Intelligent electric meter testing and calibrating device

Through the design of the smart meter test calibration device, automatic alignment and airtightness detection of the meter position is achieved using conveyor belts and adjustment components, which solves the problems of low efficiency and large error of meter testing in the prior art, and improves the testing efficiency and accuracy.

CN118897244AInactive Publication Date: 2024-11-05国网安徽省电力有限公司全椒县供电公司
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202410948877.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-16
Publication Date
2024-11-05
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

When multiple meters are tested simultaneously, the existing smart meter test device requires operators to manually adjust the meter position, which is inefficient and has high operating requirements, which can easily lead to errors in the test result.

Method used

A smart meter test calibration device is designed, including a base plate and a conveyor belt. The conveyor belt is equipped with power supply components and inflation components. The position of the meter is realized by adjusting components (frame, box, push plate, sliding frame, lifting platform, etc.) The automatic alignment and stability of the air tightness detection is combined with the air pressure sensor, and the power-on and air tightness testing steps are combined.

Benefits of technology

It realizes rapid and accurate adjustment of multiple meter positions, improves testing efficiency, reduces design and manufacturing costs, and ensures the accuracy and stability of the test results.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118897244A_ABST
    Figure CN118897244A_ABST
Patent Text Reader

Abstract

The invention discloses an intelligent electric meter testing and calibrating device, and relates to the technical field of electric meter testing, the intelligent electric meter testing and calibrating device comprises a bottom plate and a conveying belt arranged on the bottom plate, and one side of the conveying belt is provided with a power supply assembly; an adjusting assembly is arranged above the conveying belt. The adjusting assembly comprises a frame body and a plurality of box bodies fixedly installed on the frame body. A vertical baffle is fixedly installed on the inner side wall of the box body, and a first vertical push plate and a second vertical push plate are further installed on the inner side wall of the box body. The first push plate and the second push plate can translate relative to the box body, and translation paths of the first push plate and the second push plate are perpendicular to each other; the box body is further provided with a driving unit used for controlling the first push plate and the second push plate to move horizontally. Through the cooperation of the first push plate and the second push plate, the positions of the ammeters on the plurality of conveying belts can be adjusted at the same time, so that the joints of the ammeters are aligned with the power supply tubes of the power supply assembly, and the ammeters are always kept in a stable state in the testing process; the position of the ammeter can be rapidly and accurately adjusted.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of electric meter testing, and in particular to a smart electric meter testing and calibration device. Background Art

[0002] Smart meters are one of the basic devices for smart grid data collection. They are responsible for collecting, measuring and transmitting raw electric energy data, and are the basis for information integration, analysis optimization and information presentation.

[0003] During the production process of smart meters, power-on test and calibration are required to ensure the factory quality of the meters. There are various studies on this in the prior art. For example, a Chinese invention application with application publication number CN117452317A discloses a smart meter test device, which includes a transmission base, a second mounting frame fixedly connected to the transmission base, a first mounting plate connected to the second mounting frame in a lifting and sliding manner, and a first test part is arranged on the first mounting plate; a fourth mounting frame fixedly connected to the top of the second mounting frame, and a driving part for driving the test part to rise and fall is arranged on the fourth mounting frame; and two symmetrically arranged alignment plates. Another example is an electric meter testing device disclosed in a Chinese invention application with application publication number CN112505617A, which includes four columns, and an upper channel and a lower channel are fixedly connected between the four columns from top to bottom in sequence, the upper channel and the lower channel have the same structure, the upper channel includes a test assembly, a feeding mechanism is arranged above the front side of the test assembly, the test assembly includes a support plate, a material trough is fixedly connected to the top of the support plate, an upper material blocking cylinder is fixedly installed on the left side of the material trough and at the top of the support plate, and six sensing probes distributed in the vertical direction are fixedly connected to the front side wall of the material trough.

[0004] In fact, since it takes a certain amount of time to test an electric meter, in order to improve the efficiency of the test, multiple electric meters are usually tested at the same time. In the test devices in the prior art, including the above-mentioned patents, when testing multiple electric meters at the same time, the operator is required to adjust the position of each electric meter in turn before the test so that the connector of the electric meter is aligned with the connector of the test component. This is not only inefficient, but also requires a high level of operating experience from the operator. If the operator does not operate properly, the position of the electric meter will shift, which will cause errors in the test results. Based on this, how to quickly and accurately adjust the electric meter to the predetermined test position before testing multiple electric meters at the same time is a problem that technical personnel in this field need to solve. Summary of the invention

[0005] The purpose of the present invention is to provide a smart meter testing and calibration device to solve the above-mentioned deficiencies in the prior art.

[0006] In order to achieve the above-mentioned purpose, the present invention provides the following technical solutions: a smart meter testing and calibration device, comprising a base plate and a conveyor belt arranged on the base plate, a power supply assembly is arranged on one side of the conveyor belt; an adjustment assembly is arranged above the conveyor belt, the adjustment assembly comprises a frame and a plurality of boxes fixedly mounted on the frame; a vertical baffle is fixedly mounted on the inner wall of the box, and a vertical first push plate and a second push plate are also mounted on the inner wall of the box; the first push plate and the second push plate can translate relative to the box, and the translation paths of the two are perpendicular to each other; a driving unit for controlling the translation of the first push plate and the second push plate is also mounted on the box.

[0007] As a preferred technical solution of the present invention, the driving unit includes a first sliding frame fixedly mounted on the first push plate and slidably matched with the box body, and a second sliding frame fixedly mounted on the second push plate and slidably matched with the box body.

[0008] As a preferred technical solution of the present invention, a first control panel is fixedly mounted on the first sliding frame, and a second control panel is fixedly mounted on the second sliding frame; a first guide groove is provided on the first control panel, and a second guide groove is provided on the second control panel; a lifting platform is vertically slidably mounted on the outer wall of the box body, and a first round rod and a second round rod are rotatably mounted horizontally on the lifting platform, the first round rod cooperates with the first guide groove, and the second round rod cooperates with the second guide groove.

[0009] As a preferred technical solution of the present invention, an inflation component is provided on the other side of the conveyor belt, and the inflation component includes a plurality of inflation pumps whose number is the same as that of the box and whose positions correspond to each other, and an inflation tube is fixedly installed at the outlet of the inflation pump; the power supply component includes a plurality of power supplies whose number is the same as that of the box and whose positions correspond to each other, and two power supply tubes are fixedly installed on the power supply; the box is provided with a first through hole cooperating with the inflation tube, and a second through hole cooperating with the power supply tube; an air pressure sensor is fixedly installed on the inner wall of the box.

[0010] As a preferred technical solution of the present invention, the bottom surface of the box body is in a horizontal state, and a rubber layer is provided on the bottom surface of the box body; a horizontal pressure plate is provided below the conveyor belt.

[0011] As a preferred technical solution of the present invention, support arms are fixedly installed on both sides of the pressure plate and the frame, and a vertical rod passing through the support arms is installed on the base plate; a horizontal rod is fixedly installed on the base plate through a bracket, and a translation frame is horizontally slidably installed on the horizontal rod; connecting rods are rotatably installed on the ends of the support arms, and the upper and lower corresponding connecting rods are hinged together on the translation frame.

[0012] As a preferred technical solution of the present invention, a first lifting rod is vertically fixedly installed on the upper surface of the lifting platform, and a horizontal second lifting rod is commonly fixedly installed on the top of each lifting rod.

[0013] As a preferred technical solution of the present invention, the vertical rod is divided into a first section fixedly connected to the base plate and a second section rotatably installed on the top of the first section, the second section has a spiral groove on its surface, and a ball that cooperates with the spiral groove is rotatably installed inside the support arm; a wire drum coaxial with the second section is fixedly installed on the top of the second section, a pull wire is wound around the wire drum, and one end of the pull wire is fixedly connected to the second lifting rod; a vertical telescopic spring is fixedly connected between the lifting platform and the box body.

[0014] As a preferred technical solution of the present invention, a first horizontal rack is fixedly installed on the translation frame; a second horizontal rack is fixedly installed on the inflation assembly; a gear meshing with the second rack is rotatably installed on the bracket; the first rack has a first state meshing with the gear, and a second state separated from the gear.

[0015] As a preferred technical solution of the present invention, the connecting rod is an elastic telescopic rod.

[0016] In the above technical solution, the present invention provides a smart meter test and calibration device, which can adjust the position of multiple meters on the conveyor belt at the same time through the cooperation of the first push plate and the second push plate, so that the connector of the meter is aligned with the power supply tube of the power supply component, and the meter always remains in a stable state during the test; the effect of quickly and accurately adjusting the position of the meter is achieved. In addition, the device can perform power-on test and air tightness test on the meter at the same time, combining the two steps into one step, thereby improving the efficiency of the test; during the test process, only one power source is needed to realize the sequential movement of the adjustment component, the power supply component and the inflation component, thereby reducing the design and manufacturing costs. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the drawings required for use in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments recorded in the present invention. For ordinary technicians in this field, other drawings can also be obtained based on these drawings.

[0018] Figure 1 It is a schematic diagram of the three-dimensional structure of the smart meter testing and calibration device in Example 1;

[0019] Figure 2 for Figure 1 The enlarged schematic diagram of point A in the middle;

[0020] Figure 3 A top view of the smart meter testing and calibration device in Example 1;

[0021] Figure 4 It is a side view of the smart meter testing and calibration device in Example 1;

[0022] Figure 5 It is a front view of the smart meter testing and calibration device in Example 2;

[0023] Figure 6 for Figure 5 A magnified schematic diagram of point B in the middle.

[0024] Description of reference numerals:

[0025] 1. conveyor belt; 2. power supply assembly; 201. power supply device; 202. power supply tube; 3. adjustment assembly; 301. frame; 302. box; 303. baffle; 304. first push plate; 305. second push plate; 306. first sliding frame; 307. second sliding frame; 308. first control board; 309. second control board; 310. first guide groove; 311. second guide groove; 312. lifting platform; 313. first round rod; 314. second round rod; 315. first through hole; 3 16. Second through hole; 317. Air pressure sensor; 318. First lifting rod; 319. Second lifting rod; 320. Telescopic spring; 4. Inflatable assembly; 401. Air pump; 402. Inflatable tube; 5. Pressure plate; 6. Support arm; 7. Vertical rod; 701. First section; 702. Second section; 703. Spiral groove; 8. Horizontal rod; 9. Translation frame; 10. Connecting rod; 11. Ball; 12. Wire drum; 13. Pull wire; 14. First rack; 15. Second rack; 16. Gear. DETAILED DESCRIPTION

[0026] In order to enable those skilled in the art to better understand the technical solution of the present invention, the present invention will be further described in detail below with reference to the accompanying drawings.

[0027] Example 1

[0028] like Figure 1 and Figure 3As shown, this embodiment provides a smart meter test and calibration device, including a base plate and a conveyor belt 1 arranged on the base plate, the conveyor belt 1 is controlled by a pulley, and the pulley is controlled by an external driving device; the conveyor belt 1 performs intermittent conveying, the conveyor belt 1 conveys the same distance and time each time, and the time of each interval stop is also the same; the conveyor belt 1 is arranged in a ring shape and is divided into an upper and lower layer, the upper and lower layers are both in a horizontal state, and there is a distance of 40cm between the two layers; a power supply component 2 is arranged on one side of the conveyor belt 1, and the power supply component 2 includes a plurality of power supplies 201, a plurality of The power supplies 201 are arranged equidistantly and fixedly mounted on the power supply rack. Two power supply tubes 202 are fixedly mounted on the power supply 201, and conductors are arranged inside the power supply tubes 202. An inflation component 4 is arranged on the other side of the conveyor belt 1. The inflation component 4 includes a plurality of inflation pumps 401. The number of inflation pumps 401 is the same as that of the power supplies 201 and their horizontal positions correspond one to one. The plurality of inflation pumps 401 are arranged equidistantly and fixedly mounted on the inflation rack. An inflation tube 402 is fixedly mounted at the outlet of the inflation pump 401. The shape of the inflation tube 402 is adapted to the opening on the outer casing of the electric meter.

[0029] Specifically, during the movement of the conveyor belt 1, the conveying device places the electric meters on the upper surface of the conveyor belt 1 in sequence; the conveying device is a prior art in the field, including but not limited to a mechanical gripper, which will not be elaborated in detail here; after the conveying device places the same number of electric meters as the power supply 201 on the conveyor belt 1, the conveying is suspended, and the conveyor belt 1 also stops immediately; at this time, the number of electric meters on the conveyor belt 1 is the same as the number of power supplies 201, and the positions are basically corresponding, and only the position of the electric meters needs to be fine-tuned, and the electric meters can be powered by the power supply component 2 to detect whether the electric meters are working normally, and the inside of the electric meters is inflated by the inflation component 4 to detect the air tightness of the electric meters.

[0030] like Figure 1 and Figure 4As shown, based on the above structure, in this embodiment, an adjustment component 3 for fine-tuning the position of the electric meter on the conveyor belt 1 is arranged above the conveyor belt 1. The adjustment component 3 includes a frame 301 and a plurality of boxes 302 fixedly installed on the frame 301. The box 302 is a cubic structure with an open bottom. The top of the box 302 is made of a transparent material. The bottom surface of the box 302 is in a horizontal state, and a rubber layer is arranged on the bottom surface of the box 302. The number of boxes 302 is the same as the number of electric meters on the conveyor belt 1. The box 302 is provided with a first through hole 315 cooperating with the inflation tube 402 and a second through hole 316 cooperating with the power supply tube 202; an air pressure sensor 317 is fixedly installed on the inner wall of the box 302; after the conveyor belt 1 is stationary, the frame 301 and the box 302 descend, and in this process the adjustment component 3 adjusts the position of the electric meter until the bottom surface of the box 302 fits with the upper surface of the conveyor belt 1. At this time, each There is an electric meter in the box body 302; then, the power supply component 2 and the inflation component 4 start to translate synchronously and approach the box body 302. During this process, the power supply tube 202 is inserted into the second through hole 316, and the inflation tube 402 is inserted into the first through hole 315; until the conductor in the power supply tube 202 fits with the connector of the corresponding electric meter, and the inflation tube 402 fits with the opening on the outer shell of the electric meter; in this state, the power supply component 2 starts to supply power to the electric meter, and the inflation component 4 starts to inflate the electric meter; the inspection personnel observe the pointer indication of the electric meter to determine whether the electric meter is working normally, and observe the display screen of the air pressure sensor 317 to determine whether the air tightness of the electric meter is qualified; the air pressure sensor 317 monitors the air pressure outside the shell of the electric meter box inside the box body 302. If the display screen of the air pressure sensor 317 shows that the air pressure increases, it means that the air pressure outside the electric meter increases, that is, the high-pressure air in the electric meter overflows, and the air tightness of the electric meter is unqualified.

[0031] After the inspection is completed, the power supply component 2 and the inflation component 4 are synchronously translated and reset, and the frame 301 and the box 302 are also raised and reset; the conveyor belt 1 continues to convey, and the inspectors place the inspected finished products in the finished product area and the unqualified products in the repair area.

[0032] Specifically, Figure 1 , Figure 2 and Figure 3As shown, a vertical baffle 303 is fixedly installed on the inner wall of the box body 302, and a vertical first push plate 304 and a second push plate 305 are also installed on the inner wall of the box body 302. The first push plate 304 and the baffle 303 are parallel to each other, and the first push plate 304 and the second push plate 305 are perpendicular to each other; the first push plate 304 and the second push plate 305 can translate relative to the box body 302, and the translation paths of the two are perpendicular to each other; a driving unit for controlling the translation of the first push plate 304 and the second push plate 305 is also installed on the box body 302; the driving unit includes a first sliding frame 306 fixedly installed on the first push plate 304 and slidingly matched with the box body 302, and a second sliding frame 307 fixedly installed on the second push plate 305 and slidingly matched with the box body 302; the frame body 301 and During the descent of the box body 302, the first sliding frame 306 first drives the first push plate 304 to move horizontally, and the first push plate 304 pushes the electric meter horizontally, so that the electric meter is against the baffle 303, and the electric meter is located between the first push plate 304 and the baffle 303 and fits with the two; then, the second sliding frame 307 drives the second push plate 305 to move horizontally, and the second push plate 305 pushes the electric meter between the first push plate 304 and the baffle 303 to push the electric meter horizontally to a predetermined position; in this way, the adjustment of the position of the electric meter is completed; after the adjustment is completed, the first sliding frame 306 and the second sliding frame 307 remain stationary relative to the box body 302, and the second push plate 305, the first push plate 304 and the baffle 303 all remain stationary relative to the box body 302, so that the electric meter is in a stable state during the detection process.

[0033] like Figure 2As shown, a first control plate 308 is fixedly mounted on the first sliding frame 306, and a second control plate 309 is fixedly mounted on the second sliding frame 307; a first guide groove 310 is provided on the first control plate 308, and a second guide groove 311 is provided on the second control plate 309; the first guide groove 310 is composed of an inclined section in the upper part and a vertical section in the lower part, and the second guide groove 311 is composed of a vertical section in the upper part and an inclined section in the lower part; a lifting platform 312 is vertically slidably mounted on the outer wall of the box body 302, and a rotatable mounting is provided on the lifting platform 312 There are first and second round rods 313 and 314 in a horizontal direction, the first round rod 313 cooperates with the first guide groove 310, and the second round rod 314 cooperates with the second guide groove 311; in the initial state, the lifting platform 312 is located at its highest point relative to the box body 302, the first round rod 313 is located at the top of the first guide groove 310, and the second round rod 314 is located at the top of the second guide groove 311; as the box body 302 begins to descend, the lifting platform 312 also descends relative to the box body 302, and the lifting platform 312 drives the first round rod 313 and the second round rod 314 to synchronously descend relative to the box body 302 The first round rod 313 first pushes the first control plate 308 and the first sliding frame 306 to translate relative to the box body 302, so that the first sliding frame 306 drives the first push plate 304 to translate; the second control plate 309 and the second sliding frame 307 remain stationary relative to the box body 302; then, the first round rod 313 enters the lower half of the first guide groove 310, and the second round rod 314 enters the lower half of the second guide groove 311; the first control plate 308 and the first sliding frame 306 remain stationary relative to the box body 302, and the second control plate 309 and the second sliding frame 307 The box body 302 starts to translate relative to the second sliding frame 307, so that the second push plate 305 drives the second push plate 305 to translate; in this way, the lifting platform 312 is lowered to successively realize the movement of the first push plate 304 and the second push plate 305, that is, it is only necessary to control the lifting platform 312 to descend relative to the box body 302 by external force during the descending process of the box body 302, so as to realize the automatic adjustment of the position of the electric meter; as for how the lifting platform 312 descends relative to the box body 302 under external force, the electric push rod control method commonly used in this field can be adopted, or other methods that can realize this function can be adopted.

[0034] like Figure 1 and Figure 4As shown, a horizontal pressure plate 5 is arranged between the upper and lower layers of the conveyor belt 1; support arms 6 are fixedly installed on both sides of the pressure plate 5 and the frame 301, and each side of the pressure plate 5 and the frame 301 has two support arms 6, and a vertical rod 7 penetrating the support arms 6 is installed on the bottom plate; in this way, the support arms 6, the pressure plate 5, the frame 301 and the box body 302 can only move vertically up and down, and will not move horizontally; horizontal rods 8 are fixedly installed on the positions on the bottom plate corresponding to both sides of the conveyor belt 1 through brackets, and translation frames 9 are horizontally slidably installed on the horizontal rods 8, that is, translation frames 9 are arranged on both sides of the conveyor belt 1; connecting rods 10 are rotatably installed at the ends of the support arms 6, and the upper and lower corresponding connecting rods 10 are hinged together on the corresponding translation frames 9; a bidirectional lead screw is installed between the two brackets, and the bidirectional lead screw passes through the two translation frames 9; the bidirectional lead screw is bidirectionally rotated by external electrical control (not shown in the figure).

[0035] In the initial state, the connecting rod 10 is in a vertical state, and the distance between the upper surface of the pressure plate 5 and the lower surface of the upper layer of the conveyor belt 1 is equal to the distance between the bottom surface of the box body 302 and the upper surface of the upper layer of the conveyor belt 1. When the two-way screw rotates forwardly under the drive of external force, the two translation frames 9 move away from each other, and the hinged end of the connecting rod 10 and the translation frame 9 also begins to translate, and the connecting rod 10 changes from a vertical state to an inclined state, the box body 302 begins to descend, and the pressure plate 5 begins to rise; until the box body 302 is in contact with the upper surface of the upper layer of the conveyor belt 1, and the pressure plate 5 is also synchronously in contact with the lower surface of the upper layer of the conveyor belt 1; in this way, the pressure plate 5 and the box body 302 cooperate to support the conveyor belt 1, so that the upper surface of the conveyor belt 1 is tightly fitted with the bottom surface of the box body 302, ensuring that the air in the box body 302 will not overflow from the gap at the bottom of the box body 302, thereby improving the accuracy of the air tightness detection; and the box body 302 and the pressure plate 5 can be moved synchronously by an external driving source.

[0036] like Figure 4 As shown, the upper surface of the lifting platform 312 is vertically fixed with a first lifting rod 318, and the top of each lifting rod 318 is commonly fixed with a horizontal second lifting rod 319; the second lifting rod 319 descends relative to the box body 302 under the action of external force, which can drive each first lifting rod 318 and the lifting platform 312 to descend relative to the box body 302, thereby adjusting the position of the electric meter.

[0037] Example 2

[0038] Based on the previous embodiment, Figure 6As shown, the vertical rod 7 in this embodiment is divided into a first section 701 fixedly connected to the bottom plate and a second section 702 rotatably mounted on the top of the first section 701. The cross section of the second section 702 is circular and a spiral groove 703 is provided on the circumferential surface of the second section 702. A ball 11 cooperating with the spiral groove 703 is rotatably mounted inside the support arm 6. A wire drum 12 coaxial with the second section 702 is fixedly mounted on the top of the second section 702. A tensioned pull wire 13 is wound around the wire drum 12. One end of the pull wire 13 is fixedly mounted on the support arm 6. The lifting platform 312 is fixedly connected to the second lifting rod 319; a vertical telescopic spring 320 is fixedly connected between the lifting platform 312 and the box body 302; in the initial state, the telescopic spring 320 is in a compressed state and has a tendency to push the lifting platform 312 downward; the pull wire 13 is wound on the bobbin 12, and the pull wire 13 pulls the second lifting rod 319, the first lifting rod 318 and the lifting platform 312 as a whole, so that the lifting platform 312 cannot descend relative to the box body 302; when the frame 301 and the box body 302 are When the support arm 6 begins to descend, the ball 11 in the support arm 6 drives the second section 702 and the wire drum 12 to rotate through the interaction with the spiral groove 703. During the rotation of the wire drum 12, the pull wire 13 is gradually released, and the pulling effect of the pull wire 13 on the second lifting rod 319, the first lifting rod 318 and the lifting platform 312 as a whole is reduced, and the telescopic spring 320 is extended and pushes the lifting platform 312 to descend relative to the box body 302. During this period, the pull wire 13 is always in a tensioned state; when the box body 302 descends When it is in contact with the upper surface of the upper layer of the conveyor belt 1, the telescopic spring 320 also returns to its normal length, and the lifting platform 312 descends to its lowest position relative to the box body 302; when the frame 301, the box body 302 and the support arm 6 rise, the wire drum 12 rotates in the opposite direction and gradually reels the pull wire 13, and the pull wire 13 pulls the second lifting rod 319, the first lifting rod 318 and the lifting platform 312 as a whole to rise relative to the box body 302, and the telescopic spring 320 is gradually compressed until it returns to its initial state.

[0039] To summarize, the vertical rod 7 is cleverly designed to be divided into two sections, the second section 702 and the wire drum 12 rotate synchronously during the descending process of the box body 302, and the pull wire 13 is released, so that the lifting platform 312 can automatically descend relative to the box body 302 under the action of the telescopic spring 320. There is no need to separately set a driving source on the box body 302 to control the lifting and lowering of the lifting platform 312, thereby saving design and manufacturing costs.

[0040] like Figure 5As shown, the horizontal rod 8 horizontally penetrates the inflatable component 4 and the power supply component 2, so that the inflatable component 4 and the power supply component 2 can only translate along the direction of the horizontal rod 8; the connecting rod 10 is an elastic telescopic rod, and a horizontal first rack 14 is fixedly installed on the translation frame 9; a horizontal second rack 15 is fixedly installed on the inflatable frame of the inflatable component 4, and a second rack 15 is also installed on the power supply frame of the power supply component 2; a gear 16 meshing with the second rack 15 is rotatably installed on the bracket; the first rack 14 has a first state meshing with the gear 16, and a second state separated from the gear 16; during the translation of the translation frame 9 from the initial state (that is, during the process of the two translation frames 9 moving away from each other), the connecting rod 10 initially maintains a constant length, and when the box body 302 and the pressure plate 5 are both in contact with the conveyor belt 1, as the translation frame 9 continues to translate , the box body 302, the pressure plate 5 and the support arm 6 all maintain a constant height state, and the connecting rod 10 is stretched; the first rack 14 on the translation frame 9 also immediately enters the first state of meshing with the gear 16, and drives the gear 16 to rotate, and the gear 16 drives the second rack 15 meshing therewith to translate, and the second rack 15 drives the corresponding inflation component 4 or power supply component 2 to translate until the inflation tube 402 is inserted into the first through hole 315 and fits with the opening on the meter housing, and the conductor in the power supply tube 202 also synchronously fits with the connector of the corresponding meter; in this way, in this embodiment, there is no need to set a driving source for the inflation component 4 and the power supply component 2. After the box body 302 and the pressure plate 5 are fitted with the conveyor belt 1, the inflation component 4 and the power supply component 2 can automatically and synchronously move to the box body 302 to a predetermined position, saving design and manufacturing costs.

[0041] The above description is only by way of illustration of certain exemplary embodiments of the present invention. It is undoubted that those skilled in the art can modify the described embodiments in various ways without departing from the spirit and scope of the present invention. Therefore, the above drawings and descriptions are illustrative in nature and should not be construed as limiting the scope of protection of the claims of the present invention.

Claims

1. A smart meter testing and calibration device, comprising a base plate and a conveyor belt (1) arranged on the base plate, wherein a power supply component (2) is arranged on one side of the conveyor belt (1). It is characterized in that An adjustment assembly (3) is arranged above the conveyor belt (1), and the adjustment assembly (3) comprises a frame (301) and a plurality of boxes (302) fixedly mounted on the frame (301); a vertical baffle (303) is fixedly mounted on the inner wall of the box (302), and a vertical first push plate (304) and a second push plate (305) are also mounted on the inner wall of the box (302); the first push plate (304) and the second push plate (305) can translate relative to the box (302), and the translation paths of the two are perpendicular to each other; a driving unit for controlling the translation of the first push plate (304) and the second push plate (305) is also mounted on the box (302).

2. A smart meter testing and calibration device according to claim 1, It is characterized in that The driving unit comprises a first sliding frame (306) fixedly mounted on the first push plate (304) and slidably matched with the box body (302), and a second sliding frame (307) fixedly mounted on the second push plate (305) and slidably matched with the box body (302).

3. A smart meter testing and calibration device according to claim 2, It is characterized in that A first control panel (308) is fixedly mounted on the first sliding frame (306), and a second control panel (309) is fixedly mounted on the second sliding frame (307); a first guide groove (310) is provided on the first control panel (308), and a second guide groove (311) is provided on the second control panel (309); a lifting platform (312) is vertically slidably mounted on the outer wall of the box body (302), and a first round rod (313) and a second round rod (314) are rotatably mounted on the lifting platform (312) in a horizontal manner; the first round rod (313) cooperates with the first guide groove (310), and the second round rod (314) cooperates with the second guide groove (311).

4. A smart meter testing and calibration device according to claim 3, It is characterized in that An inflation component (4) is arranged on the other side of the conveyor belt (1), and the inflation component (4) comprises a plurality of inflation pumps (401) whose number is the same as that of the box body (302) and whose positions correspond to each other, and an inflation tube (402) is fixedly installed at the outlet of the inflation pump (401); the power supply component (2) comprises a plurality of power supplies (201) whose number is the same as that of the box body (302) and whose positions correspond to each other, and two power supply tubes (202) are fixedly installed on the power supply (201); a first through hole (315) cooperating with the inflation tube (402) and a second through hole (316) cooperating with the power supply tube (202) are provided on the box body (302); and an air pressure sensor (317) is fixedly installed on the inner wall of the box body (302).

5. A smart meter testing and calibration device according to claim 4, It is characterized in that The bottom surface of the box body (302) is in a horizontal state, and a rubber layer is provided on the bottom surface of the box body (302); a horizontal pressure plate (5) is provided below the conveyor belt (1).

6. A smart meter testing and calibration device according to claim 5, It is characterized in that Support arms (6) are fixedly installed on both sides of the pressure plate (5) and the frame body (301), and a vertical rod (7) penetrating the support arms (6) is installed on the bottom plate; a horizontal rod (8) is fixedly installed on the bottom plate through a bracket, and a translation frame (9) is horizontally slidably installed on the horizontal rod (8); connecting rods (10) are rotatably installed at the ends of the support arms (6), and the upper and lower corresponding connecting rods (10) are hinged together on the translation frame (9).

7. A smart meter testing and calibration device according to claim 6, It is characterized in that The upper surface of the lifting platform (312) is vertically fixedly mounted with a first lifting rod (318), and the top of each lifting rod (318) is commonly fixedly mounted with a horizontal second lifting rod (319).

8. A smart meter testing and calibration device according to claim 7, It is characterized in that The vertical rod (7) is divided into a first section (701) fixedly connected to the bottom plate and a second section (702) rotatably mounted on the top of the first section (701); a spiral groove (703) is provided on the surface of the second section (702); a ball (11) cooperating with the spiral groove (703) is rotatably mounted inside the support arm (6); a wire drum (12) coaxial with the second section (702) is fixedly mounted on the top of the second section (702); a pull wire (13) is wound around the wire drum (12); one end of the pull wire (13) is fixedly connected to the second lifting rod (319); a vertical telescopic spring (320) is fixedly connected between the lifting platform (312) and the box body (302).

9. A smart meter testing and calibration device according to claim 8, It is characterized in that A first horizontal rack (14) is fixedly mounted on the translation frame (9); a second horizontal rack (15) is fixedly mounted on the inflation assembly (4); a gear (16) meshing with the second rack (15) is rotatably mounted on the bracket; the first rack (14) has a first state of meshing with the gear (16) and a second state of being separated from the gear (16).

10. A smart meter testing and calibration device according to claim 9, It is characterized in that The connecting rod (10) is an elastic telescopic rod.

Citation Information

Patent Citations

  • Electric meter testing device

    CN112505617A

  • Intelligent electric meter test equipment

    CN117452317A