Built-in socket self-stabilizing assembly and prefabricated hollow pile cutting construction method
Through the built-in plug-in self-stabilizing assembly as the internal support and lifting hanger for prefabricated hollow pile pile cutting pile cutting, the problems of safety risks and low construction efficiency of construction personnel in the existing technology are solved, and higher quality and more efficient pile cutting are achieved process.
Patent Information
- Application Number
- CN202411197833.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-29
- Publication Date
- 2024-11-05
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The existing prefabricated pile cutting methods have problems such as high safety risks, poor quality and low construction efficiency of construction personnel. The traditional cutting methods require anti-tilt control and occupy a large amount of site space.
Using built-in plug-in self-stabilizing components, including steel pipes, cover plates and lifting rings. By setting through holes and pins on the steel pipes, it serves as the internal support and lifting hanger for prefabricated hollow piles to ensure construction safety and improve the quality of pile cutting and efficiency.
Effectively ensure the safety of construction personnel, improve the quality of pile cutting and construction efficiency, reduce site occupation, and achieve stability and safety of lifting.
Smart Images

Figure CN118895758A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building construction, and in particular to a built-in socket-and-spigot self-stabilizing component and a prefabricated hollow pile cutting construction method. Background Art
[0002] As construction enters a new stage of safer and higher-quality development, the refinement of construction technology is required to ensure the safety of personnel during the construction process while also ensuring and improving the quality and efficiency of the project.
[0003] In existing foundation projects, precast piles are usually cut or crushed manually. However, cutting requires construction risk control to prevent tipping and hitting people. Usually, workers do not completely cut the upper and lower sections of the pile, leaving a part of the pile body connected to prevent the broken pile from tipping and hitting people. Finally, an excavator is used to break and remove the cut pile part; manual crushing is when construction workers use a handheld pickaxe to crush on site, resulting in poor quality of the pile section and taking up a lot of construction time and foundation pit space.
[0004] In summary, these traditional pile cutting methods cannot effectively guarantee the safety of construction workers, and are inefficient in terms of construction quality and site arrangement. To this end, technical personnel in this field have been looking for solutions to meet this demand. Summary of the invention
[0005] The purpose of the present invention is to provide a built-in socket-and-spigot self-stabilizing component and a prefabricated hollow pile cutting construction method, which can not only ensure the safety of personnel during the construction process, but also ensure and improve the pile cutting quality and construction efficiency.
[0006] In order to solve the above technical problems, the present invention provides a built-in socket-and-spigot self-stabilizing component, the built-in socket-and-spigot self-stabilizing component comprising: a built-in socket-and-spigot self-stabilizing component and a latch; wherein the built-in socket-and-spigot self-stabilizing component comprises:
[0007] A steel pipe, the wall of which is provided with a plurality of through holes spaced apart along its axis, any of which can be adapted to receive a latch pin;
[0008] a cover plate, vertically fixed to one end of the steel pipe;
[0009] A hanging ring is fixedly arranged on the cover plate.
[0010] Optionally, in the built-in socket-and-spigot self-stabilizing component, the plurality of pairs of through holes are based on the center position of the steel pipe and are spaced apart along its axis toward both sides of the center position.
[0011] Optionally, in the built-in socket-and-spigot self-stabilizing component, the spacing between two adjacent through holes is equal to the diameter of the steel pipe.
[0012] The present invention also provides a prefabricated hollow pile cutting construction method, the prefabricated hollow pile cutting construction method comprising the following steps:
[0013] S1: processing the built-in socket-and-spigot self-stabilizing component as described above according to the inner diameter of the prefabricated hollow pile, so that the steel pipe diameter of the built-in socket-and-spigot self-stabilizing component is smaller than the inner diameter of the prefabricated hollow pile;
[0014] S2: Hanging the built-in socket-and-spigot self-stabilizing member to the predetermined position inside the prefabricated hollow pile where the pile needs to be cut;
[0015] S3: cutting the prefabricated hollow pile according to the pile cutting position;
[0016] S4: After the prefabricated hollow pile is cut, the cut upper half of the pile is slowly hoisted, and the hoisting is stopped when any pair of through holes on the steel pipe of the built-in socket-and-spigot self-stabilizing member is exposed, and a pin is inserted into the exposed through hole so that the pin cooperates with the steel pipe to receive the upper half of the pile;
[0017] S5: Stop lifting the cut upper pile section, lift the internal socket-and-spigot self-stabilizing member to the temporary stacking point for the cut piles, pull out the latch at the temporary stacking point for the cut piles, take out the internal socket-and-spigot self-stabilizing member, and leave the upper pile section at the temporary stacking point for the cut piles.
[0018] Optionally, in the prefabricated hollow pile cutting construction method, step S2 includes the following steps:
[0019] According to the insertion ratio of the built-in socket-and-spigot self-stabilizing component, the built-in socket-and-spigot self-stabilizing component is hoisted and placed inside the prefabricated hollow pile where the pile needs to be cut; wherein the insertion ratio is: 0.5≥L2 / L1≥1, L2 is the steel pipe length of the built-in socket-and-spigot self-stabilizing component below the pile cutting position; L1 is the steel pipe length of the built-in socket-and-spigot self-stabilizing component above the pile cutting position.
[0020] Optionally, in the prefabricated hollow pile cutting construction method, in step S4, the process of slowly lifting the cut upper half of the pile includes:
[0021] Use a truck crane to slowly lift the cut upper half of the pile based on temporary clamps and wire ropes.
[0022] Optionally, in the prefabricated hollow pile cutting construction method, in step S5, the process of stopping the lifting of the cut upper half of the pile includes:
[0023] Slowly lower the temporary clamp and wire rope.
[0024] Optionally, in the prefabricated hollow pile cutting construction method, in step S5, the process of hoisting the built-in socket-and-spigot self-stabilizing member to the temporary pile cutting stacking point includes:
[0025] Using a truck crane, the built-in socket-and-spigot self-stabilizing component is hoisted to the temporary stacking point for the cut piles based on the lifting ring of the built-in socket-and-spigot self-stabilizing component.
[0026] In the built-in socket-and-spigot self-stabilizing assembly and the prefabricated hollow pile cutting construction method provided by the present invention, the built-in socket-and-spigot self-stabilizing assembly includes: a built-in socket-and-spigot self-stabilizing member and a latch; wherein the built-in socket-and-spigot self-stabilizing member includes: a steel pipe, a plurality of through holes spaced along its axis are opened on the pipe wall, and any pair of through holes can be adapted to the latch; a cover plate vertically fixed to one end of the steel pipe; and a lifting ring fixed to the cover plate. During the prefabricated hollow pile cutting construction process, the built-in socket-and-spigot self-stabilizing member is hoisted and placed inside the pile to be cut, serving as an internal support for the cutting process and a hanger for hoisting the cut pile part, which not only ensures the safety of personnel during the construction process, but also ensures and improves the quality of the pile cutting and the construction efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] The above and other objects, features and advantages of the present disclosure will become more apparent through a more detailed description of exemplary embodiments of the present disclosure in conjunction with the accompanying drawings, wherein like reference numerals generally represent like components throughout the exemplary embodiments of the present disclosure.
[0028] Figure 1 It is a structural schematic diagram of a built-in socket-and-spigot self-stabilizing component in one embodiment of the present invention;
[0029] Figure 2 The present invention is a flowchart of a prefabricated hollow pile cutting construction method in one embodiment of the present invention.
[0030] Figure 3 is a schematic diagram of executing step S2 in the prefabricated hollow pile cutting construction method in one embodiment of the invention;
[0031] Figure 4 is a schematic diagram of executing step S4 in the prefabricated hollow pile cutting construction method in one embodiment of the invention;
[0032] Figure 5 It is a schematic diagram of executing step S5 in the prefabricated hollow pile cutting construction method in one embodiment of the invention.
[0033] In the figure:
[0034] 1-Built-in socket-and-spigot self-stabilizing member; 11-steel pipe; 110-through hole; 12-cover plate; 13-lifting ring;
[0035] 2- latch;
[0036] 3- Prefabricated hollow piles;
[0037] 4-temporary clamp;
[0038] 5-Wire rope. DETAILED DESCRIPTION
[0039] The following is a further detailed description of the built-in socket-and-spigot self-stabilizing component and the prefabricated hollow pile cutting construction method proposed by the present invention in combination with the accompanying drawings and specific embodiments. The advantages and features of the present invention will become clearer according to the following description and claims. It should be noted that the accompanying drawings are all in a very simplified form and are not in precise proportions, and are only used to conveniently and clearly assist in explaining the purpose of the embodiments of the present invention.
[0040] The present invention will now be described in further detail with reference to the accompanying drawings. These drawings are simplified schematic diagrams, which only illustrate the basic structure of the present invention in a schematic manner, and therefore only show the components related to the present invention.
[0041] In the description of the invention, it is necessary to understand that the terms “center”, “longitudinal”, “lateral”, “length”, “width”, “thickness”, “up”, “down”, “front”, “back”, “left”, “right”, “vertical”, “horizontal”, “top”, “bottom”, “inside”, “outside”, “clockwise”, “counterclockwise”, etc., indicating the orientation or position relationship, are based on the orientation or position relationship shown in the drawings, and are only for the convenience of describing the invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the invention.
[0042] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features. In the description of the invention, the meaning of "plurality" is two or more, unless otherwise clearly and specifically defined.
[0043] In the invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be an indirect connection through an intermediate medium, or it can be the internal communication of two elements. For ordinary technicians in this field, the specific meanings of the above terms in the invention can be understood according to the specific circumstances.
[0044] Please refer to Figure 1 and Figure 4The built-in socket-and-spigot self-stabilizing component includes: a steel pipe 11, a cover plate 12 and a lifting ring 13. The wall of the steel pipe 11 is provided with a plurality of through holes 110 spaced apart along its axis, and any pair of through holes 110 can be adapted to the plug 2; the cover plate 12 is vertically fixed to one end of the steel pipe 11; the lifting ring 13 is fixedly arranged on the cover plate 12.
[0045] Specifically, the plurality of pairs of through holes 110 are based on the center position of the steel pipe 11 and are spaced apart from each other along the axis thereof toward both sides of the center position; wherein the spacing between two adjacent pairs of through holes 110 is equal to the diameter of the steel pipe 11 .
[0046] Accordingly, this embodiment also provides a method for constructing a prefabricated hollow pile 3. Figures 1 to 5 The construction method for cutting the prefabricated hollow pile 3 described in this embodiment is described in detail.
[0047] First, please refer to Figure 1 and Figure 3 , execute step S1, and process the built-in socket-and-spigot self-stabilizing component as described above according to the inner diameter of the prefabricated hollow pile 3, so that the diameter d of the steel pipe 11 of the built-in socket-and-spigot self-stabilizing component 1 is smaller than the inner diameter D of the prefabricated hollow pile 3; in this embodiment, the prefabricated hollow pile 3 is preferably a pipe pile.
[0048] Next, please refer to Figure 3 , execute step S2, and hang the built-in socket-and-spigot self-stabilizing component 1 to a predetermined position inside the prefabricated hollow pile 3 where the pile needs to be cut; the predetermined position here refers to the need to hang the built-in socket-and-spigot self-stabilizing component 1 to the inside of the prefabricated hollow pile 3 where the pile needs to be cut according to the insertion ratio of the built-in socket-and-spigot self-stabilizing component 1; wherein the insertion ratio is: 0.5≥L2 / L1≥1, L2 is the length of the steel pipe 11 of the built-in socket-and-spigot self-stabilizing component 1 below the pile cutting position; L1 is the length of the steel pipe 11 of the built-in socket-and-spigot self-stabilizing component 1 above the pile cutting position.
[0049] Next, step S3 is executed to cut the prefabricated hollow pile 3 according to the pile cutting position. In the pile cutting stage (i.e., the pile cutting stage), the built-in socket-and-spigot self-stabilizing member 1 inside the prefabricated hollow pile 3 plays the role of internal support, thereby ensuring the safety of personnel during the construction process and ensuring and improving the quality of pile cutting.
[0050] Next, please refer to Figure 4 , execute step S4, after the prefabricated hollow pile 3 is cut, the cut upper half of the pile (i.e. Figure 4 The cut pile part in the middle is slowly lifted, and the lifting is stopped when any pair of through holes 110 on the steel pipe 11 of the built-in socket-and-spigot self-stabilizing member 1 is exposed, and the latch 2 is inserted into the exposed through hole 110 so that the latch 2 and the steel pipe 11 cooperate to receive the upper half of the pile.
[0051] The process of slowly lifting the cut upper half of the pile includes: using a car crane to slowly lift the cut upper half of the pile based on a temporary clamp 4 and a steel wire rope 5. In order to ensure the safety of the lifting process, the lifting speed should not be too fast, and the lifting should be slow.
[0052] Next, please refer to Figure 5 , execute step S5, stop lifting the upper half of the pile after cutting, lift the built-in socket-and-spigot self-stabilizing component 1 to the temporary stacking point of the cut pile, pull out the pin 2 at the temporary stacking point of the cut pile, take out the built-in socket-and-spigot self-stabilizing component 1, and leave the upper half of the pile at the temporary stacking point of the cut pile. In this process, the built-in socket-and-spigot self-stabilizing component plays the role of a hanger for lifting the cut pile part, further improving the safety of lifting the cut pile part. At this time, the disassembled built-in socket-and-spigot self-stabilizing component can be lifted back to the cut pile construction site for other cut pile construction, that is, the built-in socket-and-spigot self-stabilizing component can be reused, which is simple to operate and reduces construction costs.
[0053] Specifically, the process of stopping the lifting of the upper pile after cutting includes: slowly lowering the temporary clamp 4 and the wire rope 5; the process of lifting the built-in socket-and-spigot self-stabilizing component 1 to the temporary stacking point of the cut pile includes: using a truck crane to lift the built-in socket-and-spigot self-stabilizing component 1 to the temporary stacking point of the cut pile based on the lifting ring 13 of the built-in socket-and-spigot self-stabilizing component 1. That is, the truck crane no longer lifts on the upper pile based on the wire rope 5 and the temporary clamp 4, but changes the lifting node from the upper pile to the built-in socket-and-spigot self-stabilizing component 1. As a result, the upper pile is transported to the temporary stacking point of the cut pile based on the built-in socket-and-spigot self-stabilizing component as a hanging frame, so as to achieve a more stable lifting of the upper pile, which ensures construction safety and improves construction efficiency.
[0054] The prefabricated hollow pile 3 cutting construction method of the present invention utilizes the self-stabilizing method of steel sockets and adopts the designed built-in socket self-stabilizing components as the internal support of the pile cutting process and the hanger for lifting the pile cutting part. It has simple principle, convenient processing and convenient operation, greatly improves the self-stabilizing safety of the prefabricated hollow pile 3 and the efficiency of pile cutting construction, and ensures the quality of pile cutting.
[0055] It should be noted that, for the aforementioned method embodiments, for the sake of simplicity, they are all expressed as a series of action combinations, but those skilled in the art should be aware that the present application is not limited by the described order of actions, because according to the present application, certain steps can be performed in other orders or simultaneously. Secondly, those skilled in the art should also be aware that the embodiments described in the specification are all preferred embodiments, and the actions and modules involved are not necessarily required by the present application.
[0056] The above description is only a description of the preferred embodiments of the present invention, and is not intended to limit the scope of the present invention. Any changes or modifications made by a person skilled in the art in the field of the present invention based on the above disclosure shall fall within the scope of protection of the claims.
Claims
1. A built-in socket self-stabilizing component, characterized in that: include: An internal socket-and-spigot self-stabilizing member and a latch; wherein the internal socket-and-spigot self-stabilizing member comprises: A steel pipe, the wall of which is provided with a plurality of through holes spaced apart along its axis, any of which can be adapted to receive a latch pin; a cover plate, vertically fixed to one end of the steel pipe; A hanging ring is fixedly arranged on the cover plate.
2. The built-in socket-and-spigot self-stabilizing component according to claim 1, characterized in that: The plurality of pairs of through holes are based on the center position of the steel pipe and are spaced apart along the axis toward both sides of the center position.
3. The built-in socket-and-spigot self-stabilizing component according to claim 2, characterized in that: The distance between two adjacent through holes is equal to the diameter of the steel pipe.
4. A prefabricated hollow pile cutting construction method, characterized in that: The following steps are involved: S1: Processing the built-in socket-and-spigot self-stabilizing component according to any one of claims 1 to 3 according to the inner diameter of the prefabricated hollow pile, so that the steel pipe diameter of the built-in socket-and-spigot self-stabilizing component is smaller than the inner diameter of the prefabricated hollow pile; S2: Hanging the built-in socket-and-spigot self-stabilizing member to the predetermined position inside the prefabricated hollow pile where the pile needs to be cut; S3: cutting the prefabricated hollow pile according to the pile cutting position; S4: After the prefabricated hollow pile is cut, the cut upper half of the pile is slowly hoisted, and the hoisting is stopped when any pair of through holes on the steel pipe of the built-in socket-and-spigot self-stabilizing member is exposed, and a pin is inserted into the exposed through hole so that the pin cooperates with the steel pipe to receive the upper half of the pile; S5: Stop lifting the cut upper pile section, lift the internal socket-and-spigot self-stabilizing member to the temporary stacking point for the cut piles, pull out the latch at the temporary stacking point for the cut piles, take out the internal socket-and-spigot self-stabilizing member, and leave the upper pile section at the temporary stacking point for the cut piles.
5. The prefabricated hollow pile cutting construction method according to claim 4, characterized in that: Step S2 includes the following steps: According to the insertion ratio of the built-in socket-and-spigot self-stabilizing component, the built-in socket-and-spigot self-stabilizing component is hoisted and placed inside the prefabricated hollow pile where the pile needs to be cut; wherein the insertion ratio is: 0.5≥L2 / L1≥1, L2 is the steel pipe length of the built-in socket-and-spigot self-stabilizing component below the pile cutting position; L1 is the steel pipe length of the built-in socket-and-spigot self-stabilizing component above the pile cutting position.
6. The prefabricated hollow pile cutting construction method according to claim 4, characterized in that: In step S4, the process of slowly lifting the cut upper half of the pile includes: Use a truck crane to slowly lift the cut upper half of the pile based on temporary clamps and wire ropes.
7. The prefabricated hollow pile cutting construction method according to claim 6, characterized in that: In step S5, the process of stopping the lifting of the cut upper half pile includes: Slowly lower the temporary clamp and wire rope.
8. The prefabricated hollow pile cutting construction method according to claim 4, characterized in that: In step S5, the process of hoisting the internal socket-and-spigot self-stabilizing member to the temporary pile stacking point includes: Using a truck crane, the built-in socket-and-spigot self-stabilizing component is hoisted to the temporary stacking point for the cut piles based on the lifting ring of the built-in socket-and-spigot self-stabilizing component.
Citation Information
Patent Citations
Prefabricated hollow uplift pile plug pin type connecting structure
CN211171930U
Pile stabilizing device for pile cutting construction
CN211735395U