Precast pile bottom grouting device and grouting method thereof

By designing a prefabricated pile bottom grouting device, the combination of sliding plates and sealing spheres is used to solve the problems of soil blockage and slurry reflow, and a more efficient pile bottom grouting effect is achieved.

CN118911149AActive Publication Date: 2024-11-08SHANGHAI CONSTRUCTION FOURTH CONSTRUCTION GROUP CO LTD
View PDF 8 Cites 0 Cited by

Patent Information

Application Number
CN202411412876.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-11
Publication Date
2024-11-08
Estimated Expiration
2044-10-11

AI Technical Summary

Technical Problem

During the pile bottom grouting process of PHC pipe piles, how to prevent soil from blocking the grouting holes during pile sinking and avoid the slurry returning after grouting, resulting in limited improvement of foundation load-bearing capacity.

Method used

A prefabricated pile bottom grouting device is designed, including grouting equipment, grouting pipes and grouting pile tips. The slurry is transported into the grouting pile tips through the grouting pipe. The protective pipe of the grouting pile tips is provided with sliding. The sliding plate and the sphere are moved. The sliding plate is pushed up by the support spring when sinking the pile. The sphere is closed and the grouting hole is closed. During grouting, the sliding plate is moved down. After the grouting is completed, the sealing sphere is reset and re-enclosed to avoid slurry. Return.

Benefits of technology

It effectively prevents soil from entering the grouting hole during pile sinking and automatically sealing after grouting, preventing slurry from flowing back, significantly improving the grouting effect at the bottom of the prefabricated pile.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118911149A_ABST
    Figure CN118911149A_ABST
Patent Text Reader

Abstract

The invention discloses a precast pile bottom grouting device and a grouting method thereof, and belongs to the technical field of building construction. Comprising a grouting device, a grouting pipe and a grouting pile tip, the grouting device conveys grout into the grouting pile tip through the grouting pipe, the grouting pile tip comprises an end plate, the end plate is welded and fixed to the end, located deep underground, of a precast pile, a through hole is formed in the middle of the end plate, a protection pipe is arranged on the surface of one end of the outer side of the through hole, and the protection pipe is connected with the grouting device. One end of the protection pipe is communicated with the through hole, the other end of the protection pipe is provided with a sealing plate, the sealing plate is fixed to the protection pipe, a plurality of grouting holes are formed in the circumference of the outer side face of the protection pipe, a sliding plate is arranged in the protection pipe, and the edge of the sliding plate is slidably connected to the inner wall of the protection pipe; pulling ropes matched with the grouting holes in number are arranged on the lower surface of the sliding plate, and one end of each pulling rope is fixed to the sliding plate. The technical scheme is used for improving the grouting effect on the bottom of the precast pile.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of building construction, and in particular relates to a prefabricated pile bottom grouting device and a grouting method thereof. Background Art

[0002] PHC piles are hollow cylindrical concrete precast piles with the advantages of high bearing capacity, fast construction speed, good construction quality and low engineering cost, so they are widely used in engineering construction. However, due to the bearing capacity of the foundation, the strength of the PHC pile body is often not fully utilized, resulting in a waste of resources.

[0003] In order to make full use of the strength of the PHC pipe pile, the engineering and technical personnel thought of improving the foundation bearing capacity of the PHC pipe pile by drawing on the post-grouting technology of the bored pile end in the existing technology. When grouting the bottom of the PHC pipe pile, how to prevent the soil in the pile foundation hole from clogging the grouting holes in the grouting device during pile sinking, and how to avoid the backflow of slurry after the grouting is completed are key factors to ensure the grouting effect of the PHC pipe pile. Therefore, a prefabricated pile bottom grouting device and a grouting method thereof are proposed. Summary of the invention

[0004] In view of this, an object of the present invention is to provide a precast pile bottom grouting device and a grouting method thereof, so as to improve the grouting effect on the precast pile bottom.

[0005] In order to achieve the above object, the present invention provides the following technical solutions: The present invention discloses a precast pile bottom grouting device, which is used for grouting the precast pile bottom, and comprises a grouting device, a grouting pipe and a grouting pile tip. The grouting device transports slurry into the grouting pile tip through the grouting pipe. The grouting pile tip comprises an end plate, which is welded and fixed to one end of the precast pile located deep underground. A through hole is provided in the middle of the end plate, and a protective tube is provided on the surface of one end outside the through hole. One end of the protective tube is connected to the through hole, and the other end of the protective tube is provided with a closing plate, which is fixed to the protective tube. A plurality of grouting holes are provided on the circumference of the outer surface of the protective tube, and a sliding plate is provided inside the protective tube. The edge of the sliding plate is slidably connected to the inner wall of the protective tube, and a sliding plate is provided on the lower surface of the sliding plate, which is connected to the grouting hole. A matching number of traction ropes, one end of which is fixed on the sliding plate, and the other end of which passes through the outside of the grouting hole, and a sealing ball is provided on one end of the traction rope located on the outside of the protective tube, a supporting spring is provided between the sliding plate and the closing plate, and the two ends of the supporting spring are respectively fixed on the sliding plate and the closing plate, and a plurality of supporting blocks are circumferentially provided on the upper surface of the sliding plate, and an installation spacing is provided between adjacent supporting blocks, when the grouting pipe is connected to the protective tube for grouting, the end of the grouting pipe pushes the sliding plate to slide downward to the bottom of the grouting hole, and when the grouting pipe is separated from the protective tube, the supporting spring lifts the sliding block to the top of the grouting hole, and the sealing ball is in close contact with the outer end surface of the grouting hole.

[0006] Furthermore, a mounting tube is provided in the middle of a side surface of the end plate facing the interior of the precast pile, one end of the mounting tube is fixed to the outside of the through hole, and a rubber plug is provided on one end of the grouting tube close to the mounting tube. When the grouting tube is grouting, the rubber plug is located in the mounting tube and in close contact with the inner wall of the mounting tube.

[0007] Furthermore, a receiving groove is provided in the middle of the end plate, and the end of the rubber plug is tightly pressed against the receiving groove.

[0008] Furthermore, an annular sealing block is provided on the other end of the precast pile, the inner ring of the annular sealing block is located in the middle of the end plate, and the grouting pipe is slidably connected to the annular sealing block.

[0009] Furthermore, a plurality of support steel plates evenly distributed around the circumference are provided on the end plate, one end of the support steel plate is fixed to the end plate, and the grouting holes are provided between adjacent support steel plates.

[0010] Furthermore, the sealing sphere is provided with a conical tip on its surface outside the grouting hole, and the small diameter end of the conical tip is arranged toward the inner wall of the pile foundation hole. The sealing sphere is provided with a pushing sphere on its surface inside the grouting hole, and the surface of the pushing sphere is fixed on the sealing sphere, and part of the pushing sphere protrudes into the interior of the protective tube.

[0011] Furthermore, a column is provided in the middle of the closing plate, and the middle of the sliding plate is slidably connected to the column.

[0012] Furthermore, an annular rubber block is provided on the inner side surface of one end of the protective tube connected to the closing plate, one end of the annular rubber block is fixed to the closing plate, the upper end of the annular rubber block is located below the grouting hole, and a hollow rubber column is provided on the surface of the sliding plate facing the annular rubber block, and a rectangular groove matching the position of the traction rope is provided on the surface of the hollow rubber column, and the depth of the rectangular groove is less than the thickness of the hollow rubber column.

[0013] A grouting method for a prefabricated pile bottom grouting device comprises the following construction steps: S1, welding and fixing the end plate of the grouting pile tip to one end of the prefabricated pile installed deep underground; S2, hoisting the prefabricated pile with the grouting pile tip to the top of the pile foundation hole on the ground, and then performing the pile sinking operation; S3, installing the annular sealing block on the other end of the prefabricated pile, and then moving the end of the grouting pipe down into the protection pipe; S4, by applying pressure to the axial direction of the grouting pipe, the rubber plug is squeezed in the installation pipe to form a seal, and at the same time, the end of the grouting pipe presses the sliding plate downward, so that the sliding plate slides to the bottom of the grouting hole and contacts the sealing ball to seal the grouting hole; S5, then grouting is input into the grouting pipe through the grouting equipment, and the grouting seeps out from the grouting hole to perform grouting; S6, after the grouting is completed, the grouting pipe is lifted up, at which time the support spring is reset, driving the sliding plate to move up, and then driving the blocking ball to fit tightly on the end of the grouting hole again through the traction rope, thereby blocking the grouting hole and preventing the slurry from flowing back.

[0014] The beneficial effects of the present invention are: The grouting device in the present technical solution can close the grouting holes during the early stage of pile sinking to prevent soil from entering the interior of the grouting pile tip and clogging the grouting holes. At the same time, during grouting, the grouting holes will automatically open to facilitate the grouting operation. After the grouting is completed, the grouting holes can also be automatically closed to prevent the slurry from flowing back. Therefore, the grouting device in the present technical solution can greatly improve the grouting effect on the bottom of the precast pile.

[0015] Other advantages, objectives and features of the present invention will be described in the following description and will be apparent to those skilled in the art to some extent, or those skilled in the art may be taught from the practice of the present invention. The objectives and other advantages of the present invention may be realized and obtained through the following description. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] In order to make the purpose, technical solution and beneficial effects of the present invention clearer, the present invention provides the following drawings for illustration: Figure 1 It is a three-dimensional schematic diagram of the pile bottom grouting device in the present invention; Figure 2 It is a schematic cross-sectional view of the pile bottom grouting device in the present invention; Figure 3 It is a three-dimensional schematic diagram of the grouting pile tip in the present invention; Figure 4 It is a partial schematic diagram of the interior of the grouting pile tip protection pipe in the present invention; Figure 5 It is a three-dimensional schematic diagram of the protection tube in the present invention; Figure 6 It is a three-dimensional schematic diagram of the internal structure of the protection tube in the present invention; Figure 7 It is a three-dimensional schematic diagram of a mounting tube arranged on the end plate of the present invention; Figure 8 A schematic diagram of the arrangement of the pushing ball in the present invention; Fig. 9 It is a three-dimensional schematic diagram of the hollow rubber column of the present invention.

[0017] The following are marked in the accompanying drawings: 1. Precast pile; 2. Grouting pile tip; 3. End plate; 4. Protective tube; 5. Support steel plate; 6. Grouting hole; 7. Closing plate; 8. Sliding plate; 9. Support block; 10. Support spring; 11. Traction rope; 12. Blocking ball; 13. Column; 14. Annular rubber block; 15. Mounting tube; 16. Rubber plug; 17. Receiving groove; 18. Annular sealing block; 19. Grouting tube; 20 Pushing ball; 21. Hollow rubber column. DETAILED DESCRIPTION

[0018] like Figures 1 to 9As shown, a prefabricated pile bottom grouting device of the present invention is used for grouting the bottom of a prefabricated pile 1, comprising a grouting device, a grouting pipe 19 and a grouting pile tip 2. The grouting device is a prior art and will not be described in detail herein. The grouting device transports slurry to the grouting pile tip 2 through the grouting pipe 19. The grouting pile tip 2 comprises an end plate 3, which may be a steel pipe. The end plate 3 is welded and fixed to one end of the prefabricated pile 1 located deep underground. A through hole is provided in the middle of the end plate 3, a protective tube 4 is provided on the surface of one end outside the through hole, one end of the protective tube 4 is connected to the through hole, and a closing plate 7 is provided at the other end of the protective tube 4. The closing plate 7 is fixed to the protective tube 4, and a plurality of grouting holes 6 are provided on the circumference of the outer surface of the protective tube 4. In the present specific embodiment, the number of the grouting holes 6 is 4. A sliding plate 8 is provided inside the protective tube 4. The outer diameter of the sliding plate 8 is consistent with the inner diameter of the protective tube 4. The edge of the sliding plate 8 is slidably connected to the inner wall of the protective tube 4. The lower A traction rope 11 matching the number of grouting holes 6 is provided on the surface, one end of the traction rope 11 is fixed on the lower surface of the sliding plate 8, and the other end of the traction rope 11 passes through the outside of the grouting holes 6 respectively, and a sealing ball 12 is provided on one end of the traction rope 11 located on the outside of the protective tube 4, and the diameter of the sealing ball 12 is larger than the diameter of the grouting hole 6, and a support spring 10 is provided between the sliding plate 8 and the closing plate 7, and the two ends of the support spring 10 are respectively fixed on the sliding plate 8 and the closing plate 7, and a plurality of support blocks 9 are circumferentially provided on the upper surface of the sliding plate 8, and an installation spacing is provided between adjacent support blocks 9, and the installation spacing serves as a channel for slurry flow. When the grouting pipe 19 is connected to the protective tube 4 for grouting, the end of the grouting pipe 19 pushes the sliding plate 8 to slide downward to the bottom of the grouting hole 6, and when the grouting pipe 19 is separated from the protective tube 4, the support spring 10 lifts the sliding block to the top of the grouting hole 6, and the sealing ball 12 is in close contact with the outer end surface of the grouting hole 6.

[0019] The working principle of the above technical solution is: When the pile sinking operation is performed, since the support spring 10 exerts an upward force on the sliding plate 8, the sliding plate 8 will straighten the traction rope 11, thereby making the outer surface of the blocking ball 12 fit the grouting hole 6 to block the grouting hole 6, thereby preventing the soil on the inner wall of the pile foundation hole from contacting the protection pipe 4 during the pile sinking operation, causing the soil to enter the protection pipe 4 or block the grouting hole 6; When the pile is sunk and the grouting pipe 19 is extended into the protective pipe 4, it is not difficult to understand that the diameter of the grouting pipe 19 matches the inner diameter of the protective pipe 4, that is, it can play a certain sealing role during grouting to avoid pressure relief. The end force of the grouting pipe 19 when it moves downward will overcome the damping of the support spring 10, and then squeeze the sliding plate 8 downward. The sliding plate 8 moves downward in the protective pipe 4 to the lower position of the grouting hole 6 (below the center of the grouting hole 6). At this time, the traction rope 11 is in a relaxed state, and the blocking ball 12 loses its force and will detach under gravity or grouting pressure. That is, at this time, the end of the grouting pipe 19 is connected to the grouting hole 6, and then the grouting equipment can be used to grout the pile bottom. During the grouting operation, the slurry seeps out from the grouting hole 6 into the pile foundation hole outside the protective tube 4. When the grouting is completed, the grouting tube 19 is lifted upward. At this time, the force acting on the support spring 10 disappears, and the support spring 10 will automatically reset. During the resetting process, it will push the sliding plate 8 back to the initial position. That is, at this time, the sliding plate 8 will pull the traction rope 11, and then drive the blocking ball 12 to reset and block the end of the grouting hole 6 to prevent the slurry from flowing back (it should be noted that the grouting pressure is outward, even if there is a small amount of soil at the bottom of the pile foundation hole, the pressure will push the soil outward away from the grouting hole 6, and the grouting slurry is a flowable liquid, which will not hinder the resetting of the blocking ball 12).

[0020] The provision of the protection tube 4 can protect the end of the grouting tube 19, thereby avoiding the problem that the end of the grouting tube 19 is blocked and damaged by contact and collision due to direct grouting.

[0021] In one feasible manner, a mounting tube 15 is provided in the middle of a side surface of the end plate 3 facing the interior of the precast pile 1, one end of the mounting tube 15 is fixed to the outside of the through hole, and a rubber plug 16 is provided on one end of the grouting tube 19 close to the mounting tube 15. When the grouting tube 19 is grouting, the rubber plug 16 is located in the mounting tube 15 and is in close contact with the inner wall of the mounting tube 15. The rubber plug 16 is squeezed into the mounting tube 15, and the squeeze contact forms a seal, thereby avoiding pressure leakage during grouting and improving the grouting effect.

[0022] In one practicable manner, a receiving groove 17 is provided in the middle of the end plate 3, and the end of the rubber plug 16 is tightly pressed against the receiving groove 17. The end surface of the rubber plug 16 is pressurized in the receiving groove 17, which can further improve the sealing effect.

[0023] In one feasible manner, an annular sealing block 18 is provided on the other end of the precast pile 1, the inner ring of the annular sealing block 18 is located in the middle of the end plate 3, and the grouting pipe 19 is slidably connected to the annular sealing block 18. The setting of the annular sealing block 18 can guide and support the installation of the grouting pipe 19, thereby improving the installation accuracy and convenience of the grouting pipe 19. Of course, the grouting pipe 19 can also be installed in advance. At this time, the annular sealing block 18 can be used as a support to avoid the grouting pipe 19 from shaking during hoisting, which may cause damage.

[0024] In one feasible manner, a plurality of circumferentially evenly distributed supporting steel plates 5 are provided on the end plate 3, one end of the supporting steel plate 5 is fixed on the end plate 3, and the grouting holes 6 are provided between adjacent supporting steel plates 5. The provision of the supporting steel plates 5 can avoid the problem of the protective tube 4 being inserted into the soil due to the small contact area between the protective tube 4 and the ground of the pile foundation hole, and can also improve the bearing capacity of the bottom end of the precast pile 1.

[0025] like Figure 8 As shown, in an practicable manner, a conical tip is provided on the surface of the plugging sphere 12 located outside the grouting hole 6, and the small diameter end of the conical tip is arranged toward the inner wall of the pile foundation hole. A pushing sphere 20 is provided on the surface of the plugging sphere 12 located inside the grouting hole 6, and the surface of the pushing sphere 20 is fixed on the plugging sphere 12, and part of the pushing sphere 20 protrudes into the inside of the protective tube 4. When the outside of the plugging sphere 12 contacts the soil, the setting of the conical tip can reduce the contact area between the plugging sphere 12 and the soil when it moves outward, thereby preventing the plugging sphere 12 from contacting the soil during the grouting. Under the pressure, the blocking ball 12 can be better moved into the soil by a certain distance (penetrated into the soil), thereby facilitating the formation of a gap between the blocking ball 12 and the grouting hole 6, thereby facilitating the flow of slurry for grouting. When the sliding plate 8 moves downward, it will squeeze the pushing ball 20, that is, it will cause the pushing ball 20 to move outward or tilt, thereby driving the blocking ball 12 to overcome the pressure of the soil and move outward or tilt, and both can form a gap between the blocking ball 12 and the grouting hole 6, thereby further improving the effect of gap generation and improving the grouting effect.

[0026] In one practicable manner, a column 13 is provided in the middle of the closing plate 7, and the middle of the sliding plate 8 is slidably connected to the column 13. The setting of the column 13 can guide the movement of the sliding plate 8 and improve its movement effect.

[0027] like Figure 4 and Fig. 9As shown, in an practicable manner, an annular rubber block 14 is provided on the inner side surface of one end of the protection tube 4 connected to the closing plate 7, one end of the annular rubber block 14 is fixed on the closing plate 7, the upper end of the annular rubber block 14 is located below the grouting hole 6, a hollow rubber column 21 is provided on the surface of the sliding plate 8 facing the annular rubber block 14, a rectangular groove 22 matching the position of the traction rope 11 is provided on the surface of the hollow rubber column 21, the depth of the rectangular groove 22 is less than the thickness of the hollow rubber column 21, and the arrangement of the annular rubber block 14 and the hollow rubber column 21 can make the sliding plate 8 move downward When the sliding plate 8 moves downward, the length of the traction rope 11 will only shrink, that is, the length hanging downward will be short, that is, the traction rope 11 will not accumulate, resulting in the traction rope 11 being squeezed by the end face of the hollow rubber column, causing the blocking ball 12 to be unable to move.

[0028] A grouting method for a prefabricated pile 1 bottom grouting device comprises the following construction steps: S1, welding and fixing the end plate 3 of the grouting pile tip 2 to one end of the prefabricated pile 1 installed deep underground; S2, hoisting the prefabricated pile 1 with the grouting pile tip 2 to the top of the pile foundation hole on the ground, and then performing the pile sinking operation; S3, install the annular sealing block 18 on the other end of the precast pile 1, and then move the end of the grouting pipe 19 down into the protection pipe 4; S4, by applying pressure to the axial direction of the grouting pipe 19, the rubber plug 16 is squeezed in the mounting pipe 15 to form a seal, and at the same time, the end of the grouting pipe 19 presses the sliding plate 8 downward, so that the sliding plate 8 slides to the bottom of the grouting hole 6 and contacts the sealing ball 12 to seal the grouting hole 6; S5, then grouting is input into the grouting pipe 19 through the grouting equipment, and the grouting seeps out from the grouting hole 6 to perform grouting; S6, after grouting is completed, the grouting pipe 19 is lifted up, at which time the support spring 10 is reset, driving the sliding plate 8 to move upward, and then driving the blocking ball 12 through the traction rope 11 to fit tightly on the end of the grouting hole 6 again, thereby blocking the grouting hole 6 to prevent the slurry from flowing back.

[0029] Finally, it should be noted that the above preferred embodiments are only used to illustrate the technical solutions of the present invention rather than to limit it. Although the present invention has been described in detail through the above preferred embodiments, those skilled in the art should understand that various changes can be made in form and details without departing from the scope defined by the claims of the present invention.

Claims

1. A precast pile bottom grouting device, used for grouting the bottom of a precast pile (1). Features: The invention comprises a grouting device, a grouting pipe (19) and a grouting pile tip (2), wherein the grouting device transports slurry into the grouting pile tip (2) through the grouting pipe (19), wherein the grouting pile tip (2) comprises an end plate (3), wherein the end plate (3) is welded and fixed to one end of a prefabricated pile (1) located deep underground, wherein a through hole is provided in the middle of the end plate (3), wherein a protective pipe (4) is provided on the surface of one end outside the through hole, wherein one end of the protective pipe (4) is connected to the through hole, wherein a closing plate (7) is provided at the other end of the protective pipe (4), wherein a plurality of grouting holes (6) are provided on the circumference of the outer surface of the protective pipe (4), wherein a sliding plate (8) is provided inside the protective pipe (4), wherein the edge of the sliding plate (8) is slidably connected to the inner wall of the protective pipe (4), wherein a traction rope (11) matching the number of the grouting holes (6) is provided on the lower surface of the sliding plate (8), wherein one end of the traction rope (11) is fixed to the inner wall of the protective pipe (4), wherein ... On the sliding plate (8), the other end of the traction rope (11) passes through the outside of the grouting hole (6), and a blocking ball (12) is provided on one end of the traction rope (11) located outside the protection tube (4). A support spring (10) is provided between the sliding plate (8) and the closing plate (7), and the two ends of the support spring (10) are respectively fixed to the sliding plate (8) and the closing plate (7). A plurality of support blocks (9) are provided on the circumference of the upper surface of the sliding plate (8). , an installation spacing is provided between adjacent support blocks (9); when the grouting pipe (19) is connected to the protective pipe (4) for grouting, the end of the grouting pipe (19) pushes the sliding plate (8) to slide downward to below the grouting hole (6); when the grouting pipe (19) is separated from the protective pipe (4), the support spring (10) lifts the sliding block to above the grouting hole (6), and the blocking ball (12) is in close contact with the outer end surface of the grouting hole (6).

2. A prefabricated pile bottom grouting device according to claim 1, Features: A mounting tube (15) is provided in the middle of a side surface of the end plate (3) facing the interior of the precast pile (1); one end of the mounting tube (15) is fixed to the outside of the through hole; a rubber plug (16) is provided on an end of the grouting tube (19) close to the mounting tube (15); when the grouting tube (19) is grouting, the rubber plug (16) is located in the mounting tube (15) and is in close contact with the inner wall of the mounting tube (15).

3. A prefabricated pile bottom grouting device according to claim 2, Features: A receiving groove (17) is provided in the middle of the end plate (3), and the end of the rubber plug (16) is tightly pressed against the receiving groove (17).

4. A prefabricated pile bottom grouting device according to claim 1, Features: An annular sealing block (18) is provided on the other end of the prefabricated pile (1), the inner ring of the annular sealing block (18) is located in the middle of the end plate (3), and the grouting pipe (19) is slidably connected to the annular sealing block (18).

5. A prefabricated pile bottom grouting device according to claim 1, Features: A plurality of support steel plates (5) evenly distributed around the circumference are provided on the end plate (3), one end of the support steel plate (5) is fixed to the end plate (3), and the grouting holes (6) are arranged between adjacent support steel plates (5).

6. A prefabricated pile bottom grouting device according to claim 1, Features: The sealing sphere (12) is provided with a conical tip on its surface outside the grouting hole (6), the small diameter end of the conical tip being arranged toward the inner wall of the pile foundation hole, and the sealing sphere (12) is provided with a pushing sphere (20) on its surface inside the grouting hole (6), the surface of the pushing sphere (20) being fixed to the sealing sphere (12), and a portion of the pushing sphere (20) protruding into the interior of the protective tube (4).

7. A prefabricated pile bottom grouting device according to claim 1, Features: A column (13) is provided in the middle of the closing plate (7), and a middle of the sliding plate (8) is slidably connected to the column (13).

8. A prefabricated pile bottom grouting device according to claim 1, Features: An annular rubber block (14) is provided on the inner side surface of one end of the protection tube (4) connected to the closing plate (7); one end of the annular rubber block (14) is fixed to the closing plate (7); the upper end of the annular rubber block (14) is located below the grouting hole (6); a hollow rubber column (21) is provided on the surface of the sliding plate (8) facing the annular rubber block (14); a rectangular groove (22) matching the position of the traction rope (11) is provided on the surface of the hollow rubber column (21); the depth of the rectangular groove (22) is less than the thickness of the hollow rubber column (21).

9. A grouting method for a precast pile bottom grouting device according to any one of claims 1 to 8, Features: The construction steps include: S1, welding and fixing the end plate (3) of the grouting pile tip (2) to one end of the prefabricated pile (1) installed deep underground; S2, hoisting the prefabricated pile (1) equipped with the grouting pile tip (2) to the top of the pile foundation hole on the ground, and then performing a pile sinking operation; S3, installing the annular sealing block (18) on the other end of the prefabricated pile (1), and then moving the end of the grouting pipe (19) down into the protection pipe (4); S4, by applying pressure to the grouting pipe (19) in the axial direction, the rubber plug (16) is squeezed in the mounting pipe (15) to form a seal, and at the same time, the end of the grouting pipe (19) presses the sliding plate (8) downward, so that the sliding plate (8) slides to the bottom of the grouting hole (6) and contacts the sealing ball (12) to seal the grouting hole (6); S5, then injecting slurry into the grouting pipe (19) through the grouting equipment, and the slurry seeps out from the grouting hole (6) to perform grouting; S6, after grouting is completed, the grouting pipe (19) is lifted upward, at which time the support spring (10) is reset, driving the sliding plate (8) to move upward, and then driving the blocking ball (12) to fit tightly onto the end of the grouting hole (6) again through the traction rope (11), thereby blocking the grouting hole (6) and preventing the slurry from flowing back.

Citation Information

Patent Citations

  • Prefabricated hollow pile for post-grouting and post-grouting construction method

    CN116837834A

  • Grouting root fixing and expanding body steel pipe pile and construction method thereof

    CN117684555A

  • Post mudjack construction technics for sidewal and bottom of bore of filling pile

    CN1540104A

  • Construction method for underwater pipe pile foundation and underwater pipe pile foundation

    EP4242380A1

  • Construction method for cast-in-place concrete pile

    JP2000212961A