Method and device for stabilizing demand by using energy storage and controllable load

By analyzing the historical data of electricity and generating targeted suppression strategies, real-time control of energy storage systems and adjustable loads, the problem of insufficient real-time and accuracy of existing demand management methods is solved, and the demand suppression effect and resource utilization are improved. to ensure the stability and economicality of the power system.

CN118899878APending Publication Date: 2024-11-05NANJING ZHONGDIAN KENENG TECH CO LTD
View PDF 0 Cites 5 Cited by

Patent Information

Application Number
CN202410938511.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-13
Publication Date
2024-11-05

AI Technical Summary

Technical Problem

The existing power demand management methods lack real-time and accuracy, resulting in the inability to effectively coordinate the energy storage system and controllable load, resulting in poor demand suppression and low system resource utilization.

Method used

By obtaining the power historical data of the target enterprise, analyzing the demand changes, determining the reasons for the increase in demand, and generating targeted suppression strategies based on the capacity of the energy storage system and adjustable flexible load, controlling the discharge and adjusting the load in real time of energy storage system. to cope with fluctuations in electricity demand.

Benefits of technology

It improves the accuracy of demand suppression and system resource utilization, ensures the stable operation of the power system, reduces power waste and costs, and enhances the stability and reliability of the power system.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118899878A_ABST
    Figure CN118899878A_ABST
Patent Text Reader

Abstract

The invention discloses a method and a device for stabilizing demand by using energy storage and a controllable load, and relates to the field of power control. In the method, a target reason for demand increase is determined according to a first moment corresponding to the maximum demand; generating a demand stabilizing strategy according to the power regulation data of the target enterprise, wherein the power regulation data comprises the installed capacity of an energy storage system, the first capacity of an adjustable flexible load and the second capacity of an interruptible load; when the occurrence of the target reason is detected, judging whether the real-time power is greater than the existing maximum demand in the current period and a demand stabilizing target value in a stabilizing strategy or not; and when the real-time power is greater than the existing maximum demand in the current period and the demand stabilizing target value in the stabilizing strategy, controlling the energy storage system to discharge according to the stabilizing strategy, and / or adjusting the load capacity of the adjustable flexible load, and / or adjusting the load capacity of the interruptible load. By implementing the technical scheme provided by the invention, the demand stabilizing effect and the system resource utilization rate are improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of power control, and in particular to a method, system, electronic device and storage medium for demand smoothing using energy storage and controllable loads. Background Art

[0002] With the development of science and technology, the demand for electricity continues to rise, and the stability and economy of electricity supply have become key issues. As an important part of power control, the effectiveness of demand management is directly related to the operating costs of enterprises and the stable operation of power grids. Traditional demand management methods often rely on manual monitoring and adjustment, lack of real-time and accuracy, and are difficult to meet the needs of modern complex power systems.

[0003] At present, a separate energy storage system or a controllable load dispatching system is usually used to smooth demand, but there is a lack of effective coordination and optimization methods, resulting in poor demand smoothing effects and low system resource utilization.

[0004] Therefore, how to use energy storage and controllable loads to smooth demand more accurately and efficiently has become a technical problem that needs to be urgently solved in the current field of power control technology. Summary of the invention

[0005] The present application provides a method, system, electronic device and storage medium for demand smoothing using energy storage and controllable loads, which solves the problem that the energy storage system and the controllable load cannot effectively coordinate, and significantly improves the demand smoothing effect and system resource utilization.

[0006] In a first aspect of the present application, a method for demand balancing using energy storage and controllable loads is provided, which is applied to a power control platform. The method comprises: Acquire a power history data set of a target enterprise, determine a first moment corresponding to a first demand according to the power history data set, and determine a target reason for an increase in demand according to the first moment and a change in demand before and after the first moment, wherein the power history data set includes a time series and a demand corresponding to each moment, the first demand and the second demand are any two demands in the power history data set, and the first demand is greater than the second demand; Generate a demand smoothing strategy based on the power regulation data of the target enterprise, wherein the power regulation data includes the installed capacity of the energy storage system, the first capacity of the adjustable flexible load, and the second capacity of the interruptible load; When the target cause is detected, determining whether the real-time power is greater than the maximum demand in the current cycle and the demand leveling target value in the leveling strategy; When the real-time power is greater than the maximum demand in the current cycle and the demand leveling target value in the leveling strategy, the energy storage system is controlled to discharge according to the leveling strategy, and / or the load of the adjustable flexible load is adjusted, and / or the load of the interruptible load is adjusted.

[0007] By adopting the above technical solutions, in-depth analysis of historical data can more accurately predict future power demand and identify the key factors that cause demand changes. This prediction and cause analysis provide strong support for the subsequent formulation of demand balancing strategies. According to the power regulation data of the target enterprise (including the installed capacity of the energy storage system, the first capacity of the adjustable flexible load and the second capacity of the interruptible load), a targeted demand balancing strategy can be generated. The formulation of this strategy takes into account the actual situation and adjustable resources of the enterprise, making the balancing measures more in line with actual needs and improving the balancing effect. When the target cause is detected, it will be judged in real time whether the real-time power is greater than the maximum demand and demand balancing target value of the current cycle. If the real-time power exceeds these two thresholds, the power control platform will automatically control the energy storage system to discharge, adjust the load of the adjustable flexible load or adjust the load of the interruptible load according to the balancing strategy. This real-time response and intelligent control can quickly respond to fluctuations in power demand and maintain the stable operation of the power system. By optimizing the use of energy storage systems and controllable loads, it is possible to effectively balance power supply and demand and reduce power waste and losses. At the same time, the discharge of the energy storage system and the regulation of the controllable load can also provide the necessary regulation capability for the power system and enhance the stability and reliability of the power system. It can reduce the electricity cost of enterprises and improve the economic benefits of the power system. Through accurate demand forecasting and flexible smoothing strategy formulation, enterprises can arrange production plans and power consumption plans more reasonably and reduce unnecessary power consumption and waste. At the same time, the use of energy storage systems and controllable loads can also bring additional benefits to enterprises.

[0008] Optionally, determining the target reason for the demand increase according to the first moment and the demand change before and after the first moment includes: Determine whether there is a sudden increase in demand based on the change in demand in a preset time period before and after the first moment, where the sudden increase means that the difference between the demand at the second moment and the demand at the previous adjacent moment is greater than a first threshold; When there is a sudden increase in demand, determining a first device that is running at the second moment, and determining power characteristics of the first device, the power characteristics including starting power, running power, and stopping power; Synchronously analyzing the start or stop time of the first device and the demand change to determine a second device associated with the sudden increase in demand from the first device; One or more of the second devices are activated as a targeted cause of the demand increase.

[0009] By adopting the above technical solution, the change in demand within a preset time period is used to determine whether there is a sudden increase, thereby ensuring the accuracy of the judgment. The definition of a sudden increase (i.e., the difference in demand between the second moment and the previous adjacent moment is greater than the first threshold) provides a clear standard for quantitative analysis, thereby avoiding errors in subjective judgment. When there is a sudden increase in demand, the first device in operation is quickly determined, and its power characteristics (starting power, running power, and stopping power) are examined. This helps to narrow the search scope and quickly locate key devices that may be related to the sudden increase in demand. By synchronously analyzing the time when the first device starts or stops with the change in demand, the second device that is directly related to the sudden increase in demand can be accurately determined from a large number of devices. This synchronous analysis method improves the accuracy and reliability of the analysis. Finally, one or more starts in the second device are used as the target cause of the increase in demand, providing a clear basis for the subsequent formulation of demand stabilization strategies. Clear target causes help to formulate targeted stabilization measures and improve the stabilization effect. By accurately identifying the target causes of the increase in demand, enterprises can take preventive measures or countermeasures in advance to reduce the impact on the power system. For example, the startup sequence and time of equipment can be reasonably arranged before the peak period to avoid sudden increases in demand. By accurately identifying and responding to the target causes of increased demand, the fluctuations and instability of the power system can be effectively reduced, and the stability and reliability of the power system can be improved.

[0010] Optionally, the demand stabilization strategy for generating demand according to the power regulation data of the target enterprise includes: The optimization target is set according to the needs of the target enterprise, and the decision variables and constraints are set according to the power regulation data. The decision variables include the discharge power of the energy storage system, the operating power of the adjustable flexible load, and the interruption time of the interruptible load. The constraints are the capacity limit of the equipment, the response time requirement, and the power demand constraint. The optimization objective, decision variables and constraints are included in the preset strategy model to obtain the decision variable values ​​and optimization objective values.

[0011] By adopting the above technical solutions, optimization goals are set according to the actual needs of the target enterprise, such as minimizing electricity costs, maximizing energy efficiency, or meeting specific electricity needs. This goal-oriented optimization method ensures that the stabilization strategy can directly serve the actual needs of the enterprise. The discharge power of the energy storage system, the operating power of the adjustable flexible load, and the interruption time of the interruptible load are used as decision variables, and the possibility of different power regulation methods is fully considered. This flexible decision variable setting makes the stabilization strategy more adaptable and operable. The set constraints include equipment capacity limitations, response time requirements, and power demand constraints, which ensure the feasibility and effectiveness of the stabilization strategy in actual operation. At the same time, they also reflect the complexity and variability of the power regulation process. The optimization objectives, decision variables, and constraints are input into the preset strategy model, and the decision variable values ​​and optimization target values ​​are obtained through model calculation. This model-based method can quickly and accurately generate stabilization strategies, improving the efficiency and accuracy of power regulation. By generating stabilization strategies, enterprises can realize intelligent regulation of power demand. This can not only reduce unnecessary power waste and reduce power costs, but also improve the stability and reliability of power use. Through reasonable power regulation, fluctuations and imbalances in the power system can be reduced, and the stability and reliability of the power system can be improved. This is of great significance for maintaining the normal operation of the power system and ensuring power supply security. By optimizing the use of electricity and improving energy efficiency, the sustainable development of enterprises can be promoted. At the same time, this intelligent power regulation method also helps to promote the green and low-carbon development of the entire power industry.

[0012] Optionally, the demand stabilization strategy for generating demand according to the power regulation data of the target enterprise includes: Determining a plurality of first factors affecting the priority of adjustable loads, wherein the first factors include load adjustability, cost-effectiveness, impact on system stability, and response speed; assigning corresponding weights to the plurality of first factors according to their importance; The score of each adjustable load on each of the first factors is determined, a weighted sum is performed to obtain a total score of each adjustable load, and the priority of the adjustable load is determined according to the total score.

[0013] By adopting the above technical solution, considering multiple first factors, such as the adjustability of the load, cost-effectiveness, impact on system stability and response speed, it can be ensured that the priority of the adjustable load is based on comprehensive and reasonable considerations. These factors cover multiple dimensions from economic to technical, providing rich information support for the determination of priority. According to the importance, the corresponding weights are assigned to multiple first factors, so that the influence of different factors in the priority determination process can be flexibly adjusted. This configuration method can be adjusted according to actual conditions and needs, increasing the flexibility and adaptability of strategy formulation. By weighted summing the scores of each adjustable load on each first factor, a quantitative total score can be obtained, thereby accurately evaluating the priority of each adjustable load. This quantitative evaluation method avoids the error of subjective judgment and improves the accuracy and reliability of strategy formulation. Formulating a demand smoothing strategy based on the priority of the adjustable load can ensure that the strategy is more accurate and effective. Adjustable loads with high priority will be given priority and adjusted, so as to respond to changes in power demand more quickly and improve the stability and reliability of the power system. By considering factors such as cost-effectiveness and response speed, the allocation of power resources can be optimized. Adjustable loads with high priority tend to have higher cost-effectiveness and faster response speed, so they can get priority resource support when needed, realizing the optimal allocation of power resources. Taking system stability as a factor in determining the priority of adjustable loads can ensure that system stability is fully considered in the process of demand balancing. By giving priority to adjusting adjustable loads that have a greater impact on system stability, system fluctuations and imbalances can be reduced, and the stability and reliability of the power system can be improved.

[0014] Optionally, the demand stabilization strategy for generating demand according to the power regulation data of the target enterprise further includes: determining a plurality of second factors affecting the priority of interrupting the load, wherein the second factors include importance of the load, interruption cost, and load type; Evaluating a plurality of the second factors of each interruptible load, determining the extent to which the second factor belongs to each evaluation level to establish a single factor evaluation matrix; determining weights of a plurality of said second factors, and establishing a weight set according to said weights; The single factor evaluation matrix and the weight set are synthesized to obtain a comprehensive evaluation result, and the priority of the interruptible load is determined according to the comprehensive evaluation result.

[0015] By adopting the above technical solution, considering multiple second factors such as the importance of the load, the interruption cost, and the type of load, the evaluation process can fully reflect all aspects of the interruptible load. This multi-dimensional evaluation method ensures the accuracy and reliability of the evaluation results. The multiple second factors of each interruptible load are evaluated, and the degree to which they belong to each evaluation level is determined to establish a single factor evaluation matrix. This process converts qualitative information into quantitative data, making the evaluation results more comparable and operational. Different second factors may have different degrees of influence on the priority of interruptible loads. By determining the weights of these factors and establishing a weight set, it can be ensured that the importance of each factor in the evaluation process is reasonably reflected. The single factor evaluation matrix and the weight set are synthesized to obtain a comprehensive evaluation result of each interruptible load. This comprehensive evaluation result comprehensively considers the influence of multiple factors and is therefore more accurate and reliable. Determining the priority of interruptible loads based on the comprehensive evaluation results can provide a scientific basis for the formulation of demand balancing strategies. By giving priority to interruptible loads with high priority, the impact on important loads can be minimized while ensuring the stable operation of the power system, thereby improving the reliability and economy of power supply. By evaluating the priority of interruptible loads, power resources can be allocated more reasonably. Prioritizing high-priority loads can ensure that critical loads are powered in a timely manner while reducing unnecessary waste of resources. By considering factors such as load type, the impact of interruptible loads on system stability can be more accurately evaluated. When formulating demand balancing strategies, loads that have a greater impact on system stability can be prioritized, thereby enhancing the stability of the power system.

[0016] Optionally, controlling the discharge of the energy storage system according to the smoothing strategy, and / or adjusting the load of the adjustable flexible load, and / or adjusting the load of the interruptible load includes: Controlling the discharge of the energy storage system according to the set discharge parameters, wherein the discharge parameters include current, voltage, and discharge time; Continuously monitor the real-time power of the grid and the status of the energy storage system; When the real-time power is less than or equal to the demand leveling target value, the control system gradually reduces the discharge amount or stops discharging; When the real-time power is greater than the demand leveling target value, determining whether the discharge power of the energy storage system exceeds a second threshold; When the discharge power of the energy storage system exceeds a second threshold, the load amounts of the adjustable flexible loads and the load amounts of the interruptible loads are gradually adjusted according to the priorities.

[0017] By adopting the above technical solution, the discharge parameters (such as current, voltage, and discharge time) are set to accurately control the discharge process of the energy storage system to ensure that the discharge process is smooth and meets the requirements of the leveling strategy. This precise control helps to achieve a balance between power demand and supply and improve the stability of the power grid. Continuously monitoring the real-time power of the power grid and the status of the energy storage system provides real-time data support for dynamic adjustment. When the real-time power is less than or equal to the demand leveling target value, the control system can gradually reduce the discharge amount or stop the discharge to avoid damage to the energy storage system caused by excessive discharge. This real-time monitoring and optimization adjustment ensures the effectiveness and real-time nature of the leveling strategy. When the real-time power is greater than the demand leveling target value, if the discharge power of the energy storage system has exceeded the second threshold, the control system can gradually adjust the load of the adjustable flexible load and the load of the interruptible load according to the preset priority. This collaborative working mode can make full use of the adjustment capacity of the energy storage system and the adjustable load to achieve effective management of power demand. Through refined control means, it can ensure that the energy storage system, the adjustable flexible load, and the interruptible load participate in power regulation at the right time and under the right conditions, thereby improving the efficiency of energy utilization. This helps to reduce electricity costs and improve the economy of the power system. By implementing the smoothing strategy, the fluctuation and imbalance of power load can be reduced and the stability of the power grid can be enhanced. At the same time, the discharge of the energy storage system, the adjustment of the adjustable flexible load and the interruptible load can also provide additional support and guarantee for the power grid and improve the response capacity of the power grid. By gradually adjusting the load of the adjustable flexible load and the interruptible load according to the priority, the optimal configuration of power resources can be achieved. This helps to ensure the power supply stability of key loads while reducing unnecessary waste of resources.

[0018] Optionally, the stepwise adjusting the load amount of the adjustable flexible load and the load amount of the interruptible load according to the priority includes: Determining whether the discharge power of the energy storage system exceeds a third threshold, the third threshold being greater than the second threshold; When the discharge power of the energy storage system does not exceed the third threshold, the load of the adjustable flexible load is gradually adjusted according to the priority; when the discharge power of the energy storage system exceeds the third threshold, the load of the interruptible load is gradually adjusted according to the priority.

[0019] By adopting the above technical solution and setting the second threshold and the third threshold, different load management measures can be taken according to different stages of the energy storage system discharge power. This refined management strategy can ensure the balance of power demand and the stability of the power grid. Before the discharge power of the energy storage system reaches the third threshold, the load of the adjustable flexible load is adjusted first. In this way, the adjustment capacity of the adjustable flexible load can be fully utilized, the dependence on the energy storage system can be reduced, and the service life of the energy storage system can be extended. When the discharge power of the energy storage system exceeds the third threshold, the load of the interruptible load is gradually adjusted according to the priority. This strategy can ensure that when the power grid pressure is large, the load with less impact on the system stability or lower interruption cost is interrupted first to maintain the power supply stability of the critical load. Through reasonable load adjustment, unnecessary power waste can be reduced and energy utilization efficiency can be improved. Especially during the peak load period of the power grid, by adjusting the load, the power demand can be smoothed and the power grid operation cost can be reduced. In the case of large fluctuations in power demand, this load adjustment strategy based on priority and threshold can enhance the response capability of the power grid. By timely and effectively adjusting the load, the fluctuation and imbalance of the power grid can be reduced, and the stability and reliability of the power grid can be improved. This strategy can be flexibly adjusted according to different power demands and system states. At the same time, with the development of smart grid technology, this strategy can be further expanded and optimized to adapt to more complex and diverse electricity demands.

[0020] In a second aspect of the present application, a system for demand balancing using energy storage and controllable loads is provided, including a cause module, a strategy module, a judgment module, and an execution module, wherein: a cause module configured to obtain a power history data set of a target enterprise, determine a first moment corresponding to a first demand according to the power history data set, and determine a target cause of demand increase according to the first moment and a change in demand before and after the first moment, wherein the power history data set includes a time series and a demand corresponding to each moment, the first demand and the second demand are any two demands in the power history data set, and the first demand is greater than the second demand; A strategy module configured to generate a demand stabilization strategy according to power regulation data of the target enterprise, wherein the power regulation data includes an installed capacity of an energy storage system, a first capacity of an adjustable flexible load, and a second capacity of an interruptible load; A judgment module configured to judge whether the real-time power is greater than the maximum demand in the current cycle and the demand leveling target value in the leveling strategy when the target cause is detected; The execution module is configured to control the discharge of the energy storage system and / or adjust the load of the adjustable flexible load and / or adjust the load of the interruptible load according to the smoothing strategy when the real-time power is greater than the maximum demand in the current cycle and the demand smoothing target value in the smoothing strategy.

[0021] In the third aspect of the present application, an electronic device is provided, including a processor, a memory, a user interface and a network interface, the memory is used to store instructions, the user interface and the network interface are both used to communicate with other devices, and the processor is used to execute the instructions stored in the memory so that the electronic device executes any one of the methods described above.

[0022] In a fourth aspect of the present application, a computer-readable storage medium is provided, wherein the computer-readable storage medium stores instructions, and when the instructions are executed, any of the methods described above is executed.

[0023] In summary, one or more technical solutions provided in the embodiments of the present application have at least the following technical effects or advantages: 1. By obtaining the target enterprise's electricity historical data set and based on the time series and demand data, the first moment corresponding to the first demand increase can be accurately predicted. Furthermore, by analyzing the changes in demand before and after the first moment, the target cause of the demand increase can be accurately determined. This accurate prediction and cause analysis provides a solid foundation for subsequent demand stabilization strategies; 2. Based on the target enterprise's power regulation data (such as the installed capacity of the energy storage system, the capacity of adjustable flexible loads and interruptible loads), a customized demand balancing strategy can be generated. This strategy not only takes into account the enterprise's power regulation capabilities, but also combines the actual situation of the enterprise, thereby improving the effectiveness and applicability of the strategy; 3. When the target cause of the demand increase is detected, it can determine in real time whether the real-time power exceeds the maximum demand and demand leveling target value of the current cycle. Once exceeded, corresponding control measures can be taken immediately according to the leveling strategy, such as controlling the discharge of the energy storage system, adjusting the load of the adjustable flexible load, or adjusting the load of the interruptible load. This real-time response and adjustment can ensure the stable operation of the power grid and avoid shortage or surplus of power supply; 4. Through refined control measures, it can ensure that during peak hours of electricity demand, the discharge capacity of the energy storage system is used first, and then the load of adjustable flexible loads and interruptible loads is gradually adjusted. This priority sorting can maximize the use of the regulation capacity of the energy storage system and controllable loads and improve energy utilization efficiency; 5. By implementing demand-smoothing strategies, fluctuations and imbalances in power loads can be reduced, which helps reduce the operating pressure of the power grid and enhance the stability and reliability of the power grid. By gradually adjusting the load of adjustable flexible loads and interruptible loads according to priority, the optimal allocation of power resources can be achieved. By giving priority to loads that have less impact on system stability or have lower interruption costs, the power supply stability of key loads can be ensured while reducing unnecessary waste of resources. BRIEF DESCRIPTION OF THE DRAWINGS

[0024] Figure 1 It is a flow chart of a method for demand balancing using energy storage and controllable loads disclosed in an embodiment of the present application; Figure 2 It is a module schematic diagram of a system for demand balancing using energy storage and controllable loads disclosed in an embodiment of the present application; Figure 3 It is a structural schematic diagram of an electronic device disclosed in an embodiment of the present application.

[0025] Explanation of the accompanying drawings: 201, cause module; 202, strategy module; 203, judgment module; 204, execution module; 301, processor; 302, communication bus; 303, user interface; 304, network interface; 305, memory. DETAILED DESCRIPTION

[0026] In order to enable technicians in this field to better understand the technical solutions in this specification, the technical solutions in the embodiments of this specification will be clearly and completely described below in conjunction with the drawings in the embodiments of this specification. Obviously, the described embodiments are only part of the embodiments of this application, not all of the embodiments.

[0027] In the description of the embodiments of the present application, words such as "for example" or "for example" are used to indicate examples, illustrations or explanations. Any embodiment or design described as "for example" or "for example" in the embodiments of the present application should not be interpreted as being more preferred or more advantageous than other embodiments or designs. Specifically, the use of words such as "for example" or "for example" is intended to present related concepts in a specific way.

[0028] In the description of the embodiments of the present application, the meaning of the term "multiple" refers to two or more. For example, multiple systems refer to two or more systems, and multiple screen terminals refer to two or more screen terminals. In addition, the terms "first" and "second" are used for descriptive purposes only and cannot be understood as indicating or implying relative importance or implicitly indicating the indicated technical features. Thus, the features defined as "first" and "second" may explicitly or implicitly include one or more of the features. The terms "include", "comprise", "have" and their variations all mean "including but not limited to", unless otherwise specifically emphasized.

[0029] This embodiment discloses a method for demand balancing using energy storage and controllable loads, which is applied to a power control platform. Figure 1 is a flow chart of a method for demand balancing using energy storage and controllable loads disclosed in an embodiment of the present application, such as Figure 1 As shown, the method comprises the following steps: S110, obtaining a power history data set of the target enterprise, determining a first moment corresponding to a first demand according to the power history data set, and determining a target reason for the increase in demand according to the first moment and the change in demand before and after the first moment, wherein the power history data set includes a time series and a demand corresponding to each moment, the first demand and the second demand are any two demands in the power history data set, and the first demand is greater than the second demand; Obtain a historical electricity data set from the target enterprise. This data set usually contains two main components: a time series (usually a combination of date and time) and the power demand value corresponding to each moment. This data may be collected through smart meters, energy management systems, or other related systems. Demand usually refers to the average power load in a specific time period. Before analysis, the data may need to be preprocessed. This includes checking the integrity of the data (ensuring that there are no missing values), cleaning the data (removing errors or outliers), standardizing or normalizing the data (if the demand values ​​in different time periods vary too much), etc. In the historical electricity data set, the maximum demand (that is, the first demand) needs to be determined. Once the first demand is determined, the moment corresponding to the first demand in the time series can be determined, that is, the first moment. Select an appropriate time window to observe the demand changes before and after the first moment. This time window can be fixed (for example, one hour before and after) or dynamic (based on the speed of demand change or other factors). Plot the demand data in the time window into a curve chart to more intuitively observe the demand change trend. By analyzing the curve chart, identify the pattern of demand change. These patterns may include sudden increases, gradual increases, cyclical changes, etc. Based on the changes in demand before and after the first moment, you can try to determine the target cause of the increase in demand. This may involve internal factors, external factors, system factors, and market factors. Internal factors: Check the electricity consumption within the enterprise, such as whether the production equipment is started, whether employees are working overtime, etc. External factors: Consider changes in the external environment, such as weather conditions (high or low temperatures may cause increased electricity consumption for air conditioning), holidays (may cause increased office electricity consumption), etc. System factors: Check whether the power system is operating normally, such as whether there are changes in electricity consumption caused by equipment failure or maintenance plans. Market factors: Consider changes in market supply and demand, such as fluctuations in electricity prices may cause companies to adjust their electricity consumption strategies.

[0030] Optionally, determining the target reason for the demand increase according to the first moment and the demand change before and after the first moment includes: Determine whether there is a sudden increase in demand based on the change in demand in a preset time period before and after the first moment, where the sudden increase means that the difference between the demand at the second moment and the demand at the previous adjacent moment is greater than a first threshold; When there is a sudden increase in demand, determining a first device that is running at the second moment, and determining power characteristics of the first device, the power characteristics including starting power, running power, and stopping power; Synchronously analyzing the start or stop time of the first device and the demand change to determine a second device associated with the sudden increase in demand from the first device; One or more of the second devices are activated as a targeted cause of the demand increase.

[0031] Assume that the first moment (i.e., the moment when the demand reaches the peak) is the 30th minute, and observe the change in demand within a preset time period before and after the first moment. In an embodiment of the present application, 5 minutes before and after are selected as observation windows, i.e., the 25th minute to the 35th minute. If within this time period, the difference between the demand at a certain moment (such as the 29th minute) and the demand at the previous adjacent moment (the 28th minute) is greater than the set first threshold value (such as 100kW), it is determined that there is a sudden increase in demand. When there is a sudden increase in demand, determine all devices that are running at the second moment (such as the 29th minute). This can usually be done through an energy management system or equipment monitoring system within the enterprise. Assume that five running devices are found: A, B, C, D, and E. Obtain the power characteristics of these devices, including starting power, running power, and stopping power. This information can usually be obtained from the equipment specification, technical manual, or equipment manufacturer. Equipment A: Startup power 150kW, running power 100kW, stop power 0kW; Equipment B: Startup power 200kW, running power 120kW, stop power 0kW; Equipment C: Startup power 80kW, running power 60kW, stop power 0kW; Equipment D: Startup power 100kW, running power 70kW, stop power 0kW; Equipment E: Startup power 120kW, running power 90kW, stop power 0kW. Analyze the start or stop time of each equipment in synchronization with the demand change. For example, if equipment A starts at the end of the 28th minute (or equipment B stops at the beginning of the 29th minute), and there is a significant increase (or decrease) in demand at this moment, then this equipment may be related to the sudden increase (or decrease) in demand. Suppose it is found that equipment A starts at 28 minutes and 50 seconds, and the demand starts to rise sharply from that moment. At the same time, no other equipment starts or stops during this period. Based on the above analysis, it can be determined that the start of equipment A is the target cause of the sudden increase in demand at the 29th minute. This is because the starting power of device A (150 kW) is much greater than the operating power of other devices, and its starting time coincides with the time point when the demand suddenly increases.

[0032] By analyzing the demand changes in the preset time period before and after the first moment, it is possible to accurately identify whether there is a sudden increase in demand. This sudden increase may be caused by the start or stop of one or more devices, which has an important impact on the stability of the power grid and the energy management of the enterprise. When a sudden increase in demand is detected, by determining the first device that is running in the time period and obtaining its power characteristics, the scope can be quickly narrowed down to locate the device that may be related to the sudden increase in demand. This method improves the efficiency and accuracy of the analysis. Synchronizing the time when the device starts or stops with the demand changes can ensure that there is a direct correlation between the found device and the sudden increase in demand. This synchronous analysis method improves the accuracy and reliability of the analysis. After determining the target cause of the increase in demand, the enterprise can optimize its energy management strategy based on this information. For example, the operating time of the equipment can be adjusted, the production process can be optimized, or energy-saving measures can be taken to reduce unnecessary power consumption and costs. By promptly identifying the cause of the sudden increase in demand, the enterprise can predict and avoid overload or instability of the power grid. This is of great significance to ensure the stable operation of the power grid and improve the quality and reliability of power supply. Optimizing energy management strategies can help enterprises reduce power consumption and costs. By reducing unnecessary electricity demand and lowering peak loads, companies can save energy costs and improve economic efficiency.

[0033] S120, generating a demand smoothing strategy according to the power regulation data of the target enterprise, where the power regulation data includes the installed capacity of the energy storage system, the first capacity of the adjustable flexible load, and the second capacity of the interruptible load; When the target enterprise faces fluctuations in power demand, it is a key task to generate a demand smoothing strategy based on power regulation data. Power regulation data mainly includes the installed capacity of energy storage systems, the first capacity of adjustable flexible loads, and the second capacity of interruptible loads. The installed capacity of energy storage systems refers to the total installed capacity of energy storage equipment (such as energy storage batteries) of the target enterprise in a specific time period. It reflects the strength and level of the enterprise in energy reserves. The energy storage system can release electric energy when power demand peaks or absorb electric energy when power supply is in excess, thereby balancing the power supply and demand relationship, reducing peak loads, and improving power grid stability. Adjustable flexible loads refer to devices or systems that can adjust their power consumption within a certain range. The first capacity refers to the maximum value of the power consumption that can be adjusted by these devices or systems within a specific time period. Adjustable flexible loads can flexibly adjust their power consumption according to the power supply and demand situation, thereby helping to balance the power supply and demand relationship, reduce power waste, and reduce energy costs. Interruptible loads refer to power loads that can be temporarily interrupted or shut down under certain circumstances. The second capacity refers to the maximum power value that these loads can be interrupted or shut down within a specific time period. When the power supply is tight or the power grid fails, the interruptible load can be temporarily shut down or interrupted to reduce the impact on the power grid and ensure the stable operation of the power grid.

[0034] Optionally, the demand stabilization strategy for generating demand according to the power regulation data of the target enterprise includes: The optimization target is set according to the needs of the target enterprise, and the decision variables and constraints are set according to the power regulation data. The decision variables include the discharge power of the energy storage system, the operating power of the adjustable flexible load, and the interruption time of the interruptible load. The constraints are the capacity limit of the equipment, the response time requirement, and the power demand constraint. The optimization objective, decision variables and constraints are included in the preset strategy model to obtain the decision variable values ​​and optimization objective values.

[0035] The optimization goal is set according to the actual needs of the target enterprise. For example, the optimization goal may include minimizing electricity costs, maximizing the stability of electricity supply, minimizing demand peaks, etc. In the embodiment of the present application, it is assumed that the optimization goal is to minimize electricity costs and minimize demand peaks. Decision variables are variables that you want to determine through the optimization process. In this scenario, the decision variables include the discharge power of the energy storage system, the operating power of the adjustable flexible load, and the interruption time of the interruptible load. Discharge power of the energy storage system: represents the power that the energy storage system needs to discharge within a given time step. Operating power of adjustable flexible load: represents the power that the adjustable flexible load needs to operate within a given time step. Interruption time of interruptible load: represents the length of time that the interruptible load needs to be interrupted within a given time step. Constraints are restrictions that must be met to ensure the effectiveness and feasibility of the optimization process. In the embodiment of the present application, constraints include equipment capacity limitations, response time requirements, and power demand constraints. Equipment capacity limitations: The discharge power and charging power of the energy storage system cannot exceed their maximum and minimum limits; the operating power of the adjustable flexible load should be within its adjustable range; the interruption time of the interruptible load should meet its minimum and maximum interruption time requirements. Response time requirements: The response time of the energy storage system, adjustable flexible load and interruptible load should meet the requirements of the power grid to ensure a rapid balance of power supply and demand. Power demand constraints: At any time step, the power supply (including energy storage system discharge, adjustable flexible load and power grid supply) should meet the power demand and not exceed the maximum power supply capacity of the power grid. The optimization objectives, decision variables and constraints are input into a preset strategy model (such as an optimization algorithm or energy management system). This model will calculate based on the input parameters and conditions, and output the optimal values ​​of the decision variables and the optimal values ​​of the optimization objectives.

[0036] By accurately setting decision variables and constraints, an efficient balance between power supply and demand can be ensured. This helps to reduce power waste and improve energy efficiency. Optimization objectives usually include minimizing power costs. By optimizing the use of energy storage systems, adjustable flexible loads, and interruptible loads, it is possible to meet power demand while reducing overall power costs. This has a positive impact on the economic benefits of enterprises. By rationally dispatching energy storage systems, adjustable flexible loads, and interruptible loads, fluctuations in power demand can be smoothed and the pressure on the power grid can be reduced. This helps to enhance the stability of the power grid and reduce power grid failures and power outages caused by imbalances in power supply and demand. Using the preset strategy model to optimize and analyze power regulation data can provide enterprises with a set of scientific and reasonable energy management solutions. This helps enterprises improve energy management efficiency, reduce energy waste, and improve overall operational levels. By quantitatively analyzing power regulation data through the preset strategy model, decision recommendations based on data and models can be obtained. This decision-making method is more scientific and accurate than traditional empirical decision-making, and helps enterprises make more informed decisions. Since the preset strategy model can be adjusted and optimized according to different power regulation data and optimization objectives, the strategy has strong adaptability and flexibility. No matter how the enterprise's electricity demand changes, the model parameters can be adjusted to adapt to the new situation and ensure the balance of electricity supply and demand.

[0037] Optionally, the demand stabilization strategy for generating demand according to the power regulation data of the target enterprise includes: Determining a plurality of first factors affecting the priority of adjustable loads, wherein the first factors include load adjustability, cost-effectiveness, impact on system stability, and response speed; assigning corresponding weights to the plurality of first factors according to their importance; The score of each adjustable load on each of the first factors is determined, a weighted sum is performed to obtain a total score of each adjustable load, and the priority of the adjustable load is determined according to the total score.

[0038] For example, the embodiments of the present application include four first factors: load adjustability, cost-effectiveness, impact on system stability, and response speed. Load adjustability: refers to the degree to which the load can adjust its power consumption. The more adjustable the load, the higher the flexibility in the smoothing strategy. Cost-effectiveness: refers to the ratio between the cost of adjusting the load power consumption and the benefits brought about. The higher the cost-effectiveness of the load, the more economical it is in the smoothing strategy. Impact on system stability: refers to the impact of adjusting the load power consumption on the stability of the power system. Adjustments to some loads may have a greater impact on system stability, so they need to be handled with caution. Response speed: refers to the response speed of the load to power regulation instructions. The faster the response speed of the load, the more advantages it has when it is necessary to quickly adjust the supply and demand of electricity.

[0039] Assign weights to these factors based on their importance. This usually needs to be determined based on the specific circumstances of the target enterprise and the goals of power regulation. Assume that the weights assigned to these four factors are: load adjustability: 0.3; cost-effectiveness: 0.2; impact on system stability: 0.3; response speed: 0.2. Each adjustable load in the target enterprise is evaluated on each factor and given a corresponding score. For example, a scoring standard can be set for each factor, and then the score can be assigned based on the actual situation of the adjustable load. The following is a simplified example (full score is 10): Load A: Adjustability: 9; Cost-effectiveness: 8; Impact on system stability: 7; Response speed: 9.

[0040] Load B: Adjustability: 8; Cost-effectiveness: 9; Impact on system stability: 10; Response speed: 8.

[0041] Multiply the score of each adjustable load on each factor by its corresponding weight, and then add up the scores of all factors to get the total score of the load. The higher the total score, the higher the priority of the load in the smoothing strategy. For load A and load B, their total scores are calculated as follows: Total score of load A = 9*0.3+8*0.2+7*0.3+9*0.2=8.2; Total score of load B = 8*0.3+9*0.2+10*0.3+8*0.2=8.6; Therefore, load B has a higher priority than load A among the adjustable loads.

[0042] By considering multiple factors such as the adjustability, cost-effectiveness, impact on system stability, and response speed of adjustable loads, it is possible to ensure that power regulation resources are reasonably allocated. This helps to achieve accurate matching of power supply and demand, avoid resource waste, and improve the overall efficiency of power use. Cost-effectiveness is an important consideration when evaluating the priority of adjustable loads. By prioritizing the dispatch of loads with higher cost-effectiveness, the overall cost of power regulation can be reduced and the economic benefits of the enterprise can be improved. This is of great practical significance for those companies seeking to reduce costs and improve profitability. Taking system stability as a factor in evaluating the priority of adjustable loads helps to ensure that the power regulation process does not have an adverse impact on system stability. By avoiding or reducing the regulation of loads that have a greater impact on system stability, the risk of system collapse or failure can be reduced, and the safe and stable operation of the power system can be guaranteed. In the power regulation process, response speed is a key indicator. By considering the response speed of the load, it is possible to ensure that the corresponding adjustable load can be dispatched quickly and effectively when the power supply and demand need to be adjusted quickly. This is of great significance for responding to sudden changes in power demand or failure situations. By comprehensively considering multiple factors and allocating weights, it is possible to ensure that the determination of adjustable load priority is more scientific and accurate. This decision-making method based on data and models is more reliable than traditional empirical decision-making, and helps enterprises make more intelligent and reasonable power regulation decisions. It can be flexibly adjusted according to the specific situation of the target enterprise and the goal of power regulation. Whether it is the characteristics of the load, the change in power demand or the goal of power regulation, it can be adapted to the new situation by adjusting the weight and scoring criteria. This adaptability and flexibility make this strategy have a wider application prospect and stronger vitality.

[0043] Optionally, the demand stabilization strategy for generating demand according to the power regulation data of the target enterprise further includes: determining a plurality of second factors affecting the priority of interrupting the load, wherein the second factors include importance of the load, interruption cost, and load type; Evaluating a plurality of the second factors of each interruptible load, determining the extent to which the second factor belongs to each evaluation level to establish a single factor evaluation matrix; determining weights of a plurality of said second factors, and establishing a weight set according to said weights; The single factor evaluation matrix and the weight set are synthesized to obtain a comprehensive evaluation result, and the priority of the interruptible load is determined according to the comprehensive evaluation result.

[0044] Determine the second factors that affect the priority of the interrupted load, such as the importance of the load, the interruption cost, the load type, etc., and form a factor set. Factor set U = {u1, u2, ..., un}, where ui represents the i-th (i≤n, and i is a positive integer) second factor. Set the comment set V = {v1, v2, ..., vm}, where vj represents the j-th (j≤m, and j is a positive integer) comment level, such as "very important", "important", "general", "unimportant", etc. Perform a single-factor fuzzy evaluation on each second factor ui to determine the membership of the second factor to each element in the comment set. This is usually obtained through expert scoring, questionnaire surveys, etc. It is denoted as the fuzzy evaluation matrix R.

[0045] Where rij (i≤n, j≤m, and i and j are both positive integers) represents the membership of factor ui to comment vj. According to the importance of each second factor in determining the interruption load priority, the weight of each factor is determined. This can be obtained by expert scoring, hierarchical analysis method, etc. It is recorded as weight set A = {a1, a2, ..., an}, where ai represents the weight of the i-th factor, and a1+a2+...+an=1.

[0046] The single factor fuzzy evaluation matrix R is subjected to fuzzy synthesis operation with the factor weight set A to obtain the comprehensive evaluation result B. This is usually achieved using fuzzy matrix multiplication, that is, B = A°R (where ° represents the fuzzy synthesis operator).

[0047] According to the comprehensive evaluation result B, the priority of the interruption load can be determined by using the maximum membership principle, weighted average principle, etc. For example, the comment level with the largest membership can be selected as the priority of the interruption load, or a comprehensive score can be obtained by weighted average calculation based on the membership, and the priority can be determined based on the ranking of the comprehensive score.

[0048] Assume that there are three interruption loads L1, L2 and L3, the evaluation factor set is U = {load importance, interruption cost, load type}, and the comment set is V = {high, medium, low}. The following data are obtained through expert scoring: The fuzzy evaluation matrices R1, R2, and R3 correspond to the single-factor fuzzy evaluation matrices of L1, L2, and L3 respectively.

[0049] Factor weight set A = {0.4, 0.3, 0.3}.

[0050] After fuzzy synthesis operation, the comprehensive evaluation results B1, B2, and B3 of L1, L2, and L3 are obtained. Assume that B1 = [0.5, 0.3, 0.2], B2 = [0.2, 0.5, 0.3], and B3 = [0.1, 0.1, 0.8].

[0051] According to the maximum membership principle, L1 has a high priority (because the first element in B1 is the largest), L2 has a medium priority, and L3 has a low priority. Based on this, the priority order of interrupting loads during power regulation can be determined.

[0052] By comprehensively considering multiple factors such as the importance of loads, interruption costs, and load types, and using fuzzy comprehensive evaluation methods for quantitative evaluation, the decision-making process can be ensured to be more scientific and objective. This avoids the subjectivity and uncertainty of traditional empirical decision-making and improves the accuracy and reliability of decision-making. In the process of power regulation, limited resources need to be reasonably allocated to each interrupted load. By determining the priority of the interrupted load, it can be ensured that resources are preferentially allocated to loads with higher priority, thereby achieving optimal allocation of resources. This helps to improve resource utilization efficiency and reduce resource waste. Interruption cost is one of the important factors that need to be considered in the power regulation process. By evaluating the interruption cost and determining the priority of the load, the number and interruption time of the interrupted load can be minimized while ensuring the balance of power supply and demand, thereby reducing the interruption cost. This is of great significance for improving the economic benefits of enterprises. The importance of loads and the type of loads have an important impact on the stability of the system. By evaluating these factors and determining the priority of the loads, the loads that have a greater impact on the stability of the system can be prioritized to reduce the potential risks to the stability of the system caused by the interrupted loads. This helps to ensure the safe and stable operation of the power system. The fuzzy comprehensive evaluation method is characterized by strong adaptability and flexibility. It can adjust the factor weights and evaluation criteria according to different power regulation needs and goals to adapt to different scenarios and conditions. This makes the strategy more adaptable and flexible, and can better meet the actual needs of enterprises. By quantitatively evaluating the priority of interrupted loads, it can provide a basis for enterprises to formulate clearer and more specific power regulation plans. This helps to improve the management efficiency of enterprises, reduce management costs, and enhance their competitiveness.

[0053] S130, when the target cause is detected, determining whether the real-time power is greater than the maximum demand and demand leveling target value in the leveling strategy in the current cycle; When one or more of the second devices are detected to be started, the target cause is determined to occur, and the current real-time power data is monitored and obtained in real time. Real-time power reflects the amount of electricity being consumed or generated in the current power system and is an important basis for power regulation. Query the maximum demand value recorded in the current cycle. The maximum demand usually refers to the maximum average power reached by the system or user in a specific time period (such as a month, a quarter or a year). It is one of the important bases for power system scheduling and billing. In the demand leveling strategy, a demand leveling target value is usually set. This value is based on a comprehensive consideration of multiple factors such as the actual operation of the power system, the predicted load, the electricity price policy, and the economic benefits of the enterprise. It represents the power demand level that the system expects to achieve under specific circumstances. Compare the real-time power with the maximum demand of the current cycle and the demand leveling target value in the leveling strategy. The purpose of this step is to determine whether the current power demand situation exceeds the bearing capacity of the system or enterprise, and whether the expected power demand level has been reached. If the real-time power is greater than the maximum demand of the current cycle, this may mean that the system is facing a large power load pressure, and further measures need to be taken to reduce the load or increase the power supply capacity. If the real-time power is greater than the demand smoothing target value in the smoothing strategy, this may indicate that the current electricity demand has exceeded the expected level set by the strategy, and it is necessary to adjust the strategy or take other measures to balance electricity supply and demand.

[0054] S140. When the real-time power is greater than the maximum demand in the current cycle and the demand leveling target value in the leveling strategy, the energy storage system is controlled to discharge according to the leveling strategy, and / or the load of the adjustable flexible load is adjusted, and / or the load of the interruptible load is adjusted.

[0055] When the real-time power is greater than the maximum demand in the current cycle and the demand smoothing target value in the smoothing strategy, demand smoothing is achieved by adjusting the energy storage system, adjustable flexible load and interruptible load.

[0056] Optionally, controlling the discharge of the energy storage system according to the smoothing strategy, and / or adjusting the load of the adjustable flexible load, and / or adjusting the load of the interruptible load includes: Controlling the discharge of the energy storage system according to the set discharge parameters, wherein the discharge parameters include current, voltage, and discharge time; Continuously monitor the real-time power of the grid and the status of the energy storage system; When the real-time power is less than or equal to the demand leveling target value, the control system gradually reduces the discharge amount or stops discharging; When the real-time power is greater than the demand leveling target value, determining whether the discharge power of the energy storage system exceeds a second threshold; When the discharge power of the energy storage system exceeds a second threshold, the load amounts of the adjustable flexible loads and the load amounts of the interruptible loads are gradually adjusted according to the priorities.

[0057] When the target enterprise's real-time power exceeds the maximum demand of the current cycle and the demand leveling target value in the leveling strategy during peak hours, the power control platform decides to take a series of control measures to balance power supply and demand. According to the pre-set discharge parameters (such as current, voltage, discharge time, etc.), the system sends a discharge instruction to the energy storage system. These parameters are set based on the technical specifications of the energy storage system, the current power and the expected discharge demand. The energy storage system begins to discharge according to the instructions to provide additional power support to the power grid. The power control platform continuously monitors the real-time power of the power grid, as well as key information such as the discharge status and remaining power of the energy storage system. Through real-time data analysis, the power control platform can accurately judge the supply and demand of the power grid and the discharge efficiency of the energy storage system. When the real-time power of the power grid gradually decreases and is less than or equal to the demand leveling target value, the power control platform begins to gradually reduce the discharge of the energy storage system. If the real-time power continues to be stable below the demand leveling target value, the power control platform will completely stop the discharge of the energy storage system. If the real-time power exceeds the demand leveling target value again, the power control platform will first determine whether the discharge power of the energy storage system exceeds the preset second threshold. This second threshold is set based on the safe discharge capacity of the energy storage system and the stable operation requirements of the power grid. If the discharge power of the energy storage system exceeds the second threshold, the power control platform will begin to gradually adjust the load of the adjustable flexible load and the interruptible load according to the priority. Suppose the real-time power of the power grid suddenly soars, exceeding the demand smoothing target value of 10MW. The power control platform first controls the energy storage system to discharge according to the preset parameters, providing an additional 6MW of power. However, the real-time power is still higher than the demand smoothing target value. The power control platform continuously monitors that the discharge power of the energy storage system is close to the second threshold (set to 6MW), so it begins to adjust the adjustable flexible load. By adjusting the load of the adjustable flexible load and the load of the interruptible load, the power control platform successfully reduced the power load by 4MW.

[0058] When the real-time power of the power grid exceeds the target value of demand leveling, the power control platform can respond quickly and provide additional power support to the power grid by controlling the discharge of the energy storage system. This rapid response helps prevent power grid overload and ensure the stability of the power system. By controlling the discharge of the energy storage system and adjusting the load of the adjustable flexible load, the power control platform can make full use of the adjustment capabilities of the energy storage equipment and flexible loads to optimize the configuration of power resources. This helps to reduce resource waste and improve resource utilization efficiency. When the discharge power of the energy storage system exceeds the second threshold, the power control platform will gradually adjust the load of the interruptible load according to the priority. This gradual adjustment method can minimize the impact on critical loads while reducing the cost of interrupting loads. It can be dynamically adjusted according to the real-time power of the power grid and the status of the energy storage system, and has strong flexibility and adaptability. Whether in peak or off-peak hours, the power control platform can respond quickly to changes in demand to ensure the stable operation of the power grid. By accurately controlling the discharge parameters of the energy storage system and adjusting the load of the adjustable flexible load, the power control platform can use energy more effectively and reduce energy waste. This helps to improve energy utilization efficiency and reduce operating costs.

[0059] Optionally, the stepwise adjusting the load amount of the adjustable flexible load and the load amount of the interruptible load according to the priority includes: Determining whether the discharge power of the energy storage system exceeds a third threshold, the third threshold being greater than the second threshold; When the discharge power of the energy storage system does not exceed the third threshold, the load of the adjustable flexible load is gradually adjusted according to the priority; when the discharge power of the energy storage system exceeds the third threshold, the load of the interruptible load is gradually adjusted according to the priority.

[0060] When the discharge power of the energy storage system does not exceed the third threshold, the load of the adjustable flexible load is gradually adjusted according to the preset priority order. Adjustable flexible loads usually include adjustable industrial equipment. The power control platform will first send adjustment instructions to the adjustable flexible loads with higher priorities, requiring them to reduce power consumption. If the reduced load is not enough to balance supply and demand, the power control platform will continue to send instructions to loads with lower priorities. When the discharge power of the energy storage system exceeds the third threshold, it indicates that the energy storage system has approached or reached its limit, and further measures are needed to balance supply and demand. According to the preset interruptible load priority, the power control platform begins to gradually interrupt some loads. These interruptible loads are usually non-critical loads that can be briefly interrupted in an emergency. The power control platform first interrupts loads with lower priorities to reduce the impact on critical loads. If the interrupted load is still not enough to balance supply and demand, the power control platform will continue to interrupt loads with higher priorities.

[0061] When the discharge power of the energy storage system does not exceed the third threshold, the power control platform prioritizes balancing the supply and demand of the power grid by adjusting the load of the adjustable flexible load. This strategy can maximize the use of the adjustment capacity of the flexible load, reduce unnecessary energy waste, and thus optimize resource utilization efficiency. When the discharge power of the energy storage system exceeds the third threshold, the power control platform begins to gradually adjust the load of the interruptible load according to the priority. This means that when possible, the power control platform will try to avoid interrupting the load to reduce the impact on the critical load and ensure the stability and reliability of the power system. By setting different thresholds (the second threshold and the third threshold), the power control platform can dynamically adjust the load adjustment strategy according to the discharge state of the energy storage system. This strategy makes the power system more rapid and flexible in dealing with supply and demand imbalances, and can respond to the real-time needs of the power grid in a timely manner. By setting the third threshold as the limit of the discharge power of the energy storage system, the power control platform can avoid excessive discharge of the energy storage system, thereby protecting the health and safety of the energy storage equipment. This is of great significance for extending the service life of the energy storage system and improving the reliability of the power system.

[0062] This embodiment also discloses a system for demand balancing using energy storage and controllable loads. Figure 2 is a schematic diagram of a module of a system for demand balancing using energy storage and controllable loads disclosed in an embodiment of the present application, such as Figure 2 As shown, the system includes a cause module 201, a strategy module 202, a judgment module 203 and an execution module 204, wherein: The cause module 201 is configured to obtain a power history data set of a target enterprise, determine a first moment corresponding to a first demand according to the power history data set, and determine a target cause of demand increase according to the first moment and a change in demand before and after the first moment, wherein the power history data set includes a time series and a demand corresponding to each moment, the first demand and the second demand are any two demands in the power history data set, and the first demand is greater than the second demand; A strategy module 202, configured to generate a demand balancing strategy according to the power regulation data of the target enterprise, wherein the power regulation data includes the installed capacity of the energy storage system, the first capacity of the adjustable flexible load, and the second capacity of the interruptible load; The judgment module 203 is configured to judge whether the real-time power is greater than the maximum demand in the current cycle and the demand leveling target value in the leveling strategy when the target cause is detected; The execution module 204 is configured to control the discharge of the energy storage system and / or adjust the load of the adjustable flexible load and / or adjust the load of the interruptible load according to the smoothing strategy when the real-time power is greater than the maximum demand in the current cycle and the demand smoothing target value in the smoothing strategy.

[0063] Optionally, the cause module 201 is configured to: Determine whether there is a sudden increase in demand based on the change in demand in a preset time period before and after the first moment, where the sudden increase means that the difference between the demand at the second moment and the demand at the previous adjacent moment is greater than a first threshold; When there is a sudden increase in demand, determining a first device that is running at the second moment, and determining power characteristics of the first device, the power characteristics including starting power, running power, and stopping power; Synchronously analyzing the start or stop time of the first device and the demand change to determine a second device associated with the sudden increase in demand from the first device; One or more of the second devices are activated as a targeted cause of the demand increase.

[0064] Optionally, the policy module 202 is configured to: The optimization target is set according to the needs of the target enterprise, and the decision variables and constraints are set according to the power regulation data. The decision variables include the discharge power of the energy storage system, the operating power of the adjustable flexible load, and the interruption time of the interruptible load. The constraints are the capacity limit of the equipment, the response time requirement, and the power demand constraint. The optimization objective, decision variables and constraints are included in the preset strategy model to obtain the decision variable values ​​and optimization objective values.

[0065] Optionally, the policy module 202 is configured to: Determining a plurality of first factors affecting the priority of adjustable loads, wherein the first factors include load adjustability, cost-effectiveness, impact on system stability, and response speed; assigning corresponding weights to the plurality of first factors according to their importance; The score of each adjustable load on each of the first factors is determined, a weighted sum is performed to obtain a total score of each adjustable load, and the priority of the adjustable load is determined according to the total score.

[0066] Optionally, the policy module 202 is further configured to: determining a plurality of second factors affecting the priority of interrupting the load, wherein the second factors include importance of the load, interruption cost, and load type; Evaluating a plurality of the second factors of each interruptible load, determining the extent to which the second factor belongs to each evaluation level to establish a single factor evaluation matrix; determining weights of a plurality of said second factors, and establishing a weight set according to said weights; The single factor evaluation matrix and the weight set are synthesized to obtain a comprehensive evaluation result, and the priority of the interruptible load is determined according to the comprehensive evaluation result.

[0067] Optionally, the execution module 204 is configured to: Controlling the discharge of the energy storage system according to the set discharge parameters, wherein the discharge parameters include current, voltage, and discharge time; Continuously monitor the real-time power of the grid and the status of the energy storage system; When the real-time power is less than or equal to the demand leveling target value, the control system gradually reduces the discharge amount or stops discharging; When the real-time power is greater than the demand leveling target value, determining whether the discharge power of the energy storage system exceeds a second threshold; When the discharge power of the energy storage system exceeds a second threshold, the load amounts of the adjustable flexible loads and the load amounts of the interruptible loads are gradually adjusted according to the priorities.

[0068] Optionally, the execution module 204 is configured to: Determining whether the discharge power of the energy storage system exceeds a third threshold, the third threshold being greater than the second threshold; When the discharge power of the energy storage system does not exceed the third threshold, the load of the adjustable flexible load is gradually adjusted according to the priority; when the discharge power of the energy storage system exceeds the third threshold, the load of the interruptible load is gradually adjusted according to the priority.

[0069] It should be noted that: when the device provided in the above embodiment realizes its function, only the division of the above functional modules is used as an example. In actual application, the above functions can be assigned to different functional modules as needed, that is, the internal structure of the device is divided into different functional modules to complete all or part of the functions described above. In addition, the device and method embodiments provided in the above embodiment belong to the same concept, and the specific implementation process is detailed in the method embodiment, which will not be repeated here.

[0070] This embodiment also discloses an electronic device, referring to Figure 3 The electronic device may include: at least one processor 301 , at least one communication bus 302 , a user interface 303 , a network interface 304 , and at least one memory 305 .

[0071] The communication bus 302 is used to realize the connection and communication between these components.

[0072] The user interface 303 may include a display screen (Display) and a camera (Camera), and the optional user interface 303 may also include a standard wired interface and a wireless interface.

[0073] The network interface 304 may optionally include a standard wired interface or a wireless interface (such as a WI-FI interface).

[0074] Among them, the processor 301 may include one or more processing cores. The processor 301 uses various interfaces and lines to connect various parts in the entire server, and executes various functions of the server and processes data by running or executing instructions, programs, code sets or instruction sets stored in the memory 305, and calling data stored in the memory 305. Optionally, the processor 301 can be implemented in at least one hardware form of digital signal processing (Digital Signal Processing, DSP), field programmable gate array (Field-Programmable Gate Array, FPGA), and programmable logic array (Programmable Logic Array, PLA). The processor 301 can integrate one or a combination of a central processing unit (Central Processing Unit, CPU), a graphics processing unit (Graphics Processing Unit, GPU) and a modem. Among them, the CPU mainly processes the operating system, user interface and application programs; the GPU is responsible for rendering and drawing the content to be displayed on the display screen; the modem is used to process wireless communications. It can be understood that the above-mentioned modem may not be integrated into the processor 301, and it can be implemented separately through a chip.

[0075] Among them, the memory 305 may include a random access memory (Random Access Memory, RAM) and may also include a read-only memory (Read-Only Memory). Optionally, the memory 305 includes a non-transitory computer-readable storage medium. The memory 305 can be used to store instructions, programs, codes, code sets or instruction sets. The memory 305 may include a program storage area and a data storage area, wherein the program storage area may store instructions for implementing an operating system, instructions for at least one function (such as a touch function, a sound playback function, an image playback function, etc.), instructions for implementing the above-mentioned various method embodiments, etc.; the data storage area may store data involved in the above-mentioned various method embodiments, etc. The memory 305 may optionally be at least one storage device located away from the aforementioned processor 301. As Figure 3 As shown, the memory 305 as a computer storage medium may include an operating system, a network communication module, a user interface module, and an application program for a method of using energy storage and controllable loads to smooth demand.

[0076] exist Figure 3 In the electronic device shown, the user interface 303 is mainly used to provide an input interface for the user and obtain data input by the user; and the processor 301 can be used to call the application program stored in the memory 305 for the method of using energy storage and controllable load to smooth demand. When executed by one or more processors 301, the electronic device executes one or more methods in the above-mentioned embodiments.

[0077] It should be noted that, for the aforementioned method embodiments, for the sake of simplicity, they are all described as a series of action combinations, but those skilled in the art should be aware that the present application is not limited by the order of the actions described, because according to the present application, certain steps can be performed in other orders or simultaneously. Secondly, those skilled in the art should also be aware that the embodiments described in the specification are all preferred embodiments, and the actions and modules involved are not necessarily required for the present application.

[0078] In the above embodiments, the description of each embodiment has its own emphasis. For parts that are not described in detail in a certain embodiment, reference can be made to the relevant descriptions of other embodiments.

[0079] In the several embodiments provided in this application, it should be understood that the disclosed devices can be implemented in other ways. For example, the device embodiments described above are only schematic, such as the division of units, which is only a logical function division. There may be other division methods in actual implementation, such as multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be through some service interfaces, and the indirect coupling or communication connection of devices or units can be electrical or other forms.

[0080] The units described as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, that is, they may be located in one place or distributed on multiple network units. Some or all of the units may be selected according to actual needs to achieve the purpose of the solution of this embodiment.

[0081] In addition, each functional unit in each embodiment of the present application may be integrated into one processing unit, or each unit may exist physically separately, or two or more units may be integrated into one unit. The above-mentioned integrated unit may be implemented in the form of hardware or in the form of software functional units.

[0082] If the integrated unit is implemented in the form of a software functional unit and sold or used as an independent product, it can be stored in a computer-readable memory. Based on this understanding, the technical solution of the present application, or the part that contributes to the prior art, or all or part of the technical solution can be embodied in the form of a software product, which is stored in a memory 305 and includes several instructions for a computer device (which can be a personal computer, server or network device, etc.) to perform all or part of the steps of the various embodiments of the present application. The aforementioned memory 305 includes: various media that can store program codes, such as a USB flash drive, a mobile hard disk, a magnetic disk or an optical disk.

[0083] The above is only an exemplary embodiment of the present disclosure, and the scope of the present disclosure cannot be limited thereto. That is, any equivalent changes and modifications made according to the teachings of the present disclosure are still within the scope of the present disclosure. After considering the disclosure of the specification and the truth of practice, it will be easy for those skilled in the art to think of other embodiments of the present disclosure. This application is intended to cover any modification, use or adaptation of the present disclosure, which follows the general principles of the present disclosure and includes common knowledge or customary technical means in the technical field that are not recorded in the present disclosure. The description and examples are regarded as exemplary only, and the scope and spirit of the present disclosure are defined by the claims.

Claims

1. A method for demand balancing using energy storage and controllable loads, characterized in that: Applied to a power control platform, the method comprises: Obtain a power history data set of the target enterprise, determine a first moment corresponding to a first demand according to the power history data set, and determine a target reason for the increase in demand according to the first moment and the change in demand before and after the first moment, wherein the power history data set includes a time series and a demand corresponding to each moment, the first demand and the second demand are any two demands in the power history data set, and the first demand is greater than the second demand; Generate a demand smoothing strategy based on the target enterprise's power regulation data, where the power regulation data includes the installed capacity of the energy storage system, the first capacity of the adjustable flexible load, and the second capacity of the interruptible load; When the target cause is detected, it is determined whether the real-time power is greater than the maximum demand in the current cycle and the demand suppression target value in the suppression strategy; When the real-time power is greater than the maximum demand in the current cycle and the demand leveling target value in the leveling strategy, the energy storage system is controlled to discharge according to the leveling strategy, and / or the load of the adjustable flexible load is adjusted, and / or the load of the interruptible load is adjusted.

2. The method for demand balancing using energy storage and controllable load according to claim 1, characterized in that: Determining the target reason for the increase in demand according to the change in demand at the first moment and before and after the first moment includes: Determine whether there is a sudden increase in demand based on the change in demand in a preset time period before and after the first moment, where the sudden increase means that the difference between the demand at the second moment and the demand at the previous adjacent moment is greater than a first threshold; When there is a sudden increase in demand, determining a first device that is running at the second moment, and determining power characteristics of the first device, the power characteristics including starting power, running power, and stopping power; Synchronously analyzing the start or stop time of the first device and the demand change to determine a second device associated with the sudden increase in demand from the first device; One or more of the second devices are activated as a targeted cause of the demand increase.

3. The method for demand balancing using energy storage and controllable load according to claim 1, characterized in that: The demand stabilization strategy generated according to the power regulation data of the target enterprise includes: The optimization target is set according to the needs of the target enterprise, and the decision variables and constraints are set according to the power regulation data. The decision variables include the discharge power of the energy storage system, the operating power of the adjustable flexible load, and the interruption time of the interruptible load. The constraints are the capacity limit of the equipment, the response time requirement, and the power demand constraint. The optimization objective, decision variables and constraints are included in the preset strategy model to obtain the decision variable values ​​and optimization objective values.

4. The method for demand balancing using energy storage and controllable load according to claim 1, characterized in that: The demand stabilization strategy generated according to the power regulation data of the target enterprise includes: Determining a plurality of first factors affecting the priority of adjustable loads, wherein the first factors include load adjustability, cost-effectiveness, impact on system stability, and response speed; assigning corresponding weights to the plurality of first factors according to their importance; The score of each adjustable load on each of the first factors is determined, a weighted sum is performed to obtain a total score of each adjustable load, and the priority of the adjustable load is determined according to the total score.

5. The method for demand balancing using energy storage and controllable load according to claim 1, characterized in that: The demand stabilization strategy for generating demand according to the power regulation data of the target enterprise also includes: determining a plurality of second factors affecting the priority of interrupting the load, wherein the second factors include importance of the load, interruption cost, and load type; Evaluating a plurality of the second factors of each interruptible load, determining the extent to which the second factor belongs to each evaluation level to establish a single factor evaluation matrix; determining weights of a plurality of said second factors, and establishing a weight set according to said weights; The single factor evaluation matrix and the weight set are synthesized to obtain a comprehensive evaluation result, and the priority of the interruptible load is determined according to the comprehensive evaluation result.

6. The method for demand balancing using energy storage and controllable loads according to claim 1, characterized in that: The controlling the discharging of the energy storage system according to the smoothing strategy, and / or adjusting the load of the adjustable flexible load, and / or adjusting the load of the interruptible load includes: Controlling the discharge of the energy storage system according to the set discharge parameters, wherein the discharge parameters include current, voltage, and discharge time; Continuously monitor the real-time power of the grid and the status of the energy storage system; When the real-time power is less than or equal to the demand leveling target value, the control system gradually reduces the discharge amount or stops discharging; When the real-time power is greater than the demand leveling target value, determining whether the discharge power of the energy storage system exceeds a second threshold; When the discharge power of the energy storage system exceeds a second threshold, the load amounts of the adjustable flexible loads and the load amounts of the interruptible loads are gradually adjusted according to the priorities.

7. The method for demand balancing using energy storage and controllable load according to claim 6, characterized in that: The step of gradually adjusting the load amount of the adjustable flexible load and the load amount of the interruptible load according to the priority includes: Determining whether the discharge power of the energy storage system exceeds a third threshold, the third threshold being greater than the second threshold; When the discharge power of the energy storage system does not exceed the third threshold, gradually adjusting the load amount of the adjustable flexible load according to the priority; When the discharge power of the energy storage system exceeds a third threshold, the load amount of the interruptible load is gradually adjusted according to the priority.

8. A system for demand balancing using energy storage and controllable loads, characterized in that: It includes a cause module, a strategy module, a judgment module and an execution module, among which: a cause module configured to obtain a power history data set of a target enterprise, determine a first moment corresponding to a first demand according to the power history data set, and determine a target cause of demand increase according to the first moment and a change in demand before and after the first moment, wherein the power history data set includes a time series and a demand corresponding to each moment, the first demand and the second demand are any two demands in the power history data set, and the first demand is greater than the second demand; A strategy module configured to generate a demand stabilization strategy according to power regulation data of the target enterprise, wherein the power regulation data includes an installed capacity of an energy storage system, a first capacity of an adjustable flexible load, and a second capacity of an interruptible load; A judgment module configured to judge whether the real-time power is greater than the maximum demand in the current cycle and the demand leveling target value in the leveling strategy when the target cause is detected; The execution module is configured to control the discharge of the energy storage system and / or adjust the load of the adjustable flexible load and / or adjust the load of the interruptible load according to the smoothing strategy when the real-time power is greater than the maximum demand in the current cycle and the demand smoothing target value in the smoothing strategy.

9. An electronic device, characterized in that: It includes a processor, a memory, a user interface and a network interface, the memory is used to store instructions, the user interface and the network interface are both used to communicate with other devices, and the processor is used to execute the instructions stored in the memory so that the electronic device executes the method as described in any one of claims 1-7.

10. A computer-readable storage medium, characterized in that: The computer-readable storage medium stores instructions, and when the instructions are executed, the method according to any one of claims 1 to 7 is executed.

Citation Information

Cited By

  • Coal-fired power generation unit operation optimization method and system based on industrial big data

    CN119717519A

  • Feeder load removal method and system considering distributed power supply

    CN119944706A

  • Feeder load shedding method and system considering distributed power supply

    CN119944706B

  • Demand defense control method and system based on digital twinning

    CN120955632A

  • Data processing method and device, power monitoring equipment and computer readable storage medium

    CN121350446A