i-th batch to all the full-length prestressed beams is denoted as the second proportion, then the difference between the first proportion and the second proportion does not exceed 10%; i is a positive integer, 3≤i≤6.
[0013] Furthermore, the number of transverse prestressed pipe layers in the pedestal is 2 to 5, the uppermost layer of the transverse prestressed pipe layer is not less than 50 cm from the top surface of the pedestal, and the lowermost layer of the transverse prestressed pipe layer is not less than 100 cm from the bottom surface of the pedestal.
[0014] Furthermore, the first temporary prestressed tendons and the second temporary prestressed tendons are evenly spaced apart in the vertical direction. In step S2, the tensioned first temporary prestressed tendons account for 20% to 40% of the total number of temporary prestressed tendons.
[0015] Furthermore, in step S4, the horizontal component of the lower tower column is calculated according to the horizontal cross brace, and the second temporary prestressed beams are tensioned in batches or all at once according to the horizontal component of the lower tower column; when tensioning in batches, the first batch of second temporary prestressed beams is tensioned when the horizontal component of the tower column reaches more than 80% of the design value of the first temporary prestressed beams; when the horizontal component of the tower column reaches 80% of the tensioned temporary prestressed beams again, a new batch of second temporary prestressed beams is tensioned, and this process is repeated.
[0016] Furthermore, the vertical through-slit is disconnected along the entire cross section of the longitudinal bridge direction of the abutment, the width of the vertical through-slit is 1 to 5 cm, and the filling body is made of elastic material.
[0017] The beneficial effects of the present invention are: (1) The cap of the present invention can effectively reduce the foundation stiffness by setting a vertical through seam, avoiding the risk of cracking caused by the high temperature self-stress and secondary stress effect of the high-rigidity frame formed by the lower crossbeam, the lower tower column and the cap, and overcoming the problem that only a corbel structure with poor local stress can be used when the lower tower column is too short. The lower crossbeam of the cable tower can be widened to a cable tower structure with an ultra-short lower tower column; (2) The present invention reduces the horizontal stiffness requirement of the pile group foundation by arranging the first temporary prestressed bundle and the second temporary prestressed bundle on the cap, which is beneficial to saving the engineering cost; the cap steel casing cofferdam is removed after the first temporary prestressed bundle and the second temporary prestressed bundle are removed, thereby ensuring a dry working environment for the first temporary prestressed bundle and the second temporary prestressed bundle, and ensuring the durability of the prestressed bundle; (3) The present invention adopts the method of segmented casting of the lower cross beam, which can effectively reduce the volume of single concrete casting, solve the risk of casting interruption caused by insufficient water concrete transportation capacity, and reduce the risk of initial micro cracks in the lower cross beam caused by bracket deformation; at the same time, it is convenient to configure the segmented prestressed beams and the first and second permanent prestressed beams, and eliminates the construction of prestressed anchor teeth, which is convenient for formwork processing, and has convenient construction, reliable force and good durability; the first cast segment of the lower cross beam has a certain beam storage period before forming the system, and the concrete shrinkage is basically completed, reducing the risk of structural cracking after the bridge is completed; In short, the present invention can effectively improve the crack resistance of the lower cross beam, solve the problems of microcracks in the lower cross beam of conventional cable towers, large shrinkage deformation, cracking risks caused by high temperature stress, and difficulty in ensuring the durability of the prestressed foundation. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] The drawings constituting a part of the present invention are used to provide a further understanding of the present invention. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation of the present invention. Among them: Figure 1 is a schematic structural diagram corresponding to step S1 in an embodiment of the present invention; Figure 2 is a schematic structural diagram corresponding to step S2 in an embodiment of the present invention; Figure 3 is a structural schematic diagram corresponding to step S31 in an embodiment of the present invention; Figure 4 is a schematic structural diagram corresponding to step S32 in an embodiment of the present invention; Figure 5 This is a schematic diagram of the structure corresponding to step S4 in an embodiment of the present invention; Figure 6 is a schematic structural diagram corresponding to step S51 in an embodiment of the present invention; Figure 7It is a structural schematic diagram of a tower column in the continuous climbing formwork construction in step S4 in an embodiment of the present invention; Figure 8 This is a schematic diagram of the structure of the middle crossbeam after the step S4 of the embodiment of the invention; Fig. 9 is a schematic structural diagram corresponding to step S5 in an embodiment of the present invention; Fig.10 is a schematic structural diagram corresponding to step S6 in an embodiment of the present invention; Fig.11 It is a schematic diagram of the overall structure after forming in an embodiment of the present invention; Fig.12 is a schematic elevation view of a lower cross beam in an embodiment of the present invention; Fig.13 is a schematic plan view of a lower cross beam in an embodiment of the present invention; Fig.14 is one of the cross-sectional schematic diagrams of the lower cross beam in the embodiment of the present invention; Fig.15 The second schematic cross-sectional view of the lower cross beam in the embodiment of the present invention; Fig.16 This is the third schematic cross-sectional view of the lower cross beam in the embodiment of the present invention.
[0019] Fig.17 is a force analysis diagram of the lower cross beam in an embodiment of the present invention; Fig.18 Schematic diagram of the position of the permanent prestressed tendons of the maximum segment combination with three segments in an embodiment of the present invention.
[0020] Fig.19 Schematic diagram of the position of the permanent prestressed tendons of the maximum segment combination with 5 segments in an embodiment of the present invention.
[0021] Fig. 20 Schematic diagram of the position of the permanent prestressed tendons of the maximum segment combination with 7 segments in an embodiment of the present invention.
[0022] Fig.21 Schematic diagram of the position of permanent prestressed tendons in a maximum segment combination of 9 segments in an embodiment of the present invention.
[0023] In the figure: 10, bridge pile foundation; 20, cap steel box cofferdam; 30, cap; 310, transverse prestressed pipe layer; 311, transverse prestressed pipe; 312, water stop sleeve; 320, vertical through seam; 330, first temporary prestressed beam; 340, second temporary prestressed beam; 40, lower tower column; 50, lower crossbeam; 510, full-length prestressed beam; 520, cast-in-place bracket; 530, long prestressed pipe; 540, first cast section of lower crossbeam; 541, upper Segmental prestressed tendons; 542, lower segmental prestressed tendons; 550, first segment combination; 551, first permanent prestressed tendons; 552, second permanent prestressed tendons; 60, middle tower column; 610, horizontal cross brace; 620, beam-column joint; 630, ultra-high performance concrete; 710, transverse full-height diaphragm; 720, first longitudinal web; 730, transverse half-height diaphragm; 740, support and pad stone; 810, middle cross beam; 820, upper tower column; 830, tower crown. DETAILED DESCRIPTION
[0024] The technical solutions in the embodiments of the present invention are described clearly and completely below. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field belong to the scope of protection of the present invention.
[0025] In the description of the present invention, the terms "longitudinal", "lateral", "upper", "lower", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings. They are only for the convenience of describing the present invention and do not require that the present invention must be constructed and operated in a specific orientation. Therefore, they should not be understood as limitations on the present invention. The terms "connected" and "connected" used in the present invention should be understood in a broad sense. For example, they can be fixed connections or detachable connections; they can be directly connected or indirectly connected through intermediate components. For ordinary technicians in this field, the specific meanings of the above terms can be understood according to specific circumstances.
[0026] The present invention will be described in detail below with reference to the accompanying drawings and in combination with embodiments. It should be noted that the embodiments and features in the embodiments of the present invention can be combined with each other without conflict.
[0027] like Figures 1 to 16 As shown, a construction method for a cable-stayed bridge tower for improving the crack resistance of a lower beam comprises the following steps: S1: Construction of bridge pile foundation 10 and cap steel box cofferdam 20; S2: Tie up the steel mesh of the cap 30, and embed multiple layers of transverse prestressed pipe layers 310 arranged at intervals along the vertical direction in the steel mesh of the cap 30, each layer of the transverse prestressed pipe layer 310 includes multiple transverse prestressed pipes 311 arranged at intervals along the longitudinal bridge direction; fix a number of filling bodies (not shown) for forming vertical through seams 320 at the center line of the wide side of the cap 30; pour concrete for the cap 30, and after the concrete reaches 75% of the design strength, tension and anchor the first temporary prestressed tendons 330 to some of the transverse prestressed pipes 311; wherein, the concrete reaching 75% of the design strength is a preferred value, and those skilled in the art can also set it to other values according to actual needs; S3: Tie the steel mesh of the lower tower column 40 in sections and pour concrete to obtain the lower tower column 40, and construct the lower tower column 40 to the height of the bottom edge of the lower cross beam 50; The steel mesh of the lower cross beam 50 is tied in sections and a plurality of first full-length prestressed pipes arranged at intervals along the vertical direction are pre-buried in the steel mesh of the lower cross beam 50, and then the lower cross beam 50 is cast in sections to obtain the lower cross beam pre-cast sections 540; a plurality of long prestressed pipes 530 are constructed in each lower cross beam pre-cast section 540, and the long prestressed pipes 530 of two adjacent lower cross beam pre-cast sections 540 are connected in the transverse direction, and these long prestressed pipes 530 form a first full-length prestressed pipe; the first full-length prestressed pipe extends in the transverse direction as a whole, and is used for the corresponding full-length prestressed bundle 510 to penetrate; S4: Tie up the steel mesh of the middle tower column 60 in sections and pre-embed the second full-length prestressed pipe in the steel mesh of the middle tower column 60 corresponding to the first full-length prestressed pipe. Continue to construct the middle tower column 60 and the middle cross beam 810 of the arch frame, and set a plurality of horizontal cross braces 610 arranged at intervals along the vertical direction in the middle area of the middle tower column 60. When constructing the horizontal cross braces, tension and anchor the second temporary prestressed beam 340 into the remaining transverse prestressed pipe 311 in the pedestal 30 to resist the horizontal component of the lower tower column 40. The water of the structure The horizontal force increases with the increase of the number of horizontal cross braces. It is ideal to tension a certain number of second temporary prestressed tendons 340 each time a horizontal cross brace is constructed. In view of the complexity of the construction, it is possible to consider tensioning the second temporary prestressed tendons 340 at one time before constructing the first horizontal cross brace. The second full-length prestressed pipe includes a first end (not shown) and a second end (not shown) which are arranged opposite to each other. The first end extends inwardly and connects with the first full-length prestressed pipe, and the second end extends outwardly to the outside of the middle tower column 60. S5: pouring the joint concrete between the first pouring segments 540 of the lower cross beam in sequence, and tensioning the full-length prestressed bundle 510, wherein the full-length prestressed bundle 510 runs through the first full-length prestressed pipe and the second full-length prestressed pipe, and the two ends of the full-length prestressed bundle 510 are respectively anchored to the outside of the middle tower column 60, and after all the full-length prestressed bundles 510 are tensioned, grouting is performed in time to seal the first full-length prestressed pipe, the second full-length prestressed pipe and the corresponding anchor heads; step S4 and step S5 can be performed simultaneously; While the full-length prestressed bundle 510 is being stretched, the first temporary prestressed bundle 330 and the second temporary prestressed bundle 340 are released in equal proportion and removed, and the transverse prestressed pipe 311 is sealed by grouting; S6: Remove the steel casing cofferdam 20 of the cap, and continue to construct the remaining cable tower structure to complete the cable tower construction; the remaining cable tower structure includes conventional components such as the upper tower column 820, the tower crown 830, the support and the cushion stone 740, which will not be described in detail here.
[0028] The present application reduces the horizontal stiffness requirement of the pile group foundation by arranging the first temporary prestressed bundle 330 and the second temporary prestressed bundle 340 on the pedestal 30, which is beneficial to saving the project cost; the pedestal steel casing cofferdam 20 is removed after the first temporary prestressed bundle 330 and the second temporary prestressed bundle 340 are removed, thereby ensuring a dry working environment for the first temporary prestressed bundle 330 and the second temporary prestressed bundle 340 and ensuring the durability of the prestressed bundles.
[0029] like Figures 2 to 11 As shown, by fixing a filling body for forming a vertical through-slit 320 at the transverse center of the pedestal 30, that is, the filling body is filled in the vertical through-slit 320, a vertical through-slit 320 can be formed in the transverse center of the pedestal 30 after pouring the concrete of the pedestal 30; the pedestal 30 of the present application adopts the vertical through-slit 320 treatment, which can effectively reduce the foundation stiffness, avoid the risk of cracking caused by the high temperature self-stress and secondary stress effect of the high-rigidity frame formed by the lower crossbeam 50, the lower tower column 40 and the pedestal 30, and overcome the problem that only a corbel structure with poor local stress can be used when the lower tower column is too short (a cable tower with a too short lower tower column cannot be provided with a lower crossbeam, otherwise the temperature stress will be too large and cracking will occur, and a corbel is usually used instead, but the use of a corbel will result in poor local stress), and the lower crossbeam 50 of the cable tower can be set to a cable tower structure widened to an ultra-short lower tower column 40.
[0030] In addition, the vertical through seams 320 are provided on the pedestal 30 to make the stress mode of the structure clearer and eliminate the influence of the structural temperature secondary internal force. The temporary prestressed beam can be used to balance the horizontal force of the tower column. After the construction of the lower crossbeam 50 is completed, the horizontal force of the tower column is transferred to the lower crossbeam 50. After the first temporary prestressed beam 330 and the second temporary prestressed beam 340 are removed, the pedestal steel casing cofferdam 20 is removed to avoid the difficulty of underwater prestressed beam maintenance. There is no need to set permanent prestressed beams in the pedestal 30. Therefore, there will be no problem that the durability of the prestressed beams of the conventional pedestal 30 is difficult to ensure. Compared with the conventional cable tower structure, it has significant advantages from the perspective of stress, economy and structural durability.
[0031] As a good example, Figures 2 to 11 As shown, the vertical through-slit 320 is disconnected along the longitudinal bridge direction of the pedestal 30, and the width of the vertical through-slit 320 is 1-5 cm. The filling body is made of elastic material, which can be one or more of asphalt hemp, asphalt oil felt, and rubber sheet.
[0032] As a preferred example, Figure 2 As shown, after pre-embedding multiple layers of transverse prestressed pipe layers 310 arranged along the vertical interval in the steel mesh of the base 30 in step S2, the step also includes: setting a water stop sleeve 312 near the vertical through-slit 320 of each transverse prestressed pipe 311; wherein the water stop sleeve 312 is sealingly sleeved on the peripheral wall of the transverse prestressed pipe 311; by setting the water stop sleeve 312, water seepage from the vertical through-slit 320 can be effectively prevented from entering the transverse prestressed pipe 311 and affecting the durability of the temporary prestressed bundle.
[0033] like Figure 4 As shown, the number of layers of the transverse prestressed pipe layer 310 in the cap 30 is 2 to 5, the uppermost layer of the transverse prestressed pipe layer 310 is not less than 50 cm from the top surface of the cap 30, and the lowermost layer of the transverse prestressed pipe layer 310 is not less than 100 cm from the bottom surface of the cap 30. It can be understood that the number of layers of the transverse prestressed pipe layer 310 is 2 to 5, which is the preferred number of layers. The multi-layer transverse prestressed pipe layer 310 can be evenly spaced in the vertical direction. In other embodiments, those skilled in the art can also set it to a specific number of layers or other numbers of layers according to actual needs.
[0034] As a preferred example, the specific steps of constructing the lower beam precast segment 540 in step S3 include: S31: Figure 3 As shown, a lower crossbeam support 520 is set up on the top of the platform 30, and the lower crossbeam support 520 is overloaded and pre-pressed; S32: erecting inner and outer formworks of the lower cross beam 50 in sections along the transverse direction of the bridge, tying the steel mesh of the lower cross beam 50 of each section, and pre-embedding the long prestressed pipe 530 of each section, and then pouring concrete to obtain a plurality of lower cross beam precast sections 540 arranged at intervals along the transverse direction of the bridge; like Fig.17 As shown, according to the overall stress state of the lower beam 50, the lower beam precast segment 540 is divided into a lower beam precast segment in a positive bending moment area and a lower beam precast segment in a negative bending moment area; the prestressed pipe is configured according to the overall stress state of the lower beam 50; The short prestressed pipe of the first cast section of the lower beam in the positive bending moment area is set in the bottom plate, and the lower segment prestressed bundle 541 is tensioned inside the first cast section of the lower beam when it is prefabricated; the short prestressed pipe of the first cast section of the lower beam in the negative bending moment area is set in the top plate, and the upper segment prestressed bundle 541 is tensioned inside the first cast section of the lower beam when it is prefabricated.
[0035] like Fig.17 As shown, Fig.17 It includes a force diagram of the lower cross beam 50; specifically, the prestress of the lower cross beam 50 should take into account the effects of the horizontal component of the tower column and the reaction force of the support of the lower cross beam 50, that is, there is still a certain surplus after balancing the horizontal component of the tower column, so as to withstand the bending moment caused by the reaction force of the top support of the lower cross beam 50, and ensure that the upper and lower edge concrete of the lower cross beam 50 is not subjected to tension under the limit state of normal use; therefore, in this embodiment, a corresponding short prestressed pipe is pre-buried at the bottom of the segment located in the mid-span area of the lower cross beam (positive bending moment area) for the lower segment prestressed bundle 541 to pass through; a corresponding short prestressed pipe is pre-buried at the top of the segment in the root area of the lower cross beam (negative bending moment area) for the upper segment prestressed bundle 541, and finally ensure that the upper and lower edge concrete of the lower cross beam 50 is not subjected to tension under the limit state of normal use.
[0036] As a preferred embodiment, Figures 12 to 16 As shown, each lower beam precast segment 540 is a box-section concrete structure; Fig.12 , Fig.13 The joint concrete has not yet been poured. Fig.13 The embedded channel in the middle is schematically marked, and the embedded channels at the front and rear sides are not drawn; Fig.14 The cross-sectional view of the first cast section 540 of the lower beam corresponding to the transverse full-height partition 710 is shown in FIG. Fig.15 The cross-sectional view of the first cast section 540 of the lower beam corresponding to the transverse half-height partition 730 is shown in FIG. Fig.16 It is a cross-sectional view of the first cast segment 540 of the lower beam without a partition.
[0037] There are three kinds of embedded channels in the first cast section 540 of the lower cross beam, namely, a long prestressed pipe for the full-length prestressed bundle 510 to pass through, a short prestressed pipe for the upper segment prestressed bundle 541 or the lower segment prestressed bundle 542 to pass through, and a medium-length prestressed pipe for the first permanent prestressed bundle 551 or the second permanent prestressed bundle 552 to pass through. These embedded channels are arranged in the top plate, bottom plate and web plate of the box-shaped first cast section cross beam 540 of the lower cross beam as required; the full-length prestressed bundle 510 passes through the lower cross beam, and its end is anchored on the outside of the middle tower column, and this embedded channel is arranged in the tower column. The through-length prestressed bundle 510 is a conventional practice in the art; the first permanent prestressed bundle 551 runs through several lower beam precast segments 540; the second permanent prestressed bundle 552 runs through all lower beam precast segments 540; the upper segment prestressed bundle 541 and the lower segment prestressed bundle 542 are arranged on a single lower beam precast segment 540; in the present invention, the arrangement of the upper segment prestressed bundle 541, the lower segment prestressed bundle 542, the first permanent prestressed bundle 551, and the second permanent prestressed bundle 552 can effectively resist the positive bending moment in the mid-span area of the lower beam (the bending moment diagram of the lower beam is shown in Fig.17 ), the present invention can effectively reduce the number of full-length prestressed tendons 510 configured and the total amount of prestressed steel tendons used, thereby reducing the project cost by arranging the above-mentioned prestressed tendons that match the internal force (bending moment) of the completed bridge in the early stage; and the upper segment prestressed tendons 541, the lower segment prestressed tendons 542, the first permanent prestressed tendons 551, and the second permanent prestressed tendons 552 do not need to be made into anchor teeth blocks, and the structure is simple, the construction is convenient, the force is reliable, and the durability is good.
[0038] In this embodiment, the lower cross beam 50 adopts a box-shaped concrete section with a top plate with longitudinal and transverse partitions, which can effectively distribute the vertical force to the webs and partitions of the lower cross beam 50, and can prevent the local stress deformation of the top plate from being too large and causing cracks; in addition, the transverse full-height partition 710 and the transverse half-height partition 730 can both meet the requirements of force transmission (the shear force can be transmitted to the web to make the web evenly stressed), and at the same time, the transverse half-height partition 730 has a simple structure and saves materials. By arranging the transverse full-height partition 710 and the transverse half-height partition 730, the partition steel bars do not need to be anchored in the bottom plate of the lower cross beam first cast section 540 where the steel bars and prestressed tendons are densely distributed. In particular, the transverse half-height partition 730 reduces the cross-embedded steel bars, making it easier to ensure the construction quality, and the vertical force transmission effect is equivalent to that of the transverse full-height partition 710; in a preferred example, torsional force usually only requires one transverse full-height partition 710. The possibility of later cracking of the transverse full-height partition 710 due to uneven stress on the connected panels is avoided.
[0039] As a preferred embodiment, the number of the first cast segments 540 of the lower beam is an odd number (3, 5, 7, 9, ...) not less than 3, and a certain width of post-cast joints is set between the segments, which can be set according to actual needs; in step S5, when pouring the joint concrete between the first cast segments 540 of the lower beam, the following steps are also included: S51: Figure 6 As shown, the joint concrete between the three lower beam precast segments 540 located in the middle span area of the lower beam is first poured to form a first segment combination 550. After the joint concrete of the first segment combination 550 reaches 75% of the design strength, the first permanent prestressed beam 551 is tensioned and anchored in the prestressed middle channel of the first segment combination 550. The first permanent prestressed beam 551 runs through the entire first segment combination. S52: Continue pouring the joint concrete between the first segment combination 550 and the adjacent lower beam first cast segment 540 to form a second segment combination; adjust the second segment combination at this time to the corresponding first segment combination; tension and anchor another first permanent prestressed beam in the middle-length prestressed pipe of the first segment combination; the first permanent prestressed beam runs through the entire first segment combination; S53: repeat step S52 until the joint concrete between all the first-cast segments of the lower beams is poured, and the second permanent prestressed tendons that pass through all the first-cast segments of the lower beams are tensioned and anchored to obtain the maximum segment combination; According to the stress condition of the lower cross beam 50, the first permanent prestressed beam is only tensioned in the first cast segment of the lower cross beam in the positive bending moment area, and the first permanent prestressed beam is arranged in the bottom plate of the largest segment combination; the second permanent prestressed beam is arranged in the top plate of the largest segment combination; the first permanent prestressed beam 551 and the second permanent prestressed beam 552 are calculated according to the length of the lower cross beam, and the first permanent prestressed beam 551 and the second permanent prestressed beam 552 are arranged at a position close to the edge of the concrete, and can be staggered left and right if the spatial position permits, and can be divided into one or more layers; the first permanent prestressed beam 551 and the second permanent prestressed beam 552 are arranged at the upper edge, the lower edge, or both the upper and lower edges of the lower cross beam segment combination; the first segment combination can be less equipped with or not equipped with the first permanent prestressed beam 551 at the upper edge; the largest segment combination can be less equipped with or not equipped with the second permanent prestressed beam 552 at the lower edge; the prestressed beams in the corresponding area should be tensioned in time after pouring any joint, otherwise there will be a risk of cracking at the joint. It is worth noting that the present embodiment adopts segmented casting of the lower beam 50, which can effectively reduce the single concrete pouring volume, solve the risk of pouring interruption caused by insufficient water concrete transportation capacity, and reduce the risk of initial micro cracks in the lower beam 50 caused by bracket deformation; at the same time, it is convenient to configure prestressed in sections, and eliminates the structure of prestressed anchor tooth blocks, which is convenient for formwork processing; the first cast segment 540 of the lower beam has a certain beam storage period before the system is formed, and the concrete shrinkage is basically completed, reducing the risk of structural cracking after the bridge is completed.
[0040] In one embodiment, the lower cross beam 50 has three sections, such as Fig.18 As shown, the lower beam mid-span area (positive bending moment area) has a lower beam pre-cast segment 540, and the lower beam root area (negative bending moment area) has two lower beam pre-cast segments 540; when pouring the joint concrete, since only one pouring is required, the first stage combination 550 is the largest segment combination, and the first permanent prestressed beam 551 of the first segment combination 550 is also the second permanent prestressed beam 551 of the largest segment combination.
[0041] In a preferred example, the lower cross beam 50 has five sections. Fig.17 , Fig.19 As described, the lower beam mid-span area (positive bending moment area) has three lower beam pre-cast segments 540, and the lower beam root area (negative bending moment area) has two lower beam pre-cast segments 540; when pouring the joint concrete, first pour the two joints of the three lower beam pre-cast segments 540 in the mid-span area, and at the same time tension and anchor the first permanent prestressed beam 551 to the middle and long prestressed pipe of the first segment combination 550; then pour the joints of the lower beam pre-cast segments 540 between the mid-span area and the root area, tension and anchor the second permanent prestressed beam 552 that runs through the five lower beam pre-cast segments 540, to obtain the maximum segment combination. Fig.19In the embodiment, each time the first permanent prestressed tendon 551 and the second permanent prestressed tendon 552 are tensioned, tension is applied to both the upper edge and the lower edge of the segment assembly.
[0042] In another example, if Fig. 20 As shown, the lower beam 50 has 7 sections; when pouring the joint concrete, first pour the two joints of the three lower beam precast sections 540 in the mid-span area, and at the same time tension and anchor the first permanent prestressed tendon 551 to the middle-length prestressed pipe of the first section combination 550; then pour the joints between the adjacent lower beam precast sections 540, tension the first permanent prestressed tendon 551; finally pour the lower beam precast section 540 at the root of the lower beam, and tension the second permanent prestressed tendon. In another example, Fig.21 As shown, the lower cross beam 50 has 9 segments. It is assumed that the mid-span area (positive bending moment area) of the lower cross beam has five lower cross beam pre-cast segments 540, and the root area (negative bending moment area) of the lower cross beam has four lower cross beam pre-cast segments 540; when pouring the joint concrete, first pour the two joints of the three lower cross beam pre-cast segments 540 in the mid-span area, and then pour the joints between the adjacent lower cross beam pre-cast segments 540 section by section. In this process, the first segment combination is 3 segments, 5 segments, and 7 segments, respectively, and the first permanent prestressed beam 551 is tensioned 3 times in total; finally, the joint concrete between all the lower cross beam pre-cast segments is poured, and the second permanent prestressed beam 552 is tensioned at the upper and lower edges to obtain the maximum segment combination.
[0043] As a preferred implementation, the step S53 further includes the following steps: Cast the beam-column joint 620 between the lower cross beam 50 and the tower column; ultra-high performance concrete 630 (UHPC) or fiber concrete is used for casting within a thickness range of 10 to 20 cm at the upper edge of the beam-column joint 620; in this embodiment, a casting material with good crack resistance is used in a certain range of the top plate corresponding to the negative bending moment area at both ends of the lower cross beam 50, and UHPC or fiber concrete with excellent crack resistance is used to replace the shrinkage compensation concrete to resist the tensile stress that may occur during operation, thereby enhancing the crack resistance of the lower cross beam 50, and the full-length prestressed tendon 510 is tensioned after strong post-tensioning; Fig.12 Ultra high performance concrete 630 is schematically depicted in FIG.
[0044] As a preferred embodiment, the beam-column joint 620 adopts a tongue-and-groove joint or a serrated joint, which increases the bite force and bonding force between the precast concrete and the post-cast joint, improves the reliability of the joint connection of the lower cross beam 50, and further enhances the crack resistance of the lower cross beam 50.
[0045] As a preferred embodiment, in step S5, the steps of proportionally extending the first temporary prestressed bundle 330 and the second temporary prestressed bundle 340 are as follows: The full-length prestressed beams 510 are tensioned in batches, and the first temporary prestressed beams 330 and / or the second temporary prestressed beams 340 are tensioned in equal proportions at the same time; wherein, when the full-length prestressed beams 510 of the i-th batch are tensioned, the first temporary prestressed beams 330 and / or the second temporary prestressed beams 340 corresponding to the i-th batch are tensioned, and the full-length prestressed beams 510 tensioned in the i-th batch account for 15% to 35% of all the full-length prestressed beams 510; the proportion of the first temporary prestressed beams 330 and / or the second temporary prestressed beams 340 tensioned in the i-th batch to all the temporary prestressed beams is recorded as a first proportion, and the proportion of the full-length prestressed beams 510 tensioned in the i-th batch to all the full-length prestressed beams 510 is recorded as a second proportion, and the difference between the first proportion and the second proportion does not exceed 10%; i is a positive integer, 3≤i≤6; Those skilled in the art should know that, during the upward construction of the tower column, as the weight of the tower column increases, the horizontal force component gradually increases. Preferably, the second temporary prestressed tendons 340 are tensioned in batches as the tower column is constructed upward. For the convenience of construction, the tensioning can be divided into 1 to 3 times. Before the joints between the first cast sections 540 of the lower cross beam are cast, the horizontal force of the tower column is borne by the temporary prestress (the first temporary prestressed beam 330 and the second temporary prestressed beam 340) in the cap 30. By tensioning the full-length prestressed beam 510 in batches and releasing the first temporary prestressed beam 330 and the second temporary prestressed beam 340 in the cap 30, the horizontal force of the tower column can be gradually transferred from the cap 30 to the lower cross beam 50. If the full-length prestressed beam 510 is tensioned in one step and then all the temporary prestressed beams in the cap 30 are released, there will be a sudden change in the stress of the structural system. When the temporary prestressed beams in the cap 30 are released, the axial prestress of the lower cross beam 50 will be significantly reduced. In order to ensure the permanent prestress, the full-length prestressed beam 510 needs to be over-tensioned, which will lead to the risk of excessive pressure damage to the concrete of the lower cross beam 50. At the same time, over-tensioning may require the configuration of more steel beams, which is not conducive to the saving of prestressed beams.
[0046] As a preferred embodiment, the first temporary prestressed bundles 330 and the second temporary prestressed bundles 340 are evenly spaced vertically; in step S2, the tensioned first temporary prestressed bundles 330 account for 20% to 40% of the total number of temporary prestressed bundles.
[0047] As a preferred embodiment, in step S4, the horizontal force component of the lower tower column 40 is calculated according to the horizontal cross brace 610, and the second temporary prestressed beam 340 is tensioned in batches or all at once according to the horizontal force component of the lower tower column 40; usually, the function of the horizontal cross brace 610 is to resist the bending moment of the inclined tower column overturning inward, so that the tower column load is transmitted along the axial direction of the tower column as much as possible, that is, it is approximately considered that the bottom of the tower column only bears the axial force along the direction of the tower column, and the horizontal force component of the tower column can be calculated by geometric relationship; that is, when the axial force of the tower column is P, when the tower column is tilted inward at an angle α, the horizontal force component is P*sinα, and when the horizontal force component reaches more than 80% of the design value of the first temporary prestressed beam 330, consider tensioning the first batch of second temporary prestressed beams 340, and when the P value continues to increase and reaches 80% of the stretched temporary prestressed beams again, a new batch of second temporary prestressed beams 340 are tensioned, and so on. By adopting this embodiment, the tensioning timing and tensioning batches can be quickly determined, thereby improving construction efficiency and reducing structural secondary internal forces (such as pile foundation shear force, etc.) caused by temporary prestressing while ensuring the safety and reliability of the structure.
[0048] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention are within the scope of protection of the pending claims of the present invention.
Claims
1. A construction method for a cable-stayed bridge tower for improving the crack resistance of a lower cross beam, characterized in that: Includes steps: S1: Construction of bridge pile foundation and cap steel box cofferdam; S2: tying the cap steel mesh, pre-embedding multiple layers of transverse prestressed pipes arranged at intervals along the vertical direction in the cap steel mesh, each layer of the transverse prestressed pipe layer comprising multiple transverse prestressed pipes arranged at intervals along the longitudinal direction; fixing a plurality of filling bodies for forming vertical through seams at the center line of the wide side of the cap; pouring the cap concrete, and tensioning and anchoring the first temporary prestressed tendons to some of the transverse prestressed pipes; S3: Tie the tower column steel mesh to the height of the bottom edge of the lower beam and pour concrete; cast the lower beam in sections to obtain several lower beam precast sections, each of which has several long prestressed pipes, and the long prestressed pipes of two adjacent lower beam precast sections are connected in the transverse direction, and these long prestressed pipes form a first full-length prestressed pipe; S4: Continue to construct the tower column in sections, and pre-embed a second full-length prestressed pipe corresponding to and connected to the first full-length prestressed pipe in the tower column steel mesh; the outer end of the second full-length prestressed pipe extends outward to the outside of the middle tower column; Continue to construct the tower column, middle beam and horizontal cross brace; when constructing the horizontal cross brace, tension and anchor the second temporary prestressed tendon into the remaining transverse prestressed pipe in the cap to resist the horizontal component of the lower tower column; S5: pouring the joint concrete between the first pouring segments of the lower cross beam in sequence, and tensioning the full-length prestressed beam, wherein the full-length prestressed beam runs through the first full-length prestressed pipe and the second full-length prestressed pipe, and the two ends of the full-length prestressed beam are respectively anchored on the outside of the middle tower column, and after all the full-length prestressed beams are tensioned, grouting is promptly performed to seal the first full-length prestressed pipe, the second full-length prestressed pipe and the corresponding anchor heads; While the full-length prestressed tendons are being tensioned, the first temporary prestressed tendons and the second temporary prestressed tendons are released in equal proportion and removed, and the transverse prestressed pipes are sealed by grouting; S6: Remove the steel casing cofferdam of the foundation and continue to construct the remaining cable tower structure to complete the cable tower construction.
2. The construction method of a cable-stayed bridge tower for improving the crack resistance of the lower beam according to claim 1, characterized in that: The specific steps of constructing the first cast section of the lower beam in step S3 include: S31: erecting a lower crossbeam support on the top of the cap, and performing overload preloading on the lower crossbeam support; S32: erecting inner and outer side templates of the lower cross beam in sections along the transverse direction of the bridge, tying the steel mesh of the lower cross beam of each section, and pre-embedding the long prestressed pipe and the short prestressed pipe of each section, and then pouring concrete to obtain a plurality of lower cross beam precast sections arranged at intervals along the transverse direction of the bridge; According to the overall stress state of the lower cross beam, the first cast section of the lower cross beam is divided into a first cast section of the lower cross beam in the positive bending moment area and a first cast section of the lower cross beam in the negative bending moment area; the long prestressed pipe is configured according to the overall stress state of the lower cross beam; the short prestressed pipe of the first cast section of the lower cross beam in the positive bending moment area is arranged in the bottom plate, and the lower section prestressed tendons are tensioned therein when the first cast section of the lower cross beam is prefabricated; the short prestressed pipe of the first cast section of the lower cross beam in the negative bending moment area is arranged in the top plate, and the upper section prestressed tendons are tensioned therein when the first cast section of the lower cross beam is prefabricated.
3. The construction method of a cable-stayed bridge tower for improving the crack resistance of the lower beam according to claim 2, characterized in that: The number of the first cast sections of the lower beam is an odd number, and a medium-length prestressed pipe is also pre-buried in the first cast sections of the lower beam; in step S5, when pouring the joint concrete between the first cast sections of the lower beam, the following steps are also included: S51: first pouring joint concrete between three lower beam precast segments located in the middle span area of the lower beam to form a first segment combination; after the joint concrete of the first segment combination reaches a certain strength, tensioning and anchoring a first permanent prestressed tendon in the middle-length prestressed pipe of the first segment combination; the first permanent prestressed tendon runs through the entire first segment combination; S52: Continue pouring the joint concrete between the first segment combination and the adjacent first-cast segment of the lower crossbeam to form a second segment combination; adjust the second segment combination at this time to the corresponding first segment combination; tension and anchor the first permanent prestressed beam in the middle-length prestressed pipe of the first segment combination; the first permanent prestressed beam runs through the entire first segment combination; S53: Repeat step S52 until the joint concrete between all the first-cast segments of the lower beams is poured, and the second permanent prestressed tendons that pass through all the first-cast segments of the lower beams are tensioned and anchored to obtain the maximum segment combination.
4. The construction method of a cable-stayed bridge tower for improving the crack resistance of the lower cross beam according to claim 3, characterized in that: The first permanent prestressed tendon and the second permanent prestressed tendon are arranged at the upper edge, the lower edge, or both the upper and lower edges of the lower cross beam segment combination; the first segment combination can be less or not equipped with the first permanent prestressed tendon at the upper edge, and the largest segment combination can be less or not equipped with the second permanent prestressed tendon at the lower edge.
5. The construction method of a cable-stayed bridge tower for improving the crack resistance of the lower beam according to claim 3, characterized in that: The step S53 further includes the following steps: Cast the beam-column joint between the lower cross beam and the tower column; ultra-high performance concrete or fiber concrete is used to cast the upper edge of the beam-column joint within a thickness range of 10 to 20 cm.
6. The construction method of a cable-stayed bridge tower for improving the crack resistance of a lower cross beam according to claim 1, characterized in that: In step S5, the steps of extending the first temporary prestressed tendons and the second temporary prestressed tendons in equal proportion are: The full-length prestressed beams are tensioned in batches, and the first temporary prestressed beams and / or the second temporary prestressed beams are tensioned in equal proportions at the same time; wherein, when tensioning the full-length prestressed beams of the i-th batch, the first temporary prestressed beams and / or the second temporary prestressed beams of the i-th batch corresponding number are tensioned, and the full-length prestressed beams tensioned in the i-th batch account for 15% to 35% of all the full-length prestressed beams; the proportion of the first temporary prestressed beams and / or the second temporary prestressed beams tensioned in the i-th batch to all the temporary prestressed beams is denoted as the first proportion, and the proportion of the full-length prestressed beams tensioned in the i-th batch to all the full-length prestressed beams is denoted as the second proportion, then the difference between the first proportion and the second proportion does not exceed 10%; i is a positive integer, 3≤i≤6.
7. The construction method of a cable-stayed bridge tower for improving the crack resistance of a lower cross beam according to claim 1, characterized in that: The number of transverse prestressed pipe layers in the pedestal is 2 to 5, the uppermost layer of the transverse prestressed pipe layer is not less than 50 cm from the top surface of the pedestal, and the lowermost layer of the transverse prestressed pipe layer is not less than 100 cm from the bottom surface of the pedestal.
8. The construction method of a cable-stayed bridge tower for improving the crack resistance of a lower cross beam according to claim 1, characterized in that: The first temporary prestressed tendons and the second temporary prestressed tendons are evenly spaced apart in the vertical direction. In step S2, the tensioned first temporary prestressed tendons account for 20% to 40% of the total number of temporary prestressed tendons.
9. The construction method of a cable-stayed bridge tower for improving the crack resistance of a lower cross beam according to claim 1, characterized in that: In step S4, the horizontal component of the lower tower column is calculated according to the horizontal cross brace, and the second temporary prestressed beam is tensioned in batches or all at once according to the horizontal component of the lower tower column; when tensioning in batches, the first batch of second temporary prestressed beams is tensioned when the horizontal component of the tower column reaches more than 80% of the design value of the first temporary prestressed beam; when the horizontal component of the tower column reaches 80% of the tensioned temporary prestressed beam again, a new batch of second temporary prestressed beams is tensioned, and this process is repeated.
10. The construction method of a cable-stayed bridge tower for improving the crack resistance of a lower cross beam according to claim 1, characterized in that: The vertical through seam is disconnected along the longitudinal bridge direction of the abutment. The width of the vertical through seam is 1 to 5 cm. The filling body is made of elastic material.
Citation Information
Patent Citations
Construction method for preventing vertical cracks of platform body
CN107642043A
Construction method and system for pier bottom rotation of wide-plate type pier
CN108374352A
Control construction method for bottom stress of inclined tower column of cable-stayed bridge
CN108625286A
Self-supporting cast-in-place construction method for concrete beam of cable-stayed bridge
CN112878197A
Prestressed steel-concrete bearing platform structure of continuous rigid frame bridge and construction method of prestressed steel-concrete bearing platform structure
CN114922054A