Prestress anti-radiation anti-crack energy-saving concrete roof component and pouring configuration method thereof
By pre-embedding of corrugated pipes and branch pipes on concrete roofs and using water conduit pipes to achieve drainage, the problem of steel bar damage and bearing capacity reduction when setting rainwater collection holes on prestressed concrete roofs is solved, and a roof with high crack resistance and strong load performance is achieved Components simplify the construction process.
Patent Information
- Application Number
- CN202410928911.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-11
- Publication Date
- 2024-11-01
AI Technical Summary
When rainwater collection holes are installed on prestressed concrete roofs, drilling can easily destroy the internal steel bars of the concrete floor slab, affecting the load-bearing performance, and may damage the stress balance, resulting in the emergence of cracks and affecting the load-bearing capacity of the roof.
The corrugated pipe, the first branch pipe and the second branch pipe are pre-buried inside the concrete roof, and the drainage function is achieved through the water conduit pipe to avoid additional drainage holes. The plug is used to seal the connection between the water conduit pipe and the branch pipe to ensure that the concrete is dismantled after solidification. The head enables water conduction and reduces the roof strength loss.
It achieves the improvement of crack resistance and load performance of the roof without additional holes, ensures rainwater drainage function while protecting the overall bearing capacity of the roof, simplifying the construction process.
Smart Images

Figure CN118881104A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of concrete component construction, and in particular to a prestressed radiation-proof, crack-resistant and energy-saving concrete roof component and a casting and configuration method thereof. Background Art
[0002] Buildings in rainy and snowy areas generally use sloping roofs, which have good load-bearing capacity and are easy to drain. However, many buildings currently need to have a certain rainwater collection capacity to improve the energy-saving and environmental protection performance of the building. Therefore, the roofs of such buildings will be changed to flat roofs, so that rainwater can easily gather on the roof, thereby improving the rainwater collection effect.
[0003] As rainwater gathers on the roof, it will impose a higher load on the roof. In this case, in order to avoid damage such as cracks and collapse on the roof, it is necessary to further improve the bearing capacity of the roof.
[0004] For a concrete roof, its bearing capacity is generally determined by the concrete floor. Concrete roofs are divided into cast-in-place concrete roofs and precast concrete roofs. Precast concrete roofs are made of precast concrete floor slabs. Therefore, if you want to increase the bearing capacity of the roof, you need to increase the bearing capacity of the precast concrete floor slabs. One way to increase the bearing capacity is to perform prestressing, that is, to use prestressed concrete floor slabs.
[0005] In order to collect rainwater, it is also necessary to open rainwater collection holes on the roof that penetrate the floor so that rainwater can be discharged into the rainwater collection box on the lower floor, and then undergo subsequent purification treatment. Rainwater collection holes are usually opened by drilling, but drilling holes in prestressed concrete floors will face the following problems: 1. The drill tool is likely to damage the internal steel bars of the concrete floor when drilling; 2. Drilling will affect the strength of the concrete floor components, especially prestressed concrete components. Additional drilling may destroy the stress balance, causing cracks in the concrete floor and affecting the bearing performance.
[0006] Therefore, how to solve the problem of setting drainage holes and installing water pipes on the roof using prestressed floor slabs is one of the problems that need to be solved at present. Summary of the invention
[0007] The present application provides a prestressed radiation-proof, crack-resistant and energy-saving concrete roof component and a casting and configuration method thereof, which can achieve drainage function without additional drainage holes and has high crack resistance and strong load performance.
[0008] In the first aspect, the present application provides a prestressed radiation-proof, crack-resistant and energy-saving concrete roof component, which adopts the following technical solution: A prestressed radiation-proof, crack-resistant and energy-saving concrete roof component, comprising a component body, a corrugated pipe, a first branch pipe, a second branch pipe and a water guide pipe, wherein the corrugated pipe, the first branch pipe, the second branch pipe and the water guide pipe are all pre-buried inside the component body; The bellows penetrates both ends of the component body for passing prestressed tendons; the first branch pipe is arranged above the bellows, and one end of the first branch pipe is connected to the bellows, and the other end is connected to the upper space of the component body; the second branch pipe is arranged below the bellows, and one end of the second branch pipe is connected to the bellows, and the other end is connected to the lower space of the component body; The first branch pipe and the second branch pipe are connected to each other through the water pipe; the first branch pipe and the second branch pipe are both detachably connected with plugs, and a vent hole is opened at the center of the plug; the plug is used to block the connection between the water pipe and the first branch pipe, and the connection between the second branch pipe and the water pipe.
[0009] By adopting the above technical scheme, when processing prestressed concrete roof components, first, a casting template is set up, and a corrugated pipe, a first branch pipe and a second branch pipe are placed in the template; then, concrete is cast in situ; when the concrete solidifies and reaches the design strength, prestressed tendons are inserted into the corrugated pipe, and the prestress is prestressed; after the prestressing is completed, grouting is injected into the corrugated pipe, and the first branch pipe and the second branch pipe are used for exhaust to ensure the smooth progress of grouting; after the grouting is completed, a gripping force on the prestressed tendons can be formed; finally, the production of the prestressed concrete roof components is completed.
[0010] Before grouting into the corrugated pipe, plugs need to be installed in the first branch pipe and the second branch pipe. The plugs block the connection between the water pipe and the first branch pipe, and between the second branch pipe and the water pipe, to prevent mortar from entering the water pipe. When the mortar in the corrugated pipe solidifies, the plugs are removed to make the first branch pipe, the second branch pipe and the water pipe communicate with each other, and the drainage pipe can be connected through the first branch pipe and the second branch pipe to achieve drainage above and below the main body of the component. Therefore, no additional drilling is required, and the bearing capacity of the main body of the component can be guaranteed.
[0011] Preferably, the plug is threadably connected to the first branch pipe or the second branch pipe, and a sealing layer is provided between the plug and the first branch pipe or the second branch pipe.
[0012] By adopting the above technical solution, the threaded connection can ensure the firmness of the plug, and the sealing layer can ensure the sealing between the plug and the first branch pipe and between the plug and the second branch pipe, thereby preventing mortar from penetrating into the water pipe.
[0013] Preferably, the water pipe is sleeved on the outside of the corrugated pipe, and both ends of the water pipe are closed; the first branch pipe and the second branch pipe both pass through the water pipe and are connected to the corrugated pipe; the first branch pipe and the second branch pipe are both provided with drainage holes connected to the water pipe.
[0014] By adopting the above technical solution, the bellows and the water conduit can be integrated, thereby reducing the number of holes inside the component body, and ensuring the strength of the component body while achieving drainage.
[0015] Preferably, the end of the plug facing the bellows is located between the drain hole and the bellows and is provided with a tapered opening, and the vent hole is connected to the inside of the bellows through the tapered opening; A protrusion is arranged on the inner wall of the plug, and the protrusion is located at the junction of the tapered opening and the vent hole.
[0016] By adopting the above technical solution, the setting of the tapered mouth can form a pointed cone at the end of the mortar short column in the first branch pipe and the second branch pipe, which is beneficial to improving the drainage efficiency; the setting of the protrusion forms a stress groove on the mortar column in the vent hole, making the mortar column easier to break, so as to facilitate the removal of the plug and the mortar column together.
[0017] Preferably, the corrugated pipe is arranged in a wave shape, and a peak section and a trough section are arranged on the corrugated pipe, the first branch pipe serves as a water inlet pipe and is arranged above the peak section, and the second branch pipe serves as a water outlet pipe and is arranged below the trough section; the shape of the water guide pipe corresponds to the shape of the corrugated pipe, and the water guide pipe extends from the peak section to the trough section.
[0018] By adopting the above technical solution, the downward trend from the crest to the trough can be utilized to improve the drainage efficiency of the water pipe.
[0019] Preferably, at the wave crest section, the central axis of the water conduit is located above the central axis of the corrugated tube; at the wave trough section, the central axis of the water conduit is located below the central axis of the corrugated tube.
[0020] By adopting the above technical solution, the inclination angle of the water pipe can be further increased, thereby improving the drainage effect. In addition, when the prestressed tendons are prestressed, the prestressed tendons inside the corrugated pipe will apply a downward force to the crest section and an upward force to the trough section. Since the bottom wall of the crest section abuts against the bottom wall of the water pipe, and the top wall of the trough section abuts against the top wall of the water pipe, the forces exerted on the crest section and the trough section can be transmitted to the main body of the component, thereby avoiding excessive deformation of the corrugated pipe.
[0021] Preferably, a conical guide portion is provided at a position of the water conduit below the trough section; and the drainage hole on the second branch pipe is located inside the guide portion.
[0022] By adopting the above technical solution, the setting of the guide part can provide a larger water guiding space, which helps to improve the drainage efficiency.
[0023] Preferably, reinforcing ribs are spirally wound around the circumference of the water pipe, and the reinforcing ribs extend to the end of the water pipe; the spiral density of the reinforcing ribs gradually increases from the end of the water pipe to the center of the water pipe.
[0024] By adopting the above technical solution, the provision of reinforcing ribs can ensure the strength of the water pipe at the center position and prevent the water pipe from being deformed when the main body of the component is cast.
[0025] Preferably, the plug includes a fixed portion and an expansion portion arranged at one end of the fixed portion, and the expansion portion is located at one end of the plug facing the corrugated pipe; the vent hole passes through the fixed portion and the expansion portion; A pull rod is passed through the vent hole and is in the shape of a long tube. One end of the pull rod extends to the outside of the expansion part and is fixedly connected to an abutment plate, which abuts the expansion part. The other end of the pull rod extends to the outside of the fixing part and is threadedly connected to a nut.
[0026] By adopting the above technical solution, when the nut is continuously tightened, the expansion part will be deformed and expanded laterally due to the supporting force of the abutment plate, thereby sealing the junction between the first branch pipe, the second branch pipe and the water pipe to prevent mortar from penetrating into the water pipe.
[0027] On the other hand, the present application provides a method for casting and configuring a prestressed radiation-proof, crack-resistant and energy-saving concrete roof component, comprising the following steps: The steel cage inside the main body of the binding member; A corrugated pipe, a first branch pipe, a second branch pipe and a water pipe are manufactured, the first branch pipe, the second branch pipe and the water pipe are fixed on the corrugated pipe, and the first branch pipe and the second branch pipe are connected to the water pipe; then the corrugated pipe is installed in a steel cage, and the corrugated pipe is fixed to the steel cage; Set up a formwork for pouring the main body of the component outside the steel cage, and pour the main body of the component; Place the prestressed tendons in the corrugated tube and prestress the main body of the component; Inject grout into the corrugated pipe; before grouting, install plugs in the first branch pipe and the second branch pipe; Remove the plug after grouting.
[0028] By adopting the above technical solution, a water pipe is set up, and the mutual conduction among the first branch pipe, the second branch pipe and the water pipe is achieved through a plug after the mortar in the corrugated pipe solidifies, thereby achieving self-drainage of the component body. Therefore, when the component body is used to build a building roof, the problem of reduced strength of the component body caused by additional drilling can be avoided.
[0029] In summary, the present invention includes at least one of the following beneficial technical effects: 1. When grouting into the corrugated pipe, install the plug into the first branch pipe and the second branch pipe. When the mortar in the corrugated pipe solidifies, remove the plug to make the first branch pipe, the second branch pipe and the water pipe conduct to each other, and the drainage pipe can be connected through the first branch pipe and the second branch pipe to achieve drainage above and below the main body of the component. Therefore, no additional drilling is required, and the bearing capacity of the main body of the component can be guaranteed; 2. The present application utilizes the downward trend from the crest to the trough of the corrugated pipe to improve the drainage efficiency of the water pipe; and when the component body is prestressed, the force on the crest section and the trough section can be transmitted to the component body, which can avoid the corrugated pipe from producing transitional deformation; 3. Two plugs with different structural forms are used in this application, which can be selectively applied according to actual construction needs, which can effectively improve the convenience of construction; 4. The prestressed radiation-proof, crack-resistant and energy-saving concrete roof components provided in this application can be applied to the construction of various roof structures, and have the advantages of a wide range of applications, good drainage performance and strong load capacity. BRIEF DESCRIPTION OF THE DRAWINGS
[0030] Figure 1 It is a structural schematic diagram of the prestressed radiation-proof, crack-resistant and energy-saving concrete roof component in Example 1 of the present application; Figure 2 yes Figure 1 A partial enlarged schematic diagram of part A; Figure 3 It is a schematic diagram of the structure of the plug in Example 2 of the present application.
[0031] Markings in the accompanying drawings: 1. component body; 2. bellows; 21. crest section; 22. trough section; 3. first branch pipe; 4. second branch pipe; 5. water guide pipe; 51. transition section; 52. reinforcing rib; 53. guide section; 6. plug; 61. vent hole; 62. tapered mouth; 63. protrusion; 64. fixing section; 65. expansion section; 66. pull rod; 67. abutment plate; 68. nut. DETAILED DESCRIPTION
[0032] The following is combined with Figure 1-3 The present invention is described in further detail.
[0033] The embodiment of the present application discloses a prestressed radiation-proof, crack-resistant and energy-saving concrete roof component, which is used for assembling the roof of a building or used as a floor slab.
[0034] Reference Figure 1 and Figure 2The prestressed radiation-proof, crack-resistant and energy-saving concrete roof component includes a component body 1, a corrugated pipe 2, a first branch pipe 3, a second branch pipe 4 and a water pipe 5. The component body 1 is set in a flat plate shape and is cast with concrete. When the component body 1 is used in radiation-resistant special buildings such as atomic reactors, particle accelerators, and protective buildings for radioactive isotope equipment in industrial, agricultural and scientific research departments, radiation-proof concrete can be used when casting the component body 1, that is, the gel material of the concrete uses silicate cement with low hydration heat, or special cements such as high alumina cement, barium cement, and magnesia cement. Barite, magnetite, limonite, scrap iron blocks, etc. are used as aggregates. Adding substances containing boron, cadmium, lithium, etc. can weaken the penetration strength of the neutron flow.
[0035] The bellows 2, the first branch pipe 3, the second branch pipe 4 and the water conduit 5 are all pre-buried in the component body 1. In the embodiment of the present application, the bellows 2, the first branch pipe 3, the second branch pipe 4 and the water conduit 5 are all plastic pipes. As a preferred implementation of the embodiment of the present application, the bellows 2, the first branch pipe 3, the second branch pipe 4 and the water conduit 5 can also be metal pipes.
[0036] In the embodiment of the present application, the bellows 2 is configured to be wavy and has two wave crest sections 21 and one wave trough section 22. As a preferred implementation of the embodiment of the present application, the bellows 2 can also be configured to be V-shaped, W-shaped, etc.
[0037] The bellows 2 passes through both ends of the component body 1. The interior of the bellows 2 is used to pass prestressed tendons. By tensioning the prestressed tendons, the prestressing of the component body 1 is completed. Two first branch pipes 3 are provided and are respectively located above the two wave peak sections 21. The first branch pipe 3 is vertically arranged, and its lower end is connected and communicated with the bellows 2, and the upper end extends upward and is connected to the upper space of the component body 1. One second branch pipe 4 is provided and is located below the trough section 22. The second branch pipe 4 is vertically arranged, and its upper end is connected and communicated with the bellows 2, and the lower end is connected to the lower space of the component body 1.
[0038] In the embodiment of the present application, the water pipe 5 is sleeved on the outside of the corrugated pipe 2, and the shape of the water pipe 5 corresponds to the shape of the corrugated pipe 2. Both ends of the water pipe 5 are closed. The water pipe 5 extends from one crest section 21 of the corrugated pipe 2 to another crest section 21, and the first branch pipe 3 and the second branch pipe 4 are both connected to the water pipe 5. An arc-shaped transition portion 51 is provided between the end of the water pipe 5 and the corrugated pipe 2.
[0039] At the wave crest section 21, the central axis of the water pipe 5 is located above the central axis of the bellows 2, and the inner bottom wall of the water pipe 5 abuts against the outer bottom wall of the bellows 2; at the wave trough section 22, the central axis of the water pipe 5 is located below the central axis of the bellows 2, and the submerged top wall of the water pipe 5 abuts against the outer top wall of the bellows 2, thereby making the water pipe 5 and the bellows 2 relatively offset.
[0040] When the prestressed tendons are prestressed, they are in a taut state, so a downward force is applied to the crest section 21 and an upward force is applied to the trough section 22. Since the outer bottom wall of the crest section 21 abuts against the inner bottom wall of the water pipe 5, and the outer top wall of the trough section 22 abuts against the inner top wall of the water pipe 5, the forces exerted on the crest section 21 and the trough section 22 will be transmitted to the component body 1, thereby avoiding transitional deformation of the corrugated tube 2.
[0041] In addition, the relative offset between the water guide pipe 5 and the corrugated pipe 2 can also provide a larger water guide space for the first branch pipe 3 and the second branch pipe 4, thereby improving the water guide efficiency.
[0042] A reinforcing rib 52 is spirally wound around the water pipe 5, and the spiral density of the reinforcing rib 52 gradually increases from the end of the water pipe 5 to the center of the water pipe 5 to ensure the strength of the center of the water pipe 5 and prevent the water pipe 5 from deforming when the component body 1 is cast. The reinforcing rib 52 extends to the transition part 51 at the end of the water pipe 5 to improve the strength of the connection between the water pipe 5 and the corrugated pipe 2.
[0043] The two first branch pipes 3 and the second branch pipe 4 both pass through the water pipe 5, and drainage holes are provided at the positions of the first branch pipe 3 and the second branch pipe 4 between the corrugated pipe 2 and the water pipe 5 to achieve mutual communication among the first branch pipe 3, the water pipe 5 and the second branch pipe 4. Since mortar needs to be poured into the corrugated pipe 2 after the prestressing of the component body 1, after the grouting in the corrugated pipe 2 is completed, since the corrugated pipe 2 is filled with mortar, the first branch pipe 3 can be used as a water inlet pipe and the second branch pipe 4 can be used as a water outlet pipe, so the drainage function can be achieved through the first branch pipe 3, the water pipe 5 and the second branch pipe 4.
[0044] A conical guide portion 53 is provided at a position of the water guide pipe 5 below the trough section 22; the drainage hole on the second branch pipe 4 is located inside the guide portion 53. The setting of the guide portion 53 can provide a larger water guide space, which helps to improve drainage efficiency.
[0045] As a preferred implementation of the embodiment of the present application, the water conduit 5 can also be a common pipe and arranged in parallel with the corrugated pipe 2.
[0046] Reference Figure 2In order to prevent the drainage hole from being blocked during grouting inside the corrugated pipe 2, a plug 6 is detachably connected to the first branch pipe 3 and the second branch pipe 4. A vent hole 61 is provided at the center of the plug 6. When the plug 6 is inserted into the first branch pipe 3 and the second branch pipe 4, the drainage hole can be blocked, and the vent hole 61 can ensure ventilation inside the corrugated pipe 2 during grouting. When the grouting is completed, the plug 6 is removed to restore the connection between the first branch pipe 3, the second branch pipe 4 and the water pipe 5.
[0047] Since the mortar will enter the vent hole 61 and form a mortar column in the vent hole 61 after solidification, but since the diameter of the mortar column is small and the strength is low, when the plug 6 is removed, the mortar column will break and remain in the vent hole 61, and the mortar column and the plug 6 can be removed together.
[0048] In the embodiment of the present application, the plug 6 and the first branch pipe 3 as well as the plug 6 and the second branch pipe 4 are all threadedly connected to ensure the firmness of the plug 6. The surrounding side of the plug 6 is also covered with a sealing layer to ensure the sealing between the plug 6 and the first branch pipe 3 as well as the plug 6 and the second branch pipe 4 to prevent mortar from penetrating into the water pipe 5.
[0049] The length of the plug 6 is not less than the length of the first branch pipe 3 and the second branch pipe 4, and when the plug 6 is installed, the end of the plug 6 facing the corrugated pipe 2 is located between the drain hole and the corrugated pipe 2, so that the plug 6 protrudes to the outside of the component body 1. Therefore, when the mortar in the corrugated pipe 2 solidifies and the plug 6 is removed, a mortar short column will be formed in the first branch pipe 3 and the second branch pipe 4, and the mortar short column has a sealing effect on the first branch pipe 3 and the second branch pipe 4, reducing the probability of water infiltration into the corrugated pipe 2.
[0050] Reference Figure 2 A tapered opening 62 is also provided at one end of the plug 6 facing the corrugated pipe 2, and the vent hole 61 is connected to the tapered opening 62. The setting of the tapered opening 62 can form a pointed cone at the end of the mortar short column in the first branch pipe 3 and the second branch pipe 4, which is beneficial to the drainage efficiency.
[0051] A protrusion 63 is also provided at the junction of the conical opening 62 and the vent hole 61. The provision of the protrusion 63 forms a stress groove on the mortar column in the vent hole 61, making the mortar column easier to break, so as to facilitate the removal of the plug 6 and the mortar column together.
[0052] The implementation principle of the prestressed radiation-proof, crack-resistant and energy-saving concrete roof component in the embodiment of the present application is as follows: when processing the prestressed concrete roof component, first, a casting template is set up, and a corrugated pipe, a water pipe 5, a first branch pipe 3 and a second branch pipe 4 are placed in the template; then, the concrete is cast in place; when the concrete solidifies and reaches the designed strength, prestressed tendons are inserted into the corrugated pipe 2, and the prestress is prestressed; after the prestressing is completed, grouting is injected into the corrugated pipe 2, and at this time, the first branch pipe 3 and the second branch pipe 4 are used for exhaust to ensure the smooth progress of grouting; after the mortar solidifies, a gripping force on the prestressed tendons can be formed; finally, the production of the prestressed concrete roof component is completed.
[0053] Before grouting into the corrugated pipe, the plug 6 needs to be installed in the first branch pipe 3 and the second branch pipe 4. The plug 6 blocks the connection between the water pipe 5 and the first branch pipe 3, and the connection between the second branch pipe 4 and the water pipe 5 to prevent the mortar from entering the water pipe 5. When the mortar in the corrugated pipe 2 solidifies, the plug 6 is removed to make the first branch pipe 3, the second branch pipe 4 and the water pipe 5 communicate with each other, and the drainage pipe can be connected through the first branch pipe 3 and the second branch pipe 4 to achieve drainage above and below the component body 1.
[0054] Example 2 The embodiment of the present application discloses a prestressed radiation-proof, crack-resistant and energy-saving concrete roof component, which is different from the embodiment 1 in that the structure of the plug 6 is different.
[0055] Reference Figure 3 The plug 6 includes a fixed portion 64 and an expansion portion 65 disposed at one end of the fixed portion 64, and the expansion portion 65 is located at the end of the plug 6 facing the corrugated tube 2; the vent hole 61 passes through the fixed portion 64 and the expansion portion 65. The fixed portion 64 is made of a hard material such as metal and plastic, and the expansion portion 65 is made of a soft elastic material.
[0056] A pull rod 66 is passed through the vent hole 61 and is in the shape of a long tube. One end of the pull rod 66 extends to the outside of the expansion portion 65 and is fixedly connected to an abutment plate 67 which abuts against the expansion portion 65. The other end of the pull rod 66 extends to the outside of the fixing portion 64 and is threadedly connected to a nut 68.
[0057] When the nut 68 is continuously tightened, the expansion portion 65 will be deformed and expanded laterally due to the supporting force of the abutment plate 67 , thereby sealing the junction between the first branch pipe 3 , the second branch pipe 4 and the corrugated pipe 2 to prevent mortar from penetrating into the water pipe 5 .
[0058] Example 3 The present application embodiment discloses a method for casting and configuring a prestressed radiation-proof, crack-resistant and energy-saving concrete roof component, which is applied to a prestressed radiation-proof, crack-resistant and energy-saving concrete roof component disclosed in Embodiment 1 and Embodiment 2, and includes the following steps: A steel cage inside the binding member body 1; A corrugated pipe 2, a first branch pipe 3, a second branch pipe 4 and a water pipe 5 are manufactured, and the first branch pipe 3, the second branch pipe 4 and the water pipe 5 are all fixed on the corrugated pipe 2, and the first branch pipe 3 and the second branch pipe 4 are both connected to the water pipe 5; then the corrugated pipe 2 is installed in the steel cage, and the corrugated pipe 2 is fixed to the steel cage; A formwork for pouring the component body 1 is set up outside the steel cage, and the component body 1 is poured; The prestressed tendons are placed in the corrugated tube 2 and the component body 1 is prestressed; Grouting is performed in the corrugated pipe 2; before grouting, plugs 6 are installed in the first branch pipe 3 and the second branch pipe 4; Remove the plug 6 after grouting.
[0059] The embodiments of this specific implementation method are all preferred embodiments of the present invention, and are not intended to limit the protection scope of the present invention. Therefore, any equivalent changes made based on the structure, shape, and principle of the present invention should be included in the protection scope of the present invention.
Claims
1. A prestressed radiation-proof, crack-resistant and energy-saving concrete roof member, characterized in that: It comprises a component body (1), a bellows (2), a first branch pipe (3), a second branch pipe (4) and a water conduit (5), wherein the bellows (2), the first branch pipe (3), the second branch pipe (4) and the water conduit (5) are all pre-buried inside the component body (1); The bellows (2) penetrates both ends of the component body (1) for passing prestressed tendons; the first branch pipe (3) is arranged above the bellows (2), and one end of the first branch pipe (3) is connected to the bellows (2), and the other end is connected to the space above the component body (1); the second branch pipe (4) is arranged below the bellows (2), and one end of the second branch pipe (4) is connected to the bellows (2), and the other end is connected to the space below the component body (1); The first branch pipe (3) and the second branch pipe (4) are connected to each other via a water conduit (5); plugs (6) are detachably connected to the first branch pipe (3) and the second branch pipe (4); a vent hole (61) is provided at the center of the plug (6); the plug (6) is used to block the connection between the water conduit (5) and the first branch pipe (3), and between the second branch pipe (4) and the water conduit (5).
2. The prestressed radiation-proof, crack-resistant and energy-saving concrete roof member according to claim 1 is characterized in that: The plug (6) is threadedly connected to the first branch pipe (3) or the second branch pipe (4), and a sealing layer is provided between the plug (6) and the first branch pipe (3) or the second branch pipe (4).
3. The prestressed radiation-proof, crack-resistant and energy-saving concrete roof member according to claim 1 is characterized in that: The water guide pipe (5) is sleeved on the outside of the corrugated pipe (2), and both ends of the water guide pipe (5) are closed; the first branch pipe (3) and the second branch pipe (4) both pass through the water guide pipe (5) and are connected to the corrugated pipe (2); the first branch pipe (3) and the second branch pipe (4) are both provided with drainage holes connected to the water guide pipe (5).
4. The prestressed radiation-proof, crack-resistant and energy-saving concrete roof member according to claim 3 is characterized in that: One end of the plug (6) facing the bellows (2) is located between the drainage hole and the bellows (2) and is provided with a tapered opening (62); the vent hole (61) is connected to the interior of the bellows (2) through the tapered opening (62); A protrusion (63) is provided on the inner wall of the plug (6), and the protrusion (63) is located at the junction of the conical opening (62) and the vent hole (61).
5. The prestressed radiation-proof, crack-resistant and energy-saving concrete roof member according to claim 3 is characterized by: The corrugated pipe (2) is arranged in a wave shape, and a wave crest section (21) and a wave trough section (22) are arranged on the corrugated pipe (2); the first branch pipe (3) serves as a water inlet pipe and is arranged above the wave crest section (21); the second branch pipe (4) serves as a water outlet pipe and is arranged below the wave trough section (22); the shape of the water guide pipe (5) corresponds to the shape of the corrugated pipe (2), and the water guide pipe (5) extends from the wave crest section (21) to the wave trough section (22).
6. The prestressed radiation-proof, crack-resistant and energy-saving concrete roof member according to claim 5 is characterized in that: At the wave crest section (21), the central axis of the water conduit (5) is located above the central axis of the corrugated tube (2); at the wave trough section (22), the central axis of the water conduit (5) is located below the central axis of the corrugated tube (2).
7. The prestressed radiation-proof, crack-resistant and energy-saving concrete roof member according to claim 5 is characterized by: The water guide pipe (5) is provided with a conical guide portion (53) at a position below the trough section (22); the drainage hole on the second branch pipe (4) is located inside the guide portion (53).
8. The prestressed radiation-proof, crack-resistant and energy-saving concrete roof member according to claim 1 is characterized by: A reinforcing rib (52) is spirally wound around the circumference of the water conduit (5), and the reinforcing rib (52) extends to the end of the water conduit (5); the spiral density of the reinforcing rib (52) gradually increases from the end of the water conduit (5) to the center of the water conduit (5).
9. The prestressed radiation-proof, crack-resistant and energy-saving concrete roof member according to claim 1 is characterized by: The plug (6) comprises a fixing portion (64) and an expansion portion (65) arranged at one end of the fixing portion (64), wherein the expansion portion (65) is located at one end of the plug (6) facing the corrugated tube (2); the vent hole (61) penetrates the fixing portion (64) and the expansion portion (65); A pull rod (66) is inserted into the vent hole (61), and the pull rod (66) is arranged in a long tubular shape; one end of the pull rod (66) extends to the outside of the expansion portion (65) and is fixedly connected to an abutment plate (67), and the abutment plate (67) abuts against the expansion portion (65); the other end of the pull rod (66) extends to the outside of the fixing portion (64) and is threadedly connected to a nut (68).
10. A method for casting and arranging the prestressed radiation-proof, crack-resistant and energy-saving concrete roof member according to any one of claims 1 to 9, characterized in that: The following steps are involved: A steel cage inside the main body of the binding member (1); A corrugated pipe (2), a first branch pipe (3), a second branch pipe (4) and a water pipe (5) are manufactured, and the first branch pipe (3), the second branch pipe (4) and the water pipe (5) are all fixed on the corrugated pipe (2), and the first branch pipe (3) and the second branch pipe (4) are both connected to the water pipe (5); then, the corrugated pipe (2) is installed in a steel cage, and the corrugated pipe (2) is fixed to the steel cage; Setting up a formwork for pouring the component body (1) outside the steel cage, and pouring the component body (1); Placing prestressed tendons in the corrugated pipe (2) and applying prestress to the component body (1); Injecting grout into the corrugated pipe (2); before injecting grout, installing plugs (6) in the first branch pipe (3) and the second branch pipe (4); After grouting, remove the plug (6).