An automatic monitoring device for deep displacement of deep foundation pit
By introducing an automated processing system into the deep displacement monitoring device of deep foundation pit, the problem of water accumulation in inclined tubes is solved, and more accurate and stable monitoring data is achieved, the equipment life is extended, and the risks brought about by water accumulation are avoided.
Patent Information
- Application Number
- CN202411382056.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-30
- Publication Date
- 2024-11-29
- Estimated Expiration
- 2044-09-30
AI Technical Summary
The existing deep-level displacement monitoring device of deep foundation pit cannot effectively deal with the accumulated water inside the inclined measuring tube, resulting in inaccurate monitoring and unstable monitoring and increasing the risk of equipment damage.
An automated monitoring device including a control box, water pump, water pump, water pump, probe, filter probe, flushing mechanism, cleaning mechanism, anti-offset mechanism and mud scraping mechanism is designed to treat water accumulation through functions such as pumping, filtration, flushing and cleaning. , ensure the clean and stable interior of the inclined tube.
It effectively reduces the impact of water pressure on soil, improves the accuracy and reliability of monitoring data, prevents equipment damage caused by water accumulation, extends the service life of the equipment, and improves the stability and accuracy of the test results.
Smart Images

Figure CN118880846B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of construction monitoring, and in particular to an automatic monitoring device for deep displacement of a deep foundation pit. Background Art
[0002] Deep pit deep displacement refers to the phenomenon that the soil around the foundation pit moves due to the deformation of the rock and soil and the change of soil pressure during the excavation of the foundation pit. The size of the displacement is related to factors such as the mechanical properties of the rock and soil, the excavation method of the foundation pit, and the surrounding environmental conditions.
[0003] The basic principle of deep horizontal displacement monitoring is to measure the deep horizontal displacement of soil and surrounding structures through a borehole inclinometer. Specifically, when the measured soil is deformed, the axis of the inclinometer tube will produce deflection. At this time, the inclinometer is used to measure the change in the angle between the axis of the inclinometer tube and the plumb line, so as to obtain the horizontal displacement of each point inside the soil. In horizontal displacement monitoring, the inclinometer tube is usually divided into several sections, and then the inclinometer is used to measure the inclination angle between the axis of the probe and the plumb line on different measuring sections, and then the horizontal displacement of each measuring section is calculated. This monitoring method can continuously and segment by segment measure the angle between the axis of the inclinometer tube and the plumb line or horizontal line after the displacement, and then calculate the horizontal displacement (vertical burial of the inclinometer tube) or vertical displacement (horizontal burial of the inclinometer tube) in sections, and accumulate the total displacement.
[0004] After searching, the national patent publication number CN116623728A discloses a deep foundation pit ground-connected wall deep horizontal displacement monitoring device, which includes a support device, a monitoring device and a carrier, and the carrier is arranged on the support device. The invention can be installed and adjusted according to the actual "deep foundation pit ground-connected wall deep layer" to be monitored, that is, if the monitored part is slightly tilted to the left, vertical or slightly tilted to the right, it can be installed and adjusted; by changing the height of the monitoring device on the carrier, the construction personnel can monitor the deep horizontal displacement of the deep foundation pit ground-connected wall in real time at different positions, different depths and various stages.
[0005] Although the above patent has certain beneficial effects, it is unable to handle the water accumulation inside the inclinometer tube due to bottom seepage or heavy rainfall, which may lead to inaccurate and unstable displacement monitoring and even increase the risk of pipeline damage and misjudgment. Summary of the invention
[0006] The purpose of the present invention is to solve the problem that the automatic monitoring device for deep displacement of deep foundation pit in the prior art cannot handle the accumulated water inside the inclinometer tube, and to propose an automatic monitoring device for deep displacement of deep foundation pit.
[0007] In order to achieve the above-mentioned purpose, the present invention adopts the following technical scheme: an automatic monitoring device for deep displacement of deep foundation pit, comprising a control box, and a water pump is installed inside the control box, the input end of the water pump is connected to a water pumping pipe, the output end of the control box is connected to a first probe through a cable, and the bottom of the first probe is fixedly connected to a first butt joint pipe, a second probe is arranged below the first probe, and a second butt joint pipe is fixedly arranged at the upper end of the second probe, the first butt joint pipe is adapted to the second butt joint pipe and is sealed and fixed by a connecting assembly, the bottom of the second probe is fixedly connected to a filtering probe, and further comprising:
[0008] The accumulated water extraction mechanism includes a counterweight head fixedly connected to the bottom of the second probe, a humidity sensor is installed at the bottom of the counterweight head, a water extraction pipe is arranged inside the first probe, and the water extraction pipe is connected to the filter probe through the conveying mechanism, and a filter assembly is arranged below the side wall of the filter probe, and the filter assembly is used to filter impurities in the extracted accumulated water to prevent the pipeline in the conveying mechanism from being blocked;
[0009] A flushing mechanism, which is installed in the first installation groove and the second installation groove inside the first probe and the second probe, and is used to reuse the extracted filtered part of the accumulated water to flush the groove inside the inclinometer tube;
[0010] A cleaning mechanism, which is installed on the outer surface of the counterweight head and is used to clean the side wall and groove of the inclinometer tube for more thorough cleaning;
[0011] An anti-drift mechanism, which is installed inside the second probe and is used to prevent the probe from drifting when it descends for detection, thereby affecting the detection result;
[0012] The scraper mechanism is installed on the bottom outer surface of the filter probe and is arranged below the filter assembly to scrape away the sludge accumulated inside the inclinometer tube to improve the accuracy of the detection result.
[0013] In the above-mentioned automated monitoring device for deep displacement of deep foundation pits, the anti-deviation mechanism includes an inclination sensor fixedly connected inside the first probe, a first mounting groove is provided at the bottom of the first probe, and a second mounting groove is provided at the bottom of the second probe, and rotating frames are provided inside the first mounting groove and the second mounting groove, and one side of the top of the two rotating frames is respectively connected to the upper wall of the first mounting groove and the second mounting groove through a spring, and rollers are rotatably provided on both sides of the two rotating frames, and the rollers are slidably provided inside the groove of the side wall of the inclinometer tube.
[0014] In the above-mentioned automatic monitoring device for deep displacement of deep foundation pits, the conveying mechanism includes a water suction pipe arranged inside the first probe, and the water suction pipe is connected with the input end of the water pump, the first water pipe is connected with the bottom of the water suction pipe on both sides, and the bottom of the first water pipe is connected with the two sides of the first butt joint, two second water pipes are arranged inside the second probe, and the tops of the two second water pipes are respectively connected with the two sides of the second butt joint, a filter probe is fixedly connected to the bottom of the second probe, and a bifurcated pipe is fixedly installed inside the filter probe, and the two sides of the top of the bifurcated pipe are respectively connected with the bottoms of the two second water pipes, an annular groove is opened inside the filter probe, and the annular groove is arranged below the bifurcated pipe, and the annular groove is connected with the bifurcated pipe.
[0015] In the above-mentioned automatic monitoring device for deep displacement of deep foundation pit, the filtering assembly includes an annular filter plate arranged outside the annular groove, and a coarse-pore filter plate is fixedly connected to the bottom of the annular filter plate.
[0016] In the above-mentioned automated monitoring device for deep displacement of deep foundation pits, a first motor is fixedly installed inside the filter probe, and a connecting rod is fixedly connected to the output end of the first motor. The connecting rods are arranged in multiple forms and are evenly distributed in an array on the outer surface of the output end. A rotating ring is fixedly connected to the end of the connecting rod away from the first motor, and six cleaning scrapers are evenly distributed in an array outside the rotating ring.
[0017] In the above-mentioned automated monitoring device for deep displacement of deep foundation pits, the flushing mechanism includes a water inlet pipe running through the inside of a rotating frame, and hard pipes running through and connected on both sides of the middle of the water inlet pipe, and the hard pipes on both sides are respectively connected and provided with a first nozzle and a second nozzle.
[0018] In the above-mentioned automated monitoring device for deep displacement of deep foundation pits, the scraper mechanism includes a groove scraper rotatably connected to the outer side wall of the filter probe through a spiral spring, and the groove scraper is arranged in multiple numbers and evenly distributed on the outer side wall of the filter probe. An electromagnet is fixedly arranged inside the filter probe, and the number of the electromagnets and the groove scrapers are the same and the positions are corresponding. A permanent magnet is fixedly installed inside the groove scraper on the side close to the electromagnet, and the magnetic poles of the side where the electromagnet contacts the permanent magnet are the same.
[0019] In the above-mentioned automated monitoring device for deep displacement of deep foundation pits, a second motor is fixedly installed inside the filter probe, and the second motor is arranged below the first motor, the output end of the second motor is fixedly connected to the counterweight head, and a small push rod is fixedly arranged on the outer surface of the counterweight head, and two small push rods are arranged and distributed on the outer surface of the counterweight head in opposite directions, and a cleaning broom is fixedly connected to the side of the small push rod away from the counterweight head.
[0020] In the above-mentioned automatic monitoring device for deep displacement of deep foundation pit, the cleaning broom is arranged at an angle to clean the side wall and the groove of the inclinometer tube more evenly when the probe moves downward.
[0021] In the above-mentioned automatic monitoring device for deep displacement of deep foundation pit, the bottom of the counterweight head is designed to be conical, so as to prevent the counterweight head from blocking the water accumulation at the bottom of the inclinometer tube.
[0022] Compared with the prior art, the advantages of the present invention are:
[0023] The present invention installs devices such as a humidity sensor, a water pump and a water suction pipe, and utilizes the water pump to extract and discharge the accumulated water inside the inclinometer tube through a pipeline channel formed by an air inlet pipe, a water suction pipe, a first water delivery pipe, a second water delivery pipe, a bifurcated pipe and an annular groove, thereby reducing the influence of water pressure on the soil, thereby improving the accuracy and reliability of monitoring data, and preventing water accumulation from causing pipeline corrosion or damage to monitoring equipment.
[0024] The present invention can filter impurities or sludge in the accumulated water during the process of extracting water by installing the coarse-pore filter plate and the annular filter plate, so as to prevent the impurities or sludge from blocking the internal pipeline and thus causing damage to the equipment.
[0025] The present invention installs a first motor, a connecting rod, a cleaning scraper and other devices. The first motor drives the connecting rod to drive the rotating ring to rotate, thereby driving the cleaning scraper to clean the filter holes of the annular filter plate, which can prevent the annular filter plate from being blocked after long-term use and extend its service life.
[0026] The present invention installs the inclination sensor, rotating frame, roller and other devices, and uses the downward movement of the probe to drive the roller inside the rotating frame to roll inside the groove on the inner wall of the inclinometer tube, thereby guiding and limiting the probe, improving the stability of detection and the accuracy of detection results.
[0027] The present invention installs a water inlet pipe, a first nozzle and a first nozzle, and can reuse part of the accumulated water entering the water inlet pipe by using the first nozzle and the first nozzle, and spray the accumulated water to flush the groove, thereby further improving the cleaning effect. BRIEF DESCRIPTION OF THE DRAWINGS
[0028] Figure 1 The present invention is a schematic diagram of the overall structure of an automatic monitoring device for deep displacement of deep foundation pits.
[0029] Figure 2 The present invention is a schematic diagram of the assembly structure of a first probe, a second probe and a filter probe of an automatic monitoring device for deep displacement of a deep foundation pit proposed by the present invention.
[0030] Figure 3 The present invention provides a schematic structural diagram of a first probe of an automated monitoring device for deep displacement of a deep foundation pit.
[0031] Figure 4 This is a schematic diagram of the internal structure of the first probe of an automated monitoring device for deep displacement of a deep foundation pit proposed by the present invention.
[0032] Figure 5 This is a schematic structural diagram of the first water pipe portion of an automated monitoring device for deep displacement of a deep foundation pit proposed by the present invention.
[0033] Figure 6 This is a schematic diagram of the semi-sectioned axonometric structure of a rotating frame of an automated monitoring device for deep displacement of a deep foundation pit proposed in the present invention.
[0034] Figure 7 for Figure 3 Schematic diagram of the cross-sectional axonometric structure in the AA direction.
[0035] Figure 8 This is a schematic structural diagram of the second water pipe portion of an automated monitoring device for deep displacement of a deep foundation pit proposed by the present invention.
[0036] Fig. 9 The present invention provides a schematic structural diagram of a filter probe for an automated monitoring device for deep displacement of a deep foundation pit.
[0037] Fig.10 The figure is a schematic diagram of the internal structure of a filter probe of an automated monitoring device for deep displacement of a deep foundation pit proposed by the present invention.
[0038] Fig.11 for Fig. 9 Schematic diagram of the cross-sectional axonometric structure in the BB direction.
[0039] Fig.12 for Fig.10 Schematic diagram of the enlarged structure of part C.
[0040] In the figure: 1, control box; 101, cable; 102, water pipe; 103, water pump; 2, first probe; 201, first mounting groove; 202, first water pipe; 203, first butt joint; 3, second butt joint; 301, second water pipe; 4, second probe; 401, second mounting groove; 402, connecting assembly; 5, rotating frame; 501, water inlet pipe; 502, roller; 503, first nozzle; 504, second nozzle; 505, Spring; 6. Filter probe; 601. Bifurcated tube; 602. Rotating groove; 603. Circular groove; 604. Annular filter plate; 605. Fine-pore filter plate; 606. Coarse-pore filter plate; 7. Inclination sensor; 8. First motor; 801. Connecting rod; 802. Rotating ring; 803. Cleaning scraper; 9. Electromagnet; 901. Groove scraper; 902. Permanent magnet; 10. Second motor; 11. Counterweight head; 111. Small push rod; 112. Cleaning broom. DETAILED DESCRIPTION
[0041] The following examples are for illustrative purposes only and are not intended to limit the scope of the present invention. Example
[0042] Reference Figure 1-7 An automatic monitoring device for deep displacement of deep foundation pits includes a control box 1, and a water pump 103 is installed inside the control box 1, the input end of the water pump 103 is connected to a water pumping pipe 102, the output end of the control box 1 is connected to a first probe 2 through a cable 101, the bottom of the first probe 2 is fixedly connected to a first butt joint pipe 203, a second probe 4 is arranged below the first probe 2, and a second butt joint pipe 3 is fixedly arranged at the upper end of the second probe 4, the first butt joint pipe 203 is adapted to the second butt joint pipe 3 and is sealed and fixed by a connecting component 402 to prevent internal water from seeping out.
[0043] An inclination sensor 7 for monitoring the inclination of soil or structure around a deep foundation pit is fixedly installed inside the first probe 2. A first mounting groove 201 is provided at the bottom of the first probe 2, and a second mounting groove 401 is provided at the bottom of the second probe 4. A rotating frame 5 is provided inside the first mounting groove 201 and the second mounting groove 401. One side of the top of the two rotating frames 5 is respectively connected to the upper wall of the first mounting groove 201 and the second mounting groove 401 through a spring 505. Rollers 502 are rotatably provided on both sides of the two rotating frames 5. The rollers 502 on both sides of the rotating frames 5 can roll along the grooves on the side walls of the inclinometer tube through the springs 505. The rollers 502 can be guided and limited to a certain extent by the grooves, so that the probe moves more stably inside the inclinometer tube, avoiding the inclination sensor 7 from deviating when moving and affecting the detection result, so that the detection result of the inclination sensor 7 is more accurate.
[0044] Reference Figure 8-12A filter probe 6 is fixedly connected to the bottom of the second probe 4, and a groove scraper 901 is rotatably connected to the outer side wall of the filter probe 6 through a coil spring. The groove scraper 901 is arranged in multiple numbers and evenly distributed on the outer side wall of the filter probe 6. An electromagnet 9 is fixedly arranged inside the filter probe 6. The number of electromagnets 9 and the groove scraper 901 are the same and the positions are corresponding. A permanent magnet 902 is fixedly installed inside the groove scraper 901 close to the electromagnet 9. The magnetic poles of the electromagnet 9 and the side in contact with the permanent magnet 902 are the same, so that the electromagnet 9 can repel each other with the permanent magnet 902 when energized, driving the groove scraper 901 to rotate to the side away from the electromagnet 9 through the coil spring into the groove of the inclinometer tube, so that when the probe descends, the groove scraper 901 can be driven to scrape the sludge in the groove of the inclinometer tube, and the sludge in the groove can be regularly removed to maintain accurate monitoring data.
[0045] A counterweight head 11 is fixedly connected to the bottom of the filter probe 6. The bottom of the counterweight head 11 is conical in design to prevent it from blocking the water at the bottom of the inclinometer tube. A humidity sensor is installed at the bottom of the counterweight head 11. The humidity sensor can detect the humidity at the bottom of the inclinometer tube. When the detected humidity reaches a certain value, the water pump 103 is controlled to pump water. A water pumping pipe 102 is arranged inside the first probe 2, and the water pumping pipe 102 is connected through the input end of the water pump 103. The bottom sides of the water pumping pipe 102 are connected through the first water delivery pipe 202. The bottom of the first water delivery pipe 202 is connected through the two sides of the first docking pipe 203. Two second probes 4 are arranged inside. Two water pipes 301, and the tops of the two second water pipes 301 are respectively connected with the two sides of the second docking pipe 3, the bottom of the second probe 4 is fixedly connected with a filter probe 6, and the inside of the filter probe 6 is fixedly installed with a bifurcated pipe 601, the top two sides of the bifurcated pipe 601 are respectively connected with the bottoms of the two second water pipes 301, an annular groove 603 is opened inside the filter probe 6, and the annular groove 603 is arranged below the bifurcated pipe 601, and the annular groove 603 is connected with the bifurcated pipe 601, the water at the bottom of the inclinometer tube can be extracted by the water pump 103, to prevent the accumulation of water at the bottom from affecting the detection or damaging the equipment, thereby improving the detection results and extending the service life of the equipment.
[0046] An annular filter plate 604 is arranged on the outer side of the annular groove 603, and a coarse-pore filter plate 606 is fixedly connected to the bottom of the annular filter plate 604. The extracted water can be filtered twice by the annular filter plate 604 and the coarse-pore filter plate 606 to prevent impurities and sludge in the water from clogging the internal pipes and affecting the normal use of the equipment. A first motor 8 is fixedly installed inside the filter probe 6, and a connecting rod 801 is fixedly connected to the output end of the first motor 8. The connecting rod 801 is arranged in a plurality of ways and is evenly distributed on the outer surface of the output end. A rotating ring 802 is fixedly connected to the end of the connecting rod 801 away from the first motor 8, and six cleaning scrapers 803 are evenly distributed on the outside of the rotating ring 802. The first motor 8 drives the rotating ring 802 to rotate through the connecting rod 801, so as to clean the surface of the annular filter 604 plate to prevent the filter holes from being blocked due to long-term use and affecting the work efficiency.
[0047] A water inlet pipe 501 is fixedly connected to the center position of the two rotating frames 5, and the two ends of the water inlet pipe 501 are rotatably connected to the side walls of the first installation groove 201 and the second installation groove 401 respectively. Hard pipes are connected to both sides of the middle of the water inlet pipe 501, and the hard pipes on both sides are respectively connected to the first nozzle 503 and the second nozzle 504. By opening the first nozzle 503 and the second nozzle 504, part of the accumulated water after extraction and filtration can be reused and sprayed out from the first nozzle 503 and the second nozzle 504 to rinse the groove that the roller 502 is about to roll into, and further clean the inside of the groove, so that the cleaning effect is better and the reliability of the detection result is improved.
[0048] A second motor 10 is fixedly installed inside the filter probe 6, and the second motor 10 is arranged below the first motor 8. The output end of the second motor 10 is fixedly connected to the counterweight head 11. A small push rod 111 is fixedly provided on the outer surface of the counterweight head 11. Two small push rods 111 are provided and are tilted in opposite directions on the outer surface of the counterweight head 11. A cleaning broom 112 is fixedly connected to the side of the small push rod 111 away from the counterweight head 11. The second motor 10 can drive the counterweight head 11 to rotate, so that the side wall and the groove of the inclinometer tube can be cleaned more evenly when the probe moves downward, and the cleaning is more thorough.
[0049] In the present invention, before performing deep horizontal displacement measurement, the control box 1 needs to be placed in a suitable position and adjusted to be level. A water pump 103 is installed inside the control box 1. The input end of the water pump 103 is connected to a water pump 102. The first probe 2 and the second probe 4 are docked so that the first docking tube 203 and the second docking tube 3 are completely aligned and sealed. The locking connection component 402 fixes the first probe 2 and the second probe 4 into a whole, and the first probe 2 and the second probe 4 can be rotated ninety degrees and locked again. A plurality of groove scrapers 901 are connected to the side wall of the filter probe 6 by a spiral spring. The electromagnet 9 is not energized in the initial state. The groove scrapers 901 are close to and in contact with the electromagnet 9 under the action of the spiral spring, and will not block the device from entering the inclinometer tube.
[0050] The center positions of the two rotating frames 5 are both fixedly connected with water inlet pipes 501, and the two water inlet pipes 501 are respectively connected to the side walls of the first installation groove 201 and the second installation groove 401, so that the rotating frame 5 can rotate inside the installation groove. The two rotating frames 5 are respectively connected to the upper walls of the first installation groove 201 and the second installation groove 401 with springs 505. When the springs 505 are initially, the distance projected on the horizontal plane by the rollers 502 on both sides of the same rotating frame 5 will be greater than the diameter of the inclinometer tube. Therefore, when the rollers 502 are slid into the grooves on the side walls of the inclinometer tube, the springs 505 are in a compressed state, and the two rollers 502 of the same rotating frame 5 can roll smoothly in the grooves on the side walls of the inclinometer tube. The rotating frames 5 and rollers 502 are installed inside the upper and lower installation grooves, and the rollers 502 can only descend along the grooves on the side walls of the inclinometer tube, which can ensure that the device remains stable when descending inside the inclinometer tube, and the inclination sensor 7 inside the first probe 2 will not be affected by The movement deflection causes inaccurate measurement data. When the probe part descends, the second motor 10 rotates, the small push rod 111 controls the cleaning broom 112 to contact the inner wall of the inclinometer tube, the counterweight head 11 rotates, and the cleaning broom 112 rotates to clean the inner wall of the inclinometer tube. The extension and contraction of the small push rod 111 can control the cleaning force. The cleaning broom 112 is tilted, so that the side wall and the groove of the inclinometer tube can be cleaned more evenly when the probe moves downward. When the probe part descends, the electromagnet 9 is energized, and the side of the electromagnet 9 in contact with the permanent magnet 902 has the same magnetic poles and repel each other. The groove scraper 901 overcomes the torsion of the coil spring and rotates, and extends into the groove of the inclinometer tube. As the probe descends, the sludge attached to or accumulated in the groove is scraped off. The groove scraper 901 can further clean the cleaned groove. The four electromagnets 9 can be controlled individually. By controlling the current of each electromagnet 9, multiple groove scrapers 901 can be tilted at different angles to avoid jamming.
[0051] In actual construction, the inclinometer tube may accumulate water inside due to bottom seepage or heavy rainfall. The water accumulation inside the inclinometer tube will affect the accuracy of measurement. If the water accumulates for too long, it will easily cause pollution and corrosion to the probe. A layer of silt will gradually accumulate in the groove on the inner wall due to the water accumulation. When the probe descends inside the inclinometer tube, the silt will cause the roller 502 to slip or even slide out of the groove, resulting in the probe rotating and deflecting when it is subsequently pulled up to detect the horizontal position. A humidity sensor is installed at the bottom of the counterweight head 11. When the probe part of the device is put into the inclinometer tube to the bottom, the humidity sensor detects the humidity at the bottom of the inclinometer tube in real time. When the counterweight head 11 enters the water-accumulated part at the bottom of the inclinometer tube, the humidity sensor detects the humidity at the bottom of the inclinometer tube. The value will suddenly increase, at this time the water pump 103 is controlled to pump water, the accumulated water will pass through the coarse-pore filter plate 606, the annular filter plate 604, and will be discharged from the inclinometer tube through the annular groove 603, the bifurcated pipe 601, the two second water pipes 301, the second butt joint pipe 3, the first butt joint pipe 203, the two first water pipes 202, the pumping pipe 102 and the water pump 103. In this process, the sludge attached to the inner wall of the inclinometer tube will be cleaned by the cleaning broom 112, and the turbid accumulated water passes through the coarse-pore filter plate 606 to block large particles of solid impurities, preliminarily reducing the filtering pressure of the annular filter plate 604 and the fine-pore filter plate 605. The accumulated water that has been initially coarsely filtered will filter small solid particles when passing through the annular filter plate 604, to ensure that the accumulated water pumped upward will not block the internal pipes.
[0052] When the accumulated water is extracted, the first motor 8 works. The first motor 8 is a micro servo motor that can accurately control the rotation angle. The first motor 8 controls several connecting rods 801 to reciprocate in the rotating groove 602 respectively. The rotating ring 802 reciprocates sixty degrees. The six cleaning scrapers 803 distributed in an array outside the rotating ring 802 can fully clean the outer surface of the annular filter plate 604. Cleaning and extracting accumulated water are carried out simultaneously, and a good filtering effect can still be maintained during cleaning. During the process of extracting accumulated water, the first nozzle 503 and the second nozzle 504 are intermittently opened. When the first nozzle 503 and the second nozzle 504 are closed, the filtered and extracted accumulated water is kept extracted outwardly. When the first nozzle 503 and the second nozzle 504 are opened, the accumulated water extracted upward passes through the first water pipe 202. When filtering the second water pipe 301, a part of the accumulated water will enter the water inlet pipe 501, and enter the first nozzle 503 and the second nozzle 504 respectively through two hard pipes connecting the water inlet pipe 501 and the two nozzles and be sprayed out. The first nozzle 503 and the second nozzle 504 respectively correspond to the positions of the grooves where the roller 502 rolls. The filtered accumulated water can be reused and sprayed from the first nozzle 503 and the second nozzle 504 to rinse the groove where the roller 502 is about to roll into, thereby further improving the cleaning effect inside the groove. In addition, the two rotating frames 5 installed on the first probe 2 and the second probe 4 can be freely adjusted to face different grooves to ensure that each groove can be fully cleaned, thereby improving the stability of the upward pull-up probe measurement, improving the measurement accuracy, and greatly increasing the service life of the device and the inclinometer tube.
[0053] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.
Claims
1. An automatic monitoring device for deep displacement of a deep foundation pit, comprising a control box (1), wherein a water pump (103) is installed inside the control box (1), the input end of the water pump (103) is connected to a water pumping pipe (102), the output end of the control box (1) is connected to a first probe (2) via a cable (101), and the bottom of the first probe (2) is fixedly connected to a first butt joint pipe (203), a second probe (4) is arranged below the first probe (2), and a second butt joint pipe (3) is fixedly arranged at the upper end of the second probe (4), the first butt joint pipe (203) is matched with the second butt joint pipe (3) and is sealed and fixed by a connecting assembly (402), and the bottom of the second probe (4) is fixedly connected to a filtering probe (6), characterized in that: Also includes: A water extraction mechanism, the water extraction mechanism comprising a counterweight head (11) fixedly connected to the bottom of the second probe (4), a humidity sensor being installed at the bottom of the counterweight head (11), a water extraction pipe (102) being arranged inside the first probe (2), and the water extraction pipe (102) being connected to the filter probe (6) through a conveying mechanism, a filter assembly being arranged below the side wall of the filter probe, the filter assembly being used to filter impurities in the extracted water to prevent the pipeline in the conveying mechanism from being blocked; A flushing mechanism, the flushing mechanism being installed in the first installation groove (201) and the second installation groove (401) inside the first probe (2) and the second probe (4), and being used to reuse the extracted filtered part of the accumulated water to flush the groove inside the inclinometer tube; A cleaning mechanism, the cleaning mechanism being mounted on the outer surface of the counterweight head (11) and being used to clean the side wall and the groove of the inclinometer tube for more thorough cleaning; An anti-drift mechanism, the anti-drift mechanism being installed inside the second probe (4) and used to prevent the probe from drifting when it descends for detection, thereby affecting the detection result; A sludge scraping mechanism, which is mounted on the outer surface of the bottom of the filter probe (6) and is arranged below the filter assembly, and is used to scrape away the sludge accumulated inside the inclinometer tube, thereby improving the accuracy of the detection result; The delivery mechanism comprises a water extraction pipe (102) arranged inside the first probe (2), and the water extraction pipe (102) is connected to the input end of the water pump (103); both sides of the bottom of the water extraction pipe (102) are connected to the first water delivery pipe (202), and the bottom of the first water delivery pipe (202) is connected to both sides of the first docking pipe (203); two second water delivery pipes (301) are arranged inside the second probe (4), and the tops of the two second water delivery pipes (301) are connected to the second docking pipe (203) respectively. The two sides of the connecting pipe (3) are connected through, the bottom of the second probe (4) is fixedly connected to a filter probe (6), and a bifurcated pipe (601) is fixedly installed inside the filter probe (6), the top two sides of the bifurcated pipe (601) are respectively connected to the bottoms of the two second water pipes (301), the filter probe (6) is provided with an annular groove (603) inside, and the annular groove (603) is arranged below the bifurcated pipe (601), and the annular groove (603) is connected to the bifurcated pipe (601); The sludge scraping mechanism comprises a groove scraper (901) rotatably connected to the outer side wall of the filter probe (6) via a spiral spring, the groove scraper (901) being arranged in a plurality and evenly distributed on the outer side wall of the filter probe (6), an electromagnet (9) being fixedly arranged inside the filter probe (6), the electromagnets (9) being the same in number and corresponding in position to the groove scraper (901), a permanent magnet (902) being fixedly installed inside a side of the groove scraper (901) close to the electromagnet (9), and the side of the electromagnet (9) in contact with the permanent magnet (902) having the same magnetic pole.
2. The automatic monitoring device for deep displacement of deep foundation pit according to claim 1 is characterized in that: The anti-deviating mechanism comprises an inclination sensor (7) fixedly connected inside the first probe (2), a first mounting groove (201) is provided at the bottom of the first probe (2), and a second mounting groove (401) is provided at the bottom of the second probe (4), and a rotating frame (5) is provided inside the first mounting groove (201) and the second mounting groove (401), and one side of the top of the two rotating frames (5) is respectively connected to the upper wall of the first mounting groove (201) and the second mounting groove (401) through a spring (505), and rollers (502) are rotatably provided on both sides of the two rotating frames (5), and the rollers (502) are slidably provided inside the groove of the side wall of the inclinometer tube.
3. The automatic monitoring device for deep displacement of deep foundation pit according to claim 1, characterized in that: The filter assembly comprises an annular filter plate (604) arranged outside the annular groove (603), and a coarse-pore filter plate (606) is fixedly connected to the bottom of the annular filter plate (604).
4. The automatic monitoring device for deep displacement of deep foundation pit according to claim 1, characterized in that: A first motor (8) is fixedly installed inside the filter probe (6); a connecting rod (801) is fixedly connected to the output end of the first motor (8); a plurality of connecting rods (801) are arranged and evenly distributed in an array on the outer surface of the output end; one end of the connecting rod (801) away from the first motor (8) is fixedly connected to a rotating ring (802); and six cleaning scrapers (803) are evenly distributed in an array outside the rotating ring (802).
5. The automatic monitoring device for deep displacement of deep foundation pit according to claim 1, characterized in that: The flushing mechanism comprises a water inlet pipe (501) penetrating the interior of the rotating frame (5), and hard pipes penetrating and connected on both sides of the middle of the water inlet pipe (501), and the hard pipes on both sides are respectively connected to a first spray head (503) and a second spray head (504).
6. The automatic monitoring device for deep displacement of deep foundation pit according to claim 1, characterized in that: A second motor (10) is fixedly installed inside the filter probe (6), and the second motor (10) is arranged below the first motor (8). The output end of the second motor (10) is fixedly connected to the counterweight head (11), and a small push rod (111) is fixedly arranged on the outer surface of the counterweight head (11). Two small push rods (111) are arranged and distributed on the outer surface of the counterweight head (11) in opposite directions. A cleaning broom (112) is fixedly connected to the side of the small push rod (111) away from the counterweight head (11).
7. The automatic monitoring device for deep displacement of deep foundation pit according to claim 6, characterized in that: The cleaning broom (112) is arranged obliquely, and is used to clean the side wall and the groove of the inclinometer tube more evenly when the probe moves downward.
8. The automatic monitoring device for deep displacement of deep foundation pit according to claim 6, characterized in that: The bottom of the counterweight head (11) is of conical design, which is used to prevent the counterweight head (11) from blocking water accumulated at the bottom of the inclinometer tube.
Citation Information
Patent Citations
Deep horizontal displacement monitoring device for underground diaphragm wall of deep foundation pit
CN116623728A
Water transparency probe monitor
CN211576954U
Well wall impurity flushing device
CN218522653U