A slag spraying and drainage device and drainage method for mold steel electric arc furnace top
By using sliding grooves, sliding blocks, drainage auxiliary components, high-temperature brush cloth and air compressor in the mold steel arc furnace top slag spraying and drainage device, the problem of slag liquid adhesion on the outside of the electrode is solved, and the comprehensive cleaning of the electrode is achieved. The thorough collection of residue liquid increases the use value of the drainage device.
Patent Information
- Application Number
- CN202411357849.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-27
- Publication Date
- 2024-12-06
- Estimated Expiration
- 2044-09-27
AI Technical Summary
The existing mold steel arc furnace top slag spraying and drainage device cannot effectively treat the slag attached to the outside of the electrode and the electrode frame, resulting in a reduced efficiency of electrode use.
A furnace top slag drainage device including an upper collection cover and a lower collection cover is designed, using sliding grooves, sliding blocks, drainage auxiliary components, high-temperature resistant brush cloth and air compressor, and drives the high-temperature resistant brush cloth to rotate and The air compressor blows air, cleans the slag liquid on the outside of the electrode, and thoroughly collects the slag liquid through a pump and drainage thin tube.
It effectively avoids the accumulation of slag liquid, ensures the cleaning and use value of the electrode, and ensures the complete drainage and collection of slag spray on the top of the furnace.
Smart Images

Figure CN118882338B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of slag spraying and drainage on the top of a mold steel electric arc furnace, and in particular to a slag spraying and drainage device and a drainage method on the top of a mold steel electric arc furnace. Background Art
[0002] The electric arc furnace uses the high temperature generated by the electrode arc to melt ores and metals. When the gas discharge forms an arc, the energy is very concentrated, and the temperature in the arc zone is above 3000℃. For smelting metals, the electric arc furnace has greater process flexibility than other steelmaking furnaces, can effectively remove impurities such as sulfur and phosphorus, the furnace temperature is easy to control, and the equipment occupies a small area. It is suitable for the smelting of high-quality alloy steel. The electric arc furnace is required in the processing of mold steel. During the operation of the electric arc furnace, there is a possibility of slag spraying on the top of the furnace. In order to improve the safety of the operation of the electric arc furnace, it is necessary to install a drainage device at the top of the electric arc furnace.
[0003] During use of the existing mold steel electric arc furnace top slag spraying and drainage device, after the slag liquid is sprayed out along the electrode hole, part of the slag liquid flows along the drainage device to the collection point, and part of the slag liquid adheres to the outside of the electrode and the electrode frame. The presence of this part of the slag liquid causes damage to both the electrode and the electrode frame. If the slag liquid attached to the outside of the electrode is not processed in a short period of time, the use efficiency of the electrode is affected. The existing drainage device cannot drain this part of the slag liquid to the designated point, reducing the use value of the drainage device. Summary of the invention
[0004] The invention discloses a slag spraying and drainage device and a drainage method for a mold steel electric arc furnace top, aiming to solve the technical problem that during use of the existing mold steel electric arc furnace top slag spraying and drainage device, after slag liquid is sprayed out along electrode holes, part of the slag liquid flows along the drainage device to a collection point, and part of the slag liquid adheres to the outside of the electrode and the electrode frame, and the existence of the part of the slag liquid causes damage to both the electrode and the electrode frame. If the slag liquid adhered to the outside of the electrode is not processed in a short period of time, the use efficiency of the electrode is affected, and the existing drainage device cannot drain the part of the slag liquid to a designated point.
[0005] In order to achieve the above object, the present invention adopts the following technical solutions:
[0006] A slag spraying and drainage device for a mold steel electric arc furnace top comprises an upper collecting hood and a lower collecting hood, wherein a sliding groove is provided on the top of the upper collecting hood, and a sliding block is slidably connected to the inside of the sliding groove, and a drainage auxiliary component is provided at the bottom of the sliding block, wherein the drainage auxiliary component comprises an integrated ring rod, and the integrated ring rod is fixedly connected to the bottom of the sliding block, and lifting slide rods are distributed in an annular manner at the bottom of the integrated ring rod, and a lifting sleeve ring is slidably connected to the outer side of each lifting slide rod, and an electric telescopic rod is fixedly connected to the bottom of the integrated ring rod above the lifting sleeve ring, and the output end of the electric telescopic rod is fixedly connected to the top of the adjacent lifting sleeve ring, and the side wall of the lifting sleeve ring is fixedly connected to the bottom of the integrated ring rod. A motor frame is fixedly connected to the motor frame, and a driving motor is fixedly connected to the top of the motor frame, and the output shaft of the driving motor is fixedly connected to a rotating column through a coupling, and a high-temperature resistant brush cloth is distributed in a ring shape on the outer side of the rotating column, and two side frames are fixedly connected to the top of the motor frame, and the two side frames are symmetrically distributed with the rotating column as the center, and the bottoms of the two side frames are fixedly connected to hanging rods, and the bottoms of the two hanging rods are fixedly connected to pressing air plates, and compression air holes are opened at equal distances on opposite sides of the two pressing air plates, and air compressors are fixedly connected to opposite sides of the two pressing air plates, and the air delivery end of the air compressor is connected to the inside of the adjacent pressing air plates through a pipeline.
[0007] By providing a drainage auxiliary component, when the furnace top slag spraying and drainage is carried out, the driving motor is started, and the driving motor drives the various high-temperature resistant brush cloths on the outside of the rotating column to rotate rapidly. The rotating high-temperature resistant brush cloth contacts the outer surface of the electrode, and the two contact and squeeze, and the high-temperature resistant brush cloth removes the slag liquid attached to the outer surface of the electrode to prevent the slag liquid from accumulating on the outer surface of the electrode and causing damage to the electrode. At the same time, the electric telescopic rod is adjusted to drive the lifting ring to slide on the lifting slide rod, and the high-temperature resistant brush cloth moving up and down realizes all-round cleaning of the outer end of the electrode. During the rotation of the high-temperature resistant brush cloth, the air compressor is started, and the air compressor blasts out a large amount of gas by pressing the compressed air holes on the air plate. This part of the gas will rotate to the high-temperature resistant brush cloth at the outside of the electrode and move toward the position opposite to the electrode and the high-temperature resistant brush cloth, thereby causing the high-temperature resistant brush cloth to gradually bend, ensuring that the slag liquid attached to the outside of the electrode is thoroughly cleaned, thereby ensuring that the furnace top sprayed slag is thoroughly drained and collected, thereby improving the use value of the drainage device.
[0008] In a preferred embodiment, the bottoms of the plurality of lifting rings are fixedly connected to the same abutment ring plate, and the outer side of the abutment ring plate facing downward is fixedly connected to buffer spring rods at equal distances, the bottoms of every three adjacent buffer spring rods are fixedly connected to the same buffer limit plate, and the sides of every two adjacent buffer limit plates are in contact with each other.
[0009] By providing a buffer spring rod and a buffer limit plate, the slag liquid is shielded by the high temperature resistant brush cloth and each buffer limit plate at the moment the slag liquid sprays out from the furnace top, thereby preventing the slag liquid from splashing and causing a large area of electrode adhesion. At the same time, after the slag liquid impacts the buffer limit plate, the buffer spring rod is compressed, thereby realizing impact unloading, and the slag liquid that loses its forward momentum falls along the buffer limit plate into between the upper collecting cover and the bonding bottom film.
[0010] In a preferred solution, a fitting bottom film is fixedly connected to the bottom of the upper collecting cover, and a mounting frame is fixedly connected to the side of the fitting bottom film facing upward, an upper drainage ring frame is fixedly connected to the side of the mounting frame close to the top, upper drainage holes are equidistantly provided on the inner side wall of the upper drainage ring frame facing the drainage auxiliary component, a pump frame 2 is fixedly connected to one side of the mounting frame, an adsorption pump 2 is fixedly connected to the interior of the pump frame 2, an adsorption tube is fixedly connected to the adsorption end of the adsorption pump 2, and one end of the adsorption tube is inserted into the interior of the upper drainage ring frame.
[0011] In a preferred solution, a hand lever is fixedly connected to the top of the sliding block, and a fixed frame is fixedly connected to the side of the sliding block facing the center point of the integrated ring rod, a hydraulic cylinder is fixedly connected to the side of the fixed frame facing the sliding block, a positioning bonding plate is fixedly connected to the output end of the hydraulic cylinder, friction racks are equidistantly provided on the side of the positioning bonding plate facing the integrated ring rod, and a through hole is opened on the top of the upper collecting cover.
[0012] In a preferred embodiment, a placement hole is opened at the center of the bonding film, and an anti-retention component is provided at the placement hole. The anti-retention component includes a plurality of contact arc plates, which are fixedly connected to the inner side wall of the bonding film, and there is an angle of 150° between the contact arc plates and the bonding film.
[0013] By providing an anti-retention component, during the process of the slag liquid being ejected from the electrode hole, part of the slag liquid accumulates on the outside of the electrode hole, and it is difficult to drain and collect this part of the slag liquid. In the present invention, the anti-retention component is installed at a close distance outside the electrode hole. When the slag liquid accumulates on the outside of the electrode hole, the extraction pump is started. The extraction pump guides the slag liquid accumulated at the electrode hole into the connecting pipe through each drainage capillary tube, and then transports it to between the upper collection cover and the bonding film through the guide pipe. The slag liquid is extracted and collected at a close distance to ensure that the slag liquid will not accumulate for too long and cause corrosion damage to the electrode inside the electrode hole.
[0014] In a preferred embodiment, each of the contact arc plates is fixedly connected to an inclined plate at the top away from the bonding bottom film, each inclined plate is fixedly connected to a connecting tube at the side wall near the top, the connecting tube has connecting holes equidistantly opened on the side wall facing the bottom of the inclined plate, each connecting hole is fixedly connected to a drainage tube, the side wall of the contact arc plate is fixedly connected to an extraction pump, the extraction end of the extraction pump is connected to the inside of the connecting tube through a pipeline, the bonding bottom film is fixedly connected to a pipe sleeve near the top of each extraction pump, the delivery end of the extraction pump is fixedly connected to a delivery pipe, and the delivery pipe is inserted into the adjacent pipe sleeve.
[0015] In a preferred solution, an upper and lower quick docking frame is provided between the upper collecting hood and the lower collecting hood, and the upper and lower quick docking frame includes a fitting seat and a limit frame, the fitting seat is fixedly connected to the outer wall of the lower collecting hood, the limit frame is fixedly connected to the outer wall of the upper collecting hood, and the top of the fitting seat is fixedly connected with a hanging bracket, and the hanging bracket passes through the upper limit frame.
[0016] By providing upper and lower quick docking frames, when installing the upper collecting hood and the lower collecting hood, the fitting bottom film is brought into contact with the upper surface of the furnace cover, and then the two hangers on the lower collecting hood are hung in the two limit frames on the upper collecting hood. At the same time, the hangers are pressed downward, and the bottoms of the hangers are gradually stuck between the two locking plates. The spring rods are squeezed to drive the locking plates to tightly clamp the bottom ends of the hangers, and the docking between the upper collecting hood and the lower collecting hood is quickly completed. Then, the furnace cover is docked with the top of the electric arc furnace, the upper collecting hood and the fitting bottom film are on the outside of the electrode on the furnace top, and the lower collecting hood is on the outside of the docking point between the furnace cover and the electric arc furnace, thereby realizing all-round slag spraying and drainage.
[0017] In a preferred solution, the bottom of the limit frame is fixedly connected to a connecting frame, and one side of the connecting frame is fixedly connected to a plug-in frame, the inner walls on both sides of the plug-in frame are fixedly connected to extrusion spring rods at equal distances, one end of multiple extrusion spring rods on one side is fixedly connected to the same locking plate, and the upper and lower ends of the locking plate are fixedly connected to outward expansion plates.
[0018] In a preferred solution, a pump frame 1 is fixedly connected to the bottom of the fitting seat, and an adsorption pump 1 is fixedly connected to the interior of the pump frame 1, a lower drainage ring frame is fixedly connected to the interior of the lower collecting cover, and lower drainage holes are equidistantly provided on the inner wall of the lower drainage ring frame facing the center point of the lower collecting cover, the adsorption end of the adsorption pump 1 is connected to the interior of the lower drainage ring frame through a pipeline, the delivery end of the adsorption pump 1 is fixedly connected to a return pipe, the return pipe is plugged into the interior of the lower collecting cover, a docking hole is provided at the top of the lower collecting cover, and a guide pipe is fixedly connected to the interior of the docking hole, and the upper opening end of the guide pipe is plugged into the interior of the upper collecting cover.
[0019] A method for spraying slag and draining the top of a mold steel electric arc furnace, using the above-mentioned device for spraying slag and draining the top of a mold steel electric arc furnace, comprises the following steps:
[0020] Step 1: First, install the drainage device, make the bonding bottom plate contact with the upper surface of the furnace cover, then hang the two hangers on the lower collection cover on the two limit frames on the upper collection cover, and press the hangers downward at the same time, so that the bottom of the hangers is gradually stuck between the two locking plates, and then the furnace cover is docked with the top of the electric arc furnace, the upper collection cover and the bonding bottom plate are on the outside of the electrode on the furnace top, and the lower collection cover is on the outside of the docking point between the furnace cover and the electric arc furnace;
[0021] Step 2: When slag spraying is performed during the operation of the electric arc furnace, adsorption pump 1 and adsorption pump 2 are started to adsorb and drain the sprayed slag liquid through the lower drainage ring frame and the upper drainage ring frame, so that it quickly flows to the inner cavity below the upper collection cover and the lower collection cover. At the same time, the extraction pump is started, and the extraction pump guides the slag liquid accumulated at the electrode hole into the connecting pipe through each drainage capillary, and then transports it to between the upper collection cover and the bonding bottom film through the guide pipe;
[0022] Step three: During the operation of the upper drainage ring frame, start the drive motor, which drives the various high-temperature resistant brush cloths on the outside of the rotating column to rotate rapidly. The rotating high-temperature resistant brush cloth contacts the outer surface of the electrode, and the two contact and squeeze. The high-temperature resistant brush cloth removes the slag liquid attached to the outer surface of the electrode, and adjusts the electric telescopic rod to drive the lifting ring to slide on the lifting slide rod. The high-temperature resistant brush cloth that moves up and down realizes all-round cleaning of the outer end of the electrode. During the rotation of the high-temperature resistant brush cloth, start the air compressor, which presses the compressed air holes on the air plate to blast out a large amount of gas. This part of the gas will rotate to the high-temperature resistant brush cloth on the outside of the electrode and move toward the position opposite to the electrode and the high-temperature resistant brush cloth, so that the high-temperature resistant brush cloth gradually bends and covers the side wall of the motor away from the rotating column. After the high-temperature resistant brush cloth removes the slag liquid from the electrode, the adsorption pump 2 drains and collects this part of the slag liquid through the upper drainage hole.
[0023] The slag-removing device for the top of a mold steel electric arc furnace provided by the present invention has the following characteristics: when the slag-removing device for the top of a mold steel electric arc furnace is sprayed and drained, a driving motor is started, and the driving motor drives each high-temperature resistant brush cloth on the outside of a rotating column to rotate rapidly, and the rotating high-temperature resistant brush cloth contacts the outer surface of the electrode, and the two contact and squeeze, and the high-temperature resistant brush cloth takes away the slag liquid attached to the outer surface of the electrode to prevent the slag liquid from accumulating on the outer surface of the electrode and causing damage to the electrode. At the same time, the electric telescopic rod is adjusted to drive the lifting ring to slide on the lifting slide rod, and the high-temperature resistant brush cloth moving up and down realizes all-round cleaning of the outer end of the electrode. During the rotation of the high-temperature resistant brush cloth, the air compressor is started, and the air compressor blasts out a large amount of gas by pressing the compressed air holes on the air plate. This part of the gas will rotate to the high-temperature resistant brush cloth at the outside of the electrode and move toward the position opposite to the electrode and the high-temperature resistant brush cloth, thereby causing the high-temperature resistant brush cloth to gradually bend, ensuring that the slag liquid attached to the outside of the electrode is thoroughly cleaned, thereby ensuring the technical effect of draining and collecting the slag sprayed on the top of the furnace. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] Figure 1 The present invention is a schematic diagram of the overall structure of a slag spraying and drainage device on the top of a mold steel electric arc furnace.
[0025] Figure 2 The present invention provides a cross-sectional view of the structure of an upper collecting hood and a lower collecting hood of a slag spraying and drainage device on the top of a mold steel electric arc furnace.
[0026] Figure 3 This is a schematic diagram of the internal structure of an upper collecting hood of a slag spraying and drainage device on the top of a mold steel electric arc furnace proposed by the present invention.
[0027] Figure 4 The present invention provides a schematic diagram of the combined structure of a drainage auxiliary component and a buffer limit plate of a slag spraying drainage device on the top of a mold steel electric arc furnace.
[0028] Figure 5 This is a schematic structural diagram of a drainage auxiliary component of a slag spraying and drainage device on the top of a mold steel electric arc furnace proposed by the present invention.
[0029] Figure 6 This is a schematic diagram of the combined structure of a pressing gas plate and a high-temperature resistant brush cloth of a mold steel electric arc furnace top slag spraying and drainage device proposed by the present invention.
[0030] Figure 7 This is a schematic structural diagram of an anti-retention component of a slag spraying and drainage device on the top of a mold steel electric arc furnace proposed by the present invention.
[0031] Figure 8 for Figure 7 A magnified view of the local structure.
[0032] Fig. 9 This is a schematic diagram of the structure of upper and lower quick docking frames of a mold steel electric arc furnace top slag spraying and drainage device proposed by the present invention.
[0033] Fig.10 for Fig. 9 A magnified view of the structure of part A.
[0034] In the figure: 1. upper collecting hood; 2. upper and lower quick docking frames; 201. fitting seat; 202. hanging frame; 203. limiting frame; 204. extension piece; 205. locking plate; 206. extrusion spring rod; 207. plug-in frame; 208. connecting frame; 3. lower collecting hood; 4. hand lever; 5. sliding block; 6. perforation; 7. sliding groove; 8. pump frame 1; 9. adsorption pump 1; 10. return pipe; 11. lower drainage ring frame; 12. fitting bottom film; 13. resistance ring plate; 14. upper drainage ring frame; 15. drainage auxiliary assembly; 1501. integrated ring rod; 1502. lifting slide rod; 1503. electric telescopic rod; 1504. high temperature resistant brush cloth; 1505. driving motor; 1506. motor frame; 1507, lifting collar; 1508, air compressor; 1509, side frame; 1510, suspension rod; 1511, compression air hole; 1512, pressing air plate; 1513, rotating column; 16, upper drainage hole; 17, mounting frame; 18, adsorption pump 2; 19, pump frame 2; 20, adsorption tube; 21, friction rack; 22, buffer spring rod; 23, buffer limit plate; 24, hydraulic cylinder; 25, positioning fitting plate; 26, fixing frame; 27, anti-retention assembly; 2701, contact arc plate; 2702, drainage capillary; 2703, inclined plate; 2704, connecting pipe; 2705, extraction pump; 2706, delivery pipe; 2707, pipe sleeve; 28, lower drainage hole; 29, guide pipe. DETAILED DESCRIPTION
[0035] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments.
[0036] The present invention discloses a slag spraying and drainage device and a drainage method for a mold steel electric arc furnace top. The slag spraying and drainage device and the drainage method are mainly applied to the existing mold steel electric arc furnace top. During use, after the slag liquid is sprayed out along the electrode hole, part of the slag liquid flows along the drainage device to the collection point, and part of the slag liquid adheres to the outside of the electrode and the electrode frame. The presence of this part of the slag liquid causes damage to both the electrode and the electrode frame. If the slag liquid adhered to the outside of the electrode is not processed in a short period of time, the use efficiency of the electrode is affected, and the existing drainage device cannot drain this part of the slag liquid to the designated point.
[0037] Reference Figure 1-Figure 10A slag spraying and drainage device for a mold steel electric arc furnace top comprises an upper collecting hood 1 and a lower collecting hood 3. A sliding groove 7 is provided on the top of the upper collecting hood 1, and a sliding block 5 is slidably connected to the inside of the sliding groove 7. A drainage auxiliary component 15 is provided at the bottom of the sliding block 5. The drainage auxiliary component 15 comprises an integrated ring rod 1501, and the integrated ring rod 1501 is fixedly connected to the bottom of the sliding block 5. A lifting slide rod 1502 is distributed in an annular manner at the bottom of the integrated ring rod 1501. A lifting sleeve ring 1507 is slidably connected to the outer side of each lifting slide rod 1502. An electric telescopic rod 1503 is fixedly connected to the bottom of the integrated ring rod 1501 above the lifting sleeve ring 1507. The output end of the electric telescopic rod 1503 is fixedly connected to the top of the adjacent lifting sleeve ring 1507. The side wall of the lifting sleeve ring 1507 is fixedly connected to a motor frame 1506. A driving motor 1505 is fixedly connected to the top of the motor frame 1506, and the output shaft of the driving motor 1505 is fixedly connected to a rotating column 1513 through a coupling. A high-temperature resistant brush cloth 1504 is distributed in a ring shape on the outer side of the rotating column 1513. Two side frames 1509 are fixedly connected to the top of the motor frame 1506, and the two side frames 1509 are symmetrically distributed around the rotating column 1513. The bottoms of the two side frames 1509 are fixedly connected to a suspension rod 1510, and the bottoms of the two suspension rods 1510 are fixedly connected to a pressing air plate 1512. Compressed air holes 1511 are equidistantly provided on opposite sides of the two pressing air plates 1512. Air compressors 1508 are fixedly connected to opposite sides of the two pressing air plates 1512, and the air delivery end of the air compressor 1508 is connected to the inside of the adjacent pressing air plate 1512 through a pipeline.
[0038] In a specific application scenario, when the furnace top is spraying slag and draining, the driving motor 1505 is started, and the driving motor 1505 drives each high temperature resistant brush cloth 1504 on the outside of the rotating column 1513 to rotate rapidly, and the rotating high temperature resistant brush cloth 1504 contacts the outer surface of the electrode, and the two contact and squeeze, and the high temperature resistant brush cloth 1504 takes away the slag liquid attached to the outer surface of the electrode to prevent the slag liquid from accumulating on the outer surface of the electrode and causing damage to the electrode. At the same time, the electric telescopic rod 1503 is adjusted to drive the lifting ring 1507 to slide on the lifting slide rod 1502, and the high temperature resistant brush cloth 1504 moving up and down is moved. The brush cloth 1504 realizes all-round cleaning of the outer end of the electrode. During the rotation of the high-temperature resistant brush cloth 1504, the air compressor 1508 is started. The air compressor 1508 blows out a large amount of gas by pressing the compressed air holes 1511 on the air plate 1512. This part of the gas will rotate to the high-temperature resistant brush cloth 1504 at the outer side of the electrode and move toward the position where the electrode and the high-temperature resistant brush cloth 1504 are opposite to each other, thereby making the high-temperature resistant brush cloth 1504 gradually bend, ensuring that the slag liquid attached to the outer side of the electrode is thoroughly cleaned, thereby ensuring that the slag sprayed on the furnace top is thoroughly drained and collected, thereby improving the use value of the drainage device.
[0039] Reference Figure 1 , Figure 3 and Figure 4 In a preferred embodiment, the bottoms of multiple lifting rings 1507 are fixedly connected to the same abutment ring plate 13, and the outer side of the abutment ring plate 13 facing downward is fixedly connected to buffer spring rods 22 at equal distances, and the bottoms of every three adjacent buffer spring rods 22 are fixedly connected to the same buffer limit plate 23, and the sides of every two adjacent buffer limit plates 23 are in contact with each other.
[0040] Specifically, at the moment when the slag liquid sprays out from the furnace top, the slag liquid is blocked by the high-temperature resistant brush cloth 1504 and each buffer limit plate 23, thereby preventing the slag liquid from splashing and causing a large area of electrode adhesion. At the same time, after the slag liquid impacts the buffer limit plate 23, the buffer spring rod 22 is compressed, thereby realizing impact unloading. The slag liquid that loses its forward momentum falls along the buffer limit plate 23 into between the upper collecting cover 1 and the bonding bottom film 12.
[0041] Reference Figure 1-Figure 5 In a preferred embodiment, a fitting bottom film 12 is fixedly connected to the bottom of the upper collecting cover 1, and a mounting frame 17 is fixedly connected to the side of the fitting bottom film 12 facing upward, an upper drainage ring frame 14 is fixedly connected to the side of the mounting frame 17 close to the top, upper drainage holes 16 are equidistantly provided on the inner side wall of the upper drainage ring frame 14 facing the drainage auxiliary component 15, a pump frame 19 is fixedly connected to one side of the mounting frame 17, an adsorption pump 18 is fixedly connected to the interior of the pump frame 19, an adsorption tube 20 is fixedly connected to the adsorption end of the adsorption pump 18, and one end of the adsorption tube 20 is inserted into the interior of the upper drainage ring frame 14.
[0042] It should be noted that after the drainage device is connected to the arc furnace, the hand lever 4 is manually pulled to drive the sliding block 5 to slide in the sliding groove 7, thereby rotating each group of high-temperature resistant brush cloths 1504 to the outside of each electrode. After the position adjustment is completed, the hydraulic cylinder 24 is adjusted to drive the positioning bonding plate 25 to contact the inner wall of the perforation 6 of the upper collecting cover 1 to complete the fixation of the drainage auxiliary component 15.
[0043] In the present invention, a hand lever 4 is fixedly connected to the top of the sliding block 5, and a fixing frame 26 is fixedly connected to the side of the sliding block 5 facing the center point of the integrated ring rod 1501, a hydraulic cylinder 24 is fixedly connected to the side of the fixing frame 26 facing the sliding block 5, a positioning bonding plate 25 is fixedly connected to the output end of the hydraulic cylinder 24, and a friction rack 21 is equidistantly provided on the side of the positioning bonding plate 25 facing the integrated ring rod 1501, and a through hole 6 is opened on the top of the upper collecting cover 1.
[0044] Reference Figure 1 , Figure 3 , Figure 7 and Figure 8In a preferred embodiment, a placement hole is opened at the center of the bonding bottom film 12, and an anti-retention component 27 is provided at the placement hole. The anti-retention component 27 includes a plurality of contact arc plates 2701, and the contact arc plates 2701 are fixedly connected to the inner side wall of the bonding bottom film 12. There is an angle of 150° between the contact arc plates 2701 and the bonding bottom film 12. Each contact arc plate 2701 is fixedly connected to an inclined piece 2703 away from the top of the bonding bottom film 12, and each inclined piece 2703 is fixedly connected to a connecting pipe 2704 near the uppermost side wall, which connects The side wall of the tube 2704 facing the lower side of the inclined sheet 2703 is provided with connection holes at equal distances, and a drainage tube 2702 is fixedly connected to the inside of each connection hole. An extraction pump 2705 is fixedly connected to the side wall of the contact arc plate 2701, and the extraction end of the extraction pump 2705 is connected to the inside of the connecting tube 2704 through a pipeline. A pipe sleeve 2707 is fixedly connected to the top of each extraction pump 2705 near the bonding film 12, and a delivery pipe 2706 is fixedly connected to the delivery end of the extraction pump 2705, and the delivery pipe 2706 is inserted into the inside of the adjacent pipe sleeve 2707.
[0045] Specifically, during the process of the slag liquid being sprayed out from the electrode hole, part of the slag liquid accumulates on the outside of the electrode hole, and it is difficult to drain and collect this part of the slag liquid. In the present invention, an anti-retention component 27 is installed at a close distance to the outside of the electrode hole. When the slag liquid accumulates on the outside of the electrode hole, the extraction pump 2705 is started. The extraction pump 2705 guides the slag liquid accumulated at the electrode hole into the connecting pipe 2704 through each drainage tube 2702, and then transports it to between the upper collection cover 1 and the bonding film 12 through the guide tube 29. The slag liquid is extracted and collected at a close distance to ensure that the slag liquid will not accumulate for too long and cause corrosion damage to the electrode inside the electrode hole.
[0046] Reference Figure 1 , Figure 2 , Fig. 9 and Fig.10 In a preferred embodiment, an upper and lower quick docking frame 2 is provided between the upper collecting hood 1 and the lower collecting hood 3, and the upper and lower quick docking frame 2 includes a fitting seat 201 and a limit frame 203, the fitting seat 201 is fixedly connected to the outer wall of the lower collecting hood, the limit frame 203 is fixedly connected to the outer wall of the upper collecting hood 1, the top of the fitting seat 201 is fixedly connected with a hanging bracket 202, the hanging bracket 202 passes through the upper limit frame 203, the bottom of the limit frame 203 is fixedly connected with a connecting frame 208, and one side of the connecting frame 208 is fixedly connected with a plug-in frame 207, the inner walls on both sides of the plug-in frame 207 are fixedly connected with extrusion spring rods 206 at equal distances, one end of the multiple extrusion spring rods 206 on one side is fixedly connected with the same locking plate 205, and the upper and lower ends of the locking plate 205 are fixedly connected with extension pieces 204.
[0047] It should be noted that when installing the upper collecting hood 1 and the lower collecting hood 3, the bonding film 12 is brought into contact with the upper surface of the furnace cover, and then the two hangers 202 on the lower collecting hood 3 are hung in the two limit frames 203 on the upper collecting hood 1. At the same time, the hangers 202 are pressed downward, and the bottom of the hangers 202 are gradually stuck between the two locking plates 205. The spring rod 206 is squeezed to drive the locking plate 205 to tightly clamp the bottom end of the hanger 202, and the docking between the upper collecting hood 1 and the lower collecting hood 3 is quickly completed. Then, the furnace cover is docked with the top of the electric arc furnace, the upper collecting hood 1 and the bonding film 12 are on the outside of the electrode on the furnace top, and the lower collecting hood 3 is on the outside of the docking point between the furnace cover and the electric arc furnace, thereby realizing all-round slag spraying and drainage.
[0048] Reference Figure 1 , Figure 2 and Fig. 9 In a preferred embodiment, the bottom of the fitting seat 201 is fixedly connected to a pump frame 8, and the interior of the pump frame 8 is fixedly connected to an adsorption pump 9, the interior of the lower collecting cover 3 is fixedly connected to a lower drainage ring frame 11, and the inner wall of the lower drainage ring frame 11 facing the center point of the lower collecting cover 3 is equidistantly provided with lower drainage holes 28, the adsorption end of the adsorption pump 9 is connected to the interior of the lower drainage ring frame 11 through a pipeline, the delivery end of the adsorption pump 9 is fixedly connected to a return pipe 10, and the return pipe 10 is inserted into the interior of the lower collecting cover 3, a docking hole is opened at the top of the lower collecting cover 3, and a guide pipe 29 is fixedly connected to the interior of the docking hole, and the upper opening end of the guide pipe 29 is inserted into the interior of the upper collecting cover 1.
[0049] A method for spraying slag and draining the top of a mold steel electric arc furnace, using the above-mentioned device for spraying slag and draining the top of a mold steel electric arc furnace, comprises the following steps:
[0050] Step 1: First, install the drainage device, make the bonding bottom film 12 contact with the upper surface of the furnace cover, then hang the two hangers 202 on the lower collection cover 3 in the two limit frames 203 on the upper collection cover 1, and at the same time press the hangers 202 downward, so that the bottom of the hangers 202 is gradually stuck between the two locking plates 205, and then dock the furnace cover with the top of the electric arc furnace, the upper collection cover 1 and the bonding bottom film 12 are on the outside of the electrode on the furnace top, and the lower collection cover 3 is on the outside of the docking point between the furnace cover and the electric arc furnace;
[0051] Step 2: When slag spraying is performed during the operation of the electric arc furnace, the adsorption pump 1 9 and the adsorption pump 2 18 are started, and the sprayed slag liquid is adsorbed and drained through the lower drainage ring frame 11 and the upper drainage ring frame 14, so that it quickly flows to the inner cavity of the upper collection cover 1 and the lower collection cover 3 located below. At the same time, the extraction pump 2705 is started, and the extraction pump 2705 guides the slag liquid accumulated at the electrode hole into the connecting pipe 2704 through each drainage capillary 2702, and then transports it to between the upper collection cover 1 and the bonding bottom film 12 through the guide pipe 29;
[0052] Step 3: During the operation of the upper drainage ring frame 14, the driving motor 1505 is started, and the driving motor 1505 drives the various high-temperature resistant brush cloths 1504 on the outside of the rotating column 1513 to rotate rapidly. The rotating high-temperature resistant brush cloth 1504 contacts the outer surface of the electrode, and the two contact and squeeze, and the high-temperature resistant brush cloth 1504 removes the slag liquid attached to the outer surface of the electrode, and the electric telescopic rod 1503 is adjusted to drive the lifting ring 1507 to slide on the lifting slide rod 1502, and the high-temperature resistant brush cloth 1504 moving up and down realizes all-round cleaning of the outer end of the electrode. During the rotation of the high-temperature brush cloth 1504, the air compressor 1508 is started. The air compressor 1508 blasts out a large amount of gas by pressing the compressed air holes 1511 on the air plate 1512. This part of the gas will rotate to the high-temperature resistant brush cloth 1504 at the outside of the electrode and move toward the position opposite to the electrode and the high-temperature resistant brush cloth 1504, so that the high-temperature resistant brush cloth 1504 is gradually bent and covered on the side wall of the motor away from the rotating column 1513. After the high-temperature resistant brush cloth 1504 takes the slag liquid away from the electrode, the adsorption pump 18 drains and collects this part of the slag liquid through the upper drainage hole 16.
[0053] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes according to the technical scheme and inventive concept of the present invention within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.
Claims
1. A slag spraying and drainage device for a mold steel electric arc furnace top, comprising an upper collecting hood (1) and a lower collecting hood (3), characterized in that: The top of the upper collecting cover (1) is provided with a sliding groove (7), and a sliding block (5) is slidably connected inside the sliding groove (7), and a drainage auxiliary component (15) is provided at the bottom of the sliding block (5), and the drainage auxiliary component (15) comprises an integrated ring rod (1501), and the integrated ring rod (1501) is fixedly connected to the bottom of the sliding block (5), and lifting slide rods (1502) are distributed in an annular manner at the bottom of the integrated ring rod (1501), and the outer side of each lifting slide rod (1502) is slidably connected to a lifting ring (1507), and the bottom of the integrated ring rod (1501) located above the lifting ring (1507) is fixedly connected to an electric telescopic rod (1503), and the output end of the electric telescopic rod (1503) is fixedly connected to the top of an adjacent lifting ring (1507), and the side wall of the lifting ring (1507) is fixedly connected to a motor frame (1506), and the top of the motor frame (1506) is fixedly connected to the motor frame (1506). A driving motor (1505) is connected, and the output shaft of the driving motor (1505) is fixedly connected to a rotating column (1513) via a coupling. A high-temperature resistant brush cloth (1504) is distributed in an annular manner on the outer side of the rotating column (1513). The top of the motor frame (1506) is fixedly connected to two side frames (1509), and the two side frames (1509) are symmetrically distributed with the rotating column (1513) as the center. The bottoms of the two side frames (1509) are fixedly connected to a suspension rod (1510), and the bottoms of the two suspension rods (1510) are fixedly connected to a pressing air plate (1512). Compressed air holes (1511) are evenly spaced on opposite sides of the two pressing air plates (1512). The opposite sides of the two pressing air plates (1512) are fixedly connected to an air compressor (1508), and the air supply end of the air compressor (1508) is connected to the inside of the adjacent pressing air plate (1512) through a pipeline. The bottom of the upper collecting cover (1) is fixedly connected to a bonding bottom film (12), and the side of the bonding bottom film (12) facing upward is fixedly connected to a mounting frame (17), the side of the mounting frame (17) close to the top is fixedly connected to an upper drainage ring frame (14), the inner side wall of the upper drainage ring frame (14) facing the drainage auxiliary component (15) is provided with upper drainage holes (16) at equal distances, one side of the mounting frame (17) is fixedly connected to a second pump frame (19), the interior of the second pump frame (19) is fixedly connected to a second adsorption pump (18), the adsorption end of the second adsorption pump (18) is fixedly connected to an adsorption tube (20), and the adsorption tube (20) is fixedly connected to the adsorption end of the adsorption tube (20). ) is inserted into the interior of the upper drainage ring frame (14), the top of the sliding block (5) is fixedly connected to a hand lever (4), and the side of the sliding block (5) facing the center point of the integrated ring rod (1501) is fixedly connected to a fixed frame (26), the side of the fixed frame (26) facing the sliding block (5) is fixedly connected to a hydraulic cylinder (24), the output end of the hydraulic cylinder (24) is fixedly connected to a positioning bonding plate (25), and the side of the positioning bonding plate (25) facing the integrated ring rod (1501) is equidistantly provided with friction racks (21), the top of the upper collecting cover (1) is provided with a perforation (6), and the bonding bottom film (12 ) is provided with a placement hole at the center thereof, and an anti-retention component (27) is provided at the placement hole, the anti-retention component (27) comprising a plurality of contact arc plates (2701), the contact arc plates (2701) being fixedly connected to the inner side wall of the bonding bottom film (12), an angle of 150° existing between the contact arc plates (2701) and the bonding bottom film (12), each of the contact arc plates (2701) being fixedly connected to an inclined plate (2703) at the top away from the bonding bottom film (12), each of the inclined plates (2703) being fixedly connected to a connecting pipe (2704) at the side wall close to the top, the connecting pipe (2704) facing the inclined surface. The side wall below the placement sheet (2703) is provided with connection holes at equal intervals, and a drainage tube (2702) is fixedly connected to the inside of each connection hole. An extraction pump (2705) is fixedly connected to the side wall of the contact arc plate (2701), and the extraction end of the extraction pump (2705) is connected to the inside of the connecting pipe (2704) through a pipeline. A pipe sleeve (2707) is fixedly connected to the top of each extraction pump (2705) near the bonding bottom sheet (12), and a delivery pipe (2706) is fixedly connected to the delivery end of the extraction pump (2705), and the delivery pipe (2706) is inserted into the inside of an adjacent pipe sleeve (2707).
2. The slag spraying and drainage device for the top of a mold steel electric arc furnace according to claim 1, characterized in that: The bottoms of the plurality of lifting rings (1507) are fixedly connected to a common abutment ring plate (13), and the outer side of the abutment ring plate (13) facing downward is fixedly connected to a buffer spring rod (22) at equal distances, and the bottoms of each of three adjacent buffer spring rods (22) are fixedly connected to a common buffer limit plate (23), and the sides of each of two adjacent buffer limit plates (23) are in contact with each other.
3. The slag spraying and drainage device for the top of a mold steel electric arc furnace according to claim 2, characterized in that: An upper and lower quick docking frame (2) is provided between the upper collecting hood (1) and the lower collecting hood (3), and the upper and lower quick docking frame (2) comprises a fitting seat (201) and a limiting frame (203), the fitting seat (201) is fixedly connected to the outer wall of the lower collecting hood, the limiting frame (203) is fixedly connected to the outer wall of the upper collecting hood (1), and a hanging frame (202) is fixedly connected to the top of the fitting seat (201), and the hanging frame (202) passes through the upper limiting frame (203).
4. The slag spraying and drainage device for the top of a mold steel electric arc furnace according to claim 3, characterized in that: The bottom of the limit frame (203) is fixedly connected to a connecting frame (208), and one side of the connecting frame (208) is fixedly connected to a plug-in frame (207), and the inner walls on both sides of the plug-in frame (207) are fixedly connected to extrusion spring rods (206) at equal distances, and one end of a plurality of extrusion spring rods (206) located on one side is fixedly connected to the same locking plate (205), and the upper and lower ends of the locking plate (205) are fixedly connected to extension plates (204).
5. The slag spraying and drainage device for the top of a mold steel electric arc furnace according to claim 4, characterized in that: The bottom of the fitting seat (201) is fixedly connected to a pump frame 1 (8), and the interior of the pump frame 1 (8) is fixedly connected to an adsorption pump 1 (9), the interior of the lower collecting hood (3) is fixedly connected to a lower drainage ring frame (11), and lower drainage holes (28) are equidistantly opened on the inner side wall of the lower drainage ring frame (11) facing the center point of the lower collecting hood (3), the adsorption end of the adsorption pump 1 (9) is connected to the interior of the lower drainage ring frame (11) through a pipeline, the delivery end of the adsorption pump 1 (9) is fixedly connected to a return pipe (10), and the return pipe (10) is plugged into the interior of the lower collecting hood (3), the top of the lower collecting hood (3) is opened, and the interior of the docking hole is fixedly connected to a guide pipe (29), and the upper open end of the guide pipe (29) is plugged into the interior of the upper collecting hood (1).
6. A slag spraying and drainage method for mold steel electric arc furnace top, using the slag spraying and drainage device for mold steel electric arc furnace top as claimed in claim 5, characterized in that: The following steps are involved: Step 1: First, install the drainage device, make the bonding bottom film (12) contact with the upper surface of the furnace cover, then hang the two hangers (202) on the lower collection cover (3) in the two limit frames (203) on the upper collection cover (1), and at the same time press the hangers (202) downward, so that the bottom of the hangers (202) is gradually stuck between the two locking plates (205), and then dock the furnace cover with the top of the electric arc furnace, the upper collection cover (1) and the bonding bottom film (12) are located on the outside of the electrode on the furnace top, and the lower collection cover (3) is located on the outside of the docking point between the furnace cover and the electric arc furnace; Step 2: When slag spraying is carried out during the operation of the electric arc furnace, adsorption pump 1 (9) and adsorption pump 2 (18) are started to adsorb and drain the sprayed slag liquid through the lower drainage ring frame (11) and the upper drainage ring frame (14), so that it quickly flows to the inner cavity below the upper collection cover (1) and the lower collection cover (3). At the same time, the extraction pump (2705) is started, and the extraction pump (2705) guides the slag liquid accumulated at the electrode hole into the connecting pipe (2704) through each drainage capillary (2702), and then transports it to the space between the upper collection cover (1) and the bonding bottom film (12) through the guide pipe (29); Step 3: During the operation of the upper drainage ring frame (14), the drive motor (1505) is started, and the drive motor (1505) drives the various high-temperature resistant brush cloths (1504) on the outside of the rotating column (1513) to rotate rapidly. The rotating high-temperature resistant brush cloth (1504) contacts the outer surface of the electrode, and the two contact and squeeze each other. The high-temperature resistant brush cloth (1504) removes the slag liquid attached to the outer surface of the electrode, and the electric telescopic rod (1503) is adjusted to drive the lifting ring (1507) to slide on the lifting slide rod (1502). The high-temperature resistant brush cloth (1504) that moves up and down realizes all-round cleaning of the outer end of the electrode. During the rotation of the warm brush cloth (1504), the air compressor (1508) is started. The air compressor (1508) expels a large amount of gas by pressing the compressed air hole (1511) on the air plate (1512). This part of the gas will rotate to the high-temperature resistant brush cloth (1504) at the outside of the electrode and move toward the position opposite to the electrode and the high-temperature resistant brush cloth (1504), so that the high-temperature resistant brush cloth (1504) gradually bends and covers the side wall of the motor away from the rotating column (1513). After the high-temperature resistant brush cloth (1504) takes the slag liquid away from the electrode, the adsorption pump 2 (18) drains and collects this part of the slag liquid through the upper drainage hole (16).
Citation Information
Patent Citations
Liquid metal refining device, liquid metal smelting system and refining method
CN112176149A
Industrial waste renewable resource recovery device
CN115446072A
Flow guide device
CN208936181U
Sealing protection device for top electrode of electric arc furnace
CN214095558U
Furnace top slag spraying safety drainage device of large-scale titanium slag smelting electric arc furnace
CN216144145U
Cited By
Furnace top slag spraying drainage device of die steel electric arc furnace
CN120333129A
A slag spraying and drainage device for the top of a mold steel electric arc furnace
CN120333129B