Method for testing discrete device integrated by multiple MOSFETs

By combining the initial test bits and developing test modules, using a single pin card to connect the pads of multiple MOSFET tubes, the high cost and low efficiency problems of multi-pin card testing in the existing technology are solved, and the high efficiency of multiple MOSFET tubes is achieved test.

CN118884181APending Publication Date: 2024-11-01SHANGHAI HUAHONG GRACE SEMICON MFG CORP
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411021052.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-29
Publication Date
2024-11-01

AI Technical Summary

Technical Problem

The prior art requires the use of multiple needle cards separately when testing discrete devices integrated with multiple MOSFET tubes, resulting in high cost and low testing efficiency, and the pads are prone to repeated needle insertion.

Method used

By combining multiple initial test bits into one new test bit, connecting all pads with a single new pin card, the test module is developed to achieve a single test of multiple MOSFET tubes.

Benefits of technology

A single-pin card test is realized, saving the cost of needle card, avoiding repeated needle insertion of the pad, and improving testing efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118884181A_ABST
    Figure CN118884181A_ABST
Patent Text Reader

Abstract

The invention discloses a method for testing a discrete device integrated by a plurality of MOSFETs (Metal-Oxide-Semiconductor Field Effect Transistor), which comprises the following steps of: providing a tested bare chip which is a discrete device integrated by a plurality of MOSFETs, is provided with m gaskets and is used for realizing a logic function; and combining n initial test positions in the multiple simultaneous test machines into a new test position, wherein 3n is greater than or equal to m. New probe cards corresponding to the new test positions are arranged, probes in the new probe cards are arranged according to the positions of the m pads, and all the probes are located on one probe card channel. And connecting the new pin card with each pad of the tested bare chip and testing the tested bare chip. According to the invention, the test of each MOSFET tube in the discrete device can be realized by adopting a single-needle card single test, the cost of the needle card can be saved, repeated needle insertion of part of pads can be avoided, and the test efficiency can be improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of semiconductor technology, and in particular to a discrete device testing method for integrating multiple MOSFET tubes. Background Art

[0002] Semiconductor discrete devices are usually 2-port or 3-port devices, among which 3-port devices generally include three ports: gate (G), source (S) and drain (Drain, D). Therefore, the corresponding single test site of the wafer testing (Chip Probing, CP) mass production testing machine also only includes 3 channels.

[0003] like Figure 1 The above is a schematic diagram of the structure of an existing discrete device including two ports; the discrete device 101 is a MOSFET, including three electrodes, namely a gate 1021, a source 1022 and a drain 1023. The drain 1023 is composed of a back metal layer, so there is no need to set a pad for lead-out. Both the gate 1021 and the source 1022 need to be provided with pads, so there are two ports.

[0004] like Figure 2 The above is a schematic diagram of the structure of an existing discrete device including three ports; the discrete device 101a is a MOSFET, including three electrodes, namely a gate 1021a, a source 1022a and a drain 1023a. The three electrodes need to be provided with pads for lead-out, so there are three ports.

[0005] With the advancement of technology, the design of discrete devices has also begun to develop in the direction of integration. For example, three MOSFET tubes are integrated in a bare chip (die) of a wafer to realize the logic switch function. If the test is carried out in the existing conventional way, three test needle cards need to be made during the CP mass production test, and the functions of the three MOSFET tubes are tested separately in three steps to see if they are normal. It is inevitable that some pads need to be repeatedly punctured. The following is a further explanation:

[0006] like Figure 3 As shown, it is a connection circuit diagram of the pin card and the discrete device in the existing test method of the discrete device integrating multiple MOSFET tubes; the discrete device included in the tested bare chip includes: a first MOSFET tube MN1, a second MOSFET tube MN2, a third MOSFET tube MN3, a first resistor R1 and a second resistor R2.

[0007] The first end of the first resistor R1, the gate G1 of the first MOSFET tube MN1 and the gate G2 of the second MOSFET tube MN2 are all connected to the first pad 201a.

[0008] A first end of the second resistor R2 is connected to the second pad 201 b.

[0009] The second end of the second resistor R2 is connected to the drain D1 of the first MOSFET tube MN1 and the gate G3 of the third MOSFET tube MN3;

[0010] The drain D2 of the second MOSFET tube MN2 is connected to the third pad 201c.

[0011] The source S2 of the second MOSFET tube MN2 and the source S3 of the third MOSFET tube MN3 are both connected to the fourth pad 201d.

[0012] The second end of the first resistor R1, the source S1 of the first MOSFET tube MN1 and the source S3 of the third MOSFET tube MN3 are all connected to the fifth pad 201e.

[0013] The first MOSFET tube MN1, the second MOSFET tube MN2 and the third MOSFET tube MN3 are all NMOS.

[0014] The first pad 201a serves as an enable signal PAen terminal.

[0015] The second pad 201b serves as a device voltage Vdd terminal.

[0016] The third pad 201c serves as a circuit voltage Vc terminal.

[0017] The fourth pad 201d serves as a gate voltage Vgate terminal.

[0018] The fifth pad 201e serves as a ground terminal.

[0019] When performing CP testing, you need to set up a pin card for each of the three MOSFET tubes. Figure 3 In the embodiment, the three probes 302 of the first needle card 301a are used to connect with the three electrodes of the first MOSFET tube MN1 and to implement the test of the first MOSFET tube MN1; the three probes 302 of the second needle card 301b are used to connect with the three electrodes of the second MOSFET tube MN2 and to implement the test of the second MOSFET tube MN2; the three probes 302 of the third needle card 301c are used to connect with the three electrodes of the third MOSFET tube MN3 and to implement the test of the third MOSFET tube MN3. Figure 4 In the figure, the three pin cards are represented by pin card 1, pin card 2 and pin card 3 respectively, and the three probes of each pin card are represented by G, S and D respectively, which are used to connect to the gate, source and drain of the MOSFET tube respectively. Summary of the invention

[0020] The technical problem to be solved by the present invention is to provide a discrete device testing method integrating multiple MOSFET tubes, which can use a single pin card for a single test to test each MOSFET tube in the discrete device, save pin card costs and avoid repeated pinning of some pads, and improve test efficiency.

[0021] In order to solve the above technical problems, the present invention provides a discrete device testing method for integrating multiple MOSFET tubes, comprising the following steps:

[0022] A bare chip to be tested is provided. The bare chip to be tested is a discrete device integrated by a plurality of MOSFET tubes. The bare chip to be tested has m pads and is used to realize a logic function, where m is greater than or equal to 4.

[0023] The n initial test positions in multiple test machines are merged into a new test position, each of the initial test positions includes three pin card channels connected to the three electrodes of the MOSFET tube; the number of pin card channels of the new test position is 3n, n is an integer, and 3n is greater than or equal to m.

[0024] A new needle card corresponding to the new test position is set, and the probes in the new needle card are set according to the positions of the m pads, and each of the probes is located on a needle card channel.

[0025] The new needle card is connected to each of the pads of the tested bare chip to implement the test of the tested bare chip.

[0026] Further improvements include:

[0027] A test module is developed in the program in the multi-test machine, and the test module allocates single test resources according to the new test position, the new needle card, the needle card channel and the pad.

[0028] Afterwards, the bare chip under test is tested under the control of the test module.

[0029] A further improvement is that the test items for testing the bare chip under test are set according to the logical functions of the bare chip under test.

[0030] A further improvement is that the discrete device of the tested bare chip integrates 3 MOSFET tubes, m is equal to 5, and the tested bare chip is used to realize a logic switch function.

[0031] A further improvement is that n is equal to 2.

[0032] A further improvement is that the discrete devices included in the tested bare chip include: a first MOSFET tube, a second MOSFET tube, a third MOSFET tube, a first resistor and a second resistor.

[0033] The first end of the first resistor, the gate of the first MOSFET tube and the gate of the second MOSFET tube are all connected to the first pad.

[0034] A first end of the second resistor is connected to the second pad.

[0035] The second end of the second resistor is connected to the drain of the first MOSFET tube and the gate of the third MOSFET tube;

[0036] The drain of the second MOSFET is connected to the third pad.

[0037] The source of the second MOSFET tube and the source of the third MOSFET tube are both connected to the fourth pad.

[0038] The second end of the first resistor, the source of the first MOSFET tube and the source of the third MOSFET tube are all connected to the fifth pad.

[0039] A further improvement is that the first MOSFET tube, the second MOSFET tube and the third MOSFET tube are all NMOS.

[0040] The first pad serves as an enable signal terminal.

[0041] The second pad serves as a device voltage terminal.

[0042] The third pad serves as a circuit voltage terminal.

[0043] The fourth pad serves as a gate voltage terminal.

[0044] The fifth pad serves as a ground terminal.

[0045] A further improvement is that the three pin card channels of each initial test position are respectively a gate channel, a source channel and a drain channel.

[0046] The new test bit is formed by combining the first initial test bit and the second initial test bit.

[0047] The six pin card channels of the new test position are respectively the first gate channel, the first source channel and the first drain channel of the first initial test position and the second gate channel, the second source channel and the second drain channel of the second initial test position.

[0048] A further improvement is that, in the single test resources allocated by the test module, the three board channels of the first initial test position and the three board channels of the second initial test position are used as the six board channels of the new test position, and the five board channels in the new test position are used as the channels of the signal source required for the first to fifth pads in the test process of the tested bare chip.

[0049] A further improvement is that the first gate channel is connected to the first pad via the corresponding probe.

[0050] The first source channel is connected to the fourth pad through the corresponding probe.

[0051] The first drain channel is connected to the fifth pad through the corresponding probe.

[0052] The second gate channel is connected to the third pad through the corresponding probe.

[0053] The second source channel is connected to the second pad via the corresponding probe.

[0054] A further improvement is that the test items of the bare chip under test include tests of logic on voltage and logic off voltage.

[0055] A further improvement is that in the test item of the logic on voltage, the test conditions are:

[0056] The second pad is excited by a first voltage, the fifth pad is grounded, the first pad is excited by a high voltage and the third pad is excited by a second voltage, and whether the voltage of the fourth pad is 0V is measured; the high voltage is the voltage that turns on the first MOSFET tube and the second MOSFET tube.

[0057] A further improvement is that in the test item of the logic off voltage, the test conditions are:

[0058] The second pad is excited by a first voltage, the fifth pad is grounded, the first pad is excited by a low voltage, and the third pad is excited by a second voltage, and whether the voltage of the fourth pad is the second voltage is measured; the low voltage is a voltage that disconnects the first MOSFET tube and the second MOSFET tube.

[0059] A further improvement is that if the two test items of the tested bare chip are all passed, it is determined that all three MOSFET tubes are tested and passed.

[0060] When the discrete device of the tested bare chip includes multiple MOSFET tubes, different from the existing method that needs to test each MOSFET tube separately, the present invention combines the initial test position related to the test of a single MOSFET tube into a new test position that can include all pads in the discrete device and sets a single new probe card, i.e., a needle card, according to the new test position. In this way, during the test, it is only necessary to use the new probe card to perform a single probe on the tested bare chip to test all MOSFET tubes in the discrete device. Therefore, a single needle card can be used for a single test to test each MOSFET tube in the discrete device, which can save the needle card cost, avoid repeated probing of some pads, and improve the test efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0061] The present invention is further described in detail below with reference to the accompanying drawings and specific embodiments:

[0062] Figure 1 It is a schematic diagram of the structure of an existing discrete device including two ports;

[0063] Figure 2 It is a schematic diagram of the structure of an existing discrete device including three ports;

[0064] Figure 3 It is a connection circuit diagram of the pin card and the discrete device in the existing test method of the discrete device integrating multiple MOSFET tubes;

[0065] Figure 4 It is a flow chart of a discrete device testing method for integrating multiple MOSFET tubes according to an embodiment of the present invention;

[0066] Figure 5 It is a connection circuit diagram of a probe and a discrete device in a test method of a discrete device integrating multiple MOSFET tubes in some embodiments of the present invention. DETAILED DESCRIPTION

[0067] like Figure 4 As shown in FIG. 1 , it is a flow chart of a discrete device testing method for integrating multiple MOSFET tubes according to an embodiment of the present invention; Figure 5 FIG. 1 is a connection circuit diagram of a probe 502 and a discrete device in a test method for a discrete device integrated with multiple MOSFET tubes in some embodiments of the present invention; the test method for a discrete device integrated with multiple MOSFET tubes in an embodiment of the present invention comprises the following steps:

[0068] Step S101: providing a bare chip to be tested, wherein the bare chip to be tested is a discrete device integrated by a plurality of MOSFET tubes, and the bare chip to be tested has m pads and is used to implement a logic function, where m is greater than or equal to 4.

[0069] In some embodiments, Figure 5As shown, the discrete device of the tested bare chip integrates 3 MOSFET tubes, m is equal to 5, and the tested bare chip is used to realize the logic switch function. The discrete devices included in the tested bare chip include: a first MOSFET tube MN101, a second MOSFET tube MN102, a third MOSFET tube MN103, a first resistor R101 and a second resistor R102.

[0070] The first end of the first resistor R101, the gate G1 of the first MOSFET tube MN101 and the gate G2 of the second MOSFET tube MN102 are all connected to the first pad 401a.

[0071] A first end of the second resistor R102 is connected to the second pad 401 b.

[0072] The second end of the second resistor R102 is connected to the drain D1 of the first MOSFET tube MN101 and the gate G3 of the third MOSFET tube MN103;

[0073] The drain D2 of the second MOSFET tube MN102 is connected to the third pad 401c.

[0074] The source S2 of the second MOSFET tube MN102 and the source S3 of the third MOSFET tube MN103 are both connected to the fourth pad 401d.

[0075] The second end of the first resistor R101, the source S1 of the first MOSFET tube MN101 and the source S3 of the third MOSFET tube MN103 are all connected to the fifth pad 401e.

[0076] Preferably, the first MOSFET tube MN101, the second MOSFET tube MN102 and the third MOSFET tube MN103 are all NMOS.

[0077] The first pad 401a serves as an enable signal PAen terminal.

[0078] The second pad 401b serves as a device voltage Vdd terminal.

[0079] The third pad 401c serves as a circuit voltage Vc terminal.

[0080] The fourth pad 401d serves as a gate voltage Vgate terminal.

[0081] The fifth pad 401e serves as a ground terminal.

[0082] In other embodiments, the number of MOSFET tubes integrated in the discrete device of the tested bare chip may be greater than three.

[0083] Step S102, merging n initial test positions in multiple test machines into a new test position 501, each of the initial test positions including three pin card channels connected to the three electrodes of the MOSFET tube; the number of pin card channels of the new test position 501 is 3n, where n is an integer, and 3n is greater than or equal to m.

[0084] In some embodiments, Figure 5 As shown, n is equal to 2.

[0085] The three pin card channels of each initial test position are respectively a gate channel, a source channel and a drain channel.

[0086] The new test position 501 is formed by combining the first initial test position 501a and the second initial test position 501b. The six pin card channels of the new test position 501 are the first gate channel, the first source channel and the first drain channel of the first initial test position 501a and the second gate channel, the second source channel and the second drain channel of the second initial test position 501b. Figure 5 In the example, the first initial test position 501a is further represented by site1, and the second initial test position 501b is further represented by site2.

[0087] Step S103 , setting a new needle card corresponding to the new test position 501 , wherein the probes 502 in the new needle card are set according to the positions of the m pads, and each of the probes 502 is located on one of the needle card channels.

[0088] In some embodiments, Figure 5 As shown, a total of 6 probes 502 are shown, and the 6 probes 502 are also represented by S101, G101, D101, S102, G102 and D102, respectively, and are located on the first source channel, the first gate channel, the first drain channel, the second source channel, the second gate channel and the second drain channel respectively.

[0089] Step S104: Connect the new needle card to the pads of the bare chip under test and implement testing of the bare chip under test.

[0090] In some embodiments, it also includes:

[0091] A test module is developed in the program in the multi-test machine, and the test module allocates single test resources according to the new test position 501, the new needle card, the needle card channel and the pad.

[0092] Afterwards, the bare chip under test is tested under the control of the test module.

[0093] Among the single test resources allocated by the test module, the three board channels of the first initial test position 501a and the three board channels of the second initial test position 501b are used as the six board channels of the new test position 501, and the five board channels in the new test position 501 are used as the channels of the signal source required for the first to fifth pads 401e in the test process of the tested bare chip.

[0094] like Figure 5 As shown, the first gate channel is connected to the first pad 401 a through the corresponding probe 502 .

[0095] The first source channel is connected to the fourth pad 401d through the corresponding probe 502 .

[0096] The first drain channel is connected to the fifth pad 401 e through the corresponding probe 502 .

[0097] The second gate channel is connected to the third pad 401 c through the corresponding probe 502 .

[0098] The second source channel is connected to the second pad 401 b through the corresponding probe 502 .

[0099] In the embodiment of the present invention, the test items for testing the bare chip under test are set according to the logic function of the bare chip under test.

[0100] Further, in Figure 5 In some of the embodiments shown, the test items of the tested bare chip include tests of logic-on voltage and logic-off voltage.

[0101] In the test item of the logic on voltage, the test conditions are:

[0102] The second pad 401b is excited by a first voltage, the fifth pad 401e is grounded, the first pad 401a is excited by a high voltage, and the third pad 401c is excited by a second voltage, and whether the voltage of the fourth pad 401d is 0V is measured; the high voltage is the voltage that turns on the first MOSFET tube MN101 and the second MOSFET tube MN102.

[0103] In the test item of the logic off voltage, the test conditions are:

[0104] The second pad 401b is excited by a first voltage, the fifth pad 401e is grounded, the first pad 401a is excited by a low voltage, and the third pad 401c is excited by a second voltage, and whether the voltage of the fourth pad 401d is the second voltage is measured; the low voltage is a voltage that disconnects the first MOSFET tube MN101 and the second MOSFET tube MN102.

[0105] If the two test items of the tested bare chip are all passed, it is determined that all three MOSFET tubes are tested and passed.

[0106] When the discrete device of the tested bare chip includes multiple MOSFET tubes, different from the existing method that needs to test each MOSFET tube separately, the embodiment of the present invention combines the initial test position related to the test of a single MOSFET tube into a new test position 501 that can include all pads in the discrete device and sets a single new probe 502 card according to the new test position 501. In this way, during the test, the new probe 502 card only needs to be inserted into the tested bare chip once to test all MOSFET tubes in the discrete device. Therefore, a single needle card can be used for a single test to test each MOSFET tube in the discrete device, which can save the needle card cost, avoid repeated insertion of some pads, and improve the test efficiency.

[0107] The following table further describes the embodiments of the present invention in detail:

[0108] In the embodiment of the present invention, a multi-site synchronous test machine is used to force two sites to be merged into one site, so that the original three channels of one site are expanded to six channels: in actual testing, site1 is used as the main site and site2 is used as the auxiliary site. A single-step test with a needle card can be used to complete the verification of the logic function. In this way, it is possible to determine whether the functions of the three MOSFET tubes are ok at the same time, which can save the production cost of two needle cards, save the test time of two CP steps, and avoid repeated needle insertion on the Pad.

[0109] In the embodiment of the present invention, the board resource allocation during the test is as follows: Figure 5 As shown, the probe card is designed and manufactured: the PAen Pad, i.e. the first pad 401a, is connected to the G-end channel of site1, i.e., it is connected to the G-end channel through the probe G101; the VgatePad at the measurement end, i.e., the fourth pad 401d, is connected to the S-end channel of site1; the Ground pad, i.e., the fifth pad 401e, is connected to the D-end channel of Site1; the Vdd pad, i.e., the second pad 401b, is connected to the S-end channel of site2; and the VC pad, i.e., the third pad 401c, is connected to the G-end channel of site2.

[0110] Reconfigure the machine's control resources within the program and merge site1 and site2 into one site.

[0111] A new test module is developed in the program, and the test source board resources are reallocated: the comparison between the new and old tests is shown in Table 1 and Table 2 below:

[0112] Table 1

[0113]

[0114]

[0115] Table 1 is a table for allocating test source board resources in the existing method, namely 2 simultaneous tests are divided into 3 steps: simultaneous test resource allocation of 3 pin cards. It can be seen that 2 sites, namely site1 and site2, will realize simultaneous testing of two bare chips, namely die1 and die2. Site1 corresponds to the testing of each MOSFET of die1, namely MOSFET1, MOSFET2 and MOSFET3, and site2 corresponds to the testing of each MOSFET of die2, namely MOSFET1, MOSFET2 and MOSFET3. Among them, the test is divided into 3 steps. The first step is to simultaneously test MOSFET1 of die1 and MOSFET1 of die2. The second step is to simultaneously test MOSFET2 of die1 and MOSFET2 of die2. The third step is to simultaneously test MOSFET3 of die1 and MOSFET3 of die2.

[0116] As shown in Table 1, in site1, the three pin card channels, namely the gate channel, source channel and drain channel, are represented by Gate1, Source1 and Drain1 respectively, and the corresponding three test resources are: channel 1 of board A, channel 1 of board B and channel 1 of board C. When testing, the corresponding signals are set according to the MOSFET to be tested, combined with Figure 3 As shown, the three signals for testing MOSFET1 are die1_Paen, die1_Ground and die1_Vdd, i.e., PAen, Vdd and Ground in die1; the three signals for testing MOSFET2 are die1_Paen, die1_Vgate and die1_VC, i.e., PAen, Vgate and VC in die1; the three signals for testing MOSFET3 are die1_Vdd, die1_Ground and die1_Vgate, i.e., Vdd, Ground and Vgate in die1.

[0117] In Site2, the three pin card channels are represented by Gate2, Source2 and Drain2, and the corresponding three test resources are: Channel 2 of Board A, Channel 2 of Board B and Channel 2 of Board C. When testing, the corresponding signals are set according to the MOSFET to be tested. Figure 3 As shown, the three signals for testing MOSFET1 are die2_Paen, die2_Ground and die2_Vdd, i.e., PAen, Vdd and Ground in die2; the three signals for testing MOSFET2 are die2_Paen, die2_Vgate and die2_VC, i.e., PAen, Vgate and VC in die2; the three signals for testing MOSFET3 are die2_Vdd, die2_Ground and die2_Vgate, i.e., Vdd, Ground and Vgate in die2.

[0118] Table 2

[0119]

[0120] Table 2 is a test resource allocation scheme for a single test of a pin card corresponding to the method of the embodiment of the present invention. It can be seen that:

[0121] The site in Table 2 is formed by combining site1 and site2 in Table 1. The pin card channels use the 6 pin card channels corresponding to site1 and site2 in Table 1, namely Gate1, Source1, Drain1, Gate2, Source2 and Drain2; the test resources correspond to the 6 channel resources in Table 1, namely channel 1 of board A, channel 1 of board B, channel 1 of board C, channel 2 of board A, channel 2 of board B and channel 2 of board C. Figure 5 As shown in the figure, the signals required for the test are the signals corresponding to the five pads of die1, namely: die1_Paen, die1_Vgate, die1_Ground, die1_VC and die1_Vdd. After the resources are allocated, the required test can be completed by stimulating or measuring the signals corresponding to the test conditions of the test items.

[0122] The following further illustrates the difference between the test conditions corresponding to the test items of the existing method and the test conditions corresponding to the test items of the embodiment of the present invention in combination with Table 3 and Table 4:

[0123] Table 3

[0124]

[0125] Table 3 shows the test conditions of the two test items corresponding to the three-step test method corresponding to the existing conventional test scheme. The test items list BVDSS test and VTH, BVDSS represents source-drain breakdown voltage, and VTH represents threshold voltage.

[0126] The test conditions of BVDSS are: G / S short-circuited, D-side excitation (force) current I, and measurement of DS voltage V. For example, corresponding to the test of MOSFET1 of die1 in Table 1, gate1 and source1 are short-circuited, drain1 is excited current I, and the voltage V of drain1 and source1 is measured. The corresponding signals in Table 1 are die1_Paen, die1_Ground and die1_Vdd respectively.

[0127] Similar to the VTH test conditions, G / D are short-circuited, a force current I is applied between GS, and the voltage V between GS is measured.

[0128] In existing methods, to determine whether a MOSFET is normal, more test items are often required, such as VDSON, IGSS, and IDSS tests.

[0129] Table 4

[0130]

[0131] As shown in Table 2, the test items and corresponding test conditions used in the test method corresponding to the test scheme of the embodiment of the present invention, in the method of the embodiment of the present invention, at least only two test items are needed: Vopen and Vclose, Vopen corresponds to the logic open voltage, and Vclose corresponds to the logic close voltage.

[0132] The corresponding test conditions are:

[0133] The test conditions of Vopen are: Vdd end force voltage V0; Ground is normally grounded; PAen end force high voltage VH; VC end force voltage V1; measure whether the voltage of Vgate is 0? .

[0134] As shown in Table 1, for the bare chip die1, the signal at the Vdd end is die1_Vdd, and the corresponding pin card channel is source2; the signal at the Ground end is die1_Ground, and the corresponding pin card channel is Drain1; the signal at the PAen end is die1_PAen, and the corresponding pin card channel is Gate1; the signal at the VC end is die1_VC, and the corresponding pin card channel is Gate2; the signal at the Vgate end is die1_Vgate, and the corresponding pin card channel is Source1.

[0135] The test conditions of Vclose are: force voltage V0 at Vdd; normal grounding at Ground; force high voltage VL at PAen; force voltage V1 at VC; measure whether the voltage of Vgate is V1?

[0136] Therefore, in the embodiment of the present invention, according to the newly developed test module, at least two tests are required to determine whether all three MOSFETs have passed.

[0137] In the embodiment of the present invention, the discrete device logic module is composed of 3 MOSFETs. When using a conventional 3-port discrete device probe card for testing, 3 probe cards need to be made for 3-step testing. The embodiment of the present invention combines machine resources with discrete device pad openings, and only needs to design 1 5-port test probe card to complete a single-step test, which saves the production cost of 2 probe cards and avoids multiple probing of the PAD being tested.

[0138] For a test machine for multiple simultaneous tests of discrete devices, the embodiment of the present invention can merge two sites into one site by reconfiguring the test resources of the machine in a program.

[0139] As shown in Table 2, in the embodiment of the present invention, new test items can be developed according to the test resources, and the original maximum of 3 sources simultaneously forcing a die under test is upgraded to a maximum of 6 sources simultaneously forcing a die.

[0140] In the existing method, a conventional 3-port MOSFET tube needs to pass standard VTH / VDSON / IGSS / IDSS test items to determine whether a MOSFET tube is normal. In the method of the embodiment of the present invention, a logic chip composed of three MOSFETs can complete the inspection of all three MOSFETs through at least two test items.

[0141] The present invention has been described in detail above through specific embodiments, but these do not constitute limitations of the present invention. Without departing from the principle of the present invention, those skilled in the art may also make many variations and improvements, which should also be considered as the protection scope of the present invention.

Claims

1. A discrete device testing method for integrating multiple MOSFET tubes, characterized in that: The steps include: Providing a bare chip to be tested, wherein the bare chip to be tested is a discrete device integrated by a plurality of MOSFET tubes, the bare chip to be tested has m pads and is used to implement a logic function, where m is greater than or equal to 4; Merge n initial test positions in multiple test machines into a new test position, each of the initial test positions includes three pin card channels connected to three electrodes of the MOSFET tube; the number of pin card channels of the new test position is 3n, where n is an integer, and 3n is greater than or equal to m; Setting a new needle card corresponding to the new test position, wherein the probes in the new needle card are set according to the positions of the m pads, and each of the probes is located on one of the needle card channels; The new needle card is connected to each of the pads of the tested bare chip to implement the test of the tested bare chip.

2. The discrete device testing method for integrating multiple MOSFET tubes according to claim 1, characterized in that: Also includes: Developing a test module in a program in the multi-test machine, the test module allocating single test resources according to the new test position, the new needle card, the needle card channel and the pad; Afterwards, the bare chip under test is tested under the control of the test module.

3. The discrete device testing method for integrating multiple MOSFET tubes as claimed in claim 2, characterized in that: The test items for testing the bare chip under test are set according to the logic functions of the bare chip under test.

4. The discrete device testing method for integrating multiple MOSFET tubes as claimed in claim 3, characterized in that: The discrete device of the tested bare chip integrates 3 MOSFET tubes, m is equal to 5, and the tested bare chip is used to realize a logic switch function.

5. The discrete device testing method for integrating multiple MOSFET tubes as claimed in claim 4, characterized in that: n is equal to 2.

6. The discrete device testing method for integrating multiple MOSFET tubes as claimed in claim 5, characterized in that: The discrete devices included in the tested bare chip include: a first MOSFET tube, a second MOSFET tube, a third MOSFET tube, a first resistor and a second resistor; The first end of the first resistor, the gate of the first MOSFET tube and the gate of the second MOSFET tube are all connected to the first pad; A first end of the second resistor is connected to a second pad; The second end of the second resistor is connected to the drain of the first MOSFET tube and the gate of the third MOSFET tube; The drain of the second MOSFET tube is connected to the third pad; The source of the second MOSFET tube and the source of the third MOSFET tube are both connected to the fourth pad; The second end of the first resistor, the source of the first MOSFET tube and the source of the third MOSFET tube are all connected to the fifth pad.

7. The discrete device testing method for integrating multiple MOSFET tubes according to claim 6, characterized in that: The first MOSFET tube, the second MOSFET tube and the third MOSFET tube are all NMOS; The first pad serves as an enable signal terminal; The second pad serves as a device voltage terminal; The third pad serves as a circuit voltage terminal; The fourth pad serves as a gate voltage terminal; The fifth pad serves as a ground terminal.

8. The discrete device testing method for integrating multiple MOSFET tubes according to claim 7, characterized in that: The three pin card channels of each initial test position are respectively a gate channel, a source channel and a drain channel; The new test bit is formed by combining the first initial test bit and the second initial test bit; The six pin card channels of the new test position are respectively the first gate channel, the first source channel and the first drain channel of the first initial test position and the second gate channel, the second source channel and the second drain channel of the second initial test position.

9. The discrete device testing method for integrating multiple MOSFET tubes as claimed in claim 8, characterized in that: Among the single test resources allocated by the test module, the three board channels of the first initial test position and the three board channels of the second initial test position are used as the six board channels of the new test position, and the five board channels in the new test position are used as the channels of the signal sources required for the first to fifth pads in the test process of the tested bare chip.

10. The discrete device testing method for integrating multiple MOSFET tubes according to claim 9, characterized in that: The first gate channel is connected to the first pad via the corresponding probe; The first source channel is connected to the fourth pad via the corresponding probe; The first drain channel is connected to the fifth pad via the corresponding probe; The second gate channel is connected to the third pad via the corresponding probe; The second source channel is connected to the second pad via the corresponding probe.

11. The discrete device testing method for integrating multiple MOSFET tubes according to claim 10, characterized in that: The test items of the bare chip under test include tests of logic-on voltage and logic-off voltage.

12. The discrete device testing method for integrating multiple MOSFET tubes according to claim 11, characterized in that: In the test item of the logic on voltage, the test conditions are: The second pad is excited by a first voltage, the fifth pad is grounded, the first pad is excited by a high voltage and the third pad is excited by a second voltage, and whether the voltage of the fourth pad is 0V is measured; the high voltage is the voltage that turns on the first MOSFET tube and the second MOSFET tube.

13. The discrete device testing method for integrating multiple MOSFET tubes according to claim 12, characterized in that: In the test item of the logic off voltage, the test conditions are: The second pad is excited with a first voltage, the fifth pad is grounded, the first pad is excited with a low voltage, and the third pad is excited with a second voltage, and whether the voltage of the fourth pad is the second voltage is measured; The low voltage is a voltage that disconnects the first MOSFET tube and the second MOSFET tube.

14. The discrete device testing method for integrating multiple MOSFET tubes according to claim 13, characterized in that: If the two test items of the tested bare chip are all passed, it is determined that all three MOSFET tubes are tested and passed.

Citation Information

Cited By

  • Discrete device BVDSS test method

    CN119535127A