Drilling construction method of raise boring machine
By adding lime to the guide hole construction and using a slag discharge drilling rig to discharge rock chips in advance, combined with the abnormal conditions of filling cement slurry treatment, the problem of guide holes stuck and collapsed in the construction of the reverse well drilling rig is solved, and the construction efficiency and quality are improved , shortens construction period and reduces costs.
Patent Information
- Application Number
- CN202410920396.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-10
- Publication Date
- 2024-11-05
Smart Images

Figure CN118895976A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of drilling machines, and more specifically, to a drilling construction method of a raise borer. Background Art
[0002] At present, skylights are mainly used for ore sliding, ventilation, pedestrians, filling, pipeline installation, etc. in mining production. In addition, they have been used for a long time and are key projects in the infrastructure stage. There are problems such as high construction difficulty, long construction period, and high safety risks. In addition, skylights will increase the difficulty of construction or even make construction impossible when passing through broken and complex strata. When constructing ventilation shafts, cable shafts, and chute shafts at various levels of mining sites in mountain mines, if it is necessary to pass through broken and complex strata, reverse drilling rigs are usually used for construction. In the traditional construction process, the guide holes often get stuck, the holes collapse, etc., which seriously affect the construction progress. Summary of the invention
[0003] In view of the above problems, the present invention provides a drilling construction method of a raise boring machine to solve the problems of frequent drill jams and hole collapse in the guide holes in the existing raise boring construction, which affects the construction progress.
[0004] The drilling construction method of the raise boring machine provided by the present invention comprises the following steps: installing the raise boring machine at a preset position; debugging the raise boring machine, and when the debugging result meets the construction requirements, constructing a normal section of the guide hole and a broken rock layer section; wherein lime is added to the slurry for the guide hole construction; installing a slag discharge hole drilling machine, and drilling a lower hole through the slag discharge hole drilling machine until the lower borehole is connected with the upper guide hole; expanding the connected guide hole and the lower borehole to complete the drilling construction of the raise boring machine.
[0005] In addition, an optional technical solution is that the process of installing the raise boring rig includes: digging and building a chamber corresponding to the raise boring rig, and pouring concrete for the foundation and the sedimentation tank; when the concrete strength reaches the preset requirements, installing an I-beam on the concrete foundation; moving the raise boring rig to the center of the hole position according to the arrangement order of the drilling hole positions, and laying a track and placing a drill rod on one side of the raise boring rig; adjusting the main engine angle of the raise boring rig so that the main engine angle corresponds to the hole position; and connecting and fixing the raise boring rig to the I-beam.
[0006] In addition, an optional technical solution is that the process of constructing the normal section of the guide hole includes: connecting the drill bit with the short drill rod in the drill pipe, sending the short drill rod into the frame of the raise drilling rig through an external manipulator, and connecting and fixing it with the machine head; lowering the machine head until the drill bit contacts the rock to be drilled; first starting the slurry supply and then starting the raise drilling rig, and the drill bit uses a first preset drilling pressure to drill holes in the rock; after the short drill rod is drilled, first stopping the raise drilling rig and then stopping the slurry supply, and installing the second section of drill rod, and continuing to use the first preset drilling pressure for drilling; after the second section of drill rod has completely entered the guide hole, stopping the slurry supply and removing the second section of drill rod, installing a voltage stabilizer and pushing it into the guide hole; then installing the third section of drill rod, and continuing to use the first preset drilling pressure for drilling, and after the depth of the borehole exceeds 3 meters, drilling is carried out according to the second preset drilling pressure, and this step is repeated.
[0007] In addition, an optional technical solution is that the first preset drilling pressure is 15-20Kg / cm 2 The second preset drilling pressure is 30-40Kg / cm 2 .
[0008] In addition, an optional technical solution is that a drill support half-ring is installed in the base of the frame, and the drill support half-ring is used to support the second and third sections of the drill rod.
[0009] In addition, an optional technical solution is that the drill bit includes a roller drill bit, a ball tooth drill bit and a wedge tooth drill bit.
[0010] In addition, an optional technical solution is that during the construction of the normal section of the guide hole, a stabilizer is first added after the drill bit has drilled 3m; then, a stabilizer is added after the drill bit has drilled 10m, and thereafter a stabilizer is added every 10-20m.
[0011] In addition, an optional technical solution is to stop the drilling construction and perform cement slurry injection into the hole when the slag discharge particles in the guide hole are larger than normal or the pressure of the raise drilling rig suddenly increases; wherein the cement slurry injection into the hole includes: removing all drill rods in the borehole; pumping out the original slurry in the borehole with a water pump; preparing cement slurry with a mixing barrel and installing a grouting pipe to the bottom of the hole, and injecting the cement slurry into the borehole through the grouting pipe until the borehole is completely filled; and waiting for the cement slurry in the borehole to solidify until the strength reaches the design requirements, continuing the drilling construction at the original guide hole position.
[0012] In addition, an optional technical solution is that the process of drilling a lower hole through the slag hole drilling rig includes: closing the drill pincher of the slag hole drilling rig, starting the drilling rig and starting water drilling after the hole is drilled out, and opening the drill pincher after drilling into a preset depth; after a drill rod is drilled, the connecting sleeve is inserted into the drill pincher, and the drill clamp is closed to position the connecting sleeve; the motor of the slag hole drilling machine is controlled to reverse so that the drill tail is withdrawn from the connecting sleeve; one end of the drill rod is screwed into the connecting tube, and the other end of the drill rod is aligned with the drill tail, and the motor of the slag hole drilling machine is controlled to rotate forward, and the drill rod is connected to the tail drill; the drill pincher is opened to continue the drilling operation.
[0013] In addition, an optional technical solution is that the water-cement ratio of the cement slurry is 0.3-0.6.
[0014] The drilling construction method using the above-mentioned raise bore rig is to construct the normal section and the broken rock section of the guide hole on the raise bore rig, and at the same time install a slag hole drilling rig to drill the lower hole until the lower hole is connected with the upper guide hole; and when constructing the upper guide hole, lime is added to the slurry to improve the quality of the borehole wall protection, reduce the probability of drill sticking, and increase the speed of rock cuttings discharge; constructing the slag discharge drilling hole in the lower part can discharge the rock cuttings in advance through the slag discharge hole, solve the problem that the rock cuttings in the broken zone cannot be discharged and the drill is stuck, and can simplify the construction process, improve the construction efficiency and quality, and shorten the construction period.
[0015] In order to achieve the above and related purposes, one or more aspects of the present invention include the features that will be described in detail later. The following description and the accompanying drawings describe some exemplary aspects of the present invention in detail. However, these aspects indicate only some of the various ways in which the principles of the present invention can be used. In addition, the present invention is intended to include all these aspects and their equivalents. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] By referring to the following description in conjunction with the accompanying drawings, and with a more comprehensive understanding of the present invention, other objects and results of the present invention will become more apparent and easy to understand. In the accompanying drawings:
[0017] Figure 1 A flowchart of a drilling construction method of a raise boring machine according to an embodiment of the present invention;
[0018] Figure 2 The figure is a schematic diagram of the principle of the drilling construction method of the raise boring machine according to an embodiment of the present invention.
[0019] Figure numerals: raise boring machine 1, slag hole drilling machine 2.
[0020] The same reference numerals throughout the drawings indicate similar or corresponding features or functions. DETAILED DESCRIPTION
[0021] In the following description, for the purpose of illustration, in order to provide a comprehensive understanding of one or more embodiments, many specific details are set forth. However, it is apparent that these embodiments may also be implemented without these specific details. In other examples, for ease of describing one or more embodiments, known structures and devices are shown in the form of block diagrams.
[0022] In the description of the present invention, it is to be understood that the terms “center”, “longitudinal”, “lateral”, “length”, “width”, “thickness”, “up”, “down”, “front”, “back”, “left”, “right”, “vertical”, “horizontal”, “top”, “bottom”, “inside”, “outside”, “clockwise”, “counterclockwise”, “axial”, “radial”, “circumferential”, etc., indicating orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as limiting the present invention.
[0023] In order to solve the problems of frequent drill bit sticking and drill hole collapse in the guide hole of the existing raise drilling construction, which affects the construction progress, the present invention provides a drilling construction method of a raise drilling rig. When constructing the upper guide hole, lime is added to the slurry to improve the quality of the borehole wall protection, reduce the probability of drill bit sticking, and increase the speed of rock cuttings discharge. When constructing the slag discharge drilling hole in the lower part, the rock cuttings can be discharged in advance through the slag discharge hole, which solves the problem that the rock cuttings in the broken zone cannot be discharged and the drill is stuck. The construction process can be simplified, the construction efficiency and quality are improved, and the construction period is shortened.
[0024] In order to describe the drilling construction method of the raise boring machine of the present invention in detail, the specific embodiments of the present invention will be described in detail below with reference to the accompanying drawings.
[0025] Figure 1 The schematic flow chart of the drilling construction method of the raise boring machine according to the embodiment of the present invention is shown. Figure 2 The schematic principle of the raise boring machine according to the present invention is shown.
[0026] like Figure 1 and Figure 2 As shown together, the drilling construction method of the raise boring machine in the embodiment of the present invention includes:
[0027] S100: Install the raise boring machine at the preset location;
[0028] S200: Debugging the raise boring machine, and when the debugging result meets the construction requirements, constructing the normal section of the pilot hole and the broken rock section; wherein lime is added to the slurry of the pilot hole construction;
[0029] S300: installing a slag discharge hole drilling machine, and drilling a lower hole through the slag discharge hole drilling machine until the lower drill hole is connected with the upper guide hole;
[0030] S400: Expand the guide hole and the lower borehole after penetration to complete the drilling construction of the raise borer.
[0031] Among them, it should be noted that the raise drilling rig 1 and the slag hole drilling rig 2 can be constructed at the same time, and the start-up of the lower slag hole drilling rig 2 can be reasonably arranged according to the construction progress of the upper guide hole. The cooperation between the two can not only shorten the construction period, but also can timely discharge the rock cuttings generated by the raise drilling rig 1 through the slag hole, thereby solving the problem of rock cuttings stuck in the drill.
[0032] In addition, in the drilling construction method of the raise boring machine of the present invention, the process of installing the raise boring machine 1 may include: digging and building a chamber corresponding to the raise boring machine 1, and pouring concrete for the foundation and the sedimentation tank; when the concrete strength reaches the preset requirements, installing an I-beam crossbeam on the concrete foundation; according to the arrangement order of the drilling hole positions, moving the raise boring machine 1 to the center of the hole position, and laying a track and placing a drill rod on one side of the raise boring machine 1; adjusting the main machine angle of the raise boring machine 1 so that the angle of the main machine corresponds to the hole position; and connecting and fixing the raise boring machine 1 to the I-beam crossbeam.
[0033] As a specific example, after the chamber of the raise boring machine 1 is excavated, the foundation and sedimentation tank are poured with concrete. When the concrete strength reaches the design requirements, the Ia25×4 meter I-beam can be installed on the concrete foundation according to the equipment installation requirements, and the two ends of the beam are welded and fixed by round steel anchors with a diameter of 25×1.5 meters. After all the construction preparations are completed, the raise boring machine 1 uses diesel engine power to go to the chamber by itself, and moves the raise boring machine 1 to the center point of the hole according to the equipment layout sequence. The drilling rig position is determined according to the center of the raise boring machine 1, and the center point of the hole is aligned. The installation direction of the manipulator is determined according to the needs and assembled to the main machine according to the drawing. The track is laid on one side of the manipulator to place the drill rod.
[0034] Then, connect the power supply, air and water pipes, as well as the main engine oil pipes. Use clean diesel to clean the oil pipes before assembling them to avoid the entry of debris and damage to the hydraulic components. Fill the oil tank with hydraulic oil. Before starting the oil pump, you must fill the pump with clean hydraulic oil through the oil return port on the pump housing, otherwise it may cause damage to the oil pump. Turn on the power, start the oil pump, and run it idle for more than 5 minutes. After confirming that the equipment is running normally, operate the diagonal support cylinder to erect the main engine, control the diagonal support cylinder to slowly erect the main engine to the inclined position required for drilling, and then calibrate the verticality or inclination of the main engine through the angle adjustment boot plate to meet the drilling inclination requirements, check the inclination again, and perform a second positioning if necessary. After confirmation, use 16 M24 high-strength bolts to firmly fix the drilling rig boot plate and the two beams before drilling.
[0035] In step S200, the process of debugging the raise boring machine 1 includes: after the equipment is ready, move the main power switch to the on position, and determine whether the power is normal according to the power indicator light (red: normal; orange: wrong phase sequence); after the power is normal, comprehensively check whether the installation parts and pipeline connections of the host are firm, and start the host after everything is normal, run it for 5 minutes without load, and check whether the action of each component is accurate and reliable, whether the hydraulic system leaks oil, whether the water supply system is normal, whether the electrical system is normal, and whether the connection hose of the moving parts interferes. Drilling can only be started after confirming that everything is correct. In addition, an ultrasonic flaw detector can be used to detect the drill pipe to detect whether the medium inside the drill pipe has defects such as cracks, pores, inclusions, etc., and it can be used only after it is qualified, and the defective drill pipe should be replaced in time.
[0036] Then, the normal section of the guide hole is constructed. The process of the normal section of the guide hole construction includes: connecting the drill bit with the short drill rod in the drill pipe, sending the short drill rod into the frame of the raise drilling rig 1 through an external manipulator, and connecting and fixing it with the machine head; lowering the machine head until the drill bit contacts the rock to be drilled; first starting the slurry supply and then starting the raise drilling rig 1, and the drill bit uses the first preset drilling pressure to drill holes in the rock; after the short drill rod is drilled, first stop the raise drilling rig 1 and then stop the slurry supply, install the second section of the drill rod, and continue to use the first preset drilling pressure for drilling; after the second section of the drill rod enters the guide hole, stop the slurry supply and remove the second section of the drill rod, install the voltage stabilizer and push it into the guide hole; then install the third section of the drill rod, and continue to use the first preset drilling pressure for drilling. After the depth of the borehole exceeds 3 meters, drill according to the second preset drilling pressure, and repeat this step.
[0037] The first preset drilling pressure is 15-20Kg / cm 2 ; The second preset drilling pressure is 30-40Kg / cm 2 .
[0038] As a specific example, during the construction of the normal section of the pilot hole, ① use a short drill rod to drill a hole. First, connect the roller drill bit to the short drill rod. The manipulator grabs the short drill rod, puts it into the frame and connects it to the machine head. The manipulator is retracted, and the machine head is lowered until the roller drill bit contacts the rock. At the same time, a half-ring can be installed in the hole of the frame base to support the drill rod. The drill bit includes a roller drill bit, a ball-tooth drill bit, and a wedge-tooth drill bit. For example, a ball-tooth drill bit is used for hard rock, and a wedge-tooth drill bit is used for soft rock.
[0039] ② First open the water supply pipe and use a small drill to press (about 15-20 kg / cm 2 The drill bit is moved up and down to sweep the hole and clean the rock debris in the hole in time. At the same time, it is necessary to strengthen the measurement, correct the deviation of the hole in time, and drill another hole when the deviation is too large. It is not allowed to continue drilling in the deviated hole.
[0040] ③After drilling the short drill rod, stop the machine first and then stop the water supply. Install a drill rod according to the procedure, support the drill rod with a half-circlip, and continue to drill with a small drill pressure and a low speed. After the drill rod has completely entered the guide hole, stop the water supply, remove the drill rod, replace it with a stabilizer, and push it into the guide hole. Install another drill rod and continue to drill with a small drill pressure and a low speed. After the hole is more than 3 meters deep, drill according to normal parameters, and gradually increase the axial pressure and speed (pressure 30-40 kg / cm 2 ).
[0041] It should be noted that during the construction of the pilot hole, clean water is generally used as the slurry. The density of clean water is relatively low, and the efficiency of chip removal for broken rock formations is low. For this reason, in the present application, lime is added to the slurry to increase the density and adhesion of the slurry to improve the efficiency of drilling chip removal, and to increase the pressure of the slurry to balance the hole wall pressure and reduce the risk of hole collapse caused by imbalance in hole wall pressure; in addition, it can also calcify the rock with better anti-collapse performance, support the borehole wall, improve the forming quality of the borehole, reduce the risk of hole collapse, and ensure normal drilling of the borehole.
[0042] In another specific embodiment of the present invention, the drilling construction method of the raise boring machine also includes stopping the drilling construction and pouring cement slurry into the hole when the slag particles in the guide hole are larger than normal values or the pressure of the raise boring machine suddenly increases; wherein the pouring cement slurry into the hole includes: removing all drill rods in the borehole; pumping out the original slurry in the borehole with a water pump; preparing cement slurry with a mixing barrel and installing a grouting pipe to the bottom of the hole, pouring cement slurry into the borehole through the grouting pipe until the borehole is completely filled; and waiting for the cement slurry in the borehole to solidify until the strength reaches the design requirements, continuing the drilling construction at the original guide hole position.
[0043] The water-cement ratio of the cement slurry is in the range of 0.3-0.6, preferably 0.5, so that the cement slurry can quickly and effectively enter the borehole and reach a preset strength after solidification.
[0044] During the construction of the broken rock section of the pilot hole, ① in order to control the drilling deviation rate within 1%, the air volume, water volume, wind pressure and water pressure of the slag discharge must be guaranteed to completely discharge the rock slag in the hole to prevent hole blockage. In addition to correctly installing the host and controlling the opening of the hole, it is also necessary to add a stabilizer after drilling 3 meters, add another stabilizer after drilling 10 meters, and add a stabilizer every 10-20 meters thereafter. As the drilling depth increases, the interval between stabilizers can be appropriately increased.
[0045] ② When installing the drill pipe, add drill pipe washers and thread oil, strictly control the advancement speed to avoid damaging the threads, and tighten each drill pipe thread. This is also an extremely important part of reducing the drill pipe deflection rate.
[0046] ③ Protect the hole mouth and do not drop metal or hard objects into it. If you find abnormal noise in the hole while drilling, stop drilling and deal with it. If metal objects fall into the hole, use a magnet to suck them out.
[0047] ④ The rock debris at the hole mouth should be cleared away in time, and attention should be paid to the particle size of the slag. If the amount is small and the particles are fine, the water volume should be increased. If it still does not work, consider whether the drill bit is damaged.
[0048] ⑤ Ensure the water volume and water pressure of the slag removal system to drain the rock slag in the hole to prevent blockage. When the drilling depth exceeds 20 meters, it is necessary to flush and drain the slag for 1-2 minutes after drilling each drill rod. The deeper the hole, the longer the slag removal time.
[0049] In another specific embodiment of the present invention, the process of drilling a lower hole by means of the slag hole drilling machine 2 includes: closing the drill bit of the slag hole drilling machine 2, starting the drilling machine and starting water drilling after the hole is drilled out, and opening the drill bit after drilling into a preset depth; after a drill rod is drilled, the connecting sleeve is inserted into the drill bit, and the drill clamp is closed to position the connecting sleeve; the motor of the slag hole drilling machine is controlled to reverse so that the drill tail is withdrawn from the connecting sleeve; one end of the drill rod is screwed into the connecting tube, and the other end of the drill rod is aligned with the drill tail, and the motor of the slag hole drilling machine is controlled to rotate forward, and the drill rod is connected to the tail drill; the drill bit is opened to continue the drilling operation.
[0050] Specifically, the installation process of the slag hole drilling machine 2 includes: installing the equipment drilling frame at the bottom according to the cross center line of the skylight, and the height of the roadway leveling must meet the requirements of the travel range of the cylinder (lifting cylinder). The roadway floor is cleaned to a hard bottom and sleepers and wooden boards are laid for leveling. The orientation and angle of the equipment are controlled within the allowable error range, and then the top should be firmly fixed, and all relevant bolts and nuts should be tightened. Both tops must be checked during operation.
[0051] Furthermore, the drilling process of the slag hole drilling machine 2 includes: closing the drill pincher when drilling the hole so that the drill rod does not shake, slightly opening the impact, rotation and propulsion valves, connecting a small amount of compressed air to make the slag hole drilling machine 2 tap and rotate slowly. After the hole is drilled out, sufficient air volume can be added, and the drill hole is flushed with water at the same time. After drilling to a certain depth, the drill pincher is opened to avoid unnecessary wear of the drill pincher.
[0052] Then, after finishing a drill rod, when the connection sleeve enters the drill pincher, stop pushing, close the water valve of the slag hole drill and the air valve of the rotary motor, shake the threaded connection of the drill rod loose, and then close the impact air valve (minimize the number of empty hits as much as possible). Close the drill clamp, clamp the drill rod connection sleeve, reverse the rotary motor of the slag hole drill, and pay attention to avoid high-speed drill rotation. At the same time, start the propulsion air motor to make the slag hole drill retreat, and the drill tail will slowly withdraw from the connection sleeve. After exiting, close the slag hole drill 2, turn on the propulsion air motor, and quickly withdraw the slag hole drill 2 to the bottom position. Check whether the water hole of the drill rod to be connected is unobstructed in advance and apply diluted wire rope grease or waste oil to the threads at both ends to facilitate unloading. Screw one end of the drill rod into the connecting tube by hand for 5 to 7 turns, and then align the other end with the drill tail, start the rotary motor of the slag hole drill rig at a low speed to rotate forward, start the propulsion air motor to make the slag hole drill rig 2 move forward, and after the drill rod is firmly connected, open the drill pincher, add sufficient air and water, and continue the operation.
[0053] After the lower drill hole and the upper guide hole are connected, loosen all the bolts and clamp the connection sleeve between the drill tail and the drill rod. Loosen all the screw buckles and hold the drill tail against the connection sleeve. Open the drill pincher, retreat the slag hole drill 2, and after withdrawing a drill rod, use the drill pincher to clamp the connection sleeve of the second drill rod, and unscrew the drill rod by hand. Repeat this process until the last drill rod is removed. After all the drill rods are removed, check the drilling cuttings discharge situation to ensure that the cuttings of the upper guide hole are normally discharged from the lower drill hole, and the upper raise drilling rig does not get stuck before the down-the-hole drilling rig can be removed.
[0054] Finally, carry out the hole reaming operation: ① After reverse drilling, use the rod removal wrench to remove the roller drill bit and the short-circuit rod at the bottom of the skylight. Transport the hole reaming cutter disc to the bottom of the skylight, and connect the cutter disc and the drill rod with a hanger. Contact the upper operator by phone or other information (knocking on the drill rod, etc.), lift the drill rod, hang the cutter disc straight, take out the hanger, and instruct the operator to connect the drill rod thread and tighten it. ② The lower working surface of the skylight to be expanded should be flat to ensure that the cutter disc cutters are in good stress state to reduce the impact of the hole reaming cutter disc. ③ At the beginning of hole reaming, because the contact surface is uneven, it should be advanced slowly and intermittently, and the tension and rotation speed should be reasonably controlled. After all the cutters of the cutter disc contact the rock, the hole can be reamed at normal pressure. The hole reaming tension is maintained at 70-80 kg / cm 2 , oil motor pressure is maintained at 160-180 kg / cm 2. ④ After each 1m of drill rod is expanded, the machine head is lowered by 0.3-0.5m. Start the rod clamp to clamp the drill rod, reverse the oil motor, loosen the machine head ball drill sleeve and the drill rod thread by 180° (half a circle). If the oil motor cannot be loosened after reversing, you can use the auxiliary rod unloader to loosen the thread, install the toothed enclosure block, hold the square mouth of the drill rod, slowly lower the machine head, the external teeth and the machine head are engaged, and then loosen the auxiliary drill unloader, wait for the lower thread of the drill rod to be unloaded, and retract the ratchet. After loosening, continue to reverse the oil motor. After completely disengaging, the propulsion cylinder rises quickly into place, the manipulator is sent into the frame, the drill rod is grasped, the toothed enclosure block is removed, the oil motor is reversed, the machine head and the drill rod thread are removed, the manipulator is retracted, and the machine head drops quickly, which is consistent with the rod connection operation. After the drill rod is connected, drilling begins, and the above operations are repeated until the final hole expansion is completed.
[0055] According to the drilling construction method of the raise boring machine of the present invention, lime is added to the slurry during the construction of the upper guide hole, which can improve the quality of the drilling wall protection, reduce the probability of drill sticking, and increase the speed of rock cuttings discharge. Furthermore, after adding lime to the guide hole slurry, when the rock cuttings cannot be discharged normally, the drill is stuck, and the hole collapses, cement slurry is poured and the hole is swept after the cement solidifies to continue the guide hole operation, thereby solving the problems of rock cuttings stuck in the drill and the hole collapse. The rock cuttings are discharged through the slag discharge hole in the lower construction, which solves the problems of broken rock cuttings unable to be discharged and drill stuck. The construction process can be simplified, the construction efficiency can be improved, the construction period can be shortened, the labor intensity and cost are low, and the construction quality is safe and reliable.
[0056] The drilling method of the raise boring machine according to the present invention is described as an example with reference to the accompanying drawings. However, those skilled in the art should understand that various improvements can be made to the drilling method of the raise boring machine proposed by the present invention without departing from the content of the present invention. Therefore, the protection scope of the present invention should be determined by the content of the attached claims.
Claims
1. A drilling construction method of a raise boring machine, characterized in that: include: Install the raise boring machine at the preset location; The raise boring machine is debugged, and when the debugging result meets the construction requirements, the normal section of the pilot hole and the broken rock section are constructed; wherein lime is added to the slurry for the pilot hole construction; Install a slag discharge hole drilling machine, and use the slag discharge hole drilling machine to drill a lower hole until the lower drilled hole is connected with the upper guide hole; The through-through guide hole and the lower borehole are enlarged to complete the drilling construction of the raise borer.
2. The drilling construction method of the raise boring machine according to claim 1, characterized in that: The process of installing the raise boring machine includes: Digging and building a chamber corresponding to the raise boring machine, and pouring concrete for the foundation and sedimentation tank; When the concrete strength reaches the preset requirements, install the I-beam on the concrete foundation; According to the arrangement order of the drilling holes, the raise boring machine is moved to the center of the hole, and a track is laid on one side of the raise boring machine and a drill rod is placed; Adjusting the main machine angle of the raise boring machine so that the main machine angle corresponds to the hole position; The raise boring machine is connected and fixed to the I-beam crossbeam.
3. The drilling construction method of the raise boring machine according to claim 1, characterized in that: The process of normal section construction of the pilot hole includes: Connecting the drill bit to the short drill rod in the drill rod, sending the short drill rod into the frame of the raise boring machine through an external manipulator, and connecting and fixing it with the machine head; Lowering the drill head until the drill bit contacts the rock to be drilled; First, the slurry supply is turned on and then the raise drilling machine is started, and the drill bit uses a first preset drilling pressure to drill holes in the rock; After the short drill pipe is drilled, the raise boring machine is stopped first, then the slurry supply is stopped, and the second section of drill pipe is installed, and the drilling is continued using the first preset drilling pressure; After the second section of drill pipe has completely entered the guide hole, the slurry supply is stopped and the second section of drill pipe is removed, and a voltage stabilizer is installed and pushed into the guide hole; Then install the third drill rod, and continue to use the first preset drilling pressure for drilling. After the depth of the borehole exceeds 3 meters, drill according to the second preset drilling pressure and repeat this step.
4. The drilling construction method of the raise boring machine according to claim 3, characterized in that: The first preset drilling pressure is 15-20Kg / cm 2 ; The second preset drilling pressure is 30-40Kg / cm 2 .
5. The drilling construction method of the raise boring machine according to claim 3, characterized in that: A drill support half-circle is installed in the base of the frame, and the drill support half-circle is used to support the second drill rod section and the third drill rod section.
6. The drilling construction method of the raise boring machine according to claim 3, characterized in that: The drill bits include roller cone drill bits, ball tooth drill bits and wedge tooth drill bits.
7. The drilling construction method of a raise boring machine according to claim 1, characterized in that: During the construction of the normal section of the guide hole, a stabilizer is firstly added after the drill bit has drilled 3m; then, a stabilizer is added after the drill bit has drilled 10m, and thereafter, a stabilizer is added every 10-20m.
8. The drilling construction method of a raise boring machine according to claim 1, characterized in that: The method further includes stopping the drilling construction and performing cement slurry pouring operation in the hole when the slag particles in the guide hole are larger than a normal value or the pressure of the raise boring machine increases suddenly; wherein the cement slurry pouring operation in the hole includes: Remove all the drill rods in the borehole; Use a water pump to drain out the original slurry in the borehole; Prepare cement slurry using a mixing bucket and install a grouting pipe to the bottom of the hole, and pour the cement slurry into the borehole through the grouting pipe until the borehole is completely filled; After the cement slurry in the borehole solidifies to a strength that meets the design requirements, continue drilling construction at the original guide hole position.
9. The drilling construction method of a raise boring machine according to claim 1, characterized in that: The process of lower drilling by the slag hole drilling rig includes: The chisel of the slag hole drilling machine is closed, the drilling machine is started, and water flushing drilling is started after the hole is drilled out, and the chisel is opened after drilling to a preset depth; After a drill rod is drilled, the connecting sleeve is inserted into the drill clamp, and the drill clamp is closed to position the connecting sleeve; Controlling the motor of the slag removal drilling machine to reverse, so that the shank tail is withdrawn from the connecting sleeve; Screw one end of the drill rod into the connecting tube, align the other end of the drill rod with the drill tail, control the motor of the slag removal drilling machine to rotate forward, and connect the drill rod with the drill tail; Open the drill pincher and continue the drilling operation.
10. The drilling construction method of a raise boring machine according to claim 8, characterized in that: The water-cement ratio of the cement slurry is 0.3-0.6.